HomeMy WebLinkAbout27.0 Weekly Statament .City of Fontana
CALIFORNIA
July 31, 1995
Shanon Stewart
S.J. Burkhardt
6157 Marlatt Street
Mira Loma, CA. 91752
RE: Washington Drive Sewer Project From Cypress Avenue to
Approx. 803 Feet East (SB-71-94)
Weekly Statement of Working Days Report No. 8
Dear Mr. Stewart:
Enclosed for review is the weekly statement of working days for
week ending July 28, 1995. You will be allowed (15) days in which
to protest in writing the correctness of the statement; otherwise
the statement shall be deemed to have been accepted as correct.
Please contact Don Gilbertson at (909) 350-6659 or the undersigned
at (909) 350-6645, if any additional information is required.
Sincerely,
COMMUNITY DEVELOPMENT DEPARTMENT
Engineering Division
You~anwala, P.E.
Associate Engineer/Special Projects
YP:DG:dg
8353 SIERRA AVENUE (P.O. BOX 518) · FONTANA, CALIFORNIA 92334-0518 · (714) 350-7600
SISTER CI"Dr'-- KAMLOOPS, B.C. CANADA
CITY OF FONTANA REPORTNO. 8
WEEKLY STATEMENT OF WORKING DAYS
PROJECT: WASHINGTON DRIVE SEWER PROJECT FROM CYPRESS AVE. TO APPROX. 8O3 FEET EAST
TO: S.J. BURKHARDT
The following statement shows the number of working days charged to your contract for the week ending July 28, 1995.
Non-Working Working Days
Days No Work
Date Day Weather, Weather Conditions or Other Conditions Working Caused by Done on
Day Weather Controlling
Operation
(Note 2)
7/24/95 Mon. CLEAR/HOT, 96 DEGREES 1 0
7/25/95 Tue. CLEAR/HOT, 100 DEGREES 1 O
7/26/95 Wed, CLEAR/HOT, 105 DEGREES 1 1
7/27/95 Thur. CLEAR/HOT, 110 DEGREES 1 0
7/28/95 Fd. CLEAR. HOT, 108 DEGREES 1 1
Days this week ...........................................................................................................50 2
Days previously reported ...........................................................................................29 1 4
Total days to date .......................................................................................................341 6
TIME EXTENSIONS CCO Numbers Days Approved
Days this report ..........................................................................................................(Note 3)CCOOther
Days previously reported ........................................................................................................................
Total days to date ...................................................................................................................................00
COMPUTATION OF EXTENDED DATE FOR COMPLETION [ Number INurebared Date
of Days Day (Note 4)
8. Revised work',-S d:!~ 3 for c ', "'~.:t ~'. ir.o 2 ~:l_'~ LI,'~ ~; .................... [ 32'] ~ ...........................
9, Toted worklr.
Controrling Oporaiion(s)
Remarks: (Note 5) (Continue on reverse)
The Contractor will be allowed fifteen (15) days In which to protest in writing the R~Eng~nL
correcthess of the statement; otherwise the statement shall be deemed to have er
been accepted by the Contractor as correct. NOTE: All footnotes are on
reverse s/de.
HF;hf Revised 12/6/1993
INSTRUCTIO]~S TO RESIDENT ENGINEER
1. When recording nonworking days due to weather; state the
reason why the day was unworkable when the weather
description itself does not adequately describe
conditions. For example, "Clear-wet grade" to describe
conditions when the weather is clear, but the grade is
too wet to work. Do not list days merely as
"Unworkable".
2. Enter days on which no productive work has been performed
on the controlling operation(s) for reasons other than
weather.
3. List numbers of contract change orders providing for time
extensions.
4. Do not include noNworking days which occur after
expiration of the Extended DATE OF COMPLETION. On
contracts that are overtime, the total under WORKING DAYS
shall not be greater than the total of REVISED WORKING
DAYS, (line 8). After approved total .of working days
has been reached, continue recording working and
nonworking days but do not add into the totals. Make
statement under REMARKS the WORKING and NONWORKING days
are shown for record only since the contract time has
elapsed.
5. Time extensions other, are to be explained under REMARKS
and the following information is to be included:
(a) Cause of delay and specification reference/under
which approval was granted.
(b) Statement as to what controlling operation or
operations are being delayed and to what extent.
(c) Dates for which the extension was granted
(d). Reference to supporting data.
/~DDITIONAL REM3~RKS:
,City of Fontana
CALIFORNIA
JUly 27, 1995
Shanon Stewart
S.J. Burkhardt
6157 Marlatt Street
Mira 2Loma, CA. 91752
RE: Washington Drive Sewer Project From Cypress Avenue to
Approx. 803 Feet East (SB-71-94)
Weekly Statement of Working Days Report No. 7
Dear Mr. Stewart:
Enclosed for review is the weekly statement of working days for
week ending July 21, 1995. You will be allowed (15) days in which
to protest in writing the correctness of the statement; otherwise
the statement shall be deemed to have been accepted as correct.
Please contact Don Gilbertson at (909) 350-6659 or the undersigned
at (909) 350-6645, if any additional information is required.
Sincerely,
COMMUNITY DEVELOPMENT DEPARTMENT
Engineering Division
Yousuf Patanwala, P.E.
