HomeMy WebLinkAbout2745-2mcm
Protect Specific Notes,
& PAVEMENT REMOVAL
9. CONSTRUCTION SE.QUEMI
General Notes,
1. ALL WORK SHALL BE IN ACCORDANCE WITH THESE PLANS, THE CITY OF
FONTANA STANDARD PLANS, THE CONTRACT PROVISIONS AND THE STANDARD
SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION ("GREEN BOOK"). ALL
REFERENCE SPECIFICATIONS AND STANDARDS SHALL BE THE LATEST EDITION
UNLESS OTHERWISE NOTED.
2. CONSTRUCTION PERMITS SHALL BE OBTAINED FROM THE CiTY OF FONTANA
COMMUNITY DEVELOPMENT DEPARTMENT, ENGINEERING DIVISION PRIOR TO THE
START OF ANY WORK. INSPECTION COORDINATION SHALL BE REQUESTED AT
LEAST TWO WORKING DAYS PRIOR TO THE START OF ANY WORK IN PUBLIC
RIGHT-OF-WAY WITHIN THE CITY LIMITS. CALL (909) 350-7610.
3. THE CONTRACTOR SHALL NOT OPERATE ANY FIRE HYDRANT OR WATER MAIN
VALVES. CONTRACTOR SHALL COORDINATE WITH THE APPROPRIATE WATER
COMPANY FOR VALVE OPERATION AND WATER REQUIREMENTS.
4. STATIONING REFERS TO THE CENTERLINE OF EXCEPT WHERE OTHERWISE
NOTED.
5. ALL UNDERGROUND UTILITIES SHALL BE INSTALLED, TESTED AND APPROVED
PRIOR TO PAVING OF STREETS.
6. THE LOCATIONS OF UTILITIES SHOWN HAVE BEEN DETERMINED FROM AVAILABLE
INFORMATION. HOWEVER, IT SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR
TO DETERMINE, IN THE FIELD, THE TRUE LOCATION AND ELEVATION OF ANY
EXISTING UTILITIES, AND TO EXERCISE PROPER PRECAUTION TO AVOID DAMAGE
THERETO. THE CONTRACTOR SHALL CONTACT UNDERGROUND SERVICE ALERT AT
1-800-227-2600 TWO WORKING DAYS BEFORE EXCAVATION.
7. ALL MANHOLES, CLEANOUT FRAMES, COVERS AND VALVE BOXES SMALL BE
RAISED TO F"SHED GRADE BY THE PAVING CONTRACTOR UPON COMPLETION OF
PAVING.
8. THE CONTRACTOR SHALL COORDINATE CONSTRUCTION WITH ALL UTILITY
COMPANIES INCLUDING, BUT NOT LIMITED TO, GAS, TELEPHONE, ELECTRIC, CABLE
TELEVISION, LANDSCAPING, LANDSCAPE IRRIGATION, DOMESTIC WATER, RECLAIMED
WATER, SEWER, STORM DRAIN, FLOOD CONTROL AND CALTRANS. ALL UTILITY
COMPANIES SHALL BE GIVEN TWO WORKING DAYS NOTICE PRIOR TO WORK AROUND
THEIR FACILITIES.
9. AS -BUILT DRAWINGS SHALL BE PROVIDED BY THE CONTRACTOR TO THE ENGINEER
FOR
RECORD, WMD SHALL PROVIDE RECORD DRAWINGS TO THE CITY ENGINEER.
10. WHEN CONFLICT IS FOUND TO EXIST IN THE CONTRACT DOCUMENTS THAT CAN
NOT BE RESOLVED BY REFERENCE TO PRECEDENCE PROVISIONS IN THE "GREEN
BOOK", THE CONTRACTOR SHALL IMMEDIATELY REPORT SAID CONFLICT TO THE CITY
ENGINEER FOR RESOLUTION.
11. APPROVED SOiL STERILANT IS REQl11RED UNDER ALL NEW PERMANENT ASPHALT
PAVEMENT PRIOR TO PLACEMENT.
12. ALL EXPOSED CONCRETE SURFACES SHALL CONFORM IN GRADE, COLOR AND
FINISH TO MATCH EXISTING CONCRETE.
13. NO CONCRETE SHALL BE PLACED UNTiL THE FORMS AND REINFORCING STEEL
HAVE BEEN PLACED, INSPECTED AND APPROVED.
14. THE WALLS AND FACES OF ALL EXCAVATIONS GREATER THAN FIVE (5) FEET IN
DEPTH SHALL BE GUARDED BY SHORING, SLOPING OF THE GROUND OR OTHER
APPROVED MEANS PURSUANT TO THE REQUIREMENTS OF THE DIVISION OF
INDUSTRIAL SAFETY OF THE STATE OF CALIFORNIA. TRENCHES LESS THAN FIVE (5)
FEET SHALL ALSO BE GUARDED WHEN THE POTENTIAL EXISTS FOR GROUND
MOVEMENT.
15. THE CONTRACTOR SHALL OBTAIN A PERMIT TO PERFORM EXCAVATION OR
TRENCH WORK FOR TRENCHES 5 FEET OR GREATER IN DEPTH FROM THE CALIFORNIA
STATE DIVISION OF INDUSTRIAL SAFETY.
16. NO TRENCH BACKFILL SHALL TAKE PLACE WITHOUT PRIOR APPROVAL OF THE
CITY INSPECTOR.
17. THE CONTRACTOR SHALL NOT CAUSE ANY EXCAVATED MATERIAL, MUD SILT OR
DEBRIS TO BE DEPOSITED ONTO PUBLIC OR PRIVATE PROPERTY ADJACENT TO THE
RIGHT OF WAY DURING CONSTRUCTION WITHOUT PRIOR WRITTEN APPROVAL
18. IT SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR TO MAINTAIN
BARRICADES, DELINEATORS OR OTHER TRAFFIC CONTROL AT ALL TiMES.
19. A GEOTECHNICAL ENGINEER SHALL CERTIFY ALL BACKFILL COMPACTION. FAILURE
TO OBTAIN THE REQUIRED DENSITY SHALL REQUIRE RE -WORKING OF THAT PORTION
OF THE WORK UNTIL THE SPECIFIED DENSITY IS OBTAINED.
