1 ALL WORK SHALL BE IN ACCORDANCE WITH THESE PLANS, THE CITY OF
FONTANA STANDARD PLANS, THE CONTRACT PROVISIONS AND THE STANDARD
SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION ("GREEN BOOK"). ALL
REFERENCE SPECIFICATIONS AND STANDARDS SHALL BE THE LATEST EDITION
UNLESS OTHERWISE NOTED.
2 WHEN A TECHNICAL CONFLJCT IS FOUND TO EXIST IN THE CONTRACT
DOCUMENTS THAT CAN NOT BE RESOLVED BY REFERENCE TO PRECEDENCE
PROVISIONS IN THE "GREEN BOW, THE CONTRACTOR SHALL IMMEDIATELY
REPORT SAID CONFLICT TO THE CITY ENGINEER FOR RESOLUTION.
3 ALL MATERIALS AND METHODS ARE SUBJECT TO THE APPROVAL OF THE
CITY ENGINEER.
4 CONSTRUCTION PERMITS SHALL BE OBTAINED FROM THE CITY OF FONTANA
COMMUNITY DEVELOPMENT DEPARTMENT, ENGINEERING DIVISION PRIOR TO THE
START OF ANY WORK. INSPECTION COORDINATION SHALL BE REQUESTED AT
LEAST TWO WORKING DAYS PRIOR TO THE START OF ANY WORK IN PUBLIC
RIGHT—OF—WAY WITHIN THE CITY LIMITS. CALL (909) 350-7610.
5 THE CONTRACTOR SHALL CONFORM TO ALL TRAFFIC CONTROL POLICIES,
METHODS AND PROCEDURES DESCRIBED IN THE STATE OF CALIFORNIA MANUAL
OF TRAFFIC CONTROLS, LATEST NON—METRIC EDITION UNLESS OTHERWISE
DIRECTED BY THE CITY TRAFFIC ENGINEER.
6 IT SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR TO MAINTAIN
BARRICADES, DELINEATORS OR OTHER TRAFFIC CONTROL DEVICES AT ALL
TIMES.
7 THE CONTRACTOR SHALL OBTAIN A PERMIT TO PERFORM EXCAVATION OR
TRENCH WORK FOR TRENCHES 5 FEET OR GREATER IN DEPTH FROM THE
CALIFORNIA STATE DIVISION OF INDUSTRIAL SAFETY.
8 THE WALLS AND FACES OF ALL EXCAVATIONS GREATER THAN FIVE (5) FEET
IN DEPTH SHALL BE GUARDED BY SHORING, SLOPING OF THE GROUND OR
OTHER APPROVED MEANS PURSUANT TO THE REQUIREMENTS OF THE DIVISION
OF INDUSTRIAL SAFETY OF THE STATE OF CALIFORNIA. TRENCHES LESS THAN
FIVE (5) FEET SHALL ALSO BE GUARDED WHEN THE POTENTIAL EXISTS FOR
GROUND MOVEMENT.
9 NO MATERIAL OR EQUIPMENT SHALL BE STORED IN THE PUBLIC RIGHT OF
WAY WITHOUT OBTAINING A SEPARATE PERMIT FOR THAT PURPOSE.
10 THE LOCATIONS OF UTILITIES SHOWN HAVE BEEN DETERMINED FROM
AVAILABLE INFORMATION, HOWEVER, IT SHALL BE THE RESPONSIBILITY OF THE
CONTRACTOR TO DETERMINE, IN THE FIELD, THE TRUE LOCATION AND
ELEVATION OF ANY EXISTING UTILITIES, AND TO EXERCISE PROPER PRECAUTION
TO AVOID DAMAGE THERETO. THE CONTRACTOR SHALL CONTACT UNDERGROUND
SERVICE ALERT AT 1-800-227-2600 TWO WORKING DAYS BEFORE
EXCAVATION.
11 THE CONTRACTOR SHALL COORDINATE CONSTRUCTION WITH ALL UTILITY
COMPANIES INCLUDING, BUT NOT LIMITED TO, GAS, TELEPHONE, ELECTRIC,
CABLE TELEVISION, LANDSCAPING, LANDSCAPE IRRIGATION, DOMESTIC WATER,
RECLAIMED WATER, SEWER, STORM DRAIN, FLOOD CONTROL AND CALTRANS.