Associate Engineer/Special Projects
YP:DG:dg
8353 SIERRA AVENUE (P.O. BOX 518:~ · FONTAN& CALIFORNIA92334-0518 · (714) 350-7600
SISTER CiTY- KAMLOOPS, B.C. CANADA
CITY OF FONTANA REPORTNO, 7
WEEKLY STATEMENT OF: WORKING DAYS
PROJECT; WASHINGTON DRIVE GEWER PROJECT FROM CYPRESS AVE, TO APPROX, 808 FEET EAST
TO: 8.J. BURKHARDT
The following statement shows the number of working days charged to your contract for the week ending July 21, 1995.
Non-Working Working Days
Days No Work
Date Day Weather, Weather Conditions or Other Conditions Working Caused by Done on
Day Weather Controlling
Operation
(Note 2)
7/17/95 Men. CLEAR/HOT, 100 DEGREES 1
7/18/95 Tue. CLEAR/HOT, 100 DEGREES 1 1
7/19/96 Wed. CLEAR/HOT, 100 DEGREES 1 1
7/20/95 Thur, CLEAR/HOT, 95 DEGREES I 1
7/21/95 Fri. CLEAR, NOT, 96 DEGREES 1 1
Days this week ...........................................................................................................50 4
Days previously reported ...........................................................................................24 I 0
Total days to date .......................................................................................................29I 4
TIME EXTENSIONS CCO Numbers Days Approved
(Note 3) CCO Other
Days this report ..........................................................................................................
Days previously reported .......................................................................................................................
Total days to date ..................................................................................................................................00
COMPUTATION OF EXTENDED DATE FOR COMPLETION Number Numbered Date
of Days Day (Note 4)
2, Wsrkirg o~e s;=o'j.:;cd in c;r;trs3t .................................................................35
4. Total ti'r,o ¢,~tensicn ds~s eFi:revod :e ds'.o .CCC plus ~ :hc~l ..........................
6. Sub To~ {L;qe 4 pLs I'no 51 ..............................................................., ..........
7. EXTENDED DATE FOR COt,;PLETION ~L;no 3 p'.us L.no ~) ............................... ; ' ' ' I 7 3; 05
8, Revised w ;;rking ds) s for ccntrcct (Li,'=o 2 F'us I:ne 4) .................................... 35 I .....
Controlling Operation(s)
Remarks: (Note 5) (Continue on reverse)
The Contrecto~ will be ellowed fifteen (15) days In which to protest in wri~jng the ~n
correctnose of the statement; otherwise the statement shell be deemed to he, ve ear
been accepted by the Contractor as correct. NOTE: All footnotes ere on
reverse side.
HF:hf Revised 12/6/1993
INSTRUCTIONS TO RESIDENT ENGINEER
1. When recording nonworking days due to weather; state the
reason why the day was unworkable when the weather
description itself does not adequately describe
conditions. For example, "Clear-wet grade" to describe
conditions when the weather is clear, but the grade is
too wet to work. Do not list days merely as
"Unworkable".
2. Enter days on which no productive work has been performed
on the controlling o]peration(s) for reasons other than
weather. '
3. List numbers of contract change orders providing for time
extensions.
4. Do not include nonworking days which occur after
expiration of the Extended DATE OF COMPLETION. On
contracts that are overtime, the total under WORKING DAYS
shall not be greater than the total of REVISED WORKING
DAYS, (line 8). After approved total of working days
has been reached, continue recording working and
nonworking days but do not add into the totals. Make
statement under REMARKS the WORKING and NONWORKING days
are shown for record only since the contract time has
elapsed.
5. Time extensions other, are to be explained under REMARKS
and the following information is to be included:
(a) Cause of delay and specification reference/under
which approval was granted.
(b) Statement as te what controlling operation or
operations are being delayed and to what extent.
(c) Dates for which the extension was granted.
(d) Reference to supporting data.
ADDITIONAL REMARKS:
City of Fontana
CALIFORNIA
JUly 17, 1995
Shanon Stewart
S.J. Burkhardt
6157 Marlatt Street
Mira Loma, CA. 91752
RE: Washington Drive Sewer Project From Cypress Avenue to
Approx. 803 Feet ]East (SB-71-94)
Weekly Statement of Working Days Report No. 6
Dear Mr. Stewart:
Enclosed for review is the weekly statement of working days for
week ending July 14, 1995. You will be allowed (15) days in which
to protest in writing the correcthess of the statement; otherwise
the statement shall be deemed to have been accepted as correct.
Please contact Don Gilbertson at (909) 35'0-6659 or the undersigned
at (909) 350-6645, if any additional information is required.
Sincerely,
COMMUNITY DEVELOPMENT DEPARTMENT
Engineering Division
Yousuf Patanwala, P.E.
Associate Engineer/Special Projects
YP:DG:dg
MAILING ADDRESS: P.O.BOX 518
83S3 SIERRA AVENUE ,, FONTANA, CALIFORNIA 92334-0518 · (909) ;350-7600
CITY OF FONTANA REPOP;I' NO. 6
WEEKLY STATEMENT OF WORKING DAYS
PROJECT: WASHINGTON DRIVE SEWER PROJECT FROMI CYPRESS AVE. TO APPROX. 803 FEET EAST
TO: S.J. BURKHARDT
The following statement shows the number of working days ~harged to you~ contract for the week ending July 14, 1995.