20. ALL MATERIALS AND METHODS ARE SUBJECT TO THE APPROVAL OF THE CITY
ENGINEER.
21. ADEQUATE CONSTRUCTION CONTROL STAKES SHALL BE SET BY THE EWRAOt TO
ENABLE THE CONTRACTOR TO CONSTRUCT THE WORK TO PLAN GRADES. THE
CONTRACTOR SHALL BE RESPONSIBLE FOR THE PRESERVATION OF BENCHMARKS AND
CONSTRUCTION CONTROL STAKING DURING CONSTRUCTION.
22. CARE SHOULD BE TAKEN TO PREVENT GRADES, DITCHES, AND SWALES FROM
UNDERMINING STREET IMPROVEMENTS. UPON INSPECTION OF THE SITE, THE CITY
ENGINEER MAY REQUIRE TEMPORARY NON-ERODEABLE SWIALES ENTERING OR
LEAVING IMPROVEMENTS.
23. IF EXISTING UTILITIES OR ANY OTHER FACILITIES CONFLICT WITH THE PROPOSED
IMPROVEMENTS, THE CONTRACTOR SHALL NOTIFY THE ENGINEER AND ALL AFFECTED
AGENCIES IMMEDIATELY.
24. THE CONTRACTOR SHALL NOT DISTURB EXISTING SURVEY MONUMENTS,
MONUMENT TiES OR BENCH MARKS WITHOUT PRIOR NOTIFICATION TO THE CITY
ENGINEER.
25. REMOVAL AND REPLACEMENT OF EXISTING SURVEY CONTROL, INCLUDING SURVEY
MONUMENTS, MONUMENT TiES AND BENCH MARKS, SHALL BE DONE BY A
REGISTERED CIVIL ENGINEER OR LICENSED LAND SURVEYOR. SURVEY MONUMENTS
THAT WILL BE DESTROYED AS A RESULT OF THIS CONSTRUCTION SHALL BE
REPLACED. THE CONTRACTOR SHALL NOTIFY THE ENGINEER ONE WEEK PRIOR TO
CONSTRUCTION SO THAT TiES TO MONUMENTS CAN BE ESTABLISHED FOR LATER
REPLACEMENT OF THE MONUMENT.
26. THE CONTRACTOR SHALL MAINTAIN ACCESS FOR LOCAL RESIDENTS AND
BUSINESSES AT ALL TIMES. A MINIMUM TWELVE FOOT LANE SHALL BE MAINTAINED
AT ALL TiMES IN THE CLOSURE AREA FOR RESIDENTS AND EMERGENCY VEHICLES,
27. NO MATERIAL OR EQUIPMENT SHALL BE STORED IN THE PUBIC RIGHT OF WAY
WITHOUT OBTAINING A SEPARATE PERMIT FOR THAT PURPOSE.
28. SANITARY SEWER LINES SHALL BE CONSTRUCTED OF BELL AND SPIGOT OR BAWD
SEAL TYPE VITRIFIED CLAY PIPE (V.C.P.), EXTRA STRENGTH CLASS AND SHAM
CONFORM TO THE PROVISIONS OF THE ASTM DESIGNATION C700 FOR V. C. P.
29. THE SEWER CONTRACTOR SHALL STAMP AN "S" IN THE FACE OF THE CURB AT
THE LOCATION OF THE SEWER LATERAL
30. IF SEWER CONSTRUCTION IS TO BE DONE IN PHASES, THE CONTRACTOR SHALL
PROVIDE A TERMINAL CLEANOUT AT THE PHASE BOUNDARY, NOT MORE THAN 150
FEET FROM THE DOWNSTREAM MANHOLE. SEE CITY OF FONTANA STANDARD DETAIL
FOR TERMINAL CLEANOUT.
31. ALL HOUSE LATERALS SHALL BE INSTALLED AT A 2% MINIMUM GRADE UNLESS
OTHERWISE APPROVED BY THE CITY ENGINEER.
32. PRIOR TO CONSTRUCTION, THE CONTRACTOR SHALL EXPOSE EXISTING FACIL ITIM
AND VERIFY ELEVATION AND LOCATION OF CONNECTIONS. CITY APPROVAL OF
CONNECTIONS TO EXISTING FACILITIES DOES NOT IMPLY CORRECTNESS OF
ELEVATIONS OR LOCATIONS SHOWN ON THE PLANS.
33. THE CONTRACTOR SHALL PROVIDE AND MAINTAIN AN EFFECTIVE MEANS OF DUST
CONTROL. WCLUDING ADEQUATE WATER04 AT ALL TIMES.
34. SHORT VCP STUBS WITH FLEXIBLE COMPRESSION JOINTS SHALL BE USED AT
MANHOLE WALLS TO ALLOW FOR MINOR DEFLECTIONS IN ALIGNMENT.
35. THE CONTRACTOR SMALL CONFORM TO ALL TRAFFIC CONTROL POLICIES,
METHODS AND PROCEDURES DESCRIBED IN THE "W.A.T.C.H. MANUAL", LATEST EDI110N
UNLESS OTHERWISE DIRECTED BY THE CITY TRAFFIC ENGINEER.
36. UPON COMPLETION OF CONSTRUCTION, CONTRACTOR SHALL RESTORE ALL
SIGNING, STRIPING, BARRICADES, AND OTHER TRAFFIC CONTROL DEVICES TO THE
SATISFACTION OF THE CITY TRAFFIC ENGINEER.
37. NO OPEN TRENCH SMALL BE ALLOWED AT THE END OF THE DAY WITHOUT PRIOR
APPROVAL. OF THE CITY ENGINEER.
SELECT NATIVE -
MATERIAL
90% COMPACTED
PROPOSED VCP
� As
NO crok'"'i�T�,ys
�tGG�Z'ar, •n.�a-a
8' ASPHALT WIDTH
iV1-To = i
PVVMT. SECTION
CRUSHED ROCK
PER GRADATION
SHOWN
Bedding Detail,
N.T.S.
