GENERAL NOTES FOR STREET IMPROVEMENT PLANS
ALL WORK SHALL BE IN ACCORDANCE WITH THESE PLANS, THE CITY OF FONTANA STANDARD PLANS, THE CONTRACT PROVISIONS AND THE STANDARD SPECIFICATIONS
FOR PUBLIC WORKS CONSTRUCTION ("GREEN BOOK"). ALL REFERENCE SPECIFICATIONS AND STANDARDS SHALL BE THE LATEST EDITION UNLESS OTHERWISE NOTED.
WHEN A TECHNICAL CONFLICT IS FOUND TO EXIST IN THE CONTRACT DOCUMENTS THAT CAN NOT BE RESOLVED BY REFERENCE TO PRECEDENCE PROVISIONS IN THE
"GREEN BOOK", THE CONTRACTOR SHALL IMMEDIATELY REPORT SAID CONFLICT TO THE CITY ENGINEER FOR RESOLUTION.
ALL MATERIALS AND METHODS ARE SUBJECT TO THE APPROVAL OF THE CITY ENGINEER.
CONSTRUCTION PERMITS SHALL BE OBTAINED FROM THE CITY OF FONTANA COMMUNITY DEVELOPMENT DEPARTMENT, ENGINEERING DIVISION PRIOR TO THE
START OF ANY WORK. INSPECTION COORDINATION SHALL BE REQUESTED AT LEAST TWO WORKING DAYS PRIOR TO THE START OF ANY WORK IN PUBLIC
RIGHT-OF-WAY WITHIN THE CITY LIMITS. CALL (909) 350-7610.
THE CONTRACTOR SHALL CONFORM TO ALL TRAFFIC CONTROL POLICIES, METHODS AND PROCEDURES DESCRIBED IN THE STATE OF CALIFORNIA MANUAL OF
TRAFFIC CONTROLS, LATEST NON -METRIC EDITION UNLESS OTHERWISE DIRECTED BY THE CITY TRAFFIC ENGINEER.
IT SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR TO MAINTAIN BARRICADES, DELINEATORS OR OTHER TRAFFIC CONTROL DEVICES AT ALL TIMES.
THE CONTRACTOR SHALL OBTAIN A PERMIT TO PERFORM EXCAVATION OR TRENCH WORK FOR TRENCHES 5 FEET OR GREATER IN DEPTH FROM THE CALIFORNIA STATE
DIVISION OF INDUSTRIAL SAFETY.
THE WALLS AND FACES OF ALL EXCAVATIONS GREATER THAN FIVE (5) FEET IN DEPTH SHALL BE GUARDED BY SHORING, SLOPING OF THE GROUND OR OTHER APPROVED
MEANS PURSUANT TO THE REQUIREMENTS OF THE DIVISION OF INDUSTRIAL SAFETY OF THE STATE OF CALIFORNIA. TRENCHES LESS THAN FIVE (5) FEET SHALL ALSO BE
GUARDED WHEN THE POTENTIAL EXISTS FOR GROUND MOVEMENT.
NO MATERIAL OR EQUIPMENT SHALL BE STORED IN THE PUBLIC RIGHT OF WAY WITHOUT OBTAINING PERMISSION FROM ENGINEER.
THE LOCATIONS OF UTILITIES SHOWN HAVE BEEN DETERMINED FROM AVAILABLE INFORMATION, HOWEVER, IT SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR TO
DETERMINE, IN THE FIELD, THE TRUE LOCATION AND ELEVATION OF ANY EXISTING UTILITIES, AND TO EXERCISE PROPER PRECAUTION TO AVOID DAMAGE THERETO. THE
CONTRACTOR SHALL CONTACT UNDERGROUND SERVICE ALERT AT 1-800-227-2600 TWO WORKING DAYS BEFORE EXCAVATION.
THE CONTRACTOR SHALL COORDINATE CONSTRUCTION WITH ALL UTILITY COMPANIES INCLUDING, BUT NOT LIMITED TO, GAS, TELEPHONE, ELECTRIC, CABLE TELEVISION,
LANDSCAPING, LANDSCAPE IRRIGATION, DOMESTIC WATER, RECLAIMED WATER, SEWER, STORM DRAIN, FLOOD CONTROL AND CALTRANS. ALL UTILITY COMPANIES SHALL BE
GIVEN TWO WORKING DAYS NOTICE PRIOR TO WORK AROUND THEIR FACILITIES.
THE CONTRACTOR SHALL NOT OPERATE ANY FIRE HYDRANT OR WATER MAIN VALVES WITHOUT APPROPRIATE AGENCY AUTHORIZATION. CONTRACTOR SHALL COORDINATE
WITH THE APPROPRIATE WATER COMPANY FOR VALVE OPERATION AND WATER REQUIREMENTS.
CURVE DATA REFERS TO THE FACE OF CURB.
STATIONING REFERS TO THE CENTERLINE OF STREETS EXCEPT WHERE OTHERWISE NOTED.