Non-Working Working Days
Days No Work
Date Day Weather, Weather Conditions or Other Conditions Working Caused by Done on
Day Weather Controlling
Operation
(Note 2)
7/10/95 Mon. CLEAR/HOT, 95 DEGREES 1
7/11/95 Tee. CLEAR/HOT, 100 DEGREES 1
7/12/95 Wed. CLEAR/HOT, 100 DEGREES 1
7/13/95 Thur. CLEAR/HOT, 100 DEGREES 1
7/14/95 FH. CLEAR, HOT, 95 DEGREES 1
Days this week ...........................................................................................................50
Days previously reported ...........................................................................................19
ToteS days to date .......................................................................................................241
TIME EXTENSIONS CCO Numbera Days Approved
Days this report ..........................................................................................................(Note 3)CCO Other
Days previously reported ........................................................................................................................
Total days to date ...................................................................................................................................00
COMPUTATION OF EXTENDED DATE FOR COMPLETION [ Number ~ Numbered Date
· of Days Day (Note 4)
1. First working def dos'3nc, tod ............................................... ~ c= C-;' 95
2. Working d. :ys sp;-,c:,5,~ ;n coRt~ oct ................................................................I35 ~ .........
3. COMPUTE DA'rE FOR CCr,t~L~ ICN C; ul; c
4. Total time extonsion de:~s oppro'¢od to d!~to ICCO plus ,~'~url ..................... ...'
5. Total non-~ork:na d~ye to d~tu (Note 4) .............................................................1
6. Sub Toted :Ur:a 4 p~us bed 51 ....................................................................1
7. EXTENDEl;) DATE FCR CO;,{PLET, ION ~L:no 3 plus Uno E) ........................ ' ' ~ ~ 7~3~ ~95
8. Revised w:r~<~ra days for eontm:t {LIP, o 2 p'.qs Line 4} ................................. 35 '
9. Total work:r~:3 d~ys to do. to ........................................................................24 . .
10. WORKIN3C/'.YS R.'r,'/'I%~I';31L','o~Pi,',~sLi~ogl ................................ 11
Controlling Operation(e)
Remarks; (Note 5) (Continue on reverse)
The Contractor will be ellowed fifteen (15) days in which to protest In writing the R~ent;""
correctsass of the statement; otherwise the statement eheS]l be deemed to have ngineer
been accepted by the Contractor es correct, NOTE: All footnotes ere on
reverse side.
HF:hf Revised 12/6/1993
INSTRUCTIONS TO RESIDENT ENGINEER
1. When recording nonworking days due to weather; state the
reason why the day was unworkable when the weather
description itself does not adequately describe
conditions. For exa~!e, "Clear-wet grade" to describe
conditions when the weather is clear, but the grade is
too wet to work. Do not list days merely as
"Unworkable".
2. Enter days on which no productive work has been performed
on the controlling operation(s) for reasons other than
weather. '
3. List numbers of contract change orders providing for time
extensions.
4. Do not include nonworking days which occur after
expiration of the Extended DATE OF COMPLETION. On
contracts that are overtime, the total under WORKING DAYS
shall not be greater than the total of REVISED WORKING
DAYS, (line 8). After approved totalof working days
has been reached, continue recording working and
nonworking days but do not add into the totals. Make
statement under REMARKS the WORKING and NONWORKING days
are shown for record only since the contract time has
elapsed.
5. Time extensions other, are to be explained under REMARKS
and the following information is to be included:
(a) Cause of delay and specification reference/under
which approval was granted.
(b) Statement as to what controlling operation or.
operations are being delayed and to what extent.
(c) Dates for which the extension was granted.
(d) Reference to supporting data.
ADDITIONAL REMARES:
City of Fontana
CALIF'ORNIA
JUly 11, 1995
Shanon Stewart
S.J. Burkhardt
6157 Marlatt Street
Mira Loma, CA. 91752
RE: Washington Drive Sewer Project From Cypress Avenue to
Approx. 803 Feet East (SB-71-94)
Weekly Statement of Working Days Report No. 5
Dear Mr. Stewart:
Enclosed for review is the weekly statement of working days for
week ending July 7, 1995. You will be allowed (15) days in which
to protest in writing the correctness of the statement; otherwise
the statement shall be deemed to have been accepted as correct.
Please contact Don Gilbertson at (909) 350-6659 or the undersigned
at (909) 350-6645, if any additional information is required.
Sincerely,
COMMUNITY DEVELOPMENT DEPArtMENT
Engineering Division
YoU'~ Pa anwala, P.E.
Associate Engineer/Special Projects
YP:DG::dg
MAILING ADDRESS: P.O.BOX 518
8353 SIERRA AVENUE · FON"[ANA, CALIFORNIA 92334-0518 · (909) 350-7600
CITY OF FONTANA REPORT NO. 5
WEEKLY STATEMENT OF WORKING DAYS
PROJECT: WASHINGTON DRIVE SEWER PROJECT FROM CYPRESS AVE. TO APPROX. 803 FEET EAST
TO: 8.J. BURKHARDT
The following statement shows the number of working days charged to your contract for the week ending Jury 7, 1995,
Non-Working Working Days
Days No Work
Date Day Weather, Weather Conditions or Other Conditions Working Caused by Done on
Day Weather Controlling
Operation
(Note 2)
7/03/95 Man. CLEAR/HOT, 90 DEGREES 1
7/04/95 Tue. HOLIDAY 0
7/05/95 Wed. CLEAR/HOT, 96 DEGREES 1
7/06/95 Thur, CLEAR/HOT, 96 DEGREES 1
7/07/95 FrL CLEAR, HOT, 95 DEGREES 1
Days this week ...........................................................................................................40
Days previously reported ...........................................................................................15 1
Total days to date .......................................................................................................191
TiME EXTENSIONS CCO Numbers Days Approved
(Note 3) CCO Other
Days this reperf~ ..........................................................................................................