TABLE: 200-1.2(A)
SIEVE SiZE
CITY HAS OBTAINED AN ENCROACHMENT PERMIT FORM THE COUNTY OF SAN
CONTRACTOR SHALL RECYCLE ALL REMOVED ASPHALT CONCRETE PAVEMENT.
A. GENERAL
1 "
BERNARDINO TRANSPORTATION DEPARTMENT (FOR WORK TO BE PERFORMED
CONTRACTOR SHALL FURNISH CITY WRITTEN DOCUMENTATION THAT SAID
90 - 100
1/20
WITHIN COUNTY RIGHT-OF-WAY). CONTRACTOR SHALL PERFORM ALL WORK IN
PAVEMENT HAS BEEN RECYCLED.
1) DURING CONSTRUCTION, ALL EXISTING SEWER FACILITIES (SEWER LINES,
NO.4
ACCORDANCE WITH ALL APPLICABLE PROVISIONS OF SAID PERMIT.
NO. 8
MANHOLES, AND SEWER LATERALS) SHALL BE MAINTAINED IN PLACE AND IN
ASTM C 131
TEST GRADING
B
7. RESTORATION REQUiREMENTS
SERVICE AT ALL TiMES.
CITY WILL NOT ACCEPT THE CONTRACT WORK UN11L CONTRACTOR HAS
SUBMITTED A WRITTEN STATEMENT OF COMPLIANCE ISSUED BY THE COUNTY
CONTRACTOR SHALL PROTECT iN PLACE OR REMOVE AND REPLACE ALL
2) CONTRACTOR SHALL BYPASS WASTEWATER AROUNiD EXISTING MANHOLES
OF SAN BERNARDINO TRANSPORTATION DEPARTMENT (SPECIFICALLY
EXISTING UTILITIES AND PUBLIC AND PRIVATE IMPROVEMENTS INCLUDING, 10UT
PRIOR TO STARTING CONNECTION WORK. IF BYPASSING IS TO BE
REFERENCING RELATIVE COMPACTION AND STREET SURFACE RESTORATION
NOT LIMITED TO, POWER POLES, BERMS, CURBS, GUTTERS, WALKWAYS,
ACCOMPLISHED WITH ENGINE DRIVEN PUMPS, CONTRACTOR SHALL HAVE AN
REQUIREMENTS) ADVISING THAT THE CONTRACTOR HAS COMPLIED WITH ALL
SIDEWALKS, CROSS GUTTERS, SPANDRELS, MEDIANS, DRIVEWAYS, STORM
ADEQUATE SUPPLY OF FUEL AND SUCTION AND DISCHARGE UNE REPAIR
COUNTY REQUIREMENTS AND THAT THE COMPLETED WORK IS ACCEPTABLE.
DRAINS, LANDSCAPING, LANDSCAPING MATERIAL, LANDSCAPE IRRIGATION
CLAMPS AS WELL AS SEPARATE ENGINE DRIVEN PUMP AS A STANDBY.
SYSTEMS, MAIL BOXES, WALLS, AND FENCES. IF SAID FACILITIES ARE
CONTRACTOR SHALL ACQUIRE CiTY OF FONTANA AND SAN BERNARDiNO
DAMAGED OR UNDERMINED AS DETERMINED BY THE CITY, SAID FACILITIES
iF BYPASSiNG iS ACCOMPLiSMED WITH ELECTRIC DRIVEN PUMPS, CONTRACTOR
COUNTY APPROVAL PRIOR TO CLOSURE, INCLUDING FONTANA CITY COUi x
SHALL BE REMOVED AND REPLACED. CONTRACTOR SHALL REMOVE AND
SHALL HAVE STANDBY POWER FACIUTW_S AS WELL AS A SEPARATE ELECTRIC
AND SAN BERNARDINO BOARD OF SUPERVISORS APPROVAL FOR MARYGOLD
REPLACE ANY DAMAGED OR DESTROYED IMPROVEMENTS AS PART OF THE
DRIVEN PUMP AS STANDBY.
AVE. ROAD CLOSURE. CONTRACTOR MALL MAINTAIN TWO LANES OF TRAFFIC
CONTRACT WORK. ALL CURBS, GUTTERS, AND SIDEWALKS TO BE REPLACED
CONTRACTOR SHALL HAVE AT LEAST ONE WORKER ASSIGNED TO OPERATION
AT ALL 11MES DURING CONSTRUCTION FOR ALL OTHER STREETS. CONTRACTOR
SHALL BE COMPLETED WITHIN SEVEN (7) DAYS OF ACCEPTANCE OF THE
OF BYPASS PUMP DURING ALL BYPASS OPERATIONS. BYPASS FACILITIES
SHALL FURNISH TRENCH PROTECTION AS REQUIRED TO CONSTRUCT SEWER
SEWER TESTING.
SHALL BE LOCATED IN MANNER AS TO MINIMIZE THE EFFECT ON TRAFFIC AND
AND MAINTAIN TRAFFIC MOVEMENT.
POTENTIAL FOR SEWAGE SPILL.
DURING REPLACEMENT OF CURB, GUTTER AND SIDEWALK, CONTRACTOR SHALL
2. NOTIFICATIONS
REPLACE COMPLETE PANELS OF SIDEWALK, CONTRACTOR SHALL REPLACE
3) PRiOR TO INSTALLING ANY BYPASS AND PRIOR TO BEGINNING ANY
CURB AND GUTS BETWEEN CONSTRUCTION ,QT'S,.
CONNECTION WORK, CONTRACTOR SHALL REVIEW HIS PROPOSED METHOD AND
IN ADDITION TO NOTIFICATIONS SPECIFIED iN THE CONSTRUCTION
LOCATIONS FOR BYPASSING, INCLUDING EQUIPMENT WITH THE CITY. SAID
UTILITY REQUIREMENTS CONTRACTOR
SPECIFICATIONSGENERAL CONDITIONS )
CONTRACTOR SHALL, AS A MINIMUM, HAVE ACCOMPLISHED BY THE END OF
METHODS AND LOCATIONS SHALL BE APPROVED BY THE CITY PRIOR TO
SHALL NOTIFY RESIDENTS AND COMMERCIAL ESTABLISHMENTS OF IMPENDING
EACH WORK DAY (4:00 P.M.) THE FOLLOWING:
BEGINNING WORK.