ALL UTILITY COMPANIES SHALL BE GIVEN TWO WORKING DAYS NOTICE PRIOR
TO WORK AROUND THEIR FACIUTIES.
12 THE CONTRACTOR SHALL NOT OPERATE ANY FIRE HYDRANT OR WATER
MAIN VALVES WITHOUT APPROPRIATE AGENCY AUTHORIZATION. CONTRACTOR
SHALL COORDINATE WITH THE APPROPRIATE WATER COMPANY FOR VALVE
OPERATION AND WATER REQUIREMENTS.
13 STATIONING REFERS TO THE CENTERLINE OF SEWER EXCEPT WHERE
OTHERWISE NOTED.
14 ADEQUATE CONSTRUCTION CONTROL STAKES SHALL BE SET BY THE
ENGINEER TO ENABLE THE CONTRACTOR TO CONSTRUCT THE WORK TO THE
PLAN GRADES. THE CONTRACTOR SHALL BE RESPONSIBLE FOR THE
PRESERVATION OF BENCHMARKS AND CONSTRUCTION CONTROL STAKING
DURING CONSTRUCTION.
15 THE CONTRACTOR SHALL NOT DISTURB EXISTING SURVEY MONUMENTS,
MONUMENT TIES OR BENCH MARKS WITHOUT PRIOR NOTIFICATION TO THE CITY
ENGINEER.
16 REMOVAL AND REPLACEMENT OF EXISTING SURVEY CONTROL, INCLUDING
SURVEY MONUMENTS, MONUMENT TIES AND BENCH MARKS, SHALL BE DONE
BY A REGISTERED CML ENGINEER OR LICENSED LAND SURVEYOR. SURVEY
MONUMENTS THAT WILL BE DESTROYED AS A RESULT OF THIS CONSTRUCTION
SHALL BE REPLACED. THE CONTRACTOR SHALL NOTIFY THE ENGINEER ONE
WEEK PRIOR TO CONSTRUCTION SO THAT TIES TO MONUMENTS CAN BE
ESTABLISHED FOR LATER REPLACEMENT OF THE MONUMENT.
17 THE CONTRACTOR SHALL MAINTAIN ACCESS FOR LOCAL RESIDENTS AND
BUSINESSES AT ALL TIMES. A MINIMUM 12 FOOT LANE SHALL BE MAINTAINED
AT ALL TIMES IN THE CONSTRUCTION AREA FOR RESIDENTS AND EMERGENCY
VEHICLES.
18 THE CONTRACTOR SHALL PROVIDE AND MAINTAIN AN EFFECTIVE MEANS OF
DUST CONTROL, INCLUDING ADEQUATE WATERING, AT ALL TIMES.
19 THE CONTRACTOR SHALL NOT CAUSE ANY EXCAVATED MATERIAL, MUD, SILT
OR DEBRIS TO BE DEPOSITED ONTO PUBLIC OR PRIVATE PROPERTY ADJACENT
TO THE RIGHT OF WAY DURING CONSTRUCTION WITHOUT PRIOR WRITTEN
APPROVAL.
20 NO TRENCH BACKFILL SHALL TAKE PLACE WITHOUT PRIOR APPROVAL OF
THE CITY INSPECTOR.
21 A GEOTECHNICAL ENGINEER SHALL CERTIFY ALL BACKFILL COMPACTION.
FAILURE TO OBTAIN THE REQUIRED DENSITY SHALL REQUIRE RE—WORKING OF
THAT PORTION OF THE WORK UNTIL THE SPECIFIED DENSITY IS OBTAINED.
22 CARE SHOULD BE TAKEN TO PREVENT GRADES, DITCHES, AND SWALES
FROM UNDERMINING STREET IMPROVEMENTS. UPON INSPECTION OF THE SITE,
THE CITY ENGINEER MAY REQUIRE TEMPORARY NON—ERODABLE SWALES
ENTERING OR LEAVING IMPROVEMENTS.