ADEQUATE CONSTRUCTION CONTROL STAKES SHALL BE SET BY THE ENGINEER TO ENABLE THE CONTRACTOR TO CONSTRUCT THE WORK TO THE PLAN GRADES. THE
CONTRACTOR SHALL BE RESPONSIBLE FOR THE PRESERVATION OF BENCHMARKS AND CONSTRUCTION CONTROL STAKING DURING CONSTRUCTION.
THE CONTRACTOR SHALL NOT DISTURB EXISTING SURVEY MONUMENTS, MONUMENT TIES OR BENCH MARKS WITHOUT PRIOR NOTIFICATION TO THE CITY ENGINEER.
REMOVAL AND REPLACEMENT OF EXISTING SURVEY CONTROL, INCLUDING SURVEY MONUMENTS, MONUMENT TIES AND BENCH MARKS, SHALL BE DONE BY A REGISTERED
CIVIL ENGINEER OR LICENSED LAND SURVEYOR. SURVEY MONUMENTS THAT WILL BE DESTROYED AS A RESULT OF THIS CONSTRUCTION SHALL BE REPLACED. THE
CONTRACTOR SHALL NOTIFY THE ENGINEER ONE WEEK PRIOR TO CONSTRUCTION SO THAT TIES TO MONUMENTS CAN BE ESTABLISHED FOR LATER REPLACEMENT OF THE
MONUMENT.
THE CONTRACTOR SHALL MAINTAIN ACCESS FOR LOCAL RESIDENTS AND BUSINESSES AT ALL TIMES. A MINIMUM 12 FOOT LANE SHALL BE MAINTAINED AT ALL TIMES IN
THE CONSTRUCTION AREA FOR RESIDENTS AND EMERGENCY VEHICLES.
THE CONTRACTOR SHALL PROVIDE AND MAINTAIN AN EFFECTIVE MEANS OF DUST CONTROL, INCLUDING ADEQUATE WATERING, AT ALL TIMES.
ALL GRADING OPERATIONS SHALL BE DISCONTINUED WHEN SUSTAINED WIND VELOCITIES EXCEED 25 MILES PER HOUR.
THE CONTRACTOR SHALL NOT CAUSE ANY EXCAVATED MATERIAL, MUD, SILT OR DEBRIS TO BE DEPOSITED ONTO PUBLIC OR PRIVATE PROPERTY ADJACENT TO THE RIGHT
OF WAY DURING CONSTRUCTION WITHOUT PRIOR WRITTEN APPROVAL.
NO TRENCH BACKFILL SHALL TAKE PLACE WITHOUT PRIOR APPROVAL OF THE CITY INSPECTOR.
A GEOTECHNICAL ENGINEER SHALL CERTIFY ALL BACKFILL COMPACTION. FAILURE TO OBTAIN THE REQUIRED DENSITY SHALL REQUIRE RE -WORKING OF THAT PORTION OF
THE WORK UNTIL THE SPECIFIED DENSITY IS OBTAINED.
CARE SHOULD BE TAKEN TO PREVENT GRADES, DITCHES, AND SWALES FROM UNDERMINING STREET IMPROVEMENTS. UPON INSPECTION OF THE SITE, THE CITY ENGINEER
MAY REQUIRE TEMPORARY NON-ERODEABLE SWALES ENTERING OR LEAVING IMPROVEMENTS.
THE FINAL LOCATION AND WIDTH OF DRIVEWAY APPROACH APRONS SHALL BE APPROVED AT THE TIME OF CONSTRUCTION AND SHALL CONFORM TO THE CITY OF
FONTANA STANDARD DETAILS.
ALL EXPOSED CONCRETE SURFACES SHALL CONFORM IN GRADE, COLOR AND FINISH TO MATCH EXISTING CONCRETE.
THE SEWER CONTRACTOR SHALL STAMP AN "S" IN THE FACE OF THE CURB AT THE LOCATION OF THE SEWER LATERAL.
NO CONCRETE SHALL BE PLACED UNTIL THE FORMS AND REINFORCING STEEL HAVE BEEN PLACED, INSPECTED AND APPROVED.
ALL UNDERGROUND UTILITIES SHALL BE INSTALLED, TESTED AND APPROVED PRIOR TO PAVING OF STREETS.
APPROVED SOIL STERILANT IS REQUIRED UNDER ALL NEW ASPHALT PAVEMENT PRIOR TO PLACEMENT.
PAVEMENT STRUCTURAL SECTIONS SHOWN ARE MINIMUM AND SUBJECT TO REVISION AND APPROVAL OF THE CITY ENGINEER AS DETERMINED BY SOILS TESTS TAKEN
AFTER COMPLETION OF ROUGH GRADING.
ALL MANHOLES, CLEANOUT FRAMES, COVERS AND VALVE BOXES SHALL BE RAISED TO FINISHED GRADE BY THE PAVING CONTRACTOR UPON COMPLETION OF PAVING.
UPON COMPLETION OF CONSTRUCTION, CONTRACTOR SHALL RESTORE ALL SIGNING, STRIPING, BARRICADES, AND OTHER TRAFFIC CONTROL DEVICES TO THE SATISFACTION
OF THE CITY TRAFFIC ENGINEER.
