HomeMy WebLinkAboutSierra Business Park PM 16264 June 2004HYDROLOGY AND HYDRAULIC CALCULATIONS FOR SIERRA BUSINESS PARK SOUTH EAST CORNER OF SLOVER AVENUE AND SIERRA AVENUE PREPARED FOR LENNAR PARTNERS PREPARED BY: HUITT-ZOLLARS 1101 SOUTH MILLIKEN AVENUES SUITE #G ONTARIOS CALIFORNIA 91761 JUNE 2004 PROJECT NO. 11-0202-02 Table of Contents Title Introduction Location Purpose Previous Studies Hydrologic Analysis Hydraulic Analysis Conclusions Page 1 2 11 3 List of Technical Appendices Technical Appendix A 100-Year Rational Method Analysis Hall & Foreman, Inc. Technical Appendix B 25-Year Rational Method Analysis Hall & Foreman, Inc. Technical Appendix C Hydrology Map Hall & Foreman, Inc. Technical Appendix D 100-Year Rational Method Analysis Huitt-Zollars, Inc. Technical Appendix E 25-Year Rational Method Analysis Huitt-Zollars, Inc. Technical Appendix F Hydrology Map Huitt-Zollars, Inc. Technical Appendix G 100-Year Rational Method Analysis RBF Consulting Technical Appendix H 25-Year Rational Method Analysis RBF Consulting Technical Appendix I Hydrology Map RBF Consulting Technical Appendix J 100-Year Hydrograph Analysis Including Detention Basin Technical Appendix K 100-Year Hydraulic Analysis Technical Appendix L 25-Year Hydraulic Analysis Introduction A hydrologic and hydraulic analysis has been prepared for the Sierra Business Park and surrounding areas. Several drainage reports have been prepared in the past for this area. This report is a compilation and integration of these other reports into a global drainage design for the area. Location The Sierra Business Park site is located east of Sierra Avenue between Slover Avenue and Santa Ana Avenue in the City of Fontana, California. Other developments are also included in this hydrologic and hydraulic analysis including the Empire Center which is located north of Sierra Business Park and Sycamore Hills which is located south of Sierra Business Park. Purpose This report has been developed to evaluate drainage improvements necessary to convey flows from the Sierra Business Park site and the other surrounding developments to the DeClez Channel. The existing drainage facilities upstream of the DeClez Channel do not have adequate capacity to convey the developed 100-year peak flow rates. Due to this constraint, storm flows will need to be detained in order to reduce the peak flows to a level that can be adequately conveyed by the existing drainage facilities. Additionally, the existing drainage system in Sierra Avenue and Slover Avenue was designed to convey the 25-year return event flows. The current drainage plan for the area is to drain the 100- year return event flows. Therefore, some improvements to this existing storm drain will be required in order to meet the current criteria. Previous analyses have concentrated on incorporating onsite detention basins in each development to reduce the peak flow rate. This report has been developed to incorporate one single offsite basin, located west of Sierra Avenue, to reduce the 100-year peak flow rate to an adequate level. Previous Studies As indicated, this report is based on hydrologic and hydraulic analyses that have been previously completed. The previous reports are: Master Hydrology Study for Empire Center Lines A, B, & C Hall & Foreman, Inc — January 28, 1992 Preliminary Hydrology & Hydraulic Calculations for Sierra Business Park Huitt Zollars, Inc — November 1, 2003 Storm Drain Basis of Design Sycamore Hills II — Tentative Tract No. 16495 RBF Consulting — February 2004 Hydrologic Analysis The rational method hydrologic analysis is contained in Technical Appendices A, B, D, E, G, & H. The basis for the calculations is the previous studies. Some minor modifications were made to the previous studies to incorporate the latest drainage plans for the area. Most notably, the Sierra Business Park onsite storm drain facility Line H has been re-routed west in Santa Ana Avenue to the existing storm drain in Sierra Avenue rather than crossing Santa Ana Avenue and flowing through the residential development to the south. Since a detention basin has been proposed as an integral component of the area drainage plan, a hydrograph analysis has also been completed. In order to develop the lag parameter for the hydrograph analysis, the rational method Tc of the longest flowpath must be known. Since the previous studies "user -specified" drainage information from the upstream studies, the Tc for the longest flowpath was not available. Therefore, the rational method data files were modified to include all confluence values, including the longest flowpath, so that the Tc of the longest flowpath was available. The hydrograph and basin routing analysis is contained in Technical Appendix J. The proposed detention basin was evaluated to reduce the 100-year flows to a level that could be adequately drained by the existing storm drain facility. In order to accomplish this, the basin outlet bleeder line is required to drain south to the existing reinforced concrete box (RCB) in Jurupa Avenue. Even, draining to the RCB, the basin outlet will be impacted by a submergence effect from the downstream hydraulics. For the outlet structure calculations, the submergence effect was assumed to be linearly interpolated from zero at the basin floor to the water surface elevation determined by the downstream hydraulics at the spillway crest. The basin has also been analyzed to incorporate infiltration into the highly permeable soils. Based on a geotechnical investigation report for an adjacent site, the infiltration rate was assumed to be 1.8 inches per minute into the basin floor. Hydraulic Analysis An extensive hydraulic analysis of the drainage system was completed as part of the Storm Drain Basis of Design Sycamore Hills II — Tentative Tract No. 16495 completed by RBF Consulting in February 2004. Based on Figures 5.1 and 5.2 of that report, it has been determined that at least I I I cfs basin outflow can be reintroduced into the existing reinforced concrete box in Jurupa Avenue. A hydraulic analysis was completed for the bleeder line from the basin outlet to the reinforced concrete box in Jurupa Avenue. This analysis determined the size of the bleeder line and the water surface at the detention basin that would be used as submergence in the calculations of the basin outlet size. This hydraulic analysis was balanced with the basin analysis to determine the maximum water surface elevation in the basin. The hydraulics of the existing storm drain system in Sierra Avenue were analyzed using a controlling water surface equal to the maximum detention basin 100-year water surface elevation. Both 100-year and 25-year hydraulic analyses were completed for the Sierra Avenue system based on this same controlling hydraulic grade line elevation. The peak flow rates for these analyses were taken from the hydrologic analyses with the exception of the upstream reaches in Slover Avenue. In this area, the previous hydrologic analysis does not correspond to the 25-year peak flow rates shown on the storm drain plans for this facility. Therefore, the peak flow rates on the plans were used for the 25-year analysis and were increased for the 100-year analysis based on the ratio of 100-year to 25-year flows from the site. Additionally, 100-year hydraulic analyses were completed for Sierra Business Park onsite storm drain facility Line A, a portion of which exists in Santa Ana Avenue, and Line H. Technical Appendix K contains the 100-year hydraulic analyses and Technical Appendix L contains the 25-year hydraulic analysis of the storm drain in Sierra Avenue and Slover Avenue. Conclusions With minor improvements to the existing storm drain system, a modified drainage system has been developed to adequately convey 100-year return event flows from the Sierra Business Park site. The proposed improvements include an offsite detention basin, re-routing of the existing storm drain in Sierra Avenue into the basin, and upgrading a portion of the existing storm drain in Sierra Avenue, specifically increasing the size of the existing 54" storm drain from Sta. 36+07.33 to Sta. 42+47.67 to a 60" storm drain. The storm drain facilities serving the development north of Slover Avenue were designed to convey 25-year return event peak flow rates. Although it is not required that these storm drains be able to convey the 100-year return event flows, a quick analysis indicated that the system could likely be upsized to convey the 100-year flows. By upsizing approximately 750' of the existing 42" storm drain in Sierra Avenue from Sta. 56+07.14 to Sta. 63+58.16 to a 48" storm drain, the hydraulic grade line of the storm drain in Slover Avenue at the location where the storm drain goes onsite appears to be sufficiently low to drain the 100-year flows (no onsite analysis was completed). Technical Appendix A 100-Year Rational Method Analysis Derived from Master Hydrology Study for Empire Center Lines A, B, & C Hall & Foreman, Inc — January 28, 1992 is it i� is it is it it it it ie it it'h'h it it it it it is it is ie it it is is is it it it it it it ie it it it it is is it it it it it it it is it it it it it it it ie it ie it is sY ie it it is it it is is it it it it is RATIONAL METHOD HYDROLOGY COMPUTER PROGRAM PACKAGE (Reference: 1986 SAN BERNARDINO CO. HYDROLOGY CRITERION) (c) copyright 1983-93 Advanced Engineering software (aes) ver. 1.9B Release Date: 7/18/93 License ID 1202 Analysis prepared by: HUITT-ZOLLARS, INC. 15101 RED HILL AVENUE TUSTIN, CALIFORNIA 92780-6500 PHONE (714) 259-7900 * FAX (714) 259-0210 ---------------------------------------------------------------------------- FILE NAME: FECNLBXX.DAT TIME/DATE OF STUDY: 12:46 5/ 3/2004 -----------------------------------------------------------------------= USER SPECIFIED HYDROLOGY AND HYDRAULIC MODEL INFORMATION: ---------------------------------------------------- --*TIME-OF-CONCENTRATION MODEL* -- USER SPECIFIED STORM EVENT(YEAR) 100.00 SPECIFIED MINIMUM PIPE SIZE(INCH) = 18.00 SPECIFIED PERCENT OF GRADIENTS (DECIMAL) TO USE FOR FRICTION SLOPE = .95 *USER -DEFINED LOGARITHMIC INTERPOLATION USED FOR RAINFALL* 10-YEAR STORM 60-MINUTE INTENSITY(INCH/HOUR) _ .920 100-YEAR STORM 60-MINUTE INTENSITY(INCH/HOUR) = 1.340 COMPUTED RAINFALL INTENSITY DATA: STORM EVENT = 100.00 1-HOUR INTENSITY(INCH/HOUR) = 1.3400 SLOPE OF INTENSITY DURATION CURVE = .6000 i.•i: it is it i:it*�•**ir Xitki.•ir �•i: i; .r is tel: is �•ic�ic ir�:k fc k�ie 4r'.t it it is is k i; �'i; &.ir it i; ie��..•�it i; Xi; �•:Y is it �•i: �-ir�ir is ie i; is is it is it FLOW PROCESS FROM NODE 100.00 TO NODE 100.01 IS CODE = 2.1 ---------------------------------------------------------------------------- »»>RATIONAL METHOD INITIAL SUBAREA ANALYSIS««< ----------------------------------------------------------------------- NATURAL POOR COVER TC = K*[(LENGTH** 3.00)/(ELEVATION CHANGE)]** .20 INITIAL SUBAREA FLOW-LENGTH(FEET) = 500.00 UPSTREAM ELEVATION(FEET) = 1111.00 DOWNSTREAM ELEVATION(FEET) = 1102.00 ELEVATION DIFFERENCE(FEET) = 9.00 TC(MIN.) = .525*[( 500.00** 3.00)/( 9.00)]** .20 = 14.083 100 YEAR RAINFALL INTENSITY(INCH/HR) = 3.197 SOIL CLASSIFICATION IS "B" NATURAL POOR COVER "BARREN" SUBAREA LOSS RATE, FM(INCH/HR) = .2700 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) _ .27 SUBAREA PERVIOUS AREA FRACTION, Ap = 1.00 SUBAREA RUNOFF(CFS) = 10.41 TOTAL AREA(ACRES) = 3.95 PEAK FLOW RATE(CFS) = 10.41 '.ci:i: stir it is is it*iti:&ic*i:**iri: �Y it it*ic sY it i:i:i:*it it it i:i:ic*i: it it i:ir*ic it is it is i.•*i:**. it it it is is*i.•i: is it is is is is i�it is ir**ir it FLOW PROCESS FROM NODE 100.01 TO NODE 100.01 IS CODE = 8 ---------------------------- >>>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 100 YEAR RAINFALL INTENSITY (INCH/HR) = 3.197 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 Page 1 SUBAREA AREA(ACRES) = 2.95 SUBAREA RUNOFF(CFS) = 8.29 EFFECTIVE AREA(ACRES) = 6.90 AREA -AVERAGED FM(INCH/HR) _ .19 AREA -AVERAGED Fp(INCH/HR) = .30 AREA -AVERAGED Ap = .62 TOTAL AREA(ACRES) = 6.90 PEAK FLOW RATE(CFS) = 18.70 TC(MIN) = 14.08 icir is ie it ie ie ie is it it it it is it it it it it it it it it it it it it icic ie it it s4 is it it it it is it it it it it it is is i; is is it ic. is it it # ie ie is it ie is :Y is is it * ie is it it it is ie iric FLOW PROCESS FROM NODE 100.01 TO NODE 101.01 IS CODE = 3 ---------------------------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< -------------------------------------------------------------------- DEPTH OF FLOW IN 30.0 INCH PIPE IS 21.4 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 5.0 UPSTREAM NODE ELEVATION(FEET) = 1088.40 DOWNSTREAM NODE ELEVATION(FEET) = 1087.00 FLOW LENGTH(FEET) = 470.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 30.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 18.70 TRAVEL TIME(MIN.) = 1.57 TC(MIN.) = 15.65 it*ir*ic is is it it is it it it it it ir'k it it it is*ie*ir it it is it it it it it is it is is is*ir iri: is is it is it it*it ie is is it ie it*ir is it it it it is ie it is is it is is ie it is it it FLOW PROCESS FROM NODE 101.01 TO NODE 101.01 IS CODE = 1 --------------------------- »»>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< ------------------------------------------------------------------------ TOTAL NUMBER OF STREAMS = 2 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 1 ARE: TIME OF CONCENTRATION(MIN.) = 15.65 RAINFALL INTENSITY(INCH/HR) = 3.00 AREA -AVERAGED FM(INCH/HR) = .19 AREA -AVERAGED Fp(INCH/HR) = .30 AREA -AVERAGED Ap = .62 EFFECTIVE STREAM AREA(ACRES) = 6.90 TOTAL STREAM AREA(ACRES) = 6.90 PEAK FLOW RATE(CFS) AT CONFLUENCE = 18.70 ::i:i: �•ic ir;:iti:**ir it is*i.•it irir it ie it is*iti.•ir it is it**ir it it it �r it aY it is it it**ir it*ir it it ic.*ie ie it it***it it is ie**i; ie it it it it is*ic it FLOW PROCESS FROM NODE 102.00 TO NODE 102.01 IS CODE = 2.1 ---------------------------------------------------------------------------- »»>RATIONAL METHOD INITIAL SUBAREA ANALYSIS««< - ------------------------------------------------------------ NATURAL POOR COVER TC = K^•[(LENGTH** 3.00)/(ELEVATION CHANGE)]** .20 INITIAL SUBAREA FLOW-LENGTH(FEET) = 550.00 UPSTREAM ELEVATION(FEET) = 1111.00 DOWNSTREAM ELEVATION(FEET) = 1103.00 ELEVATION DIFFERENCE(FEET) = 8.00 TC(MIN.) = .525*[( 550.00** 3.00)/( 8.00)]** .20 = 15.267 100 YEAR RAINFALL INTENSITY(INCH/HR) = 3.046 SOIL CLASSIFICATION IS "B" NATURAL POOR COVER "BARREN" SUBAREA LOSS RATE, FM(INCH/HR) = .2700 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) _ .27 SUBAREA PERVIOUS AREA FRACTION, Ap = 1.00 SUBAREA RUNOFF(CFS) 12.24 TOTAL AREA(ACRES) = 4.90 PEAK FLOW RATE(CFS) = 12.24 it it it is x it i; : it * * it is J: i; i, is * * is is ie'., is ir'., ., is it :; it i:., .r is it * :: *'.: * it � * is ir'.r i.• it is * it * ., is is :4 ;; it �' it is it *.:Y it'..., it it it i, ., ..., FLOW PROCESS FROM NODE 102.01 TO NODE 102.01 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< Page 2 100 YEAR RAINFALL INTENSITY(INCH/HR) = 3.046 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 4.80 SUBAREA RUNOFF(CFS) = 12.84 EFFECTIVE AREA(ACRES) = 9.70 AREA -AVERAGED Fm(INCH/HR) _ .17 AREA -AVERAGED Fp(INCH/HR) _ .31 AREA -AVERAGED Ap = .55 TOTAL AREA(ACRES) = 9.70 PEAK FLOW RATE(CFS) = 25.08 TC(MIN) = 15.27 it ir'r it it is it it it Xir it it is is it it it is is it is is is it it is ie it it is i:i:i: it is it i:Yale kic is it it�ic it it is it is ie it it it it it is it is is is �i: it it it it it is is sY is it 9e FLOW PROCESS FROM NODE 102.01 TO NODE 101.01 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 33.0 INCH PIPE IS 25.3 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 5.1 UPSTREAM NODE ELEVATION(FEET) = 1088.60 DOWNSTREAM NODE ELEVATION(FEET) = 1087.00 FLOW LENGTH(FEET) = 590.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 33.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 25.08 TRAVEL TIME(MIN.) 1.91 TC(MIN.) = 17.18 ;: is ai: � � .. it it it i. 'c i:.. '..• i; it it i; i; �• i; k it it ic'.r it i; & � ., is k is i; i; i:...... �• sY it it i; � i � :.. � k ie it is � '� is i� is it it � is i.., i.• i:'.r'.c � is it i. FLOW PROCESS FROM NODE 101.00 TO NODE 101.01 IS CODE = 8 --------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 100 YEAR RAINFALL INTENSITY(INCH/HR) = 2.838 SOIL CLASSIFICATION IS "B" NATURAL POOR COVER "BARREN" SUBAREA LOSS RATE, FM(INCH/HR) = .2700 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) _ .27 SUBAREA PERVIOUS AREA FRACTION, Ap = 1.00 SUBAREA AREA(ACRES) = 3.50 SUBAREA RUNOFF(CFS) = 8.09 EFFECTIVE AREA(ACRES) = 13.20 AREA -AVERAGED FM(INCH/HR) _ .20 AREA -AVERAGED Fp(INCH/HR) = .30 AREA -AVERAGED Ap = .67 TOTAL AREA(ACRES) 13.20 PEAK FLOW RATE(CFS) = 31.35 TC(MIN) = 17.18 �i:i;isi: iv it ie �•it�•ir it sY 4:i;:c ie i; it is it i:i: it it iri; ie it it it is it i�ic it it fir it it it is it it it it it it i;i;i;ir°k it it i:i:i;i: ie is it i; i; it is it i; it it is it i; is FLOW PROCESS FROM NODE 101.01 TO NODE 101.01 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 100 YEAR RAINFALL INTENSITY(INCH/HR) = 2.838 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 3.90 SUBAREA RUNOFF(CFS) = 9.70 EFFECTIVE AREA(ACRES) = 17.10 AREA -AVERAGED FM(INCH/HR) _ .17 AREA -AVERAGED Fp(INCH/HR) = .32 AREA -AVERAGED Ap = .54 TOTAL AREA(ACRES) = 17.10 PEAK FLOW RATE(CFS) = 41.04 TC(MIN) = 17.18 i::Y it .. .. .. is is �.. ., �i: '.. �;k�... i:�:i;i:&':iei:i;'.:rir&ir �i;�i; �4r irx it it it ir��i:�i:i; ir�i:�•ie'...... .. .. .. .. it it is �i; k:: :: i; is :: ire FLOW PROCESS FROM NODE 101.01 TO NODE 101.01 IS CODE = 1 Page 3 ------------------------- »»>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< »»>AND COMPUTE VARIOUS CONFLUENCED STREAM VALUES««< --------------------------------------------------------------------------- TOTAL NUMBER OF STREAMS = 2 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 2 ARE: TIME OF CONCENTRATION(MIN.) = 17.18 RAINFALL INTENSITY(INCH/HR) = 2.84 AREA -AVERAGED FM(INCH/HR) = .17 AREA -AVERAGED Fp(INCH/HR) = .32 AREA -AVERAGED Ap = .54 EFFECTIVE STREAM AREA(ACRES) = 17.10 TOTAL STREAM AREA(ACRES) = 17.10 PEAK FLOW RATE(CFS) AT CONFLUENCE = 41.04 RAINFALL INTENSITY AND TIME OF CONCENTRATION RATIO CONFLUENCE FORMULA USED FOR 2 STREAMS. ** PEAK FLOW RATE TABLE ** Q Tc Intensity Fp Ap Fm Ae (CFS) (MIN.) (INCH/HR) (INCH/HR) (INCH/HR) (ACRES) 1 58.37 15.65 3.001 .31 .56 .18 22.48 2 58.65 17.18 2.838 .31 .56 .18 24.00 COMPUTED CONFLUENCE ESTIMATES ARE AS FOLLOWS: PEAK FLOW RATE(CFS) = 58.65 TC(MIN.) = 17.182 EFFECTIVE AREA(ACRES) = 24.00 AREA -AVERAGED Fm(INCH/HR) _ .18 AREA -AVERAGED Fp(INCH/HR) _ .31 AREA -AVERAGED Ap = .56 TOTAL AREA(ACRES) = 24.00 ,,^.�.,. .. «•?c?c?tit?e?c*4r«•?r?c?:?c?c*ir it?t'r?:�Yi•4F eY*?t*?t*?t4e?r?r'c?c?c?tir?r*?c*?t?tir?c?c?t?r***?r?r?r*?r?r?c is ?r*«•?c ?r*.*ft ?r ?r?c?r?r?r FLOW PROCESS FROM NODE 101.01 TO NODE 108.01 IS CODE = 3 ---------------------------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< - -------------------------------------------------------------------- DEPTH OF FLOW IN 42.0 INCH PIPE IS 29.9 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 8.0 UPSTREAM NODE ELEVATION(FEET) = 1087.00 DOWNSTREAM NODE ELEVATION(FEET) = 1079.70 FLOW LENGTH(FEET) = 1500.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 42.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 58.65 TRAVEL TIME(MIN.) = 3.13 TC(MIN.) = 20.31 it «• is ie?t it ?c is is it?c it?t ?r it is *?r it it it * *.?t is is ie ie is * *ic is it is ie ie?e ?e is * ie k ie is is * * is * it ?e it it?c it it ?r ?r?: it * is is * is •'k it?r is ?: *?r ?r is is FLOW PROCESS FROM NODE 108.00 TO NODE 108.01 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 100 YEAR RAINFALL INTENSITY(INCH/HR) = 2.567 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 5.60 SUBAREA RUNOFF(CFS) = 12.56 EFFECTIVE AREA(ACRES) = 29.60 AREA -AVERAGED FM(INCH/HR) = .16 AREA -AVERAGED Fp(INCH/HR) = .33 AREA -AVERAGED Ap = .48 TOTAL AREA(ACRES) = 29.60 PEAK FLOW RATE(CFS) = 64.21 TC(MIN) = 20.31 .. .. ,, ,, «'?: ?r ?t «•ic«..**?tic?:**icc*•.l•ic«?r«?r?ric«*i:*ir*........i:i:i:i:«•ir*?. is ie***'..•*iti:?..... .. .. .. .. .. .. .. .. ?t is it«•*i: :: it Page 4 FLOW PROCESS FROM NODE 111.10 TO NODE 108.01 IS CODE = 8 --------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 100 YEAR RAINFALL INTENSITY(INCH/HR) = 2.567 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 1.08 SUBAREA RUNOFF(CFS) = 2.42 EFFECTIVE AREA(ACRES) = 30.68 AREA -AVERAGED FM(INCH/HR) _ .15 AREA -AVERAGED Fp(INCH/HR) = .33 AREA -AVERAGED Ap = .46 TOTAL AREA(ACRES) = 30.68 PEAK FLOW RATE(CFS) = 66.63 TC(MIN) = 20.31 i::Y i::c it it is 4t :r ;r 4t 4c it it ie it it it it it Yc 4r it 4c * * 4c it it is is 4t it it �r fc ic:Y 4c is it fc it * it is it do 4c it it it 4: it it fir. is 9c ir:Y * ic:'t *:'r it �t de �t it 4t 4t it it it 4e FLOW PROCESS FROM NODE 115.00 TO NODE 108.01 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 100 YEAR RAINFALL INTENSITY(INCH/HR) = 2.567 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 1.23 SUBAREA RUNOFF(CFS) = 2.76 EFFECTIVE AREA(ACRES) = 31.91 AREA -AVERAGED FMCINCH/HR) _ .15 AREA -AVERAGED Fp(INCH/HR) = .34 AREA -AVERAGED Ap = .45 TOTAL AREA(ACRES) = 31.91 PEAK FLOW RATE(CFS) = 69.39 TC(MIN) = 20.31 ** PEAK FLOW RATE TABLE ** Q TC Intensit Fp Ap Fm Ae (CFS) (MIN.) (INCH/HR� (INCH/HR) (INCH/HR) (ACRES) 1 69.48 18.78 2.690 .34 .44 .15 30.39 2 69.39 20.31 2.567 .34 .45 .15 31.91 NEW PEAK FLOW DATA ARE: PEAK FLOW RATE(CFS) = 69.48 TC(MIN.) = 18.78 AREA -AVERAGED FM(INCH/HR) = .15 AREA -AVERAGED Fp(INCH/HR) _ .34 AREA -AVERAGED Ap = .44 EFFECTIVE AREA(ACRES) = 30.39 'rYt::**4:�•�c Yc't:ttc*Yt*'.cic'.r*i.•4c 4c:Y sY it it it i:ir*****ic 4r:Y it ic:Y4c*:Y*ir*ir it*ir ir�r*ic**ir'.c:c4r'c 4t***ic 4t :t '.c ::::'.t*it*ir FLOW PROCESS FROM NODE 108.01 TO NODE 107.01 IS CODE = 3 ---------------------------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< ------------------------------------------------------------------ DEPTH OF FLOW IN 36.0 INCH PIPE IS 26.3 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 12.6 UPSTREAM NODE ELEVATION(FEET) = 1079.70 DOWNSTREAM NODE ELEVATION(FEET) = 1075.90 FLOW LENGTH(FEET) = 260.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 36.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 69.48 TRAVEL TIME(MIN.) _ .35 TC(MIN.) = 19.13 4:is*is 4r:'t4�*4c'c'.c4r:'r it it it sY is 4r is ir:Y4: is it*4c it:Y it 4c is it it:Y it 4t is 4r**it ic:Y:'c is �c Yc it*:Y**°k 4c �r it 4::Y?.•�•'.t 4e.:: 4r:'e is ic'c ir:'c 4c**ir 4v FLOW PROCESS FROM NODE 107.00 TO NODE 107.01 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 100 YEAR RAINFALL INTENSITY(INCH/HR) = 2.661 Page 5 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 7.40 SUBAREA RUNOFF(CFS) = 17.22 EFFECTIVE AREA(ACRES) = 37.79 AREA -AVERAGED FM(INCH/HR) _ .13 AREA -AVERAGED Fp(INCH/HR) = .36 AREA -AVERAGED Ap = .38 TOTAL AREA(ACRES) = 39.31 PEAK FLOW RATE(CFS) = 85.90 TC(MIN) = 19.13 :c�:�.;4;4; it 4e ie:; it is f; ie it it 4r it it is icx it it ie Xir ie 4r 4r it it sY:;:;i; it 44c is u it fc is it it it is ie it is k'.e is is ie is ie is i; 4 it it i; 4; ie'.c 4r i; it ie is dr is 4; k:r FLOW PROCESS FROM NODE 107.01 TO NODE 106.11 IS CODE = 3 ---------------------------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< -------------------------------------------------------------------- DEPTH OF FLOW IN 39.0 INCH PIPE IS 28.3 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 13.3 UPSTREAM NODE ELEVATION(FEET) = 1075.90 DOWNSTREAM NODE ELEVATION(FEET) = 1070.55 FLOW LENGTH(FEET) = 360.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 39.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 85.90 TRAVEL TIME(MIN.) _ .45 TC(MIN.) = 19.58 FLOW PROCESS FROM NODE 106.11 TO NODE 106.11 IS CODE 1 ---------------------------------------------------------------------------- »»>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< ------------------------------------------------------------- TOTAL NUMBER OF STREAMS = 2 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 1 ARE: TIME OF CONCENTRATION(MIN.) = 19.58 RAINFALL INTENSITY(INCH/HR) = 2.62 AREA -AVERAGED FM(INCH/HR) = .13 AREA -AVERAGED Fp(INCH/HR) = .36 AREA -AVERAGED Ap = .38 EFFECTIVE STREAM AREA(ACRES) = 37.79 TOTAL STREAM AREA(ACRES) = 39.31 PEAK FLOW RATE(CFS) AT CONFLUENCE = 85.90 FLOW PROCESS FROM NODE 106.00 TO NODE 106.01 IS CODE = 2.1 ---------------------------------------------------------------------------- »»>RATIONAL METHOD INITIAL SUBAREA ANALYSIS««< DEVELOPMENT IS COMMERCIAL TC = K*[(LENGTH** 3. 00)/ (ELEVATION CHANGE)]** .20 INITIAL SUBAREA FLOW-LENGTH(FEET) = 500.00 UPSTREAM ELEVATION(FEET) = 1098.00 DOWNSTREAM ELEVATION(FEET) = 1095.70 ELEVATION DIFFERENCE(FEET) = 2.30 TC(MIN.) = .304*[( 500.00** 3.00)/( 2.30)]** .20 = 10.713 100 YEAR RAINFALL INTENSITY(INCH/HR) = 3.767 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA RUNOFF(CFS) = 12.63 TOTAL AREA(ACRES) = 3.80 PEAK FLOW RATE(CFS) = 12.63 Page 6 is k is ie is is ie is it ie ie � ie is it is ie it ie is it is is X it it ie ie is is ie it it ie ie it it it ie it ie ie it is is ie it it is is ie ie is it it it itit ie it is it is ie ie it is it is is ie it k sY it is FLOW PROCESS FROM NODE 106.01 TO NODE 106.11 IS CODE = 3 ---------------------------------------------------------------------------- >>>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< >>>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< - --- ----------------------------------------------------------------- DEPTH OF FLOW IN 21.0 INCH PIPE IS 12.6 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 8.4 UPSTREAM NODE ELEVATION(FEET) = 1086.00 DOWNSTREAM NODE ELEVATION(FEET) = 1070.55 FLOW LENGTH(FEET) = 1050.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 21.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 12.63 TRAVEL TIME(MIN.) = 2.09 TC(MIN.) = 12.81 d: it kic it it it it is it ie it it it it is it is is is it it is i; it iir it ie it it it s4 it it ie ie it it it it ie is it is it is it it it it it it is is ir•k it it fc ie it is it it it i; 9r it it is it is is is is FLOW PROCESS FROM NODE 106.10 TO NODE 106.11 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< ------------------------------------- 100 YEAR RAINFALL INTENSITY(INCH/HR) = 3.385 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 3.90 SUBAREA RUNOFF(CFS) = 11.62 EFFECTIVE AREA(ACRES) = 7.70 AREA -AVERAGED FM(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) _ .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 7.70 PEAK FLOW RATE(CFS) = 22.94 TC(MIN) = 12.81 it is is is it it it it i:ici; it is is ie Xir is is it �t is it it it it ie it ic�ir ie �Y Yr:e ie it it ie ir�ir it ie it is ie it is it it �sY ie ie it ie i; it it it it is is icir it �Y it it it it it i; �'r FLOW PROCESS FROM NODE 111.00 TO NODE 106.11 IS CODE = 8 ---------------------------------------------------------------------------- >>>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< ---------------------------------------------------------------------------- 100 YEAR RAINFALL INTENSITY(INCH/HR) = 3.385 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) _ .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 1.00 SUBAREA RUNOFF(CFS) = 2.98 EFFECTIVE AREA(ACRES) = 8.70 AREA -AVERAGED Fm(INCH/HR) _ .07 AREA -AVERAGED Fp(INCH/HR) _ .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 8.70 PEAK FLOW RATE(CFS) = 25.92 TC(MIN) = 12.81 •k it i<kic icir it it is ir�ic is it it ir�ir��i: fir it t. is iric it kic ic:�ir is it it it ic•k irir is it it is it it is is i<i; is iric��ic&ic it is is it i; i<ie it it is is iri;tk FLOW PROCESS FROM NODE 106.11 TO NODE 106.11 IS CODE = 1 »»>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< >>>AND COMPUTE VARIOUS CONFLUENCED STREAM VALUES««< -------------------------------------------------------------- TOTAL NUMBER OF STREAMS = 2 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 2 ARE: TIME OF CONCENTRATION(MIN.) = 12.81 RAINFALL INTENSITY(INCH/HR) = 3.38 AREA -AVERAGED Fm(INCH/HR) = .07 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = 10 EFFECTIVE STREAM AREA(ACRES) = 8.70 TOTAL STREAM AREA(ACRES) = 8.70 Page 7 PEAK FLOW RATE(CFS) AT CONFLUENCE = 25.92 RAINFALL INTENSITY AND TIME OF CONCENTRATION RATIO CONFLUENCE FORMULA USED FOR 2 STREAMS. PEAK FLOW RATE TABLE ** Q Tc Intensit Fp Ap Fm Ae (CFS) (MIN.) (INCH/HR� (INCH/HR) (INCH/HR) (ACRES) 1 105.86 19.58 2.624 .38 .32 .12 46.49 2 104.12 21.11 2.508 .38 .33 .13 48.01 3 99.29 12.81 3.385 .39 .30 .12 33.42 COMPUTED CONFLUENCE ESTIMATES ARE AS FOLLOWS: PEAK FLOW RATE(CFS) = 105.86 TC(MIN.) = 19.576 EFFECTIVE AREA(ACRES) = 46.49 AREA -AVERAGED FM(INCH/HR) _ .12 AREA -AVERAGED Fp(INCH/HR) _ .38 AREA -AVERAGED Ap .32 TOTAL AREA(ACRES) = ---------------------------------------------=------------------------------ 48.01 ---------------------------------------------------------------------------- END OF STUDY SUMMARY: TOTAL AREA(ACRES) = 48.01 TC(MIN.) = 19.58 EFFECTIVE AREA(ACRES) = 46.49 AREA -AVERAGED FM(INCH/HR)= .12 AREA -AVERAGED Fp(INCH/HR) _ .38 AREA -AVERAGED Ap = .32 PEAK FLOW RATE(CFS) = 105.86 ** PEAK FLOW RATE TABLE ** Q TC Intensity Fp Ap FM Ae (CFS) (MIN.) (INCH/HR) (INCH/HR) (INCH/HR) (ACRES) 1 99.29 12.81 3.385 .39 .30 .12 33.42 2 105.86 19.58 2.624 .38 .32 .12 46.49 3 104.12 21.11 ---------------------------------------------------------------------------- ---------------------------------------------------------------------------- 2.508 .38 .33 .13 48.01 END OF RATIONAL METHOD ANALYSIS Page 8 RATIONAL METHOD HYDROLOGY COMPUTER PROGRAM PACKAGE (Reference: 1986 SAN BERNARDINO CO. HYDROLOGY CRITERION) (c) copyright 1983-93 Advanced Engineering Software (aes) ver. 1.9B Release Date: 7/18/93 License ID 1202 Analysis prepared by: HUITT-ZOLLARS, INC. 15101 RED HILL AVENUE TUSTIN, CALIFORNIA 92780-6500 PHONE (714) 259-7900 * FAX (714) 259-0210 ---------------------------------------------------------------------------- FILE NAME: FECNLCXX.DAT TIME/DATE OF STUDY: 13:38 5/ 3/2004 ---------------------------------------------------------------------------- ---------------------------------------------------------------------------- USER SPECIFIED HYDROLOGY AND HYDRAULIC MODEL INFORMATION: ---------------------------------------------------------------------------- ---------------------------------------------------------------------------- *TIME-OF-CONCENTRATION MODEL?° -- USER SPECIFIED STORM EVENT(YEAR) = 100.00 SPECIFIED MINIMUM PIPE SIZE(INCH) = 18.00 SPECIFIED PERCENT OF GRADIENTS(DECIMAL) TO USE FOR FRICTION SLOPE = .95 *USER -DEFINED LOGARITHMIC INTERPOLATION USED FOR RAINFALL* 10-YEAR STORM 60-MINUTE INTENSITY(INCH/HOUR) _ .920 100-YEAR STORM 60-MINUTE INTENSITY(INCH/HOUR) = 1.340 COMPUTED RAINFALL INTENSITY DATA: STORM EVENT = 100.00 1-HOUR INTENSITY(INCH/HOUR) = 1.3400 SLOPE OF INTENSITY DURATION CURVE = .6000 ..::?r �•?:?: ?:?:?c*?c*?c?r?c?c*?t �?c?c**?t?c?:**::?r�YsY*�Y?r?c*?:*R•*?::c:.c�"?: �"�?v?r?r?r �?r�'.r� :ram � :e:Y?r'..' �?c?r?r?r k?:?cir?c?r?r FLOW PROCESS FROM NODE 103.00 TO NODE 103.01 IS CODE = 2.1 ---------------------------------------------------------------------------- »»>RATIONAL METHOD INITIAL SUBAREA ANALYSIS««< NATURAL POOR COVER TC = K*[(LENGTH** 3.00)/(ELEVATION CHANGE)]** .20 INITIAL SUBAREA FLOW-LENGTH(FEET) = 260.00 UPSTREAM ELEVATION(FEET) = 1110.00 DOWNSTREAM ELEVATION(FEET) = 1105.00 ELEVATION DIFFERENCE(FEET) = 5.00 TC(MIN.) = .525*[( 260.00** 3.00)/( 5.00)]** .20 = 10.699 100 YEAR RAINFALL INTENSITY(INCH/HR) = 3.770 SOIL CLASSIFICATION IS "A" NATURAL POOR COVER "BARREN" SUBAREA LOSS RATE, FM(INCH/HR) = .4100 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) _ .41 SUBAREA PERVIOUS AREA FRACTION, Ap = 1.00 SUBAREA RUNOFF(CFS) = 7.56 TOTAL AREA(ACRES) = 2.50 PEAK FLOW RATE(CFS) = 7.56 ?: *?cR•?r?r?c ?r R•?: ?c'..•4e*?r ?c ?r?: *?r*?c?c?: it ?c?r*?t ?c �Y* �•?: ?c?c *fr ?r*?c ?c ?:?e?: *?:?: is ?c ?c ?.•?: *?c ?c ?c*?c ?r?: ?: ?::: **?r4;'.c�•ir ?r i;?c?; �• FLOW PROCESS FROM NODE 103.01 TO NODE 103.02 IS CODE = 5.1 ---------------------------------------------------------------------------- »»>COMPUTE TRAPEZOIDAL CHANNEL FLOW««< »»>TRAVELTIME THRU SUBAREA««< ---------------------------------------------------------------------------- ---------------------------------------------------------------------------- UPSTREAM NODE ELEVATION = 1105.00 DOWNSTREAM NODE ELEVATION = 1095.00 CHANNEL LENGTH THRU SUBAREA(FEET) = 150.00 CHANNEL SLOPE _ .0667 Page 1 CHANNEL BASE(FEET) = 40.00 "Z" FACTOR = 99.990 MANNING'S FACTOR = .030 MAXIMUM DEPTH(FEET) _ .50 CHANNEL FLOW THRU SUBAREA(CFS) = 7.56 FLOW VELOCITY(FEET/SEC) = 2.17 FLOW DEPTH(FEET) _ .07 TRAVEL TIME(MIN.) = 1.15 TC(MIN.) = 11.85 k',t it icic�it it is ie it ie it it it is is is �Y it it it is is ie is is is it it it it it it it is is it is it is is is it is is it'h it it it is is is it is it it is is is is it it is it is ie it ie is is it it is it FLOW PROCESS FROM NODE 103.10 TO NODE 103.02 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 100 YEAR RAINFALL INTENSITY(INCH/HR) = 3.546 SOIL CLASSIFICATION IS "A" NATURAL POOR COVER "BARREN" SUBAREA LOSS RATE, Fm(INCH/HR) = .4100 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .41 SUBAREA PERVIOUS AREA FRACTION, Ap = 1.00 SUBAREA AREA(ACRES) = 1.90 SUBAREA RUNOFF(CFS) = 5.36 EFFECTIVE AREA(ACRES) = 4.40 AREA -AVERAGED FM(INCH/HR) _ .41 AREA -AVERAGED Fp(INCH/HR) _ .41 AREA -AVERAGED Ap = 1.00 TOTAL AREA(ACRES) = 4.40 PEAK FLOW RATE(CFS) = 12.42 TC(MIN) = 11.85 it i; is is it it ir:� i<it it it it � � it it is it it it is it � is is is is is irir it is is it it it it is it it it i; is it is it is is it is it it it is it is ie is sY is it is is � it is it it it it is it is is it FLOW PROCESS FROM NODE 103.02 TO NODE 103.01 IS CODE = 8 --------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 100 YEAR RAINFALL INTENSITY(INCH/HR) = 3.546 SOIL CLASSIFICATION IS "A" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0970 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .97 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 2.70 SUBAREA RUNOFF(CFS) = 8.38 EFFECTIVE AREA(ACRES) = 7.10 AREA -AVERAGED FM(INCH/HR) _ .29 AREA -AVERAGED Fp(INCH/HR) _ .44 AREA -AVERAGED Ap = .66 TOTAL AREA(ACRES) = 7.10 PEAK FLOW RATE(CFS) = 20.80 TC(MIN) = 11.85 i;.°k is it it sY �'c it it i::: it it it it is it � it is is is � it is i; is it sY is 'k it ili; it � it it it it it it it is � � i; is icdc is it is it it it it it i; a � �• i<ic it � is it it is is is i; is is FLOW PROCESS FROM NODE 103.02 TO NODE 103.11 IS CODE = 3 ---------------------------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< ------------------------------------------------------------------- DEPTH OF FLOW IN 27.0 INCH PIPE IS 17.6 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 7.6 UPSTREAM NODE ELEVATION(FEET) = 1087.80 DOWNSTREAM NODE ELEVATION(FEET) = 1076.33 FLOW LENGTH(FEET) = 1400.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 27.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 20.80 TRAVEL TIME(MIN.) = 3.09 TC(MIN.) = 14.93 is it'..•x is is it it ir�ki;;:�i:�•�i; it k it it i;�:;:r ie it s;�'ir'.c�•ir it ir��•ir sY7e irsY'.ci;ie:: Br Xir it it„�i: is ic�ir X is it it is is ir�it'.r it is it it it sic FLOW PROCESS FROM NODE 103.30 TO NODE 103.11 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 100 YEAR RAINFALL INTENSITY(INCH/HR) = 3.087 SOIL CLASSIFICATION IS "B" RESIDENTIAL-> 5-7 DWELLINGS/ACRE SUBAREA LOSS RATE, Fm(INCH/HR) = .3750 Page 2 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .50 SUBAREA AREA(ACRES) = 7.90 SUBAREA RUNOFF(CFS) = 19.28 EFFECTIVE AREA(ACRES) = 15.00 AREA -AVERAGED FM(INCH/HR) _ .34 AREA -AVERAGED Fp(INCH/HR) = .58 AREA -AVERAGED Ap = .57 TOTAL AREA(ACRES) = 15.00 PEAK FLOW RATE(CFS) = 37.15 TC(MIN) = 14.93 it it sY is it iti;*ic it it is ie ie it is is it ie it ie s4 ie is ie ie it it is it ie ie sY it ie ie it is sl-*ie ie ie ie ie it it sY ie is ie it ie is ie ie*ie it s: it it it it sY is it is ie it ie ie it it it ie FLOW PROCESS FROM NODE 116.10 TO NODE 103.11 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< ---------------------------------------------------------------------------- ---------------------------------------------------------------------------- 100 YEAR RAINFALL INTENSITY(INCH/HR) = 3.087 SOIL CLASSIFICATION IS "A" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0970 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .97 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 2.70 SUBAREA RUNOFF(CFS) = 7.26 EFFECTIVE AREA(ACRES) = 17.70 AREA -AVERAGED FM(INCH/HR) _ .30 AREA -AVERAGED Fp(INCH/HR) = .60 AREA -AVERAGED Ap = .50 TOTAL AREA(ACRES) = 17.70 PEAK FLOW RATE(CFS) = 44.41 TC(MIN) = 14.93 is is it it is it it is**its: sY it sY it it*i: sY it sY sY#***sY�•sY it it*ic is is ir:�sY is sY it is is sY it it ie ie*i.•it**it it*ic**ic **:.t i:**ir it is it it is is ic* FLOW PROCESS FROM NODE 103.11 TO NODE 103.11 IS CODE = 10 ---------------------------------------------------------------------------- »»>MAIN-STREAM MEMORY COPIED ONTO MEMORY BANK # 1 ««< ---------------------------------------------------------------------------- ---------------------------------------------------------------------------- is it is is is sc is*kits:ir'.e'.: it is it ie'.r it �•ir**�•ir it is it it it ir**kir it is it it*ir is it k it is it*k*�*4t is it is k ie�ir is ie it it it it ie it �'e it it it it �t� FLOW PROCESS FROM NODE 109.00 TO NODE 109.01 IS CODE = 2.1 ---------------------------------------------------------------------------- »»>RATIONAL METHOD INITIAL SUBAREA ANALYSIS««< DEVELOPMENT IS COMMERCIAL TC = K*E(LENGTH** 3.00)/(ELEVATION CHANGE)]** .20 INITIAL SUBAREA FLOW-LENGTH(FEET) = 900.00 UPSTREAM ELEVATION(FEET) = 1098.00 DOWNSTREAM ELEVATION(FEET) = 1091.00 ELEVATION DIFFERENCE(FEET) = 7.00 TC(MIN.) = .304*E( 900.00** 3.00)/( 7.00)1** .20 = 12.201 100 YEAR RAINFALL INTENSITY(INCH/HR) = 3.485 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA RUNOFF(CFS) = 26.70 TOTAL AREA(ACRES) = 8.70 PEAK FLOW RATE(CFS) = 26.70 ici:*ir it i.•i;i:i:iri: it it it*it*i:-kie***it*it it it ir*�•'x*ie it is it it*it it it it ie i:i: it is �•i: is it R•ir it sY*ic**ir is is*ic*ic is :; it is it it it ie it FLOW PROCESS FROM NODE 112.00 TO NODE 109.01 IS CODE 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< ---------------------------------------------------------------------------- 100 YEAR RAINFALL INTENSITY(INCH/HR) = 3.485 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 1.10 SUBAREA RUNOFF(CFS) = 3.38 Page 3 EFFECTIVE AREA(ACRES) = 9.80 AREA -AVERAGED Fp(INCH/HR) _ .75 TOTAL AREA(ACRES) _ 9.80 TC(MIN) = 12.20 AREA -AVERAGED Fm(INCH/HR) _ .08 AREA -AVERAGED Ap = .10 PEAK FLOW RATE(CFS) = 30.07 is is is sY is it is is is is icic Erie ie it ie it it icir ie is & it is is it it is is it is is is is it is it it it is is is is it is it iririr it is it it is it it it it is is �; it it it is t is is it is is it it is FLOW PROCESS FROM NODE 115.10 TO NODE 109.01 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 100 YEAR RAINFALL INTENSITY(INCH/HR) = 3.485 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 1.07 SUBAREA RUNOFF(CFS) = 3.28 EFFECTIVE AREA(ACRES) = 10.87 AREA -AVERAGED Fm(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 10.87 PEAK FLOW RATE(CFS) = 33.36 TC(MIN) = 12.20 iei:isiriritiri:icki::Yieiciriricirit�'r�ic�i;iciciricieiricicici:i<icic�i;iricieie4:•iririciciri:icisiei;iciricsY'.citXicic'.cisisi;itieisitisitititis FLOW PROCESS FROM NODE 109.01 TO NODE 116.01 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< -------------------------------------------------------------------- DEPTH OF FLOW IN 36.0 INCH PIPE IS 25.2 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 6.3 UPSTREAM NODE ELEVATION(FEET) = 1080.70 DOWNSTREAM NODE ELEVATION(FEET) = 1079.80 FLOW LENGTH(FEET) = 240.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 36.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 33.36 TRAVEL TIME(MIN.) _ .63 TC(MIN.) = 12.84 ici;�': iric�•icieiri:iciciriririti:ieiciciriciritiriri:iciri;i;icicicieicicicitiririci;irirsYiricirxirirsYiciciricici;i::Yitieiciricitici;iririti:i<icic FLOW PROCESS FROM NODE 116.01 TO NODE 110.01 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< >>>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< --------------------------------------________________________ DEPTH OF FLOW IN 36.0 INCH PIPE IS 24.4 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 6.5 UPSTREAM NODE ELEVATION(FEET) = 1079.80 DOWNSTREAM NODE ELEVATION(FEET) = 1078.45 FLOW LENGTH(FEET) = 330.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 36.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 33.36 TRAVEL TIME(MIN.) _ .84 TC(MIN.) = 13.68 .,...,i:i: is it is it it it it is is it�:Y it is is k k it ir�i; is it is i;�•�ir is it is i;i; is is is ie it fir is is is ie is i:i:iri: is is irir�i: i; it �..•ir is ir�it is it is �:r kir is FLOW PROCESS FROM NODE 110.00 TO NODE 110.01 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 100 YEAR RAINFALL INTENSITY (INCH/HR) = 3.254 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 Page 4 SUBAREA AREA(ACRES) = 11.40 SUBAREA RUNOFF(CFS) = 32.62 EFFECTIVE AREA(ACRES) = 22.27 AREA -AVERAGED FM(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 22.27 PEAK FLOW RATE(CFS) = 63.72 TC(MIN) = 13.68 FLOW PROCESS FROM NODE 113.00 TO NODE 110.01 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 100 YEAR RAINFALL INTENSITY(INCH/HR) = 3.254 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 1.08 SUBAREA RUNOFF(CFS) = 3.09 EFFECTIVE AREA(ACRES) = 23.35 AREA -AVERAGED Fm(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 23.35 PEAK FLOW RATE(CFS) = 66.81 TC(MIN) = 13.68 is ««««ic is «« �• it ««it «««««ic irk is «it ««dt «k is «ic «««««« ««««k ««««««««««««k ««« ««ic «« ««ir ««irk «ic is « FLOW PROCESS FROM NODE 118.00 TO NODE 110.01 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 100 YEAR RAINFALL INTENSITY(INCH/HR) = 3.254 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 1.08 SUBAREA RUNOFF(CFS) = 3.09 EFFECTIVE AREA(ACRES) = 24.43 AREA -AVERAGED Fm(INCH/HR) _ .07 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) 24.43 PEAK FLOW RATE(CFS) = 69.90 TC(MIN) = 13.68 FLOW PROCESS FROM NODE 110.01 TO NODE 103.11 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 45.0 INCH PIPE IS 34.3 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 7.7 UPSTREAM NODE ELEVATION(FEET) = 1078.45 DOWNSTREAM NODE ELEVATION(FEET) = 1076.33 FLOW LENGTH(FEET) = 520.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 45.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 69.90 TRAVEL TIME(MIN.) = 1.12 TC(MIN.) = 14.80 «ic « �' ««irk �' «kit is « « « «« �• :: it «««««« ««««««ir «ic::.« «k ««« «ir «««««««ic «««««k �..• k ««ir «««it «ic «:: i.• ««« FLOW PROCESS FROM NODE 103.11 TO NODE 103.11 IS CODE = 1 ---------------------------------------------------------------------------- »»>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< ------------------------------------------------------------------=-- TOTAL NUMBER OF STREAMS = 2 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 1 ARE: TIME OF CONCENTRATION(MIN.) = 14.80 Page 5 RAINFALL INTENSITY(INCH/HR) = 3.10 AREA -AVERAGED FM(INCH/HR) = .07 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 EFFECTIVE STREAM AREA(ACRES) = 24.43 TOTAL STREAM AREA(ACRES) = 24.43 PEAK FLOW RATE(CFS) AT CONFLUENCE = 69.90 .iris it is is is ie it it it it it ie ie ie ie it it ie is is it ie it ie it it it is �r it it it �t ie it ie is it it ie ie is ie it it it it*ie it it it is it it it ie it it it ie ie it is it iris is it it is ie it it is FLOW PROCESS FROM NODE 104.00 TO NODE 104.01 IS CODE = 2.1 ----------------------------------------- >>>RATIONAL METHOD INITIAL SUBAREA ANALYSIS««< ------------------------------------------------------------------------- DEVELOPMENT IS COMMERCIAL TC = K*E(LENGTH** 3. 00)/ (ELEVATION CHANGE)]** .20 INITIAL SUBAREA FLOW-LENGTH(FEET) = 520.00 UPSTREAM ELEVATION(FEET) = 1130.00 DOWNSTREAM ELEVATION(FEET) = 1110.00 ELEVATION DIFFERENCE(FEET) = 20.00 TC(MIN.) = .304*E( 520.00** 3.00)/( 20.00)]** .20 = 7.117 100 YEAR RAINFALL INTENSITY(INCH/HR) = 4.815 SOIL CLASSIFICATION IS "A" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0970 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .97 SUBAREA PERVIOUS AREA FRACTION, Ap .10 SUBAREA RUNOFF(CFS) = 4.03 TOTAL AREA(ACRES) = .95 PEAK FLOW RATE(CFS) = 4.03 : it it*i:':**::*ir it it i:'•*i:i: it ie ie it'•iri:*ie it is *i: it is it is it *k $c is ie ie icy*�•� ksY is*�•'.r it it ie i:ic*ir *i.•ir it *ic it is is it it it :: is*ir FLOW PROCESS FROM NODE 104.01 TO NODE 103.11 IS CODE = 6 ---------------------------------------------------------------------------- »»>COMPUTE STREET FLOW TRAVEL TIME THRU SUBAREA««< UPSTREAM ELEVATION(FEET) = 1110.00 DOWNSTREAM ELEVATION(FEET) = 1088.00 STREET LENGTH(FEET) = 690.00 CURB HEIGHT(INCHES) = 8. STREET HALFWIDTH(FEET) = 51.00 DISTANCE FROM CROWN TO CROSSFALL GRADEBREAK(FEET) = 37.00 INTERIOR STREET CROSSFALL(DECIMAL) = .020 OUTSIDE STREET CROSSFALL(DECIMAL) = .020 SPECIFIED NUMBER OF HALFSTREETS CARRYING RUNOFF = 1 "TRAVEL TIME COMPUTED USING MEAN FLOW(CFS) = 4.03 STREET FLOW MODEL RESULTS: STREET FLOW DEPTH(FEET) _ .34 HALFSTREET FLOOD WIDTH(FEET) = 9.27 AVERAGE FLOW VELOCITY(FEET/SEC.) = 3.84 PRODUCT OF DEPTH&VELOCITY = 1.32 STREET FLOW TRAVEL TIME(MIN.) = 2.99 TC(MIN.) = 10.11 100 YEAR RAINFALL INTENSITY(INCH/HR) = 3.901 SOIL CLASSIFICATION IS "A" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0970 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .97 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = .00 SUBAREA RUNOFF(CFS) _ .00 EFFECTIVE AREA(ACRES) _ .95 AREA -AVERAGED FM(INCH/HR) _ .10 AREA -AVERAGED Fp(INCH/HR) _ .97 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = .95 PEAK FLOW RATE(CFS) = 4.03 END OF SUBAREA STREET FLOW HYDRAULICS: DEPTH(FEET) = .34 HALFSTREET FLOOD WIDTH(FEET) = 9.27 FLOW VELOCITY(FEET/SEC.) = 3.84 DEPTH*VELOCITY = 1.32 Page 6 k fe k 4e dr iek kie it 4e k fckkkkkkkkkkkkkitkkkkkkkkkkk�: irkkkkkkic iekkkirkkkkkickkkit irkkkickkkkirkkkk FLOW PROCESS FROM NODE 105.00 TO NODE 103.11 IS CODE = 8 ----------------------------------------- >>>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 100 YEAR RAINFALL INTENSITY(INCH/HR) = 3.901 SOIL CLASSIFICATION IS "A" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0970 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .97 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = .95 SUBAREA RUNOFF(CFS) = 3.25 EFFECTIVE AREA(ACRES) = 1.90 AREA -AVERAGED Fm(INCH/HR) _ .10 AREA -AVERAGED Fp(INCH/HR) _ .97 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 1.90 PEAK FLOW RATE(CFS) = 6.51 TC(MIN) = 10.11 :: ': kkkkkkkkkkkkkkkkkkickkkkkick k�kkkkkkkkkk'.ck kirkkkkkkkkkkkkkk4r irk it it 4ck ::k it 9rkirkkkk FLOW PROCESS FROM NODE 113.10 TO NODE 103.11 IS CODE _ 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 100 YEAR RAINFALL INTENSITY(INCH/HR) = 3.901 SOIL CLASSIFICATION IS "A" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0970 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .97 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 1.38 SUBAREA RUNOFF(CFS) = 4.72 EFFECTIVE AREA(ACRES) = 3.28 AREA -AVERAGED FM(INCH/HR) _ .10 AREA -AVERAGED Fp(INCH/HR) _ .97 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 3.28 PEAK FLOW RATE(CFS) = 11.23 TC(MIN) = 10.11 kkk:r'.rk::..:t kirk k'......;:c �k.4r ick 4rk k:rkk��k�kk kk...:k�k�kkkkkitk�&k.:kk �•k �: :. R•kkkkk�' ':r�k�k'.. :rk FLOW PROCESS FROM NODE 103.11 TO NODE 103.11 IS CODE = 1 »»>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< »»>AND COMPUTE VARIOUS CONFLUENCED STREAM VALUES««< TOTAL NUMBER OF STREAMS = 2 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 2 ARE: TIME OF CONCENTRATION(MIN.) = 10.11 RAINFALL INTENSITY(INCH/HR) = 3.90 AREA -AVERAGED Fm(INCH/HR) = .10 AREA -AVERAGED Fp(INCH/HR) = .97 AREA -AVERAGED Ap = .10 EFFECTIVE STREAM AREA(ACRES) = 3.28 TOTAL STREAM AREA(ACRES) = 3.28 PEAK FLOW RATE(CFS) AT CONFLUENCE = 11.23 RAINFALL INTENSITY AND TIME OF CONCENTRATION RATIO CONFLUENCE FORMULA USED FOR 2 STREAMS. kk PEAK FLOW RATE TABLE kk Q Tc Intensity Fp Ap Fm Ae (CFS) (MIN.) (INCH/HR) (INCH/HR) (INCH/HR) (ACRES) 1 78.77 14.80 3.104 .78 .10 .08 27.71 2 71.55 10.11 3.901 .79 .10 .08 19.97 COMPUTED CONFLUENCE ESTIMATES ARE AS FOLLOWS: PEAK FLOW RATE(CFS) = 78.77 TC(MIN.) = 14.796 EFFECTIVE AREA(ACRES) = 27.71 AREA -AVERAGED FM(INCH/HR) _ .08 Page 7 AREA -AVERAGED Fp(INCH/HR) = .78 AREA -AVERAGED Ap .10 TOTAL AREA(ACRES) = 27.71 icir4eir4eieieic*iciric*iriririr4r�4ir4coYii4e4cirieiticie�c�4ir4c�Ykk4r*.4eieitiricie4eYeYrlrfriciricdcicief:isirirfriekirkicirdc4:ieirie'lcirieic FLOW PROCESS FROM NODE 103.11 TO NODE 103.11 IS CODE = 11 ---------------------------------------------------------------------------- »»>CONFLUENCE MEMORY BANK # 1 WITH THE MAIN -STREAM MEMORY««< ---------------------------------------------------------------------------- ---------------------------------------------------------------------------- ** PEAK FLOW RATE TABLE ** Q Tc Intensit FP Ap Fm Ae (CFS) (MIN.) (INCH/HR� (INCH/HR) (INCH/HR) (ACRES) 1 110.39 10.11 3.901 .64 .25 .16 31.95 2 123.04 14.80 3.104 .64 .26 .16 45.25 3 122.74 14.93 3.087 .64 .26 .16 45.41 TOTAL AREA = 45.41 COMPUTED CONFLUENCE ESTIMATES ARE AS FOLLOWS: PEAK FLOW RATE(CFS) = 123.04 TC(MIN.) = 14.796 EFFECTIVE AREA(ACRES) = 45.25 AREA -AVERAGED FM(INCH/HR) _ .16 AREA -AVERAGED Fp(INCH/HR) _ .64 AREA -AVERAGED Ap = .26 TOTAL AREA(ACRES) = 45.41 is is �•:c*i:***fit ic:c is ir*it 4r it ir*ic it it it it**�c�qc*'c is 4r ie 4r 4r it it is it is it �•**ic it is sY sY ic:r is is it*�'c'.: :c**i:**ic is is it is it*4r it �: is FLOW PROCESS FROM NODE 103.11 TO NODE 103.11 IS CODE = 12 ---------------------------------------------------------------------------- »»>CLEAR MEMORY BANK # 1 ««< ---------------------------------------------------------------------------- ---------------------------------------------------------------------------- .` �•i:'c:::r.k*:rp:*�•�•:r'.:4r::***4r ie fc��ir*�•fr****�•*ic is it it it it*:r �e ir::ir'..•i:ir�•sY�•ir it ie is Sc*k**ir is is �•***�•:c**�•*�•'.: FLOW PROCESS FROM NODE 103.11 TO NODE 117.01 IS CODE = 3 ---------------------------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< ---------------------------------------------------------------------------- ---------------------------------------------------------------------------- DEPTH OF FLOW IN 54.0 INCH PIPE IS 43.3 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 9.0 UPSTREAM NODE ELEVATION(FEET) = 1076.33 DOWNSTREAM NODE ELEVATION(FEET) = 1075.90 FLOW LENGTH(FEET) = 100.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 54.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 123.04 TRAVEL TIME(MIN.) _ .19 TC(MIN.) = 14.98 ---------------------------------------------------------------------------- ---------------------------------------------------------------------------- END OF STUDY SUMMARY: TOTAL AREA(ACRES) = 45.41 TC(MIN.) = 14.98 EFFECTIVE AREA(ACRES) = 45.25 AREA -AVERAGED Fm(INCH/HR)= .16 AREA -AVERAGED Fp(INCH/HR) _ .64 AREA -AVERAGED Ap = .26 PEAK FLOW RATE(CFS) = 123.04 PEAK FLOW RATE TABLE ** Q Tc Intensit Fp Ap Fm Ae (CFS) (MIN.) (INCH/HR� (INCH/HR) (INCH/HR) (ACRES) 1 110.39 10.30 3.858 .64 .25 .16 31.95 2 123.04 14.98 3.081 .64 .26 .16 45.25 3 122.74 15.12 3.064 .64 .26 .16 ---------------------------------------------------------------------------- ---------------------------------------------------------------------------- 45.41 ---------------------------------------------------------------------------- ---------------------------------------------------------------------------- END OF RATIONAL METHOD ANALYSIS Page 8 Technical Appendix B 25-Year Rational Method Analysis Derived from Master Hydrology Study for Empire Center Lines A, B, & C Hall & Foreman, Inc — January 28, 1992 iriricir8ciririririririe(riririririeiricicirici:nisi:irieirXirieiriri;issY4riririeiririririeieitieiririritirsYsYi;.iesYi:iririririeieiririririririeirir RATIONAL METHOD HYDROLOGY COMPUTER PROGRAM PACKAGE (Reference: 1986 SAN BERNARDINO CO. HYDROLOGY CRITERION) (c) Copyright 1983-93 Advanced Engineering Software (aes) Ver. 1.9B Release Date: 7/18/93 License ID 1202 Analysis prepared by: HUITT-ZOLLARS, INC. 15101 RED HILL AVENUE TUSTIN, CALIFORNIA 92780-6500 PHONE (714) 259-7900 * FAX (714) 259-0210 ------------------------------------------------------ FILE NAME: FECNLB25.DAT TIME/DATE OF STUDY: 12:58 6/14/2004 USER SPECIFIED HYDROLOGY AND HYDRAULIC MODEL INFORMATION: --*TIME-OF-CONCENTRATION MODEL* -- USER SPECIFIED STORM EVENT(YEAR) = 25.00 SPECIFIED MINIMUM PIPE SIZE(INCH) = 18.00 SPECIFIED PERCENT OF GRADIENTS (DECIMAL) TO USE FOR FRICTION SLOPE = .95 *USER -DEFINED LOGARITHMIC INTERPOLATION USED FOR RAINFALL* 10-YEAR STORM 60-MINUTE INTENSITY(INCH/HOUR) .920 100-YEAR STORM 60-MINUTE INTENSITY(INCH/HOUR) = 1.340 COMPUTED RAINFALL INTENSITY DATA: STORM EVENT = 25.00 1-HOUR INTENSITY(INCH/HOUR) = 1.0659 SLOPE OF INTENSITY DURATION CURVE = .6000 is*�•ir it is is*iri:*it it it it it*ir*ir is ir-k it it it i;ie*iri:ici:iri: is it*ir is i; it is it is it it ic. ie 4r*ir is ir°k it it*it*ir it i;*i: *ic is it *ir is it is is is FLOW PROCESS FROM NODE 100.00 TO NODE 100.01 IS CODE = 2.1 --------------------------------------------- >>>RATIONAL METHOD INITIAL SUBAREA ANALYSIS««< NATURAL POOR COVER TC = K*[(LENGTH** 3. 00) /(ELEVATION CHANGE)]** .20 INITIAL SUBAREA FLOW-LENGTH(FEET) = 500.00 UPSTREAM ELEVATION(FEET) = 1111.00 DOWNSTREAM ELEVATION(FEET) = 1102.00 ELEVATION DIFFERENCE(FEET) = 9.00 TC(MIN.) = .525*[( 500.00** 3.00)/( 9.00)]** .20 = 14.083 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.543 SOIL CLASSIFICATION IS "B" NATURAL POOR COVER "BARREN" SUBAREA LOSS RATE, Fm(INCH/HR) = .2700 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) _ .27 SUBAREA PERVIOUS AREA FRACTION, Ap = 1.00 SUBAREA RUNOFF(CFS) = 8.08 TOTAL AREA(ACRES) = 3.95 PEAK FLOW RATE(CFS) = 8.08 is is 4r'.:i: �•i;ir*iri:*ir is is is it it is*i; Xir it is it it it i; is ir',t*iris*i.