1. GENERAL
CITY WILL OBTAIN AN ENCROACHMENT PERMIT FROM THE COUNTY OF
SAN BERNARDINO TRANSPORTATION DEPARTMENT (FOR WORK TO BE
PERFORMED WITHIN COUNTY RIGHT-OF-WAY).
CONTRACTOR SHALL MAINTAIN TWO LANES OF TRAFFIC AT ALL TIMES DURING
CONSTRUCTION UNLESS OTHERWISE SPECIFIED OR PERMITTED BY THE
CITY. CONTRACTOR SHALL FURNISH TRENCH PROTECTION AS REQUIRED
TO CONSTRUCT SEWER AND MAINTAIN TRAFFIC MOVEMENT.
2. NOTIFICATIONS
ONE MONTH PRIOR TO BEGINNING CONSTRUCTION, CONTRACTOR SHALL
POST CONSTRUCTION NOTICE SIGNS SPECIFYING DATES WHEN CONSTRUCTION
WILL BEGIN AND CONTRACTOR'S NAME AND PHONE NUMBER.
IN ADDITION TO NOTIFICATIONS SPECIFIED IN THE CONSTRUCTION SPECIFICATIONS
(GENERAL CONDITIONS, UTILITY REQUIREMENTS), CONTRACTOR SHALL NOTIFY
RESIDENTS AND COMMERCIAL ESTABLISHMENTS OF IMPENDING WORK.
PRINTED NOTICES, PROVIDED BY THE CITY, SHALL BE DELIVERED TO ALL
RESIDENTS AND COMMERCIAL ESTABLISHMENTS IN THE VICINITY OF THE WORK
AT LEAST SEVEN DAYS IN ADVANCE OF CONSTRUCTION.
SAID NOTICES SHALL FIRST BE APPROVED BY THE CITY AND SHALL CONTAIN
A GENERAL DESCRIPTION OF THE WORK, DATES WORK WILL BE PERFORMED,
DESCRIPTIONS OF AREAS WHERE TRAVEL AND PARKING WILL BE RESTRICTED,
AND NAMES OF STREETS WHICH WILL BE CLOSED TO THROUGH TRAFFIC OR
WHERE TRAFFIC WILL BE RESTRICTED.
IF THE CITY OR COUNTY RECEIVES COMPLAINTS FROM INDIVIDUALS AFFECTED
BY CONSTRUCTION, CONTRACTOR SHALL TAKE IMMEDIATE ACTION TO CORRECT
THE SITUATION AS DIRECTED BY THE CITY. IF THE CONTRACTOR RECEIVES
COMPLAINTS DIRECTLY, HE SHALL REPORT SAME IMMEDIATELY TO THE CITY.
THEREAFTER, HE SHALL TAKE IMMEDIATE ACTION TO CORRECT THE
THE SITUATION AS DIRECTED BY THE CITY.
3. MANHOLE QRADE ADJUSTMENT
CONTRACTOR SHALL INSTALL NEW MANHOLE SHAFTS TO FINISH GRADE AND
PLACE MANHOLE FRAME AND COVER.
MANHOLE FRAMES AND COVERS TO BE CONSTRUCTED BY THE CONTRACTOR
6" BELOW FINISHED SURFACE GRADE AND UPON COMPLETION OF PAVING, THE
CONTRACTOR SHALL RAISE SAME TO FINISHED GRADE.
4. BACKRL L
WHERE PROPOSED SEWER CROSS BENEATH EXISTING WATERLINES (4" MINIMUM
DIAMETER) AND A PIPE SUPPORT IS SPECIFIED, THE CONTRACTOR SHALL WRAP
EXISTING WATERLINE WITH 60 ML VISQUINE AND CRADDLE EXISTING WATERLINE
WITH 2" THICK STYROFOAM TO THE SPRINGLINE. CONTRACTOR SHALL PROVIDE
A PIPE SUPPORT FOR THE EXISTING WATERLINE PER DETAIL 2 ON SHEET 3.
5. SEWER LATERALS
APPROXIMATE LOCATION OF LATERALS ARE SPECIFIED ON THE CONSTRUCTION
DRAWINGS. CONTRACTOR SHALL COORDINATE WITH CITY AND EACH
PROPERTY OWNER TO DETERMINE PRECISE LATERAL LOCATIONS. THE SEWER
LATERALS ARE TO BE CONSTRUCTED FROM PROPOSED SEWER TO EXISTING
RIGHT-OF-WAY OR TO 1' BEHIND CURB.
IN ACCORDANCE WITH STATE DEPARTMENT OF HEALTH SERVICES REQUIREMENTS,
LATERALS SHALL BE CONSTRUCTED A MINIMUM OF 10' FROM EXISTING PARALLEL
WATER FACILITIES.
