HomeMy WebLinkAboutSewer Installation (6) City of Fontana
CALIFORNIA
November 6, 1986
~ile: Ch. 2~ - Proposed Sewer
Installation in E1 Molino
Ct. Bet, Oleander Avenue
and Cypress N/O Mallory
Property Owners:
Subject: Petitions for the Installation of Sewer Main and Laterals in E1 Molino
Court Between Oleander Avenue and Cypress Avenue North of Mallory
The City of Fontaria has received a number of inquiries regarding the installation
of sewers within your area. Sanitary sewer facilities can be constructed under
the provisions of Chapter 27 of the Streets and Highways Code in front of the
property described above, In order to b~ve a successful petition, 60% of the
property owners on both sides of the street in which the sewer is to be installed
must sign the petition.
Under the provisions of a Chapter 27 improvement project,' the property owners pay
for their improvements according to their street frontage. For corner lots, the
costs are figured using the shortest frontage with the exception of a corner lot
that fronts an existing sewer main and is not connected. In this situation, the
property owner's costs are figured according to which frontage the sewer is in-
installed.
Regarding costs, at this time it is very difficult to estimate a cost to each
property owner. There are a number of unknowns. The main unknown is how long
the petitions are out being circulated, If it takes a long time to get a suf-
ficient number of signatures, the construction costs could be much higher. An-
other variable in this situation is that there are a number of streets which
could have successful petitions which would affect the quantity of work to be
done. A larger quantity of work means a better price per foot.
With the above information in mind, a rough estimate of the cost per property
owner would be as follows:
If all the streets have successful petitions, $!,000 to $1,500 per lot,
8353 SIERRA AVENUE (P.O. BOX 518) FONTANA, CALIFORNIA 92335 (714) 350-7600
Property Owners: -2- November 6, 1986
E1 Molino Ct. Bet. Oleander Ave.
and Cypress Avenue N/O Mallory
After the construction has been completed, a Notice of Cost will be posted on
the property. The cost will be due and payable within the five days following
the hearing which is provided for in the Notice.!. If not paid, it will become
a lien against the property, will accrueinterest at 6% per annum, and will
ultimately be collected with property taxes. The amount of the cost will be
shown in the Notice.
Before you connect your property to the sewer, you will be required to pay a
connection charge of $600.00, $20,00 to the Building Department for a plumbing
permit, $10.00 to the Public Works Department for a sewer connection permit,
and a "delinquency~'~ deposit of $19.20 (4 months sewer bill at $4.80 per month).
In the past, the City Council has .allowed bills for Chapter 27 sewer facilities
work to be paid in ten annual installments when requested by the owners.
If you should have any questions regarding this matter, please contact this
Department at 350-7610.
Robert Schoenborn, P.E.
Maintenance/Engineering Services Agency Director
By: Bob M. Porter
Engineering Services Director
RS:BMP:wp
ity of FontanY
CALIFORNIA
MEMORANDUM
TO: Jim Mocalis, Acting Public Works Director ~
FROM: Carlos Navarro, Civil Engineering Assistant III o
SUBJECT: Review of Sidewalk Policy as it Pertains to Piecemeal Portion on
Major Projects
DATE: November 14, 1988
Upon my being assigned this task, my research started with the Fontana City
Code and City of fontaria Public Works Department policies book, where I found a
policy pertaining to width and locations of sidewalks in Commercial zones,
Resolution No. 64-27.
To the best of my knowledge, there is no written policy, guidelines on side-
walk projects, other than the one stated above. Past practice, historically, has
been with use of Section 5871 of the Government Code, the Improvement Act of
1911.
The problem with major sidewalk projects is in places where ultimate
right-of-way is needed. Our first option is to ask the property owner to donate
the land; then; if they are not willing to dedicate, utilize Chapter 27 of the
1911 Act of the Streets and Highways Code, and bill the property for the improve-
ments.
In most cases, the owner refuses to participate in the project, and we then
mail a letter to these people informing them of the City's policy regarding the
utilization of condemnation for the purposes of acquiring needed street
righ-of-way and additional acquisition costs that will then be assessed including
administrative fees, title reports, legal expenses etc. All this additional cost
tends to create a more expensive method of installation of improvements.
If by this time, we have not acquired the needed right-of-way, we then return
to Council with a resolution-of-intention to obtain the right-of-way throught the
courts. But, we first obtain an appraised value for needed right-of-way, make
offer to buy, then return to court for an order of possission; and the property
owner is assessed costs.
As addressed per a previous memo, a possible solution would be to apply credit
for dedicated land directly to the proposed improvement cost. Thus both parties
would benefit (City/property owner) by a timely and cost effective project.
I will begin these projects with a field survey to determine locations in
need of sidewalk and the amount of right-of-way needed until I receive a
directive to resolve our right-of-way problems.
Each location will be handled as an individual project.
October 18, 1988
~ile: Ch. 27 - Proposed Sewer
Installation in E1 Molino
Ct. Bet, Oleander Avenue
and Cypress N/O Mallory
P~operty Owners:
Subject: Petitions for the Installation of Sewer Main and Laterals in E1 Molino
Court Between Oleander Avenue and Cypress Avenue North of Mallory
The City of Fontaria has received a number of inquiries regarding the installation
of sewers within your area. Sanitary sewer facilities can be constructed under
the provisions of Chapter 27 of the Streets and Highways Code in front of the
property described above. In order to Pave a successful petition, 60% of the
property owners on both sides of the street in which the sewer is to be installed
must sign the petition.
Under the provisions of a Chapter 27 improvement project,' the property owners pay
for their improvements according to their street frontage, For corner lots, the
costs are figured using the shortest frontage with the exception of a corner lot
that fronts an existing sewer main and is not connected. In this situation, the
property owner's costs are figured according to which frontage the sewer is in-
installed.
Regarding costs, at this time it is very difficult to estimate a cost to each
property owner. There are a number of unknowns. The main unknown is how long
the petitions are out being circulated. If it takes a long time to get a suf-
ficient number of signatures, the construction costs could be much higher. An-
other variable in this situation is that there are a number of streets which
could have successful petitions which would affect the quantity of workto be
done. A larger quantity of work means a better price per foot.
With the above information in mind, a rough estimate of the cost per property
owner would be as follows:
If all the streets have successful petitions, $!,000 to $1,500 per lot.
Property Owners: -2- October 18, 1988
E1 Molino Ct. Bet. Oleander Ave.
and Cypress Avenue N/O Mallory
After the construction has been completed, a Notice of Cost will be posted on
the property. The cost will be due and payable within the five days following
the hearing which is provided for in the Notice~. If not paid, it will become
a lien against the property, will accrue interest at 6% per annum, and will
ultimately be collected with property taxes. The amount of the cost will be
shown in the Notice.
Before you connect your property to the sewer, you will be required to pay a
connection charge of $600.00, $20~00 to the Building Department for a plumbing
permit, $10.00 to the Public Works Department for a sewer connection permit,
and a "delinquency" deposit of $19.20 (4 months sewer bill at $4.80 per month).
In the past, the City Council has allowed bills for Chapter 27 sewer facilities
work to be paid in ten annual installmenta when requested by the owners.
If you should have any questions regarding this matter, please contact this
Department at 350-7610,
James Mocalis
Acting Public Works Director
By: Carlos Navarro
Civil Engineering Assistant III
JM:CN:wR
City Counctl Agearia v' -6- Oe~eeber
(ZO. lei IlSllSS: Continued)
AV ~E ~ CYPRESS AVE~E ~R~ OF
~LLORY ORiVE:
~tton to tnstruct the Publlc torks D~r~tor to order
the construction of s/ntt/ry
Holtno Court between Oleander Avenue and C~ress Avenue
north of Ha}lory Or~ve under the provisions of the
Act of the Streets and Htghways Code.
PUBLIC
C. ~ENOZNG ORDZN~CE TO ESTABLISH NB ~GU~TIONS
RE~TiHG TO THE DISCHARGE OF NONDOHESTZC XASTBATER
THE PUBLIC SBER
(Z) Hotton to valve further readtag of Ordinance d
Hun~c~pal C~e of the Ctty of Fontaria ~tth respKt
to establishing regulations relattng to the
discharge of nond~sttc wasteater ~n the ;ubllc
se~r syste, that the reading of the t~tle
constitute ftrs~ reading theref.
(2) Hotton to ~ntr~uce Ordinance
~BLIC NO~S
.A.~
ALTE~TE AP~I~ TO AIR~
Atr~rt LaM Uses
12. ~ ~Zls
Adjourn to an ~Eut~ve
pursuant to ~vermnt C~0 ~on ~7.
13. .~) ._!~s g
Dacebar 6, 1988
16303 1El HOltno Court: ,,~//
l'on~ans, CA 9233~
-2-
UNDER I~E PROVISIONS OF C~R 27
OF THE S~EETS A~ HI~AYS CODE
AGENDA ITEH
CiTY COUNCIL ACTION REPORT
Dec. 6. 1988 New Business
Neering Date Agenda Placement
TO: Nayor and City Council
FROM: James Nocalts, Acting Public Norks Director
SUBOECT: PROPOSED CHAPTER 27 SEWER PROJECT ON EL HOLINO CT. BETWEEN
OLEANDER AVENUE AND CYPRESS AVENUE NORTH OF NALLORY DRIVE
CURRENT ACTION REQUESTFn:
HOTION TO iNSTRUCT THE PUBLIC WORKS DIRECTOR TO ORDER THE CONSTRUCTION OF
SANITARY SEWER FACILITIES ON EL NOLINO COURT BETWEEN OLEANDER AVENUE AND
CYPRESS AVENUE NORTH OF NALLORY DRIVE UNDER THE PROVISIONS OF THE 1911 ACT
OF THE STREETS AND HIGHWAYS CODE.
FISCAL IRPACT: IX { Yes [ [ No
The intttal cost of the work will be funded from the Sewer Fund at an
estimated cost of $11,400 and repaid to the fund through property owner
assessment spread over a maxlmum of 10 years.
MCKGROLIi):
Mr. Paul J. NcElroy has attempted three times to obtain the needed 60% of the
signatures needed (August 8, 1986, October 18, 1988, and November 14, 1988).
He has obtained the needed signatures on 4 of the 6 petitions (see attached
breakdown of petitions which are on file in the Public Works Department).
Authorization of the project will require a 4/5 vote of the City Council to
order the improvements installed.
aUSTIFICATIOIh
The ordering of these improvements would eliminate septic tank problems in the
project area and would ellmlnate the discharge of further amounts of nitrites
into the existing ground water basin.
ATI'ACI!~EHTS:
1. Breakdown of results of petition circulation
2. Location map
3. Petition location map
v
OTHER AFFECTEDDEPARTNENTS:
SIgnature SIgnature
ASST. MGR. PERSONNEL
ATTORNEY PLANNZNG
BLDG/SAFETY POLZCE
CLERK PW/ENGZNEERING
CON. DEV. PW/NA/NTENANCE
DEPUTY NGR. RDA
X FINANCE RISK NGMT.
' 'PARKS NA/NTENANCE SPEC. PROJ.
PARKS/REC.
RECOMMENDED:
Ctty Manager
- BREAKDOWN OF SEWER PETITION CIRCULATION FOR PROPOSED CHAPTER 27 SEWER PROJECT
ON EL MOLXNO COURT BETWEEN OLEANDER AVENUE AND CYPRESS AVENUE NORTH OF MALLORY DR.
Petition No. 1 - A total of 5 lots; signatures constitute 42% o~ the block,
Petition No. 2 - A total of 7 lots; signatures constitute 73% of the block.
Petition No. 3 - A total of 5 lots; signatures constitute 60% of the block.
Petition No. 4 - A total of 6 lots; signatures constitute 37% of the block.
Petition No. 5 - A total of 13 lots; signatures constitute 61% of the block,
Petition No. 6 - A total of 6 lots; signatures constitute 70% of the block.
This project will require a 4/5 vote of the City Council to order the improvements
installed.
ACTZQII: Hotton made by Council Hembet Boyles, seconded by ORDER CONST
Hayor Stmon, to tnstruct the Public Works Director to order EL HOLZNO/
the construction of sanitary seer facilities on [1 Holtno OLEAN/CYPRES
Court between Oleander Avenue and Cypress Avenue north of HO 88-449
December 6, 1988
Mallory Drive under the provisions of the 1911 Act of the
Streets and Htgl~vays Code. Hotton carried by 5 - 0 vote.