Days previously reported ........................................................................................................................
Total days to date ...................................................................................................................................00
COMPUTATION OF EXTENDED DATE FOR COMPLETION Number
Numbered Data
of Oa~e Day(N~e~:) "ecs~j~'' .
1. First working da)' designstad ..................................................................';...:': ... . ...............
2. Working days speci.qed in contract .............................................................35
3. COMPUTE DATE FOR COMPLETION (~f all <jays speclf.ed are workablo) .......... : ~' 7: :' I 7 2,~,~"'
4. Total ~me rextans;on days =pproved to data {CCO plus 3lhorl ....................
5. Total non-work nc days to data {Nolo 41 ..................................................I ~...
6. Sub Tobl (Line 4 pl,~s L;no 5i .......................................................................1
7. EXTENDED DATE FOR COk'.PLETION IL :no 3 p:ds Li.~c e;) .......................... . ............. * I 7,'~"ti~
8. Revised workln:~ d% s fcr cont.a:l IL:ho 2 p'us L'no 41 ............................... 35 ....... = .......
9. Total working d.~ys to da'.e ..................................................................19
10. WORK]NO DAYS FP.~AI;,I I'~S {Uhe 8 mi',L 9 Ll~.o 5i ............................... 16 '.
Controlling Operation(s)
Remarks: (Note 5) (Continue o~ reverse)
The Contractor will be ellawed fifteen (15) days in which to protest in wring ~ ~ ~
sorrectneas of the ~tatament; otherwise ~e statement ~hell be deemed to have t Engineer
been accepted by t~e Contractor as earroot. NOTE: All fo<>tnotas ere on
reverse elde.
HF:hf Revised 12/6/1993
INSTRUCTIONS TO RESIDENT ENGINEER
1. When recording nonworking days due tO weather; state the
reason why the day was unworkable when the weather
description itself does not adequately describe
conditions. For example, "Clear-wet grade" to describe
conditions when the weather is clear, but the grade is
too wet to work. Do not list days merely as
"Unworkable".
2. Enter days on which no productive work has been performed
on the controlling operation(s) for reasons other than
weather.
3. List numbers of contract change orders providing for time
extensions.
4. Do not include nonworking days which occur after
expiration of the Extended DATE OF COMPLETION. On
contracts that are Overtime, the total under WORKING DAYS
shall not be greater than the total of REVISED WORKING
DAYS, (line 8). After approved totalof working days
has been reached, continue recording working and
nonworking days but do not add into the totals. Make
statement under REMARKS the WORKING and NONWORKING days
are shown for record only since the contract time has
elapsed.
5. Time extensions other, are to be explained under REMARKS
and the following information is to be included:
(a) Cause of delay and specification reference/under
which approval was granted.
(b) Statement as to what controlling operation or.
operations are being delayed and to what extent.
(c) Dates for which the extension was granted.
_ (d). Reference to supporting data.
ADDITIONAL REMARKS:
, , v v
City of Fontana
CALIFORNIA
July 5, 1995
Shanon Ste~ Tt
S.J. Burkh.!dt
6157 Marlatt Street
Mira iLoma, CA. 91752
Washington Drive Sewer' Project From Cypress Avenue to
Approx. 803 Feet East (SB-71-94)
'Weekly Statement of Working Days Report No. 4
Dear Mr. Stewart:
Enclosed for review is the weekly statement of working days for
week ending June 30, 1995. You will be allowed (15) days in which
to protest in writing the correctness of the statement; otherwise
the statement shall be deemed to have been accepted as correct.
Please contact Don Gilbertson at (909) 350-6659 or the undersigned
at (909) 350-6645, if any additional information is required.
Sincerely,
COMMUNITY DEVELOPMENT DEPARTMENT
Engineeri g Division.
Associate Engineer/Special Projects
YP:DG:dg
8353 SIERRA AVENUE (P.O. BOX 5 '18) · FONTANA, CALIFORNIA 92334-0518 · (714) 350-7600
SISTER CITY -- KAMLOOPS, S.C. CANADA
CITY OF FONTANA REPOFff NO. 4
WEEKLY STATEMENT OF WORKING DAYS
PROJECT: WASHINGTON DRIVE SEWER PROJECT FROM CYPRESS AVE. TO APPROX. 803 FEET EAST
TO; S,J. BURKHARDT
The following ctatement shows the number of working days charged to your contract for the Week ending June 23, 1995·
Non-Working Working Days
Days No Work
Date Day Weather, Weather Conditions or Other Conditions Working Caused by Done on
Day Weather Controlling
Operation
(Note 2)
6/26/95 Men. OVERCAST, HUMID, HOT, 91 DEGREES 1
6/27/95 Tue. CLEAR, HOT, 93 DEGREES 1
6/28/95 Wed. CLEAR/HOT, 95 DEGREES 1
6/29/95 Thur. CLEAR/HOT, 90 DEGREES 1
6/30/95 Fri. CLEAR, HOT, 93 DEGREES I 0
Days this week ...........................................................................................................50
Days previously reported ...........................................................................................10 1
Total days to date ........................................................................................................151
TIME EXTENSIONS CCO Numbers Days Approved
(Note 3) CCO Other
Days this report ..........................................................................................................
Days previously reported .......................................................................................................................