Underground Service Alert
SECTION 4216/4217 OF THE GOVERNMENT CODE
REQUIRES A DIG ALERT IDENTIFICATION NUMBER
BE ISSUED BEFORE A PERMIT TO EXCAVATE WILL
BE VALID.
Call: TOLL FREE
1-800
227-2600
6. RESTORATION REOUIREMENTS 1. ALL WORK SHALL BE IN ACCORDANCE WITH THESE PLANS, THE CITY OF FONTANA
CONTRACTOR SHALL PROTECT EXISTING CURB, GUTTERS, AND SIDEWALK STANDARD PLANS, THE CONTRACT PROVISIONS AND THE STANDARD SPECIFICATIONS
IN PLACE DURING SEWER CONSTRUCTION. IF CURB, GUTTER, AND/OR SIDEWALK FOR PUBLIC WORKS CONSTRUCTION ("GREEN BOOK"). ALL REFERENCE SPECIFICATIONS
IS DAMAGED DURING CONSTRUCTION, CONTRACTOR SHALL REPLACE SAME AND STANDARDS SHALL BE THE LATEST EDITION UNLESS OTHERWISE NOTED.
TO LIMITS SPECIFIED BY THE CITY.
CONTRACTOR SHALL, AS A MINIMUM, HAVE ACCOMPLISHED BY THE END OF 2. CONSTRUCTION PERMITS SHALL BE OBTAINED FROM THE CITY OF FONTANA
EACH WORK DAY (4:00 PM) THE FOLLOWING: COMMUNITY DEVELOPMENT DEPARTMENT, ENGINEERING DIVISION PRIOR TO THE START
OF ANY WORK. INSPECTION COORDINATION SHALL BE REQUESTED AT LEAST TWO WORKING
DAYS. PRIOR TO THE START OF ANY WORK IN PUBLIC RIGHT-OF-WAY WITHIN THE CITY
A. PLATE OPEN EXCAVATIONS (30' MAXIMUM). TEMPORARY ASPHALT CONCRETE
SHALL BE PLACED AROUND PLATES FOR SMOOTH TRANSITION (WHERE APPLICABLE). LIMITS. CALL (909) 350-7610.
B. FILL ALL REMAINING EXCAVATIONS WITH COMPACTED BACKFILL AND PLACE 2"
MINIMUM TEMPORARY ASPHALT CONCRETE PAVEMENT IN ALL AREAS WHERE
EXISTING PAVEMENT WAS REMOVED AND AT ALL DRIVEWAYS. SAID PAVEMENT
SHALL BE COMPACTED, ROLLED SMOOTH AND FLUSH WITH ADJACENT PAVEMENT
SUFFICIENT TO SUPPORT TRAFFIC. SAID PAVEMENT MAY BE PLACED COLD
PROVIDED IT IS PLACED SMOOTH AND FLUSH WITH ADJACENT EXISTING
PAVEMENT AND ROLLED WITH A STEEL WHEELED PAVEMENT ROLLER,
AND PROPERLY MAINTAINED.
C. REMOVE ALL DEBRIS, CONSTRUCTION MATERIALS, AND EQUIPMENT FROM
PUBLIC STREETS, CONSTRUCTION RIGHT-OF-WAY, AND PRIVATE PROPERTY.
D. CLEAN (INCLUDING SWEEPING AND WASHING) ALL STREETS, DRIVEWAYS,
GUTTERS, SIDEWALKS, AND ALL OTHER WORK AREAS. (CONTRACTOR MAY BE
REQUIRED TO WASH AND /OR SWEEP WORK AREAS MORE THAN ONCE
A DAY, IF DIRECTED BY THE CITY).
E. RELOCATE ALL TRAFFIC CONTROL AS REQUIRED AND TO OPEN ALL STREETS TO TRAFFIC.
CONTRACTOR SHALL MAINTAIN ALL TEMPORARY ASPHALT CONCRETE THROUGHOUT THE
COURSE OF CONSTRUCTION. CONTRACTOR SHALL BE RESPONSIBLE AT ALL TIMES TO
MAINTAIN TEMPORARY ASPHALT CONCRETE AND TRENCH BACKFILL IN GOOD AND SAFE
CONDITION. CONTRACTOR SHALL IMMEDIATELY RESPOND TO ALL REQUESTS BY CITY FOR
REMEDIAL WORK (INCLUDING WEEKENDS AND HOLIDAYS). CONTRACTOR SHALL HAVE A
CREW AVAILABLE TO RESPOND TO SAID REQUESTS. CONTRACTOR SHALL RECYCLE ALL
REMOVED ASPHALT CONCRETE PAVEMENT. CONTRACTOR SHALL FURNISH CITY WRITTEN
DOCUMENTATION THAT SAID PAVEMENT HAS BEEN RECYCLED.