CONTRACTOR SHALL RELOCATE AND/OR REPLACE LANDSCAPING, SPRINKLERS AND SIDEWALKS AFFECTED BY THE CONSTRUCTION TO THE SATISFACTION OF THE CITY
ENGINEER.
AS -BUILT DRAWINGS SHALL BE PROVIDED BY THE CONTRACTOR TO THE ENGINEER OF RECORD, WHO SHALL PROVIDE RECORD DRAWINGS TO THE CITY ENGINEER.
BEST MANAGEMENT PRACTICES FOR CONSTRUCTION ACTIVITIES (SWPPP)
a) ERODED SEDIMENTS AND OTHER POLLUTANTS MUST BE RETAINED ON SITE AND MAY NOT BE TRANSPORTED FROM THE SITE VIA SWALES, AREA DRAIN OR
NATURAL DRAINAGE COURSES.
b) STOCKPILES OF EARTH AND OTHER CONSTRUCTION RELATED MATERIALS MUST BE PROTECTED FROM BEING TRANSPORTED FROM THE SITE BY THE FORCES
OF WIND OR WATER.
c) FUELS, OILS, SOLVENTS AND OTHER TOXIC MATERIAL MUST BE STORED IN ACCORDANCE WITH THEIR LISTING AND ARE NOT TO CONTAMINATE THE SOIL AND
SURFACE WATERS, ALL APPROVED STORAGE CONTAINERS ARE TO BE PROTECTED FROM WEATHER, SPILLS MUST BE CLEANED UP IMMEDIATELY AND DISPOSED
OF IN A PROPER MANNER. SPILLS MAY NOT BE WASHED INTO THE DRAINAGE SYSTEM.
d) EXCESS OR WASTE CONCRETE MAY NOT BE WASHED IN THE PUBLIC RIGHT OF WAY OR ANY OTHER DRAINAGE SYSTEM. PROVISIONS SHALL BE MADE TO DRAIN
CONCRETE WASTES ON SITE UNTIL THEY CAN BE DISPOSED OF AS SOLID WASTE.
e) TRASH AND CONSTRUCTION RELATED DEBRIS MUST BE DEPOSITED INTO COVERED RECEPTACLE TO PREVENT CONTAMINATION OF RAINWATER AND DISPERSAL BY WIND.
f) DEPOSITION OF SEDIMENTS, SOILS OR OTHER MATERIAL BY VEHICULAR TRAFFIC LEAVING THE PROJECT SITE MUST NOT BE ALLOWED. THE CONSTRUCTION ENTRANCE
ROADWAYS MUST BE STABILIZED SO AS TO INHIBIT SEDIMENTS FROM BEING DEPOSITED INTO THE PUBLIC RIGHT OF WAY, ACCIDENTAL OR BY OTHER MEANS.
g) ANY SLOPE WITH DISTURBED SOILS OR DENUDED OF VEGETATION MUST BE STABILIZED SO AS TO INHIBIT EROSION BY WIND AND WATER.
h) ALL REQUIREMENTS PER CALTRANS GENERAL NOTES NO. 16 ON SHEET 2.
NATIONAL POLLUTANT DISCHARGE EUMINA11ON SYSTEM (NPDES)
a) UNLESS NOTED OTHERWISE, ALL EXISTING SITE IMPROVEMENTS SHALL BE PROTECTED IN PLACE.
b) ALL EXISTING CONDITIONS ARE TO BE VERIFIED AT THE SITE PRIOR TO BIDDING.
c) CLEAN UP OF WORK AND SUPERVISION IS PART OF THE PROJECT.
d) CONSTRUCTION ACTIVITIES OF ONE ACRE OR MORE SHALL REQUIRE A GENERAL CONSTRUCTION STORM WATER PERMIT. FOR MORE INFORMATION, YOU MAY CALL
THE STATE WATER RESOURCES CONTROL BOARD - DIVISION OF WATER QUALITY AT (916) 657-1146.
ACTUAL THICKNESS OF A.C. PAVEMENT AND/OR BASE COURSE MATERIAL FOR STRUCTURAL STREET SECTIONS SHALL BE RECOMMENDED BY A GEOTECHNICAL REPORT AND
SUBMITTED TO THE CITY OF FONTANA FOR APPROVAL UPON COMPLETION OF ROUGH GRADING.
tAp 112. .
.12�'���
civ`�'
d►,, s� �.- 2
ATE OF 01 °rig
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
GENERAL NOTES FOR STORM DRAIN IMPROVEMENT PLANS
ALL WORK SHALL BE IN ACCORDANCE WITH THESE PLANS, THE CITY OF FONTANA STANDARD PLANS,
17.
REMOVAL AND REPLACEMENT OF EXISTING SURVEY CONTROL, INCLUDING SURVEY MONUMENTS, MONUMENT
THE CONTRACT PROVISIONS AND THE STANDARD SPECIFICATIONS FOR PUBLIC WORKS
CONSTRUCTION ("GREEN BOOK"). ALL REFERENCE SPECIFICATIONS AND STANDARDS SHALL BE THE
TIES AND BENCH MARKS, SHALL BE DONE BY A REGISTERED CIVIL ENGINEER OR LICENSED LAND SURVEYOR.