Total days to date ...................................................................................................................................00
COMPUTATION OF EXTENDED DATE FOR COMPLETION ~ N~imber ~Numbered Date
1. Firstworkingdaydesignated ................................................................................~t~lil~li~i i:: ~l~!~li~ 6/09/95
3. COMpUTLL;,',T"~RCC~,"~L'.I.L!N.it,' .;. ,:t,::,,,:; :.:Jc,';.;=l,r :I.:.. .......... : ......................... 7_2.:.,?.~..
,": .............:.... ":"""':"""':"':"""":":::::.:.::.J : -I
7. EXTENDED D,'."L w L:.R CG;.'i'LET. I~.'.% :1 n,', 3 p'u.' Ln.: '3 ............................' ..... ~.. '..~.5'..75_.
.' ...........................................................
Controlling Operation (s)
Remarks: (Note 5) (Continue on reverse)
The Contractor will be allowed fifteen (15) days in which to protest in writing the t j
correctnasa of the statement; otherwise the statement shall be deemed to have ~R '~ent Engineer
been accepted by the Contractor as correct. NOTE: Aft footnotes ere on
reverse side.
HF;hf ised 12/6/1993
INSTRUCTIO]~S TO RESIDENT ENGINEER
1. When recording nonworking days due to weather; state the
reason why the day was unworkable when the weather
description itself does not adequately describe
conditions. For example, "Clear-wet grade" to describe
conditions when the weather is clear, but the grade is
too wet to work. Do not list days merely as
"Unworkable".
2. Enter days on which no productive work has been performed
on the controlling operation(s) for reasons other than
weather.
3. List numbers of contract change orders providing. for time
extensions.
4. Do not include nom~orking days which occur after
expiration of the Extended DATE OF COMPLETION. On
contracts that are overtime, the total under WORKING DAYS
shall not be greater than the total of REVISED WORKING
DAYS, (line 8). After approved total of working days
has been reached, continue recording working and
nonworking days but do not add into the totals. Make
statement under REMARKS the WORKING and NONWORKING days
are shown for record only since the contract time has
elapsed.
5. Time extensions other,. are to be explained under REMARKS
and the following information is to be included:
(a) Cause of delay and specification reference/under
which approval was granted.
(b) Statement as to what controlling operation or
operations are being .delayed and to what extent.
(c) Dates for which the extension was granted.
(d) Reference to supporting data.
ADDITIONAL REMARKS:
City of Fontana
CALIFORNIA
June 27, 1995
Shanon Stewart
S.J. Burkhardt
6157 Marlatt Street
Mira iLoma, CA. 91752
RE: Washington Drive Sewer Project From Cypress Avenue to
Approx. 803 Feet East (SB-71-94)
Weekly Statement of Working Days Report No. 3
Dear Mr. Stewart:
Enclosed for review is the weekly statement of working days for
week ending June 23, 1995. You will be allowed (15) days in which
to protest in writing the correctness of the statement; otherwise
the statement shall be deemed to have been accepted as correct.
Please contact Don Gilbertson at (909) 350-6659 or the undersigned
at (909) 350-6645, if any additional information is required.
Sincerely,
COMMUNITY DEVELOPMENT DEPARTMENT
Engineering Division
You nwala, P.E.
Associate Engineer/Special Projects
YP:DG:dg
8353 SIERRA AVENUE(P.O. BOX518) · FONTANA, CALIFORNIA92334-O818 · (714) 350-7600
SISTER CI'r'Y- KAMLOOPS, B.C. CANADA
~w~ recycled paper
CITY OF FONTANA REPORT NO. 3
WEEKLY STATEMENT OF WORKING DAYS
PROJECT: WASHINOTON DRIVE SEWER PROJECT FROI~A CYPRESS AVE. TO APPROX. 803 FEET EAST
TO: 8.j. BURKHARDT
The following statement shows the number of working days she. rged to your sontract for the week ending June 23, 1995.
Non-Working Working Days
Days No Work
Date Day Weather, Weather Conditions or Other Conditions Working Caused by Done on
Day Weather Centrotting
Operation
(Note 2)
6/19/95 Men. CLEAR, WARM, 68 DEGREES 1
6/20/95 Tue. CLEAR, WARM, 86 DEGREES 1
6/21/95 Wed. CLEAR/WARM, 84 DEGREES 1
6/22/95 Thur. CLEAR/HOT, 95 DEGREES 1
6/23/95 Fd. CLEAR, HOT, 96 DEGREE,~ 1 0
Days this week ...........................................................................................................50
Days previously reported ...........................................................................................5 1
Total days to date .......................................................................................................101
TiME EXTENSIONS CCO Numbers Days Approved
(Note 3) CCO Other
Days this report ..........................................................................................................
Days prevloasly reported .......................................................................................................................
Total days to date ...................................................................................................................................00
COMPUTATION OF EXTENDED DATE FOR COMPLETION l Number { Numbered Date
of Days Day (Note 4)
7, EXTENDE. D :ATE (;'ICC~.'..-'.LE' .',:.~= -. 3n .~L- ..::. · '~ ....... I 771
Controlling Operation (s)
Remarks: (Note 5) (Continue on reverse)
The Contractor wiII be allowed fifteen (15) days in which to protest in writing the
correcthess of the statement; otherwise the statement shell be deemed to have er
been accepted by the Contractor as correct. NOTE: All footnotes are on
reverse side.
