HomeMy WebLinkAbout4312-2STREET IMPROVEMENTS GENERAL NOTES:
1. ALL WORK SHALL BE IN ACCORDANCE WITH THESE PLANS, THE CITY
OF FONTANA STANDARD PLANS, THE CONTRACT PROVISIONS AND
THE STANDARD SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION
("GREEN BOOK"). ALL REFERENCE SPECIFICATIONS AND STANDARDS
SHALL BE THE LATEST EDITION UNLESS OTHERWISE NOTED.
2. WHEN A TECHNICAL CONFLICT IS FOUND TO EXIST IN THE CONTRACT
DOCUMENTS THAT CAN NOT BE RESOLVED BY REFERENCE TO
PRECEDENCE PROVISIONS IN THE "GREEN BOOK", THE CONTRACTOR
SHALL IMMEDIATELY REPORT SAID CONFLICT TO THE CITY ENGINEER
FOR RESOLUTION.
3. ALL MATERIALS AND METHODS ARE SUBJECT TO THE APPROVAL OF
THE CITY ENGINEER.
4. CONSTRUCTION PERMITS SHALL BE OBTAINED FROM THE CITY
OF FONTANA COMMUNITY DEVELOPMENT DEPARTMENT, ENGINEERING
DIVISION PRIOR TO THE START OF ANY WORK. INSPECTION
COORDINATION SHALL BE REQUESTED AT LEAST TWO WORKING DAYS
PRIOR TO THE START OF ANY WORK IN PUBLIC RIGHT OF WAY
WITHIN THE CITY LIMITS. CALL (909) 350 7610.
5. THE CONTRACTOR SHALL CONFORM TO ALL TRAFFIC CONTROL
POLICIES, METHODS AND PROCEDURES DESCRIBED IN THE STATE OF
CALIFORNIA MANUAL OF TRAFFIC CONTROLS, LATEST NON METRIC
EDITION UNLESS OTHERWISE DIRECTED BY THE CITY TRAFFIC
ENGINEER. 1
6. IT SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR TO
MAINTAIN BARRICADES, DELINEATORS OR OTHER TRAFFIC CONTROL
DEVICES AT ALL TIMES.
7. THE CONTRACTOR SHALL OBTAIN A PERMIT TO PERFORM
EXCAVATION OR TRENCH WORK FOR TRENCHES 5 FEET OR GREATER
IN DEPTH FROM THE CALIFORNIA STATE DIVISION OF INDUSTRIAL
SAFETY.
B. THE WALLS AND FACES OF ALL EXCAVATIONS GREATER THAN FIVE
(5) FEET IN DEPTH SHALL BE GUARDED BY SHORING, SLOPING OF
TIDE GROUND OR OTHER APPROVED MEANS PURSUANT TO THE
REQUIREMENTS OF THE DIVISION OF INDUSTRIAL SAFETY OF THE
STATE OF CALIFORNIA. TRENCHES LESS THAN FIVE (5) FEET SHALL
ALSO BE GUARDED WHEN THE POTENTIAL EXISTS FOR GROUND
MOVEMENT.
9. NO MATERIAL OR EQUIPMENT SHALL BE STORED IN THE PUBLIC
RIGHT OF WAY WITHOUT OBTAINING A SEPARATE PERMIT FOR THAT
PURPOSE.
10. THE LOCATIONS OF UTILITIES SHOWN HAVE BEEN DETERMINED FROM
AVAILABLE INFORMATION, HOWEVER, IT SHALL BE THE
RESPONSIBILITY OF THE CONTRACTOR TO DETERMINE IN THE FIELD,
THE TRUE LOCATION AND ELEVATION OF ANY EXISTING UTILITIES,
AND TO EXERCISE PROPER PRECAUTION TO AVOID DAMAGE THERETO.
THE CONTRACTOR SHALL CONTACT UNDERGROUND SERVICE ALERT
AT 1 800 227 2600 TWO WORKING DAYS BEFORE EXCAVATION.