N ICET
NSTRUCT
Pursuant to the provisions of Chapter 27 of the "Improvement Act of 1911" of the State of
California:
NOTICE IS HEREBY GIVEN to construction - 0 - lineal feet of Portland cement
concrete curb and gutter, - 0 - square feet of Portland cemeot concrete sidewalk,
- 0 - squarefeet ofasphalt concrete paving,and 6$ T,.F. nf ~,~.~,r F.,-~H,=.
and aPPurtenances in front of your property located at
16303 E1 Mollrio Ct,. (APN 251-232-01~
Fontana, California.
All work shall be done in accordance with the City of Fontana Standard Specifications, Standard
Drawings and Plans, copies of which are on file in the Public Works Department of the City of
Fontana.
Before starting work it will be necessary for a construction permit to be obtained from the Public
Works Department. If the construction of said work or improvement is not commenced within 60
days after notice is given and diligently and without interruption prosecuted to completion, the
Superintendent of Streets shall cause the construction to be done and the cost of the same shall
be a lien on the property.
NOTICE IS FURTHER GIVEN THAT on
in the Council Chambers in the City Hall in the City of Fontana, California, the City Council will
hear and pass upon written or oral objections or protests, if any, to the proposed work or improve-
ment which may be raised by any property owner or other interested persons. Written protests
should be delivered to the City Clerk prior to the time set for the hearing.
Date December 23. 1988
Superintendent of Streets
City of Fontana, California
If further information is needed, please phone
City Hell, Public Works Department
(714) 350-7610
Ch.27 #246 H~over
N ICE'T
NSTRU
Pursuant to the provisions of Chapter 27 of the "Improvement Act of 1911" of the State of
CalifOrnia:
NOTICE IS HEREBY GIVEN to construction - 0 - lineal feet of Portland cement
concrete curb and gutter, - 0 - square feet of Portland cement concrete sidewalk,
- 0 - square feet of asphalt concrete paving, and 60 L.F. o£ sewer facili~'i~
and appurtenances in front of your property located at
16309 E1 Mol:Lno Ct. ('APN 251-232-02')
Fontana, California.
All work shall be done in accordance with the City of Fontana Standard Specifications, Standard
Drawings and Plans, copies of which are on file in the Public Works Department of the City of
Fontana.
Before starting work it will be necessary for a construction permit to be obtained from the Public
Works Department. If the construction of said work or improvement is not commenced within 60
days after notice is given and diligently and without interruption prosecuted to completion, the
Superintendent of Streets shall cause the construction to be done and the cost of the same shall
be a lien on the property.
NOTICE IS FURTHER GIVEN THAT on T~n,,.,-y ~ ~QRq at 6:00 p.m.
in the Council Chambers in the City Hall in the City of Fontana, California, the City Council will
hear and pass upon written or oral objections or protests, if any, to the proposed work or improve-
ment which may be raised by any property owner or other interested persons. Written protests
should be delivered to the City Clerk prior to the time set for the hearing.
Date December 23, 1988
Superintendent of Streets
City of Fontaria, California
'if further information is needed, please Dhone
City Hall, Public Works Department
(714)
Oh. 27. #246 Anderson
N
NSTRUCT
Pursuant to the provisions of Chapter 27 of the "Improvement Act of 1911" of the State of
California:
NOTICE IS HEREBY GIVEN to construction - 0 - lineal feet of Portland cement
concrete curb and gutter, - 0 - square feet of Portland cement concrete sidewalk,
- 0 - square feet of asphalt concrete paving, and 6n T..~. ~f ~.~ f~-~Cie~
and aPPurtenances in front of your property located at
16t17 ~1 Mnltnn ~f. (APN) ?~1-737-0~))
Fontana, California.
All work shall be done in accordance with the City of Fontana Standard Specifications, Standard
Drawings and Plans, copies of which are on file in the Public Works Department of the City of
Fontana.
Before starting work it wi II be necessary for a construction perm it to be obtai ned from the Public
Works Department. If the construction of said work or improvement is not commenced within 60
days after notice is given and diligently and without interruption prosecuted to completion, the
Superintendent of Streets shall cause the construction to be done and the cost of the same shall
be a lien on the property.
NOTICE IS FURTHER GIVEN THAT on T~,,,,=.-y t, ~9~9 at 6:00 v.m.
in the Council Chambers in the City Hall in the City of Fontana, California, the City Council will
hear and pass upon written or oral objections or protests, if any, to the proposed work or improve-
ment which may be raised by any property owner or other interested persons. Written protests
should be delivered to the City Clerk prior to the time set for the hearing.
Date December 23, 1988
Superintendent of Streets
City of Fontana, California
If further information is needed, please phone
City Hall, Public Works Department
(714) 359'-.76'10
Ch.27 #246 Turner
N ICE'T
NSTRUCT
Pursuant to the provisions of Chapter 27 of the "improvement Act of 1911" of the State of
California:
NOTICE IS HEREBY GIVEN to construction - o - lineal feet of Portland cement
concrete curb and gutter, - 0 - square feet of Portland cement concrete sidewalk,
- 0- square feet of asphatt concrete paving, and 60 L.F. o£ sewer facil'Lties
and appurtenances in front of your property located at
16325 E1 Molino Ct. (APN 25t-232-04~
Fontana, California.
All work shall be done in accordance with the City of Fontana Standard Specifications, Standard
Drawings and Plans, copies of which are on file in the Public Works Department of the City of
Fontana.
Before starting work it wi II be necessary for a construction permit to be obtai ned from the Public
Works Department. If the construction of said work or improvement is not commenced within 60
days after notice is given and diligently and without interruption prosecuted to completion, the
Superintendent of Streets shall cause the construction to be done and the cost of the same shall
be a lien on the property.
NOTICE IS FURTHER GIVEN THAT on .T~-,,~r~,
in the Council Chambers in the City Hall in the City of Fontana, California, the City Council will
hear and pass upon written or oral objections or protests, if any, to the proposed work or improve-
ment which may be raised by any property owner or other interested persons. Written protests
should be delivered to the City Clerk prior to the time set for the hearing.
Superintendent of Streets
City of Fontana, California
If further information is needed, please phone
City Hall, Public Works Department
(714)
Ch.27 #246 Palmet
NSTRU
Pursuant to the provisions of Chapter 27 of the "Improvement Act of 1911" of the State of
California:
NOTICE IS HEREBY GIVEN to construction - 0 - lineal feet of Portland cement
concrete curb and gutter, - n - square feet of Portland cement concrete sidewalk,
- 0 - squarefeet of asphalt concrete paving,and ~ T..~ n~ q~,~ F~t~
and appurtenances in front of your property located at
16333 E1 Mnl~nn (It, (APM 251-232-05]
Fontana, California.
All work shall be done in accordance with the City of Fontana Standard Specifications, Standard
Drawings and Plans, copies of which are on file in the Public Works Department of the City of
Fontana.
Before starting work it will be necessary for a construction permit to be obtained from the Public
Works Department. If the construction of said work or improvement is not commenced within 60
days after notice is given and diligently and without interruption prosecuted to completion, the
Superintendent of Streets shall cause the construction to be done and the cost of the same shall
be a lien on the property.
NOTICE IS FURTHER GIVEN THAT OnJanuary 3, 1989 at 6:00 p.m.
in the Council Chambers in the City Hall in the City of Fontana, California, the City Council will
hear and pass upon written or oral objections or protests. if any, to the proposed work or improve-
ment which may be raised by any property owner or other interested persons. Written protests
should be delivered to the City Clerk prior to the time set for the hearing.
Date DecPmhPr' ?3, 1988
Superintendent of Streets
City of Fontana, California
If further informltlon is needed, please phone
City Hall, Public Workl Department
(714) -35D,,,q~n, 0
Ch.27 #246 Hoover
N
NSTRUCT
Pursuant to the provisions of Chapter 27 of the "Improvement Act of 1911" of the State of
California:
NOTICE IS HEREBY GIVEN to construction - 0 - lineal feet of Portland cement
concrete curb and gutter, - 0 - square feet of Portland cement concrete sidewalk,
- 0 - square feet of asphalt concrete paving, and 65 L,F. nF se,,~r
and aDDurtenances in front of your property located at
16~73 E1 Molino Ct. (APN 251-232- 06)
Fontana, California.
All work shall be done in accordance with the City of Fontana Standard Specifications, Standard
Drawings and Plans, copies of which are on file in the Public Works Department of the City of
Fontana.
Before starting work it will be necessary for a construction permit to be obtained from the Public
Works Department. If the construction of said work or improvement is not commenced within 60
days after notice is given and diligently and without interruption prosecuted to completion, the
Superintendent of Streets shall cause the construction to be done and the cost of the same shall
be a lien on the property.
NOTICE IS FURTHER GIVEN THAT on January 3. 1989 at 6:00
in the Council Chambers in the City Hall in the City of Fontana, California, the City Council will
hear and pass upon written or oral objections or protests, if any, to the proposed work or improve-
ment which may be raised by any property owner or other interested persons. Written protests
should be delivered to the City Clerk prior to the time set for the hearing.
Date DpcPmher 23, 1988
Superintendent of Streets
City of Fontana, California
If further information is needed. please phone
City Hall, Public Works Department
(714)
Ch.27 #246 Morrow
N
NSTRU
Pursuant to the provisions of Chapter 27 of the "Improvement Act of 1911" of the State of
California:
NOTICE IS HEREBY GIVEN to construction - 0 - lineal feet of Portland cement
concrete curb and gutter, - 0 - square feet of Portland cement concrete sidewalk,
- 0 - square feet of asphalt concrete paving, and 6~ T.,~ nf: ~r F~-~14tle~ ~
and appnrtPn,qnc'e,~ in front Of your property located at
16381 E1 Molino Ct. (APN 251-232-07 )
Fontana, California.
All work shall be done in accordance with the City of Fontana Standard Specifications, Standard
Drawings and Plans, copies of which are on file in the Public Works Department of the City of
Fontana.
Before starting work it wi II be necessary for a construction permit to be obtained from the Public
Works Department, If the construction of said work or improvement is not commenced within 60
days after notice is given and diligently and without interruption prosecuted to completion, the
Superintendent of Streets shall cause the construction to be done and the cost of the same shall
be a lien on the property.
NOTICE IS FURTHER GIVEN THAT On January 3. 1989 at 6:00 p.m.
in the Council Chambers in the City Hall in the City of Fontana, California, the CiW Council will
hear and pass upon written or oral objections or protests, if any, to the proposed work or improve-
ment which may be raised by any property owner or other interested persons. Written protests
should be delivered to the City Clerk prior to the time set for the hearing.
Date npcpmh~r 23. 1988
Superintendent of Streets
City of Fontena, California
If further informltlon is needed. please phone
City Hall, Public Works Department
(714)
Ch.27 #246 Bansen
N I
NSTRUCT
Pursuant to the provisions of Chapter 27 of the "Improvement Act of 191'1" of the State of
Ca)ifornia:
NOTICE IS HEREBY GIVEN to construction - 0 - lineal feet of Portland cement
concrete curb and gutter, - 0 - square feet of Portland cement concrete sidewalk,
- 0 - squarefeet of asphalt concrete paving, and r~n L,F. o~ sewe~ f~c~l~t~n
and appurtenances jR front of your property located at
16389 E1 Moilrio Ct. (APN 251-232-08 )
Fontana, California,
All work shall be done in accordance with the City of FontIns Standard Specifications, Standard
Drawings and Plans, copies of which are on file in the Public Works Department of the City of
Fontana.
Before starting work it will be necessary for a construction permit tO be obtained from the Public
Works Department. If the construction of said work or improvement is not commenced within 60
days after notice is given and diligently and without interruption prosecuted to completion, the
Superintendent of Streets shall cause the construction to be done and the cost of the same shall
be a lien on the property.