CONSTRUC11ON ("GREEN BOOK"). ALL REFERENCE SPECIFICATIONS AND STANDARDS SHALL BE THE
18.
SURVEY MONUMENTS THAT WILL BE DESTROYED AS A RESULT OF THIS CONSTRUC11ON SHALL BE REPLACED.
LATEST EDITION UNLESS OTHERWISE NOTED.
RESOLVED BY REFERENCE TO PRECEDENCE PROVISIONS IN THE "GREEN BOOK", THE CONTRACTOR
THE CONTRACTOR SHALL NOTIFY THE ENGINEER ONE WEEK PRIOR TO CONSTRUCTION SO THAT TIES TO
SHALL IMMEDIATELY REPORT SAID CONFLICT TO THE CITY ENGINEER FOR RESOLUTION.
MONUMENTS CAN BE ESTABLISHED FOR LATER REPLACEMENT OF THE MONUMENT.
WHEN A TECHNICAL CONFLICT IS FOUND TO EXIST IN THE CONTRACT DOCUMENTS THAT CAN NOT BE
"GREEN
18.
THE CONTRACTOR SHALL MAINTAIN ACCESS FOR LOCAL RESIDENTS AND BUSINESSES AT ALL TIMES. A MINIMUM
RESOLVED BY REFERENCE TO PRECEDENCE PROVISIONS IN THE BOOK", THE CONTRACTOR
12 FOOT LANE SHALL BE MAINTAINED AT ALL TIMES IN THE CONSTRUCTION AREA FOR RESIDENTS AND
SHALL IMMEDIATELY REPORT SAID CONFLICT TO THE CITY ENGINEER FOR RESOLUTION.
START OF ANY WORK IN PUBLIC RIGHT-OF-WAY WITHIN THE CITY LIMITS. CALL (909) 350-7610.
EMERGENCY VEHICLES.
ALL MATERIALS AND METHODS ARE SUBJECT TO THE APPROVAL OF THE CITY ENGINEER.
PROCEDURES DESCRIBED IN THE STATE OF CALIFORNIA MANUAL OF TRAFFIC CONTROLS, LATEST
22.
19.
THE CONTRACTOR SHALL PROVIDE AND MAINTAIN AN EFFECTIVE MEANS OF DUST CONTROL, INCLUDING
ADVANCE CONSTRUCTION SIGNING INDICATING DURATION OF PROJECT SHALL BE IN PLACE ONE WEEK
23.
ADEQUATE WATERING, AT ALL TIMES.
PRIOR TO IMPLEMENTING DETOURS.
THE CONTRACTOR SHALL OBTAIN A PERMIT TO PERFORM EXCAVATION OR TRENCH WORK FOR
24.
TRENCHES 5 FEET OR GREATER IN DEPTH FROM THE CALIFORNIA STATE DIVISION OF INDUSTRIAL
20.
THE CONTRACTOR SHALL NOT CAUSE ANY EXCAVATED MATERIAL, MUD, SILT OR DEBRIS TO BE DEPOSITED
CONSTRUCTION PERMITS SHALL BE OBTr",iltiiED FROM THE CITY OF FONTANA COMMUNITY
THE WALLS AND FACES OF ALL EXCAVATIONS GREATER THAN FIVE (5) FEET IN DEPTH SHALL BE
ONTO PUBLIC OR PRIVATE PROPERTY ADJACENT TO THE RIGHT OF WAY DURING CONSTRUCTION WITHOUT
DEVELOPMENT DEPARTMENT, ENGINEERING DIVISION PRIOR TO THE START OF ANY WORK.
25.
PRIOR WRITTEN APPROVAL.
INSPECTION COORDINATION SHALL BE REQUESTED AT LEAST TWO WORKING DAYS PRIOR TO THE
LESS THAN FIVE (5) FEET SHALL ALSO BE GUARDED 'WHEN THE POTENTIAL EXISTS FOR GROUND
START OF ANY WORK IN PUBLIC RIGHT-OF-WAY WITHIN THE CITY LIMITS. CALL (909) 350-7610.
21.
NO TRENCH BACKFILL SHALL TAKE PLACE WITHOUT PRIOR APPROVAL OF THE CITY INSPECTOR.
22•
A GEOTECHNICAL ENGINEER SHALL CERTIFY ALL BACKFILL COMPACTION. FAILURE TO OBTAIN THE REQUIRED
THE CONTRACTOR SHALL CONFORM TO ALL TRAFFIC CONTROL POLICIES, METHODS AND PROCEDURES
DENSITY SHALL REQUIRE RE -WORKING OF THAT PORTION OF THE WORK UNTIL THE SPECIFIED DENSITY IS
DESCRIBED IN THE STATE OF CALIFORNIA MANUAL OF TRAFFIC CONTROLS, LATEST NON -METRIC EDITION
THE TRUE LOCATION AND ELEVATION OF ANY EXISTING UTILITIES, AND TO EXERCISE PROPER
OBTAINED.
UNLESS OTHERWISE DIRECTED BY THE CITY TRAFFIC ENGINEER.