II. THE CONTRACTOR SHALL COORDINATE CONSTRUCTION WITH ALL
UTILITY COMPANIES INCLUDING, BUT NOT LIMITED TO, GAS,
TELEPHONE, ELECTRIC, CABLE TELEVISION, LANDSCAPING,
LANDSCAPE IRRIGATION, DOMESTIC WATER, RECLAIMED WATER,
SEWER, STORM DRAIN, FLOOD CONTROL AND CALTRANS. ALL
UTILITY COMPANIES SHALL BE GIVEN TWO WORKING DAYS NOTICE
PRIOR TO WORK AROUND THEIR FACILITIES.
12. THE CONTRACTOR SHALL NOT OPERATE ANY FIRE HYDRANT OR WATER
MAIN VALVES WITHOUT APPROPRIATE AGENCY AUTHORIZATION.
CONTRACTOR SHALL COORDINATE WITH THE APPROPRIATE WATER
COMPANY FOR VALVE OPERATION AND WATER REQUIREMENTS.
13. CURVE DATA REFERS TO THE FACE OF CURB.
14., STATIONING REFERS TO THE CENTERLINE OF STREETS EXCEPT WHERE
OTHERWISE NOTED.
15., ADEQUATE CONSTRUCTION CONTROL STAKES SHALL BE SET BY
THE ENGINEER TO ENABLE THE CONTRACTOR TO CONSTRUCT
THE WORK TO THE PLAN GRADES. THE CONTRACTOR SHALL BE
RESPONSIBLE FOR THE PRESERVATION OF BENCHMARKS AND
CONSTRUCTION CONTROL STAKING DURING CONSTRUCTION.
16. THE CONTRACTOR SHALL NOT DISTURB EXISTING SURVEY MONUMENTS,
MONUMENT TIES OR BENCH MARKS WITHOUT PRIOR NOTIFICATION TO
THE CITY ENGINEER.
17.' REMOVAL AND REPLACEMENT OF EXISTING SURVEY CONTROL,
INCLUDING SURVEY MOUNTS, MONUMENT TIES AND BENCH
MARKS, SHALL BE DONE BY A REGISTERED CIVIL ENGINEER OR
LICENSED LAND SURVEYOR SURVEY MONUMENTS THAT WILL BE
DESTROYED AS A RESULT OF THIS CONSTRUCTION SHALL BE
REPLACED. THE CONTRACTOR SHALL NOTIFY THE ENGINEER ONE
WEEK PRIOR TO CONSTRUCTION SO THAT TIES TO MONUMENTS CAN
BE ESTABLISHED FOR LATER REPLACEMENT OF THE MONUMENT.
18. THE CONTRACTOR SHALL MAINTAIN ACCESS FOR LOCAL RESIDENTS
AND BUSINESSES AT ALL TIMES. A MINIMUM 12 FOOT LANE SHALL
BE MAINTAINED AT ALL TIMES IN THE CONSTRUCTION AREA FOR
RESIDENTS AND EMERGENCY VEHICLES.
HDR ENGINEERING, INC.
2880 MARKET STREET, SUITE 100
RIVERSIDE, CA 92501
(951) 320-7300
ora-filsrv01 \ustn proj\200093\003\project_drawin gs\general\200093a03.dgn
19. THE CONTRACTOR SHALL PROVIDE AND MAINTAIN AN EFFECTIVE
MEANS OF DUST CONTROL, INCLUDING ADEQUATE WATERING, AT
ALL TIMES.
20. ALL GRADING OPERATIONS SHALL BE DISCONTINUED WHEN
SUSTAINED WIND VELOCITIES EXCEED 25 MILES PER HOUR.
21. THE CONTRACTOR SHALL NOT CAUSE ANY EXCAVATED MATERIAL,
MUD, SILT OR DEBRIS TO BE DEPOSITED ONTO PUBLIC OR PRIVATE
PROPERTY ADJACENT TO THE RIGHT OF WAY DURING CONSTRUCTION
WITHOUT PRIOR WRITTEN APPROVAL.
22. NO TRENCH BACKFILL SHALL TAKE PLACE WITHOUT PRIOR
APPROVAL OF THE CITY INSPECTOR.
23. A GEOTECHNICAL ENGINEER SHALL CERTIFY ALL BACKFILL
COMPACTION. FAILURE TO OBTAIN THE REQUIRED DENSITY SHALL
REQUIRE RE WORKING OF THAT PORTION OF TIE WORK UNTIL THE
SPECIFIED DENSITY IS OBTAINED.