23 ALL EXPOSED CONCRETE SURFACES SHALL CONFORM IN GRADE, COLOR
AND FINISH TO MATCH EXISTING CONCRETE.
24 IF SEWER CONSTRUCTION IS TO BE DONE IN PHASES, THE CONTRACTOR
SHALL PROVIDE A TERMINAL CLEANOUT AT THE PHASE BOUNDARY, NOT MORE
THAN 150 FEET FROM THE DOWNSTREAM MANHOLE, SEE CITY OF FONTANA
STANDARD DETAIL FOR TERMINAL CLEANOUT.
25 SANITARY SEWER LINES SHALL BE CONSTRUCTED OF BELL AND SPIGOT OR
BAND SEAL TYPE VITRIFIED CLAY PIPE (V.C.P.) EXTRA STRENGTH CLASS AND
SHALL CONFORM TO THE PROVISIONS OF THE ASTM DESIGNATION C700 FOR
V.C.P.
26 NO OPEN TRENCH SHALL BE ALLOWED AT THE END OF THE DAY WITHOUT
PRIOR APPROVAL OF THE CITY ENGINEER.
27 SHORT VCP STUBS WITH FLEXIBLE COMPRESSION JOINTS SHALL BE USED
AT MANHOLE WALLS TO ALLOW FOR MINOR DEFLECTIONS IN ALIGNMENT.
TOLL FREE —800-227-2600
A PUBLIC SERVICE BY UNDERGROUND SERVICE ALERT
28 PRIOR TO CONSTRUCTION, THE CONTRACTOR SHALL EXPOSE EXISTING
FACILITIES, AND VERIFY ELEVATION AND LOCATION OF CONNECTIONS. CITY
APPROVAL OF CONNECTIONS TO EXISTING FACILITIES DOES NOT IMPLY
CORRECTNESS OF ELEVATIONS OR LOCATIONS SHOWN ON THE PLANS.
29 ALL 4" HOUSE LATERALS SHALL BE INSTALLED AT A 2X MINIMUM GRADE
UNLESS OTHERWISE APPROVED BY THE CITY ENGINEER.
30 TERMINATE ALL 4" HOUSE SEWER LATERALS 3 FEET INSIDE THE LOT WITH
A PLUG 12" BELOW THE GROUND SURFACE. WHEN PUBLIC UTILITY EASEMENTS
EXIST NEXT TO THE STREET RIGHT OF WAY, THE LATERAL SHALL TERMINATE 3
FEET INSIDE THE LOT AS MEASURED FROM THE UTILITY EASEMENT.
31 THE SEWER CONTRACTOR SHALL STAMP AN "S" IN THE FACE OF THE
CURB AT THE LOCATION OF THE SEWER LATERAL.
32 IF EXISTING UTILITIES OR ANY OTHER FACILITIES CONFLICT WITH THE
PROPOSED IMPROVEMENTS, THE CONTRACTOR SHALL NOTIFY THE ENGINEER
AND ALL AFFECTED AGENCIES IMMEDIATELY.
33 NO CONCRETE SHALL BE PLACED UNTIL THE FORMS AND REINFORCING
STEEL HAVE BEEN PLACED, INSPECTED AND APPROVED.
34 ALL UNDERGROUND UTILITIES SHALL BE INSTALLED, TESTED AND APPROVED
PRIOR TO PAVING OF STREETS.
35 APPROVED SOIL STERILANT IS REQUIRED UNDER ALL NEW ASPHALT
PAVEMENT PRIOR TO PLACEMENT.
36 ALL MANHOLES, CLEANOUT FRAMES, COVERS AND VALVE BOXES SHALL BE
RAISED TO FINISHED GRADE BY THE PAVING CONTRACTOR UPON COMPLETION
OF PAVING.
37 UPON COMPLETION OF CONSTRUCTION, CONTRACTOR SHALL RESTORE ALL
SIGNING, STRIPING, BARRICADES, AND OTHER TRAFFIC CONTROL DEVICES TO
THE SATISFACTION OF THE CITY TRAFFIC ENGINEER.
38 AS—BUILT DRAWINGS SHALL BE PROVIDED BY THE CONTRACTOR TO THE
ENGINEER OF RECORD, WHO SHALL PROVIDE RECORD DRAWINGS TO THE CITY
ENGINEER.