IT SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR TO MAINTAIN BARRICADES, DELINEATORS OR OTHER
23'
i�at�An��LAC-Ki-rc 110f'% 1 i ic%mr- -p D. lir �7 �r- �`�Tr T� It- �I I rLI�ILIl r-' .. w., .-+rte+. ...-.� -.r-. •r+r+^ • r+..
TRAFFIC CONTROL DEVICES AT ALL TIMES.
THE CONTRACTOR SHALL COORDINATE CONSTRUCTION WITH ALL UTILITY COMPANIES INCLUDING,
'
THE CONTRACTOR SHALL OBTAIN A PERMIT TO PERFORM EXCAVATION OR TRENCH WORK FOR TRENCHES
24.
ALL EXPOSED CONCRETE SURFACES SHALL CONFORM IN GRADE, COLOR AND FINISH TO MATCH EXISTING
5 FEET OR GREATER IN DEPTH FROM THE CALIFORNIA STATE DIVISION OF INDUSTRIAL SAFETY.
CALTRANS. ALL UTILITY COMPANIES SHALL BE GIVEN TWO WORKING DAYS NOTICE PRIOR TO WORK
CONCRETE.
THE WALLS AND FACES OF ALL EXCAVATIONS GREATER THAN FIVE (5) FEET IN DEPTH SHALL BE GUARDED BY
25.
NO OPEN TRENCH SHALL BE ALLOWED AT THE END OF THE DAY WITHOUT PRIOR APPROVAL OF THE CITY
SHORING, SLOPING OF THE GROUND OR OTHER APPROVED MEANS PURSUANT TO THE REQUIREMENTS OF THE
APPROPRIATE AGENCY AUTHORIZATION. CONTRACTOR SHALL COORDINATE WITH THE APPROPRIATE
ENGINEER.
DIVISION IF INDUSTRIAL SAFETY OF THE STATE OF CALIFORNIA . TRENCHES LESS THAN FIVE (5) FEET SHALL
26.
PRIOR TO CONSTRUCTION, THE CONTRACTOR SHALL EXPOSE EXISTING FACILITIES, AND VERIFY ELEVATION
ALSO BE GUARDED WHEN THE POTENTIAL EXISTS FOR GROUND MOVEMENT.
ADEQUATE CONSTRUCTION CONTROL STAKES SHALL BE SET BY THE ENGINEER TO ENABLE THE
AND LOCATION OF CONNECTIONS. CITY APPROVAL OF CONNECTIONS TO EXISTING FACILITIES DOES NOT IMPLY
NO MATERIAL OR EQUIPMENT SHALL BE STORED IN THE PUBLIC RIGHT OF WAY WITHOUT OBTAINING A SEPERATE
CORRECTNESS OF ELEVATIONS OR LOCATIONS SHOWN ON THE PLANS.
PERMIT FOR THAT PURPOSE.
27.
IF EXISTING UTILITIES OR ANY OTHER FACILITIES CONFLICT NTH THE PROPOSED IMPROVEMENTS, THE
THE LOCATIONS OF UTILITIES SHOWN HAVE BEEN DETERMINED FROM AVAILABLE INFORMATION, HOWEVER, IT
35.
CONTRACTOR SHALL NOTIFY THE ENGINEER AND ALL AFFECTED AGENCIES IMMEDIATELY.
SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR TO DETERMINE, IN THE FIELD, THE TRUE LOCATION AND
28.
NO CONCRETE SHALL BE PLACED UN11L THE FORMS AND REINFORCING STEEL HAVE BEEN PLACED, INSPECTED
ELEVATION OF ANY EXISTING UTILITIES, AND TO EXERCISE PROPER PRECAUTION TO AVOID DAMAGE THERETO.
37
LICENSED TO PERFORM SURVEYING. SURVEY MONUMENTS THAT WILL BE DESTROYED AS A RESULT
THE CONTRACTOR SHALL CONTACT UNDERGROUND SERVICE ALERT AT 1-800-227-2600 TWO WORKING DAYS
OF THIS CONSTRUCTION SHALL BE REPLACED. THE CONTRACTOR SHALL NOTIFY THE ENGINEER
AND APPROVED.
BEFORE EXCAVATION.
29.
ALL UNDERGROUND UTILITIES SHALL BE INSTALLED, TESTED AND APPROVED PRIOR TO PAVING OF STREETS.
THE CONTRACTOR SHALL COORDINATE CONSTRUCTION WITH ALL UTILITY COMPANIES INCLUDING, BUT NOT
30.
APPROVED SOIL STERILANT IS REQUIRED UNDER ALL NEW ASPHALT PAVEMENT PRIOR TO PLACMENT.
LIMITED TO, GAS, TELEPHONE, ELECTRIC, CABLE TELEVISION, LANDSCAPING, LANDSCAPE IRRIGATION,
31.
ALL MANHOLES, CLEANOUT FRAMES, COVERS AND VALVE BOXES SHALL BE RAISED TO FINISHED GRADE BY THE
DOMESTIC WATER, RECLAIMED WATER, SEWER, STORM DRAIN, FLOOD CONTROL, AND CALTRANS. ALL
PAVING CONTRACTOR UPON COMPLETION OF PAVING.