7. ASPHALT CONCRETE PAVEMENT/STRIPING/SIGNING
FOR ALL AREAS WHERE PROPOSED ASPHALT CONCRETE MEETS EXISTING ASPHALT CONCRETE,
SAW CUT EDGES TO NEAT VERTICAL EDGE EITHER PERPENDICULAR TO OR PARALLEL WITH
CENTERLINE. CONTRACTOR SHALL PROVIDE ALL STRIPING PLANS AS NECESSARY TO RELOCATE
TRAFFIC. CONTRACTOR SHALL FURNISH TRAFFIC SIGNING AS REQUIRED INCLUDING BUT NOT
LIMITED TO, BUS STOP SIGNS, SPEED LIMIT SIGNS, AND CONSTRUCTION SIGNS. CONTRACTOR
SHALL PLAN, SCHEDULE, AND IMPLEMENT A FINAL TRAFFIC CONTROL PLANS, APPROVED BY
THE CITY OF FONTANA.
& SEWER CONSTRUCTION SEQUENCE
CONTRACTOR SHALL CONSTRUCT SEWERS CONTINUOUSLY FROM DOWNSTREAM TO UPSTREAM STATION.
9. TRENCHING
CONTRACTOR SHALL, WHILE ACTIVELY WORKING IN CONSTRUCTION AREA, LIMIT OPEN TRENCHES
TO 100 FEET MAXIMUM. NO OPEN TRENCHES ARE PERMITTED DURING NON -WORKING HOURS.
10. MANHOLE CHANNELJNG
10.1 CONTRACTOR SHALL VERIFY EXISTING 10" SEWER INVERT ELEVATION PRIOR TO BEGINNING
OF CONNECTION CONSTRUCTION.
10.2 CORE DRILL THROUGH MANHOLE BASE AS REQUIRED
10.3 PRIOR TO CORE DRILLING, CONTRACTOR SHALL TAKE ALL NECESSARY PRECAUTIONS
TO PREVENT CORE DRILLING INTO MANHOLE AT INCORRECT ELEVATION AND SHALL PREVENT
CORING SPOILS AND/OR TOOLS FROM ENTERING SEWER SYSTEM. ALL ERRORS SHALL BE
CORRECTED AS DIRECTED BY THE CITY OF FONTANA.
10.4 CHANNEL SHALL BE CONSTRUCTED AS SHOWN ON THE CITY OF FONTANA STANDARD
DETAIL 112 AND DETAIL 4 ON SHEET 3. THERE SHALL BE 0.20' ELEVATION DIFFERENCE
ON THE CHANNEL THROUGH THE MANHOLE.
10.5 AFTER CORING OPERATION, CONTRACTOR SHALL REPAIR CHANNEL AND SHELF
WITH APPROVED EPDXY GROUT.
10.5 SEE CITY OF FONTANA STANDARD DETAIL 114, CASE 2 FOR MANHOLE CHANNELING
PLANS PREPARED BY:
ELIAS A. BUSUEGO, JR. II No. DATE BY
01/28/03 1 EAB I RECORD DRAWING.
P.E.- RCE# C 49004 DATE
3. THE CONTRACTOR SHALL NOT OPERATE ANY FIRE HYDRANT OR WATER MAIN VALVES.
CONTRACTOR SHALL COORDINATE WITH THE APPROPRIATE WATER COMPANY FOR VALVE
OPERATION AND WATER REQUIREMENTS.
4. STATIONING REFERS TO THE CENTERLINE OF SEWER MAIN EXCEPT WHERE OTHERWISE NOTED.
5. ALL UNDERGROUND UTILITIES SHALL BE INSTALLED, TESTED AND APPROVED
PRIOR TO PAVING OF STREETS.
6. THE LOCATIONS OF UTILITIES SHOWN HAVE BEEN DETERMINED FROM AVAILABLE
INFORMATION. HOWEVER, IT SHALL BE THE RESPONSIBILTY OF THE CONTRACTOR TO
DETERMINE, IN THE FIELD, THE TRUE LOCATION AND ELEVATION OF ANY EXISTING
UTILITIES, AND TO EXERCISE PROPER PRECAUTION TO AVOID DAMAGE THERETO. THE
CONTRACTOR SHALL CONTACT UNDERGROUND SERVICE ALERT AT 1-800-227-2600
TWO WORKING DAYS BEFORE EXCAVATION.
7. ALL MANHOLES CLEAN OUT FRAMES, COVER AND VALVE BOXES SHALL BE RAISED
TO FINISH GRADE BY THE CONTRACTOR UPON COMPLETION OF PAVING.