WORK. CONTRACTOR SHALL DISTRIBUTE PRINTED NOTICES, PREPARED BY
CONTRACTOR AND APPROVED BY CITY, TO ALL RESIDENTS AND COMMERCIAL
A. PLATE OPEN EXCAVATIONS (30' MAXIMUM LENGTH) AT THE END OF EACH
4) SEQUENCE OF WORK HEREIN SHALL BE FOLLOWED BY CONTRACTOR TO
ESTABLISHMENTS IN THE VICINITY (BOUNDED BY PALMETTO AVE., TO ALDER
WORK PERIOD, TEMPORARY ASPHALT CONCRETE SHALL BE PLACED AROUND
LIMIT THE POSSIBILITY OF SEWAGE SPILLS. SEQUENCE OF WORK IS NOT
AVE., SAN BERNARDINO AVE. AND VALLEY BOULEVARD) OF THE WORK AT
PLATES FOR SMOOTH TRANSITION, AND APPROPRIATE SIGNAGE WATCH
INTENDED TO COVER EVERY SPECIFIC ITEM OF WORK NECESSARY.
INTENDED
SHALL PROVIDE ALL LABOR, EQUIPMENT, AND MATERIALS AND
LEAST SEVEN DAYS IN ADVANCE OF CONSTRUCTION.
MANUAL TYPE P) SHALL BE INSTALLED.
PERFORM ALL WORK NECESSARY TO COMPLETE CONSTRUCTION WITHOUT
SAiD NOTICES SHALL CONTAIN A GENERAL DESCRIPTION OF THE WORK, DATES
B. FILL ALL EXCAVATIONS WITH COMPACTED BACKFILL AND PLACE 2" MINIMUM
SEWAGE SPILLS.
WORK WILL BE PERFORMED, DESCRIPTIONS OF AREAS WHERE TRAVEL AND
TEMPORARY ASPHALT CONCRETE PAVEMENT IN ALL. AREAS WHERE EXISTING
CONTRACTOR SHALL BE RESPONSIBLE FOR ALL COSTS RESULTING FROM
PARKING WILL BE RESTRICTED, AND NAMES OF STREETS WHICH WILL BE
PAVEMENT WAS REMOVED. SAID PAVEMENT SHALL BE COMPACTED, ROLLED
DAMAGE DUE TO SEWAGE SPILLS, INCLUDING BACKUP INTO DWELLINGS AS
CLOSED TO THROUGH TRAFFIC OR WHERE TRAFFIC WILL BE RESTRICTED.
SMOOTH AND FLUSH WITH ADJACENT PAVEMENT SUFFICIENT TO SUPPORT
RESULT OF CONSTRUCTION ACTIVITIES.
TRAFFIC. SAID PAVEMENT MAY BE PLACED COLD PROVIDED IT IS PLACED
CONTRACTOR SHALL NOTIFY COLTON JOiNT UNiFIED SCHOOL DISTRICT (CIM)
SMOOTH AND FLUSH WITH ADJACENT EXISTING PAVEMENT AND ROLLED WITH
5) CONTRACTOR SHALL SCHEDULE HiS WORK SO EACH CONNECTION IS
AT (909) 877-4227 AND OMNITRANS (OMNI) AT (909) 383-5283 PRIOR TO
A STEEL WHEELED PAVEMENT ROLLER, AND PROPERLY MAINTAINED.
COMPLETED WITHIN AN EIGHT-HOUR PERIOD. CONTRACTOR MAY BE REQUN"
BEGINNING CONSTRUCTION. CONTRACTOR SHALL ADVISE CJUSD AND OMNI OF
C. REMOVE ALL DEBRIS, CONSTRUCTION MATERIALS, AND EQUIPMENT FROM
TO CONSTRUCT CONNECTIONS AT NIGHT OR ON WEEKENDS.
IMPENDING CONSTRUCTION AND PROPOSED SCHEDULE. CONTRACTOR SHALL
COORDINATE WITH OMNI RELOCATION OF THE BUS STOP ON THE NORTH SIDE
PUBLIC STREETS, CONSTRUCTION RIGHT-OF-WAY, AND PRIVATE PROPERTY.
i& SEIIIIER CONS7RW11ION SEQUENCE
OF SAN BERNARDINO AVE. NEAR BOXWOOD AVE.
D. CLEAN (INCLUDING SWEEPING AND WASHING) ALL STREETS, DRIVEWAYS,
1) CONTRACTOR SHALL EXCAVATE AND EXPOSE EACH AND EVERY POTENTIAL
ONE MONTH PRIOR 10 B'EGMNNtNG CONSTRUCTION, CONTRACTOR SHALL POST
GUTTERS, SIDEWALKS, AND ALL OTHER WORK AREAS. (CONTRACTOR MAY BE
INTERFERENCE TO DETERMINE THE EXACT LOCATION OF EACH AND EVERY
CONSTRUCTION N0110E SIGNS SPECIFYING DATES WHEN CONSTRUCTION WILL
REQUIRED TO WASH AND/OR SWEEP WORK AREAS MORE THAN ONCE A DAY,
POTENTIAL INTERFERENCE, PRIOR TO BEGINNING SEWER CONSTRUCTOL
BEGIN AND CONTRACTOR'S NAME AND PHONE NUMBER.
IF DIRECTED BY THE CITY).
2) CONTRACTOR SHALL RELOCATE CONFLICTING UTIUTIES.
IF THE CITY OR COUNTY RECEIVES COMPLAINTS FROM INDIVIDUALS AFFECTED
E. PLACE TEMPORARY TRAFFIC STRIPING.
BY CONSTRUCTION, CONTRACTOR SHALL TAKE IMMEDIATE ACTION TO
3) CONTRACTOR SHALL CONSTRUCT SEWER, SEWER EXTENSIONS, SEWER
CORRECT THE SITUATION AS DIRECTED BY THE CITY. IF CONTRACTOR
F. REMOVE ALL TRAFFIC CONTROL AND OPEN ALL STREETS TO TRAFFIC.
LATERALS, AND SEWER MANHOLES CONTINUOUSLY FROM MANHOLE 1 (STATION
RECEIVES COMPLAINTS DIRECTLY, HE SHALL REPORT SAME IMMEDIATELY TO
CONTRACTOR SHALL INSPECT ENTIRE JOB SITE AT LEAST ONCE EACH DAY,
1+57 f) TO MANHOLE 16 (STATION 44+69.64).