•*ir it it it �•&'.:iti: is it �•*ic**ir it*ir°k it i:i:ir**�-. is 4: it it*ir it it k it FLOW PROCESS FROM NODE 100.01 TO NODE 100.01 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.543 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 Page 1 SUBAREA AREA(ACRES) = 2.95 SUBAREA RUNOFF(CFS) = 6.55 EFFECTIVE AREA(ACRES) = 6.90 AREA -AVERAGED Fm(INCH/HR) _ .19 AREA -AVERAGED Fp(INCH/HR) _ .30 AREA -AVERAGED Ap = .62 TOTAL AREA(ACRES) = 6.90 PEAK FLOW RATE(CFS) = 14.63 TC(MIN) = 14.08 ie it ie sY ie is is it it i; it i; it ie sY ie s: it it it is it ie ie � it it it sY ie ie i; it it ir'k is it it it it * ie i; ie it ie it it ie it it i; ie ie is * it « ie it ie it ir. it it ie ie it is ie ie i; it it i; FLOW PROCESS FROM NODE 100.01 TO NODE 101.01 IS CODE = 3 ---------------------------------------------------------------------------- >>>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< >USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< ---------------------------------------------------------------------------- DEPTH OF FLOW IN 27.0 INCH PIPE IS 19.8 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 4.7 UPSTREAM NODE ELEVATION(FEET) = 1088.40 DOWNSTREAM NODE ELEVATION(FEET) = 1087.00 FLOW LENGTH(FEET) = 470.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 27.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 14.63 TRAVEL TIME(MIN.) = 1.67 TC(MIN.) = 15.76 is it it it it i;i:i;i: it it i;i.•ic ie it �•i:ir�•ic*.*ic*-k it ie i.•i:ici:�ir it ie it it sY it it ie i:ir�-ir ie is it ie it it it it is ie ie ie:k*ie ie is i; is***ir it it ie is i.•*it FLOW PROCESS FROM NODE 101.01 TO NODE 101.01 IS CODE = 1 ---------------------------------------------------------------------------- »»>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< ---------------------------------------------------------------------------- ---------------------------------------------------------------------------- TOTAL NUMBER OF STREAMS = 2 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 1 ARE: TIME OF CONCENTRATION(MIN.) = 15.76 RAINFALL INTENSITY(INCH/HR) = 2.38 AREA -AVERAGED Fm(INCH/HR) = .19 AREA -AVERAGED Fp(INCH/HR) = .30 AREA -AVERAGED Ap = .62 EFFECTIVE STREAM AREA(ACRES) = 6.90 TOTAL STREAM AREA(ACRES) = 6.90 PEAK FLOW RATE(CFS) AT CONFLUENCE = 14.63 is it it it it it it is sir*i:i:i:ir*.*ir it ie i:';sY�*ic iz**::.*�*'.e�i;�ie it ir�ic is *ir is �•*ir*sir ie it k**ie**fir ir�'�•'..•'.; is is it it*�'�i: :Y FLOW PROCESS FROM NODE 102.00 TO NODE 102.01 IS CODE = 2.1 ---------------------------------------------------------------------------- »»>RATIONAL METHOD INITIAL SUBAREA ANALYSIS««< ---------------------------------------------------------------------------- ---------------------------------------------------------------------------- NATURAL POOR COVER TC = K*[(LENGTH** 3.00)/(ELEVATION CHANGE)]** .20 INITIAL SUBAREA FLOW-LENGTH(FEET) = 550.00 UPSTREAM ELEVATION(FEET) = 1111.00 DOWNSTREAM ELEVATION(FEET) = 1103.00 ELEVATION DIFFERENCE(FEET) = 8.00 TC(MIN.) = .525*[( 550.00** 3.00)/( 8.00)]** .20 = 15.267 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.423 SOIL CLASSIFICATION IS "B" NATURAL POOR COVER "BARREN" SUBAREA LOSS RATE, FM(INCH/HR) = .2700 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) _ .27 SUBAREA PERVIOUS AREA FRACTION, Ap = 1.00 SUBAREA RUNOFF(CFS) = 9.49 TOTAL AREA(ACRES) = 4.90 PEAK FLOW RATE(CFS) = 9.49 it it it it is is �k'.c**ir is it*ir**it it it*ir ie it is ie it*ir ie*ir is is it it ie it ie i:ir****ir it ir*ici;*ie is iris it i:ic°ki:ic *ir is is �k*i: it it is it it irYr FLOW PROCESS FROM NODE 102.01 TO NODE 102.01 IS CODE = 8 ----------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< Page 2 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.423 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 4.80 SUBAREA RUNOFF(CFS) = 10.14 EFFECTIVE AREA(ACRES) = 9.70 AREA -AVERAGED FM(INCH/HR) _ .17 AREA -AVERAGED Fp(INCH/HR) _ .31 AREA -AVERAGED Ap = .55 TOTAL AREA(ACRES) = 9.70 PEAK FLOW RATE(CFS) = 19.64 TC(MIN) = 15.27 is 9r'::r ie it sY 4v:Y�&&it ie k4:&:cir'.t'r:r 4t k k is it it is ie �4 isit it �r 9r sY ie it is it it'.c is it it is it �c it f:4r it 4c irir it it 4t is fr it is ;t it ie�'.t is fc St :r �dc 4e 4r FLOW PROCESS FROM NODE 102.01 TO NODE 101.01 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 30.0 INCH PIPE IS 23.2 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 4.8 UPSTREAM NODE ELEVATION(FEET) = 1088.60 DOWNSTREAM NODE ELEVATION(FEET) = 1087.00 FLOW LENGTH(FEET) = 590.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 30.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 19.64 TRAVEL TIME(MIN.) = 2.04 TC(MIN.) = 17.31 it k'r'.e'.e kir ir��4r k &ie itX� :r it is ir4r it kse �'t ie ft it is ir�it kic it d: ie is ie is �'rir:r it 4e it Yr �r it:r:: ie it it:Y°k ie it irk&ic it it k&it'.cic 4r ie Y it it is FLOW PROCESS FROM NODE 101.00 TO NODE 101.01 IS CODE = 8 w ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.247 SOIL CLASSIFICATION IS "B" NATURAL POOR COVER "BARREN" SUBAREA LOSS RATE, FM(INCH/HR) = .2700 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) _ .27 SUBAREA PERVIOUS AREA FRACTION, Ap = 1.00 SUBAREA AREA(ACRES) = 3.50 SUBAREA RUNOFF(CFS) 6.23 EFFECTIVE AREA(ACRES) = 13.20 AREA -AVERAGED FM(INCH/HR) _ .20 AREA -AVERAGED Fp(INCH/HR) = .30 AREA -AVERAGED Ap = .67 TOTAL AREA(ACRES) = 13.20 PEAK FLOW RATE(CFS) = 24.33 TC(MIN) = 17.31 i:fir �c it :e k:: �-ir ir�'.ri: it ir'k fit it Yc it 4r:t it ie it 4c is it it it it��e'k sY is �Y 4c it 4r it k it ie',t is it k is it wit it irti&�:r fir is kie lr sY �'r it is :e i.•4r 9r fe FLOW PROCESS FROM NODE 101.01 TO NODE 101.01 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.247 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 3.90 SUBAREA RUNOFF(CFS) = 7.63 EFFECTIVE AREA(ACRES) = 17.10 AREA -AVERAGED FM(INCH/HR) _ .17 AREA -AVERAGED Fp(INCH/HR) = .32 AREA -AVERAGED Ap = .54 TOTAL AREA(ACRES) = 17.10 PEAK FLOW RATE(CFS) = 31.96 TC(MIN) = 17.31 .. «•ie is �: 4r is is Yr 4r sY�°k �Y is ie�'e 4r is it it is icx �4 dt i:.f:ies:�4e is �Y it 4t°k �fe 4c is is is it 4r 4:i: it�irx is it �Y 4c it lt it dr �rir �'r 4c pie it 4t is is it ie ie ie de �4 FLOW PROCESS FROM NODE 101.01 TO NODE 101.01 IS CODE = 1 Page 3 ---------------------------------------------------------------------------- >>>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< »»>AND COMPUTE VARIOUS CONFLUENCED STREAM VALUES««< ---------------------------------------------------------------------------- ---------------------------------------------------------------------------- TOTAL NUMBER OF STREAMS = 2 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 2 ARE: TIME OF CONCENTRATION(MIN.) = 17.31 RAINFALL INTENSITY(INCH/HR) = 2.25 AREA -AVERAGED FM(INCH/HR) = .17 AREA -AVERAGED Fp(INCH/HR) = .32 AREA -AVERAGED Ap = .54 EFFECTIVE STREAM AREA(ACRES) = 17.10 TOTAL STREAM AREA(ACRES) = 17.10 PEAK FLOW RATE(CFS) AT CONFLUENCE = 31.96 RAINFALL INTENSITY AND TIME OF CONCENTRATION RATIO CONFLUENCE FORMULA USED FOR 2 STREAMS. PEAK FLOW RATE TABLE ** Q Tc Intensity Fp Ap Fm Ae (CFS) (MIN.) (INCH/HR) (INCH/HR) (INCH/HR) (ACRES) 1 45.55 15.76 2.378 .31 .56 .18 22.47 2 45.72 17.31 2.247 .31 .56 .18 24.00 COMPUTED CONFLUENCE ESTIMATES ARE AS FOLLOWS: PEAK FLOW RATE(CFS) = 45.72 TC(MIN.) = 17.306 EFFECTIVE AREA(ACRES) = 24.00 AREA -AVERAGED Fm(INCH/HR) _ .18 AREA -AVERAGED Fp(INCH/HR) _ .31 AREA -AVERAGED Ap = .56 TOTAL AREA(ACRES) = 24.00 - FLOW PROCESS FROM NODE 101.01 TO NODE 108.01 IS CODE = 3 ---------------------------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< ---------------------------------------------------------------------------- ---------------------------------------------------------------------------- DEPTH OF FLOW IN 39.0 INCH PIPE IS 26.7 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 7.5 UPSTREAM NODE ELEVATION(FEET) = 1087.00 DOWNSTREAM NODE ELEVATION(FEET) = 1079.70 FLOW LENGTH(FEET) = 1500.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 39.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 45.72 TRAVEL TIME(MIN.) = 3.31 TC(MIN.) = 20.62 i;9:ic�•i;::sY4:i: 4c�i:i:s4:;i:k�i:irf:Yi; is it it i:ic:c sti 4r'.r 4c 4:i:i: it it it it is it it i:i: k Yc is lt is '.: i; 4:4.•ir d: is&i; 4:� �*4c it it 4; i; i:i:��i:��ic FLOW PROCESS FROM NODE 108.00 TO NODE 108.01 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< ---------------------------------------------------------------------------- ---------------------------------------------------------------------------- 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.023 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 5.60 SUBAREA RUNOFF(CFS) = 9.82 EFFECTIVE AREA(ACRES) = 29.60 AREA -AVERAGED Fm(INCH/HR) _ .16 AREA -AVERAGED Fp(INCH/HR) = .33 AREA -AVERAGED Ap = .48 TOTAL AREA(ACRES) = 29.60 PEAK FLOW RATE(CFS) = 49.73 TC(MIN) = 20.62 4c?: �:c 4r': :': 4: �': 4; :r is i:.� �-f:i;i;:; 4r ir�i; ir��::s�:;'.;i;:c�•ir ir'.r it �'ri;iczY :; i:����:; i;�4r s4 i:�ki: ie �-�is �•i;�i: Y:&4; ��; :;'c :r it 4r is s; Page 4 FLOW PROCESS FROM NODE 111.10 TO NODE 108.01 IS CODE = 8 --------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.023 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 1.08 SUBAREA RUNOFF(CFS) = 1.89 EFFECTIVE AREA(ACRES) = 30.68 AREA -AVERAGED FM(INCH/HR) _ .15 AREA -AVERAGED Fp(INCH/HR) = .33 AREA -AVERAGED Ap = .46 TOTAL AREA(ACRES) = 30.68 PEAK FLOW RATE(CFS) = 51.62 TC(MIN) = 20.62 is it it it it it it it iv is it it is it it is it is it it is it is it it i; it is is it i; it it i; is is irie it it ie it is it it it kir it it it it it it it it it it it it is it it i; is i; is is it is is it it ir'k ie FLOW PROCESS FROM NODE 115.00 TO NODE 108.01 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< ---------------------------------------------------------------------------- ---------------------------------------------------------------------------- 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.023 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 1.23 SUBAREA RUNOFF(CFS) = 2.16 EFFECTIVE AREA(ACRES) = 31.91 AREA -AVERAGED FM(INCH/HR) _ .15 AREA -AVERAGED Fp(INCH/HR) = .34 AREA -AVERAGED Ap = .45 TOTAL AREA(ACRES) = 31.91 PEAK FLOW RATE(CFS) = 53.78 TC(MIN) = 20.62 PEAK FLOW RATE TABLE �* Q TC Intensity Fp Ap Fm Ae (CFS) (MIN.) (INCH/HR) (INCH/HR) (INCH/HR) (ACRES) 1 53.88 19.07 2.120 .34 .44 .15 30.38 2 53.78 20.62 2.023 .34 .45 .15 31.91 NEW PEAK FLOW DATA ARE: PEAK FLOW RATE(CFS) = 53.88 TC(MIN.) = 19.07 AREA -AVERAGED Fm(INCH/HR) = .15 AREA -AVERAGED Fp(INCH/HR) _ .34 AREA -AVERAGED Ap = .44 EFFECTIVE AREA(ACRES) = 30.38 �• �• :r �• :: it is is it i::Y it ie is is it � � is k is i::.r � ic'.r sY it is it � � it i; it ;:. � � is �• � is is it � i; is it � it it it it it it ie k i; is it �• it is i; is � it it is i; it it it :: is i; FLOW PROCESS FROM NODE 108.01 TO NODE 107.01 IS CODE = 3 ---------------------------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< ---------------------------------------------------------------------------- ---------------------------------------------------------------------------- DEPTH OF FLOW IN 33.0 INCH PIPE IS 23.7 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 11.8 UPSTREAM NODE ELEVATION(FEET) = 1079.70 DOWNSTREAM NODE ELEVATION(FEET) = 1075.90 FLOW LENGTH(FEET) = 260.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 33.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 53.88 TRAVEL TIME(MIN.) _ .37 TC(MIN.) = 19.44 is i; is is i; it i< i; it „ it it it it i; �• kit i; k is it is is i; it is is is is is it it is is it it is it it it it i; i; it it it is �Y is i; is it :: i; �k is it i,^sY is ie it it it it it it it it it it �• it'.r it FLOW PROCESS FROM NODE 107.00 TO NODE 107.01 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.096 Page 5 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 7.40 SUBAREA RUNOFF(CFS) = 13.46 EFFECTIVE AREA(ACRES) = 37.78 AREA -AVERAGED Fm(INCH/HR) _ .13 AREA -AVERAGED Fp(INCH/HR) = .36 AREA -AVERAGED Ap = .38 TOTAL AREA(ACRES) = 39.31 PEAK FLOW RATE(CFS) = 66.68 TC(MIN) = 19.44 ***Yc Yr Yr it Yt Yr Ye*ic it it Y:*Yr is is ie l:YrY: Yr Yc is*Ye Ye it it Yr Yc is Yc Ye***ic Yc Yc kic it it*Yt Yr is**&i:**Yt icYr*Yc it Yr Y:Yc is it it is ie ie it*Y: is Yr FLOW PROCESS FROM NODE 107.01 TO NODE 106.11 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 36.0 INCH PIPE IS 25.3 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 12.6 UPSTREAM NODE ELEVATION(FEET) = 1075.90 DOWNSTREAM NODE ELEVATION(FEET) = 1070.55 FLOW LENGTH(FEET) = 360.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 36.00 NUMBER OF PIPES 1 PIPE-FLOW(CFS) = 66.68 TRAVEL TIME(MIN.) _ .48 TC(MIN.) = 19.92 is it it Yr it Yr � * Yc * Yc is it Yc � is Yr Yr is ir* Ye * it * Yr.Ye Yc is Yc * Yc Yr is is is tY Yr Yr * iric Yt *Yt is *Ye it is Yr Yr Yc ie'k * it Yr Yc * is it Yt Yt Yr Yc is * Yc is Yt Yc is Yr s4 * FLOW PROCESS FROM NODE 106.11 TO NODE 106.11 IS CODE = 1 ---------------------------------------------------------------------------- >DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< TOTAL NUMBER OF STREAMS = 2 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 1 ARE: TIME OF CONCENTRATION(MIN.) = 19.92 RAINFALL INTENSITY(INCH/HR) = 2.07 AREA -AVERAGED FM(INCH/HR) = .13 AREA -AVERAGED Fp(INCH/HR) = .36 AREA -AVERAGED Ap = .38 EFFECTIVE STREAM AREA(ACRES) = 37.78 TOTAL STREAM AREA(ACRES) = 39.31 PEAK FLOW RATE(CFS) AT CONFLUENCE = 66.68 .. ., is it i�Yc Yc Yc �'.:'.r�Yc Yr is it**Yr�ic�ir Yc�Yr Yr*Yt Yr«ic Yr Y:Yt is is it*��Yt&'..•Yr��*Yc Yr Yt****it it�Yc«•� �Yr Yc is Yr**Yr Yt Y: is*ic is Y: FLOW PROCESS FROM NODE 106.00 TO NODE 106.01 IS CODE = 2.1 ---------------------------------------------------------------------------- »»>RATIONAL METHOD INITIAL SUBAREA ANALYSIS««< DEVELOPMENT IS COMMERCIAL TC = K*[(LENGTH** 3.00)/(ELEVATION CHANGE)]** .20 INITIAL SUBAREA FLOW-LENGTH(FEET) = 500.00 UPSTREAM ELEVATION(FEET) = 1098.00 DOWNSTREAM ELEVATION(FEET) = 1095.70 ELEVATION DIFFERENCE(FEET) = 2.30 TC(MIN.) = .304*[( 500.00** 3.00)/( 2.30)]** .20 = 10.713 25 YEAR RAINFALL INTENSITY (INCH/HR) = 2.997 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA RUNOFF(CFS) = 9.99 TOTAL AREA(ACRES) = 3.80 PEAK FLOW RATE(CFS) = 9.99 Page 6 i< fe fe fr fr is it is it it Eric i< i< fc is fr i< it it ie is fc * is fr is fr is is it fr it fcic ie is fe ie fe fe fe ie it fr i<ic fc is is fc i<ie fc fc it it is is is fc is fr i< is fc fr fe fe fr fc fe fc is it fr FLOW PROCESS FROM NODE 106.01 TO NODE 106.11 IS CODE = 3 ---------------------------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< >USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< ---------------------------------------------------------------------------- ---------------------------------------------------------------------------- DEPTH OF FLOW IN 18.0 INCH PIPE IS 12.2 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 7.8 UPSTREAM NODE ELEVATION(FEET) = 1086.00 DOWNSTREAM NODE ELEVATION(FEET) = 1070.55 FLOW LENGTH(FEET) = 1050.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 18.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 9.99 TRAVEL TIME(MIN.) = 2.24 TC(MIN.) = 12.95 frf:ir�•f<i:frfrf: fciricfcf:itfcicic�iciriri<i;icfrfeici:isfrir&i;iritfefrfcfriefe&itfcfri:itfrfrfcirfe:ricfefrfrfrfricfefairfrfrfrfcfricfcitfr�fifr FLOW PROCESS FROM NODE 106.10 TO NODE 106.11 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< ---------------------------------------------------------------------------- ---------------------------------------------------------------------------- 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.674 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 3.90 SUBAREA RUNOFF(CFS) = 9.12 EFFECTIVE AREA(ACRES) = 7.70 AREA -AVERAGED Fm(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) _ .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 7.70 PEAK FLOW RATE(CFS) = 18.01 TC(MIN) = 12.95 '.: kicf:fcft'.:fcicfrftfcitftirftfcftf:�x' fcitf:fei.•frfcftfcfrfrieiefriricftfcicfrfc�fefcfrftieftfczYfrftfrfrxf:fcitf:feltftftieirfricitfrfcfricicf:ft FLOW PROCESS FROM NODE 111.00 TO NODE 106.11 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.674 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 1.00 SUBAREA RUNOFF(CFS) = 2.34 EFFECTIVE AREA(ACRES) 8.70 AREA -AVERAGED Fm(INCH/HR) _ .07 AREA -AVERAGED Fp(INCH/HR) _ .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) 8.70 PEAK FLOW RATE(CFS) = 20.35 TC(MIN) = 12.95 is fr fc:Yi:f:ici:�..•irf: fr fr is ir�ir icX is is it fc ir�:k it is i; �ir�it fc fc fr is 9t ft is i;fc�'.r it fc fr it fe �icir �°k it it fc ft is fr fc is fr it fr it i; is fr fr �fc it is f: fc FLOW PROCESS FROM NODE 106.11 TO NODE 106.11 IS CODE = 1 ---------------------------------------------------------------------------- >>>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< »»>AND COMPUTE VARIOUS CONFLUENCED STREAM VALUES««< ---------------------------------------------------------------------------- ---------------------------------------------------------------------------- TOTAL NUMBER OF STREAMS = 2 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 2 ARE: TIME OF CONCENTRATION(MIN.) = 12.95 RAINFALL INTENSITY(INCH/HR) = 2.67 AREA -AVERAGED Fm(INCH/HR) = .07 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 EFFECTIVE STREAM AREA(ACRES) = 8.70 TOTAL STREAM AREA(ACRES) = 8.70 Page 7 PEAK FLOW RATE(CFS) AT CONFLUENCE = 20.35 RAINFALL INTENSITY AND TIME OF CONCENTRATION RATIO CONFLUENCE FORMULA USED FOR 2 STREAMS. PEAK FLOW RATE TABLE ** Q TC Intensit Fp Ap Fm Ae (CFS) (MIN.) (INCH/HR� (INCH/HR) (INCH/HR) (ACRES) 1 82.27 19.92 2.066 .38 .32 .12 46.48 2 80.88 21.47 1.975 .38 .33 .13 48.01 3 77.38 12.95 2.674 .39 .30 .12 33.27 COMPUTED CONFLUENCE ESTIMATES ARE AS FOLLOWS: PEAK FLOW RATE(CFS) = 82.27 TC(MIN.) = 19.917 EFFECTIVE AREA(ACRES) = 46.48 AREA -AVERAGED FM(INCH/HR) _ .12 AREA -AVERAGED Fp(INCH/HR) _ .38 AREA -AVERAGED Ap = .32 TOTAL AREA(ACRES) = 48.01 END OF STUDY SUMMARY: TOTAL AREA(ACRES) = 48.01 TC(MIN.) = 19.92 EFFECTIVE AREA(ACRES) = 46.48 AREA -AVERAGED FM(INCH/HR)= .12 AREA -AVERAGED Fp(INCH/HR) _ .38 AREA -AVERAGED Ap = .32 PEAK FLOW RATE(CFS) = 82.27 PEAK FLOW RATE TABLE ** Q Tc Intensit Fp Ap FM Ae (CFS) (MIN.) (IN CH/HR� (INCH/HR) (INCH/HR) (ACRES) 1 77.38 12.95 2.674 .39 .30 .12 33.27 2 82.27 19.92 2.066 .38 .32 .12 46.48 3 80.88 21.47 1.975 .38 .33 .13 48.01 ----------------------------- END OF RATIONAL METHOD ANALYSIS - Page 8 is it ir*ie is is it it is is i:ic is it it is it is it ie ie it is it ie it it is ie it it it it it it it ie it it icit is is is it it it is is sY it is ie it it sY it ie it it is it it it it ie is it it it it it ie it it RATIONAL METHOD HYDROLOGY COMPUTER PROGRAM PACKAGE (Reference: 1986 SAN BERNARDINO CO. HYDROLOGY CRITERION) (c) Copyright 1983-93 Advanced Engineering software (aes) Ver. 1.9B Release Date: 7/18/93 License ID 1202 Analysis prepared by: HUITT-ZOLLARS, INC. 15101 RED HILL AVENUE TUSTIN, CALIFORNIA 92780-6500 PHONE (714) 259-7900 * FAX (714) 259-0210 ---------------------------------------------------------------------------- FILE NAME: FECNLC25.DAT TIME/DATE OF STUDY: 12:58 6/14/2004 ---------------------------------------------------------------------------- ---------------------------------------------------------------------------- USER SPECIFIED HYDROLOGY AND HYDRAULIC MODEL INFORMATION: ---------------------------------------------------------------------------- --*TIME-OF-CONCENTRATION MODEL* -- USER SPECIFIED STORM EVENT(YEAR) = 25.00 SPECIFIED MINIMUM PIPE SIZE(INCH) = 18.00 SPECIFIED PERCENT OF GRADIENTS (DECIMAL) TO USE FOR FRICTION SLOPE = .95 *USER -DEFINED LOGARITHMIC INTERPOLATION USED FOR RAINFALL* 10-YEAR STORM 60-MINUTE INTENSITY(INCH/HOUR) _ .920 100-YEAR STORM 60-MINUTE INTENSITY(INCH/HOUR) = 1.340 COMPUTED RAINFALL INTENSITY DATA: STORM EVENT = 25.00 1-HOUR INTENSITY(INCH/HOUR) = 1.0659 SLOPE OF INTENSITY DURATION CURVE = .6000 ici:ic*ie it is i; it i:�::r 4c it it it ir'.cir'.r:�ic it it*fir is i:it*it*ie it i:i; it it it it it ir*i;k�•it*ir it:ei; it kic ie it it fir it*'r ie it*ic it it is is is it is is FLOW PROCESS FROM NODE 103.00 TO NODE 103.01 IS CODE = 2.1 ---------------------------------------------------------------------------- »»>RATIONAL METHOD INITIAL SUBAREA ANALYSIS««< NATURAL POOR COVER TC = K*[(LENGTH** 3.00)/(ELEVATION CHANGE)]** .20 INITIAL SUBAREA FLOW-LENGTH(FEET) = 260.00 UPSTREAM ELEVATION(FEET) = 1110.00 DOWNSTREAM ELEVATION(FEET) = 1105.00 ELEVATION DIFFERENCE(FEET) = 5.00 TC(MIN.) = .525*[( 260.00** 3.00)/( 5.00)]** .20 = 10.699 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.999 SOIL CLASSIFICATION IS "A" NATURAL POOR COVER "BARREN" SUBAREA LOSS RATE, Fm(INCH/HR) = .4100 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) _ .41 SUBAREA PERVIOUS AREA FRACTION, Ap = 1.00 SUBAREA RUNOFF(CFS) 5.83 TOTAL AREA(ACRES) = 2.50 PEAK FLOW RATE(CFS) = 5.83 4::: �•i:ir:r„ir�•4r it it it is*'.cir**i.•ic it i�ir it it*ie*iri; is ic'.r it icirir it it it sY it i;*ie it i:i: it it it k�k i:.*ic is ie it ir'.ci: �..•ie it ie is ie it is*ir is it it FLOW PROCESS FROM NODE 103.01 TO NODE 103.02 IS CODE = 5.1 ---------------------------------------------------------------------------- »»>COMPUTE TRAPEZOIDAL CHANNEL FLOW««< >>>TRAVELTIME THRU SUBAREA««< ---------------------------------------------------------------------------- ---------------------------------------------------------------------------- UPSTREAM NODE ELEVATION = 1105.00 DOWNSTREAM NODE ELEVATION = 1095.00 CHANNEL LENGTH THRU SUBAREA(FEET) = 150.00 CHANNEL SLOPE _ .0667 Page 1 CHANNEL BASE(FEET) = 40.00 "Z" FACTOR = 99.990 MANNING'S FACTOR = .030 MAXIMUM DEPTH(FEET) _ .50 CHANNEL FLOW THRU SUBAREA(CFS) = 5.83 FLOW VELOCITY(FEET/SEC) = 1.90 FLOW DEPTH(FEET) _ .07 TRAVEL TIME(MIN.) = 1.32 TC(MIN.) = 12.01 k ki: kick it ickit it k i:i: irkkkkkkk kk kk irkkitk kirk is iris it kkkkkkir is irkirir irkkkkkirkkkit 4: irkkkit it irk kirk kir is FLOW PROCESS FROM NODE 103.10 TO NODE 103.02 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.798 SOIL CLASSIFICATION IS "A" NATURAL POOR COVER "BARREN" SUBAREA LOSS RATE, Fm(INCH/HR) = .4100 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .41 SUBAREA PERVIOUS AREA FRACTION, Ap = 1.00 SUBAREA AREA(ACRES) = 1.90 SUBAREA RUNOFF(CFS) = 4.08 EFFECTIVE AREA(ACRES) = 4.40 AREA -AVERAGED FM(INCH/HR) _ .41 AREA -AVERAGED Fp(INCH/HR) _ .41 AREA -AVERAGED Ap = 1.00 TOTAL AREA(ACRES) = 4.40 PEAK FLOW RATE(CFS) = 9.45 TC(MIN) = 12.01 icirkkkkick kirk itkkkit itkkic��•kkkkkkkkkkirkkkkkkkkkkkkkkirk kic'.•i:'.c is ,ckkkkkkkkickkkkkkkkkic it FLOW PROCESS FROM NODE 103.02 TO NODE 103.01 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.798 SOIL CLASSIFICATION IS "A COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0970 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .97 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 2.70 SUBAREA RUNOFF(CFS) = 6.56 EFFECTIVE AREA(ACRES) = 7.10 AREA -AVERAGED FM(INCH/HR) _ .29 AREA -AVERAGED Fp(INCH/HR) _ .44 AREA -AVERAGED Ap = .66 TOTAL AREA(ACRES) = 7.10 PEAK FLOW RATE(CFS) = 16.02 TC(MIN) = 12.01 kkkkicie it �lrk:rkkirkkkkkkkitkkkkkirkkkkkkkkkkkkkitkkkkitkki: kkkkkkkkkkkkkkirkkkkirk kkkkirit FLOW PROCESS FROM NODE 103.02 TO NODE 103.11 IS CODE = 3 ---------------------------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME'THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< -------------------------------------------------------------------=-----=-- DEPTH OF FLOW IN 24.0 INCH PIPE IS 16.3 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 7.1 UPSTREAM NODE ELEVATION(FEET) = 1087.80 DOWNSTREAM NODE ELEVATION(FEET) = 1076.33 FLOW LENGTH(FEET) = 1400.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 24.00 NUMBER OF PIPES = l PIPE-FLOW(CFS) = 16.02 TRAVEL TIME(MIN.) = 3.30 TC(MIN.) = 15.32 .. .. i:kit'r it �•ki;ki:i:kkk kk it irk ki: kic it it irkkk'..•Y it irk kit it �..•i:�kit'.ckkkkkkkkkkic i:kkkk�..•i: ki:kkkic it irk&kki� FLOW PROCESS FROM NODE 103.30 TO NODE 103.11 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.418 SOIL CLASSIFICATION IS "B" RESIDENTIAL-> 5-7 DWELLINGS/ACRE SUBAREA LOSS RATE, FM(INCH/HR) = .3750 Page 2 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .50 SUBAREA AREA(ACRES) = 7.90 SUBAREA RUNOFF(CFS) = 14.53 EFFECTIVE AREA(ACRES) = 15.00 AREA -AVERAGED FM(INCH/HR) _ .34 AREA -AVERAGED Fp(INCH/HR) = .58 AREA -AVERAGED Ap = .57 TOTAL AREA(ACRES) = 15.00 PEAK FLOW RATE(CFS) = 28.12 TC(MIN) = 15.32 iri:idiris*iticitisie*iri:iciriciciciririciciri:*ieiririririririeici:itiririeicic*ir**irs4iciriricitieieicie*ir*irirsY4:itiririririciriririritir FLOW PROCESS FROM NODE 116.10 TO NODE 103.11 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< ------------------------------------------ -- ------------------------------ 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.418 SOIL CLASSIFICATION IS "A" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0970 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .97 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 2.70 SUBAREA RUNOFF(CFS) = 5.64 EFFECTIVE AREA(ACRES) = 17.70 AREA -AVERAGED FM(INCH/HR) _ .30 AREA -AVERAGED Fp(INCH/HR) = .60 AREA -AVERAGED Ap = .50 TOTAL AREA(ACRES) = 17.70 PEAK FLOW RATE(CFS) = 33.76 TC(MIN) = 15.32 *k it is*ic it it it is it it is is is ie is iris it it it is it it is is it sY it ie sY it it it is it ie ic�ir it ie it is it is it it*ir is it it is it is it it is it it it it is it is it it it it it it is it ie. FLOW PROCESS FROM NODE 103.11 TO NODE 103.11 IS CODE = 10 ---------------------------------------------------------------------------- »»>MAIN-STREAM MEMORY COPIED ONTO MEMORY BANK # 1 ««< irkir4r:kitic�•it*irir**ieiririrsYirieieiri;isitirir�iririririririririricitiri;.iciriciriri.•iririt*iriciriricsY:citiriciritir:;iririr:ririr'.cic;Yi; FLOW PROCESS FROM NODE 109.00 TO NODE 109.01 IS CODE = 2.1 ---------------------------------------------------------------------------- »»>RATIONAL METHOD INITIAL SUBAREA ANALYSIS««< DEVELOPMENT IS COMMERCIAL TC = K*[(LENGTH** 3.00)/(ELEVATION CHANGE)]** .20 INITIAL SUBAREA FLOW-LENGTH(FEET) = 900.00 UPSTREAM ELEVATION(FEET) = 1098.00 DOWNSTREAM ELEVATION(FEET) = 1091.00 ELEVATION DIFFERENCE(FEET) = 7.00 TC(MIN.) = .304*[( 900.00** 3.00)/( 7.00)]** .20 = 12.201 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.772 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA RUNOFF(CFS) = 21.12 TOTAL AREA(ACRES) = 8.70 PEAK FLOW RATE(CFS) = 21.12 it is is**i: i:iri:ic***it is is ir:k is it is ic'x*isis is is it is ie is is is it is it it is***ir is it is it it it it it it it is is it*i: is ie ie it *ir is it it i�ic*it is is is is it FLOW PROCESS FROM NODE 112.00 TO NODE 109.01 IS CODE = 8 ---------------------------------------------------------------------------- >>>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< --------------------------------------------------------------------- 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.772 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 1.10 SUBAREA RUNOFF(CFS) = 2.67 Page 3 EFFECTIVE AREA(ACRES) = 9.80 AREA -AVERAGED FM(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) _ .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 9.80 PEAK FLOW RATE(CFS) = 23.79 TC(MIN) = 12.20 xir:ricit:tirk4rf:4;i:irle'r4cic:tic:riciricici:itir4cicir4cir4ci:4c4riririciritis4ritie°kir4r4t4ririsitir4r:rir�ci:�4cirieic:r:r�r�eir4rdri;4t4t:r4e FLOW PROCESS FROM NODE 115.10 TO NODE 109.01 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.772 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, 4(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 1.07 SUBAREA RUNOFF(CFS) = 2.60 EFFECTIVE AREA(ACRES) = 10.87 AREA -AVERAGED FM(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 10.87 PEAK FLOW RATE(CFS) = 26.38 TC(MIN) = 12.20 ..R•'.r4r:r 4r 4c �'c9c'.r��4t �r �;4: it is it �: ie it it it �c'.r4:ic. ie�it 4t ir�ic it it it it 4: �Y sY:t it ir�:r dr Yc 4: it 4r it is is it it�ic:e is ir': dt it is 4c :r fc it it it it 4: 4c 4t FLOW PROCESS FROM NODE 109.01 TO NODE 116.01 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 33.0 INCH PIPE IS 23.1 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 5.9 UPSTREAM NODE ELEVATION(FEET) = 1080.70 DOWNSTREAM NODE ELEVATION(FEET) = 1079.80 FLOW LENGTH(FEET) = 240.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 33.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 26.38 TRAVEL TIME(MIN.) _ .67 TC(MIN.) = 12.87 :r�•n'.:is4r':ic:'.�:c�•��•�Yc:rir::�it�ftir���:it�irsY&'r�:'x�•��:��ir'r�&�•kirieie�ickit�it�:�irie�irir«:t�•�•i:&�•:cie&�.�•ic'.: FLOW PROCESS FROM NODE 116.01 TO NODE 110.01 IS CODE = 3 ---------------------------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 33.0 INCH PIPE IS 22.3 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 6.2 UPSTREAM NODE ELEVATION(FEET) = 1079.80 DOWNSTREAM NODE ELEVATION(FEET) = 1078.45 FLOW LENGTH(FEET) = 330.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 33.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 26.38 TRAVEL TIME(MIN.) _ .89 TC(MIN.) = 13.77 �c is :; �k4r i:sY?::: sY is i;i;4:4:�:::ck�ki:'.r ���ir 4:i:'r�4c is ie*tree 4r it it i;i;'.:': 3r �e'.r ic�'.:��•:c is it �; ir��:c �•4c it icy �i:4e'.; 4: ic'r�ie �: FLOW PROCESS FROM NODE 110.00 TO NODE 110.01 IS CODE = 8 ------------------ »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.578 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) _ .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 Page 4 SUBAREA AREA(ACRES) = 11.40 EFFECTIVE AREA(ACRES) = 22.27 AREA -AVERAGED Fp(INCH/HR) = .75 TOTAL AREA(ACRES) = 22.27 TC(MIN) = 13.77 SUBAREA RUNOFF(CFS) = 25.68 AREA -AVERAGED FM(INCH/HR) _ .08 AREA -AVERAGED Ap = .10 PEAK FLOW RATE(CFS) = 50.17 is is Yr ?r Ye?c Yc ?c is ?t it is Yt Ycic �' ?c i< it Yr Yt Yt?r it is Yr is Yc it Yr Yr Yt Yr 4c it?c it?c Y; Yr ?c Yt Yt ?c Y: i; i; is is ?c Yr Yr Yr Yt t it is Yc it is Y< Yc Yr Yc Yc Yc Yc itsY t Y; is ?t ?c?t � FLOW PROCESS FROM NODE 113.00 TO NODE 110.01 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.578 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 1.08 SUBAREA RUNOFF(CFS) = 2.43 EFFECTIVE AREA(ACRES) = 23.35 AREA -AVERAGED FM(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) 23.35 PEAK FLOW RATE(CFS) = 52.61 TC(MIN) = 13.77 ...... �• is ie ?r ?r Yr it � � a Yt it k i; ?r ?r ?c ?: it � it �• ?r ?r & is Y: YeYr sY i; sY >; it it it Yt Yc is � ?r Yt ?.• Yc iYYc i<?r ?r it ?r ?r Yt Yc it � sk ?r ?r Yt ?t Yr Yr -k it is Yc ?r is ?c ?r is sY FLOW PROCESS FROM NODE 118.00 TO NODE 110.01 IS CODE = 8 ---------------------------------------------------------------------------- >>>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.578 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 1.08 SUBAREA RUNOFF(CFS) = 2.43 EFFECTIVE AREA(ACRES) = 24.43 AREA -AVERAGED FM(INCH/HR) .07 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 24.43 PEAK FLOW RATE(CFS) = 55.04 TC(MIN) = 13.77 �• � ?c x is � :e ?: ?c is it Ye it iti; is ?;?r � R•. it Yck ?: ?: Yt is Yt Y: it ?: � � A• is ?c Yr ?c it sY i; ?c ?r °k it is ?c ic?r is Yr �• � Y:. it ?c ?; Ye ir'.r it Yt Yc ?; ?c i<?t?t Yc Yc Y: it Y: �• is ?r FLOW PROCESS FROM NODE 110.01 TO NODE 103.11 IS CODE = 3 ---------------------------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< >>>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< ---------------------------------------------------------------------------- DEPTH OF FLOW IN 42.0 INCH PIPE IS 30.6 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 7.3 UPSTREAM NODE ELEVATION(FEET) = 1078.45 DOWNSTREAM NODE ELEVATION(FEET) = 1076.33 FLOW LENGTH(FEET) = 520.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 42.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 55.04 TRAVEL TIME(MIN.) = 1.18 TC(MIN.) = 14.95 ., .. Y: sY?; ?; ?; ?c ?c'.• ?c ?: ?; ?; ?: ?: Y: � ?: a ?c it i::Y Yr sY Ye s4 Yc Y; i; Yr?r ?r & Yt ?r Yt & :c �•?t � ?: ?c ?: i<?t Yr � ?r?r i<Y; ?r Yt � � � i; ic?t � ?: ?: � Y: ?c �?c Yr Yr � Y: FLOW PROCESS FROM NODE 103.11 TO NODE 103.11 IS CODE = 1 ---------------------------------------------------------------------------- »»>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< ----------------------------------- TOTAL NUMBER OF STREAMS = 2 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 1 ARE: TIME OF CONCENTRATION(MIN.) = 14.95 Page 5 RAINFALL INTENSITY(INCH/HR) = 2.45 AREA -AVERAGED FM(INCH/HR) = .07 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 EFFECTIVE STREAM AREA(ACRES) = 24.43 TOTAL STREAM AREA(ACRES) = 24.43 PEAK FLOW RATE(CFS) AT CONFLUENCE = 55.04 R-ir it is is it it it ir*ir*ir it it icic*ir it s4 is is it is is it 4c it ie ie it is it it ie is it it it it it it ie it it it is it it it ie is ie it it it it it it ie it is it it is*ie is it it it is ie ie it FLOW PROCESS FROM NODE 104.00 TO NODE 104.01 IS CODE = 2.1 ---------------------------------------------------------------------------- »»>RATIONAL METHOD INITIAL SUBAREA ANALYSIS««< DEVELOPMENT IS COMMERCIAL TC = K*[(LENGTH** 3.00)/(ELEVATION CHANGE)]** .20 INITIAL SUBAREA FLOW-LENGTH(FEET) = 520.00 UPSTREAM ELEVATION(FEET) = 1130.00 DOWNSTREAM ELEVATION(FEET) = 1110.00 ELEVATION DIFFERENCE(FEET) = 20.00 TC(MIN.) = .304*[( 520.00** 3.00)/( 20.00)]** .20 = 7.117 25 YEAR RAINFALL INTENSITY(INCH/HR) = 3.830 SOIL CLASSIFICATION IS "A" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0970 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .97 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA RUNOFF(CFS) = 3.19 TOTAL AREA(ACRES) = .95 PEAK FLOW RATE(CFS) = 3.19 **it it it ie it it is *ir is ie it it it it it is is it it is it is it ie ie is is*i: is is it ir.*ir it is it*ic it it it**ir is is it is it is it is it*ic it is is ie it is it ie is*it it it is is it FLOW PROCESS FROM NODE 104.01 TO NODE 103.11 IS CODE = 6 ----------------- »»>COMPUTE STREET FLOW TRAVEL TIME THRU SUBAREA««< UPSTREAM ELEVATION(FEET) = 1110.00 DOWNSTREAM ELEVATION(FEET) = 1088.00 STREET LENGTH(FEET) = 690.00 CURB HEIGHT(INCHES) = 8. STREET HALFWIDTH(FEET) = 51.00 DISTANCE FROM CROWN TO CROSSFALL GRADEBREAK(FEET) = 37.00 INTERIOR STREET CROSSFALL(DECIMAL) = .020 OUTSIDE STREET CROSSFALL(DECIMAL) = .020 SPECIFIED NUMBER OF HALFSTREETS CARRYING RUNOFF = 1 "TRAVEL TIME COMPUTED USING MEAN FLOW(CFS) = 3.19 STREET FLOW MODEL RESULTS: STREET FLOW DEPTH(FEET) .31 HALFSTREET FLOOD WIDTH(FEET) = 7.74 AVERAGE FLOW VELOCITY(FEET/SEC.) = 4.05 PRODUCT OF DEPTH&VELOCITY = 1.27 STREET FLOW TRAVEL TIME(MIN.) = 2.84 TC(MIN.) = 9.96 25 YEAR RAINFALL INTENSITY (INCH/HR) = 3.131 SOIL CLASSIFICATION IS "A" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0970 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .97 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = .00 SUBAREA RUNOFF(CFS) _ .00 EFFECTIVE AREA(ACRES) _ .95 AREA -AVERAGED FM(INCH/HR) _ .10 AREA -AVERAGED Fp(INCH/HR) _ .97 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = .95 PEAK FLOW RATE(CFS) 3.19 END OF SUBAREA STREET FLOW HYDRAULICS: DEPTH(FEET) = .31 HALFSTREET FLOOD WIDTH(FEET) = 7.74 FLOW VELOCITY(FEET/SEC.) = 4.05 DEPTH*VELOCITY = 1.27 Page 6 Ye it Yt is Yc ie it Yrir Yc Yt Ye Yc it Ye it Yr it YrYtYe Ye it i< icYt Yt it Ye Yr it it it ie Yr i< ie ie Yr it Yt it Yt it ie ie Yc ie is Yc Yr ie it ie ie Yr ie ie Yc it it is ie itYt i<ic it Yr it Yr is Ye is Yc i� FLOW PROCESS FROM NODE 105.00 TO NODE 103.11 IS CODE = 8 ---------------------------•------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 25 YEAR RAINFALL INTENSITY(INCH/HR) = 3.131 SOIL CLASSIFICATION IS "A" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0970 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .97 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = .95 SUBAREA RUNOFF(CFS) = 2.59 EFFECTIVE AREA(ACRES) = 1.90 AREA -AVERAGED FM(INCH/HR) _ .10 AREA -AVERAGED Fp(INCH/HR) _ .97 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 1.90 PEAK FLOW RATE(CFS) = 5.19 TC(MIN) = 9.96 .. Y: Y: is �• is Y; � Yc Yc is �Y Yc it. is Yc � it it �Y is Yc Yc it it Yc is is s4 it it Y; Yt Y: it Yc sY Yt it irYr ie it Yc Yrit is it it Y: � is � it Y: Yt � it is it Yc Yc is it Yr Yr Yc X „ Yt it is Yc :.• Yc Yc FLOW PROCESS FROM NODE 113.10 TO NODE 103.11 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 25 YEAR RAINFALL INTENSITY(INCH/HR) = 3.131 SOIL CLASSIFICATION IS "A" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0970 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .97 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 1.38 SUBAREA RUNOFF(CFS) = 3.77 EFFECTIVE AREA(ACRES) = 3.28 AREA -AVERAGED FM(INCH/HR) _ .10 AREA -AVERAGED Fp(INCH/HR) _ .97 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 3.28 PEAK FLOW RATE(CFS) = 8.96 TC(MIN) = 9.96 Yr � is Yc Yt it Yr is Yc Yr i; Yr sY � � Yr Ye Yr Yc Yc Yt * is it Yr Yt � is Yr it Yt it Ye it eY -k Yt it Ye it Yr Yr Yt •k Ye Ye Yr it Yr it Yr it Yr i;: i<YrYr Yt is � Yr it � eY it Yr Yc Yr '„• � Ye :r Yc Yr & Y: FLOW PROCESS FROM NODE 103.11 TO NODE 103.11 IS CODE = 1 »»>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< »»>AND COMPUTE VARIOUS CONFLUENCED STREAM VALUES««< TOTAL NUMBER OF STREAMS = 2 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 2 ARE: TIME OF CONCENTRATION(MIN.) = 9.96 RAINFALL INTENSITY(INCH/HR) = 3.13 AREA -AVERAGED FM(INCH/HR) = .10 AREA -AVERAGED Fp(INCH/HR) = .97 AREA -AVERAGED Ap = .10 EFFECTIVE STREAM AREA(ACRES) = 3.28 TOTAL STREAM AREA(ACRES) = 3.28 PEAK FLOW RATE(CFS) AT CONFLUENCE = 8.96 RAINFALL INTENSITY AND TIME OF CONCENTRATION RATIO CONFLUENCE FORMULA USED FOR 2 STREAMS. PEAK FLOW RATE TABLE ** Q Tc Intensit Fp Ap FM Ae (CFS) (MIN.) (INCH/HR� (INCH/HR) (INCH/HR) (ACRES) 1 62.00 14.95 2.454 .78 .10 .08 27.71 2 56.06 9.96 3.131 .79 .10 .08 19.56 COMPUTED CONFLUENCE ESTIMATES ARE AS FOLLOWS: PEAK FLOW RATE(CFS) = 62.00 TC(MIN.) = 14.946 EFFECTIVE AREA(ACRES) = 27.71 AREA -AVERAGED FM(INCH/HR) _ .08 Page 7 AREA -AVERAGED Fp(INCH/HR) = .78 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 27.71 FLOW PROCESS FROM NODE 103.11 TO NODE 103.11 IS CODE = 11 ----------------------------------------- »»>CONFLUENCE MEMORY BANK # 1 WITH THE MAIN -STREAM MEMORY««< ** PEAK FLOW RATE TABLE ** Q Tc Intensit Fp Ap Fm Ae (CFS) (MIN.) (INCH/HR� (INCH/HR) (INCH/HR) (ACRES) 1 85.40 9.96 3.131 .64 .25 .16 31.07 2 95.50 14.95 2.454 .64 .25 .16 44.98 3 94.82 15.32 2.418 .64 .26 .16 45.41 TOTAL AREA = 45.41 COMPUTED CONFLUENCE ESTIMATES ARE AS FOLLOWS: PEAK FLOW RATE(CFS) = 95.50 TC(MIN.) = 14.946 EFFECTIVE AREA(ACRES) = 44.98 AREA -AVERAGED FM(INCH/HR) _ .16 AREA -AVERAGED Fp(INCH/HR) _ .64 AREA -AVERAGED Ap = .25 TOTAL AREA(ACRES) = 45.41 ..':#4c 4r###'.r##*:r##########.*###4t###sY#ic ir:c#####it##***######***###:r###�•*:r 4r 4r##::#ir#*# FLOW PROCESS FROM NODE 103.11 TO NODE 103.11 IS CODE = 12 -------------------------------------------- »»>CLEAR MEMORY BANK # 1 ««< �•##::##irk###'.::cir##�•#:r#4r##ir##:r#:rfc*ir##ir#ir#####*##�•:c#ir*##4r##:c:e###*#4r#*####:c##:t#:c# FLOW PROCESS FROM NODE 103.11 TO NODE 117.01 IS CODE = 3 ---------------------------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< >>>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW) ««< --------------------------------------------=---------------------- DEPTH OF FLOW IN 51.0 INCH PIPE IS 37.3 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 8.6 UPSTREAM NODE ELEVATION(FEET) = 1076.33 DOWNSTREAM NODE ELEVATION(FEET) = 1075.90 FLOW LENGTH(FEET) = 100.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 51.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 95.50 TRAVEL TIME(MIN.) _ .19 TC(MIN.) = 15.14 --------------------------------------------------------------------- END OF STUDY SUMMARY: TOTAL AREA(ACRES) = 45.41 TC(MIN.) = 15.14 EFFECTIVE AREA(ACRES) = 44.98 AREA -AVERAGED Fm(INCH/HR) .16 AREA -AVERAGED Fp(INCH/HR) _ .64 AREA -AVERAGED Ap .25 PEAK FLOW RATE(CFS) = 95.50 PEAK FLOW RATE TABLE ** Q Tc Intensit Fp Ap Fm Ae (CFS) (MIN.) (INCH/HR� (INCH/HR) (INCH/HR) (ACRES) 1 85.40 10.16 3.094 .64 .25 .16 31.07 2 95.50 15.14 2.435 .64 .25 .16 44.98 3 94.82 15.51 2.400 .64 .26 .16 45.41 -------------------------------------------------------------------------- END OF RATIONAL METHOD ANALYSIS Page 8 Technical appendix C Hydrology Map Reproduced from Master Hydrology Study for Empire Center Lines A, B, & C Hall & Foreman, Inc - January 28, 1992 Technical Appendix 100-Year Rational Method Analysis Derived from Preliminary Hydrology & Hydraulic Calculations for Sierra Business Park Huitt-Zollars, Inc — November I, 2003 k is kic iriskkkkkickkkirkkkkkkkkkkiek kkkkkkkkkkkkkkkitkkkkkkkkkkkkirkkkkkkkickkkkkkkirkkk RATIONAL METHOD HYDROLOGY COMPUTER PROGRAM PACKAGE (Reference: 1986 SAN BERNARDINO CO. HYDROLOGY CRITERION) (c) Copyright 1983-93 Advanced Engineering Software (aes) Ver. 1.9B Release Date: 7/18/93 License ID 1202 Analysis prepared by: HUITT-ZOLLARS, INC. 15101 RED HILL AVENUE TUSTIN, CALIFORNIA 92780-6500 PHONE (714) 259-7900 k FAX (714) 259-0210 ------------------------------------------------------ FILE NAME: 202Q100A.DAT TIME/DATE OF STUDY: 13:59 5/ 3/2004 ______________________ USER SPECIFIED HYDROLOGY AND HYDRAULIC MODEL INFORMATION: --------------------------------------------------------------------------- --*TIME-OF-CONCENTRATION MODEL* -- USER SPECIFIED STORM EVENT(YEAR) = 100.00 SPECIFIED MINIMUM PIPE SIZE(INCH) = 18.00 SPECIFIED PERCENT OF GRADIENTS (DECIMAL) TO USE FOR FRICTION SLOPE = .95 *USER -DEFINED LOGARITHMIC INTERPOLATION USED FOR RAINFALL* 10-YEAR STORM 60-MINUTE INTENSITY(INCH/HOUR) _ .920 100-YEAR STORM 60-MINUTE INTENSITY(INCH/HOUR) 1.340 COMPUTED RAINFALL INTENSITY DATA: STORM EVENT = 100.00 1-HOUR INTENSITY(INCH/HOUR) = 1.3400 SLOPE OF INTENSITY DURATION CURVE = .6000 i:kk�•kitkkickkkirk kkk>t k itkkkkkkkkkkkkkkkkkkkkk�:kkkkkkkkkkkkkkkkkkkkkkitkkkk kk kkkkk FLOW PROCESS FROM NODE 1.00 TO NODE 1.00 IS CODE = 15 -------------------------------------------- »»>DEFINE MEMORY BANK # 1 ««< MEMORY BANK # 1 DEFINED AS FOLLOWS: Q(CFS) TC(MIN.) Fp(INCH/HR) AP FM(INCH/HR) Ae(ACRES) 1 99.29 12.81 .392 .30 .119 33.42 2 105.86 19.58 .381 .32 .124 46.49 3 104.12 21.11 .378 .33 .125 48.01 TOTAL AREA = 48.01 k kki.•k kkkkkkkk *kick kirk kkkickkkkitkk ksYkkkkkkit k sYYckkkk �•it itkkkkkkk'..•kkkickkkkkkkkirkkkitk FLOW PROCESS FROM NODE 1.00 TO NODE 1.00 IS CODE = 14 ---------------------------------------------------------------------------- >>>MEMORY BANK # 1 COPIED ONTO MAIN -STREAM MEMORY««< MAIN -STREAM MEMORY DEFINED AS FOLLOWS: Q(CFS) TC(MIN.) Fp(INCH/HR) AP FM(INCH/HR) Ae(ACRES) 1 99.29 12.81 .392 .30 .119 33.42 2 105.86 19.58 .381 .32 .124 46.49 3 104.12 21.11 .378 .33 .125 48.01 TOTAL AREA = 48.01 ..kkkkkkickkkk�Y'.ckkkkkkk kkkkkkkkirkkkkickkkkkkkkkic kiekkki:kkkit. ickkkkkkkkkkkkkirk kkkkit FLOW PROCESS FROM NODE 1.00 TO NODE 1.00 IS CODE = 12 Page 1 ---------------------------------------------------------------------------- »»>CLEAR MEMORY BANK # 1 ««< Xir4tXX:cXXX4:ic:eiririrXXieiriticitXXXXXX�XXicieXXirftitXXX4cic4r',rXX#itXX4cXic4tXirXXXXirsYicXYtXXYcXicicXirXic FLOW PROCESS FROM NODE 1.00 TO NODE 1.00 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< ------------------------------------------------------------------------- 100 YEAR RAINFALL INTENSITY(INCH/HR) = 2.624 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 7.06 SUBAREA RUNOFF(CFS) = 16.20 EFFECTIVE AREA(ACRES) = 53.55 AREA -AVERAGED FM(INCH/HR) _ .12 AREA -AVERAGED Fp(INCH/HR) = .40 AREA -AVERAGED Ap = .30 TOTAL AREA(ACRES) = 55.07 PEAK FLOW RATE(CFS) = 120.80 TC(MIN) = 19.58 XXXXXX�'eXXXXdrXXfr4rXXXXXXXXXXXXXXXX4rXXieXXXXXirieXXXXXirXXXXXX4eXXirXXXXXXXi�XX4cXfrX�1.4cX FLOW PROCESS FROM NODE 1.00 TO NODE 2.00 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< ------------=------------------------------------------------------------ DEPTH OF FLOW IN 54.0 INCH PIPE IS 42.4 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 9.0 UPSTREAM NODE ELEVATION(FEET) = 1079.00 DOWNSTREAM NODE ELEVATION(FEET) = 1072.02 FLOW LENGTH(FEET) = 1620.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 54.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 120.80 TRAVEL TIME(MIN.) = 3.00 TC(MIN.) = 22.57 X X�XisXX�XX XXXirXXXXXXXXXX�XXXXXXXXXXirXXXXXirir k9rXXXicXXXXXXXX:IXXsYX itir icX XiFir i:XXX���: FLOW PROCESS FROM NODE 2.00 TO NODE 2.00 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< -------------------------------------------- ------------------------------- 100 YEAR RAINFALL INTENSITY(INCH/HR) = 2.409 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) _ .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 2.49 SUBAREA RUNOFF(CFS) = 5.23 EFFECTIVE AREA(ACRES) = 56.04 AREA -AVERAGED FM(INCH/HR) _ .12 AREA -AVERAGED Fp(INCH/HR) = .40 AREA -AVERAGED Ap = .29 TOTAL AREA(ACRES) = 57.56 PEAK FLOW RATE(CFS) = 120.80 TC(MIN) = 22.57 iricXXXXXXXXXXXXXXXXXXXXX*XXXX4:X'.rXXieX ie XicXXXX*XXXXXXXX.XXX�XXXXXX4c :r'.c 4cXX X�c is �•ie icX X. �•. FLOW PROCESS FROM NODE 2.00 TO NODE 2.00 IS CODE = 1 ---------------------------------------------------------------------------- »»>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< - ------------------------------------------ TOTAL NUMBER OF STREAMS = 2 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 1 ARE: TIME OF CONCENTRATION(MIN.) = 22.57 RAINFALL INTENSITY(INCH/HR) = 2.41 AREA -AVERAGED FM(INCH/HR) _ .12 Page 2 AREA -AVERAGED Fp(INCH/HR) _ .40 AREA -AVERAGED Ap = 29 EFFECTIVE STREAM AREA(ACRES) 56.04 TOTAL STREAM AREA(ACRES) = 57.56 PEAK FLOW RATE(CFS) AT CONFLUENCE = 120.80 k kit it it it it it ickkkic itkkkkkkkkit'kititirk kic i:kkkkkkitkkkit irkkkkkir kitkkkkit itkkkkiek kkkic it k itkkkkkit FLOW PROCESS FROM NODE 2.10 TO NODE 2.20 IS CODE = 2.1 ---------------------------------------------------------------------------- »»>RATIONAL METHOD INITIAL SUBAREA ANALYSIS««< DEVELOPMENT IS COMMERCIAL TC = K*[(LENGTH*it 3.00)/(ELEVATION CHANGE)]** .20 INITIAL SUBAREA FLOW-LENGTH(FEET) = 435.00 UPSTREAM ELEVATION(FEET) = 1088.50 DOWNSTREAM ELEVATION(FEET) = 1087.50 ELEVATION DIFFERENCE(FEET) = 1.00 TC(MIN.) = .304*[( 435.00** 3.00)/( 1.00)]** .20 = 11.640 100 YEAR RAINFALL INTENSITY(INCH/HR) = 3.584 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA RUNOFF(CFS) = 5.72 TOTAL AREA(ACRES) = 1.81 PEAK FLOW RATE(CFS) = 5.72 k irk kick ie irkk*kirk it itkkki.•kkkick kir it irk irk kirk kit irk kirkkkirk kitkkkkkkit kkkkkkiekkkkkkkk kkkkkk FLOW PROCESS FROM NODE 2.20 TO NODE 2.30 IS CODE = 3 ---------------------------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW) ««< ------------------------------------------------------------------- DEPTH OF FLOW IN 18.0 INCH PIPE IS 12.1 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 4.5 UPSTREAM NODE ELEVATION(FEET) = 1081.50 DOWNSTREAM NODE ELEVATION(FEET) = 1080.50 FLOW LENGTH(FEET) = 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 18.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 5.72 TRAVEL TIME(MIN.) _ .73 TC(MIN.) = 12.37 kkkkk',.•kki:'..•*k:ci: ickkkit it*kkkkk*ic 4**kk"..•itk:Yi: ickirkkk �•ir**kkitk kkk*�•k:.•k k:': is Y:kk�•k k*ic kit :ck is FLOW PROCESS FROM NODE 2.30 TO NODE 2.30 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 100 YEAR RAINFALL INTENSITY(INCH/HR) = 3.455 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 1.79 SUBAREA RUNOFF(CFS) = 5.45 EFFECTIVE AREA(ACRES) = 3.60 AREA -AVERAGED FM(INCH/HR) _ .07 AREA -AVERAGED Fp(INCH/HR) _ .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 3.60 PEAK FLOW RATE(CFS) = 10.95 TC(MIN) = 12.37 :c::i:ki:i:ki: kitki; itkki:ick kickkkkitk kit i:kki:kic it is**irkk*itkkkkir is it it is*k kk.*kirir k it*it i:*kkitkkki: kit is FLOW PROCESS FROM NODE 2.30 TO NODE 2.40 IS CODE = 3 ---------------------------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< Page 3 »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 24.0 INCH PIPE IS 14.8 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 5.4 UPSTREAM NODE ELEVATION(FEET) = 1080.50 DOWNSTREAM NODE ELEVATION(FEET) = 1079.50 FLOW LENGTH(FEET) = 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 24.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 10.95 TRAVEL TIME(MIN.) _ .62 TC(MIN.) = 12.99 �:: °k is i:4: 4t 4c f: fci: is it f: is 4c is is ie 4t is is it is 4r is i:i: is it �t i:4t it it sY sY �r Yr 4t$: it it it is is is is ft Y: �k �c i:i: dt 4t is 4r is �4 is it sY is sY 4r is is is is �: is is it is FLOW PROCESS FROM NODE 2.40 TO NODE 2.40 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 100 YEAR RAINFALL INTENSITY(INCH/HR) = 3.355 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 1.78 SUBAREA RUNOFF(CFS) = 5.26 EFFECTIVE AREA(ACRES) = 5.38 AREA -AVERAGED FM(INCH/HR) _ .07 AREA -AVERAGED Fp(INCH/HR) _ .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 5.38 PEAK FLOW RATE(CFS) = 15.88 TC(MIN) = 12.99 ���:i:��: �-*���•��:�::�:*����•�:�:�:�:��s:�:�:�::�:��:��:�:��:�::���*�:�:**�:��*�:�:*�:*��r*�:*��x��:�:t:�:::�:sty: FLOW PROCESS FROM NODE 2.40 TO NODE 2.50 IS CODE = 3 >>>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< ---------------------- --- ----------------------------------------------- DEPTH OF FLOW IN 27.0 INCH PIPE IS 17.4 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 5.9 UPSTREAM NODE ELEVATION(FEET) = 1079.50 DOWNSTREAM NODE ELEVATION(FEET) = 1078.50 FLOW LENGTH(FEET) = 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 27.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 15.88 TRAVEL TIME(MIN.) _ .57 TC(MIN.) = 13.56 i:4: dr it 7c4e::oY Y i:4.•4:�.k ic��4t is At it is it kic is&9:iri::r4r:c 4c dt is it is 4t it it i:�t&�:i: is is is ic��4:4r ft �'c4c::i: it it it ir. Y�i: fr is is is is it i:4e it i FLOW PROCESS FROM NODE 2.50 TO NODE 2.50 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 100 YEAR RAINFALL INTENSITY(INCH/HR) = 3.270 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 1.78 SUBAREA RUNOFF(CFS) = 5.12 EFFECTIVE AREA(ACRES) = 7.16 AREA -AVERAGED FM(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) _ .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 7.16 PEAK FLOW RATE(CFS) = 20.59 TC(MIN) = 13.56 .i::� .. .. �-i:;: s: �".•�-i:��; tr s:'�� �•4: :: .. .. .. ��k :: :Y :Y is :: �.. � :: �. .. .. .. :; :c%:e �: �r �-*��t :: �•&�:f:�-�'t�:: is ': ::4: �-.. ... .: :r :Y �:� ie�:::::4:i: FLOW PROCESS FROM NODE 2.50 TO NODE 2.60 IS CODE = 3 -----------------------------------------------------------------7---------- Page 4 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< ---------------------------------------------------=--------------- DEPTH OF FLOW IN 27.0 INCH PIPE IS 21.3 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 6.1 UPSTREAM NODE ELEVATION(FEET) = 1078.50 DOWNSTREAM NODE ELEVATION(FEET) = 1077.50 FLOW LENGTH(FEET) = 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 27.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 20.59 TRAVEL TIME(MIN.) _ .54 TC(MIN.) = 14.11 FLOW PROCESS FROM NODE 2.60 TO NODE 2.60 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 100 YEAR RAINFALL INTENSITY(INCH/HR) = 3.194 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 1.78 SUBAREA RUNOFF(CFS) = 5.00 EFFECTIVE AREA(ACRES) = 8.94 AREA -AVERAGED FM(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) _ .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 8.94 PEAK FLOW RATE(CFS) = 25.10 TC(MIN) = 14.11 # # # ««# �• «««ic «ir ««:c it «# # «# «# «# # �t «««««# :� ««# :r # «««# «�4 �r is ie «# ««'.• «.:r �• «# it «ir'.t # # «# «ir #'.r ««« �• « FLOW PROCESS FROM NODE 2.60 TO NODE 2.70 IS CODE = 3 ----------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< --------------------------------------------------------------------------- DEPTH OF FLOW IN 30.0 INCH PIPE IS 22.0 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 6.5 UPSTREAM NODE ELEVATION(FEET) = 1077.50 DOWNSTREAM NODE ELEVATION(FEET) = 1076.50 FLOW LENGTH(FEET) = 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 30.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 25.10 TRAVEL TIME(MIN.) _ .51 TC(MIN.) = 14.62 FLOW PROCESS FROM NODE 2.70 TO NODE 2.70 IS CODE = 8 ---------------------------------------------------------------------------- >>>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 100 YEAR RAINFALL INTENSITY(INCH/HR) = 3.126 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 1.78 SUBAREA RUNOFF(CFS) = 4.89 EFFECTIVE AREA(ACRES) = 10.72 AREA -AVERAGED FM(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 10.72 PEAK FLOW RATE(CFS) = 29.44 TC(MIN) = 14.62 ......., it # «« � «« is « � ...... ««««««««« �• # ««# « ., ., .. is ««««# it «« « «««i.• is # # «««««««««.... is ««# ««# is # # # «« FLOW PROCESS FROM NODE 2.70 TO NODE 2.80 IS CODE = 3 Page 5 ---------------------------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< - - - --------------------------------------------------------- DEPTH OF FLOW IN 33.0 INCH PIPE IS 22.5 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 6.8 UPSTREAM NODE ELEVATION(FEET) = 1076.50 DOWNSTREAM NODE ELEVATION(FEET) = 1075.50 FLOW LENGTH(FEET) = 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 33.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 29.44 TRAVEL TIME(MIN.) .49 TC(MIN.) = 15.11 4r it ir't 4t 4e 4r it Xit it it it it 'r 4t it �: it'h ie is ft 4t it 4c it 4r it it Y aY �; is 4r it it it it �4 it tt ft ie it&4e it icitYt ie is it ft is it sY Y&4t it fc it Yt�ic it dr it it 4r 4t it is it FLOW PROCESS FROM NODE 2.80 TO NODE 2.80 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< ---------------------------------------------------------------------------- 100 YEAR RAINFALL INTENSITY(INCH/HR) = 3.065 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 1.78 SUBAREA RUNOFF(CFS) = 4.79 EFFECTIVE AREA(ACRES) = 12.50 AREA -AVERAGED FM(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 12.50 PEAK FLOW RATE(CFS) = 33.64 TC(MIN) = 15.11 .. �•��:r ^k'k �•k 4c&� k:r�•��i.