HomeMy WebLinkAbout5485-1w ♦ TRAFFIC SIGNAL GENERAL NOTES 1. CONSTRUCTION PERMITS SHALL BE OBTAINED FROM THE CITY OF FONTANA DEPARTMENT OF ENGINEERING PRIOR TO THE START OF ANY WORK. INSPECTION COORDINATION SHALL BE REQUESTED AT LEAST TWO WORKING DAYS PRIOR TO THE START OF ANY WORK IN PUBLIC RIGHT-OF-WAY WITH IN THE CITY LIMITS. CALL (909) 350-7610. 2. ALL WORK, MATERIALS, EQUIPMENT AND TEMPORARY TRAFFIC CONTROL SHALL CONFORM TO THESE PLANS, THE ' CITY OF FONTANA STANDARD SPECIFICATIONS, THE STANDARD PLANS AND SPECIFICATIONS OF THE STATE OF CALIFORNIA, DATED 2010, AND THE CALIFORNIA MANUAL OF TRAFFIC CONTROL DEVICES, DATED 2014. 3. LOCATION OF ALL UNDERGROUND FACILITIES ARE APPROXIMATE. THE CONTRACTOR SHALL POTHOLE TO DETERMINE THE EXACT LOCATIONS AND VERIFY ALL CONDITIONS ON THE JOB SITE. HAND DIG FOUNDATIONS UNTIL CLEAR OF ANY OBSTRUCTIONS. PHONE UNDERGROUND SERVICE ALERT AT (800) 227-2600. TWO (2) WORKING DAYS BEFORE DIGGING. 4. CONTRACTOR SHALL FURNISH ALL EQUIPMENT, MATERIALS, AND HARDWARE TO CONSTRUCT THE TRAFFIC SIGNAL AND LIGHTING AS SHOWN ON THE PLANS, EXCEPT ANY CITY FURNISHED OR PROVIDED AS NOTED IN SECTION E. -5., ALL PULLBOXES SHALL BE No. 6 AND CONDUIT SHALL BE 3" RIGID METAL UNLESS OTHERWISE SHOWN. 6. CONTRACTOR SHALL MAKE APPLICATION FOR ELECTRIC SERVICE AND SCHEDULING WITH SOUTHERN CALIFORNIA EDISON COMPANY FOUR WEEKS IN ADVANCE OF NEED. 7. CONTRACTOR SHALL OBTAIN APPROVAL FROM THE ENGINEER FOR EXACT EQUIPMENT LOCATIONS PRIOR TO FINAL PLACEMENT. SEE DETAIL THIS SHEET AND SECTION E. 8. CONTRACTOR SHALL RELOCATE AND/OR REPLACE LANDSCAPING, SPRINKLERS, AND SIDEWALK AFFECTED BY THE CONSTRUCTION TO THE SATISFACTION OF THE ENGINEER. 9. CONTROLLER AND SERVICE CABINETS SHALL NOT BE SUBJECTED TO WATER FROM SPRINKLERS. CONTRACTOR SHALL MODIFY SPRINKLERS SYSTEMS AS NECESSARY. 1 d. ANY EXISTING TRAFFIC SIGNALS AND LIGHTING SHALL REMAIN IN OPERATION UNTIL REPLACED WITH NEW TRAFFIC SIGNALS AND LIGHTING. 11. CONTRACTOR SHALL REFER TO THE CITY ENGINEER IN THE EVENT OF A CONFLICT OR POTENTIAL CONFLICT WITH THESE PLANS AND,OR SPECIFICATIONS FOR THIS PROJECT. 12. TRENCH REPAIRS SHALL BE PER SPECIAL PROVISIONS, SECTION E AND CITY STANDARD PLAN 1008. 13. AS -BUILT DRAWINGS SHALL BE PROVIDED BY THE CONTRACTOR TO THE ENGINEER OF RECORD, WHO SHALL PROVIDE RECORD DRAWINGS AND ELECTRONIC AUTOCAD FILES TO THE CITY ENGINEER. CITY OF FONTANA SIERRA AVE AND RIVERSIDE AVENUE TRAFFIC SIGNAL IMPROVEMENTS PROJECT SITE VICINITY MAP NOT TO SCALE TRAFFIC SIGNAL CONSTRUCTION NOTES NOTE: SEE SPECIAL PROVISIONS FOR ANY CITY SUPPLIED EQUIPMENT AND/OR MATERIALS, a1 INSTALL CITY FURNISHED TYPE 90 CONTROLLER EQUIPMENT PACKAGE INCLUDING TYPE "R" CABINET, LOOP DETECTION, AND APPURTENANT EQUIPMENT. CONTROLLER CABINET AND FOUNDATION SHALL BE INSTALLED PER CITY STANDARD PLAN 4001. CONTRACTOR SHALL FURNISH AND INSTALL ANY ADDITIONAL EQUIPMENT REQUIRED TO PROVIDE THE SIGNAL OPERATION AS