THE CITY. THEREAFTER, THE CONTRACTOR SHALL TAKE IMMEDIATE ACTION T4
INCLUDING SATURDAYS, SUNDAYS, AND HOLIDAYS AND CORRECT ANY
CORRECT THE SITUATION AS DIRECTED BY THE CITY.
TRAFFIC, PAVEMENT (TEMPORARY, PERMANENT AND GROUND) OR BACKFILL
DEFICIENCIES. CONTRACTOR SHALL MAINTAIN STREETS INCLUDING BACK FILLED
4) CONTRACTOR SHALL TEST SEWERS, EXTENSiOiM AND LATERALS.
3. UTILITIES
TRENCHES IN GOOD REPAIR.
5) CONTRACTOR SHALL COMPLETE CONNEC7M CONSTRUCTION AT MANHOLE
IF BASED ON CONTRACTOR'S FIELD MEASUREMENTS, EXISTING WATER AND/OR
CONTRACTOR SHALL RESPOND IMMEDIATELY TO ALL REQUESTS BY THE CITY
NO. 1, PER DETAIL 'A', SHEET 3. CONTRACTOR SHALL BYPASS WASTEWATER
GAS FACILITIES CONFLICT WITH PROPOSED SEWER, CONTRACTOR SHALL
FOR REMEDIAL WORK. CONTRACTOR SHALL, AT ALL TiMES (INCLUDING
FLOW AS REQUIRED.
COORDINATE WATER AND GAS RELOCATIONS. CONTRACTOR SHALL PROVIDE
WEEKENDS AND HOLIDAYS), HAVE A CREW AVAILABLE TO RESPOND TO SAID
6) CONTRACTOR SHALL CONNECT EXISTING SEWER LATERALS TO NEW
ALL ASSISTANCE REQUIRED BY FONTANA WATER COMPANY (FWC) AND
REQUESTS.
SOUTHERN CALIFORNIA GAS COMPANY (SCGC), COMPLETE ALL REQUIRED
LATERALS. 7) CONTRACTOR SHALL CONSTRUCT CONNECTION TO EXISTING
'B ',
APPLICATIONS, ALLOW FWC AND SCGC FORCES SUFFICIENT TiME TO COMPLETE
8. PERMANENT ASPHALT CONCRETE PAVEMENT
SYSTEM PER DETAIL SHEET 7.
FACILITY RELOCATIONS, AND PAY ALL REQUIRED FWC AND SCGC FEES, ALL
8) CONTRACTOR SMALL CONSTRUCT CONNECTION TO EOQS7M SYSTEM AT
AT NO ADDITIONAL COST TO THE CITY.
PAVEMENT REPLACEMENT SHALL INCLUDE TRENCH PAVEMENT (SEWER,
EXTENSIONS AND LATERALS) AND ANY ADJACENT DAMAGED PAVEMENT.
MANHOLE NO. 17 PER DETAIL 'C', SHEET 7.
4. ADDITIONAL BACK XL TS
PERMANENT ASPHALT CONCRETE PAVEMENT SHALL BE FURNISHED AND
INSTALLED IN ACCORDANCE WITH THESE CONSTRUC11ON NOTES AND COUNTY
9) CONTRACTOR SHALL CLEAN, PLUG, ABANDON EXISTING SEWER FACILITIES,
ING
WHERE PROPOSED SEWERS CROSS BENEATH EXISTWATERLINES,
SPECIFICATIONS. IF A CONFLICT EXISTS BETWEEN SAME, THE MOST STRINGENT
PER NOTE 11, HEREON.
CONTRACTOR SHALL INSTALL 1 SACK CEMENT SLURRY BACKFILL FROM TOP
REQUIREMENTS SHALL PREVAIL
11• ABANDONMENT CONSTRUCTION
OF TRENCH PIPE ZONE TO SPRING UNE OF PIPE AND INSTALL CLEAN SAND
BEDDING TO 6" OVER EXISTING WATERLINE. BEDDING SHALL BE A MINIMUM
A. PREPARATION
12" EACH SIDE OF WATERLINE.
CONTRACTOR SHALL ABANDON EXISTING LIFT STATION, FORCEMAIN, SEWERS
"
CONTRACTOR SHALL LEAVE TEMPORARY ASPHALT CONCRETE PAVEMENT IN
AND MANHOLES AS FOLLOWS:
SES LATERALS
PLACE FOR FIVE (5) DAYS. THEREAFTER, CONTRACTOR SHALL REMOVE ALL
TEMPORARY ASPHALT CONCRETE PAVEMENT, DISPOSE OF IT AT AN
A. AFTER THE PROPOSED SEWER IS PLACED INTO SERVICE, CONTRACTOR
AUTHORIZED RECYCLING SITE, AND THEN PLACE PERMANENT PAVEMENT.
SHALL REMOVE LIFT STATION INCLUDING PUMPING UNITS, ELECTRICAL
TO CONFIRM LATERAL LOCATIONS, CONTRACTOR SHALL VIEW VIDEO
CONTROL SYSTEM, VALVES, PIPING, DRYWELL, AND WETWEL L.