•4r'r�&ic :r'.r R•k ie 4e'.•Yt it 4t fir 4: �4c sY it it :t it is k��'k'.t ��c it i::t�•ic:r;Y�irir it it :r�k-k �•°k :: ;r',.•�•4r it 4t FLOW PROCESS FROM NODE 2.80 TO NODE 2.90 IS CODE = 3 ---------------------------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< --------------------------------------------------------- DEPTH OF FLOW IN 33.0 INCH PIPE IS 25.0 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 7.0 UPSTREAM NODE ELEVATION(FEET) = 1075.50 DOWNSTREAM NODE ELEVATION(FEET) = 1074.50 FLOW LENGTH(FEET) = 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 33.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 33.64 TRAVEL TIME(MIN.) _ .48 TC(MIN.) = 15.59 .. is Xd: 4c kie k�•f: it �i: �•�t ;.: :cam �i: it is it 4r it it 4e it kie:c�:: it it ir'..•i: it it is it it it it it sY:c it fe Yc ie��i: it it i:ic�:r it sYt is it ir:r 4c �: is it is �k 4r it FLOW PROCESS FROM NODE 2.90 TO NODE 2.90 IS CODE = 8 ---------------------------------------------------------------------------- >»»ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< ---------------------------------------------------------------------------- 100 YEAR RAINFALL INTENSITY (INCH/HR) = 3.009 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) _ .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 1.78 SUBAREA RUNOFF(CFS) = 4.70 EFFECTIVE AREA(ACRES) = 14.28 AREA -AVERAGED FMCINCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 14.28 PEAK FLOW RATE(CFS) = 37.70 TC(MIN) = 15.59 �:'........::ki:'......:c:Yir:c'.c:: kir is i:iri:i: ir�k:r�:c���4: 4r 4r::�4r'.'r irx'.:�kk„k�:r .c'.. ..... d: 4: ie it«ir :c'.. �•h. 4. :':kk9r4r�ir'.r ie Page 6 FLOW PROCESS FROM NODE 2.90 TO NODE 2.10 IS CODE = 3 >>>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< >>>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 36.0 INCH PIPE IS 24.8 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 7.3 UPSTREAM NODE ELEVATION(FEET) = 1074.50 DOWNSTREAM NODE ELEVATION(FEET) = 1073.75 FLOW LENGTH(FEET) = 150.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 36.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 37.70 TRAVEL TIME(MIN.) _ .34 TC(MIN.) = 15.93 is it it ie is it it i.• ie it ie ie � � is is � it ie it it is it it it ie it ie it ie it ie it it ie it it it it it ie is ie it ic't it ie is it it it it it it it y: i; ie it it it it it ie is it it it it is ie is is is it FLOW PROCESS FROM NODE 2.10 TO NODE 2.10 IS CODE = 8 ----------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 100 YEAR RAINFALL INTENSITY(INCH/HR) = 2.969 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 1.17 SUBAREA RUNOFF(CFS) = 3.05 EFFECTIVE AREA(ACRES) = 15.45 AREA -AVERAGED FM(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 15.45 PEAK FLOW RATE(CFS) = 40.25 TC(MIN) = 15.93 it�•i;iri;iri; it it ic�ic i:�'r�it i;t it it is it it �k�it it eY�&i;i; sY it it it sY sY it it it i:i; it it it it it is it is it it is it is it it it is it it i; i; is it it it is it it ir�i: ki; FLOW PROCESS FROM NODE 2.10 TO NODE 2.11 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 36.0 INCH PIPE IS 26.1 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 7.3 UPSTREAM NODE ELEVATION(FEET) = 1073.75 DOWNSTREAM NODE ELEVATION(FEET) = 1072.40 FLOW LENGTH(FEET) = 270.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 36.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 40.25 TRAVEL TIME(MIN.) _ .61 TC(MIN.) = 16.54 .. » �k is it it k :; �Y it it i; it �• ie ie i< �• it ie ie it ir'.r is � it ie � i; is & is is is i; it i; ie ie ie it �• it s: i; is is is sY it it k i; is i; ie it � � is it it it � it is ie it it i; it � :; „ it FLOW PROCESS FROM NODE 2.11 TO NODE 2.11 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 100 YEAR RAINFALL INTENSITY(INCH/HR) = 2.903 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 1.25 SUBAREA RUNOFF(CFS) = 3.18 EFFECTIVE AREA(ACRES) = 16.70 AREA -AVERAGED FM(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 16.70 PEAK FLOW RATE(CFS) = 42.50 TC(MIN) = 16.54 Page 7 FLOW PROCESS FROM NODE 2.11 TO NODE 2.00 IS CODE 3 ---------------------------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< >>>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW) ««< -------------------------------------------------------------------- DEPTH OF FLOW IN 36.0 INCH PIPE IS 27.3 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 7.4 UPSTREAM NODE ELEVATION(FEET) = 1072.40 DOWNSTREAM NODE ELEVATION(FEET) = 1072.02 FLOW LENGTH(FEET) = 76.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 36.00 NUMBER OF PIPES = l PIPE-FLOW(CFS) = 42.50 TRAVEL TIME(MIN.) _ .17 TC(MIN.) = 16.72 .. .. .. ?:?e?r?r?c?c?r*?c?; •?e?:?;?c?r?rir?e*?c?c?c ?r �: ?c**?e ?e?e?r ?e it sY ic?c?t?: �•?�?t?c?t?c?e?ek?r?c*?e?rir?c?e?c?c?;?: ?r*?c*?e ?r ?r**?r�?e?c FLOW PROCESS FROM NODE 2.00 TO NODE 2.00 IS CODE = 1 ---------------------------------------------------------------------------- »»>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< »»>AND COMPUTE VARIOUS CONFLUENCED STREAM VALUES««< -------------------------------------------------------------------- TOTAL NUMBER OF STREAMS = 2 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 2 ARE: TIME OF CONCENTRATION(MIN.) = 16.72 RAINFALL INTENSITY(INCH/HR) = 2.88 AREA -AVERAGED FM(INCH/HR) = .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 EFFECTIVE STREAM AREA(ACRES) 16.70 TOTAL STREAM AREA(ACRES) = 16.70 PEAK FLOW RATE(CFS) AT CONFLUENCE = 42.50 RAINFALL INTENSITY AND TIME OF CONCENTRATION RATIO CONFLUENCE FORMULA USED FOR 2 STREAMS. �* PEAK FLOW RATE TABLE ** Q Tc Intensit Fp Ap Fm Ae (CFS) (MIN.) (INCH/HR� (INCH/HR) (INCH/HR) (ACRES) 1 160.85 15.81 2.983 .46 .22 .10 58.76 2 156.10 22.57 2.409 .44 .24 .11 72.74 3 152.31 24.11 2.316 .43 .25 .11 74.26 4 161.96 16.72 2.885 .46 .22 .10 61.42 COMPUTED CONFLUENCE ESTIMATES ARE AS FOLLOWS: PEAK FLOW RATE(CFS) = 161.96 TG(MIN.) = 16.716 EFFECTIVE AREA(ACRES) = 61.42 AREA -AVERAGED FM(INCH/HR) _ .10 AREA -AVERAGED Fp(INCH/HR) _ .46 AREA -AVERAGED Ap = .22 TOTAL AREA(ACRES) = 74.26 ?r :: i:: .. :r*?c ?t ?r ?: ?:•rk ; .. ?t?:.. .. �i°k'.r?r?...':?c?r?r'.. ?c ?r ?c?r**irk?: :Y it*?r**�*?r f: *:: ?e :: ?r*?: *4t*?r*i:::.. *X ?r-.. ?r :r*?c 4: �Y?r FLOW PROCESS FROM NODE 2.00 TO NODE 3.00 IS CODE = 3 ---------------------------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< -------------------------------------------------------------------- DEPTH OF FLOW IN 51.0 INCH PIPE IS 40.1 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 13.5 UPSTREAM NODE ELEVATION(FEET) = 1072.02 DOWNSTREAM NODE ELEVATION(FEET) = 1069.92 FLOW LENGTH(FEET) = 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 51.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 161.96 TRAVEL TIME(MIN.) _ .25 TC(MIN.) = 16.96 Page 8 is it is ii is is ie ie iric it is is is ie is sY ii ie ie is ie ie it it is it it is ie ie is is is ie is is it it it ie is it ie itir it is it is it is it it is ie it it itic ie ie it ie it it is ie iFic it ie ie ie ie ie FLOW PROCESS FROM NODE 3.00 TO NODE 3.00 IS CODE = 8 ---------------------•--•----------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 100 YEAR RAINFALL INTENSITY(INCH/HR) = 2.860 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 1.25 SUBAREA RUNOFF(CFS) = 3.13 EFFECTIVE AREA(ACRES) = 62.67 AREA -AVERAGED FM(INCH/HR) _ .10 AREA -AVERAGED Fp(INCH/HR) = .46 AREA -AVERAGED Ap = .22 TOTAL AREA(ACRES) = 75.51 PEAK FLOW RATE(CFS) = 161.96 TC(MIN) = 16.96 is is ie is ie it is it is it it is ie it is is is is is it it ie * it it it ie it is is is it is it ie is ie is is is is is is ii it is is is is is is ie is is is it stir is it it 4 it it it it is it is is ie it it ie ie is FLOW PROCESS FROM NODE 3.00 TO NODE 4.00 IS CODE = 3 ---------------------------------------------------------------------------- >>>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW) ««< ------------------------------------------------------------------- DEPTH OF FLOW IN 51.0 INCH PIPE IS 37.1 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 14.6 UPSTREAM NODE ELEVATION(FEET) = 1069.92 DOWNSTREAM NODE ELEVATION(FEET) = 1069.17 FLOW LENGTH(FEET) = 60.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 51.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 161.96 TRAVEL TIME(MIN.) _ .07 TC(MIN.) = 17.03 is�".i:�'t�r'X":•iC'h''.t'iCif it:[iC 1c 1'C�St'X jt 'i'X �r i:.`':Sf'ir �r`'.t'C�•'iC'ic'X ii iC:c�c:r�.i��iC:t i't if it �'r it it it �.t �`'.f wit X' ii:t'H:r)Yi'ii:'ii ii ii.��t .'": )'t :t 'X �C lit it )'t FLOW PROCESS FROM NODE 4.00 TO NODE 4.00 IS CODE = 1 ---------------------------------------------------------------------------- »»>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< -------------------------------------------------------------------------- TOTAL NUMBER OF STREAMS = 2 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 1 ARE: TIME OF CONCENTRATION(MIN.) = 17.03 RAINFALL INTENSITY(INCH/HR) = 2.85 AREA -AVERAGED FM(INCH/HR) = .10 AREA -AVERAGED Fp(INCH/HR) = .46 AREA -AVERAGED Ap = .22 EFFECTIVE STREAM AREA(ACRES) = 62.67 TOTAL STREAM AREA(ACRES) = 75.51 PEAK FLOW RATE(CFS) AT CONFLUENCE = 161.96 ii'.cici:iricic��„��*i:*ic*isisiricic�•*icir�:isii**�•itir*ic.�•*iticicic*i:ir•kit:ei:icirii*i:�:.it�•#�'; ic*iesYi:ic�•ici.•R•i:i:**ie:': FLOW PROCESS FROM NODE 4.10 TO NODE 4.20 IS CODE = 2.1 ---------------------------------------------------------------------------- »»>RATIONAL METHOD INITIAL SUBAREA ANALYSIS««< -------------------------------------------------------------------------- DEVELOPMENT IS COMMERCIAL TC = K*[(LENGTH** 3.00)/(ELEVATION CHANGE)]"* .20 INITIAL SUBAREA FLOW-LENGTH(FEET) = 511.00 UPSTREAM ELEVATION(FEET) = 1085.00 DOWNSTREAM ELEVATION(FEET) = 1084.25 ELEVATION DIFFERENCE(FEET) = .75 TC(MIN.) = .304*[( 511.00** 3.00)/( .75)]** .20 = 13.580 100 YEAR RAINFALL INTENSITY(INCH/HR) = 3.268 Page 9 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA RUNOFF(CFS) = 8.07 TOTAL AREA(ACRES) = 2.81 PEAK FLOW RATE(CFS) = 8.07 is is 3r Yr i<Yc is $c fc Yt ie k ie ie it Yc is it it it it it i< is ie icir is is Ye Yt it it is ie is & it is it iricYr Yc Yr is Ytic ie it it it Ye Yc Yc it Yc Yt it it is is is ie i<it it Yi Yt Yt is Yr Yt Yc Yr Yc FLOW PROCESS FROM NODE 4.20 TO NODE 4.30 IS CODE = 3 ---------------------------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< -------------------------------------------------------------------------- DEPTH OF FLOW IN 21.0 INCH PIPE IS 13.4 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 5.0 UPSTREAM NODE ELEVATION(FEET) = 1078.25 DOWNSTREAM NODE ELEVATION(FEET) = 1077.25 FLOW LENGTH(FEET) = 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 21.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 8.07 TRAVEL TIME(MIN.) _ .67 TC(MIN.) = 14.25 it i; � Yc it it it i< Yt Y: is Y< :Y Yc it & i<�'<Yt it Yt Ye i; Yt it Yr is .'c i<Ye it ie i<Yr Yr � i; Yr it it is Yc Yc Yc Yr :c Yt Yeir Yt it � °k it is it � is it it is it it i< is is is � & is i; is it Yr Yc FLOW PROCESS FROM NODE 4.30 TO NODE 4.30 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 100 YEAR RAINFALL INTENSITY (INCH/HR) = 3.175 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 2.81 SUBAREA RUNOFF(CFS) = 7.84 EFFECTIVE AREA(ACRES) = 5.62 AREA -AVERAGED FM(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) _ .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 5.62 PEAK FLOW RATE(CFS) = 15.68 TC(MIN) = 14.25 Y:Y: Yr Yr Yt is is is is & �• -k is i; is i; �• is is is is is *Yc is is Yr is Yt Yc � it it is it & it it Yc t is it icic it * k is it i; it it is � it it is it i<i< it i< Yr is it & Y: Yr Yc Yc it Yr is is is Yc FLOW PROCESS FROM NODE 4.30 TO NODE 4.40 IS CODE = 3 ---------------------------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< ----------------------------------------------------------------- DEPTH OF FLOW IN 27.0 INCH PIPE IS 17.2 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 5.9 UPSTREAM NODE ELEVATION(FEET) = 1077.25 DOWNSTREAM NODE ELEVATION(FEET) = 1076.25 FLOW LENGTH(FEET) = 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 27.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 15.68 TRAVEL TIME(MIN.) _ .57 TC(MIN.) = 14.82 Yci: ie Yc i<�r::Y:Y:•�•�•Yr Yr x Yt Yc Y.•Ye�•Yc it hi: ie it i; Yr is i;Y::cY:•i:Y:i: it ie it kY:i: is Yr is Yr Yr ic:�&Y:Y:Yc&Yc ir�•i: kir�i; Yc is '.: Yr �i: it it i; Y: ie i; kic i:.. FLOW PROCESS FROM NODE 4.40 TO NODE 4.40 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< ---------------------------------------------------------------------------- 100 YEAR RAINFALL INTENSITY (INCH/HR) = 3.101 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 Page 10 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 2.81 SUBAREA RUNOFF(CFS) = 7.65 EFFECTIVE AREA(ACRES) = 8.43 AREA -AVERAGED FM(INCH/HR) _ .07 AREA -AVERAGED Fp(INCH/HR) _ .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 8.43 PEAK FLOW RATE(CFS) = 22.96 TC(MIN) = 14.82 is it Y: �Yt Yr it Yt Yr Yr Ye Yr Ye Ye Yr Yr Yr Yr Ye irYr Yric Yr.Yr Yc it it Yr Yr it Yr Yt ie Yt Yr it Yr Yt Yr Yc it it Yc it * is is Yc is Yr it Yr it ie Yc i< it Yr i<Yr Yr Yc Yt Yt Yr it Yt fr Yt it Yr Yt i:Ye Ye FLOW PROCESS FROM NODE 4.40 TO NODE 4.50 IS CODE = 3 ---------------------------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESTZE (NON -PRESSURE FLOW)««< ---------------------------------------------------------------------------- ---------------------------------------------------------------------------- DEPTH OF FLOW IN 30.0 INCH PIPE IS 20.5 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 6.4 UPSTREAM NODE ELEVATION(FEET) = 1076.25 DOWNSTREAM NODE ELEVATION(FEET) = 1075.25 FLOW LENGTH(FEET) = 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 30.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 22.96 TRAVEL TIME(MIN.) _ .52 TC(MIN.) = 15.34 �• it �• ;q it Yr Y:. it � ih Yr � Ye Y: Ye Y:Yc Yr Y: Yr � Yr Yrir Yr i< Yr Yr � k � :r i; is is Y: it � aY Yr � Yr Yr i; � kYr Ye Ye Y: Yt � i; :t is & :.• � Y: �• is Y: �•Y::: Y: it Yr it it �• � it k ir'.e FLOW PROCESS FROM NODE 4.50 TO NODE 4.50 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< ---------------------------------------------------------------------------- 100 YEAR RAINFALL INTENSITY(INCH/HR) = 3.037 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 2.81 SUBAREA RUNOFF(CFS) = 7.49 EFFECTIVE AREA(ACRES) = 11.24 AREA -AVERAGED FM(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 11.24 PEAK FLOW RATE(CFS) 29.97 TC(MIN) = 15.34 Yr Yr Y;Yr Yt � � a Y: � Y; it is is it :4 is Yr Ycir is i<i:Yt Ye it Yr it is Yr � Yr Yr it it it it Yr it Yr Yt °k Yr Yt i<it i<Y: Y: Y: „ Y: ek & i< is it X'.e is it i; .r X �• is i; Yt � Yr Yt is Yr it Yt it FLOW PROCESS FROM NODE 4.50 TO NODE 4.60 IS CODE = 3 ---------------------------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< ---------------------------------------------------------------------------- ---------------------------------------------------------------------------- DEPTH OF FLOW IN 33.0 INCH PIPE IS 22.8 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 6.9 UPSTREAM NODE ELEVATION(FEET) = 1075.25 DOWNSTREAM NODE ELEVATION(FEET) = 1074.25 FLOW LENGTH(FEET) = 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 33.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 29.97 TRAVEL TIME(MIN.) _ .49 TC(MIN.) = 15.83 Y: R• :: �•Y: Y: Y; Yr� is is Yr :Y Yr is Y: Y: Ye it is i; is �"Yt i< �• � it is �• Y::: Yc �k Yr is Yr Yr Y: Yr is Yc :.• Yt i::.• is � �• it � k i:Ye is � Yc it it Y: it Y: ti it it Yt � is ie it is �• :: � it i; FLOW PROCESS FROM NODE 4.60 TO NODE 4.60 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< ---------------------------------------------------------------------------- ---------------------------------------------------------------------------- 100 YEAR RAINFALL INTENSITY(INCH/HR) = 2.981 SOIL CLASSIFICATION IS "B" Page 11 COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 2.81 SUBAREA RUNOFF(CFS) = 7.35 EFFECTIVE AREA(ACRES) = 14.05 AREA -AVERAGED FM(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 14.05 PEAK FLOW RATE(CFS) = 36.75 TC(MIN) = 15.83 k kitkkkkir it it it iskkkisk itk is �tk kkkkkkkkkkick it ickkkkic is iskkkkkkirkkkkkkirkkkkick kkkir is it ickkit irk ie FLOW PROCESS FROM NODE 4.60 TO NODE 4.70 IS CODE = 3 ---------------------------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< ---------------------------------------------------------------------------- ---------------------------------------------------------------------------- DEPTH OF FLOW IN 36.0 INCH PIPE IS 24.3 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 7.2 UPSTREAM NODE ELEVATION(FEET) = 1074.25 DOWNSTREAM NODE ELEVATION(FEET) = 1073.25 FLOW LENGTH(FEET) = 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 36.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 36.75 TRAVEL TIME(MIN.) _ .46 TC(MIN.) = 16.29 k ick kkirk �•ick kir kickkkkkkkkkkkkkkickkkkkkirk kirkkkkkkkkkkkkkkkkkkkkkkiek kickkkkkkkkkkk FLOW PROCESS FROM NODE 4.70 TO NODE 4.70 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< ---------------------------------------------------------------------------- ---------------------------------------------------------------------------- 100 YEAR RAINFALL INTENSITY(INCH/HR) = 2.930 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 2.81 SUBAREA RUNOFF(CFS) = 7.22 EFFECTIVE AREA(ACRES) = 16.86 AREA -AVERAGED Fm(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 16.86 PEAK FLOW RATE(CFS) = 43.32 TC(MIN) = 16.29 iek i:kkkkkkkkkkkkit ickkkkkkkkkki:k kkkkkir iskkitkkkkkkkkkkkkkk:tki:kkkkkkkkkkkkk'.tkkkk'.c is FLOW PROCESS FROM NODE 4.70 TO NODE 4.80 IS CODE = 3 ---------------------------------------------------------------------------- >>>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< ---------------------------------------------------------------------------- ---------------------------------------------------------------------------- DEPTH OF FLOW IN 36.0 INCH PIPE IS 27.8 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 7.4 UPSTREAM NODE ELEVATION(FEET) = 1073.25 DOWNSTREAM NODE ELEVATION(FEET) = 1072.25 FLOW LENGTH(FEET) = 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 36.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 43.32 TRAVEL TIME(MIN.) _ .45 TC(MIN.) = 16.74 .. '.c '.:'.r it is it it is kkk �•ic it it is kick it ickkkkkkki: kkick is it is it it it it is �•kkkkir it ick kir it irk is kic kkkkkkkkkic ickkkkick FLOW PROCESS FROM NODE 4.80 TO NODE 4.80 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< ---------------------------------------------------------------------------- ---------------------------------------------------------------------------- 100 YEAR RAINFALL INTENSITY(INCH/HR) = 2.883 Page 12 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 2.81 SUBAREA RUNOFF(CFS) = 7.10 EFFECTIVE AREA(ACRES) = 19.67 AREA -AVERAGED FM(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 19.67 PEAK FLOW RATE(CFS) = 49.70 TC(MIN) = 16.74 k it it is is kk kickkkic irk iek kir ie irkkkkkkick kkkkkiekkkkki:Xir ickkkkkis irkkkkkkkkkkickkkkic :rk kiekkkic it FLOW PROCESS FROM NODE 4.80 TO NODE 4.90 IS CODE = 3 ---------------------------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< >>>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< ---------------------------------------------------------------------------- ---------------------------------------------------------------------------- DEPTH OF FLOW IN 39.0 INCH PIPE IS 28.2 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 7.7 UPSTREAM NODE ELEVATION(FEET) = 1072.25 DOWNSTREAM NODE ELEVATION(FEET) = 1071.25 FLOW LENGTH(FEET) = 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 39.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 49.70 TRAVEL TIME(MIN.) _ .43 TC(MIN.) = 17.17 kkkirkkkkkitkkitkkickkkkkkkkkkkkkkkkkkkkkkkkkkickkkkkkkkkkkkkkkkk*i:4tkkiriricivkitiritkkir FLOW PROCESS FROM NODE 4.90 TO NODE 4.90 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< ---------------------------------------------------------------------------- ---------------------------------------------------------------------------- 100 YEAR RAINFALL INTENSITY(INCH/HR) = 2.839 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 2.81 SUBAREA RUNOFF(CFS) = 6.99 EFFECTIVE AREA(ACRES) = 22.48 AREA -AVERAGED FM(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 22.48 PEAK FLOW RATE(CFS) = 55.92 TC(MIN) = 17.17 k kkir ir:'r it it i;ie�:c it i:ic4.•::ir::-k 4c is is it is ic�i:�-ie�ic 4r is ir4:4r4.•ie ie.;i;ire•i:i:i:i.•ie::iri;iti:iri:'.: :r i; l: it �k ie :r ie'k is is is :r��� �•ic FLOW PROCESS FROM NODE 4.90 TO NODE 4.10 IS CODE = 3 ---------------------------------------------------------------------------- >>>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< >>>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< ---------------------------------------------------------------------------- ---------------------------------------------------------------------------- DEPTH OF FLOW IN 39.0 INCH PIPE IS 31.4 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 7.8 UPSTREAM NODE ELEVATION(FEET) = 1071.25 DOWNSTREAM NODE ELEVATION(FEET) = 1070.50 FLOW LENGTH(FEET) = 150.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 39.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 55.92 TRAVEL TIME(MIN.) _ .32 TC(MIN.) = 17.49 i:kkic is kirk is i;kk�ir:�itkkkkk*kkkkkkkkir&kkkkiekk kirkkkkkkkiekkkkkkirkkkkkkit �i:kkir is i:kkkkkk FLOW PROCESS FROM NODE 4.10 TO NODE 4.10 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< ---------------------------------------------------------------------------- ---------------------------------------------------------------------------- Page 13 100 YEAR RAINFALL INTENSITY(INCH/HR) = 2.808 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 2.02 SUBAREA RUNOFF(CFS) = 4.97 EFFECTIVE AREA(ACRES) = 24.50 AREA -AVERAGED FM(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 24.50 PEAK FLOW RATE(CFS) = 60.25 TC(MIN) = 17.49 ::'.: Yr is it �'t is 4r*4t4: 4t is is ir:: fr �r 4c 4r it it it it 4r 4: Ae it is it it s4 it it �c �:*4c it 4t 4r it 4r it fe s4 is �44c 4::4r:r sY 4t 4t it*d:.:e �c it it is :r it �c��••k is i;�:c�1; Yr FLOW PROCESS FROM NODE 4.10 TO NODE 4.00 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 42.0 INCH PIPE IS 29.1 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 8.5 UPSTREAM NODE ELEVATION(FEET) = 1070.50 DOWNSTREAM NODE ELEVATION(FEET) = 1069.17 FLOW LENGTH(FEET) = 240.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 42.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 60.25 TRAVEL TIME(MIN.) _ .47 TC(MIN.) = 17.96 it i.• � it �: 4c it*is is ir:c 9c it*ici: 4r dt*ir is it 4t is it is 4r 4r �Y it it 4t it �Y it*ie 3r*ic it it ft sY*ic it ie dr it:t it it it 4:i: ie it i:4t is sY is**�k it 4r 4t is is is fc is is FLOW PROCESS FROM NODE 4.00 TO NODE 4.00 IS CODE = 1 »»>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< »»>AND COMPUTE VARIOUS CONFLUENCED STREAM VALUES««< TOTAL NUMBER OF STREAMS = 2 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 2 ARE: TIME OF CONCENTRATION(MIN.) = 17.96 RAINFALL INTENSITY(INCH/HR) = 2.76 AREA -AVERAGED FM(INCH/HR) = .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 EFFECTIVE STREAM AREA(ACRES) = 24.50 TOTAL STREAM AREA(ACRES) = 24.50 PEAK FLOW RATE(CFS) AT CONFLUENCE = 60.25 RAINFALL INTENSITY AND TIME OF CONCENTRATION RATIO CONFLUENCE FORMULA USED FOR 2 STREAMS. ** PEAK FLOW RATE TABLE ** Q Tc Intensit FP Ap FM Ae (CFS) (MIN.) (INCH/HR� (INCH/HR) (INCH/HR) (ACRES) 1 218.66 16.12 2.948 .51 .18 .09 82.00 2 221.00 17.03 2.853 .51 .18 .09 85.91 3 207.97 22.89 2.389 .48 .21 .10 98.49 4 202.13 24.43 2.298 .47 .21 .10 100.01 5 221.29 17.96 2.763 .50 .19 .09 88.97 COMPUTED CONFLUENCE ESTIMATES ARE AS FOLLOWS: PEAK FLOW RATE(CFS) = 221.29 TC(MIN.) = 17.961 EFFECTIVE AREA(ACRES) = 88.97 AREA -AVERAGED FM(INCH/HR) _ .09 AREA -AVERAGED Fp(INCH/HR) _ .50 AREA -AVERAGED Ap = .19 TOTAL AREA(ACRES) = 100.01 it'r;: :t :'t it*ic is �•ir�:4:i:dci:�**9r it**�k*'c��t Yck*it it is �Y it �: it Yc �r�ic�ir �:***•tr:t it fc �: is 4rfe it is*4: ': 4c s: is �-.t 4r *ir is it �Y :r 4: :: it Page 14 FLOW PROCESS FROM NODE 4.00 TO NODE 5.00 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 60.0 INCH PIPE IS 46.7 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 13.5 UPSTREAM NODE ELEVATION(FEET) = 1069.17 DOWNSTREAM NODE ELEVATION(FEET) = 1065.00 FLOW LENGTH(FEET) = 495.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 60.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 221.29 TRAVEL TIME(MIN.) _ .61 TC(MIN.) = 18.57 &i: icf',.•�ic it it icftir it iricf fi: it it it is is it it irf it it it itf ie ief i�ir ie it ie sY it ie it is sY is irf is it it it irf it it irf it ie it :rffie it&fir k it it it is FLOW PROCESS FROM NODE 5.00 TO NODE 5.00 IS CODE = 8 -------------------------------------------- >ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 100 YEAR RAINFALL INTENSITY(INCH/HR) = 2.708 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 4.18 SUBAREA RUNOFF(CFS) 9.91 EFFECTIVE AREA(ACRES) = 93.15 AREA -AVERAGED FM(INCH/HR) _ .09 AREA -AVERAGED Fp(INCH/HR) = .51 AREA -AVERAGED Ap = .18 TOTAL AREA(ACRES) = 104.19 PEAK FLOW RATE(CFS) = 221.29 TC(MIN) = 18.57 it is i; is is is it is � is i; i< it it k i; it i<ir it it it i; it it it it is it is ir'.r it Yr it is is it i; is it it & it � it it it :k it is ie is it is it is it it Yr it ie it it is it it it � is it is it is it is FLOW PROCESS FROM NODE 5.00 TO NODE 6.00 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 57.0 INCH PIPE IS 43.4 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 15.3 UPSTREAM NODE ELEVATION(FEET) = 1065.00 DOWNSTREAM NODE ELEVATION(FEET) = 1064.07 FLOW LENGTH(FEET) = 80.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 57.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 221.29 TRAVEL TIME(MIN.) _ .09 TC(MIN.) = 18.66 it i.•ir it �.•:: is i:.i: is it«ic ire �•�•ir tic it is it i; it sY.�ir it it it is isfir*i: irir icn it i�ir sY ic�ir it ie��i; it it it it sir it is it it sY :Y it it it it it it it is ir�ir FLOW PROCESS FROM NODE 6.00 TO NODE 6.00 IS CODE = 8 ------------------------------------------- >>>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 100 YEAR RAINFALL INTENSITY(INCH/HR) = 2.701 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = .58 SUBAREA RUNOFF(CFS) = 1.37 EFFECTIVE AREA(ACRES) = 93.73 AREA -AVERAGED FM(INCH/HR) _ .09 AREA -AVERAGED Fp(INCH/HR) = .51 AREA -AVERAGED Ap = .18 TOTAL AREA(ACRES) = 104.77 PEAK FLOW RATE(CFS) = 221.29 TC(MIN) = 18.66 Page 15 FLOW PROCESS FROM NODE 6.00 TO NODE 6.00 IS CODE= 1 ---------------------------------------------------------------------------- >>>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< - ----------------------------------------------------------------- TOTAL NUMBER OF STREAMS = 2 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 1 ARE: TIME OF CONCENTRATION(MIN.) = 18.66 RAINFALL INTENSITY(INCH/HR) = 2.70 AREA -AVERAGED FM(INCH/HR) = .09 AREA -AVERAGED Fp(INCH/HR) = .51 AREA -AVERAGED Ap = .18 EFFECTIVE STREAM AREA(ACRES) = 93.73 TOTAL STREAM AREA(ACRES) = 104.77 PEAK FLOW RATE(CFS) AT CONFLUENCE = 221.29 FLOW PROCESS FROM NODE 6.10 TO NODE 6.20 IS CODE = 2.1 ---------------------------------------------------------------------------- »»>RATIONAL METHOD INITIAL SUBAREA ANALYSIS««< DEVELOPMENT IS COMMERCIAL TC = K*[(LENGTH** 3.00)/(ELEVATION CHANGE)]** .20 INITIAL SUBAREA FLOW-LENGTH(FEET) = 445.00 UPSTREAM ELEVATION(FEET) = 1080.00 DOWNSTREAM ELEVATION(FEET) = 1079.00 ELEVATION DIFFERENCE(FEET) = 1.00 TC(MIN.) = .304*[( 445.00** 3.00)/( 1.00)]** .20 = 11.800 100 YEAR RAINFALL INTENSITY(INCH/HR) = 3.555 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA RUNOFF(CFS) = 7.20 TOTAL AREA(ACRES) = 2.30 PEAK FLOW RATE(CFS) = 7.20 FLOW PROCESS FROM NODE 6.20 TO NODE 6.30 IS CODE = 3 ---------------------------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< ---------------------------------------------------------------------------- ---------------------------------------------------------------------------- DEPTH OF FLOW IN 18.0 INCH PIPE IS 14.7 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 4.7 UPSTREAM NODE ELEVATION(FEET) = 1073.00 DOWNSTREAM NODE ELEVATION(FEET) = 1072.00 FLOW LENGTH(FEET) = 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 18.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 7.20 TRAVEL TIME(MIN.) _ .71 TC(MIN.) = 12.51 FLOW PROCESS FROM NODE 6.30 TO NODE 6.30 IS CODE 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< ---------------------------------------------------------------------------- 100 YEAR RAINFALL INTENSITY(INCH/HR) = 3.432 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 2.30 SUBAREA RUNOFF(CFS) = 6.95 Page 16 EFFECTIVE AREA(ACRES) = 4.60 AREA -AVERAGED FM(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) _ .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 4.60 PEAK FLOW RATE(CFS) = 13.90 TC(MIN) = 12.51 it ie is it is is is it it is i:ici:i: is is it it it it it is i:i: is it is is it is s4 it is it is it ic. is is it it it it it it is it is is it is ie it it it is it is it is is it is it it it is it is is 'kir is is irk FLOW PROCESS FROM NODE 6.30 TO NODE 6.40 IS CODE = 3 --------------------------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< >>>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< ---------------------------------------------------------------------------- ---------------------------------------------------------------------------- DEPTH OF FLOW IN 24.0 INCH PIPE IS 17.7 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 5.6 UPSTREAM NODE ELEVATION(FEET) = 1072.00 DOWNSTREAM NODE ELEVATION(FEET) = 1071.00 FLOW LENGTH(FEET) = 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 24.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 13.90 TRAVEL TIME(MIN.) _ .59 TC(MIN.) = 13.11 is it is is it it is ie � X ieic is is it it � is is is ie it is is it is ie i< it it s4 is it is it is it is is it is i; it it is is it it it it it it is it ie is ie it it it is it it it it � it it is it it is iric i<ic FLOW PROCESS FROM NODE 6.40 TO NODE 6.40 IS CODE _ ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< ---------------------------------------------------------------------------- ---------------------------------------------------------------------------- 100 YEAR RAINFALL INTENSITY(INCH/HR) = 3.338 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 2.30 SUBAREA RUNOFF(CFS) = 6.75 EFFECTIVE AREA(ACRES) = 6.90 AREA -AVERAGED FM(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 6.90 PEAK FLOW RATE(CFS) = 20.26 TC(MIN) = 13.11 is itic i; * i; is it it it � it is is it is i! is it i; it it i; it it :Y it is i; i; is it it is is is iri: is it i; is i• it it it � it is is � is it it it it is i< it it it is it is it it ie � it it it it is it is •k FLOW PROCESS FROM NODE 6.40 TO NODE 6.50 IS CODE = 3 --------------------------------------------------------------------------- >>>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW) ««< - - - -------------------------------------------------------- DEPTH OF FLOW IN 27.0 INCH PIPE IS 21.0 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 6.1 UPSTREAM NODE ELEVATION(FEET) = 1071.00 DOWNSTREAM NODE ELEVATION(FEET) = 1070.00 FLOW LENGTH(FEET) = 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 27.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 20.26 TRAVEL TIME(MIN.) _ .55 TC(MIN.) = 13.65 it it�i:„i;i;iti;i: is is it iris�ic it it it i;�i:i;ir�•i; is it it sY i; ie&ir iri; *i<i<i: is i; �i<ki;iei:iei;i:i:.i;iri:iti; i.•ic i; is ic�ir irt��i: ie is i;� kir FLOW PROCESS FROM NODE 6.50 TO NODE 6.50 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< ---------------------------------------------------------------------------- ---------------------------------------------------------------------------- 100 YEAR RAINFALL INTENSITY(INCH/HR) = 3.257 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 Page 17 SUBAREA AREA(ACRES) = 2.30 SUBAREA RUNOFF(CFS) = 6.59 EFFECTIVE AREA(ACRES) 9.20 AREA -AVERAGED Fm(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 9.20 PEAK FLOW RATE(CFS) = 26.35 TC(MIN) = 13.65 4:i: sk it 4t it:c it is icir 4r ir:c sk 4r it it it tc it it it it it Yr it is fr sk it it 4r �r 4r ft it it is is it �44t Yr 4r it it 4t it 4: it it it it ie it 4c is is 4r Yr is&it is it it 4c �r do it it it 4r is it FLOW PROCESS FROM NODE 6.50 TO NODE 6.60 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 30.0 INCH PIPE IS 22.9 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 6.5 UPSTREAM NODE ELEVATION(FEET) = 1070.00 DOWNSTREAM NODE ELEVATION(FEET) = 1069.00 FLOW LENGTH(FEET) = 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 30.00 NUMBER OF PIPES 1 PIPE-FLOW(CFS) = 26.35 TRAVEL TIME(MIN.) _ .51 TC(MIN.) = 14.16 •fe�drirskskic»:r::kir�:sk�:rfr�ir�i:ieic� kiririeit&ire'rir�4t��*icle4ti:ir�i:friricsk�:r4c�kicq:fc:tic�Xir4r4r�4r�irici:irirsYd:�4'r FLOW PROCESS FROM NODE 6.60 TO NODE 6.60 IS CODE = 8 ------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 100 YEAR RAINFALL INTENSITY(INCH/HR) = 3.186 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 2.30 SUBAREA RUNOFF(CFS) = 6.44 EFFECTIVE AREA(ACRES) = 11.50 AREA -AVERAGED Fm(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 11.50 PEAK FLOW RATE(CFS) = 32.20 TC(MIN) = 14.16 i•i:ir:r it is ir�ir:r is 4:ici: it it is Yr 4r it �c is is sk ie fr 4c �Y ie icir 4r is ic�ir 4r Yr3r it it it 4:4c*ic is 4c i:iri: is �r is ie 9c ie it 4r 4: is is it is it it it it ic�ie it is 4r it it FLOW PROCESS FROM NODE 6.60 TO NODE 6.70 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW) ««< DEPTH OF FLOW IN 33.0 INCH PIPE IS 24.1 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 6.9 UPSTREAM NODE ELEVATION(FEET) = 1069.00 DOWNSTREAM NODE ELEVATION(FEET) = 1068.00 FLOW LENGTH(FEET) = 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 33.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 32.20 TRAVEL TIME(MIN.) _ .48 TC(MIN.) = 14.64 is �:r�:r�:4r�'.r'„•�•4:ic;: it fe'..•�4r zkx �:��; 4r 4c it �k ie ir:r�'��; sk�4c�4c kfr ;. ��•�:c �: it i:�'..•� ksY is �'�.�i: ir�r dr 4: kir :c wit �: le i:�i: mirk FLOW PROCESS FROM NODE 6.70 TO NODE 6.70 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 100 YEAR RAINFALL INTENSITY(INCH/HR) = 3.123 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) _ .75 Page 18 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 2.30 SUBAREA RUNOFF(CFS) = 6.31 EFFECTIVE AREA(ACRES) = 13.80 AREA -AVERAGED Fm(INCH/HR) _ .07 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 13.80 PEAK FLOW RATE(CFS) = 37.86 TC(MIN) = 14.64 Yc Y: Yc Yt is it is is Yt it it it Y: Yr Y: it Yr Yr Yr Yt Yr Yt is Yr Yr it Yt it is is it it is it Yt it it it i< it i< it is it it Yr i< Yr Yr Yr Yc Yt Yr Y: Ye Y: is Yr Yc i< is i< Yr is Yc irY: ie Y: it it i<ic it ie Yc FLOW PROCESS FROM NODE 6.70 TO NODE 6.80 IS CODE = 3 ---------------------------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< --------------------------------------------------------------------- DEPTH OF FLOW IN 36.0 INCH PIPE IS 24.9 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 7.3 UPSTREAM NODE ELEVATION(FEET) = 1068.00 DOWNSTREAM NODE ELEVATION(FEET) = 1067.00 FLOW LENGTH(FEET) = 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 36.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 37.86 TRAVEL TIME(MIN.) _ .46 TC(MIN.) = 15.10 ...'.:'.t Y:.Yr Yr Yr is k Yr it Yr Yr is Yc ic'.•Yt Yt � Yt Yt �Yr Yr Yt Yc Yc Yc it +,c +,t+,c �Y: Y: it � & it Yt is is irYt � i<it is i< Yr Yr i<Yc Yt Yc Yr YcYt Yt Yc Y: Yt Yc it Yr Yt i:Yc Y< it i; is is is Yr FLOW PROCESS FROM NODE 6.80 TO NODE 6.80 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< ---------------------------------------------------------------------------- 100 YEAR RAINFALL INTENSITY(INCH/HR) = 3.066 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 2.30 SUBAREA RUNOFF(CFS) = 6.19 EFFECTIVE AREA(ACRES) = 16.10 AREA -AVERAGED Fm(INCH/HR) _ .07 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 16.10 PEAK FLOW RATE(CFS) = 43.34 TC(MIN) = 15.10 .... Yc Yc Yc Y: Y: is Yc sY Y: Y: it Y: �- Y.• Y: i; Yr Y:Yr Yt Y: Y:Yr it ie is sY it Yr � :: Yr sY Yr Yt i; Yr it Yt Yr Yt Yc is Y: Yt is ie is is it it it Yc it it k � i:'..• & is Y: � � Y.• � � Ye Y: k �• it Yr Yr FLOW PROCESS FROM NODE 6.80 TO NODE 6.90 IS CODE = 3 ---------------------------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< -------------------------------------------------------------------- DEPTH OF FLOW IN 36.0 INCH PIPE IS 27.8 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 7.4 UPSTREAM NODE ELEVATION(FEET) = 1067.00 DOWNSTREAM NODE ELEVATION(FEET) = 1066.00 FLOW LENGTH(FEET) = 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 36.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 43.34 TRAVEL TIME(MIN.) _ .45 TC(MIN.) = 15.55 Y:.Yc :: �• :; Y: Y::::: Y: Y: � Y.• :: it Y: '.: is Y: Ye �': � Yt � i; � Yc Y: Yr � � � i; &Ye ie * Yr i; it Yr Yc is is � � Y: Y: t Yr Yr is Yr YY is it it Yc � � Yc Y< Yr Y: � a Yr � �• Yr Y: it Y: Yc �• � FLOW PROCESS FROM NODE 6.90 TO NODE 6.90 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 100 YEAR RAINFALL INTENSITY(INCH/HR) = 3.012 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 Page 19 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 2.30 SUBAREA RUNOFF(CFS) = 6.08 EFFECTIVE AREA(ACRES) = 18.40 AREA -AVERAGED Fm(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 18.40 PEAK FLOW RATE(CFS) = 48.64 TC(MIN) = 15.55 Yr Yt Yr it it Yc Yt Y: i<Yc Y: it Yc Yc Y: is is is Yc it is Yr Yt Yc it it ie Ye Yr it Y: is Yc Yc it is it Ye Yc Yc it icYc Yc Yc is is Y: Yr Yr Yr it Y: Ye Yr Yt Y: Yc Yc Yt Yc it Yc Yc is Yc Yt Yr it Yc Yr Y< it Y: & it FLOW PROCESS FROM NODE 6.90 TO NODE 6.10 IS CODE = 3 >>>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 39.0 INCH PIPE IS 27.7 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 7.7 UPSTREAM NODE ELEVATION(FEET) = 1066.00 DOWNSTREAM NODE ELEVATION(FEET) = 1065.25 FLOW LENGTH(FEET) = 150.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 39.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 48.64 TRAVEL TIME(MIN.) _ .32 TC(MIN.) = 15.88 Yc � � Y: is it ic'..•°• � Yc Yc Yr is � Yc :c & i<Yr � Yr it ir. � it � is Y: Yr Yr Yc it Y<Yr Ye Yc Yc :c is it Yc Yc :: is it Yc Y:.i: � � � -k ie Yc � � Yc Yr Yc is Yc � Y: is Yc Yr ir',c'.c %e is it Yc k FLOW PROCESS FROM NODE 6.10 TO NODE 6.10 IS CODE 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 100 YEAR RAINFALL INTENSITY(INCH/HR) = 2.975 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 1.51 SUBAREA RUNOFF(CFS) = 3.94 EFFECTIVE AREA(ACRES) = 19.91 AREA -AVERAGED Fm(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 19.91 PEAK FLOW RATE(CFS) = 51.97 TC(MIN) = 15.88 Yc Yc Yt is Y: Y: ie Yr Yc Yc is Yc Yc is Y: Yr Yc Yc is Yt Ys Yc Yr is i; 9: i<ic Yc Yr it Yt Yr is Yc Yt � is � ie Ye is is is Yc � Yc is Yt �Ytir i<Yc Yr Y<Yc * Yc Yt i<Yr Y: it it Yr is Yr it Y< is is Yc Yc Y: k FLOW PROCESS FROM NODE 6.10 TO NODE 6.11 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 42.0 INCH PIPE IS 30.2 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 7.0 UPSTREAM NODE ELEVATION(FEET) = 1065.25 DOWNSTREAM NODE ELEVATION(FEET) = 1064.50 FLOW LENGTH(FEET) = 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 42.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 51.97 TRAVEL TIME(MIN.) _ .47 TC(MIN.) = 16.35 is Y; Yc Yr is it Yc Yr Y: is it Ye Yc is is Y: it � � Ye is Yc Yc & ir'.r Yt is i< it Yc Yr is Yr ie Ys Yc Y: Ye Y: Yr it Y; Yr Yc Ye Yr is Yc Yc Yc Yt Yr'.r Yc Yt is is � Yr Yr it � Y: Y: it Yc Yt Yc Yr Yr � � it * Yr FLOW PROCESS FROM NODE 6.11 TO NODE 6.11 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 100 YEAR RAINFALL INTENSITY(INCH/HR) = 2.923 SOIL CLASSIFICATION IS "B" Page 20 COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 2.17 SUBAREA RUNOFF(CFS) = 5.56 EFFECTIVE AREA(ACRES) = 22.08 AREA -AVERAGED FM(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 22.08 PEAK FLOW RATE(CFS) = 56.60 TC(MIN) = 16.35 :t',:it:c:Yirkic4r't�:ir'.c4riei:4r'.e:r't:rir�4c::ie�ic4eir:rir�citititi::c4r4r�r4cieie�Arkici:irk::rieie�'tic4r&��':ititirit:rit4riricic4rkir4r4ri: FLOW PROCESS FROM NODE 6.11 TO NODE 6.00 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< >>>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 39.0 INCH PIPE IS 29.7 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 8.3 UPSTREAM NODE ELEVATION(FEET) = 1064.50 DOWNSTREAM NODE ELEVATION(FEET) = 1064.07 FLOW LENGTH(FEET) = 75.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 39.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 56.60 TRAVEL TIME(MIN.) _ .15 TC(MIN.) = 16.50 •k**ir**ir is is it****is is ic;r it is it*ir ir'.:ir*ic it*ir it 4r it 4t �ti it Yc sY4r it fc �'ei::c 4r 4c ��Y sY Yr:r. is is is it is is it do ie ic*:r*ic is is is is it �Y it is ic* FLOW PROCESS FROM NODE 6.00 TO NODE 6.00 IS CODE = 1 »»>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< »»>AND COMPUTE VARIOUS CONFLUENCED-STREAM VALUES««< TOTAL NUMBER OF STREAMS = 2 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 2 ARE: TIME OF CONCENTRATION(MIN.) = 16.50 RAINFALL INTENSITY(INCH/HR) = 2.91 AREA -AVERAGED Fm(INCH/HR) = .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 EFFECTIVE STREAM AREA(ACRES) = 22.08 TOTAL STREAM AREA(ACRES) = 22.08 PEAK FLOW RATE(CFS) AT CONFLUENCE = 56.60 RAINFALL INTENSITY AND TIME OF CONCENTRATION RATIO CONFLUENCE FORMULA USED FOR 2 STREAMS. ** PEAK FLOW RATE TABLE ** Q Tc Intensit Fp Ap FM Ae (CFS) (MIN.) (INCH/H� (INCH/HR) (INCH/HR) (ACRES) 1 274.59 16.82 2.874 .54 .16 .09 108.84 2 275.15 17.73 2.785 .54 .16 .09 112.75 3 273.76 18.66 2.701 .54 .17 .09 115.81 4 254.36 23.59 2.346 .51 .18 .09 125.33 5 247.27 25.15 2.258 .50 .19 .09 126.85 6 273.68 16.50 2.907 .55 .16 .09 107.21 COMPUTED CONFLUENCE ESTIMATES ARE AS FOLLOWS: PEAK FLOW RATE(CFS) = 275.15 TC(MIN.) = 17.728 EFFECTIVE AREA(ACRES) = 112.75 AREA -AVERAGED Fm(INCH/HR) _ .09 AREA -AVERAGED Fp(INCH/HR) = .54 AREA -AVERAGED Ap = .16 TOTAL AREA(ACRES) = 126.85 •fc:c it �•::*�Y:ric:r'.::;*:c**ir*ir*ic is'..•***°k•.c.'.t**ir�ie*4r**-k �Y ic**.*ic it is �'4t*ir**°k•'..•zY is*4r sc***it*:: :r 4e �'c �•:c&ic it*4c FLOW PROCESS FROM NODE 6.00 TO NODE 7.00 IS CODE = 3 Page 21 ---------------------------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW) ««< DEPTH OF FLOW IN 63.0 INCH PIPE IS 48.6 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 15.3 UPSTREAM NODE ELEVATION(FEET) = 1064.07 DOWNSTREAM NODE ELEVATION(FEET) = 1058.97 FLOW LENGTH(FEET) = 500.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 63.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 275.15 TRAVEL TIME(MIN.) _ .54 TC(MIN.) = 18.27 FLOW PROCESS FROM NODE 7.00 TO NODE 7.00 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 100 YEAR RAINFALL INTENSITY(INCH/HR) = 2.735 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 2.23 SUBAREA RUNOFF(CFS) = 5.34 EFFECTIVE AREA(ACRES) = 114.98 AREA -AVERAGED FM(INCH/HR) _ .09 AREA -AVERAGED Fp(INCH/HR) = .54 AREA -AVERAGED Ap = .16 TOTAL AREA(ACRES) = 129.08 PEAK FLOW RATE(CFS) = 275.15 TC(MIN) = 18.27 FLOW PROCESS FROM NODE 7.00 TO NODE 8.00 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 63.0 INCH PIPE IS 49.4 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 15.1 UPSTREAM NODE ELEVATION(FEET) = 1058.97 DOWNSTREAM NODE ELEVATION(FEET) = 1055.52 FLOW LENGTH(FEET) = 350.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 63.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 275.15 TRAVEL TIME(MIN.) _ .39 TC(MIN.) = 18.66 FLOW PROCESS FROM NODE 8.00 TO NODE 8.00 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 100 YEAR RAINFALL INTENSITY(INCH/HR) = 2.701 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 2.78 SUBAREA RUNOFF(CFS) = 6.57 EFFECTIVE AREA(ACRES) = 117.76 AREA -AVERAGED Fm(INCH/HR) _ .09 AREA -AVERAGED Fp(INCH/HR) = .55 AREA -AVERAGED Ap = .16 TOTAL AREA(ACRES) = 131.86 PEAK FLOW RATE(CFS) = 276.85 TC(MIN) = 18.66 Page 22 FLOW PROCESS FROM NODE 8.00 TO NODE 9.00 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 63.0 INCH PIPE IS 50.4 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 14.9 UPSTREAM NODE ELEVATION(FEET) = 1055.52 DOWNSTREAM NODE ELEVATION(FEET) = 1052.07 FLOW LENGTH(FEET) = 360.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 63.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 276.85 TRAVEL TIME(MIN.) _ .40 TC(MIN.) = 19.06 k kkkk.Yt ick kYrkkkick itk kYrkir Yck kitkkkitkkkkkkYckkkkkYekkkkYr iekkkkkirkkkkkkic irk kYrkkkkkkkkkkk FLOW PROCESS FROM NODE 9.00 TO NODE 9.00 IS CODE = 8 ----------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 100 YEAR RAINFALL INTENSITY(INCH/HR) = 2.666 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 2.75 SUBAREA RUNOFF(CFS) = 6.41 EFFECTIVE AREA(ACRES) = 120.51 AREA -AVERAGED FM(INCH/HR) _ .09 AREA -AVERAGED Fp(INCH/HR) = .55 AREA -AVERAGED Ap = .16 TOTAL AREA(ACRES) = 134.61 PEAK FLOW RATE(CFS) = 279.62 TC(MIN) = 19.06 kkkkkkkk•'kkkkkkkkkkkkkkkkki;kkkkkkk kk itk kirk kYtkkkkkkkkkkkkkkkkkkkkkkkkkkkk �•kkkkk FLOW PROCESS FROM NODE 9.00 TO NODE 9.00 IS CODE = 8 ---------------------------------------------------------------------------- >>>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 100 YEAR RAINFALL INTENSITY(INCH/HR) = 2.666 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 1.73 SUBAREA RUNOFF(CFS) = 4.03 EFFECTIVE AREA(ACRES) = 122.24 AREA -AVERAGED FM(INCH/HR) .09 AREA -AVERAGED Fp(INCH/HR) = .55 AREA -AVERAGED Ap = .16 TOTAL AREA(ACRES) = 136.34 PEAK FLOW RATE(CFS) = 283.66 TC(MIN) = 19.06 k irkkkkir kk kk kkki;kkkkitkkkkkkkkkkkkkkkk kkkkirk kk kkkkkkkkkkki;k�kkkirk kkkkkkkkkkkkYc FLOW PROCESS FROM NODE 9.00 TO NODE 10.00 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 51.0 INCH PIPE IS 41.6 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 22.9 UPSTREAM NODE ELEVATION(FEET) = 1052.07 DOWNSTREAM NODE ELEVATION(FEET) = 1049.07 FLOW LENGTH(FEET) = 100.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 51.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 283.66 TRAVEL TIME(MIN.) _ .07 TC(MIN.) = 19.13 END OF STUDY SUMMARY: Page 23 TOTAL AREA(ACRES) = 136.34 TC(MIN.) = 19.13 EFFECTIVE AREA(ACRES) = 122.24 AREA -AVERAGED Fm(INCH/HR)= .09 AREA -AVERAGED Fp(INCH/HR) _ .55 AREA -AVERAGED Ap = .16 PEAK FLOW RATE(CFS) = 283.66 ** PEAK FLOW RATE TABLE ** Q Tc Intensit Fp Ap FM Ae (CFS) (MIN.) (INCH/HR� (INCH/HR) (INCH/HR) (ACRES) 1 282.24 17.91 2.768 .56 .16 .09 116.70 2 283.08 18.22 2.739 .55 .16 .09 118.33 3 283.66 19.13 2.660 .55 .16 .09 122.24 4 282.23 20.06 2.585 .55 .16 .09 125.30 5 264.13 25.02 2.265 .52 .18 .09 134.82 6 257.02 26.59 2.184 .51 .18 .09 136.34 END OF RATIONAL METHOD ANALYSIS Page 24 is is it i:i: it is ie it is is ie is is is is �Y ie ie it it is it it ie is it ie it is is ie it is ie it i�ir i::P it it is ie ie ie is it it ie i�ir it it it is is ie it it it is it is it is it*ie it is it ie it it it RATIONAL METHOD HYDROLOGY COMPUTER PROGRAM PACKAGE (Reference: 1986 SAN BERNARDINO CO. HYDROLOGY CRITERION) (c) Copyright 1983-93 Advanced Engineering Software (aes) Ver. 1.9B Release Date: 7/18/93 License ID 1202 Analysis prepared by: HUITT-ZOLLARS, INC. 15101 RED HILL AVENUE TUSTIN, CALIFORNIA 92780-6500 PHONE (714) 259-7900 * FAX (714) 259-0210 ------------------------------------------------------- FILE NAME: 202Q100G.DAT TIME/DATE OF STUDY: 13:43 5/ 3/2004 ---------------------------------------------------------------------- USER SPECIFIED HYDROLOGY AND HYDRAULIC MODEL INFORMATION: --*TIME-OF-CONCENTRATION MODEL -- USER SPECIFIED STORM EVENT(YEAR) = 100.00 SPECIFIED MINIMUM PIPE SIZE(INCH) = 18.00 SPECIFIED PERCENT OF GRADIENTS (DECIMAL) TO USE FOR FRICTION SLOPE = .95 *USER -DEFINED LOGARITHMIC INTERPOLATION USED FOR RAINFALL" 10-YEAR STORM 60-MINUTE INTENSITY(INCH/HOUR) _ .920 100-YEAR STORM 60-MINUTE INTENSITY(INCH/HOUR) = 1.340 COMPUTED RAINFALL INTENSITY DATA: STORM EVENT = 100.00 1-HOUR INTENSITY(INCH/HOUR) = 1.3400 SLOPE OF INTENSITY DURATION CURVE = .6000 �k is i:ir�•*.i:i:°ki: it sY it ki: it �k*ir is is it is sY it is it is i; it is it it is is ie is it it it it ieic it is it icie is***ir irir it it it it i; is is it ie ic�•i: it irir i;*ir*ir* FLOW PROCESS FROM NODE 10.00 TO NODE 10.00 IS CODE = 15 ---------------------------------------------------------------------------- >>>DEFINE MEMORY BANK # 1 ««< MEMORY BANK # 1 DEFINED AS FOLLOWS: Q(CFS) TC(MIN.) Fp(INCH/HR) AP Fm(INCH/HR) Ae(ACRES) 1 110.39 10.30 .643 .25 .161 31.95 2 123.04 14.98 .638 .26 .163 45.25 3 122.74 15.12 .638 .26 .164 45.41 TOTAL AREA = 45.41 �•ic*i:�•i;.iri;�•i;i:*ici:i: ie is is ir�i: it it it i:i: ie it i:i: is it is it it i; is it i:i: it is it it it is is it it i;i: is it it it*ir it it it is is it it is it is is is*ir it ici; is is FLOW PROCESS FROM NODE 10.00 TO NODE 10.00 IS CODE = 14 ---------------------------------------------------------------------------- »»>MEMORY BANK # 1 COPIED ONTO MAIN -STREAM MEMORY««< MAIN -STREAM MEMORY DEFINED AS FOLLOWS: Q(CFS) TC(MIN.) Fp(INCH/HR) AP Fm(INCH/HR) Ae(ACRES) 1 110.39 10.30 .643 .25 .161 31.95 2 123.04 14.98 .638 .26 .163 45.25 3 122.74 15.12 .638 .26 .164 45.41 TOTAL AREA = 45.41 ..*i: *ir is �•R•*°k it 7.•.�i:ir*ir**i;i;i: k it ic;: it it is it it it it ic�ir is it ic•ki: it it it kir is it it it it it*�*tii:*�**ki;. �•*ie*ir it is �•*i: :: is it FLOW PROCESS FROM NODE 10.00 TO NODE 10.00 IS CODE = 12 Page 1 ---------------------------------------------------------------------------- »»>CLEAR MEMORY BANK # 1 ««< Sc 4r :tic't4t'c:4ir:r is it it 4t it 4r it :': is it Y is is is ft it it 4t it it*it:r it is 4r*4t �t*4t it*it is it it 4t it is 4t*ir it ie*i: is is it FLOW PROCESS PROCESS FROM NODE 10.00 TO NODE 11.00 IS CODE = 3 ---------------------------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 54.0 INCH PIPE IS 38.7 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 10.1 UPSTREAM NODE ELEVATION(FEET) = 1075.90 DOWNSTREAM NODE ELEVATION(FEET) = 107350 FLOW LENGTH(FEET) = 435.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 54.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 123.04 TRAVEL TIME(MIN.) _ .72 TC(MIN.) = 15.70 :r4::rYr*Yt4ticit ir4t4: dtic4tir:c:c4cizdciticitit*sYiritY:itir**icieieicYicirhiricicic4rititit4riefrdtitit:titiciciti:�:itic#Yric4c4titirYr4r'r4c FLOW PROCESS FROM NODE 11.00 TO NODE 11.00 IS CODE = 1 ---------------------------------------------------------------------------- »»>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< ------------------------------------------------------------------------- TOTAL NUMBER OF STREAMS = 2 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 1 ARE: TIME OF CONCENTRATION(MIN.) = 15.70 RAINFALL INTENSITY(INCH/HR) = 3.00 AREA -AVERAGED Fm(INCH/HR) = .16 AREA -AVERAGED Fp(INCH/HR) = .64 AREA -AVERAGED Ap = .26 EFFECTIVE STREAM AREA(ACRES) = 45.25 TOTAL STREAM AREA(ACRES) = 45.41 PEAK FLOW RATE(CFS) AT CONFLUENCE = 123.04 ::fit*irY:.t: it 4c s':4t*iti: is sti it***k*ic it*::***it 4c 4r it 4r'.c is 4r it****�c iz 4r it 4c**i:*it 4r 4c*9r ie*it**�r�**9c *ic ie is**:t*4: is is FLOW PROCESS FROM NODE 11.10 TO NODE 11.20 IS CODE = 2.1 ---------------------------------------------------------------------------- »»>RATIONAL METHOD INITIAL SUBAREA ANALYSIS««< --------------------------------------------------------------------------- DEVELOPMENT IS COMMERCIAL TC = K*[(LENGTH** 3.00)/(ELEVATION CHANGE)]** .20 INITIAL SUBAREA FLOW-LENGTH(FEET) = 665.00 UPSTREAM ELEVATION(FEET) = 1090.50 DOWNSTREAM ELEVATION(FEET) = 1087.50 ELEVATION DIFFERENCE(FEET) = 3.00 TC(MIN.) = .304*[( 665.00** 3.00)/( 3.00)]** .20 = 12.054 100 YEAR RAINFALL INTENSITY(INCH/HR) = 3.510 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA RUNOFF(CFS) = 7.70 TOTAL AREA(ACRES) = 2.49 PEAK FLOW RATE(CFS) = 7.70 4ri:4t::':::itq:ic:Y�st:r4::.....�•4:4:i:*:;4t:t•k�Y*ir',. �•**i:::'t:.::stir*•it*.ire•9t:r',t*it*ir:z*ire....*°k*:'.....**4ciss:•.t..*:c•.':iz:z FLOW PROCESS FROM NODE 11.20 TO NODE 11.30 IS CODE = 3 ---------------------------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW) ««< Page 2 DEPTH OF FLOW IN 18.0 INCH PIPE IS 11.6 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 6.4 UPSTREAM NODE ELEVATION(FEET) = 1081.50 DOWNSTREAM NODE ELEVATION(FEET) = 1077.27 FLOW LENGTH(FEET) = 420.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 18.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 7.70 TRAVEL TIME(MIN.) = 1.10 TC(MIN.) = 13.15 irkiriticicieiticiriciciricicieiciciticiciric�kieiritirieieititiririciticieiritiricsYieiciciriticicieicititiriririciriei:iciriric*irieiciciticiricitic FLOW PROCESS FROM NODE 11.30 TO NODE 11.30 IS CODE = 8 -------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 100 YEAR RAINFALL INTENSITY(INCH/HR) = 3.331 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 4.22 SUBAREA RUNOFF(CFS) = 12.37 EFFECTIVE AREA(ACRES) = 6.71 AREA -AVERAGED Fm(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) _ .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 6.71 PEAK FLOW RATE(CFS) = 19.66 TC(MIN) = 13.15 *ie it sY it is it ie ir.*ic it is irir it is it ie ie ie is is it it it sY is it is it*ie it is is is is it is ie is it**it it sY ie is is is is ie ie ic'.r it is ie is is is*ir ie is it is it s4 it it it is ie FLOW PROCESS FROM NODE 11.30 TO NODE 11.00 IS CODE = 3 ---------------------------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< >>>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 18.0 INCH PIPE IS 10.7 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 17.9 UPSTREAM NODE ELEVATION(FEET) = 1077.27 DOWNSTREAM NODE ELEVATION(FEET) = 1073.50 FLOW LENGTH(FEET) = 45.