NOTICE IS FURTHER GIVEN THAT OnJanuarv 3. 1989 at 6:00 p.m.
in the Council Chambers in the City Hall in the Ci.ty of FontIns, California, the City Council will
hear and pass upon written or oral objections or protests, if any, to the proposed work or improve-
ment which may be raised by any property owner or other interested persons. Written protests
should be delivered to the City Clerk prior to the time set for the hearing.
Date n~-pmhFr 23, ,3,988
Superintendent of Streets
City of Fontana, California
If furthiN' informltlon is needed, please phone
City Hall, Public Works Oepanment
(714) -3;.~),,-7610
Ch.27 #246 Lujan
N ICET
NSTRUCT
Pursuant to the provisions of Chapter 27 of the "Improvement Act of 1911" of the State of
California:
NOTICE IS HEREBY GIVEN to construction - 0 - lineal feet of Portland cement
concrete curb and gutter, - 0 - square feet of Portland cement concrete sidewalk,
- 0 - square feet of asphalt concrete paving, and ~n L.~. ~F =.,.,~f~i~t~.q
and appurtenances ili front of your property located at
16397 E1 Molino Ct. (APN 251-232-09 )
Fontaria, California.
All work shall be done in accordance with the City of Fontana Standard Specifications, Standard
Drawings and Plans, copies of which are on file in the Public Works Department of the City of
Fontana.
Before starting work it wi II be necessary for a construction permit to be obtained from the Public
Works Department. If the construction of said work or improvement is not commenced within 60
days after notice is given and diligently and without interruption prosecuted to completion, the
Superintendent of Streets shall cause the construction to be done and the cost of the same shall
be a lien on the property.
NOTICE IS FURTHER GIVEN THAT on January 3, 1989 at 6:00 p.m.
in the Council Chambers in the City Hall in the City of Fontana, California, the City Council will
hear and pass upon written or oral objections or protests, if any, to the proposed work or improve-
ment which may be raised by any property owner or other interested persons. Written protests
should be delivered to the City Clerk prior to the time set for the hearing.
Date np~-Pmher 2:], 1988
Superintendent of Streets
City of Fontana, California
If further infertuition is nildid, plelse phone
City HIll, Public Workl Oeplrtment
(714) -:~,~-7610
Ch.27 #246 Rosas
N 'TI
NS RUCT
Pursuant to the provisions of Chapter 27 of the "Improvement Act of 1911" of the State of
California:
NOTICE IS HEREBY GIVEN to construction - 0 - lineal feet of Portland cement
concrete curb and gutter, - 0 - square feet of Portland cement concrete sidewalk.
- 0 - square feet of asphalt concrete paving, and 60 L.F. o£ sewer
and aPPurtenances in front of your property located at
16407 E1 Molino Ct. (APN 251-232-10 )
Fontaria, California.
All work shall be done in accordance with the City of Fontana Standard Specifications, Standard
Drawings and Plans, copies of which are on file in the Public Works Department of the City of
Fontana.
Before starting work it will be necessary for a construction permit to be obtained from the Public
Works Department. If the construction of said work or improvement is not commenced withid 60
days after notice is given and diligently and without interruption prosecuted to completion, the
Superintendent of Streets shall cause the construction to be done and the cost of the same shall
be a lien on the property.
NOTICE IS FURTHER GIVEN THAT onJanuarv 3, 1989 at 6:00 p.m.
in the Council Chambers in the City Hall in the City of Fontana, California, the City Council will
hear and pass upon written or oral objections or protests, if any, to the proposed work or improve-
ment which may be raised by any property owner or other interested persons. Written protests
should be delivered to the City Clerk prior to the time set for the hearing.
Date Dpc~mhpr 2t, 1988
Superintendent of Streets
City of Fontena, California
If further informltlon is needed, please phone
City Hall, Public WoFka Department
(714) -3:~:)~76 ].0
Ch.27 #246 Clark
N ICET
NSTRUC
Pursuant to the provisions of Chapter 27 of the "Improvement Act of 1911" of the State of
California:
NOTICE IS HEREBY GIVEN to construction - 0 - lineal feet of Portland cement
concrete curb and gutter, - 0 - square feet of Portland cement concrete sidewalk,
- 0 - square feet of asphalt concrete paving, and 60 L.F. o£ sewer fac'illties
and appurtenances in front of your property located at
1~415 E] Mollno Ct. (APN 251-232-11 )
Fontana, California.
All work shall be done in accordance with the City of Fontana Standard Specifications, Standard
Drawings and Plans, copies of which are on file in the Public Works Department of the City of
Fontana.
Before starting work it wi II be necessary for a construction permit to be obtai ned from the Public
Works Department. If the construction of said work or improvement is not commenced within 60
days after notice is given and diligently and without interruption prosecuted to completion, the
Superintendent of Streets shall cause the construction to be done and the cost of the same shall
be a lien on the property.
NOTICE IS FURTHER GIVEN THAT on.Ianuarv 3. 1989 at 6:00 p.m.
in the Council Chambers in the City Hall in the City of Fontana, California, the City Council will
hear and pass upon written or oral objections or protests, if any, to the proposed work or improve-
ment which may be raised by any property owner or other interested persons. Written protests
should be delivered to the City Clerk prior to the time set for the hearing.
Date n~P~mher 23, 1988
Superintendent of Streets
City of Fontana, California
if further infOrmatiOn is needed. please phone
City Hall, Public Works Department
(714) -3:~:)~7610
" Ch.27 #246 O~.aeta
N ICE
NSTRUCT
Pursuant to the provisions of Chapter 27 of the "Improvement Act of 1911" of the State of
California:
NOTICE IS HEREBY GIVEN to construction - 0 - lineal feet of Portland cement
concrete curb and gutter, - 0 - square feet of Portland cement concrete sidewalk,
- 0 - square feet of asphalt concrete paving, and 65 LoFo of sewer
facilities and appurtenances in front of your property located at
16423 E1 Molino Ct, (APN 251-232-t2 )
Fontana, California.
All work shall be done in accordance with the City of FontIns Standard Specifications, Standard
Drawings and Plans, copies of which are on file in the Public Works Department of the City of
Fontana,
Before starting work it will be necessary for a construction permit to be obtained from the Public
Works Department. If the construction of said work or improvement is not commenced within 60
days after notice is given and diligently and without interruption prosecuted to completion, the
Superintendent of Streets shall cause the construction to be done and the cost of the same shall
be a lien on the property.
NOTICE IS FURTHER GIVEN THAT onJanua=v 3. 1989 at 6:00
in the Council Chambers in the City Hall in the City of FontIns, California, the City Council will
hear and pass upon written or oral objections or protests, if any, to the proposed work or improve-
ment which may be raised by any property owner or other interested persons. Written protests
should be delivered to the City Clerk prior to the time set for the hearing.
Date npcPmher 23, 1988
Superintendent of Streets
City of FontIns, California
If furYtier infOrmltiOn is needed. pielee phone
City HIll, Public Workl Department
(714) -~;.~)--7610
Ch. 27 #246 Ward
N ICET
NS RUCT
Pursuant to the provisions of Chapter 27 of the "Improvement Act of 1911" of the State of
California:
NOTICE IS HEREBY GIVEN to construction - 0 - lineal feet of Portland cement
concrete curb and gutter, - 0 - square feet of Portland cement concrete sidewalk,
-0-
square feet of asphalt concrete paving, and 65 L.F. of sewer fa~tq~+t,~
and appurtenances in front of your property located at
16463 E1 Molino Ct. (APN 251-237-]3 )
Fontana, California.
All work shall be done in accordance with the City of Fontana Standard Specifications, Standard
Drawings and Plans, copies of whik:h are on file in the Public Works Department of the City of
Fontana.
Before starting work it will be necessary for a construction permit to be obtained from the Public
Works Department. If the construction of said work or improvement is not commenced within 60
days after notice is given and diligently and without interruption prosecuted to completion, the
Superintendent of Streets shall cause the construction to be done and the cost of the same shall
be a lien on the property.
NOTICE IS FURTHER GIVEN THAT on3an. uarv 3, 1989 at 6:00 p.m. -
in the Council Chambers in the City Hall in the City of Fontana, California, the City Council will
hear and pass upon written or oral objections or protests, if any, to the proposed work or improve-
ment which may be raised by any property owner or other interested persons. Written protests
should be delivered to the City Clerk prior to the time set for the hearing.
Date nP~emher 23. 1988
Superintendent of Streets
City of Fontana, California
If further informltton is needed, please phone
City HNI. Public Works Oepanment
(714) -~.~'76 ].0
{'I,h.27 #246 ~^~ ....
N
NS, TRUCT
Pursuant to the provisions of Chapter 27 of the "Improvement Act of 1911" of the State of
California:
NOTICE IS HEREBY GIVEN to construction - 0 ~ lineal feet of Portland cement
concrete curb and gutter, - 0 - square feet of Portland cement concrete sidewalk,
- 0 - square feet of asphalt concrete paving, and60 T..F. seweT f~l~t~
and appurtenances jR front of your property located at
16471 E1 Molino Ct. (APN 251-232-14 )
Fontana, California.
All work shall be done in accordance with the City of Fontana Standard Specifications, Standard
Drawings and Plans, copies of which are on file in the Public Works Department of the City of
.Fontana.
Before starting work it will be necessary for a construction permit to be obtained from the Public
Works Department. If the construction of said work or improvement is not commenced within 60
days after notice is given and diligently and without interruption prosecuted to completion, the
Superintendent of Streets shall cause the construction to be done and the cost of the same shall
be a lien on the property.
NOTICE IS FURTHER GIVEN THAT on~nuarv 3, 1989 at 6:00
in the Council Chambers in the City Hall in the City of Fontaria, California, the City Council will
hear and pass upon written or oral objections or protests, if any, to the proposed work or improve-
ment which may be raised by any property owner or other interested persons. Written protests
should be delivered to the City Clerk prior to the time set for the hearing.
Date DPcPmher 23. 1988
Superintendent of Streets
City of Fontana, California
If further infonl~ltion is needed, please phone
City HIll, Public Works Department
(714) -~;,~76].0
Ch.27 #246 Vega
N I
NSTRU
Pursuant to the provisions of Chapter 27 of the "Improvement Act of 1911" of the State of
California:
NOTICE IS HEREBY GIVEN to construction - 0 - lineal feet of Portland cement
concrete curb and gutter, - 0 - square feet of Portland cement concrete sidewalk,
- 0 - square feet of asphalt concrete paving, and 60 L.F. of sewer fac'ilir. ies
and appurtenances in front of your property located at
16479 E1 Molino Court (APN 251-232-15 )
Fontsna, California.
All work shall be done in accordance with the City of Fontana Standard Specifications, Standard
Drawings and Plans, copies of which are on file in the Public Works Department of the City of
Fontana.
Before starting work it will be necessary for a construction permit to be obtained from the Public
Works Department. If the construction of said work or improvement is not commenced within 60
days after notice is given and diligently and without interruption prosecuted to completion, the
Superintendent of Streets shall cause the construction to be done and the cost of the same shall
be a lien on the property.
NOTICE IS FURTHER GIVEN THAT on January 3. 1989 at 6:oo
in the Council Chambers in the City Hall in the City of Fontana, California, the City Council will
hear and pass upon written or oral objections or protests, if any, to the proposed work or improve-
ment which may be raised by any property owner or other interested persons. Written protests
should be delivered to the City Clerk prior to the time set for the hearing.
Date n,~pmher 23. 1988
Superintendent of Streets
City of Fontana, California
If further informltlon i,, needed, please phone
City Hall, Public Works Oepartment
(714) -3;.~),-7610
Ch. 27 #246 Sgambati
N ICET
NSTRUCT
Pursuant to the provisions of Chapter 27 of the "Improvement Act of 1911" of the State of
California:
NOTICE IS HEREBY GIVEN to construction - 0 - lineal feet of Port and cement
concrete curb and gutter, - 0 - square feet of Portland cement concrete sidewalk.
-0-
square feet of asphalt concrete paving, and 60 L.F. of sewer
f~rt ] 'itt e.q F~nd appnrtenancPs in front of your property located at
16487 E1 Mollno Court (APN 251-232-16 )
Fontana, California.
All work shall be done in accordance with the City of Fontana Standard Specifications, Standard
Drawings and Plans, copies of which are on file in the Public Works Department of the City of
Fontana.