INSPECTION TAPES FURNISHED BY CITY. EXISTING SEWERS ALONG MARYGOLD
CONTRACTOR SHALL SAW CUT PAVEMENT EDGES TO STRAIGHT, NEAT,
AVENUE (PALMETTO AVENUE TO ENCINA AVENUE) AND ALONG SAN
VERTICAL., EDGES, EITHER PERPENDICULAR TO OR PARALLEL WITH THE
B. CONTRACTOR SHALL CLEAN EXISTING FORCE MAiN AND SEWERS MATH HIGH
BERNARDINO AVENUE (ALDER AVENUE TO BOXWOOD AVENUE) WERE
TRENCH. ALL EXISTING PAVEMENT ADJACENT TO THE TRENCH THAT IS
PRESSURE JET VACTOR TRUCK OR EQUAL FORCE MAIN AND SEWERS SHALL
INSPECTED BY CITY. THEREAFTER, CONTRACTOR SHALL EXCAVATE AND
DAMAGED, UNDERMINED, OR SCARRED, AS DETERMINED BY THE CITY, SHALL
BE CLEANED OF ALL DEPOSITS. CONTRACTOR SHALL PLUG SEWERS AT ALL
EXPOSE EACH INTERFERING LATERAL AND EACH LATERAL TO BE CONNECTED
BE REMOVED AND REPLACED. CONTRACTOR SHALL EXCAVATE UNDERLYING
OPENINGS INCLUDING SEWER LATERAL CONNECTIONS WITH CONCRETE AT 12"
TO PROPOSED SEWER TO DETERMINE THEIR
SUBGRADE TO 12" BELOW PROPOSED CLASS 2 BASE, AND COMPACT IT TO 95
MINIMUM LENGTH. CONTRACTOR SHALL PLUG FORCE MAIN AT 500'
HORIZONTAL AND VERTICAL ALIGNMENTS.
COMPACTION MINIMUM.
INTERVALS WiTH CONCRETE (12" MINIMUM).
CONTRACTOR SHALL EITHER INSTALL 4" OR 6" SERVICE LATERALS AS
B. THICKNESS
1 Z TRQICHING
REQUIRED TO MATCH EXISTING LATERALS OR AS SPECIFIED ON THE
DRAGS,
PERMANENT ASPHALT CONCRETE PAVEMENT SHALL CONSIST OF BASE
PAVEMENT AND OVERLAY PAVEMENT. SAID PERMANENT ASPHALT CONCRETE
CONTRACTOR SHALL LIMIT OPEN TRENCHES TO 100 FEET MAXIMUM
a-
APPROXIMATE LOCATIONS OF LATERALS ARE SPECIFIED ON THE
PAVEMENT SHALL BE HOT PLACED AND SHALL BE 4" THICKNESS MINIMUM (3"
c�
CONSTRUCTION DRAWINGS. CITY WILL CONFER EACH PROPERTY OWNER TO
BASE PAVEMENT PLUS 1" PAVEMENT OVERLAY) PLACED OVER 6" OF CLASS N
DETERMINE PRECISE LOCATIONS. THEREAFTER, CONTRACTOR SHALL
BASE COMPACTED TO 95% RELATIVE COMPACTION MINIMUM IN ACCORDANCE
CONSTRUCT LATERAL FROM PROPOSED SEWER TO EXISTING RIGHT-OF-WAY
WITH COUNTY SPECIFICATIONS, TRENCH DETAIL 'C'.
AT THE LOCATIONS SPECIFIED. LATERALS SHALL TERMINATE WITHIN STREET
RIGHT-OF-WAY (SEE TYPICAL CROSS SECTIONS).
OVERLAY SHALL BE PLACED FROM GUTTER LIP TO GUTTER UP OR EDGE OF
PAVEMENT TO EDGE OF PAVEMENT OR ASPHALT CONCRETE BERM TO
a.
FOR LATERALS NOT CONNECTED TO PROPOSED SEWER, CONTRACTOR SHALL
ASPHALT CONCRETE BERM OR ANY COMBINATION THEREOF FOR MARYGOLD
�^
PROTECT EACH IN PLACE.
AVE. AND ALDER AVE. OVERLAY IS NOT REQUIRED FOR SAN BERNARDINO
AVE.
. .
o•J
C. TRAFFIC SIGNING AND STRIPING
CONTRACTOR SHALL PROTECT IN PLACE ALL EXISTING TRAFFIC SIGNS. ALL
TRAFFIC STRIPING AND PAVEMENT MARKINGS, INCLUDING BUT NOT LIMITED TO,
CENTERLINE LANE LINES, STOP BARS, AND CROSSWALKS DESTROYED OR
DAMAGED DURING CONSTRUCTION SHALL BE REPLACED WITH TEMPORARY
STRIPING OR MARKINGS BY METHOD APPROVED BY THE CITY. SAID
TEMPORARY STRIPING SHALL BE PLACED AT THE END OF EACH WORK DAY.
General Notes,
1. ALL WORK SHALL BE IN ACCORDANCE WITH THESE PLANS, THE CITY OF
FONTANA STANDARD PLANS, THE CONTRACT PROVISIONS AND THE STANDARD
SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION ("GREEN BOOK"). ALL
REFERENCE SPECIFICATIONS AND STANDARDS SHALL BE THE LATEST EDITION
UNLESS OTHERWISE NOTED.
2. CONSTRUCTION PERMITS SHALL BE OBTAINED FROM THE CiTY OF FONTANA
COMMUNITY DEVELOPMENT DEPARTMENT, ENGINEERING DIVISION PRIOR TO THE
START OF ANY WORK. INSPECTION COORDINATION SHALL BE REQUESTED AT
LEAST TWO WORKING DAYS PRIOR TO THE START OF ANY WORK IN PUBLIC
RIGHT-OF-WAY WITHIN THE CITY LIMITS. CALL (909) 350-7610.
3. THE CONTRACTOR SHALL NOT OPERATE ANY FIRE HYDRANT OR WATER MAIN
VALVES. CONTRACTOR SHALL COORDINATE WITH THE APPROPRIATE WATER
COMPANY FOR VALVE OPERATION AND WATER REQUIREMENTS.
4. STATIONING REFERS TO THE CENTERLINE OF EXCEPT WHERE OTHERWISE
NOTED.
5. ALL UNDERGROUND UTILITIES SHALL BE INSTALLED, TESTED AND APPROVED
PRIOR TO PAVING OF STREETS.