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 18.00 NUMBER OF PIPES`= 1 PIPE-FLOW(CFS) = 19.66 TRAVEL TIME(MIN.) = .04 TC(MIN.) = 13.19 �•i:i: is is is is**�•ic it it is**ir*ir it it is it sY is it is it is is is ie is is it it ie it is is is �c it*it ie is it it*it*ic*ic is*k *ir it*ic it it is***ir**it it is is FLOW PROCESS FROM NODE 11.00 TO NODE 11.00 IS CODE = 1 »»>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< »»>AND COMPUTE VARIOUS CONFLUENCED STREAM VALUES««< TOTAL NUMBER OF STREAMS = 2 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 2 ARE: TIME OF CONCENTRATION(MIN.) = 13.19 RAINFALL INTENSITY(INCH/HR) = 3.32 AREA -AVERAGED Fm(INCH/HR) = .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 EFFECTIVE STREAM AREA(ACRES) = 6.71 TOTAL STREAM AREA(ACRES) = 6.71 PEAK FLOW RATE(CFS) AT CONFLUENCE = 19.66 RAINFALL INTENSITY AND TIME OF CONCENTRATION RATIO CONFLUENCE FORMULA USED FOR 2 STREAMS. PEAK FLOW RATE TABLE ** Q Tc Intensity Fp Ap Fm Ae Page 3 (CFS) (MIN.) (INCH/HR) (INCH/HR) (INCH/HR) (ACRES) 1 128.74 11.04 3.700 .65 .23 .15 37.56 2 140.71 15.70 2.995 .64 .24 .15 51.96 3 140.31 15.84 2.980 .64 .24 .15 52.12 4 135.90 13.19 3.325 .65 .23 .15 44.81 COMPUTED CONFLUENCE ESTIMATES ARE AS FOLLOWS: PEAK FLOW RATE(CFS) = 140.71 TC(MIN.) = 15.701 EFFECTIVE AREA(ACRES) = 51.96 AREA -AVERAGED FMCINCH/HR) _ .15 AREA -AVERAGED Fp(INCH/HR) _ .64 AREA -AVERAGED Ap = .24 TOTAL AREA(ACRES) = 52.12 FLOW PROCESS FROM NODE 11.00 TO NODE 12.00 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 63.0 INCH PIPE IS 46.0 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 8.3 UPSTREAM NODE ELEVATION(FEET) = 1073.50 DOWNSTREAM NODE ELEVATION(FEET) = 1072.77 FLOW LENGTH(FEET) = 240.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 63.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 140.71 TRAVEL TIME(MIN.) = .48 TC(MIN.) = 16.18 » it is it»» it k it»» it is k kk»»» k is»»»» k» it» k»»»» it»»» k»»» �•»» k»»» is k k»»»»» is»»» �r kir»»»» k it»»»» is k FLOW PROCESS FROM NODE 12.00 TO NODE 12.00 IS CODE = 8 ---------------------------------------------------------------------------- >>>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 100 YEAR RAINFALL INTENSITY(INCH/HR) = 2.942 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 1.40 SUBAREA RUNOFF(CFS) = 3.61 EFFECTIVE AREA(ACRES) = 53.36 AREA -AVERAGED FM(INCH/HR) _ .15 AREA -AVERAGED Fp(INCH/HR) = .65 AREA -AVERAGED Ap = .23 TOTAL AREA(ACRES) = 53.52 PEAK FLOW RATE(CFS) = 140.71 TC(MIN) = 16.18 »»» k «•»»» «•»» k »»» it «•»»»»» i; '..•»»»»»»»»»»»»-.r»»»» it it» ir» it is»» »»»»»»»» � ir» «•» ic» is it»» it #»» ir» is FLOW PROCESS FROM NODE 12.00 TO NODE 13.00 IS CODE 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< --------------------------------------------------------------------------- DEPTH OF FLOW IN 45.0 INCH PIPE IS 34.9 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 15.3 UPSTREAM NODE ELEVATION(FEET) = 1072.77 DOWNSTREAM NODE ELEVATION(FEET) = 1062.75 FLOW LENGTH(FEET) = 630.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 45.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 140.71 TRAVEL TIME(MIN.) _ .69 TC(MIN.) = 16.87 »» .. »»» .. » »»»»»»» ir» .. »»» is i.•» « » «•» « ir» k it k � »»» k»»»»» ., »» » » » k k „»»»»»»» «.»» « .. ,.., » «'»»»»» k» FLOW PROCESS FROM NODE 13.00 TO NODE 13.00 IS CODE = 1 ---------------------------------------------------------------------------- Page 4 »»>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< TOTAL NUMBER OF STREAMS = 2 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 1 ARE: TIME OF CONCENTRATION(MIN.) = 16.87 RAINFALL INTENSITY(INCH/HR) = 2.87 AREA -AVERAGED FM(INCH/HR) = .15 AREA -AVERAGED Fp(INCH/HR) = .65 AREA -AVERAGED Ap = .23 EFFECTIVE STREAM AREA(ACRES) = 53.36 TOTAL STREAM AREA(ACRES) = 53.52 PEAK FLOW RATE(CFS) AT CONFLUENCE = 140.71 it it it �r do 4e 4r 4r Ye it �r 4t it it it is is ie 4r is 4r 4r oY it is it:F itu ie is 4r ie is it it it sY Yt it s4 it ie lr it �c 4c*iri: 4e it 4r it ie is is lc 4r is it 4r it it 9t oY ie it it ie Yr 4c Yc ie it it FLOW PROCESS FROM NODE 13.10 TO NODE 13.20 IS CODE = 2.1 ---------------------------------------------------------------------------- »»>RATIONAL METHOD INITIAL SUBAREA ANALYSIS««< DEVELOPMENT IS COMMERCIAL TC = K*[(LENGTH** 3. 00)/ (ELEVATION CHANGE))** .20 INITIAL SUBAREA FLOW-LENGTH(FEET) = 840.00 UPSTREAM ELEVATION(FEET) = 1084.00 DOWNSTREAM ELEVATION(FEET) = 1082.00 ELEVATION DIFFERENCE(FEET) = 2.00 TC(MIN.) = .304*[( 840.00** 3.00)/( 2.00)]** .20 = 15.040 100 YEAR RAINFALL INTENSITY (INCH/HR) = 3.074 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA RUNOFF(CFS) = 12.68 TOTAL AREA(ACRES) = 4.70 PEAK FLOW RATE(CFS) = 12.68 :ci:**9:'.t4e:rir'..•'..•'.r�•ic it:';*:r�•:r*�':e*ir*4c�"::****fir 4r**'.e',r*:eie'..•*�sY is i::r it fc it i:�ir'.r:k*Y it it ie ir:r *sY it it it*ir fr ie it ir* FLOW PROCESS FROM NODE 13.20 TO NODE 13.30 IS CODE = 3 ---------------------------------------------------------------------------- >COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 21.0 INCH PIPE IS 14.1 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 7.4 UPSTREAM NODE ELEVATION(FEET) = 1076.00 DOWNSTREAM NODE ELEVATION(FEET) = 1071.20 FLOW LENGTH(FEET) = 450.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 21.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 12.68 TRAVEL TIME(MIN.) = 1.02 TC(MIN.) = 16.06 ....::;t:'r'.:'.ti;k*�•*ir is 4:R*�:**4: dr k4r ir*ic:rR•*****�:ic'..•:c*s:Y�:'it:r*°k 4c is 4t irk*i: it is it it it*iri: lr is is it is �'iY �c 4c ::**:c'c it FLOW PROCESS FROM NODE 13.30 TO NODE 13.30 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 100 YEAR RAINFALL INTENSITY(INCH/HR) = 2.955 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 4.65 SUBAREA RUNOFF(CFS) = 12.05 EFFECTIVE AREA(ACRES) 9.35 AREA -AVERAGED Fm(INCH/HR) _ .07 AREA -AVERAGED Fp(INCH/HR) _ .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 9.35 PEAK FLOW RATE(CFS) = 24.24 Page 5 TC(MIN) = 16.06 it it it it is ie it it it it it ie it it it it it it is ie sY it it ie it icir it it ie&ie it it it it is is ie it it is it it it it is it is it ie ie it it it is it it is sY ie it it ie is it it irit ie&ie ie it it it FLOW PROCESS FROM NODE 13.30 TO NODE 13.30 IS CODE = 8 --------------------------------------------------------------------------- >ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 100 YEAR RAINFALL INTENSITY(INCH/HR) = 2.955 -------------- SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 6.09 SUBAREA RUNOFF(CFS) = 15.79 EFFECTIVE AREA(ACRES) = 15.44 AREA -AVERAGED Fm(INCH/HR) _ .07 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 15.44 PEAK FLOW RATE(CFS) = 40.02 TC(MIN) = 16.06 k is it it ie it itie it it is it it is it it it it is it ie it it is it it it is is it is it ie it is it it it it it it is fc is it it is k is is is is is it ie �ti i<i< it is ie it it it it it is ie is it it is it ieir is FLOW PROCESS FROM NODE 13.30 TO NODE 13.40 IS CODE = 3 ---------------------------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 27.0 INCH PIPE IS 21.1 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 12.0 UPSTREAM NODE ELEVATION(FEET) = 1071.20 DOWNSTREAM NODE ELEVATION(FEET) = 1063.35 FLOW LENGTH(FEET) = 405.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 27.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 40.02 TRAVEL TIME(MIN.) _ .56 TC(MIN.) = 16.62 ., «•ir «•i:it is« -sir it :: is is is � �i;i:i: sY it is it it it it it is it s4 wit it is it ir�it it it it is is is 4r it is it 4r i:�i:ic�-k it it*fir*fir is is k ir�it it :t is it„it FLOW PROCESS FROM NODE 13.40 TO NODE 13.40 IS CODE = 8 ------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 100 YEAR RAINFALL INTENSITY(INCH/HR) = 2.895 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 1.23 SUBAREA RUNOFF(CFS) = 3.12 EFFECTIVE AREA(ACRES) = 16.67 AREA -AVERAGED FM(INCH/HR) _ .07 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) 16.67 PEAK FLOW RATE(CFS) = 42.31 TC(MIN) = 16.62 it is i; ie «• it it «' ;; k is «• ir'.r i; � � it «• «• is k k «• «• it is ie it is it ie � sY it it ie it sY ie i; it it ie it ie i; i< i; � & is it it i; «• i; i; is «• � i; :: is i; :: «• � it i; is � i; it � «• FLOW PROCESS FROM NODE 13.40 TO NODE 13.00 IS CODE = 3 ---------------------------------------------------------------------------- >>>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< ------------------------------------------------------------------------- --------------------- DEPTH OF FLOW IN 30.0 INCH PIPE IS 22.6 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 10.7 UPSTREAM NODE ELEVATION(FEET) = 1063.35 DOWNSTREAM NODE ELEVATION(FEET) = 1062.75 FLOW LENGTH(FEET) = 45.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 30.00 NUMBER OF PIPES = 1 Page 6 PIPE-FLOW(CFS) = 42.31 TRAVEL TIME(MIN.) _ .07 TC(MIN.) = 16.69 irkk kit irkkkkkkickirkkic is kk it irk irk kirk kkk �Y irk kir it fe$e it irk it irkkkkkkkkkkkis ick ie ie kkkkkkir ickkkic ie ie is FLOW PROCESS FROM NODE 13.00 TO NODE 13.00 IS CODE = 1 »»>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< »»>AND COMPUTE VARIOUS CONFLUENCED STREAM VALUES««< TOTAL NUMBER OF STREAMS = 2 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 2 ARE: TIME OF CONCENTRATION(MIN.) = 16.69 RAINFALL INTENSITY(INCH/HR) = 2.89 AREA -AVERAGED FM(INCH/HR) = .07 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 EFFECTIVE STREAM AREA(ACRES) = 16.67 TOTAL STREAM AREA(ACRES) = 16.67 PEAK FLOW RATE(CFS) AT CONFLUENCE = 42.31 RAINFALL INTENSITY AND TIME OF CONCENTRATION RATIO CONFLUENCE FORMULA USED FOR 2 STREAMS. *" PEAK FLOW RATE TABLE ** Q Tc Intensit Fp Ap FM Ae (CFS) (MIN.) (INCH/H� (INCH/HR) (INCH/HR) (ACRES) 1 166.27 12.23 3.480 .66 .19 .13 51.17 2 175.85 14.37 3.158 .66 .20 .13 60.56 3 182.75 16.87 2.869 .66 .20 .13 70.03 4 182.1317.01 2.855 .66 .20 .13 70.19 5 182.68 16.69 2.887 .66 .20 .13 69.52 COMPUTED CONFLUENCE ESTIMATES ARE AS FOLLOWS: PEAK FLOW RATE(CFS) = 182.75 TC(MIN.) = 16.868 EFFECTIVE AREA(ACRES) = 70.03 AREA -AVERAGED Fm(INCH/HR) _ .13 AREA -AVERAGED Fp(INCH/HR) _ .66 AREA -AVERAGED Ap = .20 TOTAL AREA(ACRES) = 70.19 ickkkirkkk �•k is �•k �kkkkkirk kkkkkkkirkkkkkirkkkkkkkkkkk k•.ckkkkiskkkkkkic it irk kkkkki: irkkkkirk FLOW PROCESS FROM NODE 13.00 TO NODE 14.00 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 60.0 INCH PIPE IS 47.0 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 11.1 UPSTREAM NODE ELEVATION(FEET) = 1062.75 DOWNSTREAM NODE ELEVATION(FEET) = 1060.88 FLOW LENGTH(FEET) = 330.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 60.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 182.75 TRAVEL TIME(MIN.) = .50 TC(MIN.) = 17.36 is i;irk**kkkkick it ic�i:kirk kic kir iskkksY i:kkkkkir itkkickkirk it itkkkkkkkkkkic irkkk*kkitk kkkkic is ::kkkic FLOW PROCESS FROM NODE 14.00 TO NODE 14.00 IS CODE = 8 ----------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 100 YEAR RAINFALL INTENSITY (INCH/HR) = 2.820 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) _ .75 Page 7 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 1.82 SUBAREA RUNOFF(CFS) = 4.50 EFFECTIVE AREA(ACRES) = 71.85 AREA -AVERAGED Fm(INCH/HR) _ .13 AREA -AVERAGED Fp(INCH/HR) = .66 AREA -AVERAGED Ap = .20 TOTAL AREA(ACRES) = 72.01 PEAK FLOW RATE(CFS) = 182.75 TC(MIN) = 17.36 is it �` �r 4c 4e is it4t is 4r X'.'c is s't it :e 4r is is is is �Y tY �• Yr'fc is * * * is Yc �'cic is 4r 4: sY Yt ie � is is it it it it ie it is it 4t it is is it it it it is i� Yt is ie it it is 4t is it it it it it it FLOW PROCESS FROM NODE 14.00 TO NODE 15.00 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 60.0 INCH PIPE IS 46.2 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 11.3 UPSTREAM NODE ELEVATION(FEET) = 1060.88 DOWNSTREAM NODE ELEVATION(FEET) = 1057.80 FLOW LENGTH(FEET) = 525.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 60.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 182.75 TRAVEL TIME(MIN.) = .78 TC(MIN.) = 18.14 '.: 4: :c it :r 4: is is *;rit%*ir**ic is is it is ic.*ii �Y:: dr ic::*ic�•ir it 4c°kic**ic it i:it*dr 4t ie it it it 4c it*�'c:t it it fc'.t is is �'r �t is it it it 4t leir it is 4fsY it is FLOW PROCESS FROM NODE 15.00 TO NODE 15.00 IS CODE = 1 ---------------------------------------------------------------------------- >>>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< TOTAL NUMBER OF STREAMS = 2 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 1 ARE: TIME OF CONCENTRATION(MIN.) = 18.14 RAINFALL INTENSITY(INCH/HR) = 2.75 AREA -AVERAGED Fm(INCH/HR) = .13 AREA -AVERAGED Fp(INCH/HR) = .66 AREA -AVERAGED Ap = .20 EFFECTIVE STREAM AREA(ACRES) = 71.85 TOTAL STREAM AREA(ACRES) = 72.01 PEAK FLOW RATE(CFS) AT CONFLUENCE = 182.75 do*ir is ir'c it it is Yr it �r 4:4:*4c:r it is f: is is it it �•fc it is f: e4 is it is s4 it it sY is ie is 4r it it it it fr it is*ic�•ic it it ie 4r�*:4 is is is it it*4r****:c Yt it it de ie FLOW PROCESS FROM NODE 15.10 TO NODE 15.20 IS CODE = 2.1 ---------------------------------------------------- »»>RATIONAL METHOD INITIAL SUBAREA ANALYSIS««< DEVELOPMENT IS COMMERCIAL TC = K*[(LENGTH** 3. 00)/ (ELEVATION CHANGE)]** .20 INITIAL SUBAREA FLOW-LENGTH(FEET) = 900.00 UPSTREAM ELEVATION(FEET) = 1075.50 DOWNSTREAM ELEVATION(FEET) = 1072.50 ELEVATION DIFFERENCE(FEET) = 3.00 TC(MIN.) = .304*[( 900.00** 3.00)/( 3.00)]** .20 = 14.454 100 YEAR RAINFALL INTENSITY(INCH/HR) = 3.148 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA RUNOFF(CFS) = 12.94 TOTAL AREA(ACRES) = 4.68 PEAK FLOW RATE(CFS) = 12.94 •:YsY4rir4ririti:ir4tirir4eir�4e*�r'.ritic�:�•4rir�s44c:'r**�ricit*irir�Y.ir**�•*�lrirsY4:*:r�k�-4r4t4tiric**:ririr::ir4r*:r:r:r�:ci:4:*i:Yr FLOW PROCESS FROM NODE 15.20 TO NODE 15.30 IS CODE = 3 ---------------------------------------------------------------------------- Page 8 >>>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< -------------------------------------------------------------------- DEPTH OF FLOW IN 21.0 INCH PIPE IS 14.7 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 7.2 UPSTREAM NODE ELEVATION(FEET) = 1066.50 DOWNSTREAM NODE ELEVATION(FEET) = 1062.60 FLOW LENGTH(FEET) = 390.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 21.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 12.94 TRAVEL TIME(MIN.) _ .90 TC(MIN.) = 15.36 kkkkkit irkkkkki: it it k irir i:k ickkkkkkkkkkkick iric kitkkkkkkkkick it irkkkkkkk�kkkkickkkkkkkkkk •irk FLOW PROCESS FROM NODE 15.30 TO NODE 15.30 IS CODE = 8 --------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< --------------------------------------------------------------------------- 100 YEAR RAINFALL INTENSITY(INCH/HR) = 3.035 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 4.69 SUBAREA RUNOFF(CFS) = 12.50 EFFECTIVE AREA(ACRES) = 9.37 AREA -AVERAGED FM(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) _ .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 9.37 PEAK FLOW RATE(CFS) = 24.96 TC(MIN) = 15.36 kkkirk irkirkkkkkk:t i:. ickkkirk ie icir kirkkkk kitkkkkkkkkkkirkkkkirk kkickkkkkkkkkkirk kir irk Yrkkkkir is FLOW PROCESS FROM NODE 15.30 TO NODE 15.30 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 100 YEAR RAINFALL INTENSITY(INCH/HR) = 3.035 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 - SUBAREA AREA(ACRES) = 6.29 SUBAREA RUNOFF(CFS) = 16.76 EFFECTIVE AREA(ACRES) = 15.66 AREA -AVERAGED FM(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 15.66 PEAK FLOW RATE(CFS) = 41.72 TC(MIN) = 15.36 k irk ki:i: kir i.•kkkkkir �•kkkkk.�•ick kkkkk �•kkkie irk kirkkkkkkkkkkkk �•k kkk:ck ki.•kkkkkkic i,•k kit irkkkirk FLOW PROCESS FROM NODE 15.30 TO NODE 15.00 IS CODE = 3 ---------------------------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 33.0 INCH PIPE IS 22.8 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 9.5 UPSTREAM NODE ELEVATION(FEET) = 1062.60 DOWNSTREAM NODE ELEVATION(FEET) = 1057.80 FLOW LENGTH(FEET) = 495.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 33.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 41.72 TRAVEL TIME(MIN.) _ .86 TC(MIN.) = 16.22 .,.,.;'.c it i.'ki: irkkkk �•k�kkkkkkick �•kkki:kkirkkkkkkitk k�k�•i;kkirkkkkkitkkkkk'..•�•irkkkk�kkkkkkkkit FLOW PROCESS FROM NODE 15.00 TO NODE 15.00 IS CODE = 1 Page 9 --------------------------------------------------------------------------- »»>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< »»>AND COMPUTE VARIOUS CONFLUENCED STREAM VALUES««< ---------------------------------------------------------- TOTAL NUMBER OF STREAMS = 2 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 2 ARE: TIME OF CONCENTRATION(MIN.) = 16.22 RAINFALL INTENSTTY(INCH/HR) = 2.94 AREA -AVERAGED FM(INCH/HR) = .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 EFFECTIVE STREAM AREA(ACRES) = 15.66 TOTAL STREAM AREA(ACRES) = 15.66 PEAK FLOW RATE(CFS) AT CONFLUENCE = 41.72 RAINFALL INTENSITY AND TIME OF CONCENTRATION RATIO CONFLUENCE FORMULA USED FOR 2 STREAMS. PEAK FLOW RATE TABLE *» Q Tc Intensit Fp Ap FM Ae (CFS) (MIN.) (INCH/HR� (INCH/HR) (INCH/HR) (ACRES) 1 205.18 13.54 3.273 .67 .17 .12 66.07 2 217.00 15.65 3.001 .67 .18 .12 77.49 3 221.86 17.96 2.763 .67 .18 .12 87.00 4 221.69 18.14 2.747 .67 .18 .12 87.51 5 220.89 18.28 2.734 .67 .18 .12 87.67 6 219.25 16.22 2.937 .67 .18 .12 80.25 COMPUTED CONFLUENCE ESTIMATES ARE AS FOLLOWS: PEAK FLOW RATE(CFS) = 221.86 TC(MIN.) = 17.964 EFFECTIVE AREA(ACRES) = 87.00 AREA -AVERAGED FM(INCH/HR) _ .12 AREA -AVERAGED Fp(INCH/HR) _ .67 AREA -AVERAGED Ap = .18 TOTAL AREA(ACRES) = 87.67 FLOW PROCESS FROM NODE 15.00 TO NODE 16.00 IS CODE = 3 ---------------------------------------------------------------------------- >>>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< -------------------------------------------------------------------- DEPTH OF FLOW IN 51.0 INCH PIPE IS 38.1 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 19.5 UPSTREAM NODE ELEVATION(FEET) = 1057.80 DOWNSTREAM NODE ELEVATION(FEET) = 1050.50 FLOW LENGTH(FEET) = 330.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 51.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 221.86 TRAVEL TIME(MIN.) _ .28 TC(MIN.) = 18.25 FLOW PROCESS FROM NODE 16.00 TO NODE 16.00 IS CODE = 1 ---------------------------------------------------------------------------- »»>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< -------------------------------------------------------------------- TOTAL NUMBER OF STREAMS = 2 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 1 ARE: TIME OF CONCENTRATION(MIN.) = 18.25 RAINFALL INTENSITY(INCH/HR) = 2.74 AREA -AVERAGED FM(INCH/HR) = .12 AREA -AVERAGED Fp(INCH/HR) = .67 AREA -AVERAGED Ap = .18 EFFECTIVE STREAM AREA(ACRES) = 87.00 TOTAL STREAM AREA(ACRES) = 87.67 Page 10 PEAK FLOW RATE(CFS) AT CONFLUENCE = 221.86 &ir*it it ie ie it it ie is it icir sY is is it it is is it sY it it it it ie it it it ir�ir it Yrieie fe is it fr ir. it it it it ie is it is it it it it ie it ie it it is it ie ie is ie is it ie it it ie is it it ie FLOW PROCESS FROM NODE 16.10 TO NODE 16.20 IS CODE = 2.1 --------------------------------------------------- »»>RATIONAL METHOD INITIAL SUBAREA ANALYSIS««< DEVELOPMENT IS COMMERCIAL TC = K*[(LENGTH** 3.00)/(ELEVATION CHANGE)]** .20 INITIAL SUBAREA FLOW-LENGTH(FEET) = 220.00 UPSTREAM ELEVATION(FEET) = 1067.00 DOWNSTREAM ELEVATION(FEET) = 1065.00 ELEVATION DIFFERENCE(FEET) = 2.00 TC(MIN.) = .304*[( 220.00** 3.00)/( 2.00)]** .20 = 6.732 100 YEAR RAINFALL INTENSITY(INCH/HR) = 4.979 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA RUNOFF(CFS) = 12.80 TOTAL AREA(ACRES) = 2.90 PEAK FLOW RATE(CFS) = 12.80 .S• sY * 4r is it is it it sY it is it is it i; it sY it it it is ie ie * it it it irir is °k it it is it it * it is it it it is is ie is is it it is is is it ie it it * * * it it it is is it it it is it it is it it it it FLOW PROCESS FROM NODE 16.20 TO NODE 16.30 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW) ««< DEPTH OF FLOW IN 21.0 INCH PIPE IS 13.2 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 8.0 UPSTREAM NODE ELEVATION(FEET) = 1059.00 DOWNSTREAM NODE ELEVATION(FEET) = 1055.03 FLOW LENGTH(FEET) = 300.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 21.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 12.80 TRAVEL TIME(MIN.) _ .62 TC(MIN.) = 7.35 ici:i; is it �•. ie it is*ire•*ir it it**it it i;ie***ir it**ic*i; it it it***ie st i; it it it kir*�•ir it**ir it i':i.•ic*ir it *ir it is it it**ir it is it *ir it it FLOW PROCESS FROM NODE 16.30 TO NODE 16.30 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 00 YEAR RAINFALL INTENSITY(INCH/HR) = 4.722 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 2.34 SUBAREA RUNOFF(CFS) = 9.79 EFFECTIVE AREA(ACRES) = 5.24 AREA -AVERAGED FM(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) _ .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 5.24 PEAK FLOW RATE(CFS) = 21.91 TC(MIN) = 7.35 i.•i:k �•--..•i;. it*i::; is is it i:i:*ic*iri:i:ir*ir*ir ir:ti:�•i;ie*R•.i:ic*ic it it it it*ic ie it i::c*irs: it irsY it it***ir it 9: it it is is it kir Yr**i:**ir FLOW PROCESS FROM NODE 16.30 TO NODE 16.00 IS CODE = 3 ---------------------------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 18.0 INCH PIPE IS 11.9 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 17.6 Page 11 UPSTREAM NODE ELEVATION(FEET) = 1055.03 DOWNSTREAM NODE ELEVATION(FEET) = 1050.50 FLOW LENGTH(FEET) = 60.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 18.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 21.91 TRAVEL TIME(MIN.) _ .06 TC(MIN.) = 7.41 :- it ie fr it is �Y $r is it it 4e * it is is it it 4t 4r it ie it it 9t it 4r 4r is Yr 4e it ie fr �'t it 4r'r Yr it Yr 4c it it it it 4r it it 4t it it 4c 9e it it 4r it i; 4: * it 4r it :ric is it it.4r it :c fe 4r sY it FLOW PROCESS FROM NODE 16.00 TO NODE 16.00 IS CODE 1 ------------------------------ »»>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< »»>AND COMPUTE VARIOUS CONFLUENCED STREAM VALUES««< ---------------------------------------------------------------------------- TOTAL NUMBER OF STREAMS = 2 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 2 ARE: TIME OF CONCENTRATION(MIN.) = 7.41 RAINFALL INTENSITY(INCH/HR) = 4.70 AREA -AVERAGED Fm(INCH/HR) = .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 EFFECTIVE STREAM AREA(ACRES) = 5.24 TOTAL STREAM AREA(ACRES) = 5.24 PEAK FLOW RATE(CFS) AT CONFLUENCE = 21.91 RAINFALL INTENSITY AND TIME OF CONCENTRATION RATIO CONFLUENCE FORMULA USED FOR 2 STREAMS. ** PEAK FLOW RATE TABLE ** Q Tc Intensity Fp Ap Fm Ae (CFS) (MIN.) (INCH/HR) (INCH/HR) (INCH/HR) (ACRES) 1 220.14 13.83 3.232 .68 .17 .11 71.31 2 230.71 15.93 2.969 .68 .17 .12 82.73 3 232.67 16.50 2.907 .67 .17 .12 85.49 4 234.47 18.25 2.737 .67 .18 .12 92.24 5 234.23 18.42 2.721 .67 .18 .12 92.75 6 233.37 18.56 2.709 .67 .18 .12 92.91 7 183.64 7.41 4.700 .68 .16 .11 40.63 COMPUTED CONFLUENCE ESTIMATES ARE AS FOLLOWS: PEAK FLOW RATE(CFS) = 234.47 TC(MIN.) = 18.245 EFFECTIVE AREA(ACRES) = 92.24 AREA -AVERAGED Fm(INCH/HR) _ .12 AREA -AVERAGED Fp(INCH/HR) _ .67 AREA -AVERAGED Ap = .18 TOTAL AREA(ACRES) = 92.91 ir:r it it it is 4r it*4e Yr it it �r4r it 4t 4e is is ie i�ir it 4r it*ic fr tr dr 9r it it it it it it it itic it it it dt:t it �r it �r it Yt ic*4r ie*4r is 4r 4r it fr 4r 4 *'k *ir 4e ie dr it it 4r it FLOW PROCESS FROM NODE 16.00 TO ---------------------------------------------------------------------------- NODE 16.00 IS CODE = 8 »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 100 YEAR RAINFALL INTENSITY(INCH/HR) = 2.737 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = ..75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 3.06 SUBAREA RUNOFF(CFS) = 7.33 EFFECTIVE AREA(ACRES) = 95.30 AREA -AVERAGED Fm(INCH/HR) _ .12 AREA -AVERAGED Fp(INCH/HR) = .67 AREA -AVERAGED Ap = .17 TOTAL AREA(ACRES) = 95.97 PEAK FLOW RATE(CFS) = 234.47 TC(MIN) = 18.25 FLOW PROCESS FROM NODE 16.00 TO NODE 17.00 IS CODE = 3 Page 12 ------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 45.0 INCH PIPE IS 31.8 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 28.1 UPSTREAM NODE ELEVATION(FEET) = 1050.50 DOWNSTREAM NODE ELEVATION(FEET) = 1039.50 FLOW LENGTH(FEET) = 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 45.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 234.47 TRAVEL TIME(MIN.) _ .12 TC(MIN.) = 18.36 ------------------ - END OF STUDY SUMMARY: TOTAL AREA(ACRES) = 95.97 TC(MIN.) = 18.36 EFFECTIVE AREA(ACRES) = 95.30 AREA -AVERAGED FM(INCH/HR)= AREA -AVERAGED Fp(INCH/HR) _ .67 AREA -AVERAGED Ap = .17 .12 PEAK FLOW RATE(CFS) = 234.47 PEAK FLOW RATE TABLE ** Q TC Intensit (CFS) (MIN.) (INCH/HR� Fp AP (INCH/HR) FM (INCH/HR) Ae (ACRES) 1 183.64 7.54 4.652 2 .68 .16 .11 43.69 220.14 13.95 3.215 .68 .16 .11 74.37 3 230.71 16.05 2.956 .68 .17 .11 85.79 4 232.67 16.62 2.894 .68 .17 .11 88.55 5 234.47 18.36 2.727 .67 .17 .12 95.30 6 234.23 18.54 2.711 .67 .17 .12 95.81 7 233.37 18.68 2.699 .67 .17 .12 95.97 END OF RATIONAL METHOD ANALYSIS Page 13 icir:eirfc'ririr*irieieiefrit�Yicir�YicieiesYfricir�'ririr4e�tirieYriciric4eic�Y4rleir�r4ririr4rieir4rfcir4eiririrfr:rsYicYricir4eiciricieicir4eirir9e4c RATIONAL METHOD HYDROLOGY COMPUTER PROGRAM PACKAGE (Reference: 1986 SAN BERNARDINO CO. HYDROLOGY CRITERION) (c) Copyright 1983-93 Advanced Engineering Software (aes) Ver. 1.9B Release Date: 7/18/93 License ID 1202 Analysis prepared by: HUITT-ZOLLARS, INC. 15101 RED HILL AVENUE TUSTIN, CALIFORNIA 92780-6500 PHONE (714) 259-7900 * FAX (714) 259-0210 --------------------------------------------------------------------------- FILE NAME: 202Q100H.DAT TIME/DATE OF STUDY: 14: 0 5/ 3/2004 USER SPECIFIED HYDROLOGY AND HYDRAULIC MODEL INFORMATION: --*TIME-OF-CONCENTRATION MODEL* -- USER SPECIFIED STORM EVENT(YEAR) = 100.00 SPECIFIED MINIMUM PIPE SIZE(INCH) = 18.00 SPECIFIED PERCENT OF GRADIENTS(DECIMAL) TO USE FOR FRICTION SLOPE = .95 ^'USER -DEFINED LOGARITHMIC INTERPOLATION USED FOR RAINFALL* 10-YEAR STORM 60-MINUTE INTENSITY(INCH/HOUR) _ .920 100-YEAR STORM 60-MINUTE INTENSITY(INCH/HOUR) = 1.340 COMPUTED RAINFALL INTENSITY DATA: STORM EVENT = 100.00 1-HOUR INTENSITY(INCH/HOUR) = 1.3400 SLOPE OF INTENSITY DURATION CURVE = .6000 p: :F ie'r it it Y:.*fe :r is**4r Y: sY it'.r is is �r Yr ie**ir eY de fr it**ie ie sY it 4c sY it*ie is ir*iri:*:e 4t it*ir it it fe ie it 4r it 9r it it ie :r ie Y: irir 4c it �'e ie it sY �e is FLOW PROCESS FROM NODE 20.00 TO NODE 22.00 IS CODE = 2.1 -------------------------------------------------------------------------- »»>RATIONAL METHOD INITIAL SUBAREA ANALYSIS««< DEVELOPMENT IS COMMERCIAL TC = K*[(LENGTH** 3.00)/(ELEVATION CHANGE)]** .20 INITIAL SUBAREA FLOW-LENGTH(FEET) = 1000.00 UPSTREAM ELEVATION(FEET) = 1073.00 DOWNSTREAM ELEVATION(FEET) = 1070.35 ELEVATION DIFFERENCE(FEET) = 2.65 TC(MIN.) = .304*[( 1000.00** 3.00)/( 2.65)]** .20 = 15.784 100 YEAR RAINFALL INTENSITY(INCH/HR) = 2.986 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA RUNOFF(CFS) = 19.46 TOTAL AREA(ACRES) = 7.43 PEAK FLOW RATE(CFS) = 19.46 :r4:*': it 4r 4t �;:r-k it Rir 4c 4;:c*�-:c is is ft it is 4t ir*4c it*ir ic:c*Yc:r 4c ie*4r k fc.:c:c do f:ici; Yrir is*4r 4tic4r it is is is is 4r it 4t 4c dt 4t sY it Yc 4r eY it sY sY it FLOW PROCESS FROM NODE 22.00 TO NODE 23.00 IS CODE = 3 -------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 27.0 INCH PIPE IS 20.2 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 6.1 UPSTREAM NODE ELEVATION(FEET) = 1063.35 DOWNSTREAM NODE ELEVATION(FEET) = 1062.35 Page 1 FLOW LENGTH(FEET) = 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 27.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 19.46 TRAVEL TIME(MIN.) .55 TC(MIN.) = 16.33 �Y i� it oY is is is it it ie k # ie ie is it it :c it is is it it it is it iririr ie is ie ie it it is ie it it it it is u is ie irie it sY it ie it it it ie it is is is ie it it it it sY it it ie ie it is ie it it it it FLOW PROCESS FROM NODE 23.00 TO NODE 23.00 IS CODE = 8 --------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 100 YEAR RAINFALL INTENSITY(INCH/HR) = 2.925 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 3.23 SUBAREA RUNOFF(CFS) = 8.29 EFFECTIVE AREA(ACRES) = 10.66 AREA -AVERAGED Fm(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 10.66 PEAK FLOW RATE(CFS) = 27.35 TC(MIN) = 16.33 is it it it it is it is it it it ie is it it it it it it is it is it it is it �Y it is it is is is is it ie it it it it'k is it is it is is is it is is it it it ie ie it it is is it is it is is it it is i; it ick it � icir FLOW PROCESS FROM NODE 23.00 TO NODE 24.00 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 30.0 INCH PIPE IS 23.7 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 6.6 UPSTREAM NODE ELEVATION(FEET) = 1062.35 DOWNSTREAM NODE ELEVATION(FEET) = 1061.35 FLOW LENGTH(FEET) = 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 30.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 27.35 TRAVEL TIME(MIN.) _ .51 TC(MIN.) = 16.84 is it � is it is is it is is ici: �'.r i; it it is �• is it is is i; '� ir',r *� iris it is it is it is k is ie is it ie ie ie � it it it it is it ifir i; i; is it i; is it it st it it k � it is it is i; is is it k FLOW PROCESS FROM NODE 24.00 TO NODE 24.00 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 100 YEAR RAINFALL INTENSITY(INCH/HR) = 2.872 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 3.23 SUBAREA RUNOFF(CFS) = 8.13 EFFECTIVE AREA(ACRES) = 13.89 AREA -AVERAGED FM(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 13.89 PEAK FLOW RATE(CFS) = 34.97 TC(MIN) = 16.84 it xi:&ir it ie is is it i:icir&ir it it ie is it iris it is it ie it it it it is it iris is it it it is t is it�ic it it is it ir'k it it is Xit is is is it it it is is is sY is it it is it it it it it it ie FLOW PROCESS FROM NODE 24.00 TO NODE 25.00 IS CODE = 3 ---------------------------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 33.0 INCH PIPE IS 25.9 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 7.0 UPSTREAM NODE ELEVATION(FEET) = 1061.35 Page 2 FLOW LENGTH(FEET) 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 27.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 19.46 TRAVEL TIME(MIN.) = .55 TC(MIN.) = 16.33' kkkirkirkkkkkirifkkkkkifit.`xkirkkfeiritkkkkkkk,kk#ifkkitkkkickkirkkkkifickkickirirkicitkkirkkkkirkkiric FLOW PROCESS FROM NODE 23.00 TO NODE 23.00 IS CODE = 8 ---------------------------- 7---------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 100 YEAR RAINFALL INTENSITY(INCH/HR) = 2.925 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 3.23 SUBAREA RUNOFF(CFS) = 8.29 EFFECTIVE AREA(ACRES) = 10.66 AREA -AVERAGED FM(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 10.66 PEAK FLOW RATE(CFS) = 27.35 TC(MIN) = 16.33 k itk&k'lr ii Yrkkkit kirk kkkkkkkkkkkkkkkkkkkkkkkkic icitkkXkkkkk;Ykk kkkkkkkkkkirkkkkkkifkkkick FLOW PROCESS FROM NODE 23.00 TO NODE 24.00 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW) ««< DEPTH OF FLOW IN 30.0 INCH PIPE IS 23.7 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 6.6 UPSTREAM NODE ELEVATION(FEET) = 1062.35 DOWNSTREAM NODE ELEVATION(FEET) = 1061.35 FLOW LENGTH(FEET) = 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 30.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 27.35 TRAVEL TIME(MIN.) _ .51 TC(MIN.) = 16.84 kkk#kkirkkkkkkk�'kkkkitkkkkkkkirkkkkkkkkkkkkiricickkkkkkki:kkkkkkkkkkifk%kitkkkkkkkkkk FLOW PROCESS FROM NODE 24.00 TO NODE 24.00 IS CODE = 8 --------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 0 YEAR RAINFALL INTENSITY(INCH/HR) = 2.872 ------------------ SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 3.23 SUBAREA RUNOFF(CFS) 8.13 EFFECTIVE AREA(ACRES) = 13.89 AREA -AVERAGED FM(INCH/HR) .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 13.89 PEAK FLOW RATE(CFS) = 34.97 TC(MIN) = 16.84 kkkickki: ickkkkk��kk::kit ickkkkkkit s��kkkkkk�kkk kk �-kkkkkkki; k:,•k kkk�irkkkkkkk�-k kir��k�kk FLOW PROCESS FROM NODE 24.00 TO NODE 25.00 IS CODE = 3 ---------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< ------------------------ DEPTH OF FLOW., IN 33.0 INCH PIPE IS 25.9 INCHES PIPE=FLOW VELO,CITY(FEET/SEC.) = 7.0 UPSTREAM NODE ELEVATION(FEET) = 1061.35 Page 2 DOWNSTREAM NODE ELEVATION(FEET) = 1060.35 FLOW LENGTH(FEET) = 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 33.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 34.97 TRAVEL TIME(MIN.) _ .48 TC(MIN.) = 17.32 iti:kkkit is kk kkis it itkkiekkkit itkkkitk itkkkkkic kkkkktYkkkkitkkkkkirkkkkkiskkkkkkirk kic itkkkkkkYrk FLOW PROCESS FROM NODE 25.00 TO NODE 25.00 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 100 YEAR RAINFALL INTENSITY(INCH/HR) = 2.824 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 3.23 SUBAREA RUNOFF(CFS) = 7.99 EFFECTIVE AREA(ACRES) = 17.12 AREA -AVERAGED FM(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 17.12 PEAK FLOW RATE(CFS) 42.36 TC(MIN) = 17.32 k kkkkkiakkkk�kkicirirkkkkkkkirkkic irkkkkkkkkkkkkkkkk4rk kYc irkkkkilitkkkkkkkkkkk�kkkkkk:ck FLOW PROCESS FROM NODE 25.00 TO NODE 26.00 IS CODE = 3 >>>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< ------------------------------------------------------------------- DEPTH OF FLOW IN 36.0 INCH PIPE IS 27.2 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 7.4 UPSTREAM NODE ELEVATION(FEET) = 1060.35 DOWNSTREAM NODE ELEVATION(FEET) = 1059.35 FLOW LENGTH(FEET) = 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 36.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 42.36 TRAVEL TIME(MIN.) _ .45 TC(MIN.) = 17.77 k kkki:kkkkkkkkki:kkkirkkkk*kkkkk�kkkkkkkkkkkkkkkkkkkk*kkkkkkkkkkkkkk*kkk�k�k�kk FLOW PROCESS FROM NODE 26.00 TO NODE 26.00 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 100 YEAR RAINFALL INTENSITY(INCH/HR) = 2.781 SOIL CLASSIFICATION IS "B COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 3.23 SUBAREA RUNOFF(CFS) = 7.87 EFFECTIVE AREA(ACRES) = 20.35 AREA -AVERAGED FM(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 20.35 PEAK FLOW RATE(CFS) = 49.56 TC(MIN) = 17.77 kiF.�-i.•i;kkkkk�kkkkisk �•kkkk&kkkn:kkk:: ick�i: �•kk�kkkit�k�kkkiek�kkki:kkkkkit Xirk FLOW PROCESS PROCESS FROM NODE 26.00 TO NODE 27.00 IS CODE = 3 ---------------------------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< --------------------------------------------------------=-=--------- DEPTH OF FLOW IN 39.0 INCH PIPE IS 28.2 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 7.7 Page 3 UPSTREAM NODE ELEVATION(FEET) = 1059.35 DOWNSTREAM NODE ELEVATION(FEET) = 1058.35 FLOW LENGTH(FEET) = 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 39.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 49.56 TRAVEL TIME(MIN) _ .43 TC(MIN.) = 18.20 itkkkic ickkkkie itkkkkkkkit ickkkkkkkirk kkkkitk ifir irk it irk kirk kirkkkkkkirk is itkkkie irkkkkkkkickkkkk FLOW PROCESS FROM NODE 27.00 TO NODE 27.00 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 100 YEAR RAINFALL INTENSITY(INCH/HR) = 2.741 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 3.23 SUBAREA RUNOFF(CFS) = 7.75 EFFECTIVE AREA(ACRES) = 23.58 AREA -AVERAGED Fm(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 23.58 PEAK FLOW RATE(CFS) = 56.58 TC(MIN) = 18.20 k is kic i; �kkkk�kkk kkk�kkk�kkkkkkit&kk�•k irkkkit k irk kk�kkir. irkk kkkkkkkkkitk kirkkkki:kkkk$•i:k FLOW PROCESS FROM NODE 27.00 TO NODE 28.00 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< >>>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 39.0 INCH PIPE IS 31.8 INCHES PIPE -FLOW VELOCITY(FEET/SEC) = 7.8 UPSTREAM NODE ELEVATION(FEET) = 1058.35 DOWNSTREAM NODE ELEVATION(FEET) = 1057.35 FLOW LENGTH(FEET) = 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 39.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 56.58 TRAVEL TIME(MIN.) _ .43 TC(MIN.) = 18.63 kkkk�•kkkirk kkkkkkkkkk kkkkkk�kki.•iri:i:i: it it �-i::Y it it it i; ir�ir i; it ir::4r�&sY ie it it s: it it it it it �•ie ie it it ie it is Yr� �•ic it FLOW PROCESS FROM NODE 28.00 TO NODE 28.00 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 100 YEAR RAINFALL INTENSITY(INCH/HR) = 2.703 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 3.23 SUBAREA RUNOFF(CFS) 7.64 EFFECTIVE AREA(ACRES) = 26.81 AREA -AVERAGED Fm(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 26.81 PEAK FLOW RATE(CFS) = 63.42 TC(MIN) = 18.63 k kki.•ickkkkkkkkkic i; irkkkkkirk'.:kkkkkkki;.i;it irkkkki;ici:ici;�i�ir it it i;i:i; it it it it it kit ir'.t is it is ie�ir�ic it ir�ir it is FLOW PROCESS FROM NODE 28.00 TO NODE 29.00 IS CODE = 3 ---------------------------------------------------------------------------- >>>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 42.0 INCH PIPE IS 33.0 INCHES Page 4 PIPE -FLOW VELOCITY(FEET/SEC.) = 7.8 UPSTREAM NODE ELEVATION(FEET) = 1057.35 DOWNSTREAM NODE ELEVATION(FEET) = 1056.75 FLOW LENGTH(FEET) = 132.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 42.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 63.42 TRAVEL TIME(MIN.) = .28 TC(MIN.) = 18.91 it tr is it Bc ir.Ye sY 4c fr ie 4r 4r it it �Y 4r fr de �'r eY ie 4r �4 fc it 4r �Y it 4t it 4r 4r 4c it is eft it dr 4r ie fe it 4r fr Ye ft it it �k it fr it 9r ie ie 3r it 4r it �h fe ie it 4r it ie it ie 4r dr 4e it �'r it it FLOW PROCESS FROM NODE 29.00 TO NODE 29.00 IS CODE = 8 --------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 100 YEAR RAINFALL INTENSITY(INCH/HR) = 2.679 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 2.13 SUBAREA RUNOFF(CFS) = 4.99 EFFECTIVE AREA(ACRES) = 28.94 AREA -AVERAGED FM(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 28.94 PEAK FLOW RATE(CFS) 67.83 TC(MIN) = 18.91 it it it 4e k9r 4c��4r st 4r is tc��ir it it is 9c itir is kic*ic'.r �Y ie is �>Y is �t is ft 9r is it it s:fr'.c�sC is it 4c wit sY it sY is is is 4c it it ir': &ir it�ir frt 4r it fir it it FLOW PROCESS FROM NODE 29.00 TO NODE 30.00 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW) ««< ------------------------------------------------------------___________ DEPTH OF FLOW IN 42.0 INCH PIPE IS 33.0 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 8.4 UPSTREAM NODE ELEVATION(FEET) = 1056.75 DOWNSTREAM NODE ELEVATION(FEET) = 1055.50 FLOW LENGTH(FEET) = 240.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 42.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 67.83 TRAVEL TIME(MIN.) _ .48 TC(MIN.) = 19.39 :4 :: �: kic tc�Y:st$ir is it it is is is&it fc it sY �:r is is 4t 4r do it is �Y Yr 4t:c it 4r ir�ic is k4t:r is it it it��ir ie �•�4r tr �Y ir�:r it is&��ir it 4c ie is 9:��ic icy FLOW PROCESS FROM NODE 30.00 TO NODE 31.00 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 42.0 INCH PIPE IS 30.7 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 9.0 UPSTREAM NODE ELEVATION(FEET) = 1055.50 DOWNSTREAM NODE ELEVATION(FEET) = 1052.20 FLOW LENGTH(FEET) = 540.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 42.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 67.83 TRAVEL TIME(MIN.) = 1.00 TC(MIN.) = 20.39 4c sY is kic sir ic:Y �c is irx �k 9c 4c 4r is 4c ic�4r it is it 4t it it is is it it is 4cit is it do 4c it it is �Y ic�ic is ic�it���'c�:r:r k4c it sY it is 4r ir�:c X :t it 4r ir'.c qc ir„ FLOW PROCESS FROM NODE 31.00 TO NODE 31.00 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 100 YEAR RAINFALL INTENSITY(INCH/HR) = 2.561 SOIL CLASSIFICATION IS "B" Page 5 COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 3.34 SUBAREA RUNOFF(CFS) = 7.47 EFFECTIVE AREA(ACRES) = 32.28 AREA -AVERAGED Fm(INCH/HR) .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 32.28 PEAK FLOW RATE(CFS) = 72.22 TC(MIN) = 20.39 Y: is ;r * ;tYr Yr :; * � it Y; is is YcYr it it � Yr is Yr Yc is Yr is it * * is � Yr ie Yc YcYc it it ir* ie YrY: it Yr ie it Yr Ye is itYt �• *. YeYc it �• Yr ie itYr Y: Yc s: it * it Ye sY Y:.Yt sY it Yr Yr FLOW PROCESS FROM NODE 31.00 TO NODE 32.00 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 39.0 INCH PIPE IS 31.4 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 10.1 UPSTREAM NODE ELEVATION(FEET) = 1052.20 DOWNSTREAM NODE ELEVATION(FEET) = 1052.00 FLOW LENGTH(FEET) = 24.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 39.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 72.22 TRAVEL TIME(MIN.) _ .04 TC(MIN.) = 20.42 it �• is Yc � Yc it �• is *Yt * it it k �• * * icic'.e Yt it * it is it Yt * it k it � is it it i;'.t :e -k ir. it ie i; it it � i; � -k is is ic'x is it it it it it is it.Yt is Yt it ititsY sY it it is is it is FLOW PROCESS FROM NODE 32.00 TO NODE 32.00 IS CODE 1 ---------------------------------------------------------------------- »»>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< TOTAL NUMBER OF STREAMS = 2 --------- CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 1 ARE: TIME OF CONCENTRATION(MIN.) = 20.42 RAINFALL INTENSITY(INCH/HR) = 2.56 AREA -AVERAGED Fm(INCH/HR) = .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 EFFECTIVE STREAM AREA(ACRES) = 32.28 TOTAL STREAM AREA(ACRES) = 32.28 PEAK FLOW RATE(CFS) AT CONFLUENCE = 72.22 Yr Yr it* � Yc �`Y: *� Y: ic�Ye Y: Yr -k � Yt **YtYc it Ye it*tic* �•ir**Yt Yc#**�Yc Yc Y.•*Yr i; *Yc is it Y: **Yc Yc is is Yc*�*Yc�*i: Yt*ic �•Yc**ir* � Yr FLOW PROCESS FROM NODE 32.10 TO NODE 32.40 IS CODE = 2.1 ------------------------------------------------------------------------- »»>RATIONAL METHOD INITIAL SUBAREA ANALYSIS««< DEVELOPMENT IS COMMERCIAL --------- TC = K*[(LENGTH** 3.00)/(ELEVATION CHANGE)]** .20 INITIAL SUBAREA FLOW-LENGTH(FEET) = 750.00 UPSTREAM ELEVATION(FEET) = 1072.00 DOWNSTREAM ELEVATION(FEET) = 1066.75 ELEVATION DIFFERENCE(FEET) = 5.25 TC(MIN.) = .304*[( 750.00** 3.00)/( 5.25)]** .20 = 11.585 100 YEAR RAINFALL INTENSITY(INCH/HR) = 3.595 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA RUNOFF(CFS) = 6.56 TOTAL AREA(ACRES) = 2.07 PEAK FLOW RATE(CFS) = 6.56 Yr it B•*Yc ir'.e iY is*ir is*i: it Yc is it is*Y:*Yr it*Yri: Yr is Y: Yc is*Ye Yr*i:ic**ic is i;•Ye*Y:ic*Y: is is*ir Yc Yc is it**Ye Ytic Yr ir�ic it *YF Yr is Yc i.•**Yr Page 6 FLOW PROCESS FROM NODE 32.40 TO NODE 32.50 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 18.0 INCH PIPE IS 13.4 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 4.6 UPSTREAM NODE ELEVATION(FEET) = 1055.75 DOWNSTREAM NODE ELEVATION(FEET) = 1054.25 FLOW LENGTH(FEET) = 300.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 18.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 6.56 TRAVEL TIME(MIN.) = 1.08 TC(MIN.) = 12.66 :: is it it is it ie is it is is is ie u ie it is is is it is it is ie it is is it i� •k is is is is it it i; is is x 9tic it is it is 4c it is is it st is it it it is 3c ie it it is it 4c it it ie dr it it it sY is i� ie is FLOW PROCESS FROM NODE 32.50 TO NODE 32.50 IS CODE = 8 -------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< ------ 100 YEAR RAINFALL INTENSITY(INCH/HR) = 3.408 ---------------- SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 2.07 SUBAREA RUNOFF(CFS) = 6.21 EFFECTIVE AREA(ACRES) = 4.14 AREA -AVERAGED Fm(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) _ .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 4.14 PEAK FLOW RATE(CFS) = 12.42 TC(MIN) = 12.66 it � �'k is * it is � �- is � it it sY it is it i; � it it � is � i; i; i; :c i,• it is is is is �: it it is � is ie it is is it it :: is is � k it is is ie it it �.: is � it k ic'x is � is '.: is is is is & �kic it FLOW PROCESS FROM NODE 32.50 TO NODE 32.60 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 24.0 INCH PIPE IS 15.7 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 5.7 UPSTREAM NODE ELEVATION(FEET) = 1054.25 DOWNSTREAM NODE ELEVATION(FEET) = 1053.00 FLOW LENGTH(FEET) = 230.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 24.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 12.42 TRAVEL TIME(MIN.) _ .67 TC(MIN.) = 13.34 is ie �s is it it fr it is is*isY:r:c�sY �•SY��ir it i;i:ic'r it ic:t it is it it is it is it 4c is 4c it i;ic�'.r is �Y*iri;�i: is ic�ir�Yt it is :c it ic'.t it k�r it it �:�i; it it s: FLOW PROCESS FROM NODE 32.60 TO NODE 32.60 IS CODE = 8 ------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< -------- 00 YEAR RAINFALL INTENSITY(INCH/HR) = 3.304 -------------- SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 1.59 SUBAREA RUNOFF(CFS) 4.62 EFFECTIVE AREA(ACRES) = 5.73 AREA -AVERAGED Fm(INCH/HR) _ .07 AREA -AVERAGED Fp(INCH/HR) _ .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 5.73 PEAK FLOW RATE(CFS) = 16.65 TC(MIN) = 13.34 Page 7 k irk is it it iFk is k irk kick kirkkkirkkkkkkirkkkkkY'o irkkkkiskkkkkirkkkkkkkkkkkkkkirfckkkiek kkitkkkkick FLOW PROCESS FROM NODE 32.60 TO NODE 32.70 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 27.0 INCH PIPE IS 18.4 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 5.8 UPSTREAM NODE ELEVATION(FEET) = 1053.00 DOWNSTREAM NODE ELEVATION(FEET) = 1052.30 FLOW LENGTH(FEET) = 150.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 27.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 16.65 TRAVEL TIME(MIN.) _ .43 TC(MIN.) = 13.77 k it irkkkki: kkkkkkkkkkkkkick ickkkirkkkkkkkitkkick fekkkkkkirkkkkkkkkkkkkfe iekkkkiek irkkkiskkk FLOW PROCESS FROM NODE 32.70 TO NODE 32.70 IS CODE = 8 ------------------------------------------------------------------------ »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 100 YEAR RAINFALL INTENSITY(INCH/HR) = 3.241 --------------- SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 2.82 SUBAREA RUNOFF(CFS) = 8.04 EFFECTIVE AREA(ACRES) = 8.55 AREA -AVERAGED Fm(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) _ .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 8.55 PEAK FLOW RATE(CFS) = 24.36 TC(MIN) = 13.77 ..�•kkkkirkkkkkkkkkkkk�kkkkkkkkkkkirkkkirkkstirkksYskititic'+Y�tiriciriricisiriri:&i;��i:irici;ici:ic:kiririr� ir°k FLOW PROCESS FROM NODE 32.70 TO NODE 32.00 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW) ««< DEPTH OF FLOW IN 30.0 INCH PIPE IS 21.5 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 6.5 UPSTREAM NODE ELEVATION(FEET) = 1052.30 DOWNSTREAM NODE ELEVATION(FEET) = 1052.00 FLOW LENGTH(FEET) = 60.00 MANNING''S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 30.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 24.36 TRAVEL TIME(MIN.) _ .15 TC(MIN.) = 13.92 kkitkkkkkkkkki:itkkkk�•kk;;kkkkkkkkkkkitkkkirkkkkkkkkkkkkki:kkkkkkkkki:kkkkkkkickkki:� �- FLOW PROCESS FROM NODE 32.00 TO NODE 32.00 IS CODE 1 »»>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< »»>AND COMPUTE VARIOUS CONFLUENCED STREAM VALUES««< TOTAL NUMBER OF STREAMS = 2 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 2 ARE: TIME OF CONCENTRATION(MIN.) = 13.92 RAINFALL INTENSITY(INCH/HR) = 3.22 AREA -AVERAGED Fm(INCH/HR) = .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 EFFECTIVE STREAM AREA(ACRES) = 8.55 TOTAL STREAM AREA(ACRES) = 8.55 PEAK FLOW RATE(CFS) AT CONFLUENCE = 24.36 Page 8 RAINFALL INTENSITY AND TIME OF CONCENTRATION RATIO CONFLUENCE FORMULA USED FOR 2 STREAMS. ** PEAK FLOW RATE TABLE ** Q Tc Intensit Fp Ap FM Ae (CFS) (MIN.) (INCH/HR� (INCH/HR) (INCH/HR) (ACRES) 1 91.46 20.42 2.558 .75 .10 .08 40.83 2 86.70 13.92 3.219 .75 .10 .08 30.55 COMPUTED CONFLUENCE ESTIMATES ARE AS FOLLOWS: PEAK FLOW RATE(CFS) = 91.46 Tc(MIN.) = 20.425 EFFECTIVE AREA(ACRES) = 40.83 AREA -AVERAGED Fm(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) _ .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 40.83 -------------------------------------------------------------------------- END OF STUDY SUMMARY: TOTAL AREA(ACRES) = 40.83 TC(MIN.) = 20.42 EFFECTIVE AREA(ACRES) = 40.83 AREA -AVERAGED Fm(INCH/HR)= .08 AREA -AVERAGED Fp(INCH/HR) _ .75 AREA -AVERAGED Ap = .10 PEAK FLOW RATE(CFS) = 91.46 ** PEAK FLOW RATE TABLE ** Q Tc Intensit Fp Ap Fm Ae (CFS) (MIN.) (INCH/HR� (INCH/HR) (INCH/HR) (ACRES) 1 86.70 13.92 3.219 .75 .10 .08 30.55 2 91.46 20.42 2.558 .75 .10 .08 40.83 END OF RATIONAL METHOD ANALYSIS Page 9 Technical Appendix E 25-Year Rational Method Analysis Derived from Preliminary Hydrology & Hydraulic Calculations for Sierra Business Park Huitt-Zollars, Inc — November 1, 2003 it it is it is it it s4 it*ir it it it is it sY is it sY is it it is ie is it ie is it it is*ic ie*it it it it it sY sY is*ic it it it ie it it icic it it it ie it ie is it it is it it it it it***ic is ie ie RATIONAL METHOD HYDROLOGY COMPUTER PROGRAM PACKAGE (Reference: 1986 SAN BERNARDINO CO. HYDROLOGY CRITERION) (c) Copyright 1983-93 Advanced Engineering Software (aes) Ver. 1.9B Release Date: 7/18/93 License ID 1202 Analysis prepared by: HUITT-ZOLLARS, INC. 15101 RED HILL AVENUE TUSTIN, CALIFORNIA 92780-6500 PHONE (714) 259-7900 * FAX (714) 259-0210 --------------------------------------------------------- FILE NAME: 202QO25A.DAT TIME/DATE OF STUDY: 13: 6 6/14/2004 USER SPECIFIED HYDROLOGY AND HYDRAULIC MODEL INFORMATION: --*TIME-OF-CONCENTRATION MODEL* - USER SPECIFIED STORM EVENT(YEAR) = 25.00 SPECIFIED MINIMUM PIPE SIZE(INCH) = 18.00 SPECIFIED PERCENT OF GRADIENTS(DECIMAL) TO USE FOR FRICTION SLOPE = .95 "USER -DEFINED LOGARITHMIC INTERPOLATION USED FOR RAINFALL* 10-YEAR STORM 60-MINUTE INTENSITY(INCH/HOUR) _ .920 100-YEAR STORM 60-MINUTE INTENSITY(INCH/HOUR) 1.340 COMPUTED RAINFALL INTENSITY DATA: STORM EVENT = 25.00 1-HOUR INTENSITY(INCH/HOUR) = 1.0659 SLOPE OF INTENSITY DURATION CURVE = .6000 *�•it it it*i:it::�•i;::-k ie it is it it it ie is*ir ic�-k it i:i:i: it is it is it it is i:i:�•ir it it***it is is is is ie is i; is is is**its: �•�•it it it *ic it *ie is it is itk FLOW PROCESS FROM NODE 1.00 TO NODE 1.00 IS CODE = 15 ---------------------------------------------------------------------------- »»>DEFINE MEMORY BANK # 1 ««< MEMORY BANK # 1 DEFINED AS FOLLOWS: Q(CFS) TC(MIN.) Fp(INCH/HR) Ap FM(INCH/HR) Ae(ACRES) 1 77.38 12.95 .392 .30 .119 33.27 2 82.27 19.92 .381 .32 .124 46.48 3 80.88 21.47 .378 .33 .125 48.01 TOTAL AREA = 48.01 '.c'r-.e;;'r�•iti:*i;*i:*i:*i: ic�i:ici:ic:F it ir:;*Y;�•::ir*it�•iri: *ir is �•i:�*kkir is is is*�-tic is s'F it is is it �•ir it is sY it&ic kir it fir is it it it FLOW PROCESS FROM NODE 1.00 TO NODE 1.00 IS CODE = 14 ------------------------------------------------------ »»>MEMORY BANK # 1 COPIED ONTO MAIN -STREAM MEMORY««< MAIN -STREAM MEMORY DEFINED AS FOLLOWS: Q(CFS) TC(MIN.) Fp(INCH/HR) AP FM(INCH/HR) Ae(ACRES) 1 77.38 12.95 .392 .30 .119 33.27 2 82.27 19.92 .381 .32 .124 46.48 3 80.88 21.47 .378 .33 .125 48.01 TOTAL AREA = 48.01 *i:*:;iti:i;iri:i:4ri:*:i:***��:1•ic it*�•*it ic�i: is is is ir�i:.i; ie it*:.•i: ie it it is is :.•i: :t ick**„ wit �•st �i: �•i: is is is is is *it is it FLOW PROCESS PROCESS FROM NODE 1.00 TO NODE 1.00 IS CODE = 12 Page 1 ------------------------------------------ »»>CLEAR MEMORY BANK # 1 ««< it is it it it it it it it it it it it it s4 it it it it it is it it is ie is it it it it it is it it ic'k*it it it it it i<it it is it is ie it it it it is it it it it it it ie it it it it it is ie it it is ie it it it is FLOW PROCESS FROM NODE 1.00 TO NODE 1.00 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.066 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 7.06 SUBAREA RUNOFF(CFS) = 12.65 EFFECTIVE AREA(ACRES) = 53.54 AREA -AVERAGED FM(INCH/HR) _ .12 AREA -AVERAGED Fp(INCH/HR) = .40 AREA -AVERAGED Ap = .30 TOTAL AREA(ACRES) = 55.07 PEAK FLOW RATE(CFS) = 93.88 TC(MIN) = 19.92 iri: ie sir it is it it it it it is it it �Y it is kic it i; it it is sir it it it is it it is it is it ie it ie ie ie is it it sY�it ie is is it ie irir it is 4e i; ie�ie it it it is kie it it ie is ie it ie ie FLOW PROCESS FROM NODE 1.00 TO NODE 2.00 IS CODE = 3 ---------------------------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW) ««< -------------------------------------------------------------------- DEPTH OF FLOW IN 51.0 INCH PIPE IS 36.8 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 8.6 UPSTREAM NODE ELEVATION(FEET) = 1079.00 DOWNSTREAM NODE ELEVATION(FEET) = 1072.02 FLOW LENGTH(FEET) = 1620.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 51.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 93.88 TRAVEL TIME(MIN.) = 3.15 TC(MIN.) = 23.07 is >; �-X�•i: ir�i.•�ir&sY is i;iti: it it ie it i; ic�kir&i:&&ir�•ir it it ir�ic i:iei; it is it it it it is&ir#ie ir'�it it it it it sY it icic it i; is i; it is it it it#:: it is FLOW PROCESS FROM NODE 2.00 TO NODE 2.00 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 25 YEAR RAINFALL INTENSITY(INCH/HR) = 1.892 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 2.49 SUBAREA RUNOFF(CFS) = 4.07 EFFECTIVE AREA(ACRES) = 56.03 AREA -AVERAGED FM(INCH/HR) _ .12 AREA -AVERAGED Fp(INCH/HR) = .40 AREA -AVERAGED Ap = .29 TOTAL AREA(ACRES) = 57.56 PEAK FLOW RATE(CFS) = 93.88 TC(MIN) = 23.07 i;iti: it ie�i;i:i:.,r.,i:R•:ir�,.•ir it it it i.•i:�i:„sir it sir is �i: sir i;ti;i; sir �i;4:�•i:�i:i;�•i: ir�i:i:::i:�&:: ir�ie it it �•it i; *i: it ir�i: �"ir FLOW PROCESS FROM NODE 2.00 TO NODE 2.00 IS CODE = 1 ---------------------------------------------------------------------------- »»>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< ---------------------------------------------------------------------------- TOTAL NUMBER OF STREAMS = 2 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 1 ARE: TIME OF CONCENTRATION(MIN.) = 23.07 RAINFALL INTENSITY(INCH/HR) = 1.89 AREA -AVERAGED Fm(INCH/HR) _ .12 Page 2 AREA -AVERAGED Fp(INCH/HR) _ .40 AREA -AVERAGED Ap = .29 EFFECTIVE STREAM AREA(ACRES) = 56.03 TOTAL STREAM AREA(ACRES) = 57.56 PEAK FLOW RATE(CFS) AT CONFLUENCE = 93.88 it ir*ir*it it ie it it is iric it ie is it ir&ic is it it ie iris it i; it it sY it is it it k ie is iris it it it sY is do it is is it it ie*ir it is it it it it is is ie it it is it it ie it ie*ie it is it FLOW PROCESS FROM NODE 2.10 TO NODE 2.20 IS CODE = 2.1 ----------------------------------------------------------------------------- »»>RATIONAL METHOD INITIAL SUBAREA ANALYSIS««< DEVELOPMENT IS COMMERCIAL TC = K*[(LENGTH** 3.00)/(ELEVATION CHANGE)]** .20 INITIAL SUBAREA FLOW-LENGTH(FEET) = 435.00 UPSTREAM ELEVATION(FEET) = 1088.50 DOWNSTREAM ELEVATION(FEET) = 1087.50 ELEVATION DIFFERENCE(FEET) = 1.00 TC(MIN.) = .304*[( 435.00** 3.00)/( 1.00)]** .20 = 11.640 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.851 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA RUNOFF(CFS) = 4.52 TOTAL AREA(ACRES) = 1.81 PEAK FLOW RATE(CFS) = 4.52 *ic sY 9:ir*irR•ic is it is i�it it iF it**ie �k ic��Y is it is it it is is it it it it iris it it it it it it it sY*ie it ie is it it ie it is it �c is it it*ic it it sY �t it it ie it ie is sY it it it FLOW PROCESS FROM NODE 2.20 TO NODE 2.30 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< ------------------------------------------------------- - DEPTH OF FLOW IN 18.0 INCH PIPE IS 10.3 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 4.3 UPSTREAM NODE ELEVATION(FEET) = 1081.50 DOWNSTREAM NODE ELEVATION(FEET) = 1080.50 FLOW LENGTH(FEET) = 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 18.