Before starting work it will be necessary for a construction permit to be obtained from the Public
Works Department. If the construction of said work or improvement is not commenced within 60
days after notice is given and diligently and without interruption prosecuted to completion, the
Superintendent of Streets shall cause the construction to be done and the cost of the same shall
be a lien on the property.
NOTICE IS FURTHER GIVEN THAT on,~anua~v 3. 1989 at 6:00
in the Council Chambers in the City Hall in the City of Fontana, California, the City Council will
hear and pass upon written or oral objections or protests, if any. to the proposed work or improve-
ment which may be raised by any property owner or other interested persons. Written protests
should be delivered to the City Clerk prior to the time set for the hearing.
Date n~remher 23, 1988
Superintendent of Streets
City of Fontshe, California
If further informBtlon is needed, please phone
City HIll, Public Workl 0eplrtment
(714)
" Ch.27 #246 Valenzuela
N ICET
NSTRUCT
Pursuant to the provisions of Chapter 27 of the "Improvement Act of 1911" of the State of
California:
NOTICE IS HEREBY GIVEN to construction - 0 - lineal feet of Portland cement
concrete curb and gutter, - 0 - square feet of Portland cement concrete sidewalk,
- 0 ~ squarefeet of asphalt concrete paving,and 65 L.F. <~f Rew~T
and apput:tenances in front of your property located at
16495 E1 Molino Court (APN 251-232-17 )
Fontana, California.
All work shall be done in accordance with the City of Fontana Standard Specifications, Standard
Drawings and Plans, copies of which are on file in the Public Works Department of the City of
Fontana.
Before starting work it will be necessary for a construction permit to be obtained from the Public
Works Department. If the construction of said work or improvement is not commenced within 60
days after notice is given and diligently and without interruption prosecuted to completion, the
Superintendent of Streets shall cause the construction to be done and the cost of the same shall
be a lien on the property.
NOTICE IS FURTHER GIVEN THAT On January 3. 1989 at 6:00 p.m.
in the Council Chambers in the City Hall in the City of Fontana, California, the City Council will
hear and pass upon written or oral objections or protests, if any, to the proposed work or improve-
ment which may be raised by any property owner or other interested persons. Written protests
should be delivered to the City Clerk prior to the time set for the hearing.
Date nP~'pmher 2q,. 1988
Superintendent of Streets
City of Fontana, California
If further informltion is nl~:led. please phone
City Hall, Public Works O~partment
(714) '3;~),-7610
Ch.27 #246 Aull
NSTRU
Pursuant to the provisions of Chapter 27 of the "Improvement Act of 1911" of the State of
California:
NOTICE IS HEREBY GIVEN to construction - 0 - lineal feet of Portland cement
concrete curb and gutter, - 0 - square feet of Portland cement concrete sidewalk,
- 0 - squarefeet of asphalt concrete paving, and 65 T..~. of sewer factli~
and appurtenances in front of your property located at
16304 E1 Molino Court (APN 251-231-09 )
Fontana, California.
All work shall be done in accordance with the City of Fontana Standard Specifications, Standard
Drawings and Plans, copies of whi~:h are on file in the Public Works Department of the City of
Fontana.
Before starting work it will be necessary for a construction permit to be obtained from the Public
Works Department. If the construction of said work or improvement is not commenced within 60
days after notice is given and diligently and without interruption prosecuted to completion, the
Superintendent of Streets shall cause the construction to be done and the cost of the same shall
· be a lien on the property.
NOTICE IS FURTHER GIVEN THAT On.Tanuarv 3, 1989 at 6:00 D,=. -
in the Council Chambers in the City Hall in the City of Fontaria, California, the City Council will
hear and pass upon written or oral objections or protests, if any, to the proposed work or improve-
ment which may be raised by any property owner or other interested persons. Written protests
should be delivered to the City Clerk prior to the time set for the hearing.
Date nPc~mher 2~. 1988
Superintendent of Streets
City of Fontana, California
If furlher informlltlon is needed, please phone
City Hill, Public WOrks Department
(714)
Ch.27 #246
N 'TICE T
NSTRU T
Pursuant to the provisions of Chapter 27 of the "Improvement Act of 1911" of the State of
California:
NOTICE IS HEREBY GIVEN to construction - 0 - lineal feet of Portland cement
concrete curb and gutter, - 0 - square feet of Portland cement concrete sidewalk,
- 0 - square feet of asphalt concrete paving, and 60 L.F. of sewer fac'i lit'l es
and appurtenances ill front of your property located at
16310 E1 Molino Court (APN 251-231-10 )
Fontana, California.
All work shall be done in accordance with the City of Fontaria Standard Specifications, Standard
Drawings and Plans, copies of which are on file in the Public Works Department of the City of
Fontana.
Before starting work it will be necessary foraconstruction permit to be obtained from the Public
Works Department. If the construction of said work or improvement is not commenced within 60
days after notice is given and diligently and without interruption prosecuted to completion, the
· Superintendent of Streets shall cause the construction to be done and the cost of the same shall
be a lien on the property.
NOTICE IS FURTHER GIVEN THAT On January 3. 1989 at 6:00 p.m.
in the Council Chambers in the City Hall in the City of Fontana, California, the City Council will
hear and pass upon written or oral objections or protests, if any, to the proposed work or improve-
ment which may be raised by any property owner or other interested persons. Written protests
should be delivered to the City Clerk prior to the time set for the hearing.
Date DPcPmher 23, 1988
Superintendent of Streets
City of Fontaria, California
If further informltion il nee:led. please phone
City HIll, Public Works Olplrtment
(714)
Ch. 27 #246 Tine
N ICE'T
NSTRUCT
Pursuant to the provisions of Chapter 27 of the "Improvement Act of 1911" of the State of
California:
NOTICE IS HEREBY GIVEN to construction - 0 - lineal feet of Portland cement
concrete curb and gutter, - 0 - square feet of Portland cement concrete sidewalk,
- 0 - square feet of asphalt concrete paving, and 60 L.F. of sewer facilities
and appurtenances in front of your property located at
16318 E1 MOLTNO Cnnrt (APN 251-231-11 )
Fontana, California.
All work shall be done in accordance with the City of Fontana Standard Specifications, Standard
Drawings and Plans, copies of which are on file in the Public Works Department of the City of
Fontana.
Before starting work it will be necessary for a construction permit to be obtained from the Public
Works Department. If the construction of said work or improvement is not commenced within 60
days after notice is given and diligently and without interruption prosecuted to completion, the
Superintendent of Streets shall cause the construction to be done and the cost of the same shall
be a lien on the property.
NOTICE IS FURTHER GIVEN THAT On January 3, 1989 at 6:00 p.m.
in the Council Chambers in the City Hall in the City of Fontana, California, the City Council will
hear and pass upon written or oral objections or protests, if any, to the proposed work or improve-
ment which may be raised by any property owner or other interested persons. Written protests
should be delivered to the City Clerk prior to the time set for the hearing.
Date npr~mhPr 23. 1988
Superintendent of Streets
City of Fontana, CaLifornia
If further information is needed. please phone
City Hall, Public Works Department
(714) -~.~'7610
Ch.27 #246 Van Norman
N ICET
NSTRUCT
Pursuant to the provisions of Chapter 27 of the "Improvement Act of 1911" of the State of
California:
NOTICE IS HEREBY GIVEN to construction - 0 - lineal feet of Portland cement
concrete curb and gutter, - 0 - square feet of Portland cement concrete sidewalk,
- 0 - square feet of asphalt concrete paving, and 60 L.F. o£ sewer £acil:Lt'ies
~n~ ~pp,~tpn~nr~ in front of your property located at
16326 E1 Molino Ct. (APN 251-231-12 )
Fontaria, California.
All work shall be done in accordance with the City of Fontana Standard Specifications, Standard
Drawings and Plans, copies of which are on file in the Public Works Department of the City of
Fontaria.
Before starting work it will be necessary for a construction permit to be obtai ned from the Public
Works Department. If the construction of said work or improvement is not commenced within 60
days after notice is given and diligently and without interruption prosecuted to completion, the
Superintendent of Streets shall cause the construction to be done and the cost of the same shall
be a lien on the property.
NOTICE IS FURTHER GIVEN THAT onJanua~:v 3. 1989 at 6:00
in the Council Chambers in the City Hall in the City of Fontana, California, the City Council will
hear and pass upon written or oral objections or protests, if any, to the proposed work or improve-
ment which may be raised by any property owner or other interested persons. Written protests
should be delivered to the City Clerk prior to the time set for the hearing.
Date Dl=rs~mb~,r 2~. lg88
Superintendent of Streets
City of Fontaria, California
If further informltlon il needed. please phone
City HIll. Public Workl Department
(714) -~:.~7610
" Ch.27 #246 Payne
N I
NSTRUCT
Pursuant to the provisions of Chapter 27 of the "Improvement Act of 1911" of the State of
California:
NOTICE IS HEREBY GIVEN to construction - 0 - lineal feet of Portland cement
concrete curb and gutter, - 0 - square feet of Portland cement concrete sidewalk,
- 0 - square feet of asphalt concrete paving, and 55,71 L,F, of: sewer facil:Ltj. es
and aDpur~:enances jR front of your property located at
16334 E1 Mol~_no Cour~ (APN 251-231-13 )
Fontana, California.
All work shall be done in accordance with the City of Fontana Standard Specifications, Standard
Drawings and Plans, copies of which are on file in the Public Works Department of the City of
Fontana.
Before starting work it will be necessary for a construction permit to be obtained from the Public
Works Department. If the construction of said work or improvement is not commenced within 60
days after notice is given and diligently and without interruption prosecuted to completion, the
Superintendent of Streets shall cause the construction to be done and the cost of the same shall
be a lien on the property.
NOTICE IS FURTHER GIVEN THAT onJanuarv 3. 1989 8t 6:00 D.at.
in the Council Chambers in the City Hall in the City of Fontana, California, the City Council will
hear and pass upon written or oral objections or protests, if any, to the proposed work or improve-
ment which may be raised by any property owner or other interested persons. Written protests
should be delivered to the City Clerk prior to the time set for the hearing.
Date D~cemhPr 23. 1988
Superintendent of Streets
City of Fontana, California
If furthlr informltlon is needed, please phone
City Hall, Public WOrks Department
(714) -3;~).,7610
Oh. 27 ~246 INGOLD
N ;TICET
NSTRU
Pursuant to the provisions of Chapter 27 of the "Improvement Act of 1911" of the State of
California:
NOTICE IS HEREBY GIVEN to construction - o - lineal feet of Portland cement
concrete curb and gutter, - 0 - square feet of Portland cement concrete sidewalk,
- o - square feet of asphalt concrete paving, and 81.4o L.F. of sewer facilites
and appurtenances in front of your property located at
16342 E1 Molino CT. (APN 251-231-14 )
Fontana, California.
All work shall be done in accordance with the City of Fontana Standard Specifications, Standard
Drawings and Plans, copies of which are on file in the Public Works Department of the City of
Fontana.
Before starting work it wi II be necessary for a construction permit to be obtai ned from the Public
Works Department. If the construction of said work or improvement is not commenced within 60
days after notice is given and diligently and without interruption prosecuted to completion. the
Superintendent of Streets shall cause the construction to be done and the cost of the same shall
be a lien on the property.
NOTICE IS FURTHER GIVEN THAT on3anuarv 3. 1989 at 6:00
in the Council Chambers in the City Hall in the City of Fontaria, California, the City Council will
hear and pass upon written or oral objections or protests, if any, to the proposed work or improve-
ment which may be raised by any property owner or other interested persons. Written protests
should be delivered to the City Clerk prior to the time set for the hearing.
Date n~Pmher 23, 1988
Superintendent of Streets
City of Fontane, California
If further informltion is needed, please phone
City Hall, Public WOrks Oepmnment
(714) -:~.-7610
Ch. 27 #246 Teal
N 'TICE T
NSTRUCT
Pursuant to the provisions of Chapter 27 of the "Improvement Act of 1911" of the State of
California:
NOTICE IS HEREBY GIVEN to construction - 0 - lineal feet of Portland cement
concrete curb and gutter, - 0 - square feet of Portland cement concrete sidewalk,
- 0 - square feet of asphalt concrete paving, and R1./.n T.. ~ n~ ~,~,J~ f~ciZ~ies
and appurtenances in front of your property located at
16350 E1 Molino Ct. (APN 251-231-15 )
Fontana, California.
