EXISTING
0.10' MIN. AC SURFACING
NEW A.C.
TACK COAT 2 -SACK
ALL EDGES SLURRY BACKFILL
EXISTING CURB (INITIAL POUR TO BE FLUSH
OR WITH SURROUNDING SURFACE)
CURB AND GUTTER
3" RIGID
METAL CONDUIT
(INSTALLED WITH 1' MIN. COVER)
DUCT INSTALLATION AND TRENCH REPAIR DETAIL
TRAFFIC SIGNAL INTERCONNECT/COMMUNICATION GENERAL NOTES
1. TRAFFIC SIGNAL INTERCONNECT SHALL CONFORM TO THESE PLANS, THE STATE OF
CALIFORNIA STANDARD SPECIFICATIONS SECTION 86 AND STANDARD PLANS (DATED
JULY 2010), AND THE SPECIAL PROVISIONS.
2. ALL REQUIRED CONSTRUCTION PERMITS SHALL BE OBTAINED FROM THE CITY OF
FONTANA ENGINEERING DIVISION PRIOR TO COMMENCENT OF WORK.
3. THE CONTRACTOR SHALL REPAIR ALL DAMAGED LANDSCAPING AND IRRIGATION TO
THE SATISFACTION OF THE ENGINEER.
4. CONDUIT SHALL NOT BE INSTALLED DIRECTLY OVER ANY UTILITY LINE (PARALLEL
WITH THE LINE). UTILITY LINE CROSSINGS ARE ALLOWED.
5. CONTRACTOR SHALL OBTAIN APPROVAL FROM THE CITY ENGINEER FOR EXACT
EQUIPMENT LOCATIONS PRIOR TO FINAL PLACEMENT.
6. PULL BOXES AND SPLICE VAULTS SHALL NOT BE LOCATED IN DRIVEWAYS OR
OTHER LOCATIONS WHICH MAY INTERFERE WITH THE MOVEMENT OF PEOPLE OR
VEHICLES. PULL BOX LOCATIONS SHALL BE ADJUSTED AS NEEDED.
7. ALL PULL BOXES SHALL BE No. 6E AND CONDUIT SHALL BE 2" GALVANIZED RIGID
METAL UNLESS OTHERWISE SHOWN. ALL SPLICE VAULTS SHALL BE TYPE P48
48.5"x30.5"x30" DEEP (INSIDE), FIBERGLASS, HAVE LOCKING LIDS, AND BE
LABELED "COMMUNICATIONS". PULL BOXES AND SPLICE VAULTS SHALL BE
INSTALLED IN ACCORDANCE WITH THE PROJECT DETAILS FOR PULL BOX AND
SPLICE VAULT INSTALLATION.
8. WHERE CONDUIT IS INSTALLED AND DISTURBS EXISTING STRIPING, CONTRACTOR
SHALL ARRANGE AND PAY FOR STRIPING. SEE SPECIAL PROVISIONS FOR
CONTRACTOR RESPONSIBILITY FOR TEMPORARY PAVEMENT MARKINGS.
DETAIL "C"
9. ALL PCC SIDEWALK DAMAGED BY THE CONTRACTORS OPERATIONS SHALL BE
SAWCUT, REMOVED, AND REPLACED TO EXISTING EXPANSION/SCRIBE JOINTS.
10. LOCATION OF ALL UNDERGROUND FACILITITES ARE APPROXIMATE. THE CONTRACTOR
SHALL POTHOLE TO DETERMINE THE EXACT LOCATIONS AND VERIFY ALL CONDITIONS
ON THE JOB SITE. HAND DIG UNTIL CLEAR OF OBSTRUCTIONS. PHONE
UNDERGROUND SERVICE ALERT AT (800) 227-2600, TWO (2) WORKING DAYS
BEFORE DIGGING. THE ENGINEER SHALL BE NOTIFIED OF ANY DISCREPENCIES OR
CONFLICTS PRIOR TO DOING STREET WORK.
11. THE CONTRACTOR SHALL LOCATE, PROTECT, SHORE, BRACE, SUPPORT, AND
MAINTAIN ALL EXISTING FACILITIES INCLUDING GAS, WATER, IRRIGATION, SEWER,
POWER, STREET LIGHTS, TELEPHONE AND OTHER CONSTRUCTION WHICH MAY BE
UNCOVERED OR OTHERWISE AFFECTED BY THE WORK. CONTRACTOR SHALL BE
RESPONSIBLE FOR THE LOCATION AND PRESERVATION OF ALL SUCH FACILITIES IN
THE AREA OF CONSTRUCTION, AND SHALL NOTIFY UTILITIES FORTY-EIGHT (48)
HOURS IN ADVANCE OF ANY CONSTRUCTION.
12. ALL TRAFFIC CONTROL DEVICES SHALL BE IN PLACE BEFORE WORK IS STARTED.
TRAFFIC CONTROL, WORK ZONES, AND LANE CLOSURES SHALL BE COMPLETELY
DELINEATED BY CHANNELIZATION DEVICES AND SHIELDED BY BARRIERS TO EXCLUDE
VEHICLE AND/OR PEDESTRIAN TRAFFIC. CONTRACTOR SHALL FOLLOW THE
CALIFORNIA MANUAL ON UNIFORM TRAFFIC CONTROL DEVICES (CALIFORNIA MUTCD
DATED JANUARY, 2012) FOR CONSTRUCTION AND MAINTENANCE WORK ZONES,
CALTRANS STANDARD SPECIFICATIONS, AND STANDARD PLANS, DATED 2010. EXACT
LOCATION OF ALL TRAFFIC CONTROL TO BE DETERMINED BY THE ENGINEER AND
ADDITIONAL WARNING AND/OR CONSTRUCTION SIGNING MAY BE REQUIRED. DEVICES
NO LONGER REQUIRED SHALL BE REMOVED AS SOON AS POSSIBLE. CONTRACTOR
SHALL PROVIDE TRAFFIC CONTROL PLANS TO ENGINEER FOR APPROVAL PRIOR TO
CONSTRUCTION.