8. THE CONTRACTOR SHALL COORDINATE CONSTRUCTION WITH ALL UTILITY COMPANIES
INCLUDING, BUT NOT LIMITED TO GAS, TELEPHONE, ELECTRIC, CABLE TELEVISION,
LANDSCAPING, LANDSCAPING IRRIGATION, DOMESTIC WATER, RECLAIM WATER, SEWER,
STORM DRAIN, FLOOD CONTROL AND CALTRANS. ALL UTILITY COMPANIES SHALL BE
GIVEN TWO WORKING DAYS NOTICE PRIOR TO WORK AROUND THEIR FACILITIES.
9. AS -BUILT DRAWINGS SHALL BE PROVIDED BY THE CONTRACTOR TO THE ENGINEER
OF RECORD, WHO SHALL PROVIDE RECORD DRAWINGS TO THE CITY ENGINEER.
10. WHEN A CONFLICT IS FOUND TO EXIST IN THE CONTRACT DOCUMENTS THAT CAN
NOT BE RESOLVED BY REFERENCE TO PRECEDENCE PROVISIONS IN THE "GREEN BOOK",
THE CONTRACTOR SHALL IMMEDIATELY REPORT SAID CONFLICT TO THE CITY ENGINEER
FOR RESOLUTION.
11. APPROVED SOIL STERILANT IS REQUIRED UNDER ALL NEW PERMANENT ASPHALT
PAVEMENT PRIOR TO PLACEMENT.
12. ALL EXPOSED CONCRETE SURFACES SHALL CONFORM IN GRADE, COLOR AND
FINISH TO MATCH EXISTING CONCRETE.
13. NO CONCRETE SHALL BE PLACED UNTIL THE FORMS AND REINFORCING STEEL
HAVE BEEN PLACED, INSPECTED AND APPROVED.
14. THE WALLS AND FACES OF ALL EXCAVATIONS GREATER THAN FIVE (5) FEET IN
DEPTH SHALL BE GUARDED BY SHORING, SLOPING OF THE GROUND OR OTHER
APPROVED MEANS PURSUANT TO THE REQUIREMENTS OF THE DIVISION OF INDUSTRIAL
SAFETY OF THE STATE OF CALIFORNIA. TRENCHES LESS THAN FIVE (5) FEET SHALL
ALSO BE GUARDED WHEN THE POTENTIAL EXISTS FOR GROUND MOVEMENT.
15. THE CONTRACTOR SHALL OBTAIN A PERMIT TO PERFORM EXCAVATION OR TRENCH
WORK FOR TRENCHES FIVE (5) FEET OR GREATER IN DEPTH FROM THE CALIFORNIA
STATE DIVISION OF INDUSTRIAL SAFETY.
16. NO TRENCH BACKFILL SHALL TAKE PLACE WITHOUT PRIOR APPROVAL OF THE
CITY INSPECTOR.
17. THE CONTRACTOR SHALL NOT CAUSE ANY EXCAVATED MATERIAL, MUD SILT
OR DEBRIS TO BE DEPOSITED ONTO PUBLIC PROPERTY ADJACENT TO THE RIGHT-OF-WAY
DURING CONSTRUCTION WITHOUT PRIOR WRITTEN APPROVAL.
REVISIONS BENCH MARK:
DESCRIPTION APPT BY DATE
GENERAL NOTES:
18. IT SHALL BE THE RESPONSIBILTY OF THE CONTRACTOR TO MAINTAIN BARRICADES,
DELINEATORS OR OTHER TRAFFIC CONTROL AT ALL TIMES.
19. A GEOTECHINCAL ENGINEER SHALL CERTIFY ALL BACKFILL COMPACTION. FAILURE TO
OBTAIN THE REQUIRED DENSITY SHALL REQUIRE REWORKING OF THAT PORTION OF THE
WORK UNTIL THE SPECIFIED DENSITY IS OBTAINED.
20. ALL MATERIALS AND METHODS ARE SUBJECT TO THE APPROVAL OF THE CITY ENGINEER.
21. ADEQUATE CONSTRUCTION CONTROL STAKES SHALL BE SET BY THE ENGINEER TO ENABLE
THE CONTRACTOR TO CONSTRUCT THE WORK TO PLAN GRADES. THE CONTRACTOR SHALL BE
RESPONSIBLE FOR THE PRESERVATION OF BENCHMARKS AND CONSTRUCTION CONTROL
STAKING DURING CONSTRUCTION.