All work shall be done in accordance with the City of Fontana Standard Specifications, Standard
Drawings and Plans, copies of which are on file in the Public Works Department of the City of
Fontana.
Before starting work it will be necessary for a construction permit to be obtained from the Public
Works Department. If the construction of said work or improvement is not commenced within 60
days after notice is given and diligently and without interruption prosecuted to completion, the
Superintendent of Streets shall cause the construction to be done and the cost of the same shall
be a lien on the property.
NOTICE IS FURTHER GIVEN THAT on January 3. 1989 at 6:0o p.m.
in the Council Chambers in the City Hall in the City of Fontana, California, the CiW Council will
hear and pass upon written or oral objections or protests, if any, to the proposed work or improve-
ment which may be raised by any property owner or other interested persons. Written protests
should be delivered to the City Clerk prior to the time set for the hearing.
Date nprPmhPr 23, 1988
Superintendent of Streets
City of Fontana, California
If further informltton is needed. please phone
City HIll, PUlPlie Workl Department
(714) -~h.,7610
Ch.27 #246 C~m~rhn
N ICET
NSTRUCT
Pursuant to the provisions of Chapter 27 of the "Improvement Act of 1911" of the State of
California:
NOTICE IS HEREBY GIVEN to construction - 0 - lineal feet of Portland cement
concrete curb and gutter, - 0 - square feet of Portland cement concrete sidewalk,
- 0 - squarefeet of asphalt concrete paving, and 52.97 L.F. of sewer facilities
and appurtenances in front of your property located at
16358 E1 Molino Ct. (APN 251-231-16 )
Fontana, California.
All work shall be done in accordance with the City of Fontana Standard Specifications, Standard
Drawings and Plans, copies of whi'ch are on file in the Public Works Department of the City of
Fontana.
Before starting work it will be necessary for a construction permit to be obtained from the Public
Works Department. If the construction of said work or improvement is not commenced within 60
days after notice is given and diligently and without interruption prosecuted to completion, the
Superintendent of Streets shall cause the construction to be done and the cost of the same shall
be a lien on the property.
NOTICE IS FURTHER GIVEN THAT on.tanuarv 3. 1989 81 6:00
in the Council Chambers in the City Hall in the City of Fontana, California, the City Council will
hear and pass upon written or oral objections or protests, if any, to the proposed work or improve-
ment which may be raised by any property owner or other interested persons. Written protests
should be delivered to the City Clerk prior to the time set for the hearing.
Date n~rPmher ?3, 1988
Superintendent of Streets
City of Fontana, California
If further information is needed. Dieass !ohone
CIty Hall. Public Works Oeplrtmant
(714)
Ch.~7 #246 Wallace
N ICET
NSTRUCT
Pursuant to the provisions of Chapter 27 of the "Improvement Act of 1911" of the State of
California:
NOTICE IS HEREBY GIVEN to construction - o - lineal feet of Portland cement
concrete curb and gutter, - 0 - square feet of Portland cement concrete sidewalk,
- 0 - square feet of asphalt concrete paving, and 60 L.F. o£ se,~er ~:ac:Llities
and aDpurtenaaces in front of your property located at
16366 El Molino Ct. (APN 251-231-17 )
Fontana, 'California.
All work shall be done in accordance with the City of Fontana Standard Specifications, Standard
Drawings and Plans, copies of which are on file in the Public Works Department of the City of
Fontana.
Before starting work it will be necessary for a construction permit to be obtained from the Public
Works Department. If the construction of said work or improvement is not commenced within 60
days after notice is given and diligently and without interruption prosecuted to completion, the
Superintendent of Streets shall cause the construction to be done and the cost of the same shall
be a lien on the property.
NOTICE IS FURTHER GIVEN THAT on3anuarv 3. 1989 at 6:00 p.m.
in the Council Chambers in the City Hall in the City of Fontana, California, the City Council will
hear and pass upon written or oral objections or protests, if any, to the proposed work or improve-
ment which may be raised by any property owner or other interested persons, Written protests
should be delivered to the City Clerk prior to the time set for the hearing.
Date ~pcPmhP~' 23, 1988
Superintendent of Streets
City of Fontana, California
If further informitlon is needed, pielee phone
City Hall, Public Works Department
(714)
" ~h,?7 #246
N 'TICE'T
NSTRU
Pursuant to the provisions of Chapter 27 of the "Improvement Act of 1911" of the State of
California:
NOTICE IS HEREBY GIVEN to construction - 0 - lineal feet of Portland cement
concrete curb and gutter, - 0 - square feet of Portland cement concrete sidewalk,
- 0 - square feet of asphalt concrete paving, and 60 L.F. of sewer £acilities and
appurtenances in front of your property located at
1~%7A R1 Hnl~no Ct. (APN 251-231-18 )
Fontana, California.
All work shall be done in accordance with the City of Fontana Standard Specifications, Standard
Drawings and Plans, copies of which are on file in the Public Works Department of the City of
Fontana.
Before starting work it will be necessary for a construction permit to be obtained from the Public
Works Department. If the construction of said work or improvement is not commenced within 60
days after notice is given and diligently and without interruption prosecuted to completion, the
Superintendent of Streets shall cause the construction to be done and the cost of the same shall
be a lien on the property.
NOTICE IS FURTHER GIVEN THAT on January 3. 1989 8t 6:00 p.m.
in the Council Chambers in the City Hall in the City of Fontana, California, the City Council will
hear and pass upon written or oral objections or protests, if any, to the proposed work or improve-
ment which may be raised by any property owner or other interested persons. Written protests
should be delivered to the City Clerk prior to the time set for the hearing.
Date n~cemher 23. 1988
Superintendent of Streets
City of Fontana, California
If further informltion is needed. please phone
City Hall, Public Works Department
(714)
Ch.27 #246 Lopez
N ICE
NS RUCT
Pursuant to the provisions of Chapter 27 of the "Improvement Act of 1911" of the State of
California:
NOTICE IS HEREBY GIVEN to construction - 0 - lineal feet of Portland cement
concrete curb and gutter, - 0 - square feet of Portland cement concrete sidewalk,
- 0 - square feet of asphalt concrete paving, and 60 L.F. o£ sewer faci],it'les
and a,~pul-f-en~ln(,.~.~ in front of your property located at
16382 E1 Molino Ct. (APN 251-231-19 )
Fontana, California.
All work shall be done in accordance with the City of Fontana Standard Specifications, Standard
Drawings and Plans, copies of which are on file in the Public Works Department of the City of
Fontana.
Before starting work it will be necessary for a construction permit to be obtained from the Public
Works Department. If the construction of said work or improvement is not commenced within 60
days after notice is given and diligently and without interruption prosecuted to. completion, the
Superintendent of Streets shall cause the construction to be done and the cost of the same shall
be a lien on the property.
NOTICE IS FURTHER GIVEN THAT on january 3. 1989 at 6:00 p.m.
in the Council Chambers in the City Hall in the City of Fontana, California, the City Council will
hear and pass upon written or oral objections or protests, if any, to the proposed work or improve-
ment which may be raised by any property owner or other interested persons. Written protests
should be delivered to the City Clerk prior to the time set for the hearing.
Date D~'Pmber 23. 1988
Superintendent of Streets
City of Forttans, California
If further information is needed. please phone
City Hall, Public Works Department
(714) ~.~:)~76].0
Ch,27 #246 Sandova].
N ICET
NSTRUCT
Pursuant to the provisions of Chapter 27 of the "Improvement Act of 1911" of the State of
California:
NOTICE IS HEREBY GIVEN to construction - 0 - lineal feet of Portland cement
concrete curb and gutter, - 0 - square feet of Portland cement concrete sidewalk,
- 0 - squarefeet of asphalt concrete paving,and 6n I. F. n{ ,=~=~,~t- F~c41it;iea
and appurtenances in front of your property located at
16390 E1 Molino Ct, (APN 251-231-20 )
Fontana, California.
All work shall be done in accordance with the City of Fontana Standard Specifications, Standard
Drawings and Plans, copies of which are on file in the Public Works Department of the City of
Fontana,
Before starting work it will be necessary for a construction permit to be obtai ned from the Public
Works Department. If the construction of said work or improvement is not commenced within 60
days after notice is given and diligently and without interruption prosecuted to completion, the
Superintendent of Streets shall cause the construction to be done and the cost of the same shall
be a lien on the property.
NOTICE IS FURTHER GIVEN THAT on January 3. 1989 at 6:00 p.m.
in the Council Chambers in the City Hall in the City of Fontana, California, the City Council will
hear and pass upon written or oral objections or protests, if any, to the proposed work or improve-
ment which may be raised by any property owner or other interested persons. Written protests
should be delivered to the City Clerk prior to the time set for the hearing.
Date n,=cPmh~r 23, 1988
Superintendent of Streets
City of Fontana, California
If furtrtlr informltlon is needed, please phone
City Hall, Public WOrks Department
(714)
Ch. 27 #246 Sweeney
N ICET
NSTRU
Pursuant to the provisions of Chapter 27 of the "improvement Act of 1911" of the State of
California:
NOTICE IS HEREBY GIVEN to construction - o - lineal feet of Portland cement
concrete curb and gutter, - o - square feet of Portland cement concrete sidewalk,
- 0 - square feet of asphalt concrete paving, and 60 L.F, o£ sewer £ac'[lit;;[.es
and a~purtensnces in front of your property located at
16398 E1 Molino Ct, (APN 251-231- 21 )
Fontana, California.
All work shall be done in accordance with the City of Fontana Standard Specifications, Standard
Drawings and Plans, copies of which are on file in the Public Works Department of the City of
Fontana.
Before starting work it will be necessary for a construction permit to be obtained from the Public
Works Department. If the construction of said work or improvement is not commenced within 60
days after notice is given and diligently and without interruption prosecuted to completion, the
Superintendent of Streets shall cause the construction to be done and the cost of the same shall
be a lien on the property.
NOTICE IS FURTHER GIVEN THAT on January 3. 1989 at 6:00 p.m.
in the Council Chambers in the City Hall in the City of Fontana, California, the City Council will
hear and pass upon written or oral objections or protests, if any, to the proposed work or improve-
ment which may be raised by any property owner or other interested persons. Written protests
should be delivered to the City Clerk prior to the time set for the hearing.
Date neoemher 23. 1988
Superintendent of Streets
City of Fontana, California
If further information is needed, please phone
City Hall. Put)lic Works Department
(714) 3;~0~76J, 0
Ch.27 #246 Hengeveld
NTI
NSTRUCT
Pursuant to the provisions of Chapter 27 of the "Improvement Act of 1911" of the State of
California:
NOTICE IS HEREBY GIVEN to construction - 0 - lineal feet of Portland cement
concrete curb and gutter, - 0 - square feet of Portland cement concrete side~valk,
- 0 - square feet of asphalt concrete paving, and ~n T ~. o~ sewer fac~l~rte~
and appurtenances in front of your property located at
16408 E1 Molino Ct. (APN 251-23~- ~ )
Fontana, California.
All work shall be done in accordance with the City of Fontana Standard Specifications, Standard
Drawings and Plans, copies of which are on file in the Public Works Department of the City of
Fontana.
Before starting work it will be necessary for a construction permit to be obtained from the Public
Works Department. If the construction of said work or improvement is not commenced within 60
days after notice is given and diligently and without interruption prosecuted to completion, the
Superintendent of Streets shall cause the construction to be done and the cost of the same shall
be a lien on the property.
NOTICE IS FURTHER GIVEN THAT on,Ianuarv 3. 1989 at 6:00 p.m.
in the Council Chambers in the City Hall in the City of Fontana, California, the City Council will
hear and pass upon written or oral objections or protests, if any, to the proposed work or improve-
ment which may be raised by any property owner or other interested persons. Written protests
should be delivered to the City Clerk prior to the time set for the hearing.