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 4.52 TRAVEL TIME(MIN.) _ .77 TC(MIN.) = 12.41 **i;'.r is it**ir is is*ic it*ir it*ie ki; it it*eY*ic*'.: it is ie is it ie ie it it is it it it*ic is it it it is i; it is it*it it ie is is is is it *ir it �k it is it ie ie**iris FLOW PROCESS FROM NODE 2.30 TO NODE 2.30 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.744 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 1.79 SUBAREA RUNOFF(CFS) = 4.30 EFFECTIVE AREA(ACRES) = 3.60 AREA -AVERAGED FM(INCH/HR) _ .07 AREA -AVERAGED Fp(INCH/HR) _ .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 3.60 PEAK FLOW RATE(CFS) = 8.65 TC(MIN) = 12.41 iti;ici;i: it it is it it it it is it ir°k it it iris it it s4 it i:i:'.t*ic s4 it i; it is it*ie it*sY*i�sY it is sY**i; it it it*-k it �•ir �k it it it�ir is*-k it is*ie ie it i.•it it SY FLOW PROCESS FROM NODE 2.30 TO NODE 2.40 IS CODE = 3 ---------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< Page 3 »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW) ««< --- DEPTH OF FLOW IN 21.0 INCH PIPE IS 14.1 INCHES ------------ PIPE -FLOW VELOCITY(FEET/SEC.) = 5.0 UPSTREAM NODE ELEVATION(FEET) = 1080.50 DOWNSTREAM NODE ELEVATION(FEET) = 1079.50 FLOW LENGTH(FEET) = 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 21.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 8.65 TRAVEL TIME(MIN.) _ .66 TC(MIN.) = 13.07 it is it is is icir is is is is ie it ic:c it is is is if it it it is is it it it it is it&ir is ie is is it ie it it is it is it it Yc it it is it it is is ie it is it is is it is it s4 ie it is is is it is it is if is i� FLOW PROCESS FROM NODE 2.40 TO NODE 2.40 IS CODE = 8 ----------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 5 YEAR RAINFALL INTENSITY (INCH/HR) = 2.659 ---------------- SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 1.78 SUBAREA RUNOFF(CFS) = 4.14 EFFECTIVE AREA(ACRES) = 5.38 AREA -AVERAGED FM(INCH/HR) _ .07 AREA -AVERAGED Fp(INCH/HR) _ .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 5.38 PEAK FLOW RATE(CFS) = 12.51 TC(MIN) = 13.07 i; it it X i.• is it is i; if ira if ie is it :Y :; it it is is it i; is it it is � °k is ie is it °k it it it is is is i; is it it ie it is it it �k it it it is is is it � is is is � is is it ir:ic it is �• it is is is it FLOW PROCESS FROM NODE 2.40 TO NODE 2.50 IS CODE '= 3 >>>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 24.0 INCH PIPE IS 16.3 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 5.5 UPSTREAM NODE ELEVATION(FEET) = 1079.50 DOWNSTREAM NODE ELEVATION(FEET) = 1078.50 FLOW LENGTH(FEET) = 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 24.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 12.51 TRAVEL TIME(MIN.) _ .60 TC(MIN.) = 13.68 it it � :t it i; it ie is it it is :t a ici: « � it it it it is ie is & if it i� ie it � i; is is ie if it ie ie is is it �• it i; it it it is � is sY is is it is �• it sk it it s: �• ie is it is itk is icit iric is FLOW PROCESS FROM NODE 2.50 TO NODE 2.50 IS CODE = 8 -------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 5 YEAR RAINFALL INTENSITY(INCH/HR) = 2.588 --------------- SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 1.78 SUBAREA RUNOFF(CFS) = 4.03 EFFECTIVE AREA(ACRES) = 7.16 AREA -AVERAGED FM(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) _ .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) 7.16 PEAK FLOW RATE(CFS) = 16.20 TC(MIN) = 13.68 �i:�'it �iC is it it if is it if is if i.•�-it it i; if is �'•i;•i;iri:kir:t iennkn kif �i:ici;,if�R•i;k'F i.•i: i:.if ic�ir it it kir is i; i:�n �'�i; i; nif is it it i;n :: i; �' FLOW PROCESS FROM NODE 2.50 TO NODE 2.60 IS CODE = 3 --------------------------------------------------------------------------- Page 4 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 27.0 INCH PIPE IS 17.6 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 5.9 UPSTREAM NODE ELEVATION(FEET) = 1078.50 DOWNSTREAM NODE ELEVATION(FEET) = 1077.50 FLOW LENGTH(FEET) = 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 27.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 16.20 TRAVEL TIME(MIN.) _ .56 TC(MIN.) = 14.24 ir:cYric4tYricirics4ir4eir4f:rsYir4rlr�4�ricis4rici:9eic�:r:Yir4eic4r4r�rirfr4r�cie9r:fsYYeic4tic4e4e��irYciefririric4cic�C�4t�'r'xie4r�sYiciricie,fr FLOW PROCESS FROM NODE 2.60 TO NODE 2.60 IS CODE = 8 ------------------------------------------------------ >>>>>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 5 YEAR RAINFALL INTENSITY(INCH/HR) = 2.526 ----------------- SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 1.78 SUBAREA RUNOFF(CFS) = 3.93 EFFECTIVE AREA(ACRES) = 8.94 AREA -AVERAGED FM(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) _ .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 8.94 PEAK FLOW RATE(CFS) = 19.72 TC(MIN) = 14.24 �4r 4e is is ie 4r is is&�:: it Yc ie �;i:ic:r is �; tic 4: it it 4:�ir ic��&pie is if k Yc it dc4c k4c 4c 4c 4r:r fir it fr*Yt it�ir st it is °k it �t &ic�ic ic�Y sir it �Y iex it FLOW PROCESS FROM NODE 2.60 TO NODE 2.70 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 27.0 INCH PIPE IS 20.5 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 6.1 UPSTREAM NODE ELEVATION(FEET) = 1077.50 DOWNSTREAM NODE ELEVATION(FEET) = 1076.50 FLOW LENGTH(FEET) = 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 27.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 19.72 TRAVEL TIME{MIN.) _ .55 TC(MIN.) = 14.79 '.:4ei: fir �:'.::t���k sY it it ir�ir�'.ti: is it it&:r it icx :r it �Ye :c :r :c��•�ir �.�:f „ir s: �dc it ic�ic ir:r itkk�sY it :r�ic is ir�ir iric ie :r sY :e is is is FLOW PROCESS FROM NODE 2.70 TO NODE 2.70 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 5 YEAR RAINFALL INTENSITY(INCH/HR) = 2.470 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 1.78 SUBAREA RUNOFF(CFS) = 3.84 EFFECTIVE AREA(ACRES) = 10.72 AREA -AVERAGED Fm(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) 10.72 PEAK FLOW RATE(CFS) = 23.10 TC(MIN) = 14.79 FLOW PROCESS FROM NODE 2.70 TO NODE 2.80 I5 CODE = 3 Page 5 -----------.----------------------------------------------------------------- >>>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 30.0 INCH PIPE IS 20.6 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 6.4 UPSTREAM NODE ELEVATION(FEET) = 1076.50 DOWNSTREAM NODE ELEVATION(FEET) = 1075.50 FLOW LENGTH(FEET) = 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 30.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 23.10 TRAVEL TIME(MIN.) _ .52 TC(MIN.) = 15.31 FLOW PROCESS FROM NODE 2.80 TO NODE 2.80 IS CODE = 8 --------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.419 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 1.78 SUBAREA RUNOFF(CFS) = 3.76 EFFECTIVE AREA(ACRES) = 12.50 AREA -AVERAGED Fm(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 12.50 PEAK FLOW RATE(CFS) = 26.37 TC(MIN) = 15.31 � it ««««««««««««ie.« «« «««««««««««�• ««�- «««ir « ««««««««««it ««'..• is �• «««« ««« ;c.««««««««« �• ir:: «i: FLOW PROCESS FROM NODE 2.80 TO NODE 2.90 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 30.0 INCH PIPE IS 23.0 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 6.5 UPSTREAM NODE ELEVATION(FEET) = 1075.50 DOWNSTREAM NODE ELEVATION(FEET) = 1074.50 FLOW LENGTH(FEET) = 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 30.00 NUMBER OF PIPES 1 PIPE-FLOW(CFS) = 26.37 TRAVEL TIME(MIN.) _ .51 TC(MIN.) = 15.82 ««. «««• ««««i: «««««ir it ««. ««« ««• «««ir ««««««««««ir ««ir «««« �• «««« �• «««««« « «ir «ir «««««««««• �- is « FLOW PROCESS FROM NODE 2.90 TO NODE 2.90 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.372 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 1.78 SUBAREA RUNOFF(CFS) = 3.68 EFFECTIVE AREA(ACRES) = 14.28 AREA -AVERAGED FM(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 14.28 PEAK FLOW RATE(CFS) = 29.52 TC(MIN) = 15.82 Page 6 FLOW PROCESS FROM NODE 2.90 TO NODE 2.10 IS CODE = 3 >COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 33.0 INCH PIPE IS 22.5 INCHES - - PIPE -FLOW VELOCITY(FEET/SEC.) = 6.8 UPSTREAM NODE ELEVATION(FEET) = 1074.50 DOWNSTREAM NODE ELEVATION(FEET) = 1073.75 FLOW LENGTH(FEET) = 150.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 33.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 29.52 TRAVEL TIME(MIN.) _ .37 TC(MIN.) = 16.18 is is is it is is it is it :: is ie is is is it it is is is it is it ;r is it ie it it it it ie it is is is is is is it it is it it ie it is &'k is sY it is 9: it Y is is it is icir is k is is is it it is sY is it is it it FLOW PROCESS FROM NODE 2.10 TO NODE 2.10 IS CODE = 8 ------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.340 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 1.17 SUBAREA RUNOFF(CFS) = 2.38 EFFECTIVE AREA(ACRES) = 15.45 AREA -AVERAGED FM(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 15.45 PEAK FLOW RATE(CFS) = 31.49 TC(MIN) = 16.18 ..&ir&ic ici: it i; is&iri: ic���•�ir it i;i;isi:iti; sir is �ic�*ic kir is ic��ic it it �,:�sY�ic it i; it is it �k it i; it it is tic is it it is is is is it :t tic ic�:r is FLOW PROCESS FROM NODE 2.10 TO NODE 2.11 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW) ««< DEPTH OF FLOW IN 33.0 INCH PIPE IS 23.7 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 6.9 UPSTREAM NODE ELEVATION(FEET) = 1073.75 DOWNSTREAM NODE ELEVATION(FEET) = 1072.40 FLOW LENGTH(FEET) = 270.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 33.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 31.49 TRAVEL TIME(MIN.) _ .65 TC(MIN.) = 16.83 i; is is it is it it is ie is is it it it it it it is ir. is it it it is ie is is it is is it is •k is ie is it is it it it ie it 4c it it it i; is ie is is is is it it is st is i; it it is �t it it it is is it is ie is is is it FLOW PROCESS FROM NODE 2.11 TO NODE 2.11 IS CODE = 8 --------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< --------- 5 YEAR RAINFALL INTENSITY(INCH/HR) = 2.285 --------------- SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 1.25 SUBAREA RUNOFF(CFS) = 2.49 EFFECTIVE AREA(ACRES) = 16.70 AREA -AVERAGED FM(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 16.70 PEAK FLOW RATE(CFS) = 33.22 TC(MIN) = 16.83 Page 7 Yr Yr YFYr is it Yr Yr Yc Yr it Yc Ye Yr Yr Yt Ya * Yc is Yr * Yr fr Ye * Yr Yc Yc tY * Yt Yr Yc Ye Yr Ye Yc >Y Yt Yr Yr Yr Yr Yr Yc Yr Ye Yr Ye * Ye Yt YrYc Yr Yr Yr Ye Yr Yr Yr Yc Yr Yr Yc Ye Yr Ytir Yc Yc Yr Y Yc Yr --FLOW-PROCESS-FROM NODE 2.11 TO NODE 2.00 IS CODE = 3 ------------------------- ____ »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 33.0 INCH PIPE IS 24.7 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 7.0 UPSTREAM NODE ELEVATION(FEET) = 1072.40 DOWNSTREAM NODE ELEVATION(FEET) = 1072.02 FLOW LENGTH(FEET) = 76.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 33.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 33.22 TRAVEL TIME(MIN.) _ .18 TC(MIN.) = 17.02 Yc Yr Yc Yr Yr Yr Yc Yr Yr Yr Yt Yr Yr YYr Yt it Yt Yr Ye Yr Ye Yrir Yr Yr Yc Yc Yr is Yr Yr Yr Yr Yr YrYt Yr Yr Yt * it Ys Yr Yt Yr Yc Yr Yt Yc Yt Yc Yr Yr it Yc Yr tYYc Yc Yc Ye Yr Yc Yc is Yr Yr Yc Yc it Yr Yc Ye Yr Ye FLOW PROCESS FROM NODE 2.00 TO NODE 2.00 IS CODE --= 1 ---------------------- »»>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< »»>AND COMPUTE VARIOUS CONFLUENCED STREAM VALUES««< TOTAL NUMBER OF STREAMS = 2 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 2 ARE: TIME OF CONCENTRATION(MIN.) = 17.02 RAINFALL INTENSITY(INCH/HR) = 2.27 AREA -AVERAGED F►►1(INCH/HR) = .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 EFFECTIVE STREAM AREA(ACRES) = 16.70 TOTAL STREAM AREA(ACRES) = 16.70 PEAK FLOW RATE(CFS) AT CONFLUENCE = 33.22 RAINFALL INTENSITY AND TIME OF CONCENTRATION RATIO CONFLUENCE FORMULA USED FOR 2 STREAMS. *Y7 PEAK FLOW RATE TABLE ** Q TC Intensit (CFS) (MIN.) (INCH/HR� Fp (INCH/HR) Ap FM (INCH/HR) Ae (ACRES) 1 125.54 16.11 2.346 2 121.36 23.07 1.892 .46 .22 .10 58.62 3 118.37 24.62 1.819 .44 .43 .24 .25 .11 72.73 74.26 4 126.34 17.02 2.270 .46 .22 .11 .10 61.25 COMPUTED CONFLUENCE ESTIMATES ARE AS FOLLOWS: PEAK FLOW RATE(CFS) = 126.34 TC(MIN.) = 17.017 EFFECTIVE AREA(ACRES) = 61.25 AREA -AVERAGED FM(INCH/HR) _ AREA -AVERAGED Fp(INCH/HR) _ .46 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 74.26 .22 Yc Yr Yc * Yc * * Yr Yc Yr * * Yr Yc Yc Yr Yr Yr Yt Yr Yr Yc Yc Yc it Yt Yr Yc YcYr it Yc Yr Yt *Yc Yr Yr Yc Yc * Yt Yr Yr Yr Yc Yc Yc Yr Yt Yr * * Yr Yt Yr Yc Yc it * * it Yr Yr * * * it Yc Yc * * *Yt Yr Yc FLOW PROCESS FROM NODE 2.00 TO NODE 3.00 IS CODE = 3 -- - ---------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< --»»>USING-COMPUTER- ESTIMATED-PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 48.0 INCH PIPE IS 35.0 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 12.9 UPSTREAM NODE ELEVATION(FEET) = 1072.02 DOWNSTREAM NODE ELEVATION(FEET) = 1069.92 FLOW LENGTH(FEET) = 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 48.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 126.34 TRAVEL TIME(MIN.) _ .26 TC(MIN.) = 17.28 Page 8 4r is*4e'r it 9c sr k s4 it �r it is it is it is is �c Yr is is k it it ie is fr ie 4c ie 4r Yt is 4t 4r it 'i 4r ie. is Y st is it is �t ie it 4c 4r ie it is Yr is it ft ie �'c&ic 9r it ie is 4r 'lc is 4c 4c is 4e fe is FLOW PROCESS FROM NODE 3.00 TO NODE 3.00 IS CODE = 8 --------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.250 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 1.25 SUBAREA RUNOFF(CFS) = 2.45 EFFECTIVE AREA(ACRES) 62.50 AREA -AVERAGED Fm(INCH/HR) _ .10 AREA -AVERAGED Fp(INCH/HR) = .46 AREA -AVERAGED Ap = .22 TOTAL AREA(ACRES) = 75.51 PEAK FLOW RATE(CFS) = 126.34 TC(MIN) = 17.28 :rir;: 4c Vic'::r it 4: fe it k4r 4:*ic is :tlr �Y it&ic it sY is it �c �Y�ir it is f: is 4c*ir it it 4r it �k 4r is �c 4r ks4 it is Yc 4t it is 9i*sF ir-k iric is is f<ic is is it is �'e it is it �c it FLOW PROCESS FROM NODE 3.00 TO NODE 4.00 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 45.0 INCH PIPE IS 35.3 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 13.6 UPSTREAM NODE ELEVATION(FEET) = 1069.92 DOWNSTREAM NODE ELEVATION(FEET) = 1069.17 FLOW LENGTH(FEET) = 60.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 45.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 126.34 TRAVEL TIME(MIN.) _ .07 TC(MIN.) = 17.35 .. .. :: k:r:'ci:ir�•4c�*'.:4c*::***icy**4t �'.:.*4:ir�*�•**�Y�:rit:t�•fc �..•*�•**ic{c:t4c***icy****fit 4r**k �--k*�'r Ye :r *."c is it FLOW PROCESS FROM NODE 4.00 TO NODE 4.00 IS CODE = 1 ------------------------------------------------------------------------ »»>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< TOTAL NUMBER OF STREAMS = 2 --------- CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 1 ARE: TIME OF CONCENTRATION(MIN.) = 17.35 RAINFALL INTENSITY(INCH/HR) = 2.24 AREA -AVERAGED Fm(INCH/HR) = .10 AREA -AVERAGED Fp(INCH/HR) = .46 AREA -AVERAGED Ap = .22 EFFECTIVE STREAM AREA(ACRES) = 62.50 TOTAL STREAM AREA(ACRES) = 75.51 PEAK FLOW RATE(CFS) AT CONFLUENCE = 126.34 irz:Jc*ic**ie;:***'cY*ic**4c dr it fe*ic'c:::r;c is dr*Y'.r 9c is it*3r it*ic'c:cic*'r is is 4c Y it*ir*'k it i:ir**ic s4 it 3c is *ir is is it is 4r is k d: 't FLOW PROCESS FROM NODE 4.10 TO NODE 4.20 IS CODE = 2.1 ------------------------------------------------------------------------- »»>RATIONAL METHOD INITIAL SUBAREA ANALYSIS««< DEVELOPMENT IS COMMERCIAL TC = K*[(LENGTH** 3.00)/(ELEVATION CHANGE)]** .20 INITIAL SUBAREA FLOW-LENGTH(FEET) = 511.00 UPSTREAM ELEVATION(FEET) = 1085.00 DOWNSTREAM ELEVATION(FEET) = 1084.25 ELEVATION DIFFERENCE(FEET) = .75 TC(MIN.) = .304*[( 511.00** 3.00)/( .75)]** .20 = 13.580 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.599 Page 9 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA RUNOFF(CFS) = 6.38 TOTAL AREA(ACRES) = 2.81 PEAK FLOW RATE(CFS) = 6.38 >; is i; k is it it is it is is is kir is it it ie is it is sY is it is it it * it it sY is it it is is � it k is it it it it it it iciCir it is it it it it is it is is i� is it it it is ie ie �Y iv it it ie it is is it FLOW PROCESS FROM NODE 4.20 TO NODE 4.30 IS CODE = 3 >>>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 18.0 INCH PIPE IS 13.1 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 4.6 UPSTREAM NODE ELEVATION(FEET) = 1078.25 DOWNSTREAM NODE ELEVATION(FEET) = 1077.25 FLOW LENGTH(FEET) = 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 18.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 6.38 TRAVEL TIME(MIN.) _ .72 TC(MIN.) = 14.30 & & is :h & i; is it is it ie it it it is it it is is is it is it is ie is �" ie is i; it is it ie ie ie is i; it is it is is irit is ie it icic � it is i; it it it it is it is is it is is it ie it is is is i; � i; ie it FLOW PROCESS FROM NODE 4.30 TO NODE 4.30 IS CODE = 8 -------------------------------------------- ------ »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.520 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 2.81 SUBAREA RUNOFF(CFS) = 6.18 EFFECTIVE AREA(ACRES) = 5.62 AREA -AVERAGED Fm(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 5.62 PEAK FLOW RATE(CFS) = 12.37 TC(MIN) = 14.30 is it it � is it is is is i; � it it �k irk «• is � is it it it is itic it it it is i< is is is fc it it is is ie it it is i; '� it is is is i; � it it i; i< i< i; is is it it it i; it it it it it it it is it is :Y i; i< FLOW PROCESS FROM NODE 4.30 TO NODE 4.40 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 24.0 INCH PIPE IS 16.1 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 5.5 UPSTREAM NODE ELEVATION(FEET) = 1077.25 DOWNSTREAM NODE ELEVATION(FEET) = 1076.25 FLOW LENGTH(FEET) = 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 24.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 12.37 TRAVEL TIME(MIN.) _ .61 TC(MIN.) = 14.91 �• k is is is is is it it is � it it �• is is it it it i;'.c is �k is is sY is � is it is it is is it it it is is is it it it is is it is is ie it it & sY is it is is k it � it is it i; is is it is it it is is is # it is FLOW PROCESS FROM NODE 4.40 TO NODE 4.40 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.458 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 Page 10 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 2.81 SUBAREA RUNOFF(CFS) = 6.03 EFFECTIVE AREA(ACRES) = 8.43 AREA -AVERAGED FM(INCH/HR) _ .07 AREA -AVERAGED Fp(INCH/HR) _ .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 8.43 PEAK FLOW RATE(CFS) = 18.08 TC(MIN) = 14.91 s44rsY4ric�'riricirir�Yse4cicireYieiriririric4e4r4c4cie4cie�Y�rir4ritirir9ricitYrte4r4rie4e4riririririrsY4r�Yirfcir4r�Yi:iruiriedr4efeir�eieYc�r4c4r4ric FLOW PROCESS FROM NODE 4.40 TO NODE 4.50 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 27.0 INCH PIPE IS 19.1 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 6.0 UPSTREAM NODE ELEVATION(FEET) = 1076.25 DOWNSTREAM NODE ELEVATION(FEET) = 1075.25 FLOW LENGTH(FEET) = 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 27.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 18.08 TRAVEL TIME(MIN.) _ .55 TC(MIN.) = 15.46 4r Yr it 4r :t �: it 4r'.r 4c sY it it it is is �Y � is it grit dr * is it it ie 4r it it it is is it le it it 4r dt it �Y ie it it it �Y it ft �'e �c it is eY 4r it is it � de * it it it it it 4r it it it dr 4e ie it �r it FLOW PROCESS FROM NODE 4.50 TO NODE 4.50 IS CODE = 8 ------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.405 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 2.81 SUBAREA RUNOFF(CFS) = 5.89 EFFECTIVE AREA(ACRES) = 11.24 AREA -AVERAGED Fm(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 11.24 PEAK FLOW RATE(CFS) = 23.57 TC(MIN) = 15.46 '.e:: ie ir��ir 4r 4r'.r sir 4e it s: is 4r�ir it it it ie 4t 4r it it 4c is �Y it it is fr it it 4r it is ie ir��ie�4t 4r it s'e ie �'r�ir ie it it it fr:e it it is 4r ie 4e ie ie �•&4e fr it �:4c it :e FLOW PROCESS FROM NODE 4.50 TO NODE 4.60 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< ------------------------------------------------------------------------ DEPTH OF FLOW IN 30.0 INCH PIPE IS 20.9 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 6.4 UPSTREAM NODE ELEVATION(FEET) = 1075.25 DOWNSTREAM NODE ELEVATION(FEET) = 1074.25 FLOW LENGTH(FEET) = 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 30.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 23.57 TRAVEL TIME(MIN.) _ .52 TC(MIN.) = 15.98 i::e h it is is :: is :c x" it is � 4r k 4r it is � ie is it is :r sY :::c it Yc k 4e is it �Y oY4e� it it it is is it dr4r. k it it �Y it it � is ie ie ie it � it :c !r is � ie 4e ie �e it is 4c is it dr it sY FLOW PROCESS FROM NODE 4.60 TO NODE 4.60 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.358 SOIL CLASSIFICATION IS "B" Page 11 COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 2.81 SUBAREA RUNOFF(CFS) = 5.77 EFFECTIVE AREA(ACRES) = 14.05 AREA -AVERAGED FM(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 14.05 PEAK FLOW RATE(CFS) = 28.86 TC(MIN) = 15.98 Yt Yt Ye Y< k Yr Yc Yc Yc Yt it Yr Yr Yt x Yr Y<it fc it sY Yc Y<ir 4c sk it Yc Yc Yc & Y: is Yc s4 Y: Yt Yc Y: it is Yr Yr it Yr Yc Yc Yr it Yr Yr is Yc ie Y: Yr it Yr :: Ye Yr YrYr is Ye Yc is Y: Yc Ye Ye sY Yc is Yc Yr FLOW PROCESS FROM NODE 4.60 TO NODE 4.70 IS CODE = 3 -------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 33.0 INCH PIPE IS 22.2 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 6.8 UPSTREAM NODE ELEVATION(FEET) = 1074.25 DOWNSTREAM NODE ELEVATION(FEET) = 1073.25 FLOW LENGTH(FEET) = 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 33.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 28.86 TRAVEL TIME(MIN.) _ .49 TC(MIN.) = 16.47 Y: is � :R � Yr sk sY Yc sY >; it sY Y: Yc � sY Yrir.Yr � Yr Yt � it Yr Yr sF Yc sY Yr Yr Yc it Yt it Yt Yr is sYYc is �Yc Yc sY � is sY Y: it sY sY sY Yt Yc sY Yr sY Yr it Ys Yt Yc sk sY Y: Yc it Yr it sY Yc * Yc k FLOW PROCESS FROM NODE 4.70 TO NODE 4.70 IS CODE = 8 ------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.315 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 2.81 SUBAREA RUNOFF(CFS) = 5.67 EFFECTIVE AREA(ACRES) = 16.86 AREA -AVERAGED FM(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 16.86 PEAK FLOW RATE(CFS) = 34.00 TC(MIN) = 16.47 FLOW PROCESS FROM NODE 4.70 TO NODE 4.80 IS CODE = 3 ---------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< -------_____ DEPTH OF FLOW IN 33.0 INCH PIPE IS 25.2 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 7.0 UPSTREAM NODE ELEVATION(FEET) = 1073.25 DOWNSTREAM NODE ELEVATION(FEET) = 1072.25 FLOW LENGTH(FEET) = 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 33.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 34.00 TRAVEL TIME(MIN.) .48 TC(MIN.) = 16.95 Yt Yc sY sYYc sY R-Yr Yr it irk&.:r Yr ;; �Ye sY Y:sY sY Y: sk Yr �k'.r Ye sY �Yr is Yr Yr Yr�I; Yc Yr st Yr:c:c �sY it it sY is Yr Ye�'.e��it Yr it �sY Yr ie Yr it is Yt��Yrir�Ye Y: i:'.e Y: FLOW PROCESS FROM NODE 4.80 TO NODE 4.80 IS CODE = 8 ------------------------------------------------------ »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 25 YEAR RAINFALL INTENSITY (INCH/H R) = 2.276 Page 12 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 2.81 SUBAREA RUNOFF(CFS) = 5.57 EFFECTIVE AREA(ACRES) = 19.67 AREA -AVERAGED Fm(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 19.67 PEAK FLOW RATE(CFS) = 38.96 TC(MIN) = 16.95 FLOW PROCESS FROM NODE 4.80 TO NODE 4.90 IS CODE = 3 ----------------------- ---------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 36.0 INCH PIPE IS 25.4 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 7.3 UPSTREAM NODE ELEVATION(FEET) = 1072.25 DOWNSTREAM NODE ELEVATION(FEET) = 1071.25 FLOW LENGTH(FEET) = 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 36.00 NUMBER OF PIPES 1 PIPE-FLOW(CFS) = 38.96 TRAVEL TIME(MIN.) _ .46 TC(MIN.) = 17.40 k it it is it ic�ir it:.•ir is is ic�ir it sY is*wit it is icit is is it it ic�ir ir�ir it is ic�ir ir�irK it ie it it sY �•:c ie is k it is it&ic is it it Xie&ir k ie it it it ir�ir is FLOW PROCESS FROM NODE 4.90 TO NODE 4.90 IS CODE = 8 ------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.240 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 2.81 SUBAREA RUNOFF(CFS) 5.48 EFFECTIVE AREA(ACRES) = 22.48 AREA -AVERAGED FM(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) 22.48 PEAK FLOW RATE(CFS) = 43.80 TC(MIN) = 17.40 it i.• it it is it �'l: it it is it is is is it it it it it it it it it it is it it it'k is is it it it ir'k it it is it it it it it it it it it is ie it it i:'k it is it it it it it it ie ir'k is it is is it it it is it is FLOW PROCESS FROM NODE 4.90 TO NODE 4.10 IS CODE = 3 ------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< >>>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< ---------- ______________________ DEPTH OF FLOW IN 36.0 INCH PIPE IS 28.1 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 7.4 UPSTREAM NODE ELEVATION(FEET) = 1071.25 DOWNSTREAM NODE ELEVATION(FEET) = 1070.50 FLOW LENGTH(FEET) = 150.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 36.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 43.80 TRAVEL TIME(MIN.) _ .34 TC(MIN.) = 17.74 is �•ir�ir„ic is R•� �•:;i: Yr�i.•&�•ir ir':9r ic�ir is is is �•ir is � sic it :: ie ie�ir it is �•ic ire is it ie�ir s; ie it 4c is it tic is is :c is is it is is sY it ic��ic is is is FLOW PROCESS FROM NODE 4.10 TO NODE 4.10 IS CODE = 8 ----------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< Page 13 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.214 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 2.02 SUBAREA RUNOFF(CFS) = 3.89 EFFECTIVE AREA(ACRES) = 24.50 AREA -AVERAGED FM(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 24.50 PEAK FLOW RATE(CFS) = 47.17 TC(MIN) = 17.74 FLOW PROCESS FROM NODE 4.10 TO NODE 4.00 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 36.0 INCH PIPE IS 28.7 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 7.8 UPSTREAM NODE ELEVATION(FEET) = 1070.50 DOWNSTREAM NODE ELEVATION(FEET) = 1069.17 FLOW LENGTH(FEET) = 240.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 36.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 47.17 TRAVEL TIME(MIN.) _ .51 TC(MIN.) = 18.25 ..:: ?r ?c *?r ?:.?e ?c ?r?r?c ?c ?r?t?e ?c?r?r ir?r � R• ?r?c � ?e ?r i; ?: � � ?: ?t & ?c ?r ?r?r ?r ?c � �• ?e ie?c ?r?: ?: ?r ?r ?r?e?r � ?r?r it ?.• * �• ?r �• � ?r?r ?k ?t ?c ?r ?c � * k it it FLOW PROCESS FROM NODE 4.00 TO NODE 4.00 IS CODE = 1 >>>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< >AND COMPUTE VARIOUS CONFLUENCED STREAM VALUES««< TOTAL NUMBER OF STREAMS = 2 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 2 ARE: TIME OF CONCENTRATION(MIN.) = 18.25 RAINFALL INTENSITY(INCH/HR) = 2.18 AREA -AVERAGED Fm(INCH/HR) = .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 EFFECTIVE STREAM AREA(ACRES) = 24.50 TOTAL STREAM AREA(ACRES) = 24.50 PEAK FLOW RATE(CFS) AT CONFLUENCE = 47.17 RAINFALL INTENSITY AND TIME OF CONCENTRATION RATIO CONFLUENCE FORMULA USED FOR 2 STREAMS. ** PEAK FLOW RATE TABLE ** Q Tc Intens. FP Ap FM Ae (CFS) (MIN.) (INCH/HR� (INCH/HR) (INCH/HR) (ACRES) 1 170.87 16.44 2.318 .51 .18 .09 81.94 2 172.61 17.35 2.244 .51 .18 .09 85.78 3 161.77 23.40 1.875 .48 .21 .10 98.48 4 157.17 24.96 1.804 .47 .21 .10 100.01 5 172.77 18.25 2.177 .50 .19 .09 88.71 COMPUTED CONFLUENCE ESTIMATES ARE AS FOLLOWS: PEAK FLOW RATE(CFS) = 172.77 TC(MIN.) = 18.253 EFFECTIVE AREA(ACRES) = 88.71 AREA -AVERAGED Fm(INCH/HR) _ .09 AREA -AVERAGED Fp(INCH/HR) _ .50 AREA -AVERAGED Ap = .19 TOTAL AREA(ACRES) = 100.01 ?c*?: �•�'?:?e*?r ?:**?r ?r ?r ?r ?r?c*?r?r*�*?r ?r ?tie?:?t?r?r�'x?t?:?r?ri.'?r?r?rk?r:Y**?r?r*?r*?cic?r?c?r ?c ?c *?: ?r*?t sF ?r k?r**?:�*?r?:?e Page 14 FLOW PROCESS FROM NODE 4.00 TO NODE 5.00 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 54.0 INCH PIPE IS 43.4 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 12.6 UPSTREAM NODE ELEVATION(FEET) = 1069.17 DOWNSTREAM NODE ELEVATION(FEET) = 1065.00 FLOW LENGTH(FEET) = 495.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 54.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 172.77 TRAVEL TIME(MIN.) = .65 TC(MIN.) = 18.91 &ir it ie it is it it is it it it is kie is it it it is �k is ie is ie ie it is ie it is it it it it ie it it ie it ic�ir it is it it is is is it it is it it ie is it it it is it is sY it is ie it is it&ic it it is is FLOW PROCESS FROM NODE 5.00 TO NODE 5.00 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 5 YEAR RAINFALL INTENSITY(INCH/HR) = 2.131 ----------- SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 4.18 SUBAREA RUNOFF(CFS) = 7.74 EFFECTIVE AREA(ACRES) = 92.89 AREA -AVERAGED Fm(INCH/HR) _ .09 AREA -AVERAGED Fp(INCH/HR) = .51 AREA -AVERAGED Ap = .18 TOTAL AREA(ACRES) = 104.19 PEAK FLOW RATE(CFS) = 172.77 TC(MIN) = 18.91 i; i;��ir it i; i:x it is&ic ir�lr ir�� �.ie ic�sY it it sc it i:�ir�it tS'ic:: it sY it is it icy*&tic i; it ic�ir it is is it ie is it i; it jr�ir'k it �k it it i; it it °k R•ir is FLOW PROCESS FROM NODE 5.00 TO NODE 6.00 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW) ««< DEPTH OF FLOW IN 51.0 INCH PIPE IS 40.6 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 14.3 UPSTREAM NODE ELEVATION(FEET) = 1065.00 DOWNSTREAM NODE ELEVATION(FEET) = 1064.07 FLOW LENGTH(FEET) = 80.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 51.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 172.77 TRAVEL TIME(MIN.) = .09 TC(MIN.) = 19.00 it it � it is �• is it ie is �'« is it �• ie is it i; i< is ie is it it it it it ie is it it ie it it it it � it it %� it it it � it it is ie is it i• it it X is it �• it it it it ie is it i; i< i; i< it it it is � i; i< i< FLOW PROCESS FROM NODE 6.00 TO NODE 6.00 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 5 YEAR RAINFALL INTENSITY (INCH/HR) = 2.125 SOIL CLASSIFICATION IS "B COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA, FRACTION, Ap = .10 SUBAREA AREA(ACRES) = .58 SUBAREA RUNOFF(CFS) = 1.07 EFFECTIVE AREA(ACRES) = 93.47 AREA -AVERAGED Fm(INCH/HR) _ .09 AREA -AVERAGED Fp(INCH/HR) = .51 AREA -AVERAGED Ap = .18 TOTAL AREA(ACRES) = 104.77 PEAK FLOW RATE(CFS) = 172.77 TC(MIN) = 19.00 Page 15 is it is *ir it is it is ieYr it it it ie. is sY it is is is it it it it is it it it is �Y it it it it it is is it it it it it it is is it is ie it is is is * is is it it it is it it ie is ir'k is it it is ie is it it it it --FLOW PROCESS FROM NODE 6.00 TO NODE 6.00 IS CODE = 1 --------------------------------------------------- »»>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< TOTAL NUMBER OF STREAMS = 2 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 1 ARE: TIME OF CONCENTRATION(MIN.) = 19.00 RAINFALL INTENSITY(INCH/HR) = 2.12 AREA -AVERAGED Fm(INCH/HR) = .09 AREA -AVERAGED Fp(INCH/HR) = .51 AREA -AVERAGED Ap = .18 EFFECTIVE STREAM AREA(ACRES) = 93.47 TOTAL STREAM AREA(ACRES) = 104.77 PEAK FLOW RATE(CFS) AT CONFLUENCE = 172.77 iekiciriririricie*irici.iriririririciririr**icieieirieiciricicieicicie*ieicitiririricicic*ir�eiriciricsYieiririr*icirieiciriririeicirieiririeicir FLOW PROCESS FROM NODE 6.10 TO NODE 6.20 IS CODE = 2.1 - -------------------------- »»>RATIONAL METHOD INITIAL SUBAREA ANALYSIS««< DEVELOPMENT IS COMMERCIAL TC = K*[(LENGTH** 3.00)/(ELEVATION CHANGE)]** .20 INITIAL SUBAREA FLOW-LENGTH(FEET) = 445.00 UPSTREAM ELEVATION(FEET) = 1080.00 DOWNSTREAM ELEVATION(FEET) = 1079.00 ELEVATION DIFFERENCE(FEET) = 1.00 TC(MIN.) = .304*[( 445.00** 3.00)/( 1.00)]** .20 = 11.800 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.828 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA RUNOFF(CFS) = 5.76 TOTAL AREA(ACRES) = 2.30 PEAK FLOW RATE(CFS) 5.70 *.:rir**it'&it***ic*ir�'e it it**ir it is it it it*sY is is ic-k is ic-k it it it it is ie it*icy'*�•***ic*�•ir it it it is is it*+Y fr it*ic it sY is it ie it is its*.* FLOW PROCESS FROM NODE 6.20 TO NODE 6.30 IS CODE = 3 ----------------------------------- >COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 18.0 INCH PIPE IS 12.0 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 4.5 UPSTREAM NODE ELEVATION(FEET) = 1073.00 DOWNSTREAM NODE ELEVATION(FEET) = 1072.00 FLOW LENGTH(FEET) = 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 18.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 5.70 TRAVEL TIME(MIN.) _ .73 TC(MIN.) = 12.53 it ic**i: �•;Y it ir�•it ic•kir°k is it it**ir*ie it i:*it it ie it it is is*ir is it it it it*Yr*ic�•ir is it it it*ic**sY**ie*ir*ir*ir {r it is**ir ie 'c ie it it is FLOW PROCESS FROM NODE 6.30 TO NODE 6.30 IS CODE = 8 ----------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.727 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 2.30 SUBAREA RUNOFF(CFS) = 5.49 Page 16 EFFECTIVE AREA(ACRES) = 4.60 AREA -AVERAGED Fm(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) _ .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 4.60 PEAK FLOW RATE(CFS) = 10.98 TC(MIN) = 12.53 ie :: � it is it is � it ie iric is it it ie :c it i< i<ir is it � it ie ie is is it it k ilic ie it it ie �Y it is ie it it it it itit is ie it is is ie it i.• it ie is is it is is it ie it is it ie is it it is it is it FLOW PROCESS FROM NODE 6.30 TO NODE 6.40 IS CODE = 3 >>>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 24.0 INCH PIPE IS 14.9 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 5.4 UPSTREAM NODE ELEVATION(FEET) = 1072.00 DOWNSTREAM NODE ELEVATION(FEET) = 1071.00 FLOW LENGTH(FEET) = 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 24.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 10.98 TRAVEL TIME(MIN.) _ .62 TC(MIN.) = 13.15 is is it is �cit it �k is is is it ie it k is is is is ie is is it sY it it'h is it is it it is is is is ie is it it it it it it it is is it ie � is � it is is $c it it it i; ie is ie is is is it it it it it it it it is is FLOW PROCESS FROM NODE 6.40 TO NODE 6.40 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.649 ------------ SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 2.30 SUBAREA RUNOFF(CFS) = 5.33 EFFECTIVE AREA(ACRES) = 6.90 AREA -AVERAGED FM(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) _ .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 6.90 PEAK FLOW RATE(CFS) = 15.99 TC(MIN) = 13.15 i:i;i: it sY it is is i:i; it is it it it i:�i<ic is it is it i; is is ie it is is it it it �4 it is it it it is i�ic is it is i; ft is is is ie is s4 is is it is is �k i; it is icy&ic is it is it it it it it it i; FLOW PROCESS FROM NODE 6.40 TO NODE 6.50 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 27.0 INCH PIPE IS 17.4 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 5.9 UPSTREAM NODE ELEVATION(FEET) = 1071.00 DOWNSTREAM NODE ELEVATION(FEET) = 1070.00 FLOW LENGTH(FEET) = 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 27.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 15.99 TRAVEL TIME(MIN.) _ .57 TC(MIN.) = 13.72 is i; � is i< it ie it is is is it is is is irit is is is is it is 4: it it it i:. it i; it � is is ie is it it it it is it is is � is it is it •k ie � i; it is is is �• �• k ie is is it � � i< � � it is �kir i; � is FLOW PROCESS FROM NODE 6.50 TO NODE 6.50 IS CODE 8 --------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.583 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 Page 17 SUBAREA AREA(ACRES) = 2.30 SUBAREA RUNOFF(CFS) = 5.19 EFFECTIVE AREA(ACRES) = 9.20 AREA -AVERAGED Fm(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) _ .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 9.20 PEAK FLOW RATE(CFS) = 20.77 TC(MIN) = 13.72 9; Yc Yt Yc Yr Yc it Yc Yr Yr Y<Yr Yr Yt Yr Yr Y<Yr Yc Yr Yr Yc Yr Yc Yr Yr Yr Yc Ye Yr Yc Yc it Yr Yc Ye Yc Yt it Yc Yr Yc Yr Yr Yc Yr Yr Ye Yt Yr Yr Ye ie Yc 9c is Yr Yt Yr Ye Yc Ye Yr Yc Ye Yt Yr Yc YfYr Yr Y: Ye it Yr Yc FLOW PROCESS FROM NODE 6.50 TO NODE 6.60 IS CODE = 3 -- --------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 27.0 INCH PIPE IS 21.5 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 6.1 UPSTREAM NODE ELEVATION(FEET) = 1070.00 DOWNSTREAM NODE ELEVATION(FEET) = 1069.00 FLOW LENGTH(FEET) = 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 27.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 20.77 TRAVEL TIME(MIN.) = .54 TC(MIN.) = 14.27 Yc �r Yr Yc Ye Yc Y: Yr � is Yc Y: Yr kYr'.c kYc Yr Yr Yr Yr Yc � Yc Yr Yr Yr Y; Yc Yr'.r Yr Y; Yr ie Yc is Yr Yr �Ye Ye Yr Y: Ye Ye Y: Ye Yr Y: Yc Yr Yc Y: Ye Ye Yr Y;Yc Yr Yc YrYr :r & Yr Yr Yc Yr Yc Ye Yt Yr Yr Yc FLOW PROCESS FROM NODE 6.60 TO NODE 6.60 Is CODE = 8 --------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.524 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 M., SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 2.30 SUBAREA RUNOFF(CFS) = 5.07 EFFECTIVE AREA(ACRES) = 11.50 AREA -AVERAGED FM(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 11.50 PEAK FLOW RATE(CFS) = 25.34 TC(MIN) = 14.27 Yr�Yr Yr Yr YrYc.;YYe Ye Yc �Yr Yc Yc Yr Ye Yc Yt Y<Yr Ye Yr Y;�Yr-&k Yt Yc Y�Ye Yc is Yr it Yc Yr Y; Yr Yc&dr Yt Ye Yc Yr Yr Yr Yt:r Ye Yr Y; Yr Yc Yc#Yc Yc Yc Ye Yc Yr Ye Yc Yr Yc Yr Yr is Yr Yr Yr Y:Ye FLOW PROCESS FROM NODE 6.60 TO NODE 6.70 IS CODE = 3 -- - ------------------------------- >>>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< >>>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< --------------- ---------------------------------- - -----------=---------- DEPTH OF FLOW IN 30.0 INCH PIPE IS 22.2 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 6.5 UPSTREAM NODE ELEVATION(FEET) = 1069.00 DOWNSTREAM NODE ELEVATION(FEET) = 1068.00 FLOW LENGTH(FEET) = 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 30.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 25.34 TRAVEL TIME(MIN.) _ .51 TC(MIN.) = 14.78 Y: Y; ;: YrY; �Yc Y: YrYcYr Yr :: Yr YcY: Y; Y: YrYtYc � Ye � Yr Yc f. Yc � Y; Yc Yr Y: Yt &Yc k it :Y Yc � �• Yt.Yt i; � YcYr :rY; & � �• Yr Yr Yr i; Yc Y: Yr Yt Yc Yc Yr Yr i; Y< it Y; Y: Yr:Yr Yr Y: Yr Yr FLOW PROCESS FROM NODE 6.70 TO NODE 6.70 IS CODE = 8 -------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.471 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 Page 18 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA EFFECTIVEAREA(ACRES)= 2.30 SUBAREA 133.80 AREA -AVERAGED ECTIVE.07 AREA -AVERAGED TOTAL AREA(ACRES)INCH/H13.80 75 PEAK FLOW ARATE(CFS) = 1029.76 TC(MIN) = 14.78 it it is is is it sY icie is is it ie iri; it is it ie it it is it it ie ie is ie it it is ie is ie is it i� it ie it is is is ie is ie ie ie ie is it it is is Y ie ie is it ie is ie is ie is is ie is it it it it ie ie Yr it FLOWPROCESSFROM NODE 6.70 TO NODE 6.80 IS CODE = 3 --- - ------------------------------- -------------------------- >COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 33.0 INCH PIPE IS 22.7 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 6.8 UPSTREAM NODE ELEV,ATION(FEET) = 1068.00 DOWNSTREAM NODE ELEVATION(FEET) = 1067.00 FLOW LENGTH(FEET) = 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 33.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 29.76 TRAVEL TIME(MIN.) _ .49 TC(MIN.) = 15.26 is � ie � ie i; it is it it it it is it ie it it is is ie Yc is it is it it it is is it i; it is it it is it is is it ie it ii is it � it is it it ie it i; it it it is :: it it it is ic'.r :F is it is it is it ie it it ie it FLOW PROCESS FROM NODE 6.80 TO NODE 6.80 IS CODE = 8 -- - ----------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 25 YEAR RAINFALL INTENSITY (INCH/HR) = 2.423 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 2.30 SUBAREA RUNOFF(CFS) = 4.86 EFFECTIVE AREA(ACRES) = 16.10 AREA -AVERAGED Fm(INCH/HR) _ .07 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 16.10 PEAK FLOW RATE(CFS) = 34.03 TC(MIN) = 15.26 i; i; � & is it � it is i; it is is it & it is it it is i� �`' i; & it is k'.r � is is is it it is irir'.c it is it ie it -k is it it it it it is it it is is i; it i; is i; it it is it is it it it it it is it is is is FLOW PROCESS FROM NODE 6.80 TO NODE 6.90 IS CODE 3 -- - -------------------------------- --------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 33.0 INCH PIPE IS 25.3 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 7.0 UPSTREAM NODE ELEVATION(FEET) = 1067.00 DOWNSTREAM NODE ELEVATION(FEET) = 1066.00 FLOW LENGTH(FEET) = 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 33.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 34.03 TRAVEL TIME(MIN.) _ .48 TC(MIN.) = 15.74 t is ie ,k k � ie it is it is is k it k is is �' � it is it is i; is i< is i; i< i< i<icir is is is is is it it it sY it Yr is i; it is it is � � is ie is it it is it is it Y: is is is is � is is :Y it t is it is ie FLOW PROCESS FROM NODE 6.90 TO NODE 6.90 IS CODE = 8 --- -------------------------------------- ---------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 25 YEAR RAINFALL INTENSITY (INCH/HR) = 2.379 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 Page 19 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 2.30 SUBAREA RUNOFF(CFS) = 4.77 EFFECTIVE AREA(ACRES) = 18.40 AREA -AVERAGED FM(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 18.40 PEAK FLOW RATE(CFS) = 38.15 TC(MIN) = 15.74 h hh�thhit hh h'; it iehith hirhhhuir&hh hhhhhhhhhhic ichhhhhichhhhith ithhhhithithhirh ithhhhhit is is it is irhh FLOW PROCESS FROM NODE 6.90 TO NODE 6.10 IS CODE = 3 -- ---------------------------- -------------------------------- >>>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 36.0 INCH PIPE IS 25.0 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 7.3 UPSTREAM NODE ELEVATION(FEET) = 1066.00 DOWNSTREAM NODE ELEVATION(FEET) = 1065.25 FLOW LENGTH(FEET) = 150.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 36.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 38.15 TRAVEL TIME(MIN.) _ .34 TC(MIN.) = 16.09 hhh°k hhhhie is it hirh hhhiz �4 is ich irhhhirh �rh hhhhhhhhhhhic ie irhhh his ieh ithhichhhithhhhir irh hithhhhhhh h. FLOW PROCESS FROM NODE 6.10 TO NODE 6.10 IS CODE = 8 -- --------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.348 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 1.51 SUBAREA RUNOFF(CFS) = 3.09 EFFECTIVE AREA(ACRES) = 19.91 AREA -AVERAGED FM(INCH/HR) = .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 19.91 PEAK FLOW RATE(CFS) = 40.73 TC(MIN) = 16.09 h it it hi: h°kh hhhich hhhh:t irhhhirhhhhhh h�•ie irh it'.t hirh irkhhhichhhhhhic hie ichhh:c it h is hh hh'.r hi:hhhirhhh FLOW PROCESS FROM NODE 6.10 TO NODE 6.11 IS CODE = 3 - --------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< --»»>USING- COMPUTER -ESTIMATED -PIPESIZE-(NON-PRESSURE FLOW)««< ------------------------------------------------------------------------- DEPTH OF FLOW IN 39.0 INCH PIPE IS 27.0 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 6.6 UPSTREAM NODE ELEVATION(FEET) = 1065.25 DOWNSTREAM NODE ELEVATION(FEET) = 1064.50 FLOW LENGTH(FEET) = 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 39.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 40.73 TRAVEL TIME(MIN.) = 50 TC(MIN.) = 16.59 hhhhhi: 'k z4hhh hhhhhhhhhhhhhhhhhhhhhithhhirhhhhhh irh pith hic it hichhhir it ithhhhhhhhhithhhhirhh FLOW PROCESS FROM NODE 6.11 TO NODE 6.11 IS CODE = 8 -- ------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.305 SOIL CLASSIFICATION IS "B" Page 20 COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 2.17 SUBAREA RUNOFF(CFS) = 4.36 EFFECTIVE AREA(ACRES) = 22.08 AREA -AVERAGED FM(INCH/HR) _ .08 AREA-TOTALAVERAGED AREA(ACRES) NCH/H2� 08 EAK FLOW .75 PREA-AVERARATE(CFS) = 1044.32 TC(MIN) = 16.59 it it is Yr ie ie it ie is it � is it is it is * ie ie it it it is is is ie is it is it & it is it it is ie it it it is it it it it it is it sY it is it it it ie iF it it it is is it ie ie is is is it it it ie ie it it ie it FLOW PROCESS FROM NODE 6.11 TO NODE 6.00 IS CODE = 3 -- - --------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< >>>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 36.0 INCH PIPE IS 26.7 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 7.9 UPSTREAM NODE ELEVATION(FEET) = 1064.50 DOWNSTREAM NODE ELEVATION(FEET) = 1064.07 FLOW LENGTH(FEET) = 75.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 36.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 44.32 TRAVEL TIME(MIN.) _ .16 TC(MIN.) = 16.75 is it it ie is it is**ir it**ir icir ie it it it it it it sY it it is it it it it it it is is it it is it it it ie it ie it*ir is i:ir fr ilir it it ie it it is it ic�ir is ie ir°k&**tY is it ie it is FLOW PROCESS FROM NODE 6.00 TO NODE 6.00 IS CODE --- = 1 ----------------------------------- ------------------------- »»>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< »»>AND COMPUTE VARIOUS CONFLUENCED STREAM VALUES««< TOTAL NUMBER OF STREAMS = 2 -----_ CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 2 ARE: TIME OF CONCENTRATION(MIN.) = 16.75 RAINFALL INTENSITY(INCH/HR) = 2.29 AREA -AVERAGED FM(INCH/HR) = .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 EFFECTIVE STREAM AREA(ACRES) = 22.08 TOTAL STREAM AREA(ACRES) = 22.08 PEAK FLOW RATE(CFS) AT CONFLUENCE = 44.32 RAINFALL INTENSITY AND TIME OF CONCENTRATION RATIO CONFLUENCE FORMULA USED FOR 2 STREAMS. PEAK FLOW RATE TABLE ** Q Tc (CFS) (MIN.) Intensit (INCH/HR� Fp (INCH/HR) Ap FM (INCH/HR) Ae (ACRES) 1 214.49 17.19 2 214.85 18.10 2.257 2.188 .55 .54 .16 .09 108.78 3 213.74 19.00 2.125 .54 .16 .17 .09 112.62 115.55 4 197.24 24.15 5 191.75 25.72 1.840 1.772 .51 .18 .09 .09 125.32 6 213.54 16.75 2.292 .50 .55 .19 .16 .09 .09 126.85 106.56 COMPUTED CONFLUENCE ESTIMATES ARE AS FOLLOWS: PEAK FLOW RATE(CFS) = 214.85 TC(MIN.) = 18.097 EFFECTIVE AREA(ACRES) = 112.62 AREA -AVERAGED FM(INCH/HR) _ AREA -AVERAGED Fp(INCH/HR) = .54 AREA -AVERAGED Ap = .16 .09 TOTAL AREA(ACRES) = 126.85 is is is it is •!r *:: *:F***.r**ir is it �•ie it is is i; {c is is*st *�k is is it*ir it*ir*i: sY is is it**ir �-ir is is it *iric it ic'r it it it it �'.: it it is it it is it it*4r FLOW PROCESS FROM NODE 6.00 TO NODE 7.00 IS CODE = 3 Page 21 ------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< >»»USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 57.0 INCH PIPE IS 44.8 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 14.4 UPSTREAM NODE ELEVATION(FEET) = 1064.07 DOWNSTREAM NODE ELEVATION(FEET) = 1058.97 FLOW LENGTH(FEET) = 500.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 57.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 214.85 TRAVEL TIME(MIN.) = .58 TC(MIN.) = 18.68 is i; � it ie is it is it YrYr sYYt it is it it is it it it it it is it ie is is ic. it it it it it ie is is is it ie it it is ie is it is it ie it is it it it is is it is it is it is it is is Yc ie is it it ie it ie it i; � FLOW PROCESS FROM NODE 7.00 TO NODE 7.00 IS CODE = 8 -- - ------------------------- -------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.147 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 2.23 SUBAREA RUNOFF(CFS) = 4.16 EFFECTIVE AREA(ACRES) = 114.85 AREA -AVERAGED FM(INCH/HR) _ .09 AREA -AVERAGED Fp(INCH/HR) = .54 AREA -AVERAGED Ap = .16 TOTAL AREA(ACRES) 129.08 PEAK FLOW RATE(CFS) = 214.85 TC(MIN) = 18.68 :: i; irir it � ic. it is is �• � it it it it it it � ir.-k it it is it i; it is is is � it i; it it iric it is it is is ie it it i; i<ir is it it it is it is is is it is it is ie it it it ie is is it is i; it ie � it FLOW PROCESS FROM NODE 7.00 TO NODE 8.00 IS CODE = 3 -- - ----------------------- >>>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< --»»>USING-COMPUTER- ESTIMATED-PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 57.0 INCH PIPE IS 45.6 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 14.1 UPSTREAM NODE ELEVATION(FEET) = 1058.97 DOWNSTREAM NODE ELEVATION(FEET) = 1055.52 FLOW LENGTH(FEET) = 350.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 57.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 214.85 TRAVEL TIME(MIN.) = .41 TC(MIN.) = 19.09 R• is it kit i; :Y �• is i!',c � X i; '.: is k �• ie i.• sY is i; & � i< i; & is i; .c ie i; i; it is it sY it i; i; is it is it is is it ie ie it is it is t i; # st is is is i; is it it i::r it it is it is it it is is FLOW PROCESS FROM NODE 8.00 TO NODE 8.00 IS CODE = 8 -- --------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.119 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 2.78 SUBAREA RUNOFF(CFS) = 5.11 EFFECTIVE AREA(ACRES) = 117.63 AREA -AVERAGED FM(INCH/HR) _ .09 AREA -AVERAGED Fp(INCH/HR) = .55 AREA -AVERAGED Ap = .16 TOTAL AREA(ACRES) = 131.86 PEAK FLOW RATE(CFS) = 214.99 TC(MIN) = 19.09 ki: it s4 is �k is ki: it :: �zY is is is hi:x kiri: fir ie icrt it it is ie it it it is is is it it i:�-ir it it s4 is �t is it �r it is it is is is it is it is it it is it it ie it it it iris is is ie i; is Page 22 FLOW PROCESS FROM NODE 8.00 TO NODE 9.00 IS CODE = 3 -- >>>>>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< --------- »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 57.0 INCH PIPE IS 46.3 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 13.9 UPSTREAM NODE ELEVATION(FEET) = 1055.52 DOWNSTREAM NODE ELEVATION(FEET) = 1052.07 FLOW LENGTH(FEET) = 360.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 57.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 214.99 TRAVEL TIME(MIN.) = .43 TC(MIN.) = 19.52 f: it it sY 'r Yr��4r 4c f:i::r'.::e ir�ir �r ir'.c ie icu it it it it ie i::r:r fir �e 4r Ye fr it it Yr 4r sY it 4r 4r ir�it �"�&�•sY �k ie 4r it it ie it :e 4c :r it :c 4e it 4r kir kir it 'r it FLOW PROCESS FROM NODE 9.00 TO NODE 9.00 IS CODE = 8 ----------------------------------------------------------- >>>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.091 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 2.75 SUBAREA RUNOFF(CFS) = 4.99 EFFECTIVE AREA(ACRES) = 120.38 AREA -AVERAGED Fm(INCH/HR) _ .09 AREA -AVERAGED Fp(INCH/HR) = .55 AREA -AVERAGED Ap = .16 TOTAL AREA(ACRES) = 134.61 PEAK FLOW RATE(CFS) = 216.99 TC(MIN) = 19.52 Y sY sY sY 4c it 4r-k �4r 'k �r�f: 4r it it 4r'ir it Y it eY it it it i:�ic�ir it ir&ic it 4t it is k 4r is is it 4r �k it ie 4r 4r°k is 4r 4r Y it ir�ic it it is ir��ic 4r is fir it is 4r 4rie 4r FLOW PROCESS FROM NODE 9.00 TO NODE 9.00 IS CODE = 8 -- ----------------------- ---------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.091 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 1.73 SUBAREA RUNOFF(CFS) = 3.14 EFFECTIVE AREA(ACRES) = 122.11 AREA -AVERAGED Fm(INCH/HR) _ .09 AREA -AVERAGED Fp(INCH/HR) = .55 AREA -AVERAGED Ap = .16 TOTAL AREA(ACRES) = 136.34 PEAK FLOW RATE(CFS) = 220.13 TC(MIN) = 19.52 xi::t::irt'tirir� �•ir;:iririr.'r:rir�&iririr4r'r�tci:�ic#�:rksr&.;;�yrirsY�c� �����4tsY:c.:rirfc;c4ri:i:4t�*°k:Y��•�;�;efc��4cYrir&:: FLOW PROCESS FROM NODE 9.00 TO NODE 10.00 IS CODE = 3 -- - ----------------------------------------------------------- >>>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 48.0 INCH PIPE IS 35.9 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 21.9 UPSTREAM NODE ELEVATION(FEET) = 1052.07 DOWNSTREAM NODE ELEVATION(FEET) = 1049.07 FLOW LENGTH(FEET) = 100.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 48.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 220.13 TRAVEL TIME(MIN.) _ .08 TC(MIN.) = 19.60 END OF STUDY SUMMARY: Page 23 TOTAL AREA(ACRES) = 136.34 TC(MIN.) = 19.60 EFFECTIVE AREA(ACRES) AREA -AVERAGED Fp(INCH/HR) = 122.11 - AREA -AVERAGED AREA FM(INCH/HR)= .09 PEAK FLOW RATE(CFS) .55 = 220.13 -AVERAGED Ap = .16 PEAK FLOW RATE TABLE ** Q Tc (CFS) (MIN.) Intensit (INCH/HR� Fp {INCH/HR) AP FM (INCH/HR) Ae (ACRES) 1 218.85 18.25 2 219.71 18.69 2.177 2.146 .56 .16 .09 116.05 3 220.13 19.60 2.086 .56 .55 .16 .16 .09 118.27 122.11 4 219.05 20.50 5 204.52 25.66 2.030 1.774 .55 .16 .09 .09 125.04 6 199.00 27.25 1.712 .52 .51 .18 .18 .09 .09 134.81 136.34 END OF RATIONAL METHOD ANALYSIS -- Page 24 ir;c',riris9r:e:efsiriririrlt#Yfr*kieir�'rkirhx:es'rir4e9rieirieisi•ic4ru4r�4:rirY4rie4r'.:4tiririr4riric'.eirirsf4:4r�ririt�'e4e4rhirirfsiefc4edefr RATIONAL METHOD HYDROLOGY COMPUTER PROGRAM PACKAGE (Reference: 1986 SAN BERNARDINO CO. HYDROLOGY CRITERION) (C) Copyright 1983-93 Advanced Engineering Software (aes) Vera 1.9B Release Date: 7/18/93 License ID 1202 Analysis prepared by: HUITT-ZOLLARS, INC. 15101 RED HILL AVENUE TUSTIN, CALIFORNIA 92780-6500 PHONE (714) 259-7900 * FAX (714) 259-0210 ---------------------------------------- ------------------------------------ FILE NAME: 202QO25G.DAT TIME/DATE OF STUDY: 13: 7 6/14/2004 USER SPECIFIED HYDROLOGY AND HYDRAULIC MODEL INFORMATION: --*TIME-OF-CONCENTRATION MODEL* USER SPECIFIED STORM EVENT(YEAR) = 25.00 SPECIFIED MINIMUM PIPE SIZE(INCH) = 18.00 SPECIFIED PERCENT OF GRADIENTS (DECIMAL) TO USE FOR FRICTION SLOPE = .95 *USER -DEFINED LOGARITHMIC INTERPOLATION USED FOR RAINFALL* 10-YEAR STORM 60-MINUTE INTENSITY(INCH/HOUR) _ .920 100-YEAR STORM 60-MINUTE INTENSITY(INCH/HOUR) = 1.340 COMPUTED RAINFALL INTENSITY DATA: STORM EVENT = 25.00 1-HOUR INTENSITY(INCH/HOUR) = 1.0659 SLOPE OF INTENSITY DURATION CURVE = .6000 *:tit*it*i:it#*ir*ir it it**it �k*ir ir:Y is 4t*:t 4r i:4r*it sY'.c:e it ic'.e k it itit irici:ir': oY it it it it it ie �'t:c it it �Y:k il::i: �c it 9c**:t is 4t sY :r*�•:e --FLOW PROCESS FROM NODE 10.00 TO NODE 10.00 IS CODE = 15 ----------------------------------------------------------- »»>DEFINE MEMORY BANK # 1 ««< MEMORY BANK # 1 DEFINED AS FOLLOWS: 1 Q85F39 Tc(1ON16 Fp(INC644R) 25 FM(IN160HR) Ae(AC07S) 2 95.50 15.14 .639 .25 .162 44.98 3 94.82 15.51 .638 .26 .164 45.41 TOTAL AREA = 45.41 8t :t�': �: fir*?c :•r :t*�•ir i.