22. CARE SHOULD BE TAKEN TO PREVENT GRADES, DITCHES AND SWALES FROM
UNDERMINING STREET IMPROVEMENTS. UPON INSPECTION OF THE SITE, THE CITY
ENGINEER MAY REQUIRE TEMPORARY NON-ERODEABLE SWALES ENTERING OR
LEAVING IMPROVEMENTS.
23. IF EXISTING UTILITIES OR ANY OTHER FACILITIES CONFLICT WITH THE PROPOSED
IMPROVEMENTS, THE CONTRACTOR SHALL NOTIFY THE ENGINEER AND ALL AFFECTED
AGENCIES IMMEDIATELY.
24. THE CONTRACTOR SHALL NOT DISTURB EXISTING SURVEY MONUMENTS, MONUMENT TIES
OR BENCH MARKS WITHOUT PRIOR NOTIFICATION TO THE CITY ENGINEER.
25. REMOVAL AND REPLACEMENT OF EXISTING SURVEY CONTROL, INCLUDING SURVEY
MONUMENTS, MONUMENT TIES AND BENCHMARKS, SHALL BE DONE BY A REGISTERED
CIVIL ENGINEER OR LICENSED LAND SURVEYOR. SURVEY MONUMENTS THAT WILL BE
DESTROYED AS A RESULT OF THIS CONSTRUCTION SHALL BE REPLACED. THE CONTRACTOR
SHALL NOTIFY THE ENGINEER ONE WEEK PRIOR TO CONSTRUCTION SO THAT TIES TO
MONUMENTS CAN BE ESTABLISHED FOR LATER REPLACEMENT OF THE MONUMENT.
26. THE CONTRACTOR SHALL MAINTAIN ACCESS FOR LOCAL RESIDENTS AND
BUSINESSES AT ALL TIMES. A MINIMUM TWELVE FOOT LANE SHALL BE MAINTAINED
AT ALL TIMES IN THE CLOSURE AREA FOR RESIDENTS AND EMERGENCY VEHICLES.
27. NO MATERIAL OR EQUIPMENT SHALL BE STORED IN THE PUBLIC RIGHT-OF-WAY
WITHOUT OBTAINING A SEPARATE PERMIT FOR THAT PURPOSE.
28. SANITARY SEWER LINES SHALL BE CONSTRUCTED OF BELL AND SPIGOT OR
BAND SEAL TYPE VITRIFIED CLAY PIPE (VCP) EXTRA STRENGTH CLASS AND SHALL
CONFORM TO THE PROVISIONS OF THE ASTM DESIGNATION C 700 FOR VCP.
29. THE SEWER CONTRACTOR SHALL STAMP AN "S" IN THE FACE OF THE CURB AT
THE LOCATION OF THE SEWER LATERAL.
30. IF SEWER CONSTRUCTION IS TO BE DONE IN PHASES, THE CONTRACTOR SHALL
PROVIDE A TERMINAL CLEAN OUT AT THE PHASE BOUNDARY, NOT MORE THAN 150
FEET FROM THE DOWNSTREAM MANHOLE. SEE CITY OF FONTANA STANDARD DETAIL
FOR TERMINAL CLEAN OUT.
31. ALL HOUSE LATERALS SHALL BE INSTALLED AT A 2% MINIMUM GRADE UNLESS
OTHERWISE APPROVED BY THE CITY ENGINEER.
32. PRIOR TO CONSTRUCTION, THE CONTRACTOR SHALL EXPOSE EXISTING FACILITIES,
AND VERIFY ELEVATION AND LOCATION OF CONNECTIONS. CITY APPROVAL OF CONNECTIONS
TO EXISTING FACILITIES DOES NOT IMPLY CORRECTNESS OF ELEVATIONS OR LOCATIONS
SHOWN ON THE PLANS.
33. THE CONTRACTOR SHALL PROVIDE AND MAINTAIN AN EFFECTIVE MEANS OF
DUST CONTROL, INCLUDING ADEQUATE WATERING, AT ALL TIMES.
34. SHORT VCP STUBS WITH FLEXIBLE COMPRESSION JOINTS SHALL BE USED AT
MANHOLE WALLS TO ALLOW FOR MINOR DEFLECTIONS IN ALIGNMENT.
35. THE CONTRACTOR SHALL CONFORM TO ALL TRAFFIC CONTROL POLICIES, METHODS
AND PROCEDURES DESCRIBED IN THE "W.A.T.C.H. MANUAL," LATEST EDITION, UNLESS
OTHERWISE DIRECTED BY THE CITY TRAFFIC ENGINEER.
36. UPON COMPLETION OF CONSTRUCTION, CONTRACTOR SHALL RESTORE ALL
SIGNING, STRIPING, BARRICADES, AND OTHER TRAFFIC CONTROL DEVICES TO THE
SATISFACTION OF THE CITY TRAFFIC ENGINEER.