Date nprPmher 23, t988
Superintendent of Streets
City of Fontana, California
If further informltion is ne~:lKI. please phone
City Hall, Public Works Department
(714)
Ch. 27 f~246 Mann~on
NSTRUCT
Pursuant to the provisions of Chapter 27 of the "Improvement Act of 1911" of the State of
California:
NOTICE IS HEREBY GIVEN to construction - 0 - lineal feet of Portland cement
concrete curb and gutter, - 0 - square feet of Portland cement concrete sidewalk,
- 0 - square feet of asphalt concrete paving, and 60 L,F. o£ sewer fac'il~.t'Les
and apDurCenances in front of your property located at
1~41~ F. 1 Mn]ino Ct. (APN 251-231- 23)
Fontana, California.
All work shall be done in accordance with the City of Fontana Standard Specifications, Standard
Drawings and Plans, copies of which are on file in the Public Works Department of the City of
Fontana.
Before starting work it wi II be necessary for a construction permit to be obtained from the Public
Works Department. If the construction of said work or improvement is not commenced within 60
days after notice is given and diligently and without interruption prosecuted to completion, the
Superintendent of Streets shall cause the construction to be done and the cost of the same shall
be a lien on the property.
NOTICE IS FURTHER GIVEN THAT onJanuarv 3. 1989 at 6:00 D.111.
in the Council Chambers in the City Hall in the City of Fontana, California, the City Council will
hear and pass upon written or oral objections or protests, if any, to the proposed work or improve-
ment which may be raised by any property owner or other interested persons. Written protests
should be delivered to the City Clerk prior to the time set for the hearing.
Date D~cernht=r 23, t988
Superintendent of Streets
City of Fontane, California
If further information is needed. I)lease phone
City Hall. Public Works D®partment
(714) 3:~O,~76].0
Ch. 27 #246 Sanchez
N ICET
NSTRUCT
Pursuant to the provisions of Chapter 27 of the "Improvement Act of 1911" of the State of
California:
NOTICE IS HEREBY GIVEN to construction - 0 - lineal feet of Portland cement
concrete curb and gutter, - o - square feet of Portland cement concrete sidewalk,
- 0 - square feet of asphalt concrete paving, and 6o .L .F. o£ sewer fac'l litteR
and appurtenances in front of your property located at
16424 E1 Molino Ct. (APN 251-231- 24)
Fontana, California.
All work shall be done in accordance with the City of Fontana Standard Specifications, Standard
Drawings and Plans, copies of which are on file in the Public Works Department of the City of
Fontana.
Before starting work it will be necessary for a construction permit to be obtained from the Public
Works Department. If the construction of said work or improvement is not commenced within 60
days after notice is given and diligently and without interruption prosecuted to completion, the
Superintendent of Streets shall cause the construction to be done and the cost of the same shall
be a lien on the property.
NOTICE IS FURTHER GIVEN THAT On January 3. 1989 at 6:00 p.m.
in the Council Chambers in the City Hall in the City of Fontana, California, the City Council will
hear and pass upon written or oral objections or protests, if any, to the proposed work or improve-
ment which may be raised by any property owner or other interested persons. Written protests
should be delivered to the City Clerk prior to the time set for the hearing.
Date DPcPmher 23, 1988
Superintendent of Streets
City of Fontana, California
If further infOrmltion is needed, please phone
City Hall, Public Works Oepartrnent
(714) :~:)~-7610
Ch.27 #246 Rice
N ICET
NSTRU
Pursuant to the provisions of Chapter 27 of the "Improvement Act of 1911" of the State of
California:
NOTICE IS HEREBY GIVEN to construction - 0 - lineal feet of Portland cement
concrete curb and gutter, - 0 - square feet of Portland cement concrete sidewalk,
- 0 - square feet of asphalt concrete paving, and 60 L.~'. of .~ewe~' f~c~H~q
and 8DDurt:eD. ance8 in front of your property located at
16432 E1 Molino Ct. (APN 251-231-25 )
Fontana, California.
All work shall be done in accordance with the City of Fontana Standard Specifications, Standard
Drawings and Plans, copies of which are on file in the Public Works Department of the City of
Fontana.
Before starting work it will be necessary for a construction permit to be obtai ned from the Public
Works Department. If the construction of said work or improvement is not commenced within 60
days after notice is given and diligently and without interruption prosecuted to completion, the
Superintendent of Streets shall cause the construction to be done and the cost of the same shall
be a lien on the property.
NOTICE IS FURTHER GIVEN THAT on January 3. 1989 at 6:00 p.m.
in the Council Chambers in the City Hall in the City of Fontana, California, the City Council will
hear and pass upon written or oral objections or protests, if any, to the proposed work or improve-
ment which may be raised by any property owner or other interested persons. Written protests
should be delivered to the City Clerk prior to the time set for the hearing.
Date nPrprnher 23. 1988
Superintendent of Streets
CiW of Fontana, California
If further information is needed, please phone
City Hall Public Works Oeplrtment
(714) -~-,~h--7610
Ch.27 #246 Razon
N ICE'T
NSTRUCT
Pursuant to the provisions of Chapter 27 of the "Improvement Act of 1911" of the State of
California:
NOTICE IS HEREBY GIVEN to construction - 0 - lineal feet of Portland cement
concrete curb and gutter, - 0 - square feet of Portland cement concrete sidewalk,
- 0 ~ squarefeet of asphalt concrete paving, and 41.66 L,F. of sewer facil'lr~e~
and appurt:enances in front of your property located at
16440 E1 Molino Ct, (APN 251-231-26 )
Fontana, California.
All work shall be done in accordance with the City of Fontana Standard Specifications, Standard
Drawings and Plans, copies of which are on file in the Public Works Department of the City of
Fontaria.
Before starting work it wiII be necessary for a construction permit to be obtai ned from the Public
Works Department. If the construction of said work or improvement is not commenced within 60
days after notice is given and diligently and without interruption prosecuted to completion, the
Superintendent of Streets shall cause the construction to be done and the cost of the same shall
be a lien on the property.
NOTICE IS FURTHER GIVEN THAT onJanuarv 3, 1989 at 6:00 p.m.
in the Council Chambers in the City Hall in the City of Fontana, California, the City Council will
hear and pass upon written or oral objections or protests, if any, to the proposed work or improve-
ment which may be raised by any property owner or other interested persons, Written protests
should be delivered to the City Clerk prior to the time set for the hearing.
Date n~cpmhPr 23, 1988
Superintendent of Streets
City of Fontana, California
If further infofmltion i$ needed, pleame phone
City Hall, Public Works Department
(714) -3;,~4~7610
Ch. 27 #246 ~gan
N ICET
NSTRU
Pursuant to the provisions of Chapter 27 of the "Improvement Act of 1911" of the State of
California:
NOTICE IS HEREBY GIVEN to construction - 0 - lineal feet of Portland cement
concrete curb and gutter, - 0 - square feet of Portland cement concrete sidewalk,
- 0 - square feet of asphalt concrete paving, and 90;70 L.F. ~ ~ewer ~,'~i,-.
and appurtenances in front of your property located at
16448 E1 Mollno Ct. (APN 251-231-27 )
Fontana, California.
All work shah be done in accordance with the City of Fontana Standard Specifications, Standard
Drawings and Plans, copies of which are on file in the Public Works Department of the City of
FoRtans.
Before starting work it will be necessary for a construction permit to be obtained from the Public
Works Department. If the construction of said work or improvement is not commenced within 60
days after notice is given and diligently and without interruption prosecuted to completion, the
Superintendent of Streets shall cause the construction to be done and the cost of the same shall
be a lien on the property.
NOTICE IS FURTHER GIVEN THAT on,~anuarv 3, ].989 at 6:00
in the Council Chambers in the City Hall in the City of Fontaria, California, the City Council will
hear and pass upon written or oral objections or protests, if any, to the proposed work or improve-
ment which may be raised by any property owner or other interested persons. Written protests
should be delivered to the City Clerk prior to the time set for the hearing.
Date nprPmhPr 23. 1988
Superintendent of Streets
City of Fontana, California
If further information is needed, please phone
City Hall, Public Works Department
(714) -~0-7610
C..h, 27 #246 Sit:ompul
N ICET
NSTRUCT
Pursuant to the provisions of Chapter 27 of the "Improvement Act of 1911" of the State of
California:
NOTICE IS HEREBY GIVEN to construction ~ 0 - lineal feet of Portland cement
concrete curb and gutter, - 0 - square feet of Portland cement concrete sidewalk,
- 0 - square feet of asphalt concrete paving, and 90,]0 L,F, of sewer facilities
and appurtenances in front of your property located at
16456 E1 Molino' Ct, (APN 251-23 1~ 28 )
Fontana, California.
All work shall be done in accordance with the City of Fontana Standard Specifications, Standard
Drawings and Plans, copies of which are on file in the Public Works Department of the City of
Fontaria.
Before starting work it will be necessary for a construction permit to be obtained from the Public
Works Department. If the construction of said work or improvement is not commenced within 60
days after notice is given and diligently and without interruption prosecuted to completion, the
Superintendent of Streets shall cause the construction to be done and the cost of the same shall
be a lien on the property.
NOTICE IS FURTHER GIVEN THAT on January 3. 1989 8t 6:00 p.m.
in the Council Chambers in the City Hall in the City of Fontana, California, the City Council will
hear and pass upon written or oral objections or protests, if any, to the proposed work or improve-
ment which may be raised by any property owner or other interested persons. Written protests
should be delivered to the City Clerk prior to the time set for the hearing.
Date npcPmher 23. 1988
Superintendent of Streets
City of Fontana, California
If further informltion il needed. please phone
City Hall. Public Works Oepartment
(714)
Ch.27 #246 Stillwell
N I
NSTRUCT
Pursuant to the provisions of Chapter 27 of the "Improvement Act of 1911" of the State of
California:
NOTICE IS HEREBY GIVEN to construction - 0 - lineal feet of Portland cement
concrete curb and gutter, - 0 - square feet of Portland cement concrete sidewalk,
- 0 - square feet of asphalt concrete paVing, and 48,45 L.F. of sewer facilir~e~
and aDDurtenance8 in front of your property located at
16464 E1 Molino Ct, (AgN 251-231-29 )
Fontana, California.
All work shall be done in accordance with the City of Fontana Standard Specifications. Standard
Drawings and Plans, copies of which are on file in the Public Works Department of the City of
Fontana.
Before starting work it wi II be necessary for a construction permit to be obtai ned from the Public
Works Department. If the construction of said work or improvement is not commenced within 60
days after notice is given and diligently and without interruption prosecuted to completion, the
Superintendent of Streets shall cause the construction to be done and the cost of the same shall
be a lien on the property.
NOTICE IS FURTHER GIVEN THAT on,Ianuarv 3. 1989 at 6:00
in the Council Chambers in the City Hall in the City of Fontana, California, the City Council will
hear and pass upon written or oral objections or protests, if any, to the proposed work or improve-
ment which may be raised by any property owner or other interested persons. Written protests
should be delivered to the City Clerk prior to the time set for the hearing.
Date D.oemher 23. 1988
Superintendent of Streets
City of Fontana, California
If further information i- needed. please phone
City Hall, Public Works Department
(714) -3:~>-7610
Ch. 27 #246 Jamerson
N ICET
NSTRUCT
Pursuant to the provisions of Chapter 27 of the "Improvement Act of 1911" of the State of
California:
NOTICE IS HEREBY GIVEN to construction - o - lineal feet of Portland cement
concrete curb and gutter, - 0 - square feet of Portland cement concrete sidewalk, - 0 - square feet of asphalt concrete paving, and 6o T .~,. of ~ewer facil'[ties
and appurtenances in front of your property located at
16472 ~1 Molino Ct. (APN 251-231-30 )
Fontana, California.
All work shall be done in accordance with the City of Fontana Standard Specifications, Standard
Drawings and Plans, copies of which are on file in the Public Works Department of the City of
Fontana.
Before starting work it will be necessary for a construction permit to be obtained from the Public
Works Department, If the construction of said work or improvement is not commenced within 60
days after notice iS given and diligently and without interruption prosecuted to completion, the
Superintendent of Streets shall cause the construction to be done and the cost of the same shall
be a lien on the property.