UTILITY COMPANIES SHALL BE GIVEN TWO WORKING DAYS NOTICE PRIOR TO WORK AROUND THEIR FACILITIES.
32.
UPON COMPLETION OF CONSTRUCTION, CONTRACTOR SHALL RESTORE ALL SIGNING, STRIPING, BARRICADES,
THE CONTRACTOR SHALL NOT OPERATE ANY FIRE HYDRANT OR WATER MAIN VALVES WITHOUT APPROPRIATE
AND OTHER TRAFFIC CONTROL DEVICES TO THE SATISFACTION OF THE CITY TRAFFIC ENGINEER.
AGENCY AUTHORIZATION. CONTRACTOR SHALL COORDINATE WITH THE APPROPRIATE WATER COMPANY FOR
VALVE OPERATION AND WATER REQUIREMENTS.
33.
AS -BUILT DRAWINGS SHALL BE PROVIDED BY THE CONTRACTOR TO THE ENGINEER OF RECORD, WHO SHALL
STATIONING REFERS TO THE CENTERLINE OF STORM DRAIN EXCEPT WHERE OTHERWISE NOTED.
PROVIDE RECORD DRAWINGS TO THE CITY ENGINEER.
ADEQUATE CONSTRUCTION CONTROL STAKES SHALL BE SET BY THE ENGINEER TO ENABLE THE CONTRACTOR
34.
MINIMUM D -LOAD FOR ALL RCP IS 1350.
TO CONSTRUCT THE WORK TO THE PLAN GRADES. THE CONTRACTOR SHALL BE RESPONSIBLE FOR THE
35.
PRECAST RCB SHALL BE PER THE LATEST REVISION OF ASTM C1433, TABLE 1 HS20 HIGHWAY LOADING
PRESERVATION OF BENCHMARKS AND CONSTRUCTION CONTROL STAKING DURING CONSTRUCTION.
(OR IF YOU PREFER TABLE 2 INTERSTATE LOADING) FOR DEPTH OF COVER AS SHOWN ON PLANS. THE
THE CONTRACTOR SHALL NOT DISTURB EXISTING SURVEY MONUMENTS, MONUMENT TIES OR BENCH MARKS
PRECAST RCB MAY BE MANUFACTURED USING THE DRYCAST MANUFACTURED USINTG THE DRYCAST
WITHOUT PRIOR NOTIFICATION TO THE CITY ENGINEER.
MANUFACTURING PROCEDURE WITH ZERO SLUMP CONCRETE. JOINTS SHALL BE SEALED BY GROUTING THE
INSIDE INVERT OF THE RCB JOINTS TO THE SPRINGLINE USING A 2 PART SAND 1 PART CEMENT GROUT
MIXTURE, AND/OR JOINTS SHALL BE SEALED USING A BITUMIN FLEXIBLE GASKET MATERIAL PER ASTM
C990 OR AASHTO M198.
GENERAL NOTES FOR SEWER IMPROVEMENT PLANS
ALL WORK SHALL BE IN ACCORDANCE WITH THESE PLANS, THE CITY OF FONTANA STANDARD PLANS,
17.
THE CONTRACT PROVISIONS AND THE STANDARD SPECIFICATIONS FOR PUBLIC WORKS
CONSTRUCTION ("GREEN BOOK"). ALL REFERENCE SPECIFICATIONS AND STANDARDS SHALL BE THE
LATEST EDITION UNLESS OTHERWISE NOTED.
18.
WHEN A TECHNICAL CONFLICT IS FOUND TO EXIST IN THE CONTRACT DOCUMENTS THAT CAN NOT BE
RESOLVED BY REFERENCE TO PRECEDENCE PROVISIONS IN THE "GREEN BOOK", THE CONTRACTOR
19.
SHALL IMMEDIATELY REPORT SAID CONFLICT TO THE CITY ENGINEER FOR RESOLUTION.
ALL MATERIALS AND METHODS ARE SUBJECT TO THE APPROVAL OF THE CITY ENGINEER.
CONSTRUCTION PERMITS SHALL BE OBTAINED FROM THE CITY OF FONTANA COMMUNITY
20.
DEVELOPMENT DEPARTMENT, ENGINEERING DIVISION PRIOR TO THE START OF ANY WORK.
INSPECTION COORDINATION SHALL BE REQUESTED AT LEAST TWO WORKING DAYS PRIOR TO THE
21.
START OF ANY WORK IN PUBLIC RIGHT-OF-WAY WITHIN THE CITY LIMITS. CALL (909) 350-7610.
THE CONTRACTOR SHALL CONFORM TO ALL TRAFFIC CONTROL POLICIES, METHODS AND
PROCEDURES DESCRIBED IN THE STATE OF CALIFORNIA MANUAL OF TRAFFIC CONTROLS, LATEST
22.
NON -METRIC EDITION UNLESS OTHERWISE DIRECTED BY THE CITY TRAFFIC ENGINEER.
IT SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR TO MAINTAIN BARRICADES, DELINEATORS
23.