37. NO OPEN TRENCH SHALL BE ALLOWED AT THE END OF THE DAY WITHOUT PRIOR
APPROVAL OF THE CITY ENGINEER.
SAN BERNARDINO COUNTY BENCH MARK
NO. 616, BRASS CAP IN GAS STATION
PUMP ISLAND SOUTHEAST CORNER
HIGHLAND AVE. AND CITRUS AVE,
ELEVATION = 1510.91
(NOTE: GAS STATION IS ABANDONED)
CITY OF FONTANA
SOUTH HIGHLAND AVENUE AND JUNIPER AVENUE SEWER SYSTEM IMPROVEMENTS SP -46-01
DRAWN BY: SEWER IMPROVEMENT PLAN SCALE:
EAB S. HIGHLAND AVE., JUNIPER AVE., & WALNUT ST. 1" = 40'
DESIGNED BY: DATE:
TRH C S CTION NOTES 11/15/2001
CHECKED BY:ROV DATE: DRAWING NO. 2
IlIZZLP3
CITY ENGINEER R.C.E. KO._,o 3133 14
iH15 PLAN IS COPYRIGHTED BY ASSOCIATED ENGINEERS, INC. 2001 L:\2001\01064\DWG\AsBuilt\Sewe2C.dwg
an i_.........n Ana
'
Associated
Engineers
y S G. DYE m
DESIGNED BY:
T. R. HOLLIMAN, P.E. DATE:
3311 EAST SHELBY STREET
ONTARIO, CALIFORNIA 91764
NO. C 49004
p
DRAWN BY:
E. A. BUSUEGO, JR. II DATE:
TEL.: (909) 980-1982
FAX: (909) 941-0891
" EXP.09 31 05
CHECKED BY:
T. R. HOLLIMAN, P.E. DATE:
CIVIL
APPROVED:
P.E.- RCE# C 49004 DATE
3. THE CONTRACTOR SHALL NOT OPERATE ANY FIRE HYDRANT OR WATER MAIN VALVES.
CONTRACTOR SHALL COORDINATE WITH THE APPROPRIATE WATER COMPANY FOR VALVE
OPERATION AND WATER REQUIREMENTS.
4. STATIONING REFERS TO THE CENTERLINE OF SEWER MAIN EXCEPT WHERE OTHERWISE NOTED.
5. ALL UNDERGROUND UTILITIES SHALL BE INSTALLED, TESTED AND APPROVED
PRIOR TO PAVING OF STREETS.
6. THE LOCATIONS OF UTILITIES SHOWN HAVE BEEN DETERMINED FROM AVAILABLE
INFORMATION. HOWEVER, IT SHALL BE THE RESPONSIBILTY OF THE CONTRACTOR TO
DETERMINE, IN THE FIELD, THE TRUE LOCATION AND ELEVATION OF ANY EXISTING
UTILITIES, AND TO EXERCISE PROPER PRECAUTION TO AVOID DAMAGE THERETO. THE
CONTRACTOR SHALL CONTACT UNDERGROUND SERVICE ALERT AT 1-800-227-2600
TWO WORKING DAYS BEFORE EXCAVATION.
7. ALL MANHOLES CLEAN OUT FRAMES, COVER AND VALVE BOXES SHALL BE RAISED
TO FINISH GRADE BY THE CONTRACTOR UPON COMPLETION OF PAVING.
8. THE CONTRACTOR SHALL COORDINATE CONSTRUCTION WITH ALL UTILITY COMPANIES
INCLUDING, BUT NOT LIMITED TO GAS, TELEPHONE, ELECTRIC, CABLE TELEVISION,
LANDSCAPING, LANDSCAPING IRRIGATION, DOMESTIC WATER, RECLAIM WATER, SEWER,
STORM DRAIN, FLOOD CONTROL AND CALTRANS. ALL UTILITY COMPANIES SHALL BE
GIVEN TWO WORKING DAYS NOTICE PRIOR TO WORK AROUND THEIR FACILITIES.
9. AS -BUILT DRAWINGS SHALL BE PROVIDED BY THE CONTRACTOR TO THE ENGINEER
OF RECORD, WHO SHALL PROVIDE RECORD DRAWINGS TO THE CITY ENGINEER.
10. WHEN A CONFLICT IS FOUND TO EXIST IN THE CONTRACT DOCUMENTS THAT CAN
NOT BE RESOLVED BY REFERENCE TO PRECEDENCE PROVISIONS IN THE "GREEN BOOK",
THE CONTRACTOR SHALL IMMEDIATELY REPORT SAID CONFLICT TO THE CITY ENGINEER
FOR RESOLUTION.