NOTICE IS FURTHER GIVEN THAT on January 3. 1989 at 6:00
in the Council Chambers in the City Hall in the City of Fontana, California, the City Council will
hear and pass upon written or oral objections or protests, if any, to the proposed work or improve-
ment which may be raised by any property owner or other interested persons. Written protests
should be delivered to the City Clerk prior to the time set for the hearing.
Date DPeemhPr 23, 1988
Superintendent of Streets
City of Fontana, California
if further informltion il n~ldKI, please phone
City Hall, Public Works Department
(714) -~0~7610
Ch.27 #246 Keever
N 'TI
NSTRUCT
Pursuant to the provisions of Chapter 27 of the "Improvement Act of 1911" of the State of
California:
NOTICE IS HEREBY GIVEN to construction - 0 - lineal feet of Portland cement
concrete curb and gutter, - 0 - square feet of Portland cement concrete sidewalk,
- 0 - squarefeet of asphalt concrete paving, and 60 LoF. o£ sewer £acil'lt;ieR
and appurtenances in'front of your property located at
16480 E1 Molino Ct. (APN 251-231-31 )
Fontana, California.
All work shall be done in accordance with the City of Fontana Standard Specifications, Standard
Drawings and Plans, copies of which are on file in the Public Works Department of the City of
Fontana.
Before starting work it wi II be necessary for a construction permit to be obtained from the Public
Works Department. If the construction of said work or improvement is not commenced within 60
days after notice is given and diligently and without interruption prosecuted to completion, the
Superintendent of Streets shall cause the construction to be done and the cost of the same shall
be a lien on the property.
NOTICE IS FURTHER GIVEN THAT on-Ianuarv 3. 1989 at 6:00 p.m.
in the Council Chambers in the City Hall in the City of Fontana, California, the City Council will
hear and pass upon written or oral objections or protests, if any, to the proposed work or imp rove-
ment which may be raised by any property owner or other interested persons. Written protests
should be delivered to the City Clerk prior to the time set for the hearing.
Date n~cPtnher 23, 1988 I
Superintendent of Streets
City of Fontaria, California
If further informetlon i$ neeaed. ple&$e p~one
City HIll, Put)liC Works Del~rlment
(714) ':~,~:~7610
Ch. 27 #246 Westbrook
N ICET
NSTRU T
Pursuant to the provisions of Chapter 27 of the "Improvement Act of 1911" of the State of
California:
NOTICE IS HEREBY GIVEN to construction - 0 - lineal feet of Portland cement
concrete curb and gutter, - 0 - square feet of Portland cement concrete sidewalk,
-0-
square feet of asphalt concrete paving, and 6n T. ~' ,~: .~.~,~.?- facil-l t:'l es
arid appurtenances in front of your property located at
16488 E1 Molino Ct. (APN 251-231-32 )
Fontaria, California.
All work shall be done in accordance with the City of Fontana Standard Specifications, Standard
Drawings and Plans, copies of whrch are on file in the Public Works Department of the City of
Fontaria.
Before starting work it will be necessary for a construction permit to be obtained from the Public
Works Department. If the construction of said work or improvement is not commenced within
days after notice is given and diligently and without interruption prosecuted to completion, the
Superintendent of Streets shall cause the construction to be done and the cost of the same shall
be a lien on the property.
NOTICE IS FURTHER GIVEN THAT onJauuarv 3. 1989 at 6:00
in the Council Chambers in the City Hall in the City of Fontana, California, the City Council will
hear and pass upon written or oral objections or protests, if any, to the proposed work or improve-
ment which may be raised by any property owner or other interested persons. Written protests
should be delivered to the City Clerk prior to the time set for the hearing.
Date rl~,~'~=mher 2t, 1988
Superintendent of Streets
City of Fontana, California
If further informltlon ia need/d, please tohone
City Hall, Public Works Department
(714)
C,h. 57 #246 Kondus
N ICET
NSTRUCT
Pursuant to the provisions of Chapter 27 of the "Improvement Act of 1911" of the State of
California:
NOTICE IS HEREBY GIVEN to construction - 0 - lineal feet of Portland cement
concrete curb and gutter, - 0 - square feet of Portland cement concrete sidewalk,
- 0 - square feet of asphalt concrete paving, and 65 L.F. of sewer {:acil:[t:L~R
and appurtenances in front of your property located at
16496 E1 Molino Ct. (APN 251-231-33 )
Fontana, California.
All work shall be done in accordance with the City of Fontana Standard Specifications, Standard
Drawings and Plans, copies of whi~:h are on file in the Public Works Department of the City of
Fontana.
Before starting work it will be necessary for a construction permit to be obtained from the Public '
Works Department. If the construction of said work or improvement is not commenced within 60
days after notice is given and diligently and without interruption prosecuted to completion, the
Superintendent of Streets shall cause the construction to be done and the cost of the same shall
be a lien on the property,
NOTICE IS FURTHER GIVEN THAT on january 3. 1989 at 6:00
in the Council Chambers in the City Hall in the City of Fontana, California, the City Council will
hear and pass upon written or oral objections or protests, if any, to the proposed work or improve-
ment which may be raised by any property owner or other interested persons. Written protests
should be delivered to the City Clerk prior to the time set for the hearing.
Date Dpr~mher 2~, 1988
Superintendent of Streets
City of Fontana, California
If further informltion is ne~:led, please phone
City Hall, Public Works Department
(714) ':~.~)-7610
Oanuary 3, [989
Public hearing was opened on notice to construct street gC PH ITEM
improvements on E1 Moltno Court between Oleander Avenue and CONT. 2/7/89
Cypress Avenue north of Mallory Drive (Ch. 27 #246). There CHPT 27 #246
were no written communications received In favor of or in NO 8g-21
opposition to this proposal, Director Mocalh suggested post-
pontng this ~tem due to confusion over some of the lots who
are hooked in to the sewer l~ne on the neighboring tract, and
therefore, w~11 receive zero benefit and zero charge.
Speaking in favor of thts proposal was: (Z) Pamela Hengeveld,
[6398 E1 Moltno Court, Fontana, who requested the 10year 6%
interest assessment on her property. Speaking tn opposition
to this proposal were: (1) Barbara Anderson, 16309 E1 Moltno
Court; (2) Mr. Anderson, 16309 E1 Moltno Court, and (3) 0elf
Carmello, 16464 E1 Moltno Court; who were all concerned about
the charges and felt the residents should be given an accurate
estimate of the cost.
ACTION: Motion made by Council Member Murray, seconded by
Counctl Member Kragness, to continue this item unit1 February 7,
1989 and directed staff to provide for accurate information to
the residents on the costs; permtts, 1the Installation, fees and
monthly charges. Motion carried by 5-0 vote.
February 7, 1989
Public hearing on notlce to construct sewer improvements 90 ITEM CONT
on E1Noltna Court between 01eander Avenue and Cypress TIL 2/21
Avenue north of Mallory Drive (Ch. 27 #246) was continued MO 89-70
as follows:
AC'rION= Notion made by Council Member Kragness, seconded
by Council Member Murray, to continue the publlc hearing
until the meeting of February 21, 1989, as requested by
staff. Motion carried by 5-O vote.
City of Fontana
CALIFORNIA
January 5, 1989
File: Chapter 27 #246
Mr. Ken Heasley
16304 E1Molino Ct.
Fontana, CA 92335
This is in response to your letter dated December 28, 1988.
The posting of your property was an oversight on my behalf. You do have
a legal voice on the current project as proposed. But I assure you,
there will be no cost assessed to you nor any lien against your property.
George Gaswell
Acting Public Works Director
By: Carlos Navarro
Civil Engineering Assistant III
GC~CN:ll
8353 SIERRA AVENUE (P.O. BOX 518) FONTANA, CALIFORNIA 92334-0518 (714) 350-7600
December 28, 1988
SUPERINTENDENT OF STREETS
CITY HALL
8353 Sierra Av
Fontana CA 92335
ATTN: Wilma
This is a written protest to the NOTICE TO CONSTRUCT
posted in my yard December 23, 1988. The same notice
was posted on December 5, 1980, and I was later'billed
$873.40 for sanitary sewer facilities installed in
Mallory Drive between Oleander and Cypress.
The above mentioned construction and resulting bill
is now a lien against the property and accrues~6%
per annum and is collected with my property taxes.
In August of 1988, Permit No. 49194, I paid for the
necessary permit and sewer connection; a total of
$651.20, and later hooked up to the facilities.
I feel I should not have to be assessed again for
Public Works that I am already paying for and using.
Respond as soon as possible to this written protest
to further assessments on 16304 E1 Molino Ct.
Sincerely,
Mr Ken Heasley
16304 E1 Molino Ct
Fontana CA 92335
N lET
NSTRUCT
Pursuant to the provisions of Chapter 27 of the "Improvement Act of 1911" of the State of
California:
NOTICE IS HEREBY GIVEN to construction -0- lineal feet of Portland cement
concrete curb and gutter, -o- square feet of Portland cement concrete sidewalk,
o square feet of asphalt concrete paving, and 60 L .F. of sewer facilit:Les
and appurtenances in front of your property located at
16309 El Molino Ct. (APN 251-232-02)
Fontana, California.
All work shall be done in accordance with the City of Fontana Standard Specifications, Standard
Drawings and Plans, copies of which are on file in the Public Works Department of the City of
Fontana.
Before starting work it will be necessary for a construction permit to be obtained from the Public
Works Department. If the construction of said work or improvement is not commenced within 60
days after notice is given and diligently and without interruption prosecuted to completion, the
Superintendent of Streets shall cause the construction to be done and the cost of the same shall
be a lien on the property.
NOTICE IS FURTHER GIVEN THAT on April 4. 1989 at 6:00 p.,..
in the Council Chambers in the City Hall in the City of Fontana, California, the City Council will
hear and pass upon written or oral objections or protests, if any, to the proposed work or improve-
ment which may be raised by any property owner or other interested persons. Written protests
should be delivered to the City Clerk prior to the time set for the hearing.
Date March 24, 1989
Superintendent of Streets
City of Fontana, California
If further information is needed, please phone
City Hail, Public Works Department
(714) 89~-L%414-- 350-7610
Ch. 27 #246 Anderson
File: Ch. 27 #246
16381 E1 Molino Ct.
APN 251-232-07
Steve L. & Sandra L. Hansen
16381 E1 Molino Ct.
Fontana, CA 92335
File: Ch. 27 #246
16389 E1 Molino Ct.
APN 251-232-08
Eddie Lujan
16389 E1 MolinoCt.
Fontana, CA 92335
File: Ch. 27 #246
16397 E1 Molino Ct.
APN 251-232-09
Daniel C. & Juanita Rosas
16397 E1 Molino Ct,
Fontana, CA 92335
File: Ch. 27 #246
16407 E1 Molino Ct.
APN 251-232-10
Rose B. & Larry J, Clark
16407 E1 Molino Ct.
Font~na, CA 92335
File: C~. 27 #246
16415 E1 Molino Ct.
APN 251-232-11
Robert Ozaeta
16433 Aliso Dr.
Fontana,CA 92335
File: Ch. 27 #246
16423 E1 Molino Ct.
APN 251-232-12
Paul & Shelly Ward
16423 E1 Molino Ct.
Fontana, CA 92335
-2-
File: Ch. 27 ~246
16463 E1 Molino Ct.
APN 251-232-13
Stephen B. & Lea M. Johnson
16463 E1 Molino
Fontana, EA 92335
File: Eh. 27 #246
16471 E1 Molino Ct.
APN 251-232-14
Luis A. & Evangelina V. Vega
16473 E~ Molino Ct.
Fontana CA 92335
File: Ch. 27 #246
16479 E1 Mollrio Ct.
APN 251-232-15
Barbara S. & Michael Fo Sgambati, Sr.