OR OTHER TRAFFIC CONTROL DEVICES AT ALL TIMES.
THE CONTRACTOR SHALL OBTAIN A PERMIT TO PERFORM EXCAVATION OR TRENCH WORK FOR
24.
TRENCHES 5 FEET OR GREATER IN DEPTH FROM THE CALIFORNIA STATE DIVISION OF INDUSTRIAL
SAFETY.
THE WALLS AND FACES OF ALL EXCAVATIONS GREATER THAN FIVE (5) FEET IN DEPTH SHALL BE
GUARDED- BY SHORING, SLOPING OF THE GROUND OR OTHER APPROVED MEANS PURSUANT TO THE
25.
REQUIREMENTS OF THE DIVISION OF INDUSTRIAL SAFETY OF THE STATE OF CALIFORNIA. TRENCHES
LESS THAN FIVE (5) FEET SHALL ALSO BE GUARDED 'WHEN THE POTENTIAL EXISTS FOR GROUND
MOVEMENT.
26.
NO MATERIAL OR EQUIPMENT SHALL BE STORED IN THE PUBLIC RIGHT OF WAY WITHOUT
OBTAINING A SEPARATE PERMIT FOR THAT PURPOSE.
27.
THE LOCATIONS OF UTILITIES SHOWN HAVE BEEN DETERMINED FROM AVAILABLE INFORMATION,
HOWEVER, IT SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR TO DETERMINE, IN THE FIELD,
28.
THE TRUE LOCATION AND ELEVATION OF ANY EXISTING UTILITIES, AND TO EXERCISE PROPER
PRECAUTION TO AVOID DAMAGE THERETO. THE CONTRACTOR SHALL CONTACT UNDERGROUND
SERVICE ALERT AT 1-800-227-2600 TWO WORKING DAYS BEFORE EXCAVATION.
29.
THE CONTRACTOR SHALL COORDINATE CONSTRUCTION WITH ALL UTILITY COMPANIES INCLUDING,
BUT NOT LIMITED TO, GAS, TELEPHONE, ELECTRIC, CABLE TELEVISION, LANDSCAPING, LANDSCAPE
IRRIGATION, DOMESTIC WATER, RECLAIMED WATER, SEWER, STORM DRAIN, FLOOD CONTROL AND
30.
CALTRANS. ALL UTILITY COMPANIES SHALL BE GIVEN TWO WORKING DAYS NOTICE PRIOR TO WORK
AROUND THEIR FACILITIES.
THE CONTRACTOR SHALL NOT OPERATE ANY FIRE HYDRANT OR WATER MAIN VALVES WITHOUT
31.
APPROPRIATE AGENCY AUTHORIZATION. CONTRACTOR SHALL COORDINATE WITH THE APPROPRIATE
WATER COMPANY FOR VALVE OPERATION AND WATER REQUIREMENTS.
32.
STATIONING REFERS TO THE CENTERLINE OF SEWER EXCEPT WHERE OTHERWISE NOTED.
ADEQUATE CONSTRUCTION CONTROL STAKES SHALL BE SET BY THE ENGINEER TO ENABLE THE
33.
CONTRACTOR TO CONSTRUCT THE WORK TO THE PLAN GRADES. THE CONTRACTOR SHALL BE
RESPONSIBLE FOR THE PRESERVATION OF BENCHMARKS AND CONSTRUCTION CONTROL STAKING
34.
DURING CONSTRUCTION.
THE CONTRACTOR SHALL NOT DISTURB EXISTING SURVEY MONUMENTS, MONUMENT TIES OR BENCH
35.
MARKS WITHOUT PRIOR NOTIFICATION TO THE CITY ENGINEER.
36.
REMOVAL AND REPLACEMENT OF EXISTING SURVEY CONTROL, INCLUDING SURVEY MONUMENTS,
MONUMENT TIES AND BENCH MARKS, SHALL BE DONE BY A REGISTERED CIVIL ENGINEER
37
LICENSED TO PERFORM SURVEYING. SURVEY MONUMENTS THAT WILL BE DESTROYED AS A RESULT
OF THIS CONSTRUCTION SHALL BE REPLACED. THE CONTRACTOR SHALL NOTIFY THE ENGINEER
ONE WEEK PRIOR TO CONSTRUCTION SO THAT TIES TO MONUMENTS CAN BE ESTABLISHED FOR LATER
38.
REPLACEMENT OF THE MONUMENT.
THE CONTRACTOR SHALL MAINTAIN ACCESS FOR LOCAL RESIDENTS AND BUSINESSES AT ALL TIMES.
A MINIMUM 12 FOOT LANE SHALL BE MAINTAINED AT ALL TIMES IN THE CONSTRUC11ON AREA FOR
RESIDENTS AND EMERGENCY VEHICLES.
THE CONTRACTOR SHALL PROVIDE AND MAINTAIN AN EFFECTIVE MEANS OF DUST CONTROL,
INCLUDING ADEQUATE WATERING, AT ALL TIMES.