H F:hf Revised 12/6/1993
INSTRUCTIONS TO RESIDENT ENGINEER
1. When recording nonworking days due to weather; state the
reason why the day was unworkable when the weather
description itself does not adequately describe
conditions. For example, "Clear-wet grade" Co describe
conditions when the weather is clear, but the grade is
too wet to work. Do no~ list days merely as
"Unworkable".
2. Enter days on which no productive work has been performed
on the controlling operation(s) for reasons other than
weather.
3. List numbers of contract change orders providing'for time
extensions.
4. Do not include nonworking days which occur after
expiration of the Extended DATE OF COMPLETION. On
contracts that are overtime, the total under WORKING DAYS
shall not be greater than the total of REVISED WORKING
DAYS, (line 8). After approved total of working days
has been reached, continue recording working and
nonworking days but d~o not add into the totals. Make
statement under REMARKS the WORKING and NONWORKING days
are shown for record only since the contrack time has
elapsed.
5. Time extensions other, are to be explained under REMARKS
and the following information is to be included:
(a) Cause of delay and specification reference/under
which approval was granted.
(b) Statement as to what controlling operation or
operations are being delayed and to what extent.
(c) Dates for which the extension was granted.
(d) Reference to supporting data.
kDDITIO~AL REMARKS:
City of Fontaria
CALIFORNIA
June 27, 1995
Shanon Stewart
S.J. Burkhardt
6157 Marlatt Street
Mira Loma, CA. 91752
RE: Washington Drive Sewer Project From Cypress Avenue to
Approx. 803 Feet East (SB-71-94)
Weekly Statement of Working Days Report No. 2 (Revised)
Dear Mr. Stewart:
Enclosed for review is the weekly statement of working days for
week ending June 16, 1995, revised to reflect correct completion
date. You will be allowed (15) days in which to protest in writing
the correctness of the statement; otherwise the statement shall be
deemed to have been accepted as correct.
Please contact Don Gilbertson at (909) 350-6659 or the undersigned
at (909) 350-6645, if any additional information is required.
Sincerely,
COMMUNITY DEVELOPMENT DEPARTMENT
Engineering Division
Yousu~Pat~nwala, P.E.
Associate Engineer/Special Projects
YP:DG:dg
8353 SIERRA AVENUE (P.O. BOX 51 B) · FONTAN,a, CALIFORNIA 92334-0518 · (714) 350-7600
SISTER CITY- KAMLOOPS, B.C. CANADA
~ recycled paper
CITY OF FONTANA REPORT NO. 2 (Revised)
WEEKLY STATEMENT C)F WORKING DAYS
PROJECT: WASHINGTON DRIVE 8E'VVER PROJECT FROM CYPRESS AVE. TO APPROX. 803 FEET EAST
TO: 8.J. BURKHARDT
The following statement shows the number of working days charged to your contract for the week ending June 23, 1995.
Non-Working Working Days
Days No Work
Date Day Weather, Weather Conditions or Other Conditions Working Caused by Done on
Day Weather Controlling
Operation
(Note 2)
6/12/95 Mon. SUNNY/HOT, 97 DEGREES 1
6/13/95 Tue. CLEAR/HOT, 98 DEGREES 1
6/14/95 Wed. CLEAR/WARM, 80 DEGREES 1
6/15/95 '[hur. CLEAR/COOL 68 DEGREES 1
6/16/95 FH. RAIN, 60 DEGREES 0 1
Days this week ..........................................................................................................'41
Days previously reported .........................................................................................1 0
Total days to date .....................................................................................................51
TIME EXTENSIONS CCO Numbers Days Approved
Days this report ........................................................................................................(Note 3)CCO Other
Days prevlously reported .....................................................................................................................
Total days to date ................................................................................................................................00
coMPuTAT,o. oF ENDED DATE FoR coMPLET,oNoats
9. Work,rig .~.',. ,.:;;: '. ~,: .,, :=,'....'.: ...............................!:.'_. 'T:.,r_.. ~7"i. "" :7.'. 'Z:E:"". :. :' .' '
3. COMpUTE~r',.~T:FC.'~CC.,~'..ET,;'...,:¢.t=:~.c::::r..:..:r.:.v.:.~!d..,:: ........I 72~;,5
4. Total time e4~,'-.i;: d~;s ,;.?.r:..',.~.. ;: r.: tc ,:~ b ~c,':.,'2.. F- ..~ :.%::r, ..........r ...... ~' ......................
":" ""' "" "": ..........................................I
· :,:::;%..;'L...:-;, ................................................_.
7. EXTENDEO D/,TF.' FC;I CC:,:2: .-.'I',C'; :L:n.: 3 =~1,~ !it c 6...r ......I ....t ........I7~'~ 95
8. Revised wc -king :la, s rcr c.~"'
9. Total work .~g :::':.s to d~.o ................................ . ..................I 5
10. WORKIN'~ C;.vS r;E'.' ;'.',~
Controlling Operation(s)
Remarks: (Note 5) (Continue on reverse)
Extended date for completion added.
The Contrastor will be allowed fifteen (15) days in which to protest in writing the
correcthess of the statement; otherwise the statement shall be deemed to have R r
been accepted by the Contractor as correct, NOTE: All footnotes are on
reverse side.
HF:hf Revised 12/6/1993
INSTRUCTICeS TO RESIDENT ENGINEER
1. When recording nonworking days due to weather; state the
reason why the day was unworkable when the weather
description itself does not adequately describe
conditions. For example, "Clear-wet grade" to describe
conditions when the weather is clear, but the grade is
too wet to work. Do not list days merely as
"Unworkable".