24. CARE SHOULD BE TAKEN TO PREVENT GRADES, DITCHES, AND SWALES
FROM UNDERMINING STREET IMPROVEMENTS. UPON INSPECTION OF
THE SITE, THE CITY ENGINEER MAY REQUIRE TEMPORARY
NONERODEABLE SWALES ENTERING OR LEAVING IMPROVEMENTS.
25. THE FINAL LOCATION AND WIDTH OF DRIVEWAY APPROACH APRONS
SHALL BE APPROVED AT THE TIME OF CONSTRUCTION AND SHALL
CONFORM TO THE CI`fY OF FONTANA STANDARD DETAILS.
26. ALL EXPOSED CONCRETE SURFACES SHALL CONFORM IN GRADE,
COLOR AND FINISH TO MATCH EXISTING CONCRETE.
27. THE SEWER CONTRACTOR SHALL STAMP AN "S" IN THE FACE OF THE
CURB AT THE LOCATION OF THE SEWER LATERAL.
28. NO CONCRETE SHALL BE PLACED UNTIL THE FORMS AND
REINFORCING STEEL HAVE BEEN PLACED, INSPECTED AND APPROVED.
29. ALL UNDERGROUND UTILITIES SHALL BE INSTALLED, TESTED AND
APPROVED PRIOR TO PAVING OF STREETS.
30. APPROVED SOIL STERILANT IS REQUIRED UNDER ALL NEW ASPHALT
PAVEMENT PRIOR TO PLACEMENT.
31. PAVEMENT STRUCTURAL SECTIONS SHOWN ARE MINIMUM AND
SUBJECT TO REVISION AND APPROVAL OF THE CITY ENGINEER AS
DETERMINED BY SOILS TESTS TAKEN AFTER COMPLETION OF ROUGH
GRADING.
32. ACTUAL THICKNESS OF A.C. PAVEMENT AND/OR BASE COURSE
MATERIAL FOR STRUCTURAL STREET SECTIONS SHALL BE
RECOMMENDED BY A GEOTECHNICAL REPORT AND SUBMITTED TO
THE CITY OF FONTANA FOR APPROVAL UPON COMPLETION OF ROUGk
GRADING.
I iT
33. ALL MANHOLES, CLEANOUT FRAMES, COVERS AND VALVE BOXES SHALL
BE RAISED TO FINISHED GRADE BY THE PAVING CONTRACTOR UPON
COMPLETION OF PAVING.
34. UPON COMPLETION OF CONSTRUCTION, CONTRACTOR SHALL RESTORE
ALL SIGNING, STRIPING, BARRICADES, OTHER TRAFFIC CONTROL
DEVICES TO THE SATISFACTION OF THE CITY TRAFFIC ENGINEER.
35. CONTRACTOR SHALL RELOCATE AND/OR REPLACE LANDSCAPING,
SPRINKLERS AND SIDEWALKS AFFECTED BY THE CONSTRUCTION
TO THE SATISFACTION OF THE CITY ENGINEER.
36. AS BUILT DRAWINGS SHALL BE PROVIDED BY THE CONTRACTOR TO
THE ENGINEER OF RECORD, WHO SHALL PROVIDE RECORD DRAWINGS
TO THE CITY ENGINEER.
37. CITY OF FONTANA, UTILITY NOTIFICATION LIST:
CITY OF FONTANA
ATTN:_ _FP.ED' RICuTER
8353 SIERRA AVENUE
FONTANA, CA 92335
(909) 350-6684
GAS COMPANY
ATTN: BRUCE YONKERS
1981 W. LUGONIA AVENUE
REDLANDS, CA 92374
(909) 335-7871
METROPOLITAN WATER
ATTN: DAFFNEY IVERSON
700 N. ALAMEDA STREET
LOS ANGELES, CA 90012
(951) 776-2668
SCE TRANSMISSION
ATTN: TIM BEST
300 N. PEPPER AVENUE
RIALTO, CA 92376
(909) 820-5588
AT&T
ENGINEERING
ATTN: SUSAN MORGAN
3939 E. CORONADO STREET
ANAHEIM, CA 92807
(714) 666-5401
TIME WARNER (CABLE TV)
ATTN: LEWIS MCDONALD
1500 S. AUTO CENTER DRIVE
ONTARIO, CA 91716
(909) 975-3341
SCE -DISTRIBUTION
ATTN: P05LRT AIAREIIDT
7951 REDWOOD AVENUE
FONTANA, CA 92336
(909) 357-6221
FONTANA WATER CO.
