HomeMy WebLinkAbout3258-28CONDUCTOR
TYPE
FUNCTION
RUN
t
2
3
4
RG -59/U QUAD SHEILD COAX
CCTV VIDEO
1
1
3PR 24AWG CONDUTOR CABLE
CCTV DATA
1
1
#12
CCTV POWER
2
2
#12
CCTV SERVICE
12-SMFO
DROP CABLE
1
1
CONDUIT SIZE
E
E
2"
E
NOTE: ALL CONDUITS AND CONDUCTORS ARE NEW UNLESS
OTHERWISE SPECIFIED:
(E) EXISTING
CONSTRUCTION NOTES (THIS SHEET ONLY.
�5 FURNISH AND INSTALL ONE (1) 2" (51 mm) HDPE CONDUIT. FURNISH AND
INSTALL 12 -STRAND SMFO CABLE IN NEW CONDUIT. SEE SHEET 33, DETAIL B.
[7]REMOVE EXISTING PULL BOX. FURNISH AND INSTALL NEW PULL BOX NO. 6 WITH
EXTENSION. COIL MINIMUM OF 16 -FEET (4.9 m) OF 12 -STRAND SMFO CABLE
FOR SLACK IN PULL BOX.
10 FURNISH AND INSTALL WALL INTERCONNECT CENTER (WIC) IN EXISTING TRAFFIC
CABINET WITH LINE CONDITIONER/SURGE SUPPRESSOR, IF REQUIRED AS
DIRECTED BY THE ENGINEER. INSTALL AND TERMINATE 12—STRAND SMFO CABLE
USING WIC IN EXISTING CABINET.
12 REMOVE DETECTOR INTERFACE PANEL IN EXISTING TRAFFIC CABINET TO
ACCOMMODATE WIC AS DIRECTED BY ENGINEER.
[1-4] FUSION SPLICE SIX (6) STRANDS OF 96—STRAND SMFO CABLE TO THE
APPROPRIATE STRANDS OF 12 -STRAND SMFO CABLE USING SPLICE ENCLOSURE
PER FIBER ASSIGNMENT SCHEDULE ON SHEET 38. COIL MINIMUM OF 16 -FEET
(4.9 m) OF 12 -STRAND SMFO CABLE FOR SLACK IN SPLICE VAULT.
COORDINATE SPLICING WITH CCTV DETAILS AND AS NOTED IN FIBER
ASSIGNMENT TABLE ON SHEET 38.
[f7] FURNISH AND INSTALL FIBER OPTIC MODEM TO SUPPORT TRAFFIC SIGNAL
CONTROLLER. COMPLETE CONNECTION TO THE EXISTING TRAFFIC SIGNAL
CONTROLLER AND WIC.
[f8] FURNISH AND INSTALL FIBER MULTIPLEXER TO SUPPORT VIDEO DETECTION
SYSTEM. COMPLETE CONNECTION TO THE VIDEO DETECTION UNIT AND WIC.
R3 FURNISH AND INSTALL ONE (1) 2" (51 mm) HDPE CONDUIT. SEE SHEET 33,
DETAIL B.
3� REMOVE EXISTING PULL BOX. FURNISH AND INSTALL NEW PULL BOX N0. 5.
41 FURNISH AND INSTALL DOME CCTV CAMERA SYSTEM, ON EXISTING SIGNAL POLE
USING CCTV MOUNTING EQUIPMENT. SEE SPECIAL PROVISIONS FOR DETAILS.
FOR MOUNTING, USE MANUFACTURER'S MOUNTING STANDARDS.
fl2 FURNSIH AND INSTALL FIBER OPTIC TRANSCEIVER (1) IN EXISTING CABINET WITH
LINE CONDITIONER/SURGE SUPPRESSOR (IF REQUIRED). COMPLETE CONNECTION
TO WIC.
FF� FURNISH AND INSTALL AND TERMINATE CCTV CAMERA DATA CABLE AND COAX
CABLE ON FIBER OPTIC TRANSCEIVER.
F4� FURNISH AND INSTALL NEW SERVICE CABINET PER CITY STANDARDS. FURNISH
AND INSTALL NEW 20 -AMP BREAKER FOR CCTV CAMERA SERVICE AND 20 -AMP
BREAKER FOR TRAFFIC SIGNAL CONTROLLER. CONTRACTOR TO COORDINATE
WITH SCE FOR POWER TO NEW SERVICE CABINET.
GENE
THIS SHEET ONLY):
1. CONTRACTOR SHALL PROVIDE ALL NECESSARY PATCH CORDS WITH APPLICABLE
CONNECTORS (ST, FCPC) AT BOTH ENDS.
2. CONTRACTOR SHALL FIELD VERIFY ELECTRICAL SERVICE LOCATION AND PROVIDE
ALL NECESSARY ACCESSORIES FOR INSTALLING CCTV SERVICE.
3. CONTRACTOR SHALL COORDINATE WORK DONE ON CCTV LOCATION SHEETS WITH
WORK DONE ON COMMUNICATION SHEETS.
4. TO ATTACH CAMERA BRACKET TO POLE, CONTRACTOR SHALL UTILIZE STAINLESS
STEEL STRAP; AS DIRECTED BY ENGINEER.
1 1 /2 0 1 2
3 inches on original drawing
SCALE:1 "= 20'