•its't icy':*it it it it*it ir'.t 4r it it *ir •&4r is**ir :tit*it is*ir**;r:tir*Yt4:'t is ir'.e*ic 9c ie :t �r *°k'.r sY 4r sY dr :ram-** -- ------------------------------------ FLOW PROCESS FROM NODE 10.00 TO NODE 10.00 IS CODE = 14 ------------------------ _ >>>MEMORY BANK # 1 COPIED ONTO MAIN -STREAM MEMORY««< MAIN -STREAM MEMORY DEFINED AS FOLLOWS: Q(CFS) TC(MIN.) Fp(INCH/HR) AP FM(INCH/HR) Ae(ACRES) 1 85.39 10.16 .644 .25 .160 31.07 2 95.50 15.14 .639 .25 .162 44.98 3 94.82 15.51 .638 .26 .164 45.41 TOTAL AREA = 45.41 is is it ie is is it is*ic it �•iti:x is is is ie is �F is is is it it it*it*ic*ir it it it i�*sY ie it it*ie is is it ie it is is it it**it is ie*ic it it it it it it it it is is it it is it it it FLOW PROCESS FROM NODE 10.00 TO NODE 10.00 IS CODE = 12 Page 1 ----------------------------------------- »»>CLEAR MEMORY BANK # 1 ««< Yeir*YcYrieYeirir*YrYtY�Yeyt-YriciricitirisieYrYcicYcYc*YeYricYcYcYrYric**Ycic*it*irYrYrYrYoiticYrYcYrieicYrYtitYricit*ir*Ye*itiririeicYrYcYrYc FLOW PROCESS FROM NODE 10.00 TO NODE 11.00 IS CODE = 3 ---------------------------------------------------------- >>>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< --»»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 48.0 INCH PIPE IS 36.2 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 9.4 UPSTREAM NODE ELEVATION(FEET) = 1075.90 DOWNSTREAM NODE ELEVATION(FEET) = 1073.50 FLOW LENGTH(FEET) = 435.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 48.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 95.50 TRAVEL TIME(MIN.) _ .77 TC(MIN.) = 15.91 Y: YrYtY:YcYtYc *itY: �Y:YcY: Yr*i: irY:itit*ic*YricYtit*****YcitYc*YcitYtYr*icitit**Yt*Y:Y:Yc*Yririti:YcicYtYcY: icYtYtirYt°kYc*YtYtYt*it it FLOW PROCESS FROM NODE 11.00 TO NODE 11.00 IS CODE = 1 ------------------------------- --------------------------- »»>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< TOTAL NUMBER OF STREAMS = 2 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 1 ARE: TIME OF CONCENTRATION(MIN.) = 15.91 RAINFALL INTENSITY(INCH/HR) = 2.36 AREA -AVERAGED Fm(INCH/HR) = .16 AREA -AVERAGED Fp(INCH/HR) = .64 AREA -AVERAGED Ap = .25 EFFECTIVE STREAM AREA(ACRES) = 44.98 TOTAL STREAM AREA(ACRES) = 45.41 PEAK FLOW RATE(CFS) AT CONFLUENCE = 95.50 fir Yr**Yt Y:*Y:•Y: Y: *::*Y: is Yc Yr*Y:*ir**ir**Yt Y:.*it*Yt *ir Y: is Yr Yr it Yr Y:ir**Y:Yc*Yc**Yr Yt Ye Yt Yt Yt it Yc*YcYc it is***ie is Yt it it*ic ie Yc FLOW PROCESS FROM NODE 11.10 TO NODE 11.20 IS CODE = 2.1 -------------------------------------------------------- »»>RATIONAL METHOD INITIAL SUBAREA ANALYSIS««< DEVELOPMENT IS COMMERCIAL TC = K*[(LENGTH** 3.00)/(ELEVATION CHANGE)]** .20 INITIAL SUBAREA FLOW-LENGTH(FEET) = 665.00 UPSTREAM ELEVATION(FEET) = 1090.50 DOWNSTREAM ELEVATION(FEET) = 1087.50 ELEVATION DIFFERENCE(FEET) = 3.00 TC(MIN.) = .304*[( 665.00** 3.00)/( 3.00)]** .20 = 12.054 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.792 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA RUNOFF(CFS) = 6.09 TOTAL AREA(ACRES) = 2.49 PEAK FLOW RATE(CFS) = 6.09 Y:*Yt*Yr Yr**Y:�.YtY:**Yr Yr Yr it Y:*ic Ye it*Yt it is Yc*Yr Ye is Yt is it is it*Yc*it Yt it it**Yr Yt Yr*4t Yc;;ic*ic ir*iti: Yc ie is*Yc is it is*YtYr is is**:: FLOW PROCESS FROM NODE 11.20 TO NODE 11.30 IS CODE = 3 ----------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< Page 2 ESTIMATED PIPE DIAMETER(INCH) INCREASED TO 18.000 DEPTH OF FLOW IN 18.0 INCH PIPE IS 10.0 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 6.1 UPSTREAM NODE ELEVATION(FEET) = 1081.50 DOWNSTREAM NODE ELEVATION(FEET) = 1077.27 FLOW LENGTH(FEET) = 420.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 18.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 6.09 TRAVEL TIME(MIN.) = 1.16 TC(MIN.) = 13.21 is it it it it it ic;:',t it it it it it is fit it is it is is is is it is kic is it ic�ir :.tic it is ie is irit it is it :Rick:c it is it fir kit is ir�ic it it is it is it it it it it sY it is tic i;ir FLOW PROCESS FROM NODE 11.30 TO NODE 11.30 IS CODE = 8 -------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.643 ----------------- SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 4.22 SUBAREA RUNOFF(CFS) = 9.75 EFFECTIVE AREA(ACRES) = 6.71 AREA -AVERAGED Fm(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) _ .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 6.71 PEAK FLOW RATE(CFS) = 15.51 TC(MIN) = 13.21 ki:irieici;:isiciti:iricici.•«:Yiririci;ie:tiriti:�'.ciricic�iciririritirir:Yi:iticirieic:;isieiciciri;i<irieicsYirieicirieiri; �•iriririeiti;�i:itirir FLOW PROCESS FROM NODE 11.30 TO NODE 11.00 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< ESTIMATED PIPE DIAMETER(INCH) INCREASED TO 18.000 DEPTH OF FLOW IN 18.0 INCH PIPE IS 9.2 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 17.0 UPSTREAM NODE ELEVATION(FEET) = 1077.27 DOWNSTREAM NODE ELEVATION(FEET) = 1073.50 FLOW LENGTH(FEET) = 45.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 18.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 15.51 TRAVEL TIME(MIN.) _ .04 TC(MIN.) = 13.25 ..ic:ci:i:ici;i;*it it i:i; ic�ic�ic it it is i:i:ic*ir is i; ir��:k��irfii;�ir Yr ie i:�i;i;i:i;Yts:i;����ic it it ie�ic it ic�R•iri: i; sYic is it is is �k is FLOW PROCESS FROM NODE 11.00 TO NODE 11.00 IS CODE = 1 »»>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< »»>AND COMPUTE VARIOUS CONFLUENCED STREAM VALUES««< TOTAL NUMBER OF STREAMS = 2 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 2 ARE: TIME OF CONCENTRATION(MIN.) = 13.25 RAINFALL INTENSITY(INCH/HR) = 2.64 AREA -AVERAGED FM(INCH/HR) = .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 EFFECTIVE STREAM AREA(ACRES) = 6.71 TOTAL STREAM AREA(ACRES) = 6.71 PEAK FLOW RATE(CFS) AT CONFLUENCE = 15.51 RAINFALL INTENSITY AND TIME OF CONCENTRATION RATIO CONFLUENCE FORMULA USED FOR 2 STREAMS. Page 3 ** PEAK FLOW RATE TABLE ** Q Tc (CFS) (MIN.) Intensit (INCH/HR� Fp (INCH/HR) Al FM (INCH/HR) Ae (ACRES) 1 99.81 10.96 2.956 .65 .23 .15 36.62 2 109.34 15.91 2.364 .65 .23 .15 51.69 3 108.47 16.28 2.331 .64 .24 .15 52.12 4 105.58 13.25 2.637 .65 .23 .15 44.22 COMPUTED CONFLUENCE ESTIMATES ARE AS FOLLOWS: PEAK FLOW RATE(CFS) = 109.34 TC(MIN.) = 15.912 EFFECTIVE AREA(ACRES) = 51.69 AREA -AVERAGED FM(INCH/HR) _ .15 AREA -AVERAGED Fp(INCH/HR) _ .65 AREA -AVERAGED Ap = .23 TOTAL AREA(ACRES) = 52.12 k ie k is ie ie kick 9cir irk kie*kkkirkkkkkkfFSYkkkkkirk kiekkkkkkkkkkkk9r it ick kie it irkkkkkkkkkic ick kiekkkick FLOW PROCESS FROM NODE 11.00 TO NODE 12.00 IS CODE = 3 >>>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 57.0 INCH PIPE IS 42.1 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 7.8 UPSTREAM NODE ELEVATION(FEET) = 1073.50 DOWNSTREAM NODE ELEVATION(FEET) = 1072.77 FLOW LENGTH(FEET) = 240.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 57.00 NUMBER OF PIPES 1 PIPE-FLOW(CFS) = 109.34 TRAVEL TIME(MIN.) = .51 TC(MIN.) = 16.43 i.•irkkkk**�'d:4c:r it is***�i::r*;r it sY it tr �r°ks4:r it ir*it ir:r*sY is fc :: itir�*itlr4:�•*ir�it it ic%r*�•ir'.r ir',: '.r �•****:r**ir FLOW PROCESS FROM NODE 12.00 TO NODE 12.00 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 5 YEAR RAINFALL INTENSITY(INCH/HR) = 2.319 --------------- SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 1.40 SUBAREA RUNOFF(CFS) = 2.83 EFFECTIVE AREA(ACRES) = 53.09 AREA -AVERAGED FM(INCH/HR) _ .15 AREA -AVERAGED Fp(INCH/HR) = .65 AREA -AVERAGED Ap = .23 TOTAL AREA(ACRES) = 53.52 PEAK FLOW RATE(CFS) = 109.34 TC(MIN) = 16.43 kkkkkirkkkk�•kkk*k*kkkirkk*kkkkkickkkkkirkkicitkkkkkkkkkkkkkkkkkkkkkkkkkkkkkickkkkkk FLOW PROCESS FROM NODE 12.00 TO NODE 13.00 IS CODE = 3 -------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 42.0 INCH PIPE IS 30.7 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 14.5 UPSTREAM NODE ELEVATION(FEET) = 1072.77 DOWNSTREAM NODE ELEVATION(FEET) = 1062.75 FLOW LENGTH(FEET) = 630.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 42.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 109.34 TRAVEL TIME(MIN.) = .72 TC(MIN.) = 17.15 isiskkk*kk*::*ir:rkk*ki.•kkiek*kkkkk�ick*kkkkkkkkk*kkkkkkic i:kkkkkickkkkkkirkkkkkkirkkkkkk Page 4 FLOW PROCESS FROM NODE 13.00 TO NODE 13.00 IS CODE = 1 --------------------------------------------- »»>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< TOTAL NUMBER OF STREAMS = 2 --------- CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 1 ARE: TIME OF CONCENTRATION(MIN.) = 17.15 RAINFALL INTENSITY(INCH/HR) = 2.26 AREA -AVERAGED FM(INCH/HR) = .15 AREA -AVERAGED Fp(INCH/HR) = .65 AREA -AVERAGED Ap = .23 EFFECTIVE STREAM AREA(ACRES) = 53.09 TOTAL STREAM AREA(ACRES) = 53.52 PEAK FLOW RATE(CFS) AT CONFLUENCE = 109.34 it it it it * is iric Ye it it is is it is it it ie it it it is it is it it it it it ie it it is it is it is is is it iris is it ie is iric it it it ie * it it it is it ie it is it ie it ie is is it * * * * it is ie ie FLOW PROCESS FROM NODE 13.10 TO NODE 13.20 IS CODE = 2.1 ----------------------------------------------------------------------- »»>RATIONAL METHOD INITIAL SUBAREA ANALYSIS««< DEVELOPMENT IS COMMERCIAL ------------ TC = K*[(LENGTH** 3.00)/(ELEVATION CHANGE)]** .20 INITIAL SUBAREA FLOW-LENGTH(FEET) = 840.00 UPSTREAM ELEVATION(FEET) = 1084.00 DOWNSTREAM ELEVATION(FEET) = 1082.00 ELEVATION DIFFERENCE(FEET) = 2.00 TC(MIN.) = .304*[( 840.00** 3.00)/( 2.00)]** .20 = 15.040 25 YEAR RAINFALL INTENSITY (INCH/HR) = 2.445 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA RUNOFF(CFS) = 10.02 TOTAL AREA(ACRES) = 4.70 PEAK FLOW RATE(CFS) = 10.02 **ir it is s4 ie it is is is is it is is*ic is is it ici:i: is is it is is it is*ir ir:c*ic is is it it is 4r ie it st***ir*ir it it*ic*.ic it *°k is *it it****ir ie ir-k is it is is FLOW PROCESS FROM NODE 13.20 TO NODE 13.30 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 18.0 INCH PIPE IS 14.0 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 6.8 UPSTREAM NODE ELEVATION(FEET) = 1076.00 DOWNSTREAM NODE ELEVATION(FEET) = 1071.20 FLOW LENGTH(FEET) = 450.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 18.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 10.02 TRAVEL TIME(MIN.) = 1.10 TC(MIN.) = 16.14 i:i:*ir is ic:':*ic �*i: it is%**iri: is it i:sY*i:i: is is*sY**ic fe is*ie ie is**ir**ir'.cir*ic it*��t is is it is is*ir is .r it it it it it is is is*ir is is it it FLOW PROCESS FROM NODE 13.30 TO NODE 13.30 IS CODE = 8 --------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.343 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 4.65 SUBAREA RUNOFF(CFS) = 9.49 EFFECTIVE AREA(ACRES) = 9.35 AREA -AVERAGED FM(INCH/HR) _ .07 Page 5 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 9.35 PEAK FLOW RATE(CFS) = 19.09 TC(MIN) = 16.14 is is � it ie ie it is it it it it it is k is is is ic'.r ie it is it it it ie is is it ie ie is ie is is it it it ie it it it it is it is ieie ie it sY it is is it it :: is is it is ie it it is 4e it it is it k it it ie is FLOW PROCESS FROM NODE 13.30 TO NODE 13.30 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.343 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 6.09 SUBAREA RUNOFF(CFS) = 12.43 EFFECTIVE AREA(ACRES) = 15.44 AREA -AVERAGED FM(INCH/HR) _ .07 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 15.44 PEAK FLOW RATE(CFS) = 31.52 TC(MIN) = 16.14 is is sY is is it is is it i:ici: it it is it i:ir&ir is is is is is it it it ie ilir is it is is it is is is ie it is ie is is is is is is it it fir is it is it is it it irX i<it�ic is is it is it it is it i:ir FLOW PROCESS FROM NODE 13.30 TO NODE 13.40 IS CODE = 3 ---------------------------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< -------------------------------------------------------------------- DEPTH OF FLOW IN 27.0 INCH PIPE IS 17.4 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 11-.6 UPSTREAM NODE ELEVATION(FEET) = 1071.20 DOWNSTREAM NODE ELEVATION(FEET) = 1063.35 FLOW LENGTH(FEET) = 405.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 27.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 31.52 TRAVEL TIME(MIN.) _ .58 TC(MIN.) = 16.72 it it is � is it it ie i< is it i; k is it is is � �• it it & is is �i< �• is irx � it � it it it is is it it �c it it �• �' is �• � � it it � it R• it is ie it � it �'.: i; �• is it :Y it it ie it �' i; i< �- is FLOW PROCESS FROM NODE 13.40 TO NODE 13.40 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< ---------------------------------------------------------------------- 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.294 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 1.23 SUBAREA RUNOFF(CFS) = 2.46 EFFECTIVE AREA(ACRES) = 16.67 AREA -AVERAGED FM(INCH/HR) _ .07 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 16.67 PEAK FLOW RATE(CFS) = 33.29 TC(MIN) = 16.72 it kic is it i:Yi: it it it&ic is l: tic it is is icie it it is it ie ie is is is is ir�it is i; is it ie it is is is it is is it is is sY s: it it it it it is it it it it is it is fir it is it is is is it is is FLOW PROCESS FROM NODE 13.40 TO NODE 13.00 IS CODE = 3 ---------------------------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< >>>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< -------------------------------------------------------------------- DEPTH OF FLOW IN 27.0 INCH PIPE IS 21.1 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 10.0 UPSTREAM NODE ELEVATION(FEET) = 1063.35 DOWNSTREAM NODE ELEVATION(FEET) = 1062.75 Page 6 FLOW LENGTH(FEET) = 45.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 27.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 33.29 TRAVEL TIME(MIN.) _ .08 TC(MIN.) = 16.80 �c fe 4c*icy'; is tY is 4e is is is is 4r is is fe it is it is is is 4c 4c it fe 4:'lc is is is is Y 4r is is is it fr 4c it i;9cY:i: it is it �c is is Yc fe is is it Yc ie sY ie •lc •1: �c is is is is is is f: it it is 4c FLOW PROCESS FROM NODE 13.00 TO NODE 13.00 IS CODE = 1 ---------------------------------------------------------------------------- »»>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< »»>AND COMPUTE VARIOUS CONFLUENCED STREAM VALUES««< TOTAL NUMBER OF STREAMS = 2 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 2 ARE: TIME OF CONCENTRATION(MIN.) = 16.80 RAINFALL INTENSITY(INCH/HR) = 2.29 AREA -AVERAGED Fm(INCH/HR) = .07 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 EFFECTIVE STREAM AREA(ACRES) = 16.67 TOTAL STREAM AREA(ACRES) = 16.67 PEAK FLOW RATE(CFS) AT CONFLUENCE = 33.29 RAINFALL INTENSITY AND TIME OF CONCENTRATION RATIO CONFLUENCE FORMULA USED FOR 2 STREAMS. ** PEAK FLOW RATE TABLE ** Q Tc Intens. Fp Ap Fm Ae (CFS) (MIN.) (INCH/HR� (INCH/HR) (INCH/HR) (ACRES) 1 129.32 12.24 2.766 .66 .19 .13 50.17 2 137.07 14.51 2.498 .66 .19 .13 60.02 3 142.21 17.15 2.260 .66 .20 .13 69.76 4 140.90 17.52 2.231 .66 .20 .13 70.19 5 142.14 16.80 2.288 .66 .20 .13 68.77 COMPUTED CONFLUENCE ESTIMATES ARE AS FOLLOWS: PEAK FLOW RATE(CFS) = 142.21 TC(MIN.) = 17.149 EFFECTIVE AREA(ACRES) = 69.76 AREA -AVERAGED Fm(INCH/HR) _ .13 AREA -AVERAGED Fp(INCH/HR) _ .66 AREA -AVERAGED Ap = .20 TOTAL AREA(ACRES) = 70.19 '..•ic**'c;ci;*'.•*x:c fc*:;i:'.r�•4:s;�*ir**i::c*irk*�&**ic%ic*4r sY*****fe*4:i:i;*ir ie******�4:'.a****�:r is sc***s4� FLOW PROCESS FROM NODE 13.00 TO NODE 14.00 IS CODE = 3 ---------------------------------------------------------------------------- >>>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< ---------------------------------------------------------------------------- ---------------------------------------------------------------------------- DEPTH OF FLOW IN 54.0 INCH PIPE IS 43.6 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 10.3 UPSTREAM NODE ELEVATION(FEET) = 1062.75 DOWNSTREAM NODE ELEVATION(FEET) = 1060.88 FLOW LENGTH(FEET) = 330.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 54.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 142.21 TRAVEL TIME(MIN.) _ .53 TC(MIN.) = 17.68 sY*'.:':'.:':i:;:'.ck*�-':�•i:'.:*�•�•**�•�*4;*:rye:r**�-.�'..•�-'c:o**tic*�-ki;********k:r**ics::F :c.::'.c*:: *:'k*irk*�c is '.c :c* FLOW PROCESS FROM NODE 14.00 TO NODE 14.00 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< - - - - - - -------------------------------------- 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.219 SOIL CLASSIFICATION IS "B" Page 7 COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 1.82 SUBAREA RUNOFF(CFS) = 3.51 EFFECTIVE AREA(ACRES) = 71.58 AREA -AVERAGED FM(INCH/HR) _ .13 AREA -AVERAGED Fp(INCH/HR) = .66 AREA -AVERAGED Ap = .20 TOTAL AREA(ACRES) = 72.01 PEAK FLOW RATE(CFS) = 142.21 TC(MIN) = 17.68 i::'r4r*ie4;4:'e:ri:*4r:ririr*4r*icie4c:'c:Yteftir:Y�ciriciric4r*icie8rir4r:':ic:;4ricici::e:r�Yis:Yititi:4r4ritititit4tisk*isitir:YisstisitsYititit FLOW PROCESS FROM NODE 14.00 TO NODE 15.00 IS CODE = 3 ---------------------------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< >>>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< ---------------------------------------------------------------------------- ---------------------------------------------------------------------------- DEPTH OF FLOW IN 54.0 INCH PIPE IS 42.8 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 10.5 UPSTREAM NODE ELEVATION(FEET) = 1060.88 DOWNSTREAM NODE ELEVATION(FEET) = 1057.80 FLOW LENGTH(FEET) = 525.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 54.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 142.21 TRAVEL TIME(MIN.) _ .83 TC(MIN.) = 18.51 .. 4r it it*9r is 4r:: it 4t*:Y 4r 4r 4c it*it is it is is it•lr it it ic::4e ie it :::.•.*ir k i;:r*ir Yc ie ic:Y*irfe:4 it ir:e*:tir:rir:'c**ic it is i;*it :t it it 4t:Y :r is is is is FLOW PROCESS FROM NODE 15.00 TO NODE 15.00 IS CODE = 1 ---------------------------------------------------------------------------- »»>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< ---------------------------------------------------------------------------- ---------------------------------------------------------------------------- TOTAL NUMBER OF STREAMS = 2 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 1 ARE: TIME OF CONCENTRATION(MIN.) = 18.51 RAINFALL INTENSITY(INCH/HR) = 2.16 AREA -AVERAGED FM(INCH/HR) = .13 AREA -AVERAGED Fp(INCH/HR) = .66 AREA -AVERAGED Ap = .20 EFFECTIVE STREAM AREA(ACRES) = 71.58 TOTAL STREAM AREA(ACRES) = 72.01 PEAK FLOW RATE(CFS) AT CONFLUENCE = 142.21 ic'c.:r 4t ie ir:c4r****4::Y*it*ir ic*it is it it Yr it is it is it is it it*4r***:tic:Y it is is it ic*'.c:Y*dr it is it 4t it it is it*ir*ic is :Y:Y it it ic:.:Y dr:Y 4c it :Y FLOW PROCESS FROM NODE 15.10 TO NODE 15.20 IS CODE = 2.1 ---------------------------------------------------------------------------- »»>RATIONAL METHOD INITIAL SUBAREA ANALYSIS««< - ------------------- DEVELOPMENT IS COMMERCIAL TC = K*[(LENGTH** 3.00)/(ELEVATION CHANGE)]** .20 INITIAL SUBAREA FLOW-LENGTH(FEET) = 900.00 UPSTREAM ELEVATION(FEET) = 1075.50 DOWNSTREAM ELEVATION(FEET) = 1072.50 ELEVATION DIFFERENCE(FEET) = 3.00 TC(MIN.) = .304*[( 900.00** 3.00)/( 3.00)]** .20 = 14.454 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.504 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA RUNOFF(CFS) = 10.23 TOTAL AREA(ACRES) = 4.68 PEAK FLOW RATE(CFS) 10.23 ::It*ir ir:Yic:'t*�'.t:t'..•'t�•**it:t4t**'x'.t*ir it it't4t:r it it dr:Y it it 4r ir:Yi:fit***�•:ti:it'.t it 4c*it ir:rit**:t it 4: it ft is it �t it it it Yc 4r it it it :r Page 8 FLOW PROCESS FROM NODE 15.20 TO NODE 15.30 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< ---------------------------------------------------------------------------- ---------------------------------------------------------------------------- DEPTH OF FLOW IN 18.0 INCH PIPE IS 14.7 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 6.6 UPSTREAM NODE ELEVATION(FEET) = 1066.50 DOWNSTREAM NODE ELEVATION(FEET) = 1062.60 FLOW LENGTH(FEET) = 390.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 18.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 10.23 TRAVEL TIME(MIN.) _ .98 TC(MIN.) = 15.44 iskkirkkkiskkkic irkkkkkkkkkk�kkk4tkkkkkkkkkkkkkkkkkkYtkkkkkkkk�kkkkkirkkkkirk kkic kitkkir FLOW PROCESS FROM NODE 15.30 TO NODE 15.30 IS CODE = --------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.407 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 4.69 SUBAREA RUNOFF(CFS) = 9.84 EFFECTIVE AREA(ACRES) = 9.37 AREA -AVERAGED FM(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) _ .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 9.37 PEAK FLOW RATE(CFS) = 19.66 TC(MIN) = 15.44 k is kki:k�•k kki;kkkkkkkkk�•kkkkkkkkirk kirkkkkirk kir is kk kkkkkkkkkkkkkkkkkkkkirkkk&irk itkkkk FLOW PROCESS FROM NODE 15.30 TO NODE 15.30 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< ---------------------------------------------------------------------------- 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.407 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 6.29 SUBAREA RUNOFF(CFS) = 13.20 EFFECTIVE AREA(ACRES) = 15.66 AREA -AVERAGED FM(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 15.66 PEAK FLOW RATE(CFS) = 32.86 TC(MIN) = 15.44 ..kkkk...:kkkkkkkkR•kkkkkkkkkitkkkick�kkkkkki.•k kkitkkkkkkkkkk�.. .. .. ..kkic �•k it k ickir ki:k'..•kkit FLOW PROCESS FROM NODE 15.30 TO NODE 15.00 IS CODE = 3 ---------------------------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< - -------------------------------------------------------------------- DEPTH OF FLOW IN 30.0 INCH PIPE IS 21.0 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 9.0 UPSTREAM NODE ELEVATION(FEET) = 1062.60 DOWNSTREAM NODE ELEVATION(FEET) = 1057.80 FLOW LENGTH(FEET) = 495.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 30.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 32.86 TRAVEL TIME(MIN.) _ .92 TC(MIN.) = 16.36 Page 9 ick ickkickkkiekkkkirkki:kkkir irk kir kir irkkkkkkirk kirk irk ie irk kk it is ickkir irkkkkkkie it it kie kir is irk ick ickkk FLOW PROCESS FROM NODE 15.00 TO NODE 15.00 IS CODE = 1 ---------------------------------------------------------------------------- »»>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< »»>AND COMPUTE VARIOUS CONFLUENCED STREAM VALUES««< ---------------------------------------------------------------- TOTAL NUMBER OF STREAMS = 2 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 2 ARE: TIME OF CONCENTRATION(MIN.) = 16.36 RAINFALL INTENSITY(INCH/HR) = 2.32 AREA -AVERAGED FM(INCH/HR) = .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = 10 EFFECTIVE STREAM AREA(ACRES) = 15.66 TOTAL STREAM AREA(ACRES) = 15.66 PEAK FLOW RATE(CFS) AT CONFLUENCE = 32.86 RAINFALL INTENSITY AND TIME OF CONCENTRATION RATIO CONFLUENCE FORMULA USED FOR 2 STREAMS. ** PEAK FLOW RATE TABLE ** Q Tc Intensit Fp Ap Fm Ae (CFS) (MIN.) (INCH/HR (INCH/HR) (INCH/HR) (ACRES) 1 159.97 13.62 2.595 .68 .17 .12 65.03 2 169.56 15.88 2.367 .67 .17 .12 77.04 3 172.93 18.16 2.183 .67 .18 .12 86.25 4 172.65 18.51 2.158 .67 .18 .12 87.24 5 170.96 18.89 2.133 .67 .18 .12 87.67 6 171.00 16.36 2.325 .67 .17 .12 79.34 COMPUTED CONFLUENCE ESTIMATES ARE AS FOLLOWS: PEAK FLOW RATE(CFS) = 172.93 TC(MIN.) = 18.162 EFFECTIVE AREA(ACRES) = 86.25 AREA -AVERAGED Fm(INCH/HR) _ .12 AREA -AVERAGED Fp(INCH/HR) _ .67 AREA -AVERAGED Ap = .18 TOTAL AREA(ACRES) = 87.67 it ick kkick kickki: kk isk ki: kirk it*kkkkirkkkkkkkkkirk irk kk kkkkkkkkkkkkkic �i:ir*ir #i it *i; it it is it'.r�ir is is FLOW PROCESS FROM NODE 15.00 TO NODE 16.00 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< -------------------------------------------------------------- DEPTH OF FLOW IN 45.0 INCH PIPE IS 36.3 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 18.1 UPSTREAM NODE ELEVATION(FEET) = 1057.80 DOWNSTREAM NODE ELEVATION(FEET) = 1050.50 FLOW LENGTH(FEET) = 330.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 45.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 172.93 TRAVEL TIME(MIN.) = .30 TC(MIN.) = 18.47 .. ., •irk i,.: irkkki.ki.iskkkki:k�......kkki...kkkkkkkkkk�: ickkkkk.:k:..... .. kickkkkkgi. .. i:kkkX .. kirk i;kk FLOW PROCESS FROM NODE 16.00 TO NODE 16.00 IS CODE = 1 ---------------------------------------------------------------------------- »»>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< ------------------------------------ TOTAL NUMBER OF STREAMS = 2 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 1 ARE: TIME OF CONCENTRATION(MIN.) = 18.47 RAINFALL INTENSITY(INCH/HR) = 2.16 AREA -AVERAGED FM(INCH/HR) = .12 AREA -AVERAGED Fp(INCH/HR) = .67 AREA -AVERAGED Ap = .18 Page 10 EFFECTIVE STREAM AREA(ACRES) = 86.25 TOTAL STREAM AREA(ACRES) = 87.67 PEAK FLOW RATE(CFS) AT CONFLUENCE = 172.93 it is iek kie iek it ick irk ie it iek iek it irk itk it it is ie itir iekkkkir it irk kie kirkkkirkkir iekkkkit it ick it it it is it it it it kir kic irk ick ie FLOW PROCESS FROM NODE 16.10 TO NODE 16.20 IS CODE = 2.1 ---------------------------------------------------------------------------- »»>RATIONAL METHOD INITIAL SUBAREA ANALYSIS««< - ---------------------------------- DEVELOPMENT IS COMMERCIAL TC = K*[(LENGTH** 3.00)/(ELEVATION CHANGE)]** .20 INITIAL SUBAREA FLOW-LENGTH(FEET) = 220.00 UPSTREAM ELEVATION(FEET) = 1067.00 DOWNSTREAM ELEVATION(FEET) = 1065.00 ELEVATION DIFFERENCE(FEET) = 2.00 TC(MIN.) = .304*[( 220.00** 3.00)/( 2.00)]** .20 = 6.732 25 YEAR RAINFALL INTENSITY(INCH/HR) = 3.960 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FMCINCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA RUNOFF(CFS) = 10.14 TOTAL AREA(ACRES) = 2.90 PEAK FLOW RATE(CFS) = 10.14 iti: irkkkkitkkirk kkitkkkkickkkkkkkkkkkkkkkkkkkkirkkkkkitkkkitkkkkit kkkitkk kk irkkkkkir itk kirk FLOW PROCESS FROM NODE 16.20 TO NODE 16.30 IS CODE = 3 ---------------------------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< >>>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< ---------------------------------------------------------------------------- DEPTH OF FLOW IN 18.0 INCH PIPE IS 12.9 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 7.5 UPSTREAM NODE ELEVATION(FEET) = 1059.00 DOWNSTREAM NODE ELEVATION(FEET) = 1055.03 FLOW LENGTH(FEET) = 300.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 18.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 10.14 TRAVEL TIME(MIN.) _ .67 TC(MIN.) = 7.40 '.t itk kit iskirk i:kkkkkkkkkkkkkkkkkisk kkkkkk kirk kit it it �.t*kkkkitkk �i Okkkitkkkkkkkkki:kkir iskkit k itk FLOW PROCESS FROM NODE 16.30 TO NODE 16.30 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 25 YEAR RAINFALL INTENSITY(INCH/HR) = 3.742 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 2.34- SUBAREA RUNOFF(CFS) = 7.72 EFFECTIVE AREA(ACRES) = 5.24 AREA -AVERAGED FM(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) _ .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 5.24 PEAK FLOW RATE(CFS) 17.29 TC(MIN) = 7.40 .. ., i.•k itkkirkk it itkkk*kic kirkkk kirkkkkkkkirkitk k'hkkicickkkkk�Yk*irkkkkkkick is itk kirk kirkkkk'.r* R FLOW PROCESS FROM NODE 16.30 TO NODE 16.00 IS CODE = 3 ---------------------------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< Page 11 ESTIMATED PIPE DIAMETER(INCH) INCREASED TO 18.000 DEPTH OF FLOW IN 18.0 INCH PIPE IS 10.2 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 16.7 UPSTREAM NODE ELEVATION(FEET) = 1055.03 DOWNSTREAM NODE ELEVATION(FEET) = 1050.50 FLOW LENGTH(FEET) = 60.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 18.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 17.29 TRAVEL TIME(MIN.) _ .06 TC(MIN.) = 7.46 4r Yr sk �Y is S:ic:: is ie it 4c s4 is is is it �r is is is �4*ic it fair i:4c is is 4c is sY ie is Yc it is is is fr �4 is is i:4r is Yc 4c is is ft 4c is Ye it 4c it at is it is fr it is it s4 it it it it is 4r it 4r FLOW PROCESS FROM NODE 16.00 TO NODE 16.00 IS CODE = 1 »»>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< »»>AND COMPUTE VARIOUS CONFLUENCED STREAM VALUES««< -------------------------------------------------------------------------- TOTAL NUMBER OF STREAMS = 2 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 2 ARE: TIME OF CONCENTRATION(MIN.) = 7.46 RAINFALL INTENSITY(INCH/HR) = 3.72 AREA -AVERAGED FM(INCH/HR) = .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 EFFECTIVE STREAM AREA(ACRES) = 5.24 TOTAL STREAM AREA(ACRES) = 5.24 PEAK FLOW RATE(CFS) AT CONFLUENCE = 17.29 RAINFALL INTENSITY AND TIME OF CONCENTRATION RATIO CONFLUENCE FORMULA USED FOR 2 STREAMS. ** PEAK FLOW RATE TABLE ** Q Tc Intensit Fp Ap FM Ae (CFS) (MIN.) (INCH/HR� (INCH/HR) (INCH/HR) (ACRES) 1 171.75 13.93 2.560 .68 .17 .11 70.27 2 180.30 16.18 2.340 .68 .17 .11 82.28 3 181.54 16.66 2.299 .68 .17 .11 84.58 4 182.82 . 18.47 2.162 .67 .17 .12 91.49 5 182.42 18.82 2.137 .67 .17 .12 92.48 6 180.61 19.19 2.112 .67 .18 .12 92.91 7 143.75 7.46 3.724 .68 .16 .11 40.07 COMPUTED CONFLUENCE ESTIMATES ARE AS FOLLOWS: PEAK FLOW RATE(CFS) = 182.82 TC(MIN.) = 18.466 EFFECTIVE AREA(ACRES) = 91.49 AREA -AVERAGED FM(INCH/HR) _ .12 AREA -AVERAGED Fp(INCH/HR) _ .67 AREA -AVERAGED Ap = .17 TOTAL AREA(ACRES) = 92.91 i:i:*ic*:::ric'..•i::r'.r is do �':4:***{:*fe sY fr*:r*i:*ir fc dt it 4r it is 4r it*Yru i:i:4r:t it it is �':*4: �k is 4c is is �k it 4e 4r is i:i�ir**ie h'.•i: ?r is it*it it FLOW PROCESS FROM NODE 16.00 TO NODE 16.00 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.162 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 3.06 SUBAREA RUNOFF(CFS) = 5.75 EFFECTIVE AREA(ACRES) = 94.55 AREA -AVERAGED FM(INCH/HR) _ .12 AREA -AVERAGED Fp(INCH/HR) = .67 AREA -AVERAGED Ap = .17 TOTAL AREA(ACRES) = 95.97 PEAK FLOW RATE(CFS) = 182.82 TC(MIN) = 18.47 Page 12 * Yc Yr is Yc Yc Yc Yc is ie Yc is Yc Yc Yr is Yt it it Yc Yc it Yc Yt it Yt Yc Yt Yr Yc Yt Yc is Yr i< it Ye Yr Ye Yc Yr it Yr Yr is Yc Yrit Yt Yc it Yt Yr it Yc Yr is Yr 9c Yt Yt Yr Yt Yr it Ye it Ye Yc Yr Yc it Yt Ye Yr it FLOW PROCESS FROM NODE 16.00 TO NODE 17.00 --------------------------------------------------------- IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 39.0 INCH PIPE IS 30.9 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 25.9 UPSTREAM NODE ELEVATION(FEET) = 1050.50 DOWNSTREAM NODE ELEVATION(FEET) = 1039.50 FLOW LENGTH(FEET) = 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 39.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 182.82 TRAVEL TIME(MIN.) _ .13 TC(MIN.) ---------------------------------------------- = 18.59 END OF STUDY SUMMARY: - TOTAL AREA(ACRES) = 95.97 TC(MIN.) = 18.59 EFFECTIVE AREA(ACRES) = 94.55 AREA -AVERAGED Fm(INCH/HR)= .12 AREA -AVERAGED Fp(INCH/HR) _ .67 AREA -AVERAGED Ap = .17 PEAK FLOW RATE(CFS) = 182.82 it it PEAK FLOW RATE TABLE ** Q Tc Intensity Fp Ap Fm Ae (MIN.) (IN3H684) (INCH/HHR) (INCH/HR) (ACRES) 1 143F75 16 .11 43.13 2 171.75 14.06 2.546 .68 .16 .11 73.33 3 180.30 16.31 2.329 .68 .17 .11 85.34 4 181.54 16.79 2.289 .68 .17 .11 87.64 5 182.82 18.59 2.153 .67 .17 .12 94.55 6 182.42 18.95 2.129 .67 .17 .12 95.54 7 180.61 19.32 2.104 .67 .17 .12 95.97 END OF RATIONAL METHOD ANALYSIS Page 13 '.: sY4:4c is �'c*ie do sY is 4c is is 4c:c fc ir*4c is it Y 4c Yc is is it 9r 4r it it it 4e it sk it fr Y fr*ic is it 'e 4c is is 4c is 4r 4c 4r{c'k ie is is i:4:4c 4r 4r it Y is �r is is lr is Yc is 4t 4r it RATIONAL METHOD HYDROLOGY COMPUTER PROGRAM PACKAGE (Reference: 1986 SAN BERNARDINO CO. HYDROLOGY CRITERION) (c) Copyright 1983-93 Advanced Engineering Software (aes) Ver. 1.9B Release Date: 7/18/93 License ID 1202 Analysis prepared by: HUITT-ZOLLARS, INC. 15101 RED HILL AVENUE TUSTIN, CALIFORNIA 92780-6500 PHONE (714) 259-7900 * FAX (714) 259-0210 ----------------------------------------------------------------------- FILE NAME: 202QO25H.DAT TIME/DATE OF STUDY: 13: 8 6/14/2004 ----------------- ---_------ ___ USER SPECIFIED HYDROLOGY AND HYDRAULIC MODEL INFORMATION: --*TIME-OF-CONCENTRATION MODEL* -- USER SPECIFIED STORM EVENT(YEAR) = 25.00 SPECIFIED MINIMUM PIPE SIZE(INCH) = 18.00 SPECIFIED PERCENT OF GRADIENTS(DECIMAL) TO USE FOR FRICTION SLOPE = .95 ^•USER -DEFINED LOGARITHMIC INTERPOLATION USED FOR RAINFALL* 10-YEAR STORM 60-MINUTE INTENSITY(INCH/HOUR) _ .920 100-YEAR STORM 60-MINUTE INTENSITY(INCH/HOUR) = 1.340 COMPUTED RAINFALL INTENSITY DATA: STORM EVENT = 25.00 1-HOUR INTENSITY(INCH/HOUR) = 1.0659 SLOPE OF INTENSITY DURATION CURVE = .6000 lrsY:s*is*'c:r:r*ic:t�•i:::':�c*�•*ir is �•ir it ie 4r*ic**4r:.'*�ti*::::***icy'',: :.•ic*i: �r :r i.•*:r :r �.: is :: �•ic**'r 4:*ic**ic'.c :r k is '.c is ic* FLOW PROCESS FROM NODE 20.00 TO NODE 22.00 IS CODE --------------------------------------------------------------------------- = 2.1 »»>RATIONAL METHOD INITIAL SUBAREA ANALYSIS««< DEVELOPMENT IS COMMERCIAL TC = K*[(LENGTH** 3.00)/(ELEVATION CHANGE)]** .20 INITIAL SUBAREA FLOW-LENGTH(FEET) = 1000.00 UPSTREAM ELEVATION(FEET) = 1073.00 DOWNSTREAM ELEVATION(FEET) = 1070.35 ELEVATION DIFFERENCE(FEET) = 2.65 TC(MIN.) = .304*[( 1000.00** 3.00)/( 2.65)]** .20 = 15.784 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.375 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA RUNOFF(CFS) = 15.38 TOTAL AREA(ACRES) = 7.43 PEAK FLOW RATE(CFS) = 15.38 ., is iri:*it is*4c�i:4r'r'r:: 4r it �•i:it:c 4c it is ie*i'rit:r**ic:r is is is 4t is it**4e it ic:r*:c',r*ic**ic*ic 4c �e it is it 4r *ic is *:e is ;: ie Sri: is it :r :r it FLOW PROCESS FROM NODE 22.00 TO NODE 23.00 IS CODE = 3 ----------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 24.0 INCH PIPE IS 19.4 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 5.7 UPSTREAM NODE ELEVATION(FEET) = 1063.35 DOWNSTREAM NODE ELEVATION(FEET) = 1062.35 Page 1 FLOW LENGTH(FEET) 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 24.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 15.38 TRAVEL TIME(MIN.) _ .59 TC(MIN.) = 16.37 FLOW PROCESS FROM NODE 23.00 TO NODE 23.00 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.323 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 3.23 SUBAREA RUNOFF(CFS) = 6.54 EFFECTIVE AREA(ACRES) = 10.66 AREA -AVERAGED Fm(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 10.66 PEAK FLOW RATE(CFS) = 21.57 TC(MIN) = 16.37 ?: » 'k»»»»»»»»»»»»»»»»?r it ?r»»»»»»»»»»»» it»»»?:»»»» » �•»» ir?r »»»»»»»» k» »ic » it»» ?c»»»»» it»»»» FLOW PROCESS FROM NODE 23.00 TO NODE 24.00 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 30.0 INCH PIPE IS 19.6 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 6.3 UPSTREAM NODE ELEVATION(FEET) = 1062.35 DOWNSTREAM NODE ELEVATION(FEET) = 1061.35 FLOW LENGTH(FEET) = 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 30.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 21.57 TRAVEL TIME(MIN.) _ .53 TC(MIN.) = 16.90 FLOW PROCESS FROM NODE 24.00 TO NODE 24.00 IS CODE = 8 -------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.280 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 3.23 SUBAREA RUNOFF(CFS) = 6.41 EFFECTIVE AREA(ACRES) = 13.89 AREA -AVERAGED Fm(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 13.89 PEAK FLOW RATE(CFS) = 27.56 TC(MIN) = 16.90 ?: » Yc» »»?c ?c » »?c?t» ». ;� »»»» ?:» ?c it ».»»»»»»»»»»»»»» i,'-»»?: »»?c ?r»?: »»»»» :r»»»» ?c.» it»»»»?.• ?r it»»» �•»»» i; FLOW PROCESS FROM NODE 24.00 TO NODE 25.00 IS CODE = 3 ---------------------------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 30.0 INCH PIPE IS 23.9 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 6.6 UPSTREAM NODE ELEVATION(FEET) = 1061.35 Page 2 DOWNSTREAM NODE ELEVATION(FEET) = 1060.35 FLOW LENGTH(FEET) = 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 30.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 27.56 TRAVEL TIME(MIN.) _ .51 TC(MIN.) = 17.41 FLOW PROCESS FROM NODE 25.00 TO NODE 25.00 IS CODE = 8 ---------------------------------------------------------------------------- >>>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.240 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 3.23 SUBAREA RUNOFF(CFS) = 6.29 EFFECTIVE AREA(ACRES) = 17.12 AREA -AVERAGED Fm(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 17.12 PEAK FLOW RATE(CFS) = 33.35 TC(MIN) = 17.41 �:r'.[�dr:[�'.ti::r it d::::[ir it it ir:rk:f�k�:c:tkif�'f*tic i::r it �4c i[ir'u it 4r ir'.f:t it ic��ir if�kif'.ei[it it it it�'.r it ie i[sY sY 4r is sY Y[it it is is :Y �'t :r FLOW PROCESS FROM NODE 25.00 TO NODE 26.00 IS CODE = 3 >>>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 33.0 INCH PIPE IS 24.8 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 7.0 UPSTREAM NODE ELEVATION(FEET) = 1060.35 DOWNSTREAM NODE ELEVATION(FEET) = 1059.35 FLOW LENGTH(FEET) = 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 33.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 33.35 TRAVEL TIME(MIN.) _ .48 TC(MIN.) = 17.89 .. .. .. cif it s': �•:: �•�•�•k�: is is �•��:&R ir:[��°k it it 9r�4c�:c :[:[fr �r :r it :t irk �•ir :['.[sY 4: it :r is sir cif �t ir��•�&i[ic �„i k'.[�•�c': if it �e is �•�4[ FLOW PROCESS FROM NODE 26.00 TO NODE 26.00 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««r 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.203 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 3.23 SUBAREA RUNOFF(CFS) = 6.19 EFFECTIVE AREA(ACRES) = 20.35 AREA -AVERAGED Fm(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) 20.35 PEAK FLOW RATE(CFS) = 38.98 TC(MIN) = 17.89 .. �•'x'.: it is kit'r;rifY:::ici:�'.c��•kir Yr �:c��4: it is Y 4t ir;rk4{i:A•de:t it if4fif&ir&4f it 4r icic if�ic is is ir�irt it is is Y it is is is 4t 4t is :; :F Yr is it FLOW PROCESS FROM NODE 26.00 TO NODE 27.00 IS CODE = 3 ---------------------------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 36.0 INCH PIPE IS 25.4 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 7.3 Page 3 UPSTREAM NODE ELEVATION(FEET) = 1059.35 DOWNSTREAM NODE ELEVATION(FEET) = 1058.35 FLOW LENGTH(FEET) = 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 36.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 38.98 TRAVEL TIME(MIN.) _ .46 TC(MIN.) = 18.34 is it it ie irir is iF it it it ie is is it is it it ie is is it is icir is it sY it it is ie it it is is it it is sY it it is it it it ie it'k is ie is icie is it it it is iric is ie it � it is is it is it is is is it FLOW PROCESS FROM NODE 27.00 TO NODE 27.00 IS CODE = 8 ---------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 5 YEAR RAINFALL INTENSITY(INCH/HR) = 2.170 ----------------- SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 3.23 SUBAREA RUNOFF(CFS) = 6.09 EFFECTIVE AREA(ACRES) = 23.58 AREA -AVERAGED FM(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 23.58 PEAK FLOW RATE(CFS) = 44.47 TC(MIN) = 18.34 it is is ie it it it is it ic-k it is is it ie ie it is it is it ie is sY is it is ic&:c icit it it it is is is is it it it is is it ie it is it it ir°k ie it it ie it it is is it it is is ii is is ie it s4 is it is is it FLOW PROCESS FROM NODE 27.00 TO NODE 28.00 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 36.0 INCH PIPE IS 28.5 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 7.4 UPSTREAM NODE ELEVATION(FEET) = 1058.35 DOWNSTREAM NODE ELEVATION(FEET) = 1057.35 FLOW LENGTH(FEET) = 200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 36.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 44.47 TRAVEL TIME(MIN.) _ .45 TC(MIN.) = 18.79 iric�•�•icicirir.;t;yitici;it�i:i;iticiticitiricieiris�:'r��iri:ici;&i;*is�iritiri;isiriciticiricR•ici;ieiriritiricicirir��ir:Yi:ici:i;it�irtic FLOW PROCESS FROM NODE 28.00 TO NODE 28.00 IS CODE = 8 ------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 25 YEAR. RAINFALL INTENSITY(INCH/HR) = 2.139 ------------------ SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 3.23 SUBAREA RUNOFF(CFS) = 6.00 EFFECTIVE AREA(ACRES) = 26.81 AREA -AVERAGED FM(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 26.81 PEAK FLOW RATE(CFS) = 49.80 TC(MIN) = 18.79 is X it �• is it is is ki; i; k is :k is k it it it is it it it is it is is ie is is is i.• it is it it i� is it ie is is it �• it it'..• it irir is is it is � it it it is is k is is i; � it is it is is it it is it �. ;: FLOW PROCESS FROM NODE 28.00 TO NODE 29.00 IS CODE = 3 ---------------------------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW) ««< DEPTH OF FLOW IN 39.0 INCH PIPE IS 29.4 INCHES Page 4 PIPE -FLOW VELOCITY(FEET/SEC.) = 7.4 UPSTREAM NODE ELEVATION(FEET) = 1057.35 DOWNSTREAM NODE ELEVATION(FEET) = 1056.75 FLOW LENGTH(FEET) = 132.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 39.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 49.80 TRAVEL TIME(MIN.) _ .30 TC(MIN.) = 19.09 sk is sY is is it it is it is it it it it irir is it ie it it s4 is is is s4 sY ie is it is sY ie ie it it is it ie it is it it it is ie ie it is ie it sY it sk it it it sY sY is is it is is it it icic it it it is is it ie ie FLOW PROCESS FROM NODE 29.00 TO NODE 29.00 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.119 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 2.13 SUBAREA RUNOFF(CFS) = 3.92 EFFECTIVE AREA(ACRES) = 28.94 AREA -AVERAGED FM(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 28.94 PEAK FLOW RATE(CFS) = 53.24 TC(MIN) = 19.09 9;i5-ir it i:ici;>: sY sY is ie sY is i<it it icic.;ri:i; ir�ic it sY i<>; sY is sk is is is it#ic is it it ie sti it it ie is it i�sY sY is sY s4 sY ic��sYic sY is it it is i<ic it is �e is is sY it is sY FLOW PROCESS FROM NODE 29.00 TO NODE 30.00 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< ---------------------------------------------------------------=---- DEPTH OF FLOW IN 39.0 INCH PIPE IS 29.4 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 7.9 UPSTREAM NODE ELEVATION(FEET) = 1056.75 DOWNSTREAM NODE ELEVATION(FEET) = 1055.50 FLOW LENGTH(FEET) = 240.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 39.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 53.24 TRAVEL TIME(MIN.) _ .50 TC(MIN.) = 19.59 � it is is it it is is � � ir>; is R• it is >'; � it is sY is is k is i.• is is k is � '.c is i; is ie ie it �• is it Yr � :t is s: sY it is �- � i; >'; i; is is is it X i::: � is it it is ie it it it it it it is 'c st FLOW PROCESS FROM NODE 30.00 TO NODE 31.00 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 39.0 INCH PIPE IS 27.5 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 8.5 UPSTREAM NODE ELEVATION(FEET) = 1055.50 DOWNSTREAM NODE ELEVATION(FEET) = 1052.20 FLOW LENGTH(FEET) = 540.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 39.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 53.24 TRAVEL TIME(MIN.) = 1.06 TC(MIN.) = 20.65 se is :r i.•i; is is it is i.•i: kir:e�'.eR-ic'.r kic�i:�•�•i;>';i: it sY it'x is sk is is it is it is is is ie i:iri: ie ie ir�ir�ie sY it it is i<it9:>4 it irie is is :c it it is i<ie ic�ir ie FLOW PROCESS FROM NODE 31.00 TO NODE 31.00 IS CODE = 8 ----------------------- ---------------------------------------------------- >>>>>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.021 SOIL CLASSIFICATION IS "B" Page 5 COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 3.34 SUBAREA RUNOFF(CFS) = 5.85 EFFECTIVE AREA(ACRES) = 32.28 AREA -AVERAGED FM(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 32.28 PEAK FLOW RATE(CFS) = 56.54 TC(MIN) = 20.65 iric*irieiri�iririsirieiciriririe*isiciricicsYiYit*ieiriririciririririeiriricieicir**iriciririeitieiritieieiciriririciririririeicisicicic*irieiei; FLOW PROCESS FROM NODE 31.00 TO NODE 32.00 IS CODE 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW) ««< DEPTH OF FLOW IN 36.0 INCH PIPE IS 28.1 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 9.6 UPSTREAM NODE ELEVATION(FEET) = 1052.20 DOWNSTREAM NODE ELEVATION(FEET) = 1052.00 FLOW LENGTH(FEET) = 24.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 36.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 56.54 TRAVEL TIME(MIN.) _ .04 TC(MIN.) = 20.69 it �•sY it*ie ie :4*«ie it :: is �•iri:*ir is is is*ir it ie sY ie ie it*****ie*sY it it it ie**i:ie*ir**ic it is it is it is it is i; is is*ir it is it it is is it it it*'.e it FLOW PROCESS FROM NODE 32.00 TO NODE 32.00 IS CODE = 1 ------------------------------------------------------------------------ »»>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< TOTAL NUMBER OF STREAMS = 2 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 1 ARE: TIME OF CONCENTRATION(MIN.) = 20.69 RAINFALL INTENSITY(INCH/HR) = 2.02 AREA -AVERAGED Fm(INCH/HR) = .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 EFFECTIVE STREAM AREA(ACRES) = 32.28 TOTAL STREAM AREA(ACRES) = 32.28 PEAK FLOW RATE(CFS) AT CONFLUENCE = 56.54 ic*i:iri:*ir it is*-k is is i;. it is*1: is it ie'..•ir it*i:ie9:i:*i: it is i;-k it it is*it is is is it is ir�i:it'.r sY irit*s: it it ir:Y *ir*ie is it*i.•ie it i.•ie is it °k** FLOW PROCESS FROM NODE 32.10 TO NODE 32.40 IS CODE = 2.1 ---------------------------------------------------------------------------- »»>RATIONAL METHOD INITIAL SUBAREA ANALYSIS««< DEVELOPMENT IS COMMERCIAL TC = K*[(LENGTH** 3 . 00) /(ELEVATION CHANGE)]** .20 INITIAL SUBAREA FLOW-LENGTH(FEET) = 750.00 UPSTREAM ELEVATION(FEET) = 1072.00 DOWNSTREAM ELEVATION(FEET) = 1066.75 ELEVATION DIFFERENCE(FEET) = 5.25 TC(MIN.) = .304*[( 750.00*it 3.00)/( 5.25)]** .20 = 11.585 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.859 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA RUNOFF(CFS) = 5.19 TOTAL AREA(ACRES) = 2.07 PEAK FLOW RATE(CFS) = 5.19 ic'..-it**ir it*ir-kic:Y',r is is ir*ici: it is it i;*ic:t is is it it is is �•ir it ir:c*ic Yr.ic is*ic*'.c is is it*ir it is it it it it i:ir -k is is*ir it it �•ir is is*ir is *ic :; Page 6 FLOW PROCESS FROM NODE 32.40 TO NODE 32.50 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 18.0 INCH PIPE IS 11.3 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 4.5 UPSTREAM NODE ELEVATION(FEET) = 1055.75 DOWNSTREAM NODE ELEVATION(FEET) = 1054.25 FLOW LENGTH(FEET) = 300.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 18.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 5.19 TRAVEL TIME(MIN.) = 1.12 TC(MIN.) = 12.71 p:4::'e it ie'.e4::'r4e'c is is Sc:Y kie�'.:'ci::YYr:Y:c it 4c 9r ie ic.4ci: sY it 4r�ic ie�ic it 4r it 4r i:ie:Y ic�ic ic'k4r:'rir:ti::ic'.eir:: 4�ic �c�ir �..•i:�:4 :4 k'.c 4r is fc it FLOW PROCESS FROM NODE 32.50 TO NODE 32.50 IS CODE = 8 ---------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 5 YEAR RAINFALL INTENSITY(INCH/HR) = 2.705 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 2.07 SUBAREA RUNOFF(CFS) = 4.90 EFFECTIVE AREA(ACRES) = 4.14 AREA -AVERAGED FM(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) _ .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 4.14 PEAK FLOW RATE(CFS) = 9.80 TC(MIN) = 12.71 k :'cdr is 4c ir:'c it � dr is aY it x is it dr is �c is f:4r ir:Y is is irie ic4c it it ic:Y is it dr 4c ic:Y dt k is dr:YYr is :Y ie it it dr:Y icic:Y fr fc is is ir'.c is it Yc is is it is :Y is 4t it it �'c & FLOW PROCESS FROM NODE 32.50 TO NODE 32.60 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 21.0 INCH PIPE IS 15.0 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 5.3 UPSTREAM NODE ELEVATION(FEET) = 1054.25 DOWNSTREAM NODE ELEVATION(FEET) = 1053.00 FLOW LENGTH(FEET) = 230.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 21.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 9.80 TRAVEL TIME(MIN.) _ .72 TC(MIN.) = 13.43 :::::e:::r•l: tic Yt::4::c�c:::Y;r k�r:Y��i.'.•��:r 4r`.c:ti<*it is it is :r :; '.c��:':�::'..•'.: �•�'�#:c��:r�•ic:Yi:ic :Y�ie is 4: Yr:'c �•����:r is :c&:rh FLOW PROCESS FROM NODE 32.60 TO NODE 32.60 IS CODE _ 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.617 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 1.59 SUBAREA RUNOFF(CFS) = 3.64 EFFECTIVE AREA(ACRES) = 5.73 AREA -AVERAGED FM(INCH/HR) _ .07 AREA -AVERAGED Fp(INCH/HR) _ .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) = 5.73 PEAK FLOW RATE(CFS) = 13.11 TC(MIN) = 13.43 Page 7 kirkkkkkitkkkkkkkkkiskiekkirkk$tkkkkkkkkkirkirkkkkkkkkkkiekkiekiekkkkkkickisitkkkiticirkkkirkk FLOW PROCESS FROM NODE 32.60 TO NODE 32.70 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 24.0 INCH PIPE IS 17.3 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 5.4 UPSTREAM NODE ELEVATION(FEET) = 1053.00 DOWNSTREAM NODE ELEVATION(FEET) = 1052.30 FLOW LENGTH(FEET) = 150.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 24.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 13.11 TRAVEL TIME(MIN.) _ .46 TC(MIN.) = 13.89 kkkirk ickkkkkkkkk'.: kirk kkkkkkkkkkk �•kirkkkkit irk ki; ick irkkk kirk icki:k kkkkkkit iekkkkkit k'.•kkkkk FLOW PROCESS FROM NODE 32.70 TO NODE 32.70 IS CODE = 8 ---------------------------------------------------------------------------- »»>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW««< 5 YEAR RAINFALL INTENSITY(INCH/HR) = 2.564 ------------- SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA AREA(ACRES) = 2.82 SUBAREA RUNOFF(CFS) = 6.32 EFFECTIVE AREA(ACRES) = 8.55 AREA -AVERAGED FM(INCH/HR) _ .08 AREA -AVERAGED Fp(INCH/HR) _ .75 AREA -AVERAGED Ap = .10 TOTAL AREA(ACRES) 8.55 PEAK FLOW RATE(CFS) = 19.16 TC(MIN) = 13.89 kkkkitkkitkkkkitkkkkk�•kkkkkkkkki:kick•kkkitkkkickkkkirkkkkkkkkkkickk�•kkickkicitkkkkickicsYk FLOW PROCESS FROM NODE 32.70 TO NODE 32.00 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 27.0 INCH PIPE IS 20.0 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 6.1 UPSTREAM NODE ELEVATION(FEET) = 1052.30 DOWNSTREAM NODE ELEVATION(FEET) = 1052.00 FLOW LENGTH(FEET) = 60.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 27.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 19.16 TRAVEL TIME(MIN.) _ .16 TC(MIN.) = 14.06 ...,kkkYckkki;ki;kkic iskkkki�k ickkkkkkkkkkkkic is i;kkkkkkkki�kkkkick kickkkkkkkkkkkkkkir kk iskkk FLOW PROCESS FROM NODE 32.00 TO NODE 32.00 IS CODE = 1 »»>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< »»>AND COMPUTE VARIOUS CONFLUENCED STREAM VALUES««< TOTAL NUMBER OF STREAMS = 2 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 2 ARE: TIME OF CONCENTRATION(MIN.) = 14.06 RAINFALL INTENSITY(INCH/HR) = 2.55 AREA -AVERAGED Fm(INCH/HR) = .08 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .10 EFFECTIVE STREAM AREA(ACRES) = 8.55 TOTAL STREAM AREA(ACRES) = 8.55 PEAK FLOW RATE(CFS) AT CONFLUENCE = 19.16 Page 8 RAINFALL INTENSITY AND TIME OF CONCENTRATION RATIO CONFLUENCE FORMULA USED FOR 2 STREAMS. PEAK FLOW RATE TABLE ** Q Tc Intensit (CFS) (MIN.) (INCH/HR� Fp Ap (INCH/HR) FM (INCH/HR) Ae (ACRES) 1 71.61 20.69 2.019 2 .75 .10 .08 40.83 67.98 14.06 2.546 .75 .10 .08 30.48 COMPUTED CONFLUENCE ESTIMATES ARE AS FOLLOWS: PEAK FLOW RATE(CFS) = 71.61 TC(MIN.) = 20.693 EFFECTIVE AREA(ACRES) = 40.83 AREA -AVERAGED FM(INCH/HR) _ AREA -AVERAGED Fp(INCH/HR) _ .75 AREA -AVERAGED Ap = .10 .08 TOTAL AREA(ACRES) = 40.83 END OF STUDY SUMMARY: TOTAL AREA(ACRES) = 40.83 TC(MIN.) = 20.69 EFFECTIVE AREA(ACRES) = 40.83 AREA -AVERAGED FM(INCH/HR)= .08 AREA -AVERAGED Fp(INCH/HR) _ .75 AREA -AVERAGED Ap = .10 PEAK FLOW RATE(CFS) = 71.61 PEAK FLOW RATE TABLE ** Q Tc Intensit (CFS) (MIN.) (INCH/HR} Fp Ap (INCH/HR) FM (INCH/HR) Ae (ACRES) 1 67.98 14.06 2.546 2 .75 .10 .08 30.48 71.61 20.69 2.019 .75 .10 .08 40.83 END OF RATIONAL METHOD ANALYSIS Page 9 Technical Appendix F Hydrology Map Reproduced from Preliminary Hydrology & Hydraulic Calculations for Sierra Business Park Huitt-Zollars, Inc — November 1, 2003 Technical Appendix G 100-Year Rational Method Analysis Derived from Storm Drain Basis of Design Sycamore Hills II Tentative Tract No. 16495 RBF Consulting — February 2004 it is ie it it it is it it is ie i�ir �Y it it it ie ie is is it it ie is ie it it ie is is ie it it it is it it is it it ie sY it it ie ie is ie is it it it is is i:*ic it is is ie ie it is it it ie ie it it it sY it is ie RATIONAL METHOD HYDROLOGY COMPUTER PROGRAM PACKAGE (Reference: 1986 SAN BERNARDINO CO. HYDROLOGY CRITERION) (c) Copyright 1983-93 Advanced Engineering Software (aes) ver. 1.9B Release Date: 7/18/93 License ID 1202 Analysis prepared by: HUITT-ZOLLARS, INC. 15101 RED HILL AVENUE TUSTIN, CALIFORNIA 92780-6500 PHONE (714) 259-7900 * FAX (714) 259-0210 --------------------------------------------------------- FILE NAME: F100AULB.DAT TIME/DATE OF STUDY: 11:20 5/ 3/2004 USER SPECIFIED HYDROLOGY AND HYDRAULIC MODEL INFORMATION: --*TIME-OF-CONCENTRATION MODEL* -- USER SPECIFIED STORM EVENT(YEAR) = 100.00 SPECIFIED MINIMUM PIPE SIZE(INCH) = 18.00 SPECIFIED PERCENT OF GRADIENTS (DECIMAL) TO USE FOR FRICTION SLOPE = .90 *USE R-DEFINED LOGARITHMIC INTERPOLATION USED FOR RAINFALL* 10-YEAR STORM 60-MINUTE INTENSITY(INCH/HOUR) _ .920 100-YEAR STORM 60-MINUTE INTENSITY(INCH/HOUR) = 1.330 COMPUTED RAINFALL INTENSITY DATA: STORM EVENT = 100.00 1-HOUR INTENSITY(INCH/HOUR) = 1.3300 SLOPE OF INTENSITYDURATION CURVE = .6000 *;Yi:iri.•iri..i..*.•,.icic*ic*iriri.•*isic***i:*isi;ic*****.*ieieiciciriri:*iri:icic**isiririciririci:**itir°ki.•i:**ici:.i;ic*i:ir**ir FLOW PROCESS FROM NODE 300.70 TO NODE 300.60 IS CODE = 2.1 ---------------------------------------------------------------------------- >>>>>RATIONAL METHOD INITIAL SUBAREA ANALYSIS««< DEVELOPMENT IS COMMERCIAL TC = K*[(LENGTH** 3.00)/(ELEVATION CHANGE)]** .20 INITIAL SUBAREA FLOW-LENGTH(FEET) = 85.00 UPSTREAM ELEVATION(FEET) = 1066.50 DOWNSTREAM ELEVATION(FEET) = 1066.00 ELEVATION DIFFERENCE(FEET) = .50 TC(MIN.) = .304*[( 85.00** 3.00)/( .50)]** .20 = 5.020 100 YEAR RAINFALL INTENSITY(INCH/HR) = 5.893 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, Fm(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA RUNOFF(CFS) _ .47 TOTAL AREA(ACRES) = .09 PEAK FLOW RATE(CFS) _ .47 ., is is*i: it :,•ic ie i; :: �•*i; is* ie it is is i:****i;ir*isic***i:ir**i:i:iei:ica•*i:ir�•**ic it r•ir�:ir*ic;:ir�•ir it is *ir is it :Y it s: it*i: i; is FLOW PROCESS FROM NODE 300.60 TO NODE 300.10 IS CODE 6 ------------------------------------------------------ >>>COMPUTE STREET FLOW TRAVEL TIME THRU SUBAREA««< UPSTREAM ELEVATION(FEET) = 1066.00 DOWNSTREAM ELEVATION(FEET) = 1053.27 STREET LENGTH(FEET) = 600.00 CURB HEIGHT(INCHES) = 8. STREET HALFWIDTH(FEET) = 20.00 DISTANCE FROM CROWN TO CROSSFALL GRADEBREAK(FEET) = 15.00 Page 1 INTERIOR STREET CROSSFALL(DECIMAL) = .020 OUTSIDE STREET CROSSFALL(DECIMAL) = .020 SPECIFIED NUMBER OF HALFSTREETS CARRYING RUNOFF = 1 "TRAVEL TIME COMPUTED USING MEAN FLOW(CFS) = 4.50 STREET FLOW MODEL RESULTS: STREET FLOW DEPTH(FEET) _ .37 HALFSTREET FLOOD WIDTH(FEET) = 10.72 AVERAGE FLOW VELOCITY(FEET/SEC.) = 3.36 PRODUCT OF DEPTH&VELOCITY = 1.25 STREET FLOW TRAVEL TIME(MIN.) = 2.97 TC(MIN.) = 7.99 100 YEAR RAINFALL INTENSITY(INCH/HR) = 4.457 SOIL CLASSIFICATION IS "B" RESIDENTIAL-> 8-10 DWELLINGS/ACRE SUBAREA LOSS RATE, Fm(INCH/HR) = .3000 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .40 SUBAREA AREA(ACRES) = 2.10 SUBAREA RUNOFF(CFS) = 7.86 EFFECTIVE AREA(ACRES) = 2.19 AREA -AVERAGED Fm(INCH/HR) _ .29 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .39 TOTAL AREA(ACRES) = 2.19 PEAK FLOW RATE(CFS) = 8.21 END OF SUBAREA STREET FLOW HYDRAULICS: DEPTH(FEET) = .43 HALFSTREET FLOOD WIDTH(FEET) = 13.53 FLOW VELOCITY(FEET/SEC.) = 4.06 DEPTH"VELOCITY = 1.74 it�•k irkkkkkitkkkkkkkkkkkkkkkkir irkkkkkkkkkkkkkk"it k irkkirkkkkkk-kkR•kkkkirk kitkkkkkkkkkk FLOW PROCESS FROM NODE 300.10 TO NODE 300.00 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< ESTIMATED PIPE DIAMETER(INCH) INCREASED TO 18.000 DEPTH OF FLOW IN 18.0 INCH PIPE IS 4.9 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 21.2 UPSTREAM NODE ELEVATION(FEET) = 1053.27 DOWNSTREAM NODE ELEVATION(FEET) = 1047.75 FLOW LENGTH(FEET) = 21.