CITY OF FONTANA, UTILITY NOTIFICATION UST
CITY OF FONTANA
AT&T
8353 SIERRA AVE
22311 BROOKHURST ST SUITE 203
FONTANA, CA 92335
HUNTINGTON BEACH, CA 92646
(909) 350-6632
(714) 963-7964
SO. CALIF. GAS COMPANY
SPRINT
1981 W. LUGONIA AVE
2592 DUPONT DR
REDLANDS, CA 92374
IRVINE, CA 92612
(909) 335-7967
(800) 659-9698
EMERGENCIES: (800) 427-2200
PROJECT
FIRE HYDRANT
TIME WARNER CABLE
SO. CALIF. EDISON COMPANY
1500 AUTO CENTER DR
300 N. PEPPER AVE
ONTARIO, CA 91761
RIALTO, CA 92376
(909) 975-3439
909 820-5598 — UNDERGROUND
SUNESYS, LLC
909 875-5100 — TRANSMISSION
1325 PICO ST 1106
213 637-1233 — PIPELINES
CORONA, CA 92881
909 357-6505 —DISTRIBUTION
(951) 278-0400
FONTANA WATER COMPANY
UNDERGROUND SERVICE ALERT
15966 ARROW BOULEVARD
(800) 422-4133
FONTANA, CA 92335
(909) 822-2201
DEVELOPER
LENNAR HOMES OF CALIFORNIA, INC. LEIGHTON AND ASSOCIATES, INC.
980 MONTECITO DRIVE, SUITE 302 17781 COWAN
CORONA, CA 92879 IRVINE, CA 92614
TEL (951) 817-3545 TEL (949) 250-1421
FAX 951) 817-3650 FAX (949) 250-1114
PRIVATE ENGINEER'S NOTICE TO CONTRACTOR.-
THE
ONTRACTOR:
THE EXISTENCE AND LOCATION OF ANY UNDERGROUND UTILITY PIPES AND/OR STRUCTURES
SHOWN ON THESE PLANS WERE OBTAINED BY A SEARCH OF THE AVAILABLE RECORDS.
THESE LOCATIONS ARE APPROXIMATE AND SHALL BE CONFIRMED BY THE CONTRACTOR,
SO THAT ANY NECESSARY ADJUSTMENT CAN BE MADE IN ALIGNMENT AND/OR GRADE
OF THE PROPOSED IMPROVEMENT. THE CONTRACTOR IS REQUIRED TO TAKE DUE
PRECAUTIONARY MEASURES TO PROTECT ANY UTILITY LINES SHOWN AND ANY OTHER
ONES NOT ON RECORD OR NOT SHOWN ON THESE PLANS.
CONSTRUCTION CONTRACTOR AGREES THAT IN ACCORDANCE WITH GENERALLY ACCEPTED
CONSTRUCTION PRACTICES, HE WILL BE REQUIRED TO ASSUME
SOLE AND COMPLETE RESPONSIBILITY FOR JOB SITE CONDITIONS DURING THE COURSE
OF CONSTRUCTION OF THE PROJECT, INCLUDING THE SAFETY OF ALL PERSONS AND
PROPERTY. THIS REQUIREMENT SHALL BE MADE TO APPLY CONTINUOUSLY AND
NOT BE LIMITED TO NORMAL WORKING HOURS. CONSTRUCTION CONTRACTOR FURTHER
AGREES TO DEFEND, INDEMNIFY AND HOLD DESIGN PROFESSIONAL HARMLESS FROM ANY
AND ALL LIABIUTY, REAL OR ALLEGED, IN CONNECTION WITH THE PERFORMANCE OF
WORK ON THIS PROJECT, EXCEPTING LIABILITY ARISING FROM THE SOLE NEGLIGENCE
OF THE DESIGN PROFESSIONAL.
UNAUTHORIZED CHANCES AND USES: -
THE ENGINEER PREPARING THESE PLANS WILL NOT BE RESPONSIBLE FOR OR LIABLE
FOR, UNAUTHORIZED CHANGES TO OR USES OF THESE PLANS. ALL CHANGES TO THE
PLANS MUST BE IN WRITING AND MUST BE APPROVED BY THE PREPARER OF THESE PLANS.