THE CONTRACTOR SHALL NOT CAUSE ANY EXCAVATED MATERIAL, MUD, SILT OR DEBRIS TO BE
DEPOSITED ONTO PUBLIC OR PRIVATE PROPERTY ADJACENT TO THE RIGHT OF WAY DURING
CONSTRUCTION WITHOUT PRIOR WRITTEN APPROVAL.
NO TRENCH BACKFILL SHALL TAKE PLACE WITHOUT PRIOR APPROVAL BY THE CITY INSPECTOR.
A GEOTECHNICAL ENGINEER SHALL CERTIFY ALL BACKFILL COMPACTION. FAILURE TO OBTAIN THE
REQUIRED DENSITY SHALL REQUIRE RE -WORKING OF THAT PORTION OF THE WORK UNTIL THE
SPECIFIED DENSITY IS OBTAINED.
CARE SHOULD BE TAKEN TO PREVENT GRADES, DITCHES, AND SWALES FROM UNDERMINING STREET
IMPROVEMENTS. UPON INSPECTION OF THE SITE, THE CITY ENGINEER MAY REQUIRE TEMPORARY
NON-ERODEABLE SWALES ENTERING OR LEAVING IMPROVEMENTS.
ALL EXPOSED CONCRETE SURFACES SHALL CONFORM IN GRADE, COLOR AND FINISH TO MATCH
EXISTING CONCRETE.
IF SEWER CONSTRUCTION IS TO BE DONE IN PHASES, THE CONTRACTOR SHALL PROVIDE A TERMINAL
CLEANOUT AT THE PHASE BOUNDARY, NOT MORE THAN 150 FEET FROM THE DOWNSTREAM MANHOLE,
SEE CITY OF FONTANA STANDARD DETAIL FOR TERMINAL CLEANOUT.
SANITARY SEWER LINES SHALL BE CONSTRUCTED OF BELL AND SPIGOT OR BAND SEAL TYPE
VITRIFIED CLAY PIPE (V.C.P.) EXTRA STRENGTH CLASS AND SHALL CONFORM TO THE PROVISIONS OF
THE ASTM DESIGNATION C700 FOR V.C.P.
NO OPEN TRENCH SHALL BE ALLOWED AT THE END OF THE DAY WITHOUT PRIOR APPROVAL OF THE
CITY ENGINEER.
SHORT VCP STUBS WITH FLEXIBLE COMPRESSION JOINTS SHALL BE USED AT MANHOLE WALLS TO
ALLOW FOR MINOR DEFLECTIONS IN ALIGNMENT.
PRIOR TO CONSTRUCTION, THE CONTRACTOR SHALL EXPOSE EXISTING FACILITIES, AND VERIFY
ELEVATION AND LOBATION OF CONNECTIONS. CITY APPROVAL OF CONNEC11ONS TO EXISTING
FACILITIES DOES NOT IMPLY CORRECTNESS OF ELEVATIONS OR LOCATIONS SHOWN ON THE PLANS.
ALL 4" HOUSE LATERALS SHALL BE INSTALLED AT A 2% MINIMUM GRADE UNLESS OTHERWISE
APPROVED BY THE CITY ENGINEER.
TERMINATE ALL 4" HOUSE SEWER LATERALS 3 FEET INSIDE THE LOT WITH A PLUG 12" BELOW THE
GROUND SURFACE. WHEN PUBLIC UTILITY EASEMENTS EXIST NEXT TO THE STREET RIGHT OF WAY,
THE LATERAL SHALL TERMINATE 3 FEET INSIDE THE LOT AS MEASURED FROM THE UTILITY EASEMENT.
THE SEWER CONTRACTOR SHALL STAMP AN "S" IN THE FACE OF THE CURB AT THE LOCATION OF
THE SEWER LATERAL.
IF EXISTING UTILITIES OR ANY OTHER FACILITIES CONFLICT WITH THE PROPOSED IMPROVEMENTS,
THE CONTRACTOR SHALL NOTIFY THE ENGINEER AND ALL AFFECTED AGENCIES IMMEDIATELY.
NO CONCRETE SHALL BE PLACED UNTIL THE FORMS AND REINFORCING STEEL HAVE BEEN PLACED,
INSPECTED AND APPROVED.
ALL UNDERGROUND UTILITIES SHALL BE INSTALLED, TESTED AND APPROVED PRIOR TO PAVING OF
STREETS.
APPROVED SOIL STERILANT IS REQUIRED UNDER ALL NEW ASPHALT PAVEMENT PRIOR TO PLACEMENT.
ALL MANHOLES, CLEANOUT FRAMES, COVERS AND VALVE BOXES SHALL BE RAISED TO FINISHED
GRADE BY THE PAVING CONTRACTOR UPON COMPLETION OF PAVING.
UPON COMPLETION OF CONSTRUCTION, CONTRACTOR SHALL RESTORE ALL SIGNING, STRIPING,
BARRICADES, AND OTHER TRAFFIC CONTROL DEVICES TO THE SATISFACTION OF THE CITY TRAFFIC
ENGINEER.
AS -BUILT DRAWINGS SHALL BE PROVIDED BY THE CONTRACTOR TO THE ENGINEER OF RECORD, WHO
SHALL PROVIDE RECORD DRAWINGS TO THE CITY ENGINEER.