SHOWN ON THE PLAN. INSTALL TYPE III -BF SERVICE EQUIPMENT ENCLOSURE PER CITY OF FONTANA AND SOUTHERN CALIFORNIA EDISON COMPANY REQUIREMENTS. a FURNISH k INSTALL 2"C. 216, 1#8 CONDUCTORS (SIGNAL SERVICE) FURNISH do INSTALL 2"C. 2#10 CONDUCTORS (LUMINAIRES) FURNISH AND INSTALL 3" PVC CONDUIT WITH Um POLY PULL ROPE PER SCE REQUIREMENTS. COORDINATE SERVICE WITH SCE PLANNING DEPARTMENT AT 909.357.6116. VERIFY PHONE NUMBERS AT TIME OF CONSTRUCTION E6 REMOVE EXISTING LANDSCAPING AND MODIFY IRRIGATION SYSTEM AS NECESSARY. CONSTRUCT 4" THICK PCC PAD ON COMPACTED NATIVE AROUND PROPOSED SIGNAL CONTROLLER AND SERVICE CABINETS. SPRINKLERS SHALL NOT SPRAY ONTO CONTROLLER CABINET OR SERVICE PEDESTAL �j INSTALL CITY -FURNISHED UNI -DIRECTIONAL. SINGLE CHANNEL OPTICOM DETECTOR, PER DETAIL B ON SHEET 2 AND AS DIRECTED BY THE ENGINEER ® INSTALL SIGN AND HARDWARE PER CALTRANS DETAIL "U", ES -7N. ❑9 FURNISH AND INSTALL SIGN ON SIGNAL POLE AS SHOWN. MOUNTING SHALL BE PER CALTRANS STD. PLANS RS4. 10 FURNISH AND INSTALL DIMENSION BATTERY BACK-UP SYSTEM PER MANUFACTURERS REQUIREMENTS. LEGEND: A*�-- PROPOSED SIGNAL EQUIPMENT OPROPOSED TYPE E LOOP f PROPOSED TYPE D LOOP LEGEND: SIGN LEGEND REMOVE EXISTING PROPOSED INDEX OF SHEETS: TYPE IV (L or R) PAVEMENT ARROW DRAWING NUMBER 5484 -STREET IMPROVEMENT PLAN ROADSIDE SIGN 5485 -TRAFFIC SIGNAL PLAN - R3-4 R3-18 OM1 -3 R9_3 5486 -SIGNING AND STRIPING PLAN ------------ TRAFFIC STRIPE OR MARKING 36 X 36 36 X 36 .18' X 18' CITY OF RIALTO DEPARTMENT OF PUBLIC WORKS APPROVED BY: Y74/017 ROBERT EISENBEISZ, PUBLIC WORKS DIRECTOR/CITY ENGINEER, RCE 54931 DATE UNDERGROUND SERVICE ALERT (USA)REV. REVISION DESCRIPTION DATE ENGR. CITY DATE Prepared Under The Supervision Of : CITY OF FONTANA, CALIFORNIA SHOULD CONSTRUCTION OF THE REQUIRED QapFESS/04 KOA COPA30RArnON IT'S -THE LAW! IMPROVEMENTS NOT COMMENCE WITHIN TWO ���� ANG GU4��Ey PLANNING & ENGINEERING TITLE SHEET YEARS OF THE DATE OF APPROVAL SHOWN HEREON 3190 C. Shelby Street DRAWN BY: SIERRA AVENUE SCALE: DIAL BEFORE ! y ti `y YOU DIG! ! Ontario, California 91764 AND As Noted AND CARRIED FORTH IN A DILIGENT MANNER, THE Na 75793 Tel: (909) 890-9693 Fax: (909) 890-9694 CITY ENGINEER MAY REQUIRE. REVISIONS TO THE �• 6/30/18 DESIGNED BY: DATE: CALL AT LEAST a * BENCH MARKalv&: FONTANA BM8-17 ELEV 1428.609 RIALTO BM042-88 ELEv 1924.262 RIVE DE AVENUE TWO WORKING DAYS Knowwhaftbelow. PLANS TO BRING THEM INTO CONFORMANCE WITH sT7TfOFCAI�Fp��\P DESCRIPTION: CITY OF FONTANA BM #8-17: BRASS CAP IN CONCRETE BASE OF SOUTH LEG OF AN i CHECKED BY: PP VE B DRAWING NO..- BEFORE O..- BEFORE YOU DIG Call before you dig. SCE TOWER, 343' NORTH OF HIGHLAND AVE AND 0.2 MILES WEST OF SAN SEVAINE ROAD. ` n .�. 1 STANDARDS IN EFFECT. CITY OF RIALTO BM #042-88 :BRASS DISK IN TOP OF SOUTHERLY CURB RIVERSIDE AVENUE 0.25 DATE: I �F/11 DATE` 5485 2 MILES SOUTHEAST OF SIERRA AVENUE. MING UAN. R.C.E. 75793 N ANA ENGINEER 11 t