11. APPROVED SOIL STERILANT IS REQUIRED UNDER ALL NEW PERMANENT ASPHALT
PAVEMENT PRIOR TO PLACEMENT.
12. ALL EXPOSED CONCRETE SURFACES SHALL CONFORM IN GRADE, COLOR AND
FINISH TO MATCH EXISTING CONCRETE.
13. NO CONCRETE SHALL BE PLACED UNTIL THE FORMS AND REINFORCING STEEL
HAVE BEEN PLACED, INSPECTED AND APPROVED.
14. THE WALLS AND FACES OF ALL EXCAVATIONS GREATER THAN FIVE (5) FEET IN
DEPTH SHALL BE GUARDED BY SHORING, SLOPING OF THE GROUND OR OTHER
APPROVED MEANS PURSUANT TO THE REQUIREMENTS OF THE DIVISION OF INDUSTRIAL
SAFETY OF THE STATE OF CALIFORNIA. TRENCHES LESS THAN FIVE (5) FEET SHALL
ALSO BE GUARDED WHEN THE POTENTIAL EXISTS FOR GROUND MOVEMENT.
15. THE CONTRACTOR SHALL OBTAIN A PERMIT TO PERFORM EXCAVATION OR TRENCH
WORK FOR TRENCHES FIVE (5) FEET OR GREATER IN DEPTH FROM THE CALIFORNIA
STATE DIVISION OF INDUSTRIAL SAFETY.
16. NO TRENCH BACKFILL SHALL TAKE PLACE WITHOUT PRIOR APPROVAL OF THE
CITY INSPECTOR.
17. THE CONTRACTOR SHALL NOT CAUSE ANY EXCAVATED MATERIAL, MUD SILT
OR DEBRIS TO BE DEPOSITED ONTO PUBLIC PROPERTY ADJACENT TO THE RIGHT-OF-WAY
DURING CONSTRUCTION WITHOUT PRIOR WRITTEN APPROVAL.
REVISIONS BENCH MARK:
DESCRIPTION APPT BY DATE
GENERAL NOTES:
18. IT SHALL BE THE RESPONSIBILTY OF THE CONTRACTOR TO MAINTAIN BARRICADES,
DELINEATORS OR OTHER TRAFFIC CONTROL AT ALL TIMES.
19. A GEOTECHINCAL ENGINEER SHALL CERTIFY ALL BACKFILL COMPACTION. FAILURE TO
OBTAIN THE REQUIRED DENSITY SHALL REQUIRE REWORKING OF THAT PORTION OF THE
WORK UNTIL THE SPECIFIED DENSITY IS OBTAINED.
20. ALL MATERIALS AND METHODS ARE SUBJECT TO THE APPROVAL OF THE CITY ENGINEER.
21. ADEQUATE CONSTRUCTION CONTROL STAKES SHALL BE SET BY THE ENGINEER TO ENABLE
THE CONTRACTOR TO CONSTRUCT THE WORK TO PLAN GRADES. THE CONTRACTOR SHALL BE
RESPONSIBLE FOR THE PRESERVATION OF BENCHMARKS AND CONSTRUCTION CONTROL
STAKING DURING CONSTRUCTION.
22. CARE SHOULD BE TAKEN TO PREVENT GRADES, DITCHES AND SWALES FROM
UNDERMINING STREET IMPROVEMENTS. UPON INSPECTION OF THE SITE, THE CITY
ENGINEER MAY REQUIRE TEMPORARY NON-ERODEABLE SWALES ENTERING OR
LEAVING IMPROVEMENTS.
23. IF EXISTING UTILITIES OR ANY OTHER FACILITIES CONFLICT WITH THE PROPOSED
IMPROVEMENTS, THE CONTRACTOR SHALL NOTIFY THE ENGINEER AND ALL AFFECTED
AGENCIES IMMEDIATELY.
24. THE CONTRACTOR SHALL NOT DISTURB EXISTING SURVEY MONUMENTS, MONUMENT TIES
OR BENCH MARKS WITHOUT PRIOR NOTIFICATION TO THE CITY ENGINEER.
25. REMOVAL AND REPLACEMENT OF EXISTING SURVEY CONTROL, INCLUDING SURVEY
MONUMENTS, MONUMENT TIES AND BENCHMARKS, SHALL BE DONE BY A REGISTERED
CIVIL ENGINEER OR LICENSED LAND SURVEYOR. SURVEY MONUMENTS THAT WILL BE
DESTROYED AS A RESULT OF THIS CONSTRUCTION SHALL BE REPLACED. THE CONTRACTOR
SHALL NOTIFY THE ENGINEER ONE WEEK PRIOR TO CONSTRUCTION SO THAT TIES TO
MONUMENTS CAN BE ESTABLISHED FOR LATER REPLACEMENT OF THE MONUMENT.