6. THE LOCATIONS OF UTILITIES SHOWN HAVE BEEN DETERMINED FROM AVAILABLE
INFORMATION. HOWEVER, IT SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR
TO DETERMINE, IN THE FIELD, THE TRUE LOCATION AND ELEVATION OF ANY
EXISTING UTILITIES, AND TO EXERCISE PROPER PRECAUTION TO AVOID DAMAGE
THERETO. THE CONTRACTOR SHALL CONTACT UNDERGROUND SERVICE ALERT AT
1-800-227-2600 TWO WORKING DAYS BEFORE EXCAVATION.
7. ALL MANHOLES, CLEANOUT FRAMES, COVERS AND VALVE BOXES SMALL BE
RAISED TO F"SHED GRADE BY THE PAVING CONTRACTOR UPON COMPLETION OF
PAVING.
8. THE CONTRACTOR SHALL COORDINATE CONSTRUCTION WITH ALL UTILITY
COMPANIES INCLUDING, BUT NOT LIMITED TO, GAS, TELEPHONE, ELECTRIC, CABLE
TELEVISION, LANDSCAPING, LANDSCAPE IRRIGATION, DOMESTIC WATER, RECLAIMED
WATER, SEWER, STORM DRAIN, FLOOD CONTROL AND CALTRANS. ALL UTILITY
COMPANIES SHALL BE GIVEN TWO WORKING DAYS NOTICE PRIOR TO WORK AROUND
THEIR FACILITIES.
9. AS -BUILT DRAWINGS SHALL BE PROVIDED BY THE CONTRACTOR TO THE ENGINEER
FOR
RECORD, WMD SHALL PROVIDE RECORD DRAWINGS TO THE CITY ENGINEER.
10. WHEN CONFLICT IS FOUND TO EXIST IN THE CONTRACT DOCUMENTS THAT CAN
NOT BE RESOLVED BY REFERENCE TO PRECEDENCE PROVISIONS IN THE "GREEN
BOOK", THE CONTRACTOR SHALL IMMEDIATELY REPORT SAID CONFLICT TO THE CITY
ENGINEER FOR RESOLUTION.
11. APPROVED SOiL STERILANT IS REQl11RED UNDER ALL NEW PERMANENT ASPHALT
PAVEMENT PRIOR TO PLACEMENT.
12. ALL EXPOSED CONCRETE SURFACES SHALL CONFORM IN GRADE, COLOR AND
FINISH TO MATCH EXISTING CONCRETE.
13. NO CONCRETE SHALL BE PLACED UNTiL THE FORMS AND REINFORCING STEEL
HAVE BEEN PLACED, INSPECTED AND APPROVED.
14. THE WALLS AND FACES OF ALL EXCAVATIONS GREATER THAN FIVE (5) FEET IN
DEPTH SHALL BE GUARDED BY SHORING, SLOPING OF THE GROUND OR OTHER
APPROVED MEANS PURSUANT TO THE REQUIREMENTS OF THE DIVISION OF
INDUSTRIAL SAFETY OF THE STATE OF CALIFORNIA. TRENCHES LESS THAN FIVE (5)
FEET SHALL ALSO BE GUARDED WHEN THE POTENTIAL EXISTS FOR GROUND
MOVEMENT.
15. THE CONTRACTOR SHALL OBTAIN A PERMIT TO PERFORM EXCAVATION OR
TRENCH WORK FOR TRENCHES 5 FEET OR GREATER IN DEPTH FROM THE CALIFORNIA
STATE DIVISION OF INDUSTRIAL SAFETY.
16. NO TRENCH BACKFILL SHALL TAKE PLACE WITHOUT PRIOR APPROVAL OF THE
CITY INSPECTOR.
17. THE CONTRACTOR SHALL NOT CAUSE ANY EXCAVATED MATERIAL, MUD SILT OR
DEBRIS TO BE DEPOSITED ONTO PUBLIC OR PRIVATE PROPERTY ADJACENT TO THE
RIGHT OF WAY DURING CONSTRUCTION WITHOUT PRIOR WRITTEN APPROVAL
18. IT SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR TO MAINTAIN
BARRICADES, DELINEATORS OR OTHER TRAFFIC CONTROL AT ALL TiMES.
19. A GEOTECHNICAL ENGINEER SHALL CERTIFY ALL BACKFILL COMPACTION. FAILURE
TO OBTAIN THE REQUIRED DENSITY SHALL REQUIRE RE -WORKING OF THAT PORTION
OF THE WORK UNTIL THE SPECIFIED DENSITY IS OBTAINED.
20. ALL MATERIALS AND METHODS ARE SUBJECT TO THE APPROVAL OF THE CITY
ENGINEER.
21. ADEQUATE CONSTRUCTION CONTROL STAKES SHALL BE SET BY THE EWRAOt TO
ENABLE THE CONTRACTOR TO CONSTRUCT THE WORK TO PLAN GRADES. THE
CONTRACTOR SHALL BE RESPONSIBLE FOR THE PRESERVATION OF BENCHMARKS AND
CONSTRUCTION CONTROL STAKING DURING CONSTRUCTION.
22. CARE SHOULD BE TAKEN TO PREVENT GRADES, DITCHES, AND SWALES FROM
UNDERMINING STREET IMPROVEMENTS. UPON INSPECTION OF THE SITE, THE CITY
ENGINEER MAY REQUIRE TEMPORARY NON-ERODEABLE SWIALES ENTERING OR
LEAVING IMPROVEMENTS.
23. IF EXISTING UTILITIES OR ANY OTHER FACILITIES CONFLICT WITH THE PROPOSED
IMPROVEMENTS, THE CONTRACTOR SHALL NOTIFY THE ENGINEER AND ALL AFFECTED
AGENCIES IMMEDIATELY.
24. THE CONTRACTOR SHALL NOT DISTURB EXISTING SURVEY MONUMENTS,
MONUMENT TiES OR BENCH MARKS WITHOUT PRIOR NOTIFICATION TO THE CITY
ENGINEER.
25. REMOVAL AND REPLACEMENT OF EXISTING SURVEY CONTROL, INCLUDING SURVEY
MONUMENTS, MONUMENT TiES AND BENCH MARKS, SHALL BE DONE BY A
REGISTERED CIVIL ENGINEER OR LICENSED LAND SURVEYOR. SURVEY MONUMENTS
THAT WILL BE DESTROYED AS A RESULT OF THIS CONSTRUCTION SHALL BE
REPLACED. THE CONTRACTOR SHALL NOTIFY THE ENGINEER ONE WEEK PRIOR TO
CONSTRUCTION SO THAT TiES TO MONUMENTS CAN BE ESTABLISHED FOR LATER
REPLACEMENT OF THE MONUMENT.
26. THE CONTRACTOR SHALL MAINTAIN ACCESS FOR LOCAL RESIDENTS AND
BUSINESSES AT ALL TIMES. A MINIMUM TWELVE FOOT LANE SHALL BE MAINTAINED
AT ALL TiMES IN THE CLOSURE AREA FOR RESIDENTS AND EMERGENCY VEHICLES,
27. NO MATERIAL OR EQUIPMENT SHALL BE STORED IN THE PUBIC RIGHT OF WAY
WITHOUT OBTAINING A SEPARATE PERMIT FOR THAT PURPOSE.
28. SANITARY SEWER LINES SHALL BE CONSTRUCTED OF BELL AND SPIGOT OR BAWD
SEAL TYPE VITRIFIED CLAY PIPE (V.C.P.), EXTRA STRENGTH CLASS AND SHAM
CONFORM TO THE PROVISIONS OF THE ASTM DESIGNATION C700 FOR V. C. P.
29. THE SEWER CONTRACTOR SHALL STAMP AN "S" IN THE FACE OF THE CURB AT
THE LOCATION OF THE SEWER LATERAL
30. IF SEWER CONSTRUCTION IS TO BE DONE IN PHASES, THE CONTRACTOR SHALL
PROVIDE A TERMINAL CLEANOUT AT THE PHASE BOUNDARY, NOT MORE THAN 150
FEET FROM THE DOWNSTREAM MANHOLE. SEE CITY OF FONTANA STANDARD DETAIL
FOR TERMINAL CLEANOUT.
31. ALL HOUSE LATERALS SHALL BE INSTALLED AT A 2% MINIMUM GRADE UNLESS
OTHERWISE APPROVED BY THE CITY ENGINEER.
32. PRIOR TO CONSTRUCTION, THE CONTRACTOR SHALL EXPOSE EXISTING FACIL ITIM
AND VERIFY ELEVATION AND LOCATION OF CONNECTIONS. CITY APPROVAL OF
CONNECTIONS TO EXISTING FACILITIES DOES NOT IMPLY CORRECTNESS OF
ELEVATIONS OR LOCATIONS SHOWN ON THE PLANS.
33. THE CONTRACTOR SHALL PROVIDE AND MAINTAIN AN EFFECTIVE MEANS OF DUST
CONTROL. WCLUDING ADEQUATE WATER04 AT ALL TIMES.
34. SHORT VCP STUBS WITH FLEXIBLE COMPRESSION JOINTS SHALL BE USED AT
MANHOLE WALLS TO ALLOW FOR MINOR DEFLECTIONS IN ALIGNMENT.
35. THE CONTRACTOR SMALL CONFORM TO ALL TRAFFIC CONTROL POLICIES,
METHODS AND PROCEDURES DESCRIBED IN THE "W.A.T.C.H. MANUAL", LATEST EDI110N
UNLESS OTHERWISE DIRECTED BY THE CITY TRAFFIC ENGINEER.
36. UPON COMPLETION OF CONSTRUCTION, CONTRACTOR SHALL RESTORE ALL
SIGNING, STRIPING, BARRICADES, AND OTHER TRAFFIC CONTROL DEVICES TO THE
SATISFACTION OF THE CITY TRAFFIC ENGINEER.
37. NO OPEN TRENCH SMALL BE ALLOWED AT THE END OF THE DAY WITHOUT PRIOR
APPROVAL. OF THE CITY ENGINEER.
SELECT NATIVE -
MATERIAL
90% COMPACTED
PROPOSED VCP
� As
NO crok'"'i�T�,ys
�tGG�Z'ar, •n.�a-a
8' ASPHALT WIDTH
iV1-To = i
PVVMT. SECTION
CRUSHED ROCK
PER GRADATION
SHOWN
Bedding Detail,
N.T.S.
TABLE: 200-1.2(A)
SIEVE SiZE
PERCENTAGE
PASSING SIEVES
1 1/2
-
1 "
100
3/4"
90 - 100
1/20
30 - 60
3/8"
0 - 20
NO.4
0-5
NO. 8
-
ASTM C 131
TEST GRADING
B
9
"in
Underground Service Alert L.D. KING, INC. CITY OF FONTANA, CALIFORNIA
ESSi 2151 CONVENTION CENTER WAY CONSTRUCTION NOTES FOR
SECTION 4216/4217 OF THE GOVERNMENT �TRIq� ` SUITE 1008 MARYGOLD AVE. ALDER AVE. S E WE R
o CODE REQUIRES A DIG ALERT IDENTIFICATION 4 ONTARIO, CA 91764 SEWER IMPROVEMENTS DIMM Br.
SCALL
Ll)
NUMKR BE ISSUED BEFORE A PERMIT TO ti (909) 937-0200
EXCAVATE WILL BE VALID - MARYGOLD / ALDERVE CCP CONSTRUCTION NOTES AS SHOWN
cinG
No.44226 A
s�� FOR YOUR DIG ALERT I.D. NUMBER CALL .6 -30 -CM DESIGNED 8Y: DANE
UNDERGROUND SERVICE ALERT C �r ; �l� CCP/I[P? NOV., 1999
�, AND
TOLL FREE 1-800-227-2600 OF MICHAEL PATRICK THORNTON R.C.E. 44 OEM Br. APMM 13 : D TE DRAM N0.:
CN- MCH EL EXPIRES: 6-30-01 C E. o. 226 LOCUST AVE■ LIFT STATION �/i/� �
TWO WORKING DAYS BEFORE YOU DIG REV ��� DESCRIPTION DATE ENGR. CITY DATE DHS 2745 10
CITY ENGDdEQt R.C.E 2512
LDK JOB f 124-04
1I UU-5