CONSTRUCTION STAKING NOTICE
THESE IMPROVEMENT PLANS HAVE BEEN PREPARED WITH THE INTENT THAT THE FIRM OF
ALLARD ENGINEERING INC. WILL BE PERFORMING THE CONSTRUCTION STAKING FOR THE
COMPLETE PROJECT. HOWEVER, IF ANOTHER ENGINEERING AND/OR SURVEYING FIRM
SHOULD BE EMPLOYED TO USE THESE PLANS FOR THE PURPOSE OF CONSTRUCTION
STAKING, NOTICE IS HEREBY GIVEN THAT THE FIRM OF ALLARD ENGINEERING INC. WILL NOT
ASSUME ANY RESPONSIBILITY FOR ERRORS OR OMISSIONS, WHICH COULD HAVE BEEN
AVOIDED, CORRECTED OR MITIGATED IF ALLARD ENGINEERING INC. HAD PERFORMED THE
STAKING WORK.
REV. REVISION DESCRIPTION ENGR. DATE CITY DATE
CITY OF FONTANA
TRACT N0. 18939
SEWER IMPROVEMENT PLANS
NOTE
CONTRACTOR AND SURVEYOR TO VERIFY
SEWER LATERAL LOCATIONS WITH
ENGINEER PRIOR TO STAKING AND
CONSTRUCTION.
SHOULD CONSTRUCTION OF REQUIRED
IMPROVEMENTS NOT COMMENCE WITHIN
TWO YEARS OF THE DATE OF APPROVAL
SHOWN HEREON AND CARRIED FORTH IN A
DILIGENT MANNER, THE CITY ENGINEER MAY
REQUIRE REVISIONS TO THE PLANS TO
BRING THEM INTO CONFORMANCE WITH
CONDITIONS AND STANDARDS IN EFFECT
INDEX MAP
SCALE: 1"=80'
Prepared For:
LENNAR
980 MONTECITO DRIVE, SUITE 302
CORONA, CA 92879
(951) 817-3545
FAX (951) 817-3650
SHEET INDEX
1. — TITLE SHEET
2. — MONTGOMERY AVENUE
3. — SUGAR HOLLOW LANE
4. — EDGEWATER WAY & CANAL COURT
BASIS OF BEARINGS:
THE BEARINGS SHOWN HEREON ARE BASED ON THE
CENTERLINE OF SIERRA AVENUE, PER TRACT 17634,
M.B. 340/72-73, BEING: N 00'00'12"
BENCHMARK
2" BRASS CAP LOCATED ON THE TOP OF CURB AT
THE EASTERLY END OF THE CURB RETURN AT THE
NE CORNER OF SIERRA AVE. AND MILLER AVE.
ELEVATION: 1364.32
!°WAM
VICINITY MAP
NTS
THE QUANTITIES SHOWN HEREON ARE ESTIMATES ONLY. THE CONTRACTORS SHALL PREPARE THEIR
OWN QUANTITIES AND BID A COMPLETE JOB.
CONSTRUCTION NOTES QL MITITI' W -MATES
I51 CONSTRUCT 8" EXTRA STRENGTH V.C.P. SEWER MAIN 1,404 LF
2 CONSTRUCT 48" PRECAST CONCRETE MANHOLE PER CITY STD. DWG. NO. 2001 8 Eq
3 CONSTRUCT 4" V.C.P. SEWER LATERAL & HOUSE CLEANOUT PER CITY STD. DWG. NO 2005 1,955 LF
4 CONSTRUCT BACKWATER CHECK VALVE 12 EA
REMOVE 8" SEWER PLUG AND JOIN NEW CONSTRUCTION 2 FA
LEGEND
SUMMIT AVENUE
— —80 S—
STATE RO�U f
2V r1Q�I A
8" W
W
r
�
FUTURE STORM DRAIN LINE
0
EXIST. SEWER MANHOLE
U
SEWER MANHOLE
WSELINE AVENUE
CENTERLINE
PROJECT
FIRE HYDRANT
LOCATION
STREET LIGHT
V FR&WwAY
!°WAM
VICINITY MAP
NTS
THE QUANTITIES SHOWN HEREON ARE ESTIMATES ONLY. THE CONTRACTORS SHALL PREPARE THEIR
OWN QUANTITIES AND BID A COMPLETE JOB.