TOLL FREE `- 1-800-227-2600
A PUBLIC SERVICE BY UNDERGROUND SERVICE ALERT
m
1 . «, - I +.k
13. PEDESTRIAN TRAFFIC MUST BE MAINTAINED AT ALL TIMES. PEDESTRIANS MAY BE
RELOCATED ONTO PRIVATE PROPERTY WITH OWNERS PERMISSION ONLY.
14. NO EQUIPMENT OR MATERIALS SHALL BE STORED ON SIDEWALK AT ANY TIME.
15. A 12" VERTICAL SEPARATION BETWEEN NEW CONDUITS AND OTHER UTILITIES SHALL
BE MAINTAINED AT CROSSINGS. A 3' MIN. HORIZONTAL SEPARATION BETWEEN NEW
CONDUITS AND POWER AND WATER UTILITIES THAT RUN PARALLEL SHALL BE
MAINTAINED. A 3' (EXCEPT WHERE NOTED) MINIMUM SEPARATION BETWEEN
CONDUIT AND SANITARY SEWER AND STORM DRAINS THAT RUN PARALLEL SHALL BE
MAINTAINED, UNLESS OTHERWISE APPROVED BY THE ENGINEER. THE CONTRACTOR
SHALL MAINTAIN A MINIMUM 3' CLEARANCE FOR ALL OTHER FACILITIES.
16. TRAFFIC SIGNAL CIRCUITS AND INTERCONNECT CONDUITS MAY NOT BE SHOWN.
CONTRACTOR SHALL LOCATE ALL TRAFFIC SIGNAL CIRCUITS AND INTERCONNECT
CONDUITS PRIOR TO ANY TRENCHING OR BORING. ALL TRAFFIC SIGNAL AND
INTERCONNECT CONDUITS SHALL BE MAINTAINED AND PROTECTED. SEE DRAWING NO.
4927 FOR THE TRAFFIC SIGNAL INSTALLATION PLAN.
17. THE CONTRACTOR SHALL BE RESPONSIBLE FOR MAINTAINING RECORD DRAWINGS
FOR ALL WORK THROUGHOUT THE COURSE OF CONSTRUCTION.
18. THE CONTRACTOR SHALL BE RESPONSIBLE FOR THE PROTECTION OF ALL EXISTING
SURVEY MONUMENTS OR MARKERS DURING CONSTRUCTION.
DATE I ENGR. I CITY I DATE
SHOULD CONSTRUCTION OF THE REQUIRED
IMPROVEMENTS NOT COMMENCE WITHIN TWO
YEARS OF THE DATE OF APPROVAL SHOWN HEREON
AND CARRIED FORTH IN A DILIGENT MANNER, THE
CITY ENGINEER MAY REQUIRE REVISIONS TO THE
PLANS TO BRING THEM INTO CONFORMANCE WITH
STANDARDS IN EFFECT.
150' + L.F
CD
1 o a
F—
L�
� W
7 �
� nn//
W
=3
�o
�w
Li
0
AVENUE
FIC SIGNAL INTERCONNECT/COMMUNICATION CONSTRUCTION NOTES
❑1 FURNISH AND INSTALL TYPE P48 (SEE GENERAL NOTE #7) SPLICE BOX
FURNISH AND INSTALL 3" CONDUIT PER DETAIL C. FURNISH AND INSTALL
96 STRAND S.M.F.O. CABLE.
❑3 COIL AN ADDITIONAL 50' OF 96 -STRAND SMFO CABLE FOR SLACK IN P48 BOX
❑4 COIL AN ADDITIONAL 50' OF 96 -STRAND SMFO CABLE FOR SLACK IN PULL BOX
❑5 FURNISH AND INSTALL 96 STRAND S.M.F.O. CABLE IN EXISTING CONDUIT
SPLICE DESIGNATED FIBERS FROM 96 -STRAND SMFO TO EXISTING SPLICE
6❑ ENCLOSURE CONTAINING A 96 -STRAND AND 12 STRAND SMFO CABLE PER
FIBER SPLICE SCHEDULE DRAWING 4948 3/3. COIL A MINIMUM OF 50' OF
96 STRAND SMFO CABLE WITHIN SPLICE VAULT.
7 PULL 12 STRAND S.M.F.O. CABLE INTO TRAFFIC SIGNAL CONTROLLER CABINET
FURNISH AND INSTALL SPLICE ENCLOSURE. FUSION SPLICE DESIGNATED
PLICE
SC96-STRAND
SCHEDULE (SEE DWG. OT
4948 3/3) COIL AMINIMUM OF 12 -STRAND SMFO 1FIBERER 6' OIF12 -STRAND
SMFO CABLE AND 50' OF 96 -STRAND SMFO CABLE FOR SLACK IN SPLICE VAULT
SO = SIGNALIZED INTERSECTION
Under The Supervision Of :
DRAWN BY:
No. C 78044 * DT
Exp. 9-30-13 DESIGNED BY.
DT
CU
Date -713/�.=- CHECKED BY-
�A�C� Noel Castillo, R.C.E. 78044 w MP
• 20 • 40 :• i
r a�w
CITY OF FONTANA, CALIFORNIA
FIBER OPTIC INTERCONNECT PLAN
SCALE:
SAN BERNARDINO AVENUE 1:40
r—_�PTERRA AV TO JUNIPER AVE DATE
7/26/2012
`APP D DRAWING NO.:IY3
DATE: _1'
4948
CITY ENGINEER R.C.E. 51152