26. THE CONTRACTOR SHALL MAINTAIN ACCESS FOR LOCAL RESIDENTS AND
BUSINESSES AT ALL TIMES. A MINIMUM TWELVE FOOT LANE SHALL BE MAINTAINED
AT ALL TIMES IN THE CLOSURE AREA FOR RESIDENTS AND EMERGENCY VEHICLES.
27. NO MATERIAL OR EQUIPMENT SHALL BE STORED IN THE PUBLIC RIGHT-OF-WAY
WITHOUT OBTAINING A SEPARATE PERMIT FOR THAT PURPOSE.
28. SANITARY SEWER LINES SHALL BE CONSTRUCTED OF BELL AND SPIGOT OR
BAND SEAL TYPE VITRIFIED CLAY PIPE (VCP) EXTRA STRENGTH CLASS AND SHALL
CONFORM TO THE PROVISIONS OF THE ASTM DESIGNATION C 700 FOR VCP.
29. THE SEWER CONTRACTOR SHALL STAMP AN "S" IN THE FACE OF THE CURB AT
THE LOCATION OF THE SEWER LATERAL.
30. IF SEWER CONSTRUCTION IS TO BE DONE IN PHASES, THE CONTRACTOR SHALL
PROVIDE A TERMINAL CLEAN OUT AT THE PHASE BOUNDARY, NOT MORE THAN 150
FEET FROM THE DOWNSTREAM MANHOLE. SEE CITY OF FONTANA STANDARD DETAIL
FOR TERMINAL CLEAN OUT.
31. ALL HOUSE LATERALS SHALL BE INSTALLED AT A 2% MINIMUM GRADE UNLESS
OTHERWISE APPROVED BY THE CITY ENGINEER.
32. PRIOR TO CONSTRUCTION, THE CONTRACTOR SHALL EXPOSE EXISTING FACILITIES,
AND VERIFY ELEVATION AND LOCATION OF CONNECTIONS. CITY APPROVAL OF CONNECTIONS
TO EXISTING FACILITIES DOES NOT IMPLY CORRECTNESS OF ELEVATIONS OR LOCATIONS
SHOWN ON THE PLANS.
33. THE CONTRACTOR SHALL PROVIDE AND MAINTAIN AN EFFECTIVE MEANS OF
DUST CONTROL, INCLUDING ADEQUATE WATERING, AT ALL TIMES.
34. SHORT VCP STUBS WITH FLEXIBLE COMPRESSION JOINTS SHALL BE USED AT
MANHOLE WALLS TO ALLOW FOR MINOR DEFLECTIONS IN ALIGNMENT.
35. THE CONTRACTOR SHALL CONFORM TO ALL TRAFFIC CONTROL POLICIES, METHODS
AND PROCEDURES DESCRIBED IN THE "W.A.T.C.H. MANUAL," LATEST EDITION, UNLESS
OTHERWISE DIRECTED BY THE CITY TRAFFIC ENGINEER.
36. UPON COMPLETION OF CONSTRUCTION, CONTRACTOR SHALL RESTORE ALL
SIGNING, STRIPING, BARRICADES, AND OTHER TRAFFIC CONTROL DEVICES TO THE
SATISFACTION OF THE CITY TRAFFIC ENGINEER.
37. NO OPEN TRENCH SHALL BE ALLOWED AT THE END OF THE DAY WITHOUT PRIOR
APPROVAL OF THE CITY ENGINEER.
SAN BERNARDINO COUNTY BENCH MARK
NO. 616, BRASS CAP IN GAS STATION
PUMP ISLAND SOUTHEAST CORNER
HIGHLAND AVE. AND CITRUS AVE,
ELEVATION = 1510.91
(NOTE: GAS STATION IS ABANDONED)
CITY OF FONTANA
SOUTH HIGHLAND AVENUE AND JUNIPER AVENUE SEWER SYSTEM IMPROVEMENTS SP -46-01
DRAWN BY: SEWER IMPROVEMENT PLAN SCALE:
EAB S. HIGHLAND AVE., JUNIPER AVE., & WALNUT ST. 1" = 40'
DESIGNED BY: DATE:
TRH C S CTION NOTES 11/15/2001
CHECKED BY:ROV DATE: DRAWING NO. 2
IlIZZLP3
CITY ENGINEER R.C.E. KO._,o 3133 14
iH15 PLAN IS COPYRIGHTED BY ASSOCIATED ENGINEERS, INC. 2001 L:\2001\01064\DWG\AsBuilt\Sewe2C.dwg
an i_.........n Ana