ATTN: LUIS MONTENEGRO
11142 GARVEY AVENUE
EL MONTE, CA 91733
(626) 448-6183
INLAND EMPIRE UTILITIES AGENCY
LISA MUNOZ
IEUA ON KIMBALL AVE
CHINO, CA 91710
(909) 993-1522
WEST VALLEY WATER DIST.
DISTRICT
ATTN: LON TSAT
855 W. BASELINE ROAD
RIALTO, CA 92376
(909) 875-1322
Lo
M O
C'7
co
Lu Lu > co �
46+320 25 JURUPA AVE Q Q w �1�'� "� W
BEG I N PROJECT _Lu
Q �ae;�c Q Q Qiz
Lu Q > Q rl Q >- 0 Q
> m °° Q ¢/ o p p v
---- z--
------------ 0
Q --------------r=,- �- �---- 1=------ - L .�---------
Q ���� �.--------- ----i-, � � 13 � I' 1�+ U I I � I I 16 � � � �' I I I; �; � I
-z-- ------- ��, 11 12 ; ; '�� 1���� J I I 17 ; 18 ; ; 19 ; I 20 W
I c' I 1O0 - ILV - I I I I
f�F (� \
J=am 7
Ir' ------ I-1---- ----- I I Q I I 15 '- I ------------I I I I I- i I' ' I I 21 i
I ------------T ------------- I '-------------- I
F------ ------ ' I i -I I Itfi------------
I, --------- --------------I I --------------
,o ---------------- Q
I
V)
�-
F I �` p Lij �O CN
d- _ w
�G j p >
> > > CV w Q
Q 0- Q Q QZ
Q w o
I ' I Q I I M
-
I aI
jM m w r) w iQ� , I- Z
"' w Ug- -- �
-- -- <Z z
w }-----------
IO Z
O
� -
-------- ---7-I-------- (---- -------
ZQ-
-
r----W----q---------------
I-------------.--------------------------=---rI_I ------------ I I ------
I I �22 W I l I I
- 2bI I :zzzoOuu
I
> 2o >: 292 30 I II 32' I I II
34 ; ----_
-----------1-------------T---- --------------J=1 I
I G-----------� 1----------- =t-------------
w o INDEX MAP
Co °' NOT TO SCALE
REV.
A PUBLIC SERVICE BY UNDERGROUND SERVICE ALERT
12/4/2007
REVISION DESCRIPTION
8:28:44 PM
DFLTUSER
0
DATE I ENGR. I CITY I DATE
SHOULD CONSTRUCTION OF THE REQUIRED IMPROVEMENTS NOT
COMMENCE WITHIN TWO YEARS OF THE DATE OF APPROVAL
SHOWN HEREON AND CARRIED FORTH IN A DILIGENT MANNER,
THE CITY ENGINEER MAY REQUIRE REVISIONS TO THE PLANS TO
BRING THEM INTO CONFORMANCE WITH CONDITIONS
AND STANDARDS IN EFFECT.
Prepared Under The Supervision Of
�o Q�pFESS/pN `
4
sir
�t MMAS-T. KIM" z
wrn
0.
C 5T3T4
gyp. 12-31-09
CIVIL
T4TF O F C Mfi
355+49°54 JURUPA AVE
END PROJECT
Octet 12/5/OT
CITY OF FONTANA, CALIFORNIA
JURUPA AVENUE STREET IMPROVEMENTS
DRAWN BY: MM SCALE:
GENERAL NOTES NO SCALE
DESIGNED BY: JT 1 O F 2 DATE
12/5/2007
CHECKED BY- APPROVED BY: / DRAWING NO.: 2
TK -f.�/-�� °3/Z 4 312
m, CITY ENGINEER DATE: 4