2. Enter days on which no productive work has been performed
on the controlling operation(s) for reasons other than
weather.
3. List numbers of contract change orders providing for time
extensions.
4. Do not include nonworking days which occur after
expiration of the Extended DATE OF COMPLETION. On
contracts that are overtime, the total under WORKING DAYS
shall not be greater than the total of REVISED WORKING
DAYS, (line 8). After approved total of working days
has been reached, continue recording working and
nonworking days but do not add into the totals. Make
statement under REMARKS the WORKING and NONWORKING days
are shown for record only since the contract time has
elapsed.
5. Time extensions other, are to be explained under REMARKS
and the following information is to be included:
(a) Cause of delay and specification reference/under
which approval was granted.
(b) Statement as to what controlling operation or
operations are being delayed and to what extent.
(c) Dates for which the extension was granted.
_ (d) Reference to supporting data.
ADDITIONAL REMARKS:
City of Fontana
CALIFORNIA
June 19, 1995
Shanon Stewart
S.J. Burkhardt
6157 Marlatt Street
Mira Loma, CA. 91752
RE: Washington Drive Sewer Project From CyDress Avenue to
Approx. 803 Feet East (SB-71-94)
Weekly Statement of Working Days Report No. 2
Dear Mr. Stewart:
Enclosed for review is the 'weekly statement of working days for
week ending June 16, 1995. You will be allowed (15) days in which
to protest in writing the correctness of the statement; otherwise
the statement shall be deemed to have been accepted as correct.
Please contact Don Gilbertson at (909) 350-6659 or the undersigned
at (909) 350-6645, if any additional information is required.
Sincerely,
COMMUNITY DEVELOPMENT DEPARTMENT
Engineering Division
Yousuf Patanwala, P.E.
Associate Engineer/Special Projects
YP:DG:dg
8353 SIERRA AVENUE (P.O. BOX 518) · FONTANA, CALIFORNIA 92334-0518 · (714) 350-7600
SISTER CITY -- KAMLOOPS, B.C. CANADA
CITY OF FONTANA REPORT NO.
WEEKLY STATEMENT OF WORKING DAYS
PROJECT= WASHINGTON DRIVE SEWER PROJECT FROM CYPRESS AVE. TO APPROX. 803 FEET EAST
TO; S.J, SURKHARDT
The following statement shows the number of worklng dey~a charged to your contract for the week ending June 16, 1995.
Non-Working Working Days
Days No Work
Date Day Weather, Weather Conditions or Other Conditions Working Caused by Done on
Day Weather Controlling
Operation
(Note 2)
6/12/95 Men. SUNNY/HOT, 97 DEGREES 1
6/13/95 Tue. CLEAR/HOT, 98 DEGREES 1
6/14/95 Wed. CLEAR/WARM, 80 DEGREES t
6/16/95 Thur. CLEAR/COOL, 68 DEGREES 1
6/16/93 Fd. RAIN, 60 DEGREES O 1
Days this week ..........................................................................................................41
Days previously reported .........................................................................................1 0
Total days to date .....................................................................................................51
TIME EXTENSIONS CCO Numbers Days Approved
(Note 3) CCO Other
Days this report ........................................................................................................
Days previously reported .....................................................................................................................
Total days to date ................................................................................................................................0O
COMPUTATION OF EXTENDED DATE FOR COMPLETION Number Numbered Date
of Days Day (Note 4) ..... ~J~
1. First working day dc ~:gllb;..'3 ............................................................, . . ........................................................
2. Working days specFied In ccr,t-o:t .............................................................~,5i
3. coMPUTE DATE FC~ CC','.P.-r..O~ ;f .,1 d.-.,'s ,p~.d...d ,.-o v.:,P.;.,~.:> ........' .....................................::3......~'Ei!E::...
4. Total time extension db';9 op;:rc,;od to d:,:e (CCO plus ~ti..q; .......! · ' :...
s. To., .on-work,nO ~,'.>s to d..,:. ~.o.o. ...........................................:.:::::::: ......Ji': ·."
0
6, Sub Total (LIne 4 plus L no 5; ................................................................ .......
7, EXTENDEO DATE FCR CCM~L_'TiCN (L:no ~ plus L'r,.: (:~ ............................ ]
8. Revised w:h::-'g c.: ~8 f.:.r cch=.r:!ct (Lir,c 2 p,us UP..~ -;t ............................ 35 i ;J :
9. Total worki~:g c!:.# s :.3 dote .................................................................~. _._5____i ' ' '
10. WORKIN 3 .'3..',YS ;:EMA kl'~G ~L/n: ," mi.-..,s L "~ 9'. ...................... 33 :
Controlling Operation(e)
Remarks: (No!re 5) (Continue on reverse)
The Contractor will be allowed fifteen (15) days in which to protest in writing the e~
correotness of the statement; otherwise the statement shell be deemed to have R
been accepted by the Contractor as correct. NOTE: All footnotes are on
reverse side.
HF:hf Revised 12/6/1993
I~STRUCTIONS TO RESIDENT ENGINEER
1. When recordin9 nonworking days due to weather; state the
reason why the day was unworkable when the weather
description itself does not adequately describe
conditions. For example, "Clear-wet grade" to describe
conditions when the weather is clear, but the grade is
too wet to work. Do not list days merely as
"Unworkable".
2. Enter days on which no productive work has been performed
on the controlling operation(s) for reasons other. than
weather.