16479 E1 Molino Ct.
Fontana CA 92335
File: Ch..27 #246
16487 E1 Molino Ct.
APN 251-232-16
Dolores & Raymond Valenzuela
16487 E1 Mollrio Ct.
Fontaria, CA 92335
File: Ch. 27 #246
16495 E1 Mollrio Ct.
APN 251-232-17
Darcella A. Aull
16495 E1 Molino Ct.
Fontaria CA 92335
............
ile: Ch. 27 #246
APN 251-231-09
Kenneth W. Kathleen Heasley
16304 E1 Mol _o Ct.
-3-
File: Ch. 27 #246
16310 E1 Molino Ct.
APN 251-231-10
Ralph E. & Gall Van Tine
16310 E1 Molino Ct.
Fontana, CA 92335
File: Ch. 27 #246
16318 E1 Molino Ct.
APN 251-231-11
Tom R. & Peggy L. Van Norman
16318 E1 Molino Ct.
Fontana, CA 92335
File: Cho 27 #246
16326 E1 Molino Ct.
APN 251-231-12
James F. & Judy D. Payne
9784 Tangelo
Bloomington, CA 92316
File: Ch. 27 #246
16314 E1 Molino Ct.
APN 251-231-13
Raymond Ingold
11050 Bryant St., Space 63
Yucaipa, CA 92399
File: Ch. 27 #246
16342 E1 Molino Ct.
APN 251-231-14
Janice & George Teal, Jr.
16342 E1 Molino Ct.
Fontana, CA 92335
File: Ch. 27 #246
16350 E1 Molino Ct.
APN 251-231-15
Armando A. Camacho
16350 E1 Molino Ct.
Fontana, CA 92335
-4-
File: Ch. 27 #246
16358 E1 Molino Ct.
APN 251-231-16
Ronald G. & Thelma B. Wallace
16358 E1 Molino Ct.
Fontaria CA 92335
File: Ch. 27 #246
16366 E1 Molino Ct.
APN 251-231-17
Bertha M. Andrade
16366 E1 Molino Ct.
Fontana CA 92335
File: Ch. 27 #246
1637~ E1 Molino Ct.
APN 251-231-18
Charles B. & Clara A. Lopez
16374 E1 Molino Ct.
Fontana CA 9233b
File: Ch. 27 #246
16382 El Molino Ct.
Fontana, CA 92335
Rudolpho Sandoval
16382 E1 Molino Ct.
Fontana CA 92335
File: Ch. 27 #246
16390 E1 Molino Ct.
Fontana, CA 92335
James A. Sweeney
16390 E1 Molino Ct.
Fontana, CA 92335
File: Ch. 27 #246
16398 E1 Molino Ct.
APN 251-231-21
Gary J. & Pamela M. Hengeveld
16398 E1 Molino Ct.
Fontana, CA 92335
-5-
File: Ch. 27 #246
16408 E1 Molino Ct.
~D1LtaLl~, CA 9233frc~
Vada L. Mannion
16408 E1 Molino Ct.
Fontana, CA 92335
File: Ch. 27 #246
~ontana,
Rodolfo & Eloisa Sanchez
16416 E1 Molino Ct.
Fon~ana, CA 92335
.File: Ch. 27 ~246
16424 E1 Mollrio Ct.
APN 251-231-24
Daniel S. & Redona L. Rice
105 W. Virginia, Apt. D
Rialto, CA 92376
File: Ch. 27 #246
16432 E1 Molino Ct.
APN 251-231-25
Juan Estrada & Rosa Razon
16432 E1 Molino Ct.
Fontana, CA 92335
File: Ch. 27 #246
16440 E1 Molino Ct.
APN 251-231-26
Margaret Egan
16440 E1 Molino Ct.
Fotnana, CA 92335
File: Ch. 27 #246
16448 E1 Molino Ct.
APN 251-231-27
Paul P. & Gladys A. Sitompul
619 Norwood Ct.
San Dimas, CA 91773
-6-
File: Ch. 27 ~246
16456 E1 Molino Ct.
APN 251-231-28
Ronald & Sharon A. Stillwell
16456 E1 Molino Ct.
Fontana, CA 92335
File: Ch. 27 #246
16464 E1 Molino Ct.
APN 251-231-29
Gynthia Jamerson
16464 E1 Molino Ct.
Fontana CA 92335
File: Ch.. 27 #246
16472 E1 Molino Ct.
APN 251-231-30
Grace P. Keever
16472 E1 Molino Ct.
Fotnana CA 92335
File: Ch. 27 #246
16480 E1 Molino Ct.
APN 251-231-31
Charles L. & Bernice P. Westbrook
16480 E1 Molino Ct.
Fontana, CA 92335
File: Ch. 27 #246
16488 E1 Molino Ct.
APN 251-231-32
Millie J. Kondus
16488 E1 Molino Ct.
Fontana CA 92335
File: Ch. 27 #246
16496 E1 Molino Ct. ~ ~
Guy R. & Joyce A. Centanni
16496 E1 Molino Ct.
Fontaria, CA 92335
-7-
~nuary 2, 1989
Carlos:
The following people have said that they shouldnvt be included in the E1 Molino
Court Sewer Installation Project:
Guy Centanni, 16496 E1 Molino, 823-1463 (says he is connected already to Mallory
sewers and paid through that project.)
Heasley, 16304 E1 Molino Ct., 829-1968 (corner of E1 Molino & Mallory, says he is
already connected to Mallory project.)
Rhonald A. Wallace, 16358 1 - a o ract
behind him--has been on sewer for some time.)
Hoover (one property on corner of E1 Molino Ct. & Mallory? Seems to have connected
to ~{allory Project)
City of Fontana
CALIFORNIA
April 27, 1989
File: Proposed E1Molino Sewer
Installation Project
Property Owner:
Subject: Proposed Installation of Sanitary Sewer Facilities in
E1Molino Court between Oleander Avenue & Cypress Avenue
North of Mallory Drive
This is to inform you that the Engineering Division of the Public Works
Department of the City of Fontaria is not continuing the Public Hearing on
the subject project. The Public Hearing had been continued to the Council
meeting of May Znd~ however, because of irregularities in the petition sig-
natures and because of the strong objections which the City has received from
some of the property owners involved in this project, the Public Hearing has
not been placed on the May Znd Council agenda.
If there are property owners who still feel strongly about going ahead with
the installation of sewers in this area, there is the option of a property
owner who is willing to do so circulating new petitions. If any property owner
is interested in doing this, the Engineering Division should be contacted for
the necessary petitions and an explanation of the process.
We regret that we were unable to carry this project to completion. If we can
be of any assistance to you or answer any questions, please contact this office
at 350-7610.
Sincerely,
Annivory Calvert
Public Works Director
By: Carlos Navarro
Civil Engineering Assistant III
AC:CN:wp
8353 SIERRA AVENUE (P,O. BOX 518) FONTANA, CALIFORNIA 92334-0518 (714) 350-7600
ADDRESS A.P.N.# OWNER AMOUNT
16303 251-232-01 Chester D.& Vickie 65 linear ft of sewer
Hoover facilities appurtenance
16309 251-232-02 Richard J.& Barbara 60 linear ft.
Anderson
16317 251-232-03 Charles L. & Blanch 60 linear ft.
Turner
16325 251-232-04 Charles F. & Vanett 60 linear ft.
Palmer
16333 251-232-05 same as 251-232-01 65 linear ft.
16373 251-232-06 John T. & Patricia 65 linear ft.
K. Morrow
16381 251-232-07 Steve L. & Sandra 60 linear ft.
L.~ Hansen
16389 251-232-08 Eddie Lujan 60 linear ft.
16397 251-232-09 Daniel C. & Juanita 60 linear ft.
Rosas
16407 251-232-10 Rose B. & Larry J. 60 linear ft.
Clark
16415 251-232-11 Robert Ozaeta 60 linear ft.
16433 Aliso Dr.
16423 251-232-12 ~Paul & Shelly Ward 65 linear ft.
16463 251-232-13 Stephen B. & Lea M. 65 linear ft.
Johnson
16471 251-232-14 Luis A. & Evangelina~60 linear ft.
V. Vega ~
16479 251-232-15 Barbara S. & Michael160 linear ft.
F. Sgambati, Sr. ~
16487 251-232-16 Dolres & Raymond ~60 linear ft.
Valenzuela ~
2 of 4
ADDRESS A.P.N.# OWNER AMOUNT
16495 251-232-17 A Aull 65 linear ft.
16304 251-231-09 Kenneth W. &Kathleen~65 linear ft.
Heasley
16310 251-231-10 Ralph E. & Gall Van 60 linear ft.
Tine
16318 251-231-11 Tom R. & Peggy L. 60 linear ft.
Van Norman
16326 251-231-12 James F. & Judy D. 60 linear ft.
Payne
9784 Tangelo
Bloomington, Ca.
92316
16334 251-231-13 IRaymond Ingold 55.71 linear ft.
~11050 Bryant St.
~Space 63, Yucaipe
Ca. 92399
16342 251-231-14 Janice & George Teal~81.40 linear ft.
Jr.
16350 251-231-15 Armando A. Camacho 81.40 linear ft.
16358 251-231-16 Rhonald G. & Thelma ~
~B. Wallace t
16366 251-231-17 Bertha M. Andrade 60 linear ft.
16374 251-231-18 Charles B. Clara A. 60 linear ft.
~Lopez
16382 251-231-19 ~Rudolpho Sandoval 60 linear ft.
16390 251-231-20 ~Jame A. Sweeney 60 linear ft.
16398 251-231-21 Gary J. & Pamela M. 60 linear ft.
Hengeveld
166020 Manzanita Ct.~
16408 251-231-22 Vada L. Mannion 160 linear ft.
16416 251-231-23 Rodolofo & Eloisa ~60 linear ft.
Sanchez ~
3 of 4
ADDRESS A.P.N.# OWNER ~ AMOUNT
16424 251-231-2~ Daniel S. & Redona L. 160 linear ft.
Rice 105 W. Virginia~
Apt. D. Rialto Ca. ~
92376 ~
16432 251-231-25 Juan Estrada & Rosa~60 linear ft.
Razon ~
16440 251-231-26 ~Margaret Egan 141.66 linear ft.
16448 251-231-27 Paul P. & Gladys A.~90.70 linearft.
Sitompul 619 Norwood8
Ct. San Dimas Ca.
91773
16456 251-231-28 Ronald & Sharon A. 90.70 linear ft.
Stillwell
16464 251-231-29 Cynthia Jamersom 48.45 linear ft.
16472 251-231-30 Grace P Keever 60 linear ft.
16480 251-231-31 Charles L. & Bernice~60 linear ft.
P. Westbrook
16488 251-231-32 Millie J. Kondus 60 linear ft.
16496 251-231-33 ~Guy R.& Joyce A. 65 linear ft.
MCentanni
4of4
MARCH. 24, ~.~9
CHAPTER 27
PUBLIC WORKS DEPT.
CITY OF FONTANA
BY: C. NAVARRO
EL MOLINO COURT SEWER PROJECT ESTIMATE
8 " V.C.P. 1400 L.FL @ 35.00/L.F. = $49,000.00
4" V.C.P. 1182 L.F. @ 18.00/L.F. = 21,276.00
3 MANHOLES @ 1700.00 EACH = 5,100.00
285 TON A.Co MATH-IN @ 65.00/TON = 18,525.00
SUB-TOTAL $ 93,901.00
ENGINEERING AND STAKING 17.5% =$ 16,432.00
TOTAL $110,333.00
35 LOTS IN PROJECT:
TOTAL ESTIMATED COST FOR LATEHAL CONSTRUCTION = $2t,276.00
ESTIMATE OF COST TO PROPERTY OWNER = $625.76
ESTIMATE OF PROJECT COST =$110,333.00
MINUS LATERAL COST - 21,276.00
$89,057.00
CITIES SHARE OF COST = 25% - 22,264.25
plus corner lots four 265 L.F. @ 35/L.F. = - 9,275.00
plus two side yards 206 L.F> @ 35/L.F.= - 7,210.00
$50,307.25
TOTAL FRONTAGE ON PROJECT = 2549.05 L.F.
ESTIMATED PROJECT COST TO EACH PROPERTY OWNER
(THIS IS BASED ON A 60 L.F. FRONTAGE LOT)
$ 1,184.14 each (MAIN LINE CONSTRUCTION COST,50,307.25/2549.05
$ 635.14 each ( 4" SEWER LATERAL CONSTRUCTION COST)
$1,819.28 ESTIMATED PROJECT COST PER HOMEOWNER
(plus connection charge and permits)
We would normally place a 1" overlay over the total street with capital
improvement funds. On this project we well just repair trenches and place on a
future overlay list. 1 of 4