CONSTRUCTION NOTES QL MITITI' W -MATES
I51 CONSTRUCT 8" EXTRA STRENGTH V.C.P. SEWER MAIN 1,404 LF
2 CONSTRUCT 48" PRECAST CONCRETE MANHOLE PER CITY STD. DWG. NO. 2001 8 Eq
3 CONSTRUCT 4" V.C.P. SEWER LATERAL & HOUSE CLEANOUT PER CITY STD. DWG. NO 2005 1,955 LF
4 CONSTRUCT BACKWATER CHECK VALVE 12 EA
REMOVE 8" SEWER PLUG AND JOIN NEW CONSTRUCTION 2 FA
LEGEND
Prepared By:
ALLARD ENGINEERING
Civil Engineering -Land Surveying -Land Planning
16866 Seville Avenue
Fontana, California 92335
(909) 356-1815 Fax (909) 365-1795
�Gcm'je �w_ 3-1•Iy
Raymond I Allard, A.C.E. 36052 Date
(expires 6/30/2016)
2' MIN,
SELECTIVE BEDD
IIN.
MAX. SIZE NATIVE SOIL,
WACTED 90X
TYPICAL BEDDING/TRENCH REPAIR FOR r VCP
SEE CITY STD. 1008
NTS
Q�pFESSION
SEWER IMPROVEMENT PLAN
TRACT NO. V9.
SCALE:
0 No. 36052 m HMG AS NOTED
°L Exp. 6/30/16 DESIGNED BY: TITLE DATE:
DBW March, 2016
��q O I P CHECKED BY: APPRO BY: DRAWING NO.:
TF OF CAo- RJA DATE:
CITY ENGINEER R.C.E. 51152 "D 4
Filename: I:\Inland Construction — Gabriella\ DWG's\ FINAL DESIGN\ SEWER\ PHASE 3\SEWER TR18939 SHT 01.dwg
* GRIND AND OVERLAY SHALL BE FULL LANE
WITDTH AND NOT STOP WITHIN A LANE
CITY OF FONTANA, CALIFORNIA
SEWER LINE
— —80 S—
— EXIST. SEWER UNE
WATER MAIN
8" W
STORM DRAIN LINE
FUTURE STORM DRAIN LINE
0
EXIST. SEWER MANHOLE
0
SEWER MANHOLE
CENTERLINE
~�
FIRE HYDRANT
STREET LIGHT
f—
DIRECTION OF FLOW
— —
RIGHT OF WAY
Prepared By:
ALLARD ENGINEERING
Civil Engineering -Land Surveying -Land Planning
16866 Seville Avenue
Fontana, California 92335
(909) 356-1815 Fax (909) 365-1795
�Gcm'je �w_ 3-1•Iy
Raymond I Allard, A.C.E. 36052 Date
(expires 6/30/2016)
2' MIN,
SELECTIVE BEDD
IIN.
MAX. SIZE NATIVE SOIL,
WACTED 90X
TYPICAL BEDDING/TRENCH REPAIR FOR r VCP
SEE CITY STD. 1008
NTS
Q�pFESSION
SEWER IMPROVEMENT PLAN
TRACT NO. V9.
SCALE:
0 No. 36052 m HMG AS NOTED
°L Exp. 6/30/16 DESIGNED BY: TITLE DATE:
DBW March, 2016
��q O I P CHECKED BY: APPRO BY: DRAWING NO.:
TF OF CAo- RJA DATE:
CITY ENGINEER R.C.E. 51152 "D 4
Filename: I:\Inland Construction — Gabriella\ DWG's\ FINAL DESIGN\ SEWER\ PHASE 3\SEWER TR18939 SHT 01.dwg
* GRIND AND OVERLAY SHALL BE FULL LANE
WITDTH AND NOT STOP WITHIN A LANE
CITY OF FONTANA, CALIFORNIA