3. List numbers of contract change orders providing for time
extensions.
4. Do not include nonworking days which occur after
expiration of the Extended DATE OF COMPLETION. On
contracts that are overtime, the total under WORKING DAYS
shall not be greater than the total of REVISED WORKING
DAYS, (line 8). After approved total of working days
has been reached, continue recording working and
nonworking days but do not add into the totals. Make
statement under REMARKS the WORKING and NONWORKING days
are shown for record only since the contract time has
elapsed.
5. Time extensions other, are to be explained under REMARKS
and the following information is to be included:
(a) Cause of delay and specification reference/under
which approval was granted.
(b) Statement as to what controlling operation or
operations are being delayed and to what extent.
(c) Dates for which the extension was granted.
(d) Reference to supporting data.
ADDITIONAL REMARKS:
City of Fontana
CALIFORNIA
June 19, 1995
Shanon Stewart
S.J. Burkhardt
6157 Marlatt Street
Mira Loma, CA. 91752
RE: Washington Drive Sewer Project From Cypress Avenue to
Approx. 803 Feet East (SB-71-94)
Weekly Statement of Working Days Report No. 1
Dear Mr. Stewart:
Enclosed for review is the weekly statementof working days for
week ending June 9, 1995, You will be allowed (15) days in which
to protest in writing the correctness of the statement; otherwise
the statement shall be deemed to have been accepted as correct.
Please contact Don Gilbertson at (909) 35'0-6659 or the undersigned
at (909) 350-6645, if any additional information is required.
Sincerely,
COMMUNITY DEVELOPMENT DEPARTMENT
Engineering Division
YousuE Patanwala, P.E.
Associate Engineer/Special Projects
YP:DG:dg
6353 SIERRA AVENUE (P O. BOX 51,8) · FONTAN& CALIFORNIA 92334-0518 · (714) 350-7600
SISTER CI'P,'- KAMLOOPS, B.C. CANADA
~ recycled paper
CITY OF FONTANA REPORT NO. 1
WEEKLY STATEMENT OF WORKING DAYS
PROJECT: WASHINGTON DRIVE SEWER PROJECT FROM CYPRESS AVE. TOAPPROX. 803 FEET EAST
TO: S.J. BURKHARDT
The following statement shows the number of working days charged to your contract for the week ending June 9, 1995.
Non-Working Working Days
Days No Work
Date Day Weather, Weather Conditions or Other Conditions Working Caused by Done on
Day Weather Controlling
Operation
(Note 2)
Man.
Tue.
Wed.
Thur.
6/9/95 Fd. CLEAR/WARM, 85 DEGREES 1
Days this week ...............................................................................................................1
Days previously reported ................................................................................................0
Total days to date ..........................................................................................................1
TIME EXTENSIONS CCO Numbers Days Approved
(Note 3) CCO Other
Days this report ..............................................................................................................
Days previously reported ...........................................................................................................................
Total days to date ....................................................................................................................: ..................00
COMPUTATION OF EXTENDED DATE FOR COMPLETION Number J Numbered Date
~ ~.,;,,.~ Day (Note 4)
1, First working day designated ...................................................................................~3~,~ 6/09/95
3. COMPUTE DATE FOR CC'.;=L="T' 3N j= ~1. d'.!, s ~:F-c':"';;;: ,"e ,;c'L~': 7.~ ..... r" ' ~ .....
4. Totedtimeox'.~ms';;ndc, r~c.[.:F~'c',cot,:,~:,.tc ~C'20;;.:.,cl.'c-~ ............ " ........... ! .......... J' 72~95
............................................................ o .. .......
:~ 'PEA i'i cc>r.'r, LE'rloN ,.i.-.:s::
9. Total working c;cys [o tint:: ..................................................................
10. WORKIt!G D;,Yg Ft"',';, I,I'~G d =no e r'i~'us D"'~.. -3.1 .............................. I ~.1 J
Controlling Operation(s)
Remarks: (Note 5) (Continue on reverse)
The Contractor will be allowed fifteen (15) days in which to protest in wdting the d/~~m Eng~n
correcthess of the statement; otherwise the statement shal[ be deemed to have ear
been accepted by the Contractor ae correct. NOTE: All 1rootnotes are on
reverse side,·
H F ;hf Revised 12/6/1993
INSTRUCTIONS TO RESIDENT ENGINEER
1. When recording nonworking days due to weather; state the
reason why the day was unworkable when the weather
description itself does not adequately describe
conditions. For example, "Clear-wet grade" to describe
conditions when the weather is clear, but the grade is
too wet to work. Do not list days merely as
"Unworkable".
2. Enter days on which no productive work has been performed
on the controlling operation(s) for reasons other than
weather.
3. List numbers of contract change orders providing for time
extensions.
4. Do not include nonworking days which occur after
expiration of the Extended DATE OF COMPLETION. On
contracts that are overtime, the total under WORKING DAYS
shall not be greater than the total of REVISED WORKING
DAYS, (line 8). After approved total of working days
has been reached, continue recording working and
nonworking days but do not add into the totals. Make
statement under REMARKS the WORKING and NONWORKING days
are shown for record only since the contract time has
elapsed.
5. Time extensions other, are to be explained under REMARKS
and the following information is to be included:
(a) Cause of delay and specification reference/under
which approval was granted.
(b) Statement as to what controlling operation or
operations are being delayed and to what extent.
(c) Dates for which the extension was granted.
_ (d) Reference to supporting data.
ADDITIONAL REMARKS: