HomeMy WebLinkAbout26.1 Progress Schedule LOCUST AVENUE SEWER EXTENSION CiTY OF FONTANA CONTRACTOR SJ. BURKHARDT,INC March 31 April 7 April 14 April 21 April 28 May 5 ID N.m. D.ra,lo. SlMITIWlTIFIS SIMITtWITIFIS SlMITIWlTIFIS SlMITIWlTIFIs SlMITIWlTIFIs SlMITIWlTIFIs 1 PRECONST CONFERENCE 1 d 2 NOTICE TO PROCEED ld 3 SET UP TRAFFIC CONTROL ld 4 SURVEY ld 5 DIG BORE PIT 1 d 6 MOBILIZE BORE CREW ld 7 INSTALL BORE CASING AND PI 6d 8 DIG RECEIVER PiT 1 d 9 DIG,LAY,L BACKFILL OPEN CUT 2d 10 BUILD SEWER MANHOLE 2d 11 B.FILL BORE PIT ld 12 B.FILL RECEIVER PIT l d 13 INSTALL BASE PAVING ld 14 INSTALL CAP PAVING ld 15 RESTORE TRAFFIC LOOPS ld 16 CLEANUP AND SELL JOB 2d : Project: LOCUST AVENUE SEWER Critical ~,//////,///'///'/'/////~ Noncritical ~ Progress Milestone '~ Summary Date: 4/1/96