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 18.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 8.21 TRAVEL TIME(MIN.) _ .02 TC(MIN.) = 8.01 irkkkkkir irk kkkkkitkkkkkkkkkitkkkkirkkkkkkk#kkitkkkick k�k kicirk kkkkitkkkkkickkkkkkkkkkkkk FLOW PROCESS FROM NODE 300.00 TO NODE 300.00 IS CODE = 1 ---------------------------------------------------------------------------- »»>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< TOTAL NUMBER OF STREAMS = 3 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 1 ARE: TIME OF CONCENTRATION(MIN.) = 8.01 RAINFALL INTENSITY(INCH/HR) = 4.45 AREA -AVERAGED Fm(INCH/HR) = .29 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .39 EFFECTIVE STREAM AREA(ACRES) = 2.19 TOTAL STREAM AREA(ACRES) = 2.19 PEAK FLOW RATE(CFS) AT CONFLUENCE = 8.21 .. kkkkkkkkkickkkitkkiti.•kkkickkkkkkkkkkkkiekirkkkkitkkkkkkkkkkkkkirkkkkkkkkkkkkkickkkkk FLOW PROCESS FROM NODE 300.50 TO NODE 300.40 IS CODE = 2.1 ---------------------------------------------------------------------------- »»>RATIONAL METHOD INITIAL SUBAREA ANALYSIS««< Page 2 DEVELOPMENT IS SINGLE FAMILY RESIDENTIAL -> 5-7 DWELLINGS/ACRE TC = K*[(LENGTH** 3.00)/(ELEVATION CHANGE)]** .20 INITIAL SUBAREA FLOW-LENGTH(FEET) = 154.00 UPSTREAM ELEVATION(FEET) = 1062.90 DOWNSTREAM ELEVATION(FEET) = 1060.80 ELEVATION DIFFERENCE(FEET) = 2.10 TC(MIN.) = .389*[( 154.001t* 3.00)/( 2.10)]** .20 = 6.887 100 YEAR RAINFALL INTENSITY(INCH/HR) = 4.875 SOIL CLASSIFICATION IS "B" RESIDENTIAL-> 5-7 DWELLINGS/ACRE SUBAREA LOSS RATE, FM(INCH/HR) = .3750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) _ .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .50 SUBAREA RUNOFF(CFS) _ .93 TOTAL AREA(ACRES) = .23 PEAK FLOW RATE(CFS) _ .93 it it is it it*ie it it it it �Y it it icir iric it it it it it it ir*ic it it ie it it it ie is is is it it it it it is ie is*ie it ie**it is ie it it is it it is is it it is ie it it it is it it ie is it ir* FLOW PROCESS FROM NODE 300.40 TO NODE 300.30 IS CODE = 6 ---------------------------------------- »»>COMPUTE STREET FLOW TRAVEL TIME THRU SUBAREA««< UPSTREAM ELEVATION(FEET) = 1060.80 DOWNSTREAM ELEVATION(FEET) = 1053.85 STREET LENGTH(FEET) = 143.00 CURB HEIGHT(INCHES) = 8. STREET HALFWIDTH(FEET) = 20.00 DISTANCE FROM CROWN TO CROSSFALL GRADEBREAK(FEET) = 15.00 INTERIOR STREET CROSSFALL(DECIMAL) = .020 OUTSIDE STREET CROSSFALL(DECIMAL) = .020 SPECIFIED NUMBER OF HALFSTREETS CARRYING RUNOFF = 1 **TRAVEL TIME COMPUTED USING MEAN FLOW(CFS) = 2.98 STREET FLOW MODEL RESULTS: STREET FLOW DEPTH(FEET) _ .29 HALFSTREET FLOOD WIDTH(FEET) = 6.78 AVERAGE FLOW VELOCITY(FEET/SEC.) = 4.58 PRODUCT OF DEPTH&VELOCITY = 1.35 STREET FLOW TRAVEL TIME(MIN.) = .52 TC(MIN.) = 7.41 100 YEAR RAINFALL INTENSITY(INCH/HR) = 4.666 SOIL CLASSIFICATION IS "B" RESIDENTIAL-> 8-10 DWELLINGS/ACRE SUBAREA LOSS RATE, FM(INCH/HR) = .3000 SUBAREA PERVIOUS LOSS RATE, FP(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .40 SUBAREA AREA(ACRES) = 1.04 SUBAREA RUNOFF(CFS) = 4.09 EFFECTIVE AREA(ACRES) = 1.27 AREA -AVERAGED FM(INCH/HR) _ .31 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .42 TOTAL AREA(ACRES) = 1.27 PEAK FLOW RATE(CFS) = 4.98 END OF SUBAREA STREET FLOW HYDRAULICS: DEPTH(FEET) = .34 HALFSTREET FLOOD WIDTH(FEET) = 9.03 FLOW VELOCITY(FEET/SEC.) = 4.95 DEPTH*VELOCITY = 1.68 it it �-ic*ir it it it i.•ic*ic it it it it *ir is is irk**ir ir*iris*�..•ic k it is is it it it *it :r it �•': it ie*i: it it*:.•ir ic:r it is it *sY is ie it it *it ie it is it it it it it FLOW PROCESS FROM NODE 300.30 TO NODE 300.00 IS CODE = 3 ---------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< ESTIMATED PIPE DIAMETER(INCH) INCREASED TO 18.000 DEPTH OF FLOW IN 18.0 INCH PIPE IS 6.0 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 9.7 UPSTREAM NODE ELEVATION(FEET) = 1053.85 DOWNSTREAM NODE ELEVATION(FEET) = 1047.75 Page 3 FLOW LENGTH(FEET) = 138.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 18.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 4.98 TRAVEL TIME(MIN.) _ .24 TC(MIN.) = 7.64 is is is is*ic it is is is is it is is is is it ie it it is it is is ie is ie it it it it*ie it ie it ie it it it is �'r it is is it is is is it is it is ie it is it is it it is it irie is it is it it is is is is it it it FLOW PROCESS FROM NODE 300.00 TO NODE 300.00 IS CODE = 1 ---------------------------------------------------------------------------- »»>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< TOTAL NUMBER OF STREAMS = 3 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 2 ARE: TIME OF CONCENTRATION(MIN.) = 7.64 RAINFALL INTENSITY(INCH/HR) = 4.58 AREA -AVERAGED FM(INCH/HR) = .31 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .42 EFFECTIVE STREAM AREA(ACRES) = 1.27 TOTAL STREAM AREA(ACRES) = 1.27 PEAK FLOW RATE(CFS) AT CONFLUENCE = 4.98 is*#ir icsY it ie it is is it icit ie it is it ie ie&icic k is is is it it**ic it ir. ie is is ie is ie it it is it*i<*ir it is is it*ir is ie is is it is it is is it *irYc it it is it is is is ie it FLOW PROCESS FROM NODE 300.90 TO NODE 300.80 IS CODE = 2.1 ---------------------------------------------------------------------------- »»>RATIONAL METHOD INITIAL SUBAREA ANALYSIS««< DEVELOPMENT IS SINGLE FAMILY RESIDENTIAL -> 5-7 DWELLINGS/ACRE TC = K*[(LENGTH** 3.00)/(ELEVATION CHANGE)]** .20 INITIAL SUBAREA FLOW-LENGTH(FEET) = 145.00 UPSTREAM ELEVATION(FEET) = 1062.90 DOWNSTREAM ELEVATION(FEET) = 1060.76 ELEVATION DIFFERENCE(FEET) = 2.14 TC(MIN.) = .389*[( 145.00** 3.00)/( 2.14)]** .20 = 6.617 100 YEAR RAINFALL INTENSITY(INCH/HR) = 4.993 SOIL CLASSIFICATION IS "B" RESIDENTIAL-> 5-7 DWELLINGS/ACRE SUBAREA LOSS RATE, FM(INCH/HR) = .3750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) _ .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .50 SUBAREA RUNOFF(CFS) _ .96 TOTAL AREA(ACRES) = .23 PEAK FLOW RATE(CFS) _ .96 iric is is is is is is is icir:c-k*ic*ic it**ir it it is**ir is is it ir•'k it is it is it it is it*ic it is*4r fr is it it it it is is it it is �•ic 4r is ieir��.c *'k**ir it it*it'.c* FLOW PROCESS FROM NODE 300.80 TO NODE 300.20 IS CODE = 6 ---------------------------------------------------------------------------- »»>COMPUTE STREET FLOW TRAVEL TIME THRU SUBAREA««< UPSTREAM ELEVATION(FEET) = 1060.76 DOWNSTREAM ELEVATION(FEET) =1053.25 STREET LENGTH(FEET) = 270.00 CURB HEIGHT(INCHES) = 8. STREET HALFWIDTH(FEET) = 20.00 DISTANCE FROM CROWN TO CROSSFALL GRADEBREAK(FEET) = 15.00 INTERIOR STREET CROSSFALL(DECIMAL) = .020 OUTSIDE STREET CROSSFALL(DECIMAL) = .020 SPECIFIED NUMBER OF HALFSTREETS CARRYING RUNOFF = 1 **TRAVEL TIME COMPUTED USING MEAN FLOW(CFS) 3.72 STREET FLOW MODEL RESULTS: STREET FLOW DEPTH(FEET) _ .34 HALFSTREET FLOOD WIDTH(FEET) = 9.03 AVERAGE FLOW VELOCITY(FEET/SEC.) = 3.70 PRODUCT OF DEPTH&VELOCITY = 1.25 Page 4 STREET FLOW TRAVEL TIME(MIN.) = 1.22 TC(MIN.) = 7.83 100 YEAR RAINFALL INTENSITY(INCH/HR) = 4.512 SOIL CLASSIFICATION IS "B" RESIDENTIAL-> 8-10 DWELLINGS/ACRE SUBAREA LOSS RATE, FM(INCH/HR) = .3000 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .40 SUBAREA AREA(ACRES) = 1.45 SUBAREA RUNOFF(CFS) = 5.50 EFFECTIVE AREA(ACRES) = 1.68 AREA -AVERAGED FM(INCH/HR) _ .31 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .41 TOTAL AREA(ACRES) = 1.68 PEAK FLOW RATE(CFS) = 6.35 END OF SUBAREA STREET FLOW HYDRAULICS: DEPTH(FEET) = .38 HALFSTREET FLOOD WIDTH(FEET) = 11.28 FLOW VELOCITY(FEET/SEC.) = 4.35 DEPTH*VELOCITY = 1.67 ie it it :Y'cir i::r 4r it it 4r i; i; it it :t ie 4r 4: ie Yr * is it it it 4t it 4c it it Ye * is ie is Ar * 4r it �t i; :t ie it is sY ie �Y is it 4t it it it ie 4e �Y irYeir it it# it it ie it it irYr it is it ie FLOW PROCESS FROM NODE 300.20 TO NODE 300.00 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< ESTIMATED PIPE DIAMETER(INCH) INCREASED TO 18.000 DEPTH OF FLOW IN 18.0 INCH PIPE IS 4.7 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 17.3 UPSTREAM NODE ELEVATION(FEET) = 1053.25 DOWNSTREAM NODE ELEVATION(FEET) = 1047.75 FLOW LENGTH(FEET) = 30.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 18.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 6.35 TRAVEL TIME(MIN.) _ .03 TC(MIN.) = 7.86 'u �'e it*'x it k sY sY fc*fit �Y 4r x' *�Y 4t fS is it 4r it it it 4t Yt ie k 4c 4r it i; dr dt it it 4t ft �'t it 4r it is sY fr nY*ir 4t is it**it it**it it 9r itir ie it ie it it 4t k �;*i: is sY 4t FLOW PROCESS FROM NODE 300.00 TO NODE 300.00 IS CODE = 1 >>>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< »»>AND COMPUTE VARIOUS CONFLUENCED STREAM VALUES««< -------------------- - TOTAL NUMBER OF STREAMS = 3 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 3 ARE: TIME OF CONCENTRATION(MIN.) = 7.86 RAINFALL INTENSITY(INCH/HR) = 4.50 AREA -AVERAGED FM(INCH/HR) = .31 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .41 EFFECTIVE STREAM AREA(ACRES) = 1.68 TOTAL STREAM AREA(ACRES) = 1.68 PEAK FLOW RATE(CFS) AT CONFLUENCE = 6.35 RAINFALL INTENSITY AND TIME OF CONCENTRATION RATIO CONFLUENCE FORMULA USED FOR 3 STREAMS. *�P PEAK FLOW RATE TABLE ** Q Tc Intensit Fp Ap Fm Ae (CFS) (MIN.) (INCH/HR� (INCH/HR) (INCH/HR) (ACRES) 1 19.34 7.64 4.579 .75 .40 .30 4.99 2 19.32 8.01 4.452 .75 .40 .30 5.14 3 19.40 7.86 4.502 .75 .40 .30 5.10 COMPUTED CONFLUENCE ESTIMATES ARE AS FOLLOWS: PEAK FLOW RATE(CFS) = 19.40 TC(MIN.) = 7.862 EFFECTIVE AREA(ACRES) = 5.10 AREA -AVERAGED FM(INCH/HR) _ AREA -AVERAGED Fp(INCH/HR) _ .75 AREA -AVERAGED Ap = .40 TOTAL AREA(ACRES) = 5.14 Page 5 .30 it is sY it is is it ie ie it it it it it it it is is it is it it ie ie ic*i�i�it it it it it is it is it it it is ie ie is it is it it ie is ie ie it it is it ie it it it it it iricit ie it ie is it is it ie ie is is is FLOW PROCESS FROM NODE 300.00 TO NODE 301.00 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< -------------------------------------------------------------------- DEPTH OF FLOW IN 30.0 INCH PIPE IS 20.1 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 5.6 UPSTREAM NODE ELEVATION(FEET) = 1047.75 DOWNSTREAM NODE ELEVATION(FEET) = 1045.88 FLOW LENGTH(FEET) = 467.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 30.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 19.40 TRAVEL TIME(MIN.) = 1.40 TC(MIN.) = 9.26 it it it irir:Y*ir*:e ie is ie ie it it is is it it is it it icir it is ie it fir is ie it is*ir it it it it it is ie is ie it ie sY is is is is ie it it is it is is *sY it *ir is it ie it is it it it is is is FLOW PROCESS FROM NODE 301.00 TO NODE 301.00 IS CODE = 1 ---------------------------------------------------------------------------- »»>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< ------------------------------------------------------------- TOTAL NUMBER OF STREAMS = 3 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 1 ARE: TIME OF CONCENTRATION(MIN.) = 9.26 RAINFALL INTENSITY(INCH/HR) = 4.08 AREA -AVERAGED FM(INCH/HR) = .30 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .40 EFFECTIVE STREAM AREA(ACRES) = 5.10 TOTAL STREAM AREA(ACRES) = 5.14 PEAK FLOW RATE(CFS) AT CONFLUENCE = 19.40 *ir is it it is it is*i: �•*ic oY it**it is it is is it is*ic fr is it is is it it it it*it ie it it is it it is is is ie it ie it is it ir.**ic is it*ir is is it it it it it *ir*ic it it it it it FLOW PROCESS FROM NODE 301.60 TO NODE 301.50 IS CODE = 2.1 ---------------------------------------------------------------------------- »»>RATIONAL METHOD INITIAL SUBAREA ANALYSIS««< - - - - - - - ------------------------------ DEVELOPMENT IS SINGLE FAMILY RESIDENTIAL -> 5-7 DWELLINGS/ACRE TC = K*[(LENGTH** 3.00)/(ELEVATION CHANGE)]** .20 INITIAL SUBAREA FLOW-LENGTH(FEET) = 123.00 UPSTREAM ELEVATION(FEET) = 1062.10 DOWNSTREAM ELEVATION(FEET) = 1060.25 ELEVATION DIFFERENCE(FEET) = 1.85 TC(MIN.) = .389*[( 123.00** 3.00)/( 1.85)]** .20 = 6.172 100 YEAR RAINFALL INTENSITY(INCH/HR) = 5.206 SOIL CLASSIFICATION IS "B" RESIDENTIAL-> 5-7 DWELLINGS/ACRE SUBAREA LOSS RATE, FM(INCH/HR) = .3750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) _ .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .50 SUBAREA RUNOFF(CFS) _ .61 TOTAL AREA(ACRES) = .14 PEAK FLOW RATE(CFS) _ .61 is is is 'c it *iris*ir*'.:i:i:ic*iri: it it it it is is it it is**i::: ie ir�ir;Y it i:�•i: is is it it i:ic*iri:ir*ic it it it it sk is*i: it it is it it it it ir*ir it is it is is is FLOW PROCESS FROM NODE 301.50 TO NODE 301.10 IS CODE = 6 ---------------------------------------------------------------------------- »»>COMPUTE STREET FLOW TRAVEL TIME THRU SUBAREA««< ----------------------------- - ----- ------ - - --------------------------------------- UPSTREAM ELEVATION(FEET) = 1060.25 DOWNSTREAM ELEVATION(FEET) = 1052.83 STREET LENGTH(FEET) = 238.00 CURB HEIGHT(INCHES) = 8. STREET HALFWIDTH(FEET) = 20.00 Page 6 DISTANCE FROM CROWN TO CROSSFALL GRADEBREAK(FEET) = 15.00 INTERIOR STREET CROSSFALL(DECIMAL) = .020 OUTSIDE STREET CROSSFALL(DECIMAL) = .020 SPECIFIED NUMBER OF HALFSTREETS CARRYING RUNOFF = 1 "TRAVEL TIME COMPUTED USING MEAN FLOW(CFS) = 1.72 STREET FLOW MODEL RESULTS: STREET FLOW DEPTH(FEET) _ .27 HALFSTREET FLOOD WIDTH(FEET) = 5.66 AVERAGE FLOW VELOCITY(FEET/SEC.) = 3.38 PRODUCT OF DEPTH&VELOCITY = .92 STREET FLOW TRAVEL TIME(MIN.) = 1.17 TC(MIN.) = 7.35 100 YEAR RAINFALL INTENSITY(INCH/HR) = 4.689 SOIL CLASSIFICATION IS "B" RESIDENTIAL-> 8-10 DWELLINGS/ACRE SUBAREA LOSS RATE, FM(INCH/HR) = .3000 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .40 SUBAREA AREA(ACRES) = .56 SUBAREA RUNOFF(CFS) = 2.21 EFFECTIVE AREA(ACRES) _ .70 AREA -AVERAGED FM(INCH/HR) _ .32 AREA -AVERAGED Fp(INCH/HR) _ .75 AREA -AVERAGED Ap = .42 TOTAL AREA(ACRES) = .70 PEAK FLOW RATE(CFS) = 2.76 END OF SUBAREA STREET FLOW HYDRAULICS: DEPTH(FEET) = .31 HALFSTREET FLOOD WIDTH(FEET) = 7.34 FLOW VELOCITY(FEET/SEC.) = 3.78 DEPTH«VELOCITY = 1.15 FLOW PROCESS FROM NODE 301.10 TO NODE 301.00 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< ESTIMATED PIPE DIAMETER(INCH) INCREASED TO 18.000 DEPTH OF FLOW IN 18.0 INCH PIPE IS 3.1 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 13.3 UPSTREAM NODE ELEVATION(FEET) = 1052.83 DOWNSTREAM NODE ELEVATION(FEET) = 1045.88 FLOW LENGTH(FEET) = 40.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 18.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = - 2.76 TRAVEL TIME(MIN.) _ .05 TC(MIN.) = 7.40 FLOW PROCESS FROM NODE 301.00 TO NODE 301.00 IS CODE = 1 ---------------------------------------------------------------------------- »»>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< TOTAL NUMBER OF STREAMS = 3 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 2 ARE: TIME OF CONCENTRATION(MIN.) = 7.40 RAINFALL INTENSITY(INCH/HR) = 4.67 AREA -AVERAGED FM(INCH/HR) = .32 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .42 EFFECTIVE STREAM AREA(ACRES) _ .70 TOTAL STREAM AREA(ACRES) = .70 PEAK FLOW RATE(CFS) AT CONFLUENCE = 2.76 FLOW PROCESS FROM NODE 301.40 TO NODE 301.30 IS CODE = 2.1 ---------------------------------------------------------------------------- Page 7 >>>RATIONAL METHOD INITIAL SUBAREA ANALYSIS««< DEVELOPMENT IS SINGLE FAMILY RESIDENTIAL -> 5-7 DWELLINGS/ACRE TC = K*[(LENGTH** 3.00)/(ELEVATION CHANGE)]** .20 INITIAL SUBAREA FLOW-LENGTH(FEET) = 177.00 UPSTREAM ELEVATION(FEET) = 1062.40 DOWNSTREAM ELEVATION(FEET) = 1060.46 ELEVATION DIFFERENCE(FEET) = 1.94 TC(MIN.) = .389*[( 177.00** 3.00)/( 1.94)]** .20 = 7.606 100 YEAR RAINFALL INTENSITY(INCH/HR) = 4.592 SOIL CLASSIFICATION IS "B" RESIDENTIAL-> 5-7 DWELLINGS/ACRE SUBAREA LOSS RATE, FM(INCH/HR) = .3750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .50 SUBAREA RUNOFF(CFS) = 1.14 TOTAL AREA(ACRES) = .30 PEAK FLOW RATE(CFS) = 1.14 it is*'.ci: ie it it'r it ie is it is it it it is it ie is it is it is it it icic is it it&*ic is is it is is it is it it sY ie it it is ie is it*°k ie is it*ir is it it is is it ie is is it is it it is*ic is FLOW PROCESS FROM NODE 301.30 TO NODE 301.20 Is CODE = 6 ---------------------------------------------------------------------------- »»>COMPUTE STREET FLOW TRAVEL TIME THRU SUBAREA««< UPSTREAM ELEVATION(FEET) = 1060.46 DOWNSTREAM ELEVATION(FEET) = 1052.77 STREET LENGTH(FEET) = 320.00 CURB HEIGHT(INCHES) = 8. STREET HALFWIDTH(FEET) = 20.00 DISTANCE FROM CROWN TO CROSSFALL GRADEBREAK(FEET) = 15.00 INTERIOR STREET CROSSFALL(DECIMAL) = .020 OUTSIDE STREET CROSSFALL(DECIMAL) = .020 SPECIFIED NUMBER OF HALFSTREETS CARRYING RUNOFF = 1 **TRAVEL TIME COMPUTED USING MEAN FLOW(CFS) = 4.78 STREET FLOW MODEL RESULTS: STREET FLOW DEPTH(FEET) _ .37 HALFSTREET FLOOD WIDTH(FEET) = 10.72 AVERAGE FLOW VELOCITY(FEET/SEC.) = 3.57 PRODUCT OF DEPTH&VELOCITY = 1.33 STREET FLOW TRAVEL TIME(MIN.) = 1.49 TC(MIN.) 9.10 100 YEAR RAINFALL INTENSITY(INCH/HR) = 4.124 SOIL CLASSIFICATION IS "B" RESIDENTIAL-> 8-10 DWELLINGS/ACRE SUBAREA LOSS RATE, FM(INCH/HR) = .3000 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .40 SUBAREA AREA(ACRES) = 2.10 SUBAREA RUNOFF(CFS) = 7.23 EFFECTIVE AREA(ACRES) = 2.40 AREA -AVERAGED FM(INCH/HR) _ .31 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .41 TOTAL AREA(ACRES) = 2.40 PEAK FLOW RATE(CFS) = 8.24 END OF SUBAREA STREET FLOW HYDRAULICS: DEPTH(FEET) = .43 HALFSTREET FLOOD WIDTH(FEET) = 13.53 FLOW VELOCITY(FEET/SEC.) = 4.08 DEPTH*VELOCITY = 1.75 i:*it*ir*ir is *xic ic*is it is it it is*.it is o7 ie it is it is it it is*ic is ie is is it ie is ie is is it*ic is is is is*i: ft is is is is is it it is is it ic*it it is*it is it it ;;*i: FLOW PROCESS FROM NODE 301.20 TO NODE 301.00 IS CODE = 3 ---------------------------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< >>>>>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< ESTIMATED PIPE DIAMETER(INCH) INCREASED TO 18.000 DEPTH OF FLOW IN 18.0 INCH PIPE IS 4.9 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 21.0 UPSTREAM NODE ELEVATION(FEET) = 1052.77 Page 8 DOWNSTREAM NODE ELEVATION(FEET) = 1045.88 FLOW LENGTH(FEET) = 27.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 18.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 8.24 TRAVEL TIME(MIN.) _ .02 TC(MIN.) = 9.12 :::e;c�r*:r it 4r i:'.r 9r it k4r 9r 4r is ic:c it �r kic 4r i:k'e:e�:Yr'.r Yr is is it it is is ie 4c is �c 4r it it ir:�ir it it it it ie 4r it Yr�k it 4r it 9e it it it :r it sY is Yr it it it it 4e it FLOW PROCESS FROM NODE 301.00 TO NODE 301.00 IS CODE = 1 »»>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< »»>AND COMPUTE VARIOUS CONFLUENCED STREAM VALUES««< TOTAL NUMBER OF STREAMS = 3 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 3 ARE: TIME OF CONCENTRATION(MIN.) = 9.12 RAINFALL INTENSITY(INCH/HR) = 4.12 AREA -AVERAGED FM(INCH/HR) = .31 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .41 EFFECTIVE STREAM AREA(ACRES) = 2.40 TOTAL STREAM AREA(ACRES) = 2.40 PEAK FLOW RATE(CFS) AT CONFLUENCE = 8.24 RAINFALL INTENSITY AND TIME OF CONCENTRATION RATIO CONFLUENCE FORMULA USED FOR 3 STREAMS. ** PEAK FLOW RATE TABLE ** Q Tc Intensit Fp Ap Fm Ae (CFS) (MIN.) (INCH/H� (INCH/HR) (INCH/HR) (ACRES) 1 28.41 7.40 4.670 .75 .41 .31 6.73 2 29.97 9.04 4.139 .75 .41 .31 8.07 3 29.94 9.26 4.081 .75 .41 .31 8.20 4 29.75 9.41 4.041 .75 .41 .31 8.24 5 30.01 9.12 4.118 .75 .41 .31 8.13 COMPUTED CONFLUENCE ESTIMATES ARE AS FOLLOWS: PEAK FLOW RATE(CFS) = 30.01 TC(MIN.) = 9.121 EFFECTIVE AREA(ACRES) = 8.13 AREA -AVERAGED FM(INCH/HR) _ .31 AREA -AVERAGED Fp(INCH/HR) _ .75 AREA -AVERAGED Ap = .41 TOTAL AREA(ACRES) = 8.24 sY': ?:*ir 4c**'.: »-*. �c it**»•*-k**ir ie*ic**�*4r***ir is �Y**ic �e*****:r****»•*******ic*ir******»•»-*ic***:'r'r* FLOW PROCESS FROM NODE 301.00 TO NODE 302.00 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 33.0 INCH PIPE IS 25.6 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 6.1 UPSTREAM NODE ELEVATION(FEET) = 1045.88 DOWNSTREAM NODE ELEVATION(FEET) = 1043.16 FLOW LENGTH(FEET) = 681.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 33.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 30.01 TRAVEL TIME(MIN.) = 1.87 TC(MIN.) = 10.99 ie it do 4::t�'�:r'rd::Yir*ie 4t sY �Y»•»•:e it it it*it&4t:c 4t 4c ir*9:4c it Yr:t4r'.t it it is it i:*4c it is is it is is is 4r it is �Y is fr»ie it is it 4c it fr ir:Y*4c*:r *4r 4r'.c FLOW PROCESS FROM NODE 302.00 TO NODE 302.00 IS CODE = 1 ---------------------------------------------------------------------------- »»>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< TOTAL NUMBER OF STREAMS = 3 Page 9 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 1 ARE: TIME OF CONCENTRATION(MIN.) = 10.99 RAINFALL INTENSITY(INCH/HR) = 3.68 AREA -AVERAGED FM(INCH/HR) = .31 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .41 EFFECTIVE STREAM AREA(ACRES) = 8.13 TOTAL STREAM AREA(ACRES) = 8.24 PEAK FLOW RATE(CFS) AT CONFLUENCE = 30.01 it ir&ir it it is ie it it it it ie ie it is it ie it it it it*ic ie is it it is is it ie it it ie it it is it it is is it is it ie it ie is is it it it it is is is*ir ie it is ie ie is it it it it it is is ie ie ir* FLOW PROCESS FROM NODE 302.40 TO NODE 302.30 IS CODE = 2.1 ---------------------------------------------------------------------------- >>>RATIONAL METHOD INITIAL SUBAREA ANALYSIS««< DEVELOPMENT IS SINGLE FAMILY RESIDENTIAL -> 5-7 DWELLINGS/ACRE TC = K*[(LENGTH** 3.00)/(ELEVATION CHANGE)]** .20 INITIAL SUBAREA FLOW-LENGTH(FEET) = 128.00 UPSTREAM ELEVATION(FEET) = 1060.20 DOWNSTREAM ELEVATION(FEET) = 1058.41 ELEVATION DIFFERENCE(FEET) = 1.79 TC(MIN.) = .389*[( 128.00** 3.00)/( 1.79)]** .20 = 6.364 100 YEAR RAINFALL INTENSITY(INCH/HR) = 5.111 SOIL CLASSIFICATION IS "B" RESIDENTIAL-> 5-7 DWELLINGS/ACRE SUBAREA LOSS RATE, FM(INCH/HR) = .3750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) _ .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .50 SUBAREA RUNOFF(CFS) _ .64 TOTAL AREA(ACRES) = .15 PEAK FLOW RATE(CFS) _ .64 ..........R•ic*s:i:*ir it'.r'.r*'..*ir'.ri:*�*..***ic�•�:rir:r it is k *'.r *ir is ie':��.. ,, 'r 4r***iris ;,.***:r*::fr ir'.: is *:c**ir***:'. FLOW PROCESS FROM NODE 302.30 TO NODE 302.10 IS CODE = 6 --------------------------------------------------- »»>COMPUTE STREET FLOW TRAVEL TIME THRU SUBAREA««< UPSTREAM ELEVATION(FEET) = 1058.41 DOWNSTREAM ELEVATION(FEET) = 1046.00 STREET LENGTH(FEET) = 619.00 CURB HEIGHT(INCHES) = 8. STREET HALFWIDTH(FEET) = 20.00 DISTANCE FROM CROWN TO CROSSFALL GRADEBREAK(FEET) = 15.00 INTERIOR STREET CROSSFALL(DECIMAL) = .020 OUTSIDE STREET CROSSFALL(DECIMAL) = .020 SPECIFIED NUMBER OF HALFSTREETS CARRYING RUNOFF = 1 **TRAVEL TIME COMPUTED USING MEAN FLOW(CFS) = 3.98 STREET FLOW MODEL RESULTS: STREET FLOW DEPTH(FEET) _ .36 HALFSTREET FLOOD WIDTH(FEET) = 10.16 AVERAGE FLOW VELOCITY(FEET/SEC.) = 3.26 PRODUCT OF DEPTH&VELOCITY = 1.18 STREET FLOW TRAVEL TIME(MIN.) = 3.16 TC(MIN.) = 9.53 100 YEAR RAINFALL INTENSITY(INCH/HR) = 4.012 SOIL CLASSIFICATION IS "B" RESIDENTIAL-> 8-10 DWELLINGS/ACRE SUBAREA LOSS RATE, FM(INCH/HR) = .3000 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .40 SUBAREA AREA(ACRES) = 1.96 SUBAREA RUNOFF(CFS) = 6.55 EFFECTIVE AREA(ACRES) = 2.11 AREA -AVERAGED FM(INCH/HR) _ .31 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .41 TOTAL AREA(ACRES) = 2.11 PEAK FLOW RATE(CFS) = 7.04 END OF SUBAREA STREET FLOW HYDRAULICS: Page 10 DEPTH(FEET) = .42 HALFSTREET FLOOD WIDTH(FEET) = 12.97 FLOW VELOCITY(FEET/SEC.) = 3.76 DEPTH*VELOCITY = 1.57 is is is it is * is is is is is is is it is is is is is it sY it is is * it it is is it it it is irir it it is it it ie it is is is it is ie it ie it ie it it ie ie ie it is iric is * is it is ie ie is ie is is it it is it FLOW PROCESS FROM NODE 302.10 TO NODE 302.00 IS CODE = 3 ---------------------------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< ESTIMATED PIPE DIAMETER(INCH) INCREASED TO 18.000 DEPTH OF FLOW IN 18.0 INCH PIPE IS 7.6 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 10.0 UPSTREAM NODE ELEVATION(FEET) = 1046.00 DOWNSTREAM NODE ELEVATION(FEET) = 1043.16 FLOW LENGTH(FEET) = 78.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 18.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 7.04 TRAVEL TIME(MIN.) _ .13 TC(MIN.) = 9.66 *irir*iciririririririciriritieirir::sY***iriciciricirieic*irirsY***iri:iri:ie****i�i.•irieirir*iciriri:iririciticit**irieiritici:icirieir FLOW PROCESS FROM NODE 302.00 TO NODE 302.00 IS CODE = 1 ---------------------------------------------------------------------------- »»>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< ------------------------------------------------------------------------ TOTAL NUMBER OF STREAMS = 3 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 2 ARE: TIME OF CONCENTRATION(MIN.) = 9.66 RAINFALL INTENSITY(INCH/HR) = 3.98 AREA -AVERAGED FM(INCH/HR) = .31 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .41 EFFECTIVE STREAM AREA(ACRES) = 2.11 TOTAL STREAM AREA(ACRES) = 2.11 PEAK FLOW RATE(CFS) AT CONFLUENCE = 7.04 i:ic*it it is i:itx**�•i:i: it it it it �•-kie*ic is it*ic it ie**ic�ir Yc it it it it it is is*ie*it**ir it it*i.•ie*ir it*ici: is is it it it**�•i: it it'.•ir it is it FLOW PROCESS FROM NODE 302.60 TO NODE 302.50 IS CODE = 2.1 ---------------------------------------------------------------------------- »»>RATIONAL METHOD INITIAL SUBAREA ANALYSIS««< DEVELOPMENT IS SINGLE FAMILY RESIDENTIAL -> 5-7 DWELLINGS/ACRE TC = K*[(LENGTH** 3. 00) /(ELEVATION CHANGE)]"* .20 INITIAL SUBAREA FLOW-LENGTH(FEET) = 176.00 UPSTREAM ELEVATION(FEET) = 1062.60 DOWNSTREAM ELEVATION(FEET) = 1060.75 ELEVATION DIFFERENCE(FEET) = 1.85 TC(MIN.) = .389*[( 176.00** 3.00)/( 1.85)]** .20 = 7.653 100 YEAR RAINFALL INTENSITY(INCH/HR) = 4.576 SOIL CLASSIFICATION IS "B" RESIDENTIAL-> 5-7 DWELLINGS/ACRE SUBAREA LOSS RATE, FM(INCH/HR) = .3750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) _ .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .50 SUBAREA RUNOFF(CFS) _ .98 TOTAL AREA(ACRES) = .26 PEAK FLOW RATE(CFS) _ .98 i:ir*Yi: is it*'.: it ir*ir is*it it it it is is is is*ir it it is it �k it°k ie it it i:ic*it ie ieie*ir sY*ir it sY it is is*ic*ir it is is*�•ir*i: it is is is*i: *ick it *ir FLOW PROCESS FROM NODE 302.50 TO NODE 302.20 IS CODE = 6 ---------------------------------------------------------------------------- »»>COMPUTE STREET FLOW TRAVEL TIME THRU SUBAREA««< UPSTREAM ELEVATION(FEET) = 1060.75 DOWNSTREAM ELEVATION(FEET) = 1046.24 Page 11 STREET LENGTH(FEET) = 959.00 CURB HEIGHT(INCHES) = 8. STREET HALFWIDTH(FEET) = 20.00 DISTANCE FROM CROWN TO CROSSFALL GRADEBREAK(FEET) = 15.00 INTERIOR STREET CROSSFALL(DECIMAL) = .020 OUTSIDE STREET CROSSFALL(DECIMAL) = .020 SPECIFIED NUMBER OF HALFSTREETS CARRYING RUNOFF = 1 "TRAVEL TIME COMPUTED USING MEAN FLOW(CFS) = 5.68 STREET FLOW MODEL RESULTS: STREET FLOW DEPTH(FEET) _ .41 HALFSTREET FLOOD WIDTH(FEET) = 12.41 AVERAGE FLOW VELOCITY(FEET/SEC.) = 3.28 PRODUCT OF DEPTH&VELOCITY = 1.33 STREET FLOW TRAVEL TIME(MIN.) = 4.87 TC(MIN.) = 12.52 100 YEAR RAINFALL INTENSITY(INCH/HR) = 3.405 SOIL CLASSIFICATION IS "B" RESIDENTIAL-> 8-10 DWELLINGS/ACRE SUBAREA LOSS RATE, FM(INCH/HR) = .3000 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .40 SUBAREA AREA(ACRES) = 3.34 SUBAREA RUNOFF(CFS) = 9.33 EFFECTIVE AREA(ACRES) = 3.60 AREA -AVERAGED FM(INCH/HR) _ .31 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .41 TOTAL AREA(ACRES) = 3.60 PEAK FLOW RATE(CFS) = 10.04 END OF SUBAREA STREET FLOW HYDRAULICS: DEPTH(FEET) = .47 HALFSTREET FLOOD WIDTH(FEET) = 15.78 FLOW VELOCITY(FEET/SEC.) = 3.75 DEPTH*VELOCITY = 1.78 k'.:�ic:t ;t��� �-t: ie 4r dt i::c�i.•�4t 4e �: it ie'.r4r it 4t is is ie ie irirdr:ie*Yc it Yr sY is kir �°k'..•ir �r:Yi:��s"'a��•ic it ic'.:.:r&ir#:c :: is :::r is i:��': FLOW PROCESS FROM NODE 302.20 TO NODE 302.00 IS CODE = 3 ---------------------------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< ESTIMATED PIPE DIAMETER(INCH) INCREASED TO 18.000 DEPTH OF FLOW IN 18.0 INCH PIPE IS 6.9 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 16.0 UPSTREAM NODE ELEVATION(FEET) = 1046.24 DOWNSTREAM NODE ELEVATION(FEET) = 1043..16 FLOW LENGTH(FEET) = 30.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 18.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 10.04 TRAVEL TIME(MIN.) _ .03 TC(MIN.) = 12.55 s:�; ;;�::�:�:;�:::��:::�e'..•': �':rY:'.t:;�:�: �•�:'..•:r4ci:����:c��•�: k� � �-ie�•����drk�4r&k&iric',�*�Yeici:�ir4: �frieY:�*:�::�:�r FLOW PROCESS FROM NODE 302.00 TO NODE 302.00 IS CODE = 1 --------------------------------------- »»>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< »»>AND COMPUTE VARIOUS CONFLUENCED STREAM VALUES««< ------------------------------------------------------------------------ TOTAL NUMBER OF STREAMS = 3 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 3 ARE: TIME OF CONCENTRATION(MIN.) = 12.55 RAINFALL INTENSITY(INCH/HR) = 3.40 AREA -AVERAGED FM(INCH/HR) = .31 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .41 EFFECTIVE STREAM AREA(ACRES) = 3.60 TOTAL STREAM AREA(ACRES) = 3.60 PEAK FLOW RATE(CFS) AT CONFLUENCE = 10.04 Page 12 RAINFALL INTENSITY AND TIME OF CONCENTRATION RATIO CONFLUENCE FORMULA USED FOR 3 STREAMS. ** PEAK FLOW RATE TABLE ** Q Tc Intensit Fp Ap Fm Ae (CFS) (MIN.) (INCH/HR� (INCH/HR) (INCH/HR) (ACRES) 1 44.39 9.28 4.077 .75 .41 .31 11.42 2 44.99 9.66 3.979 .75 .41 .31 11.92 3 46.05 10.91 3.698 .75 .41 .31 13.31 4 46.07 10.99 3.682 .75 .41 .31 13.39 5 45.99 11.13 3.654 .75 .41 .31 13.50 6 45.79 11.28 3.625 .75 .41 .31 13.59 7 43.71 12.55 3.400 .75 .41 .31 13.95 COMPUTED CONFLUENCE ESTIMATES ARE AS FOLLOWS: PEAK FLOW RATE(CFS) = 46.07 TC(MIN.) = 10.990 EFFECTIVE AREA(ACRES) = 13.39 AREA -AVERAGED Fm(INCH/HR) _ .31 AREA -AVERAGED Fp(INCH/HR) _ .75 AREA -AVERAGED Ap = .41 TOTAL AREA(ACRES) = 13.95 4r:r•.r it it �c it is Ar i; it 4�4r*ir sY 4: 4r 4r dr dr is ie it it i; it dr it �r:r it i; it it it it it sY fr is 4r it it**°k iric*4c ir.*:e ft it it 4r ic•.r it 4c ic*4; iv 4r is it it*ir 4r :e fr :r FLOW PROCESS FROM NODE 302.00 TO NODE 303.00 IS CODE = 3 >>>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 39.0 INCH PIPE IS 29.7 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 6.8 UPSTREAM NODE ELEVATION(FEET) = 1043.16 DOWNSTREAM NODE ELEVATION(FEET) = 1042.19 FLOW LENGTH(FEET) = 242.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 39.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 46.07 TRAVEL TIME(MIN.) _ .59 TC(MIN.) = 11.58 i:'r':r:�•*4r'.r*:t'..•::*.**�•�•**ir is*:r*�*ir ic***ir**ir**�•*sY�•4:�'..•i:'.r�:r���•&ic�ic �:: :r :: sY�i; :c :r :ram �•ic �•�kir :r &s: :r FLOW PROCESS FROM NODE 303.00 TO NODE 303.00 IS CODE 1 ---------------------------------------------------------------------------- >>>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< TOTAL NUMBER OF STREAMS = 3 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 1 ARE: TIME OF CONCENTRATION(MIN.) = 11.58 RAINFALL INTENSITY(INCH/HR) = 3.57 AREA -AVERAGED FM(INCH/HR) = .31 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .41 EFFECTIVE STREAM AREA(ACRES) = 13.39 TOTAL STREAM AREA(ACRES) = 13.95 PEAK FLOW RATE(CFS) AT CONFLUENCE = 46.07 �•�:ei:�:�•::;.: 4r 4r*'.; *:!**': *:;'.: it �'r**4; sir sY�*�•°k**4;i;:k sir•.'::rf: �Y��it ��r it ir'.;�•ir'.rk:r'.r is�'.r it �r 4r ic'.r ir��it sY is��•:r •k :'r FLOW PROCESS FROM NODE 303.60 TO NODE 303.50 IS CODE = 2.1 ------------------------------------------ »»>RATIONAL METHOD INITIAL SUBAREA ANALYSIS««< DEVELOPMENT IS SINGLE FAMILY RESIDENTIAL -> 5-7 DWELLINGS/ACRE TC = K*[(LENGTH * 3. 00) /(ELEVATION CHANGE)]** .20 INITIAL SUBAREA FLOW-LENGTH(FEET) = 177.00 UPSTREAM ELEVATION(FEET) = 1055.90 DOWNSTREAM ELEVATION(FEET) = 1054.15 ELEVATION DIFFERENCE(FEET) = 1.75 Page 13 TC(MIN.) = .389*[( 177.00** 3.00)/( 1.75)]** .20 = 7.765 100 YEAR RAINFALL INTENSITY(INCH/HR) = 4.536 SOIL CLASSIFICATION IS "B" RESIDENTIAL-> 5-7 DWELLINGS/ACRE SUBAREA LOSS RATE, FM(INCH/HR) = .3750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .50 SUBAREA RUNOFF(CFS) _ .97 TOTAL AREA(ACRES) = .26 PEAK FLOW RATE(CFS) _ .97 irk-k is it i:kkir k is iskiek kiskkkick ickk kk isk kkkie is is irkkkkit irkkkkickkkirkkickkkkkkic ickkkkkkkir it irk it kic FLOW PROCESS FROM NODE 303.50 TO NODE 303.10 IS CODE = 6 -------------------------------------------- - >>>COMPUTE STREET FLOW TRAVEL TIME THRU SUBAREA««< UPSTREAM ELEVATION(FEET) = 1054.15 DOWNSTREAM ELEVATION(FEET) = 1046.17 STREET LENGTH(FEET) = 359.00 CURB HEIGHT(INCHES) = 8. STREET HALFWIDTH(FEET) = 20.00 DISTANCE FROM CROWN TO CROSSFALL GRADEBREAK(FEET) = 15.00 INTERIOR STREET CROSSFALL(DECIMAL) = .020 OUTSIDE STREET CROSSFALL(DECIMAL) = .020 SPECIFIED NUMBER OF HALFSTREETS CARRYING RUNOFF = 1 **TRAVEL TIME COMPUTED USING MEAN FLOW(CFS) = 3.46 STREET FLOW MODEL RESULTS: STREET FLOW DEPTH(FEET) _ .34 HALFSTREET FLOOD WIDTH(FEET) = 9.03 AVERAGE FLOW VELOCITY(FEET/SEC.) = 3.44 PRODUCT OF DEPTH&VELOCITY = 1.17 STREET FLOW TRAVEL TIME(MIN.) = 1.74 TC(MIN.) = 9.50 100 YEAR RAINFALL INTENSITY(INCH/HR) = 4.018 SOIL CLASSIFICATION IS "B" RESIDENTIAL-> 8-10 DWELLINGS/ACRE SUBAREA LOSS RATE, FM(INCH/HR) = .3000 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .40 SUBAREA AREA(ACRES) = 1.49 SUBAREA RUNOFF(CFS) = 4.99 EFFECTIVE AREA(ACRES) = 1.75 AREA -AVERAGED FM(INCH/HR) _ .31 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .41 TOTAL AREA(ACRES) = 1.75 PEAK FLOW RATE(CFS) = 5.84 END OF SUBAREA STREET FLOW HYDRAULICS: DEPTH(FEET) = .40 HALFSTREET FLOOD WIDTH(FEET) = 11.84 FLOW VELOCITY(FEET/SEC.) = 3.67 DEPTH*VELOCITY = 1.45 k itkkkirkkkick kirkkkkirkkkir irk ick kic*kick kic sYkkkkkkkkkic itk irkkkkkkiekkkk �•�kkkkkirkkiskirkirir* FLOW PROCESS FROM NODE 303.10 TO NODE 303.00 IS CODE = 3 >>>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< ESTIMATED PIPE DIAMETER(INCH) INCREASED TO 18.000 DEPTH OF FLOW IN 18.0 INCH PIPE IS 5.5 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 12.9 UPSTREAM NODE ELEVATION(FEET) = 1046.17 DOWNSTREAM NODE ELEVATION(FEET) = 1042.19 FLOW LENGTH(FEET) = 46.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 18.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 5.84 TRAVEL TIME(MIN.) _ .06 TC(MIN.) = 9.56 k kick irk �•kkkkki: 9rkkkit irk irkkkkkkk �-irk is kir is irk:Y it is 4r:Y ickk kkkitk**ir�'k kic it ick is it is is is i;kkickkkic*kk Page 14 FLOW PROCESS FROM NODE 303.00 TO NODE 303.00 IS CODE = 1 -------------------------------------------------------------- »»>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< TOTAL NUMBER OF STREAMS = 3 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 2 ARE: TIME OF CONCENTRATION(MIN.) = 9.56 RAINFALL INTENSITY(INCH/HR) = 4.00 AREA -AVERAGED FM(INCH/HR) = .31 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .41 EFFECTIVE STREAM AREA(ACRES) = 1.75 TOTAL STREAM AREA(ACRES) = 1.75 PEAK FLOW RATE(CFS) AT CONFLUENCE = 5.84 FLOW PROCESS FROM NODE 303.40 TO NODE 303.30 IS CODE = 2.1 ---------------------------------------------- »»>RATIONAL METHOD INITIAL SUBAREA ANALYSIS««< DEVELOPMENT IS SINGLE FAMILY RESIDENTIAL -> 5-7 DWELLINGS/ACRE TC = K*[(LENGTH** 3.00)/(ELEVATION CHANGE)]** .20 INITIAL SUBAREA FLOW-LENGTH(FEET) = 181.00 UPSTREAM ELEVATION(FEET) = 1056.00 DOWNSTREAM ELEVATION(FEET) = 1054.16 ELEVATION DIFFERENCE(FEET) = 1.84 TC(MIN.) = .389*[( 181.00** 3.00)/( 1.84)]** .20 = 7.791 100 YEAR RAINFALL INTENSITY(INCH/HR) = 4.527 SOIL CLASSIFICATION IS "B" RESIDENTIAL-> 5-7 DWELLINGS/ACRE SUBAREA LOSS RATE, FM(INCH/HR) = .3750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) _ .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .50 SUBAREA RUNOFF(CFS) _ .90 TOTAL AREA(ACRES) = .24 PEAK FLOW RATE(CFS) _ .90 FLOW PROCESS FROM NODE 303.30 TO NODE 303.20 IS CODE = 6 ---------------------------------------------------------------------------- »»>COMPUTE STREET FLOW TRAVEL TIME THRU SUBAREA««< UPSTREAM ELEVATION(FEET) = 1054.16 DOWNSTREAM ELEVATION(FEET) = 1046.00 STREET LENGTH(FEET) = 384.00 CURB HEIGHT(INCHES) = 8. STREET HALFWIDTH(FEET) = 20.00 DISTANCE FROM CROWN TO CROSSFALL GRADEBREAK(FEET) = 15.00 INTERIOR STREET CROSSFALL(DECIMAL) = .020 OUTSIDE STREET CROSSFALL(DECIMAL) = .020 SPECIFIED NUMBER OF HALFSTREETS CARRYING RUNOFF = 1 **TRAVEL TIME COMPUTED USING MEAN FLOW(CFS) = 3.23 STREET FLOW MODEL RESULTS: STREET FLOW DEPTH(FEET) _ .34 HALFSTREET FLOOD WIDTH(FEET) = 9.03 AVERAGE FLOW VELOCITY(FEET/SEC.) = 3.21 PRODUCT OF DEPTH&VELOCITY = 1.09 STREET FLOW TRAVEL TIME(MIN.) = 1.99 TC(MIN.) = 9.78 100 YEAR RAINFALL INTENSITY(INCH/HR) = 3.948 SOIL CLASSIFICATION IS "B" RESIDENTIAL-> 8-10 DWELLINGS/ACRE SUBAREA LOSS RATE, FM(INCH/HR) _ .3000 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .40 Page 15 SUBAREA AREA(ACRES) = 1.42 SUBAREA RUNOFF(CFS) = 4.66 EFFECTIVE AREA(ACRES) = 1.66 AREA -AVERAGED Fm(INCH/HR) _ .31 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .41 TOTAL AREA(ACRES) = 1.66 PEAK FLOW RATE(CFS) = 5.43 END OF SUBAREA STREET FLOW HYDRAULICS: DEPTH(FEET) = .38 HALFSTREET FLOOD WIDTH(FEET) = 11.28 FLOW VELOCITY(FEET/SEC.) = 3.72 DEPTH*VELOCITY = 1.43 4r dr 4r it dr �r is f: it iric 4r 4r it&ir �r it �c it it it �cir 4r �44r it it it do 4e it fr it dr ie ie lr it it it it fr it it it tr it&ir is it 4r it it it �Y is it fr �r it 9c it is it drx &ir it is fc 4r it FLOW PROCESS FROM NODE 303.20 TO NODE 303.00 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< ESTIMATED PIPE DIAMETER(INCH) INCREASED TO 18.000 DEPTH OF FLOW IN 18.0 INCH PIPE IS 5.3 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 12.5 UPSTREAM NODE ELEVATION(FEET) = 1046.00 DOWNSTREAM NODE ELEVATION(FEET) = 1042.19 FLOW LENGTH(FEET) = 46.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 18.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 5.43 TRAVEL TIME(MIN.) = .06 TC(MIN.) = 9.85 it*'r�ir 4r �t'.::Yir�sY s't���•ic�ic it i��4c ir:r it it it ic'�ir is sY 4e it de it ir�ir it ie sY it ir�:r it ie it it is it ir�ir ie ir�'.r it fr it �•�Sr it it Yr it :r ie it k �'c it FLOW PROCESS FROM NODE 303.00 TO NODE 303.00 IS CODE = 1 »»>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< >>>AND COMPUTE VARIOUS CONFLUENCED STREAM VALUES««< ------------------------------------------------------------------------- TOTAL NUMBER OF STREAMS = 3 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 3 ARE: TIME OF CONCENTRATION(MIN.) = 9.85 RAINFALL INTENSITY(INCH/HR) = 3.93 AREA -AVERAGED FM(INCH/HR) = .31 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .41 EFFECTIVE STREAM AREA(ACRES) = 1.66 TOTAL STREAM AREA(ACRES) = 1.66 PEAK FLOW RATE(CFS) AT CONFLUENCE = 5.43 RAINFALL INTENSITY AND TIME OF CONCENTRATION RATIO CONFLUENCE FORMULA USED FOR 3 STREAMS. * PEAK FLOW RATE TABLE ** Q Tc Intens. Fp Ap Fm Ae (CFS) (MIN.) (INCH/HR� (INCH/HR) (INCH/HR) (ACRES) 1 55.12 9.56 4.003 .75 .41 .31 14.42 2 55.54 9.87 3.927 .75 .41 .31 14.83 3 55.86 10.25 3.839 .75 .41 .31 15.33 4 56.13 11.51 3.582 .75 .41 .31 16.72 5 56.11 11.58 3.568 .75 .41 .31 16.80 6 55.95 11.73 3.542 .75 .41 .31 16.91 7 55.66 11.88 3.515 .75 .41 .31 17.00 8 52.94 13.15 3.307 .75 .41 .31 17.36 9 55.52 9.85 3.934 .75 .41 .31 14.79 COMPUTED CONFLUENCE ESTIMATES ARE AS FOLLOWS: PEAK FLOW RATE(CFS) = 56.13 TC(MIN.) = 11.508 EFFECTIVE AREA(ACRES) = 16.72 AREA -AVERAGED FM(INCH/HR) _ .31 AREA -AVERAGED Fp(INCH/HR) _ .75 AREA -AVERAGED Ap = .41 TOTAL AREA(ACRES) = 17.36 Page 16 ie it it it it it ie ie * ie ie it it sY it ie it it ie ie ie is it is it it ie is it ie o4 is it ie ie is is it ie it ie ie is it it �Y it ie is it it is it is it is it it it it is iis it iCiric iric is is ie ie it ie ie FLOW PROCESS FROM NODE 303.00 TO NODE 400.00 ---------------------------------------------------------------------------- IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< -------------------------------------------------------------------- DEPTH OF FLOW IN 42.0 INCH PIPE IS 32.0 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 7.1 UPSTREAM NODE ELEVATION(FEET) = 1042.19 DOWNSTREAM NODE ELEVATION(FEET) = 1041.27 FLOW LENGTH(FEET) = 230.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 42.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 56.13 TRAVEL TIME(MIN.) _ .54 TC(MIN.) = 12.05 --------------------------------------------------------------------- END OF STUDY SUMMARY: TOTAL AREA(ACRES) = 17.36 TC(MIN.) = 12.05 EFFECTIVE AREA(ACRES) = 16.72 AREA -AVERAGED FM(INCH/HR)= .31 AREA -AVERAGED Fp(INCH/HR) _ .75 AREA -AVERAGED Ap = .41 PEAK FLOW RATE(CFS) = 56.13 ** PEAK FLOW RATE TABLE ** Q Tc Intensit FPAp FM Ae (CFS) (MIN.) (INCH/HR� (INCH/HR) (INCH/HR) (ACRES) 1 55.12 10.10 3.874 .75 .41 .31 14.42 2 55.52 10.38 3.810 .75 .41 .31 14.79 3 55.54 10.41 3.804 .75 .41 .31 14.83 4 55.86 10.79 3.723 .75 .41 .31 15.33 5 56.13 12.05 3.485 .75 .41 .31 16.72 6 56.11 12.12 3.472 .75 .41 .31 16.80 7 55.95 12.26 3.448 .75 .41 .31 16.91 8 55.66 12.42 3.423 .75 .41 .31 17.00 9 52.94 13.69 3.227 .75 .41 .31 17.36 END OF RATIONAL METHOD ANALYSIS Page 17 �'r is i:i::r:rir*ic*4r 4r ie �r it it it it Yrir irx do it it 4r ie 4t it it it it it ie 4r it it ie it irsY dr iric it it fr sY it it 9r 9r fr dr 4r 4r 4r it it 4r ie ie it it it it dr 4e ie ie ie it it it it 4r RATIONAL METHOD HYDROLOGY COMPUTER PROGRAM PACKAGE (Reference: 1986 SAN BERNARDINO CO. HYDROLOGY CRITERION) (c) Copyright 1983-93 Advanced Engineering Software (aes) Ver. 1.9B Release Date: 7/18/93 License ID 1202 Analysis prepared by: HUITT-ZOLLARS, INC. 15101 RED HILL AVENUE TUSTIN, CALIFORNIA 92780-6500 PHONE (714) 259-7900 * FAX (714) 259-0210 ---------------------------------------------------------------------------- FILE NAME: F100SRAB.DAT TIME/DATE OF STUDY: 14:27 5/ 3/2004 --------------------------------------------------------------------------- USER SPECIFIED HYDROLOGY AND HYDRAULIC MODEL INFORMATION: ------------------------------------------ --*TIME-OF-CONCENTRATION MODEL* -- USER SPECIFIED STORM EVENT(YEAR) = 100.00 SPECIFIED MINIMUM PIPE SIZE(INCH) = 18.00 SPECIFIED PERCENT OF GRADIENTS (DECIMAL) TO USE FOR FRICTION SLOPE = .90 *USER -DEFINED LOGARITHMIC INTERPOLATION USED FOR RAINFALL* 10-YEAR STORM 60-MINUTE INTENSITY(INCH/HOUR) _ .920 100-YEAR STORM 60-MINUTE INTENSITY(INCH/HOUR) = 1.330 COMPUTED RAINFALL INTENSITY DATA: STORM EVENT = 100.00 1-HOUR INTENSITY(INCH/HOUR) = 1.3300 SLOPE OF INTENSITY DURATION CURVE = .6000 «�*:e*fr �Y«*::*sY*:';:: ie is*:r 4r it ie ie �c it dr*:r it 4r:cir*ie sY is ir'.e'.r*«•ic;r4r:r«•sY it it J: it 4e 4r 4r*sY*:r*9rk*4r :r it tr kir it :r*k«•*ir 4r �r FLOW PROCESS FROM NODE 10.00 TO NODE 10.00 IS CODE = 15 ------------------------------------------ »»>DEFINE MEMORY BANK # 1 ««< MEMORY BANK # 1 DEFINED AS FOLLOWS: Q(CFS) TC(MIN.) Fp(INCH/HR) Ap FM(INCH/HR) Ae(ACRES) 1 282.24 17.91 .556 .16 .087 116.70 2 283.08 18.23 .555 .16 .088 118.33 3 283.66 19.13 .551 .16 .088 122.24 4 282.23 20.06 .547 .16 .089 125.30 5 264.13 25.02 .517 .18 .092 134.82 6 257.02 26.58 .511 .18 .093 136.34 TOTAL AREA = 136.34 ir::*':4::t it it it«•«•*i:ir:r:::c**ie is 4r ir«-ic*«•irh*ir**ir*eY 4r«-*�'cic*ic«•:t4t*«•ir Yr***i: it ir:r-k it it �r ie ir'r is it it it :Y it it*�**'r FLOW PROCESS FROM NODE 10.00 TO NODE 10.00 IS CODE = 14 ---------------------------------------------------------------------------- »»>MEMORY BANK # 1 COPIED ONTO MAIN -STREAM MEMORY««< MAIN -STREAM MEMORY DEFINED AS FOLLOWS: Q(CFS) TC(MIN.) Fp(INCH/HR) Ap FMCINCH/HR) Ae(ACRES) 1 282.24 17.91 .556 .16 .087 116.70 2 283.08 18.23 .555 .16 .088 118.33 3 283.66 19.13 .551 .16 .088 122.24 4 282.23 20.06 .547 .16 .089 125.30 5 264.13 25.02 .517 .18 .092 134.82 Page 1 6 257.02 26.58 .511 .18 .093 136.34 TOTAL AREA = 136.34 it it sY sY iFic it is is is is it is sY it is sY it is sY is sY sY ie is is is it it is iC it is it is it sY it dr is it it is sY st it it it ie it it sY sY sY is it it is it it icsYsY is se>•i it is it it it is it it is sY FLOW PROCESS FROM NODE 10.00 TO NODE 10.00 IS CODE = 12 ---------------------------------------------------------------------------- >>>CLEAR MEMORY BANK # 1 ««< iti: it kir��s'r:r�•:: sh sY it it is ie ic�ic sY it sY sv it sY is it&it ie is it it it it it it ie it it it it s:�ir is it ir.:rir&ir it it it it is it it it it it ie it it it it>: ie it �sY it is it FLOW PROCESS FROM NODE 10.00 TO NODE 34.00 IS CODE = 3 ---------------------------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< - ----------------------------------------------------------------- DEPTH OF FLOW IN 54.0 INCH PIPE IS 39.1 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 23.0 UPSTREAM NODE ELEVATION(FEET) = 1075.90 DOWNSTREAM NODE ELEVATION(FEET) = 1039.50 FLOW LENGTH(FEET) = 1200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 54.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 283.66 TRAVEL TIME(MIN.) _ .87 TC(MIN.) = 20.00 it i; it ie � it is it it is ie iri: it � it it it 4c it it it ie it it it it ie it it # sY sY it it sY it it ir. sY irir irir it & it it it sY it it is � it it sY >; it sY it it it sY it it it it it it it >': it is it it FLOW PROCESS FROM NODE 34.00 TO NODE 34.00 IS CODE = 10 ---------------------------------------------------------------------------- »»>MAIN-STREAM MEMORY COPIED ONTO MEMORY BANK # 1 ««< i; it sY it i<ir is it � is � it it i; it �• sY ie sY sk it it sY it is sY sY 4t it it Yt & sY it is it it sY � �• it icir it it is s: it it i; s: � i; it i< it it is it {r it �^ir it � it is i< � it sY sY it it t � FLOW PROCESS FROM NODE 34.00 TO NODE 34.00 IS CODE = 15 ---------------------------------------------------------------------------- »»>DEFINE MEMORY BANK # 2 ««< MEMORY BANK # 2 DEFINED AS FOLLOWS: Q(CFS) TC(MIN.) Fp(INCH/HR) Ap FM(INCH/HR) Ae(ACRES) 1 183.64 7.54 .684 .16 .109 43.69 2 220.14 13.95 .680 .17 .112 74.37 3 230.71 16.05 .677 .17 .114 85.79 4 232.67 16.62 .676 .17 .114 88.55 5 234.47 18.36 .672 .17 .116 95.30 6 234.23 18.54 .672 .17 .117 95.81 7 233.37 18.68 .672 .17 .117 95.97 TOTAL AREA = 95.97 is it sY it i.•sY it it i:�ic i;>'; it it�ir it ksY it ie sY sk it it it st>;sY>; it in&i<ir it sY is is it i:�ir#irir is i:i: sY it sY sY it �i:ir>;iri: it it �..•i.•s: iric it it &ir it it it FLOW PROCESS FROM NODE 34.00 TO NODE 34.00 IS CODE = 14 ---------------------------------------------------------------------------- »»>MEMORY BANK # 2 COPIED ONTO MAIN -STREAM MEMORY««< MAIN -STREAM MEMORY DEFINED AS FOLLOWS: Q(CFS) TC(MIN.) Fp(INCH/HR) Ap FM(INCH/HR) Ae(ACRES) 1 183.64 7.54 .684 .16 .109 43.69 2 220.14 13.95 .680 .17 .112 74.37 3 230.71 16.05 .677 .17 .114 85.79 4 232.67 16.62 .676 .17 .114 88.55 Page 2 5 234.47 18.36 .672 .17 .116 95.30 6 234.23 18.54 .672 .17 .117 95.81 7 233.37 18.68 .672 .17 .117 95.97 TOTAL AREA = 95.97 icit is is is ie it it&it it it it itic°k is it it it it is it it is is is it is ie is it it it it it is is is ie it is it is irie is ie is is is is is i;it it it is it it it it is it it it it it it it is is it is it it FLOW PROCESS FROM NODE 34.00 TO NODE 34.00 IS CODE = 12 ---------------------------------------------------------------------------- »»>CLEAR MEMORY BANK # 2 ««< �•ie is i; it it ic*ir it ie itie it ie it it is it*#ic is it ie it&it it is it is �ititic is it is is is is is it is is tic ie�ic is is**i; it it it it�ic is is it itit is it it it is is icit'.: FLOW PROCESS FROM NODE 34.00 TO NODE 34.00 IS CODE = 11 ---------------------------------------------------------------------------- »»>CONFLUENCE MEMORY BANK # 1 WITH THE MAIN -STREAM MEMORY««< id* PEAK FLOW RATE TABLE ** Q Tc Intensit FP Ap FM Ae (CFS) (MIN.) (INCH/HR� (INCH/HR) (INCH/HR) (ACRES) 1 382.35 7.54 4.617 .62 .16 .10 90.55 2 472.16 13.95 3.191 .61 .16 .10 161.08 3 496.60 16.05 2.934 .61 .16 .10 185.55 4 502.13 16.62 2.873 .61 .16 .10 191.86 5 514.33 18.36 2.706 .61 .16 .10 209.42 6 515.11 18.54 2.691 .61 .16 .10 211.03 7 515.05 18.68 2.679 .61 .16 .10 212.06 8 514.85 18.78 2.670 .61 .16 .10 212.67 9 513.27 19.09 2.644 .61 .17 .10 214.30 10 507.22 20.00 2.571 .61 .17 .10 218.21 11 499.48 20.93 2.502 .60 .17 .10 221.27 12 453.98 25.91 2.201 .58 .18 .10 230.79 13 439.94 27.48 2.125 .58 .18 .10 232.31 TOTAL AREA = 232.31 COMPUTED CONFLUENCE ESTIMATES ARE AS FOLLOWS: PEAK FLOW RATE(CFS) = 515.11 TC(MIN.) = 18.541 EFFECTIVE AREA(ACRES) = 211.03 AREA -AVERAGED FM(INCH/HR) _ .10 AREA -AVERAGED Fp(INCH/HR) = .61 AREA -AVERAGED Ap = .16 TOTAL AREA(ACRES) = 232.31 Yr it it :c it 'k is °k :: it it is is it it :t i; is i; ki: is �ir�i; it �i<� wit is #itic �•k fir is i; i; '.cam is is is is pie i.•�i: is is if-k �'.,' ems: ie��i; i.•��ir it it it it it it FLOW PROCESS FROM NODE 34.00 TO NODE 34.00 IS CODE = 12 ---------------------------------------------------------------------------- »»>CLEAR MEMORY BANK # 1 ««< it it :c it ie ie is is i; i; i; is is it is it i; it it is it is ie it it is is * it it k is is is is i; it it it is it is is is is is is i; i<it i; i;.ir it ie is ic'� is is it i; it it is i; ie it it is it is it is is ir. FLOW PROCESS FROM NODE 34.00 TO NODE 35.00 IS CODE = 3 ---------------------------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< -------------------------------------------------------------------- DEPTH OF FLOW IN 96.0 INCH PIPE IS 74.1 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 12.4 UPSTREAM NODE ELEVATION(FEET) = 1039.50 DOWNSTREAM NODE ELEVATION(FEET) = 1039.40 FLOW LENGTH(FEET) = 25.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 96.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 515.11 TRAVEL TIME(MIN.) _ .03 TC(MIN.) = 18.57 Page 3 is s; i< is is is is ie it it it it is it is is is :Y it icie ie is it is is kit ie it ie is it is is is it it it ie icir ie sY it it it is is ie is is it it is it ie is is it is it it is iric ie ie it is is it ie ie it it FLOW PROCESS FROM NODE 35.00 TO NODE 35.00 IS CODE = 10 ---------------------------------------------------------------------------- »»>MAIN-STREAM MEMORY COPIED ONTO MEMORY BANK # 1 ««< FLOW PROCESS FROM NODE 32.00 TO NODE 32.00 IS CODE = 15 ---------------------------------------------------------------------------- >>>DEFINE MEMORY BANK # 2 ««< MEMORY BANK # 2 DEFINED AS FOLLOWS: Q(CFS) TC(MIN.) Fp(INCH/HR) Ap FM(INCH/HR) Ae(ACRES) 1 86.70 13.92 .750 .10 .075 30.55 2 91.46 20.42 .750 .10 .075 40.83 TOTAL AREA = 40.83 is is ie is it ie ie is is is is is is i�'k is is it is is is it it ie it it is ie is it it is k is it irie it it i; it is 4e is ie is it is is it ie is is it ie it it is h � is � is it it ie is it it ie ie et ie ie ie it FLOW PROCESS FROM NODE 32.00 TO NODE 32.00 IS CODE = 14 ---------------------------------------------------------------------------- »»>MEMORY BANK # 2 COPIED ONTO MAIN -STREAM MEMORY««< MAIN -STREAM MEMORY DEFINED AS FOLLOWS: Q(CFS) TC(MIN.) Fp(INCH/HR) Ap FM(INCH/HR) Ae(ACRES) 1 86.70 13.92 .750 .10 .075 30.55 2 91.46 20.42 .750 .10 .075 40.83 TOTAL AREA = 40.83 :: is ;<ir it is is i; i; i; is it it is ire �ic'kR•i: ie it is is is it is i:iri:ieir'.e ie it it is it is it it ie is die it is is it it it ie it ie ie it it ie ie i; it ic�it is it is ie�ie it it ie it is FLOW PROCESS FROM NODE 32.00 TO NODE 32.00 IS CODE = 12 ---------------------------------------------------------------------------- »»>CLEAR MEMORY BANK # 2 ««< it i; it k is �• i; it is it � it it i;.ic is it it is is it is � i; irir is ie it is irir it ie it it it it is is is it it it it ie it irk is it it it it ie it it i; it it it sY it is it is it it iric ie irit it it is FLOW PROCESS FROM NODE 32.00 TO NODE 35.00 IS CODE = 3 ------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< ------------------------------------------------------------------- DEPTH OF FLOW IN 42.0 INCH PIPE IS 32.2 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 11.6 UPSTREAM NODE ELEVATION(FEET) = 1052.00 DOWNSTREAM NODE ELEVATION(FEET) = 1039.40 FLOW LENGTH(FEET) = 1200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 42.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 91.46 TRAVEL TIME(MIN.) = 1.73 TC(MIN.) = 22.16 .... » it it :.•,:. it � � � 9; it ie ie it it ie ie � is ie it i; is �• ie ie i; it is # i; it ie it ie is � �• is is 9: � �• is is is it Yc is is ie it i; ie is i; �• ie is it is i; i; i; k �•it ir'.r is i; is it is FLOW PROCESS FROM NODE 35.00 TO NODE 35.00 IS CODE = 11 ---------------------------------------------------------------------------- »»>CONFLUENCE MEMORY BANK # 1 WITH THE MAIN -STREAM MEMORY««< Page 4 ** PEAK FLOW RATE TABLE ** Q Tc Intensit Fp Ap FM Ae (CFS) (MIN.) (INCH/HR� (INCH/HR) (INCH/HR) (ACRES) 1 578.38 15.66 2.977 .63 .15 .10 211.18 2 580.09 22.16 2.418 .61 .16 .10 264.37 3 447.79 7.58 4.604 .63 .15 .09 105.32 4 555.16 13.99 3.186 .63 .15 .10 188.37 5 583.61 16.09 2.930 .63 .15 .10 216.78 6 589.56 16.66 2.869 .63 .15 .10 223.99 7 603.04 18.40 2.703 .62 .16 .10 244.30 8 603.95 18.57 2.688 .62 .16 .10 246.19 9 603.99 18.71 2.676 .62 .16 .10 247.44 10 603.86 18.81 2.667 .62 .16 .10 248.20 11 602.51 19.13 2.641 .62 .16 .10 250.33 12 597.13 20.04 2.568 .62 .16 .10 255.68 13 590.07 20.97 2.499 .62 .16 .10 260.22 14 536.90 25.95 2.199 .60 .16 .10 271.62 15 519.89 27.52 2.123 .59 .17 .10 273.14 TOTAL AREA = 273.14 COMPUTED CONFLUENCE ESTIMATES ARE AS FOLLOWS: PEAK FLOW RATE(CFS) = 603.99 TC(MIN.) = 18.714 EFFECTIVE AREA(ACRES) = 247.44 AREA -AVERAGED Fm(INCH/HR) _ .10 AREA -AVERAGED Fp(INCH/HR) = .62 AREA -AVERAGED Ap = .16 TOTAL AREA(ACRES) = 273.14 SYi:**ir it is 4r:r 4r it**4:Yr*ir:r:r:r sY it**ie 4r it �'c****ir:Y ie fr it is ksY 4r is*i:i:4r:ri: it 4r:a it ie 4r ie it 4r sY ie 4r Yr :e �c�ir it it*fir �: it it*** FLOW PROCESS FROM NODE 35.00 TO NODE 35.00 IS CODE = 12 ------ --------------- »»>CLEAR MEMORY BANK # 1 ««< ---------------------------------------------------------------------------- ---------------------------------------------------------------------------- ir'.r :r �•;: ?: is is �•4.•�•:t it 4r �•'rir;r;:ic5'c it fe:t it ir:r ie it it it*ir is*�ic:r it it sir it*fc it 4t �r is it it it fr:r 4r ie it it it it 4r ie 4t is Ye*it is ir4r*ir**fir :r FLOW PROCESS FROM NODE 35.00 TO NODE 400.00 IS CODE = 3 ---------------------------------------------------------------------------- >COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< ---------------------------------------------------------------------------- ---------------------------------------------------------------------------- DEPTH OF FLOW IN 102.0 INCH PIPE IS 78.3 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 12.9 UPSTREAM NODE ELEVATION(FEET) = 1039.40 DOWNSTREAM NODE ELEVATION(FEET) = 1036.08 FLOW LENGTH(FEET) = 825.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 102.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 603.99 TRAVEL TIME(MIN.) = 1.06 TC(MIN.) = 19.78 '.r 4r ir.***f:tr*4r it**4c�'.r::Y: it it is 4: 4c it it'�.•ic it 4r ir�ir it 4c**s:4r:c is Ycic'.c:k xY 9c is do ir:�r tc*sY it is 4r*9c it it it sY is :Y is*ic**ir*4: *i: 9: :r FLOW PROCESS FROM NODE 400.00 TO NODE 400.00 IS CODE = 10 ---------------------------------------------------------------------------- >>>MAIN-STREAM MEMORY COPIED ONTO MEMORY BANK # 1 ««< ---------------------------------------------------------------------------- ---------------------------------------------------------------------------- 'r it te'r 4r ir:r*it*it it irgr:ri: �k it*::4c*9r�•9:::*ic 4r*ir it it 4c irir sY it it iririr it it is is sY is is it*ir is it it Yr:r*ir is it it it it it �Y fr�4r dr �Y 4c 4r dr fr FLOW PROCESS FROM NODE 400.00 TO NODE 400.00 IS CODE = 15 ---------------------------------------------------------------------------- >DEFINE MEMORY BANK # 2 ««< ---------------------------------------------------------------------------- MEMORY BANK # 2 DEFINED AS FOLLOWS: Page 5 Q(CFS) TC(MIN.) Fp(INCH/HR) Ap FM(INCH/HR) Ae(ACRES) 1 55.12 10.10 .750 .41 .307 14.42 2 55.51 10.39 .750 .41 .307 14.80 3 55.54 10.41 .750 .41 .307 14.83 4 55.86 10.79 .750 .41 .307 15.33 5 56.13 12.05 .750 .41 .307 16.72 6 56.11 12.12 .750 .41 .307 16.80 7 55.95 12.26 .750 .41 .307 16.91 8 55.66 12.41 .750 .41 .307 17.00 9 52.94 13.69 .750 .41 .307 17.36 TOTAL AREA = 17.36 ickkkkitkkkkkir is kk kkkkkkkkkkkkkkk kkkic ickkkkkickkkkickk�kk kkkkkitk kkkkkkkkiric k4tk is ickkk FLOW PROCESS FROM NODE 400.00 TO NODE 400.00 IS CODE = 14 ---------------------------------------------------------------------------- >>>MEMORY BANK # 2 COPIED ONTO MAIN -STREAM MEMORY««< MAIN -STREAM MEMORY DEFINED AS FOLLOWS: Q(CFS) TC(MIN.) Fp(INCH/HR) Ap FM(INCH/HR) Ae(ACRES) 1 55.12 10.10 .750 .41 .307 14.42 2 55.51 10.39 .750 .41 .307 14.80 3 55.54 10.41 .750 .41 .307 14.83 4 55.86 10.79 .750 .41 .307 15.33 5 56.13 12.05 .750 .41 .307 16.72 6 56.11 12.12 .750 .41 .307 16.80 7 55.95 12.26 .750 .41 .307 16.91 8 55.66 12.41 .750 .41 .307 17.00 9 52.94 13.69 .750 .41 .307 17.36 TOTAL AREA = 17.36 kkickkkkkkk�'-kkkkk��kkkitkkkkkkkkk�kkic�•�ititkkkitk�kkkitkirkkkkkkkkkkkkkkitkkitic.&kkk�it FLOW PROCESS FROM NODE 400.00 TO NODE 400.00 IS CODE = 12 ---------------------------------------------------------------------------- >CLEAR MEMORY BANK # 2 ««< itkkkkkkirkk4: itk k4tkkk�t is is kirkkkkkkkkkirk kkkkkkkkkkkkkkkir irk itkkkkkkkkkkkkkkkkkkkkkkk FLOW PROCESS FROM NODE 400.00 TO NODE 400.00 IS CODE = 11 ---------------------------------------------------------------------------- »»>CONFLUENCE MEMORY BANK # 1 WITH THE MAIN -STREAM MEMORY««< PEAK FLOW RATE TABLE itk Q Tc Intensit Fp Ap FM Ae (CFS) (MIN.) (INCH/HR� (INCH/HR) (INCH/HR) (ACRES) 1 526.14 10.10 3.874 .66 .18 .12 137.71 2 531.37 10.39 3.810 .66 .18 .12 141.82 3 531.83 10.41 3.804 .66 .18 .12 142.19 4 538.61 10.79 3.723 .66 .18 .12 147.70 5 560.14 12.05 3.485 .66 .18 .12 165.53 6 561.40 12.12 3.472 .66 .18 .12 166.60 7 563.65 12.26 3.448 .66 .18 .12 168.57 8 565.93 12.41 3.423 .66 .18 .12 170.64 9 584.85 13.69 3.227 .65 .18 .11 187.74 10 500.15 8.73 4.228 .66 .18 .12 117.78 11 604.84 15.06 3.048 .65 .17 .11 205.73 12 624.69 16.73 2.861 .65 .17 .11 228.54 13 629.14 17.16 2.819 .65 .17 .11 234.14 14 634.10 17.72 2.764 .65 .17 .11 241.35 15 644.85 19.,46 2.614 .64 .17 .11 261.66 16 645.50 19.64 2.599 .64 .17 .11 263.55 Page 6 17 645.34 19.78 2.588 .64 .17 .11 264.80 18 645.07 19.88 2.581 .64 .17 .11 265.56 19 643.29 20.19 2.556 .64 .17 .11 267.69 20 636.70 21.10 2.490 .64 .17 .11 273.04 21 628.48 22.03 2.426 .64 .17 .11 277.58 22 617.13 23.22 2.351 .63 .17 .11 281.73 23 570.22 27.05 2.145 .62 .18 .11 288.98 24 551.92 28.62 2.074 .61 .18 .11 290.50 TOTAL AREA = 290.50 COMPUTED CONFLUENCE ESTIMATES ARE AS FOLLOWS: PEAK FLOW RATE(CFS) = 645.50 TC(MIN.) = 19.639 EFFECTIVE AREA(ACRES) = 263.55 AREA -AVERAGED FM(INCH/HR) AREA -AVERAGED Fp(INCH/HR) = .64 AREA -AVERAGED Ap = .17 TOTAL AREA(ACRES) = 290.50 is is it it is is it it is it it it tY it it is is it it it is is is is it is itir is is it is is is is it is it it it is it it is is is is it is is ie it is it it it is it ic*ic it is is it it**is is it ie it is is is FLOW PROCESS FROM NODE 400.00 TO ----------------------------------------------- NODE 400.00 IS CODE = 12 »»>CLEAR MEMORY BANK # 1 ««< END OF STUDY SUMMARY: TOTAL AREA(ACRES) - 290.50 TC(MIN.) = 19.64 EFFECTIVE AREA(ACRES) = 263.55 AREA -AVERAGED FM(INCH/HR)= .11 AREA -AVERAGED Fp(INCH/HR) _ .64 AREA -AVERAGED Ap = .17 PEAK FLOW RATE(CFS) = 645.50 PEAK FLOW RATE TABLE ** Q Tc Intensit FP Ap FM Ae (CFS) (MIN.) (INCH/HR� (INCH/HR) (INCH/HR) (ACRES) 1 500.15 8.73 4.228 .66 .18 .12 117.78 2 526.14 10.10 3.874 .66 .18 .12 137.71 3 531.37 10.39 3.810 .66 .18 .12 141.82 4 531.83 10.41 3.804 .66 .18 .12 142.19 5 538.61 10.79 3.723 .66 .18 .12 147.70 6 560.14 12.05 3.485 .66 .18 .12 165.53 7 561.40 12.12 3.472 .66 .18 .12 166.60 8 563.65 12.26 3.448 .66 .18 .12 168.57 9 565.93 12.41 3.423 .66 .18 .12 170.64 10 584.85 13.69 3.227 .65 .18 .11 187.74 11 604.84 15.06 3.048 .65 .17 .11 205.73 12 624.69 16.73 2.861 .65 .17 .11 228.54 13 629.14 17.16 2.819 .65 .17 .11 234.14 14 634.10 17.72 2.764 .65 .17 .11 241.35 15 644.85 19.46 2.614 .64 .17 .11 261.66 16 645.50 19.64 2.599 .64 .17 .11 263.55 17 645.34 19.78 2.588 .64 .17 .11 264.80 18 645.07 19.88 2.581 .64 .17 .11 265.56 19 643.29 20.19 2.556 .64 .17 .11 267.69 20 636.70 21.10 2.490 .64 .17 .11 273.04 21 628.48 22.03 2.426 .64 .17 .11 277.58 22 617.13 23.22 2.351 .63 .17 .11 281.73 23 570.22 27.05 2.145 .62 .18 .11 288.98 24 551.92 28.62 2.074 .61 .18 .11 290.50 -----------------------------------------------------------------=------ END OF RATIONAL METHOD ANALYSIS Page 7 Technical Appendix It 25-Year Rational Method Analysis Derived from Storm Drain Basis of Design Sycamore Hills II Tentative Tract No. 16495 RBF Consulting — February 2004 * Ye Ye Yr Yc Yr Y: Yc *Yr it Yr Yc4e Yc Yr it Y: Yr Yr Yc Yc Yc it Ye Yr Yr Yr ie YCYt Yr Yc Yr is Yr Yr Yc Yr Yr Yr * Yc Yr Yc * Ye Yc is Y: Yr *Yc Yc Yr Yr Yc Yr Yc Ye Yr * Yc Yr Ye Yc Yr Ye Yt Yr Yr is YCYr Yc * RATIONAL METHOD HYDROLOGY COMPUTER PROGRAM PACKAGE (Reference: 1986 SAN BERNARDINO CO. HYDROLOGY CRITERION) (c) Copyright 1983-93 Advanced Engineering Software (aes) Ver. 1.9B Release Date: 7/18/93 License ID 1202 Analysis prepared by: HUITT-ZOLLARS, INC. 15101 RED HILL AVENUE TUSTIN, CALIFORNIA 92780-6500 PHONE (714) 259-7900 * FAX (714) 259-0210 ---------------------------------------------------------------------------- FILE NAME: F025AULB.DAT TIME/DATE OF STUDY: 13: 9 6/14/2004 USER SPECIFIED HYDROLOGY AND HYDRAULIC MODEL INFORMATION: ------------------------------------------------ --*TIME-OF-CONCENTRATION MODEL* -- USER SPECIFIED STORM EVENT(YEAR) = 25.00 SPECIFIED MINIMUM PIPE SIZE(INCH) = 18.00 SPECIFIED PERCENT OF GRADIENTS (DECIMAL) TO USE FOR FRICTION SLOPE = .90 *USER -DEFINED LOGARITHMIC INTERPOLATION USED FOR RAINFALL* 10-YEAR STORM 60-MINUTE INTENSITY(INCH/HOUR) _ .920 100-YEAR STORM 60-MINUTE INTENSITY(INCH/HOUR) = 1.330 COMPUTED RAINFALL INTENSITY DATA: STORM EVENT = 25.00 1-HOUR INTENSITY(INCH/HOUR) = 1.0620 SLOPE OF INTENSITY DURATION CURVE = .6000 YI Yr Yr �•Yr Yr Yr Yr Yc Ye**Yr Yr Y: Yr Ye Yc it Yr Yr Yr*Yc**Yr Yr Yc*Yc°k***Yc Yr*Yc. Yc Yr Yc Yr Yc Yc Yc Yc Yc Yr is Yc Yr Yr Yr Yc Yr Ye Yc Yr Yr Y: Yr Yc Yr Yr Yr Yc Yt Yc Yc Ye**Yc Ye Ye FLOW PROCESS FROM NODE 300.70 TO NODE 300.60 IS CODE = 2.1 ---------------------------------------------------------------------------- »»>RATIONAL METHOD INITIAL SUBAREA ANALYSIS««< DEVELOPMENT IS COMMERCIAL TC = K*[(LENGTH** 3. 00) /(ELEVATION CHANGE)]** .20 INITIAL SUBAREA FLOW-LENGTH(FEET) = 85.00 UPSTREAM ELEVATION(FEET) = 1066.50 DOWNSTREAM ELEVATION(FEET) = 1066.00 ELEVATION DIFFERENCE(FEET) = .50 TC(MIN.) = .304*[( 85.00** 3.00)/( .50)]** .20 = 5.020 25 YEAR RAINFALL INTENSITY (INCH/HR) = 4.705 SOIL CLASSIFICATION IS "B" COMMERCIAL SUBAREA LOSS RATE, FM(INCH/HR) = .0750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .10 SUBAREA RUNOFF(CFS) _ .38 TOTAL AREA(ACRES) = .09 PEAK FLOW RATE(CFS) _ .38 Yc Yc Yr Yc Y: Yc Yc * * *Yr Yc Y: Yr Yr * Yc Yr *YcYc * �' � Yc *Yr Y.• Ye it * Yr Yr it Yr Yc Yr Yc YcY: Yr Yc Yc * * Ye Yc Yr is Yc s4Yr Yr Yc Yc Yt Yr Ye *Y: Yc Yr YrY:Yr it Yr Yr Yc is Yc Yr Yc Yc Ye Yt FLOW PROCESS FROM NODE 300.60 TO NODE 300.10 IS CODE = 6 ---------------------------------------------------------------------------- »»>COMPUTE STREET FLOW TRAVEL TIME THRU SUBAREA««< UPSTREAM ELEVATION(FEET) = 1066.00 DOWNSTREAM ELEVATION(FEET) = 1053.27 STREET LENGTH(FEET) = 600.00 CURB HEIGHT(INCHES) = 8. STREET HALFWIDTH(FEET) = 20.00 DISTANCE FROM CROWN TO CROSSFALL GRADEBREAK(FEET) = 15.00 Page 1 INTERIOR STREET CROSSFALL(DECIMAL) = .020 OUTSIDE STREET CROSSFALL(DECIMAL) = .020 SPECIFIED NUMBER OF HALFSTREETS CARRYING RUNOFF = 1 "TRAVEL TIME COMPUTED USING MEAN FLOW(CFS) = 3.50 STREET FLOW MODEL RESULTS: STREET FLOW DEPTH(FEET) _ .35 HALFSTREET FLOOD WIDTH(FEET) = 9.59 AVERAGE FLOW VELOCITY(FEET/SEC.) = 3.15 PRODUCT OF DEPTH&VELOCITY = 1.10 STREET FLOW TRAVEL TIME(MIN.) = 3.18 TC(MIN.) = 8.20 25 YEAR RAINFALL INTENSITY(INCH/HR) = 3.506 SOIL CLASSIFICATION IS "B" RESIDENTIAL-> 8-10 DWELLINGS/ACRE SUBAREA LOSS RATE, FM(INCH/HR) = .3000 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .40 SUBAREA AREA(ACRES) = 2.10 SUBAREA RUNOFF(CFS) = 6.06 EFFECTIVE AREA(ACRES) = 2.19 AREA -AVERAGED Fm(INCH/HR) _ .29 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .39 TOTAL AREA(ACRES) = 2.19 PEAK FLOW RATE(CFS) = 6.34 END OF SUBAREA STREET FLOW HYDRAULICS: DEPTH(FEET) = .41 HALFSTREET FLOOD WIDTH(FEET) = 12.41 FLOW VELOCITY(FEET/SEC.) = 3.67 DEPTHkVELOCITY = 1.49 kkkkkkiekkkkir itk kirkkkkkkkkkkilirkkkkkkkkkkkkkkkkkkkkkkkkkkkirkkkkkksYkkkkkkkkkkkkk FLOW PROCESS FROM NODE 300.10 TO NODE 300.00 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< >>>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW) ««< ESTIMATED PIPE DIAMETER(INCH) INCREASED TO 18.000 DEPTH OF FLOW IN 18.0 INCH PIPE IS 4.3 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 19.7 UPSTREAM NODE ELEVATION(FEET) = 1053.27 DOWNSTREAM NODE ELEVATION(FEET) = 1047.75 FLOW LENGTH(FEET) = 21.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 18.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 6.34 TRAVEL TIME(MIN.) _ .02 TC(MIN.) = 8.21 ki.•kkkkkkkkkkkickkkkkkkiekkkkkkkkkkkk$rkkkkiriskkkkkkkkkkkkkkkkkkkkkkkkkkkkkki�kkirk FLOW PROCESS FROM NODE 300.00 TO NODE 300.00 IS CODE = 1 ---------------------------------------------------------------------------- »»>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< TOTAL NUMBER OF STREAMS = 3 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 1 ARE: TIME OF CONCENTRATION(MIN.) = 8.21 RAINFALL INTENSITY(INCH/HR) = 3.50 AREA -AVERAGED FM(INCH/HR) = .29 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .39 EFFECTIVE STREAM AREA(ACRES) = 2.19 TOTAL STREAM AREA(ACRES) = 2.19 PEAK FLOW RATE(CFS) AT CONFLUENCE = 6.34 irkkkkkirk kirk kkkirkkiek ifir kk>;kkkkkirkkkkkkkkkkkkkkkkkkkkkkkkkk kkkkkkkki:kkkkitkkkkit it FLOW PROCESS FROM NODE 300.50 TO NODE 300.40 IS CODE = 2.1 ---------------------------------------------------------------------------- »»>RATIONAL METHOD INITIAL SUBAREA ANALYSIS««< Page 2 DEVELOPMENT IS SINGLE FAMILY RESIDENTIAL -> 5-7 DWELLINGS/ACRE TC = K*[(LENGTH** 3.00)/(ELEVATION CHANGE)]** .20 INITIAL SUBAREA FLOW-LENGTH(FEET) = 154.00 UPSTREAM ELEVATION(FEET) = 1062.90 DOWNSTREAM ELEVATION(FEET) = 1060.80 ELEVATION DIFFERENCE(FEET) = 2.10 TC(MIN.) = .389*[( 154.00** 3.00)/( 2.10)]** .20 = 6.887 25 YEAR RAINFALL INTENSITY(INCH/HR) = 3.892 SOIL CLASSIFICATION IS "B" RESIDENTIAL-> 5-7 DWELLINGS/ACRE SUBAREA LOSS RATE, Fm(INCH/HR) = .3750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) _ .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .50 SUBAREA RUNOFF(CFS) _ .73 TOTAL AREA(ACRES) = .23 PEAK FLOW RATE(CFS) _ .73 ick 4ckkkkkickkkitkkkkkkkkkkkkkir �4kkkkkkkkkk***kk*kir k ick it ick kkkkkkkkic iekkkkisk irkkir kk it k FLOW PROCESS FROM NODE 300.40 TO NODE 300.30 IS CODE = 6 ---------------------------------------------------------------------------- »»>COMPUTE STREET FLOW TRAVEL TIME THRU SUBAREA««< UPSTREAM ELEVATION(FEET) = 1060.80 DOWNSTREAM ELEVATION(FEET) = 1053.85 STREET LENGTH(FEET) = 143.00 CURB HEIGHT(INCHES) = 8. STREET HALFWIDTH(FEET) = 20.00 DISTANCE FROM CROWN TO CROSSFALL GRADEBREAK(FEET) = 15.00 INTERIOR STREET CROSSFALL(DECIMAL) = .020 OUTSIDE STREET CROSSFALL(DECIMAL) = .020 SPECIFIED NUMBER OF HALFSTREETS CARRYING RUNOFF = 1 **TRAVEL TIME COMPUTED USING MEAN FLOW(CFS) = 2.32 STREET FLOW MODEL RESULTS: STREET FLOW DEPTH(FEET) _ .28 HALFSTREET FLOOD WIDTH(FEET) = 6.22 AVERAGE FLOW VELOCITY(FEET/SEC.) = 4.03 PRODUCT OF DEPTH&VELOCITY = 1.14 STREET FLOW TRAVEL TIME(MIN.) = .59 TC(MIN.) = 7.48 25 YEAR RAINFALL INTENSITY(INCH/HR) = 3.705 SOIL CLASSIFICATION IS "B" RESIDENTIAL-> 8-10 DWELLINGS/ACRE SUBAREA LOSS RATE, FM(INCH/HR) _ .3000 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .40 SUBAREA AREA(ACRES) = 1.04 SUBAREA RUNOFF(CFS) = 3.19 EFFECTIVE AREA(ACRES) = 1.27 AREA -AVERAGED Fm(INCH/HR) _ .31 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .42 TOTAL AREA(ACRES) = 1.27 PEAK FLOW RATE(CFS) = 3.88 END OF SUBAREA STREET FLOW HYDRAULICS: DEPTH(FEET) = .32 HALFSTREET FLOOD WIDTH(FEET) = 7.91 FLOW VELOCITY(FEET/SEC.) = 4.76 DEPTH*VELOCITY = 1.51 k kkkkkkick ick kkkkkkkick i�kkkkk k�'c ickk*kkkis hick kickk*kirk ickkkkkkkkkkkkkicirk it is ickkkkkkickk FLOW PROCESS FROM NODE 300.30 TO NODE 300.00 IS CODE = 3 ---------------------------------------------------------------------------- >>>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< ESTIMATED PIPE DIAMETER(INCH) INCREASED TO 18.000 DEPTH OF FLOW IN 18.0 INCH PIPE IS 5.2 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 9.1 UPSTREAM NODE ELEVATION(FEET) = 1053.85 DOWNSTREAM NODE ELEVATION(FEET) = 1047.75 Page 3 FLOW LENGTH(FEET) = 138.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 18.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 3.88 TRAVEL TIME(MIN.) _ .25 TC(MIN.) = 7.73 *Yc Yt is Yt Yr Yc * Yr Ye Yr Yc Yc sY Yc Yr $c is Yr Yc Yt Yr * Yc * Yr *Yr Yr Yc Yc Yc Yc Ye Yc Yc Y: * Yr Yc YrYc Yc Yr Y: * * Yc Yt Yr Ye * Y: Yt Yc Yc Yr Yt kYc Yc Yc Yr Yc Yc Yr Yc Yt Yc YcYcYc is Yt Yc Yr FLOW PROCESS FROM NODE 300.00 TO NODE 300.00 IS CODE = 1 ---------------------------------------------------------------------------- »»>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< TOTAL NUMBER OF STREAMS = 3 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 2 ARE: TIME OF CONCENTRATION(MIN.) = 7.73 RAINFALL INTENSITY(INCH/HR) = 3.63 AREA -AVERAGED FM(INCH/HR) = .31 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .42 EFFECTIVE STREAM AREA(ACRES) = 1.27 TOTAL STREAM AREA(ACRES) = 1.27 PEAK FLOW RATE(CFS) AT CONFLUENCE = 3.88 Yc Yc Yr Yc Yr Yc Y:***Y: Ye Yc Yric Yr Ye Yc Ye Yr is Yc Yc Yc Yr Yr Yc is Yc Yr 4r Ye*Ye Yc********Yc Yric Yc Yr Ye Yr YrYr Yc Ye*Yr Yc Ye Yc Yr*Yc Yr is Yc Yc is Yr Ye Yr it is Yc ie Yc Yc FLOW PROCESS FROM NODE 300.90 TO NODE 300.80 IS CODE = 2.1 ---------------------------------------------------------------------------- »»>RATIONAL METHOD INITIAL SUBAREA ANALYSIS««< DEVELOPMENT IS SINGLE FAMILY RESIDENTIAL -> 5-7 DWELLINGS/ACRE TC = K*[(LENGTH** 3.00)/(ELEVATION CHANGE)]** .20 INITIAL SUBAREA FLOW-LENGTH(FEET) = 145.00 UPSTREAM ELEVATION(FEET) = 1062.90 DOWNSTREAM ELEVATION(FEET) = 1060.76 ELEVATION DIFFERENCE(FEET) = 2.14 TC(MIN.) = .389*[( 145.00** 3.00)/( 2.14)]** .20 = 6.617 25 YEAR RAINFALL INTENSITY(INCH/HR) = 3.987 SOIL CLASSIFICATION IS "B" RESIDENTIAL-> 5-7 DWELLINGS/ACRE SUBAREA LOSS RATE, FMCINCH/HR) = .3750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) _ .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .50 SUBAREA RUNOFF(CFS) _ .75 TOTAL AREA(ACRES) = .23 PEAK FLOW RATE(CFS) _ .75 Yc Yr ;r * is Yr Yr Y: is * *Yc Yr Yr * Yc Yr Yc Yc is Yc *Yr YrYc Yc.Ye Yc * Y: * Yc is Yc Yc Yr * Yc Yt Yt Ye Yc Yc �Yc * Yt Yr Yr Yr *Yt k Yc Yc Yr Yc Yc * * Yr Yc is Yr Yc Yr Yr *Yr * Yr Yc Yr Yc Y: Ye FLOW PROCESS FROM NODE 300.80 TO NODE 300.20 IS CODE = 6 ---------------------------------------------------------------------------- »»>COMPUTE STREET FLOW TRAVEL TIME THRU SUBAREA««< UPSTREAM ELEVATION(FEET) = 1060.76 DOWNSTREAM ELEVATION(FEET) = 1053.25 STREET LENGTH(FEET) = 270.00 CURB HEIGHT(INCHES) = 8. STREET HALFWIDTH(FEET) = 20.00 DISTANCE FROM CROWN TO CROSSFALL GRADEBREAK(FEET) = 15.00 INTERIOR STREET CROSSFALL(DECIMAL) = .020 OUTSIDE STREET CROSSFALL(DECIMAL) = .020 SPECIFIED NUMBER OF HALFSTREETS CARRYING RUNOFF = 1 **TRAVEL TIME COMPUTED USING MEAN FLOW(CFS) = 2.89 STREET FLOW MODEL RESULTS: STREET FLOW DEPTH(FEET) _ .32 HALFSTREET FLOOD WIDTH(FEET) = 7.91 AVERAGE FLOW VELOCITY(FEET/SEC.) = 3.54 PRODUCT OF DEPTH&VELOCITY = 1.12 Page 4 STREET FLOW TRAVEL TIME(MIN.) = 1.27 TC(MIN.) = 7.89 25 YEAR RAINFALL INTENSITY (INCH/HR) = 3.588 SOIL CLASSIFICATION IS "B" RESIDENTIAL-> 8-10 DWELLINGS/ACRE SUBAREA LOSS RATE, FM(INCH/HR) = .3000 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .40 SUBAREA AREA(ACRES) = 1.45 SUBAREA RUNOFF(CFS) = 4.29 EFFECTIVE AREA(ACRES) = 1.68 AREA -AVERAGED Fm(INCH/HR) _ .31 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .41 TOTAL AREA(ACRES) = 1.68 PEAK FLOW RATE(CFS) = 4.96 END OF SUBAREA STREET FLOW HYDRAULICS: DEPTH(FEET) = .36 HALFSTREET FLOOD WIDTH(FEET) = 10.16 FLOW VELOCITY(FEET/SEC.) = 4.06 DEPTH*VELOCITY = 1.47 4r it ir'.rii'.r fe ir*it is**ic**ir Ye it it*ie ie it it it it',e it it it it it it 4t 4e it it it 4r it fe �Y it'x �Y it ie is it ie *;r 4e it �c :e :e 4e 9: it it it it it it it x it it it it it it sF ie FLOW PROCESS FROM NODE 300.20 TO NODE 300.00 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< ESTIMATED PIPE DIAMETER(INCH) INCREASED TO 18.000 DEPTH OF FLOW IN 18.0 INCH PIPE IS 4.1 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 16.1 UPSTREAM NODE ELEVATION(FEET) = 1053.25 DOWNSTREAM NODE ELEVATION(FEET) = 1047.75 FLOW LENGTH(FEET) = 30.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 18.00 NUMBER OF PIPES 1 PIPE-FLOW(CFS) = 4.96 TRAVEL TIME(MIN.) _ .03 TC(MIN.) = 7.92 it ir$*ic it is de 4r 4r is it*ir*4: dt sY it it it it it it*it 4t is ir**iti: it it 3t sY it it 4r 4r 4r 4c it it s4 is fr 4t �Y is is it :r it it it it*ic *4t is it s4*9r *it it 4r 9r*4:4t :e FLOW PROCESS FROM NODE 300.00 TO NODE 300.00 IS CODE = 1 »»>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< »»>AND COMPUTE VARIOUS CONFLUENCED STREAM VALUES««< --------------------------------------------------=-------------------- TOTAL NUMBER OF STREAMS = 3 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 3 ARE: TIME OF CONCENTRATION(MIN.) = 7.92 RAINFALL INTENSITY(INCH/HR) = 3.58 AREA -AVERAGED FM(INCH/HR) = .31 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .41 EFFECTIVE STREAM AREA(ACRES) = 1.68 TOTAL STREAM AREA(ACRES) = 1.68 PEAK FLOW RATE(CFS) AT CONFLUENCE = 4.96 RAINFALL INTENSITY AND TIME OF CONCENTRATION RATIO CONFLUENCE FORMULA USED FOR 3 STREAMS. PEAK FLOW RATE TABLE ** Q Tc Intensit Fp Ap Fm Ae (CFS) (MIN.) (INCH/HR (INCH/HR) (INCH/HR) (ACRES) 1 15.00 7.73 3.631 .75 .40 .30 4.97 2 14.90 8.21 3.502 .75 .40 .30 5.14 3 15.03 7.92 3.579 .75 .40 .30 5.06 COMPUTED CONFLUENCE ESTIMATES ARE AS FOLLOWS: PEAK FLOW RATE(CFS) = 15.03 TC(MIN.) = 7.919 EFFECTIVE AREA(ACRES) = 5.06 AREA -AVERAGED Fm(INCH/HR) _ .30 AREA -AVERAGED Fp(INCH/HR) _ .75 AREA -AVERAGED Ap = .40 TOTAL AREA(ACRES) = 5.14 Page 5 it it it it ie:4 it it fir ie it it it it ie�it is ic�ic is it is sY ie is is it is ie it is*ie it is is it is ie is is is ie it ie*ie it it is it ie it is is it it*ic it it ie it it ie it ie is ie is is it is FLOW PROCESS FROM NODE 300.00 TO NODE 301.00 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< >>>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 27.0 INCH PIPE IS 18.4 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 5.2 UPSTREAM NODE ELEVATION(FEET) = 1047.75 DOWNSTREAM NODE ELEVATION(FEET) = 1045.88 FLOW LENGTH(FEET) = 467.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 27.00 NUMBER OF PIPES r 1 PIPE-FLOW(CFS) = 15.03 TRAVEL TIME(MIN.) = 1.50 TC(MIN.) = 9.41 is �• it it is it it it is is is it ie ie it ie it is is it irir it it ie is is is * it is icirir ie it it it is is it is it is it ie it is it is it it it it it ie it it is it ie is is is it it it it is is it it it is ic:4 FLOW PROCESS FROM NODE 301.00 TO NODE 301.00 IS CODE = 1 ---------------------------------------------------------------------------- »»>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< TOTAL NUMBER OF STREAMS = 3 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM l ARE: TIME OF CONCENTRATION(MIN.) = 9.41 RAINFALL INTENSITY(INCH/HR) = 3.23 AREA -AVERAGED Fm(INCH/HR) = .30 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .40 EFFECTIVE STREAM AREA(ACRES) 5.06 TOTAL STREAM AREA(ACRES) = 5.14 PEAK FLOW RATE(CFS) AT CONFLUENCE = 15.03 icyici;ieir***itiririric*isiririciri;iticir**itieiririciciciritirieic.4ricicitir*isiririririric**iriedr*ire*ir*ic**irir**iritir**�.:: FLOW PROCESS FROM NODE 301.60 TO NODE 301.50 IS CODE = 2.1 ------------------------------------------ »»>RATIONAL METHOD INITIAL SUBAREA ANALYSIS««< DEVELOPMENT IS SINGLE FAMILY RESIDENTIAL -> 5-7 DWELLINGS/ACRE TC = K*[(LENGTH** 3. 00) /(ELEVATION CHANGE)]** .20 INITIAL SUBAREA FLOW-LENGTH(FEET) = 123.00 UPSTREAM ELEVATION(FEET) = 1062.10 DOWNSTREAM ELEVATION(FEET) = 1060.25 ELEVATION DIFFERENCE(FEET) = 1.85 TC(MIN.) = .389*[( 123.00** 3.00)/( 1.85)]** .20 = 6.172 25 YEAR RAINFALL INTENSITY(INCH/HR) = 4.157 SOIL CLASSIFICATION IS "B" RESIDENTIAL-> 5-7 DWELLINGS/ACRE SUBAREA LOSS RATE, FM(INCH/HR) = .3750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) _ .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .50 SUBAREA RUNOFF(CFS) _ .48 TOTAL AREA(ACRES) = .14 PEAK FLOW RATE(CFS) _ .48 �•ic ir:r is ic'.:i:',.•::*ic4:*ism*R•:c'.rit:ci;i:i•***S:*ir*ir *i: is irsY it *ir R•iri: is k*ir�•ic'..•ic is icy*iri:s: is is ?c it is****i: is :r is :; it *:'; FLOW PROCESS FROM NODE 301.50 TO NODE 301.10 IS CODE = 6 ---------------------------------------------------------------------------- »»>COMPUTE STREET FLOW TRAVEL TIME THRU SUBAREA««< UPSTREAM ELEVATION(FEET) = 1060.25 DOWNSTREAM ELEVATION(FEET) = 1052.83 STREET LENGTH(FEET) = 238.00 CURB HEIGHT(INCHES) = 8. STREET HALFWIDTH(FEET) = 20.00 Page 6 DISTANCE FROM CROWN TO CROSSFALL GRADEBREAK(FEET) = 15.00 INTERIOR STREET CROSSFALL(DECIMAL) = .020 OUTSIDE STREET CROSSFALL(DECIMAL) = .020 SPECIFIED NUMBER OF HALFSTREETS CARRYING RUNOFF = 1 ##TRAVEL. TIME COMPUTED USING MEAN FLOW(CFS) = 1.34 STREET FLOW MODEL RESULTS: STREET FLOW DEPTH(FEET) _ .25 HALFSTREET FLOOD WIDTH(FEET) = 4.53 AVERAGE FLOW VELOCITY(FEET/SEC.) = 3.39 PRODUCT OF DEPTH&VELOCITY = .84 STREET FLOW TRAVEL TIME(MIN.) = 1.17 TC(MIN.) = 7.34 25 YEAR RAINFALL INTENSITY(INCH/HR) = 3.746 SOIL CLASSIFICATION IS "B" RESIDENTIAL-> 8-10 DWELLINGS/ACRE SUBAREA LOSS RATE, FM(INCH/HR) _ .3000 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .40 SUBAREA AREA(ACRES) = .56 SUBAREA RUNOFF(CFS) = 1.74 EFFECTIVE AREA(ACRES) _ .70 AREA -AVERAGED FM(INCH/HR) _ .32 AREA -AVERAGED Fp(INCH/HR) _ .75 AREA -AVERAGED Ap = .42 TOTAL AREA(ACRES) = .70 PEAK FLOW RATE(CFS) = 2.16 END OF SUBAREA STREET FLOW HYDRAULICS: DEPTH(FEET) = .29 HALFSTREET FLOOD WIDTH(FEET) = 6.78 FLOW VELOCITY(FEET/SEC.) = 3.33 DEPTH#VELOCITY = .98 #####ic#######iv#######�##########ie#######ir###:r##ic############�•#fir##ir####ir##sY## FLOW PROCESS FROM NODE 301.10 TO NODE 301.00 IS CODE = 3 >>>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< ESTIMATED PIPE DIAMETER(INCH) INCREASED TO 18.000 DEPTH OF FLOW IN 18.0 INCH PIPE IS 2.8 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 12.4 UPSTREAM NODE ELEVATION(FEET) = 1052.83 DOWNSTREAM NODE ELEVATION(FEET) = 1045.88 FLOW LENGTH(FEET) = 40.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 18.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 2.16 TRAVEL TIME(MIN.) _ .05 TC(MIN.) = 7.40 FLOW PROCESS FROM NODE 301.00 TO NODE 301.00 IS CODE = 1 ---------------------------------------------------------------------------- »»>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< TOTAL NUMBER OF STREAMS = 3 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 2 ARE: TIME OF CONCENTRATION(MIN.) = 7.40 RAINFALL INTENSITY(INCH/HR) = 3.73 AREA -AVERAGED FM(INCH/HR) = .32 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .42 EFFECTIVE STREAM AREA(ACRES) _ .70 TOTAL STREAM AREA(ACRES) = .70 PEAK FLOW RATE(CFS) AT CONFLUENCE = 2.16 ####iei:#####dr ir#########f:#:####�4##############ir it#######################i.•#ir it##ic# FLOW PROCESS FROM NODE 301.40 TO NODE 301.30 IS CODE = 2.1 ---------------------------------------------------------------------------- Page 7 »»>RATIONAL METHOD INITIAL SUBAREA ANALYSIS««< DEVELOPMENT IS SINGLE FAMILY RESIDENTIAL -> 5-7 DWELLINGS/ACRE TC = K*[(LENGTH** 3.00)/(ELEVATION CHANGE)]** .20 INITIAL SUBAREA FLOW-LENGTH(FEET) = 177.00 UPSTREAM ELEVATION(FEET) = 1062.40 DOWNSTREAM ELEVATION(FEET) = 1060.46 ELEVATION DIFFERENCE(FEET) = 1.94 TC(MIN.) = .389*[( 177.00** 3.00)/( 1.94)]** .20 = 7.606 25 YEAR RAINFALL INTENSITY(INCH/HR) = 3.667 SOIL CLASSIFICATION IS "B" RESIDENTIAL-> 5-7 DWELLINGS/ACRE SUBAREA LOSS RATE, FM(INCH/HR) = .3750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .50 SUBAREA RUNOFF(CFS) _ .89 TOTAL AREA(ACRES) = .30 PEAK FLOW RATE(CFS) _ .89 ****4: '.r **:c'..•*ir it ir* �•4r*ir*4r is t: it it it sY is Ye:rir*it it it it is do is kxic**:r is it �r Y it is it 4r it it ic'.c 4c ic:r it it iric 4c Yc ie is dc'c is it it 4r it it FLOW PROCESS FROM NODE 301.30 TO NODE 301.20 IS CODE = 6 ------------------------------------------------ »»>COMPUTE STREET FLOW TRAVEL TIME THRU SUBAREA««< UPSTREAM ELEVATION(FEET) = 1060.46 DOWNSTREAM ELEVATION(FEET) = 1052.77 STREET LENGTH(FEET) = 320.00 CURB HEIGHT(INCHES) = 8. STREET HALFWIDTH(FEET) = 20.00 DISTANCE FROM CROWN TO CROSSFALL GRADEBREAK(FEET) = 15.00 INTERIOR STREET CROSSFALL(DECIMAL) = .020 OUTSIDE STREET CROSSFALL(DECIMAL) = .020 SPECIFIED NUMBER OF HALFSTREETS CARRYING RUNOFF = 1 **TRAVEL TIME COMPUTED USING MEAN FLOW(CFS) = 3.72 STREET FLOW MODEL RESULTS: STREET FLOW DEPTH(FEET) _ .35 HALFSTREET FLOOD WIDTH(FEET) = 9.59 AVERAGE FLOW VELOCITY(FEET/SEC.) = 3.35 PRODUCT OF DEPTH&VELOCITY = 1.17 STREET FLOW TRAVEL TIME(MIN.) = 1.59 TC(MIN.) = 9.20 25 YEAR RAINFALL INTENSITY(INCH/HR) = 3.272 SOIL CLASSIFICATION IS "B" RESIDENTIAL-> 8-10 DWELLINGS/ACRE SUBAREA LOSS RATE, Fm(INCH/HR) = .3000 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .40 SUBAREA AREA(ACRES) = 2.10 SUBAREA RUNOFF(CFS) = 5.62 EFFECTIVE AREA(ACRES) = 2.40 AREA -AVERAGED FM(INCH/HR) _ .31 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .41 TOTAL AREA(ACRES) = 2.40 PEAK FLOW RATE(CFS) = 6.40 END OF SUBAREA STREET FLOW HYDRAULICS: DEPTH(FEET) = .40 HALFSTREET FLOOD WIDTH(FEET) = 11.84 FLOW VELOCITY(FEET/SEC.) = 4.02 DEPTH*VELOCITY = 1.59 �•:k*::4t*'.c�•'r**'t 4c i:4r:4**ir is is*fr**Yc'rdc.*4r*ir Yr is 4r it it is �r fc*4r*.'t 4r is it it it****4c.**ir**4t*ic is �c irX***it is*�.:'.c *4:. FLOW PROCESS FROM NODE 301.20 TO NODE 301.00 IS CODE = 3 ---------------------------------------------------------------------------- »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< ESTIMATED PIPE DIAMETER(INCH) INCREASED TO 18.000 DEPTH OF FLOW IN 18.0 INCH PIPE IS 4.3 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 19.5 UPSTREAM NODE ELEVATION(FEET) = 1052.77 Page 8 DOWNSTREAM NODE ELEVATION(FEET) = 1045.88 FLOW LENGTH(FEET) = 27.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 18.00 NUMBER OF PIPES = PIPE-FLOW(CFS) = 6.40 TRAVEL TIME(MIN.) _ .02 TC(MIN.) = 9.22 it is is it it is it is it is it is it it t: ie is is it is fr it it ie is it ir&ir is it it it it it ie it it it is ie is is is itit it is is it is is is is is is is is it ie it it is it it it is it is ie is it it it i:Ye FLOW PROCESS FROM NODE 301.00 TO NODE 301.00 IS CODE = 1 »»>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< »»>AND COMPUTE VARIOUS CONFLUENCED STREAM VALUES««< ----------------------------------------------------------------------- TOTAL NUMBER OF STREAMS = 3 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 3 ARE: TIME OF CONCENTRATION(MIN.) = 9.22 RAINFALL INTENSITY(INCH/HR) = 3.27 AREA -AVERAGED Fm(INCH/HR) = .31 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .41 EFFECTIVE STREAM AREA(ACRES) = 2.40 TOTAL STREAM AREA(ACRES) = 2.40 PEAK FLOW RATE(CFS) AT CONFLUENCE = 6.40 RAINFALL INTENSITY AND TIME OF CONCENTRATION RATIO CONFLUENCE FORMULA USED FOR 3 STREAMS. ** PEAK FLOW RATE TABLE ** Q Tc Intensit Fp Ap Fm Ae (CFS) (MIN.) (INCH/H� (INCH/HR) (INCH/HR) (ACRES) 1 22.00 7.40 3.729 .75 .41 .31 6.61 2 23.26 9.23 3.266 .75 .41 .31 8.07 3 23.18 9.41 3.227 .75 .41 .31 8.16 4 22.89 9.71 3.167 .75 .41 .31 8.24 5 23.26 9.22 3.267 .75 .41 .31 8.07 COMPUTED CONFLUENCE ESTIMATES ARE AS FOLLOWS: PEAK FLOW RATE(CFS) = 23.26 TC(MIN.) = 9.221 EFFECTIVE AREA(ACRES) 8.07 AREA -AVERAGED Fm(INCH/HR) _ .31 AREA -AVERAGED Fp(INCH/HR) _ .75 AREA -AVERAGED Ap = .41 TOTAL AREA(ACRES) = 8.24 sY.i:**it*ic it 4c �Y is*ir is it*ir it*ir it it it is*ic it is is it it it ie is is is is it it it it it it is it it ic•k it it is i:i:ic is is it it it it ie is is is is it it is is it is sY is it ick FLOW PROCESS FROM NODE 301.00 TO NODE 302.00 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 30.0 INCH PIPE IS 23.2 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 5.7 UPSTREAM NODE ELEVATION(FEET) = 1045.88 DOWNSTREAM NODE ELEVATION(FEET) = 1043.16 FLOW LENGTH(FEET) = 681.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 30.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 23.26 TRAVEL TIME(MIN.) = 1.99 TC(MIN.) = 11.21 *i; is i; *�Y it*ie is is is is �•i: ie �: it R•*ic*':**:tic*****i:ir�..•ic it ic:es:*iri:ir*:'r4;�•�r�•*9t*:c�•':it�•fc�•:r 4: 4r is it**it i; it �Y �.•4r**ic FLOW PROCESS FROM NODE 302.00 TO NODE 302.00 IS CODE = 1 ---------------------------------------------------------------------------- »»>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< TOTAL NUMBER OF STREAMS = 3 Page 9 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 1 ARE: TIME OF CONCENTRATION(MIN.) = 11.21 RAINFALL INTENSITY(INCH/HR) = 2.91 AREA -AVERAGED FM(INCH/HR) = .31 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .41 EFFECTIVE STREAM AREA(ACRES) = 8.07 TOTAL STREAM AREA(ACRES) = 8.24 PEAK FLOW RATE(CFS) AT CONFLUENCE = 23.26 is is ie ie ie it ie it ie is ie ie it it it stir it it ie is it is it it ie ie is ie it it it is ie it sY it it it it it is it it it it it ie it#ir is it iric is it is it it is it it ie it it it is ie it is it is it it it FLOW PROCESS FROM NODE 302.40 TO NODE 302.30 IS CODE = 2.1 ---------------------------------------------------------------------------- »»>RATIONAL METHOD INITIAL SUBAREA ANALYSIS««< ---------------------------------------------------------------------------- ---------------------------------------------------------------------------- DEVELOPMENT IS SINGLE FAMILY RESIDENTIAL -> 5-7 DWELLINGS/ACRE TC = K*[(LENGTH** 3.00)/(ELEVATION CHANGE)]** .20 INITIAL SUBAREA FLOW-LENGTH(FEET) = 128.00 UPSTREAM ELEVATION(FEET) = 1060.20 DOWNSTREAM ELEVATION(FEET) = 1058.41 ELEVATION DIFFERENCE(FEET) = 1.79 TC(MIN.) = .389*[( 128.00** 3.00)/( 1.79)] ** .20 = 6.364 25 YEAR RAINFALL INTENSITY(INCH/HR) = 4.081 SOIL CLASSIFICATION IS "B" RESIDENTIAL-> 5-7 DWELLINGS/ACRE SUBAREA LOSS RATE, FM(INCH/HR) = .3750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) _ .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .50 SUBAREA RUNOFF(CFS) _ .50 TOTAL AREA(ACRES) = .15 PEAK FLOW RATE(CFS) _ .50 is it is it it it it is it is it it is it it it it*ir it it it it it it ie it it ie is*it is ie is it ie ie it it ie*ir it it it it it it it sY is it sY is it it itit it it it it is is is it it it is sY is is it it it FLOW PROCESS FROM NODE 302.30 TO NODE 302.10 IS CODE = 6 ---------------------------------------------------------------------------- »»>COMPUTE STREET FLOW TRAVEL TIME THRU SUBAREA««< UPSTREAM ELEVATION(FEET) = 1058.41 DOWNSTREAM ELEVATION(FEET) = 1046.00 STREET LENGTH(FEET) = 619.00 CURB HEIGHT(INCHES) = 8. STREET HALFWIDTH(FEET) = 20.00 DISTANCE FROM CROWN TO CROSSFALL GRADEBREAK(FEET) = 15.00 INTERIOR STREET CROSSFALL(DECIMAL) = .020 OUTSIDE STREET CROSSFALL(DECIMAL) = .020 SPECIFIED NUMBER OF HALFSTREETS CARRYING RUNOFF = 1 "TRAVEL TIME COMPUTED USING MEAN FLOW(CFS) = 3.08 STREET FLOW MODEL RESULTS: STREET FLOW DEPTH(FEET) _ .34 HALFSTREET FLOOD WIDTH(FEET) = 9.03 AVERAGE FLOW VELOCITY(FEET/SEC.) = 3.07 PRODUCT OF DEPTH&VELOCITY = 1.04 STREET FLOW TRAVEL TIME(MIN.) = 3.36 TC(MIN.) = 9.73 25 YEAR RAINFALL INTENSITY(INCH/HR) = 3.164 SOIL CLASSIFICATION IS "B" RESIDENTIAL-> 8-10 DWELLINGS/ACRE SUBAREA LOSS RATE, FM(INCH/HR) = .3000 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .40 SUBAREA AREA(ACRES) = 1.96 SUBAREA RUNOFF(CFS) = 5.05 EFFECTIVE AREA(ACRES) = 2.11 AREA -AVERAGED FM(INCH/HR) _ .31 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .41 TOTAL AREA(ACRES) = 2.11 PEAK FLOW RATE(CFS) = 5.43 END OF SUBAREA STREET FLOW HYDRAULICS: Page 10 DEPTH(FEET) = .40 HALFSTREET FLOOD WIDTH(FEET) = 11.84 FLOW VELOCITY(FEET/SEC.) = 3.41 DEPTH*VELOCITY = 1.35 YriririririsYr�'rir'.riririririciricititir�'t9ric9tic�Ylc.*9tkicitirir�'cic*4c4c1ciricYticiriCititiririciticYciclYititir4r4cic4rir4r4tir4ritirYrir4rirsY4e FLOW PROCESS FROM NODE 302.10 TO NODE 302.00 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW) ««< ESTIMATED PIPE DIAMETER(INCH) INCREASED TO 18.000 DEPTH OF FLOW IN 18.0 INCH PIPE IS 6.6 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 9.3 UPSTREAM NODE ELEVATION(FEET) = 1046.00 DOWNSTREAM NODE ELEVATION(FEET) = 1043.16 FLOW LENGTH(FEET) = 78.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 18.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 5.43 TRAVEL TIME(MIN.) _ .14 TC(MIN.) = 9.87 is is is it it is � is it is it is it it i; it is itir ie ie it it is it it is ie is is it * sY is it it is is is is it ie *ir ie is is it it it it it ie ie $tir it is it is it it is is is ie ie is it is ie * it it ie ie FLOW PROCESS FROM NODE 302.00 TO NODE 302.00 IS CODE = 1 ---------------------------------------- »»>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< TOTAL NUMBER OF STREAMS = 3 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 2 ARE: TIME OF CONCENTRATION(MIN.) = 9.87 RAINFALL INTENSITY(INCH/HR) = 3.14 AREA -AVERAGED Fm(INCH/HR) = .31 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .41 EFFECTIVE STREAM AREA(ACRES) = 2.11 TOTAL STREAM AREA(ACRES) = 2.11 PEAK FLOW RATE(CFS) AT CONFLUENCE = 5.43 �': �•*ic**ic it is***ir*ir it*it•k*4c is****ic s4 is it*ir it is ie ic**ir*ic it it it*ic is is sY it it it stir it*'�Y it it it it is is it it it icic*ie is***ir �• FLOW PROCESS FROM NODE 302.60 TO NODE 302.50 IS CODE = 2.1 ---------------------------------------------------------------------------- »»>RATIONAL METHOD INITIAL SUBAREA ANALYSIS««< DEVELOPMENT IS SINGLE FAMILY RESIDENTIAL -> 5-7 DWELLINGS/ACRE TC = K*[(LENGTH** 3.00)/(ELEVATION CHANGE)]** .20 INITIAL SUBAREA FLOW-LENGTH(FEET) = 176.00 UPSTREAM ELEVATION(FEET) = 1062.60 DOWNSTREAM ELEVATION(FEET) = 1060.75 ELEVATION DIFFERENCE(FEET) = 1.85 TC(MIN.) = .389*[( 176.00** 3.00)/( 1.85)]** .20 = 7.653 25 YEAR RAINFALL INTENSITY(INCH/HR) = 3.654 SOIL CLASSIFICATION IS "B" RESIDENTIAL-> 5-7 DWELLINGS/ACRE SUBAREA LOSS RATE, Fm(INCH/HR) = .3750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) _ .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .50 SUBAREA RUNOFF(CFS) _ .77 TOTAL AREA(ACRES) = .26 PEAK FLOW RATE(CFS) _ .77 is**ir it is it*ic it is is is is it is is*ic it is is is**i; it it it it ir^k sY Yc is it is it sY it is is it it is is**it it it it is icic it is it sY it is is :Y *ic it is i.•ir is is *i: 'c is i; FLOW PROCESS FROM NODE 302.50 TO NODE 302.20 IS CODE = 6 ---------------------------------------------------------------------------- »»>COMPUTE STREET FLOW TRAVEL TIME THRU SUBAREA««< UPSTREAM ELEVATION(FEET) = 1060.75 DOWNSTREAM ELEVATION(FEET) = 1046.24 Page 11 STREET LENGTH(FEET) = 959.00 CURB HEIGHT(INCHES) = 8. STREET HALFWIDTH(FEET) = 20.00 DISTANCE FROM CROWN TO CROSSFALL GRADEBREAK(FEET) = 15.00 INTERIOR STREET CROSSFALL(DECIMAL) = .020 OUTSIDE STREET CROSSFALL(DECIMAL) = .020 SPECIFIED NUMBER OF HALFSTREETS CARRYING RUNOFF = 1 **TRAVEL TIME COMPUTED USING MEAN FLOW(CFS) = 4.41 STREET FLOW MODEL RESULTS: STREET FLOW DEPTH(FEET) _ .38 HALFSTREET FLOOD WIDTH(FEET) = 11.28 AVERAGE FLOW VELOCITY(FEET/SEC.) = 3.01 PRODUCT OF DEPTH&VELOCITY = 1.16 STREET FLOW TRAVEL TIME(MIN.) = 5.30 TC(MIN.) = 12.96 25 YEAR RAINFALL INTENSITY(INCH/HR) = 2.664 SOIL CLASSIFICATION IS "B" RESIDENTIAL-> 8-10 DWELLINGS/ACRE SUBAREA LOSS RATE, FM(INCH/HR) _ .3000 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .40 SUBAREA AREA(ACRES) = 3.34 SUBAREA RUNOFF(CFS) = 7.11 EFFECTIVE AREA(ACRES) = 3.60 AREA -AVERAGED FM(INCH/HR) _ .31 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .41 TOTAL AREA(ACRES) = 3.60 PEAK FLOW RATE(CFS) = 7.64 END OF SUBAREA STREET FLOW HYDRAULICS: DEPTH(FEET) = .44 HALFSTREET FLOOD WIDTH(FEET) = 14.09 FLOW VELOCITY(FEET/SEC.) = 3.51 DEPTH*VELOCITY = 1.55 FLOW PROCESS FROM NODE 302.20 TO NODE 302.00 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< ESTIMATED PIPE DIAMETER(INCH) INCREASED TO 18.000 DEPTH OF FLOW IN 18.0 INCH PIPE IS 6.0 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 14.8 UPSTREAM NODE ELEVATION(FEET) = 1046.24 DOWNSTREAM NODE ELEVATION(FEET) = 1043.16 FLOW LENGTH(FEET) = 30.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 18.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 7.64 TRAVEL TIME(MIN.) _ .03 TC(MIN.) = 12.99 FLOW PROCESS FROM NODE 302.00 TO NODE 302.00 IS CODE = 1 ---------------------------------------------------------------------------- »»>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< »»>AND COMPUTE VARIOUS CONFLUENCED STREAM VALUES««< -------------------------------------------------------=--------------- TOTAL NUMBER OF STREAMS = 3 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 3 ARE: TIME OF CONCENTRATION(MIN.) = 12.99 RAINFALL INTENSITY(INCH/HR) = 2.66 AREA -AVERAGED FM(INCH/HR) = .31 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .41 EFFECTIVE STREAM AREA(ACRES) = 3.60 TOTAL STREAM AREA(ACRES) = 3.60 PEAK FLOW RATE(CFS) AT CONFLUENCE = 7.64 Page 12 RAINFALL INTENSITY AND TIME OF CONCENTRATION RATIO CONFLUENCE FORMULA USED FOR 3 STREAMS. PEAK FLOW RATE TABLE ** Q Tc Intensit Fp Ap FM Ae (CFS) (MIN.) (INCH/HR� (INCH/HR) (INCH/HR) (ACRES) 1 34.21 9.40 3.230 .75 .41 .31 11.22 2 34.73 9.87 3.137 .75 .41 .31 11.83 3 35.53 11.21 2.905 .75 .41 .31 13.29 4 35.53 11.22 2.904 .75 .41 .31 13.29 5 35.44 11.41 2.876 .75 .41 .31 13.43 6 35.12 11.71 2.831 .75 .41 .31 13.59 7 33.49 12.99 2.660 .75 .41 .31 13.95 COMPUTED CONFLUENCE ESTIMATES ARE AS FOLLOWS: PEAK FLOW RATE(CFS) = 35.53 TC(MIN.) = 11.212 EFFECTIVE AREA(ACRES) = 13.29 AREA -AVERAGED FM(INCH/HR) _ .31 AREA -AVERAGED Fp(INCH/HR) _ .75 AREA -AVERAGED Ap = .41 TOTAL AREA(ACRES) = 13.95 ie i::': *4: it it*ir �Y* �•*h ir�ir 4c� �Yf:4r it 9c is is*9c is 4c'.r ii it ie fr it i:ir�'r �r 4c i:�r�'i it 4r it 4r it*die it sY is ie ie it it it is �'c it it is 4r*ie fr oY 9r is it Pc 7e it FLOW PROCESS FROM NODE 302.00 TO NODE 303.00 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 36.0 INCH PIPE IS 26.4 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 6.4 UPSTREAM NODE ELEVATION(FEET) = 1043.16 DOWNSTREAM NODE ELEVATION(FEET) = 1042.19 FLOW LENGTH(FEET) = 242.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 36.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 35.53 TRAVEL TIME(MIN.) _ .63 TC(MIN.) = 11.84 is****ic �i: it is*�:**it it is i:'.c it �k is*ir�ic is is is*:kir*ir is *ic it*:Y is is i:*�•4c it*4c i:'.'iris**i:ic:t�:r *ir �c it �':c fir �"**ir it is 9c is FLOW PROCESS FROM NODE 303.00 TO NODE 303.00 IS CODE = 1 ---------------------------------------------------------------------------- »»>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< TOTAL NUMBER OF STREAMS = 3 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 1 ARE: TIME OF CONCENTRATION(MIN.) = 11.84 RAINFALL INTENSITY(INCH/HR) = 2.81 AREA -AVERAGED Fm(INCH/HR) = .31 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .41 EFFECTIVE STREAM AREA(ACRES) = 13.29 TOTAL STREAM AREA(ACRES) = 13.95 PEAK FLOW RATE(CFS) AT CONFLUENCE = 35.53 is it is it i.•is ie isi:iri:�•ici:*iri:*i:*ic�•****ir it is it sY is*ir is it it*ir**ie it**ir °k ie is it 4:**ie*iris*f: *ir*sic is is �*ir s; it it is s; ir'.: FLOW PROCESS FROM NODE 303.60 TO NODE 303.50 IS CODE = 2.1 ---------------------------------------------------------------------------- »»>RATIONAL METHOD INITIAL SUBAREA ANALYSIS««< DEVELOPMENT IS SINGLE FAMILY RESIDENTIAL -> 5-7 DWELLINGS/ACRE TC = K*[(LENGTH** 3.00)/(ELEVATION CHANGE)]** .20 INITIAL SUBAREA FLOW-LENGTH(FEET) = 177.00 UPSTREAM ELEVATION(FEET) = 1055.90 DOWNSTREAM ELEVATION(FEET) = 1054.15 ELEVATION DIFFERENCE(FEET) = 1.75 Page 13 TC(MIN.) = .389*[( 177.00** 3.00)/( 1.75)]** .20 = 7.765 25 YEAR RAINFALL INTENSITY(INCH/HR) = 3.622 SOIL CLASSIFICATION IS "B" RESIDENTIAL-> 5-7 DWELLINGS/ACRE SUBAREA LOSS RATE, FM(INCH/HR) = .3750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .50 SUBAREA RUNOFF(CFS) _ .76 TOTAL AREA(ACRES) = .26 PEAK FLOW RATE(CFS) _ .76 it is is it it it is is ir*ir ie is ie it is is is it it i:i: is is Yr is ie'lc ie is it it it ic'k is it i:i: is Yc is it is it it ie it it is it it is ie itir is it it is is ie it is is it it is it it is is it is is is FLOW PROCESS FROM NODE 303.50 TO NODE 303.10 IS CODE = 6 ---------------------------------------------------------------------------- »»>COMPUTE STREET FLOW TRAVEL TIME THRU SUBAREA««< UPSTREAM ELEVATION(FEET) = 1054.15 DOWNSTREAM ELEVATION(FEET) = 1046.17 STREET LENGTH(FEET) = 359.00 CURB HEIGHT(INCHES) = 8. STREET HALFWIDTH(FEET) = 20.00 DISTANCE FROM CROWN TO CROSSFALL GRADEBREAK(FEET) = 15.00 INTERIOR STREET CROSSFALL(DECIMAL) = .020 OUTSIDE STREET CROSSFALL(DECIMAL) = .020 SPECIFIED NUMBER OF HALFSTREETS CARRYING RUNOFF = 1 **TRAVEL TIME COMPUTED USING MEAN FLOW(CFS) = 2.70 STREET FLOW MODEL RESULTS: STREET FLOW DEPTH(FEET) _ .32 HALFSTREET FLOOD WIDTH(FEET) = 7.91 AVERAGE FLOW VELOCITY(FEET/SEC.) = 3.31 PRODUCT OF DEPTH&VELOCITY = 1.05 STREET FLOW TRAVEL TIME(MIN.) = 1.81 TC(MIN.) = 9.57 25 YEAR RAINFALL INTENSITY(INCH/HR) = 3.194 SOIL CLASSIFICATION IS "B" RESIDENTIAL-> 8-10 DWELLINGS/ACRE SUBAREA LOSS RATE, FM(INCH/HR) = .3000 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .40 SUBAREA AREA(ACRES) = 1.49 SUBAREA RUNOFF(CFS) = 3.88 EFFECTIVE AREA(ACRES) = 1.75 AREA -AVERAGED FM(INCH/HR) _ .31 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .41 TOTAL AREA(ACRES) = 1.75 PEAK FLOW RATE(CFS) = 4.54 END OF SUBAREA STREET FLOW HYDRAULICS: DEPTH(FEET) = .36 HALFSTREET FLOOD WIDTH(FEET) = 10.16 FLOW VELOCITY(FEET/SEC.) = 3.72 DEPTH*VELOCITY = 1.34 �; it it*ir is*i::;i: �i:i: it it it it 4r::;:i:i: is ie k**i: it tr*ir ie::*ir*ie**i: ir�ir it it is it it ie*�•i; it ie is ki:i: is icy:: it it ;r it it it i; is*�•�•i: is FLOW PROCESS FROM NODE 303.10 TO NODE 303.00 IS CODE = 3 >>>>>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< ESTIMATED PIPE DIAMETER(INCH) INCREASED TO 18.000 DEPTH OF FLOW IN 18.0 INCH PIPE IS 4.8 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 12.0 UPSTREAM NODE ELEVATION(FEET) = 1046.17 DOWNSTREAM NODE ELEVATION(FEET) = 1042.19 FLOW LENGTH(FEET) = 46.00 MANNING`S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 18.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 4.54 TRAVEL TIME(MIN.) .06 TC(MIN.) 9.64 ': is :: it it i.•it is is i:i:ieY:i;i:***i:i:i:i:'..•***ir it*iri:*ici:i:i:i:it*icR•i: it it it is*'.c it it***ic':iti:ic***ic it is*ir k it*'.: it :.•i: it :c is Page 14 FLOW PROCESS FROM NODE 303.00 TO NODE 303.00 IS CODE = 1 -------------------------------------------------------------- »»>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< TOTAL NUMBER OF STREAMS = 3 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 2 ARE: TIME OF CONCENTRATION(MIN.) = 9.64 RAINFALL INTENSITY(INCH/HR) = 3.18 AREA -AVERAGED Fm(INCH/HR) = .31 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .41 EFFECTIVE STREAM AREA(ACRES) = 1.75 TOTAL STREAM AREA(ACRES) = 1.75 PEAK FLOW RATE(CFS) AT CONFLUENCE = 4.54 is is it it is it it it it it is it it it is is is is is it is is is is is it ie it is it is is is is is it it it it it it ie it it it is it it it is is it it it it is is it is it is is it is is is it it is * is is is it is it FLOW PROCESS FROM NODE 303.40 TO NODE 303.30 IS CODE = 2.1 --------------------------------------------- »»>RATIONAL METHOD INITIAL SUBAREA ANALYSIS««< DEVELOPMENT IS SINGLE FAMILY RESIDENTIAL -> 5-7 DWELLINGS/ACRE TC = K*[(LENGTH** 3. 00) /(ELEVATION CHANGE)]** .20 INITIAL SUBAREA FLOW-LENGTH(FEET) = 181.00 UPSTREAM ELEVATION(FEET) = 1056.00 DOWNSTREAM ELEVATION(FEET) = 1054.16 ELEVATION DIFFERENCE(FEET) = 1.84 TC(MIN.) = .389*[( 181.00** 3.00)/( 1.84)]** .20 = 7.791 25 YEAR RAINFALL INTENSITY(INCH/HR) = 3.615 SOIL CLASSIFICATION IS "B" RESIDENTIAL-> 5-7 DWELLINGS/ACRE SUBAREA LOSS RATE, Fm(INCH/HR) = .3750 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .50 SUBAREA RUNOFF(CFS) _ .70 TOTAL AREA(ACRES) = .24 PEAK FLOW RATE(CFS) _ .70 it it is is irir it sY*ir it it is it it is is it**ic is it**it ie is it*ic it***it it it**it it*it k is is it**ie is is is it it is is is it *ir it it it it it it it it is**ir*�• FLOW PROCESS FROM NODE 303.30 TO NODE 303.20 IS CODE = 6 ---------------------------------------------------------------------------- »»>COMPUTE STREET FLOW TRAVEL TIME THRU SUBAREA««< UPSTREAM ELEVATION(FEET) = 1054.16 DOWNSTREAM ELEVATION(FEET) = 1046.00 STREET LENGTH(FEET) = 384.00 CURB HEIGHT(INCHES) = 8. STREET HALFWIDTH(FEET) = 20.00 DISTANCE FROM CROWN TO CROSSFALL GRADEBREAK(FEET) = 15.00 INTERIOR STREET CROSSFALL(DECIMAL) = .020 OUTSIDE STREET CROSSFALL(DECIMAL) = .020 SPECIFIED NUMBER OF HALFSTREETS CARRYING RUNOFF = 1 "TRAVEL TIME COMPUTED USING MEAN FLOW(CFS) = 2.51 STREET FLOW MODEL RESULTS: STREET FLOW DEPTH(FEET) _ .32 HALFSTREET FLOOD WIDTH(FEET) = 7.91 AVERAGE FLOW VELOCITY(FEET/SEC.) = 3.08 PRODUCT OF DEPTH&VELOCITY = .97 STREET FLOW TRAVEL TIME(MIN.) = 2.08 TC(MIN.) = 9.87 25 YEAR RAINFALL INTENSITY(INCH/HR) = 3.137 SOIL CLASSIFICATION IS "B" RESIDENTIAL-> 8-10 DWELLINGS/ACRE SUBAREA LOSS RATE, Fm(INCH/HR) = .3000 SUBAREA PERVIOUS LOSS RATE, Fp(INCH/HR) = .75 SUBAREA PERVIOUS AREA FRACTION, Ap = .40 Page 15 SUBAREA AREA(ACRES) = 1.42 SUBAREA RUNOFF(CFS) = 3.63 EFFECTIVE AREA(ACRES) = 1.66 AREA -AVERAGED Fm(INCH/HR) _ .31 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .41 TOTAL AREA(ACRES) = 1.66 PEAK FLOW RATE(CFS) = 4.22 END OF SUBAREA STREET FLOW HYDRAULICS: DEPTH(FEET) = .36 HALFSTREET FLOOD WIDTH(FEET) = 10.16 FLOW VELOCITY(FEET/SEC.) = 3.46 DEPTH*VELOCITY = 1.25 icir is it is it is sY is ie it is it is is is is * is it is it it is it it it it it it it sY it it it it is it ^h it iric it it ie is is is it sY is it irit itx * it it it it it it it * it it is icit is is sY itit it FLOW PROCESS FROM NODE 303.20 TO NODE 303.00 IS CODE = 3 >>>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< ESTIMATED PIPE DIAMETER(INCH) INCREASED TO 18.000 DEPTH OF FLOW IN 18.0 INCH PIPE IS 4.7 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 11.6 UPSTREAM NODE ELEVATION(FEET) = 1046.00 DOWNSTREAM NODE ELEVATION(FEET) = 1042.19 FLOW LENGTH(FEET) = 46.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 18.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 4.22 TRAVEL TIME(MIN.) _ .07 TC(MIN.) = 9.93 *it iticir�icits4iritit*iris*ir*it*it**icicitit it itic*icieicititiricitititiciciciciticitiricicir*iriciririririritititicir***iririeitir*icic FLOW PROCESS FROM NODE 303.00 TO NODE 303.00 IS CODE = 1 »»>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE««< >>>AND COMPUTE VARIOUS CONFLUENCED STREAM VALUES««< TOTAL NUMBER OF STREAMS = 3 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 3 ARE: TIME OF CONCENTRATION(MIN.) = 9.93 RAINFALL INTENSITY(INCH/HR) = 3.12 AREA -AVERAGED Fm(INCH/HR) = .31 AREA -AVERAGED Fp(INCH/HR) = .75 AREA -AVERAGED Ap = .41 EFFECTIVE STREAM AREA(ACRES) = 1.66 TOTAL STREAM AREA(ACRES) = 1.66 PEAK FLOW RATE(CFS) AT CONFLUENCE = 4.22 RAINFALL INTENSITY AND TIME OF CONCENTRATION RATIO CONFLUENCE FORMULA USED FOR 3 STREAMS. ** PEAK FLOW RATE TABLE ** Q Tc Intensity Fp Ap FM Ae (CFS) (MIN.) (INCH/HR) (INCH/HR) (INCH/HR) (ACRES) 1 42.47 9.64 3.182 .75 .41 .31 14.14 2 42.82 10.03 3.106 .75 .41 .31 14.63 3 43.09 10.50 3.022 .75 .41 .31 15.24 4 43.24 11.84 2.812 .75 .41 .31 16.70 5 43.23 11.85 2.811 .75 .41 .31 16.70 6 43.06 12.04 2.784 .75 .41 .31 16.84 7 42.62 12.34 2.743 .75 .41 .31 17.00 8 40.50 13.63 2.585 .75 .41 .31 17.36 9 42.76 9.93 3.124 .75 .41 .31 14.52 COMPUTED CONFLUENCE ESTIMATES ARE AS FOLLOWS: PEAK FLOW RATE(CFS) = 43.24 TC(MIN.) = 11.842 EFFECTIVE AREA(ACRES) = 16.70 AREA -AVERAGED FM(INCH/HR) _ .31 AREA -AVERAGED Fp(INCH/HR) _ .75 AREA -AVERAGED Ap = .41 TOTAL AREA(ACRES) = 17.36 Page 16 it Yr Ye Yc * Ye Yr ie Yr Ye Yr Yc Yr Yr *Yc Ye Yr * Yc Yr Yc Yr Yr Ye Yc Yr Yr Yr Yc Ye Ye Ye it Yc * YcYc Yc it Ye Ye Yr it *Yc Yr *Yr Yc * Ye Yrie fr Yc Yr ie Yc Yc Yc Ye Yr Ye Yr Yr Ye Ye Yr Ye Ye Yc Ye Yc Yr Ye FLOW PROCESS FROM NODE 303.00 TO NODE 400.00 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME ------------------------ THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< -------------------------------------------------------------------- DEPTH OF FLOW IN 39.0 INCH PIPE IS 28.2 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 6.7 UPSTREAM NODE ELEVATION(FEET) = 1042.19 DOWNSTREAM NODE ELEVATION(FEET) = 1041.27 FLOW LENGTH(FEET) = 230.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 39.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 43.24 TRAVEL TIME(MIN.) _ .57 TC(MIN.) = 12.41 --------------------------------------------------------------------- END OF STUDY SUMMARY: TOTAL AREA(ACRES) = 17.36 TC(MIN.) = 12.41 EFFECTIVE AREA(ACRES) = 16.70 AREA -AVERAGED FM(INCH/HR)= .31 AREA -AVERAGED Fp(INCH/HR) _ .75 AREA -AVERAGED Ap = .41 PEAK FLOW RATE(CFS) = 43.24 PEAK FLOW RATE TABLE ** Q TC Intensit Fp Ap FM Ae (CFS) (MIN.) (INCH/HR� (INCH/HR) (INCH/HR) (ACRES) 1 42.47 10.21 3.074 .75 .41 .31 14.14 2 42.76 10.50 3.021 .75 .41 .31 14.52 3 42.82 10.60 3.004 .75 .41 .31 14.63 4 43.09 11.07 2.928 .75 .41 .31 15.24 5 43.24 12.41 2.733 .75 .41 .31 16.70 6 43.23 12.42 2.733 .75 .41 .31 16.70 7 43.06 12.61 2.708 .75 .41 .31 16.84 8 42.62 12.91 2.670 .75 .41 .31 17.00 9 40.50 14.20 2.521 .75 .41 .31 17.36 - ------------------------------------------------------------------- END OF RATIONAL METHOD ANALYSIS Page 17 Yr is Yc �Y Yr Yr is it Ye Yr Ye it Yc Yr Yr * it * it Ye Ye Yc Yc Yr Ye is Yr Yr Ye Yc is *Yr Yc Yc ie Yr Ye Yr it Yc YCYc it Yc Ye Yr * is Yc ie Ye Yc * Yr Ye * is it Y; Yr it it Yc Ye Yc * Yr Yc Yc it * Ye Yc Ye it RATIONAL METHOD HYDROLOGY COMPUTER PROGRAM PACKAGE (Reference: 1986 SAN BERNARDINO CO. HYDROLOGY CRITERION) (c) Copyright 1983-93 Advanced Engineering Software (aes) ver. 1.9B Release Date: 7/18/93 License ID 1202 Analysis prepared by: HUITT-ZOLLARS, INC. 15101 RED HILL AVENUE TUSTIN, CALIFORNIA 92780-6500 PHONE (714) 259-7900 it FAX (714) 259-0210 ---------------------------------------------------------------------------- FILE NAME: F025SRAB.DAT TIME/DATE OF STUDY: 13:15 6/14/2004 USER SPECIFIED HYDROLOGY AND HYDRAULIC MODEL INFORMATION: --*TIME-OF-CONCENTRATION MODEL* -- USER SPECIFIED STORM EVENT(YEAR) = 25.00 SPECIFIED MINIMUM PIPE SIZE(INCH) = 18.00 SPECIFIED PERCENT OF GRADIENTS(DECIMAL) TO USE FOR FRICTION SLOPE = .90 *USER -DEFINED LOGARITHMIC INTERPOLATION USED FOR RAINFALL* 10-YEAR STORM 60-MINUTE INTENSITY(INCH/HOUR) _ .920 100-YEAR STORM 60-MINUTE INTENSITY(INCH/HOUR) = 1.330 COMPUTED RAINFALL INTENSITY DATA: STORM EVENT = 25.00 1-HOUR INTENSITY(INCH/HOUR) = 1.0620 SLOPE OF INTENSITY DURATION CURVE = .6000 '.c �•i: is Y: is Yr Yr � is Y: Yr Yc is*Yr***i: Yr****'.c Y�ir it Yc *4r* is Yc*Yc*ic Yr*Yc Yr Ye Yr*i: *ie Yr Yr*ir Yr**** �•ie ie is Yr Ye Yr***Y: Yc Yr*Yr *Yr Yr FLOW PROCESS FROM NODE 10.00 TO NODE 10.00 IS CODE = 15 -------------------------------------------- »»>DEFINE MEMORY BANK # 1 ««< MEMORY BANK # 1 DEFINED AS FOLLOWS: Q(CFS) TC(MIN.) Fp(INCH/HR) Ap FM(INCH/HR) Ae(ACRES) 1 218.85 18.25 .556 .16 .087 116.05 2 219.71 18.68 .555 .16 .087 118.27 3 220.13 19.60 .552 .16 .088 122.11 4 219.05 20.50 .548 .16 .088 125.04 5 204.52 25.66 .517 .18 .092 134.81 6 199.00 27.25 .511 .18 .093 136.34 TOTAL AREA = 136.34 Y:Yr*'.:i.•Yr Yt;;;;;;i: irYrir***ir*Yt Ye**:4*Yr irY: Yt Yr Yr Yc Yc Yc ir***it**Yc**it**ic***«Yr**Y:Yci:**ir Yc Yr it Yr it*Yr Y: Yr is Yr Ye*ir is FLOW PROCESS FROM NODE 10.00 TO NODE 10.00 IS CODE = 14 ------------------------------------------------------- »»>MEMORY BANK # 1 COPIED ONTO MAIN -STREAM MEMORY««< MAIN -STREAM MEMORY DEFINED AS FOLLOWS: Q(CFS) Tc(MIN.) Fp(INCH/HR) Ap FM(INCH/HR) Ae(ACRES) 1 218.85 18.25 .556 .16 .087 116.05 2 219.71 18.68 .55.5 .16 .087 118.27 3 220.13 19.60 .552 .16 .088 122.11 4 219.05 20.50 .548 .16 .088 125.04 5 204.52 25.66 .517 .18 .092 134.81 Page 1 6 199.00 27.25 .511 .18 .093 136.34 TOTAL AREA = 136.34 it i<Yr Yc it Yr Yt is is Yt is it Yr Yc Yr is i<Yr Yt Yt is Yr Yc Yt Yt i� Yt Yr it Yt Yc Yt it is ie it it i< Ye ie it it it it Ye Ye it is Yt Ye Yt Yr Yt is ie Ye it ie it ie Yr is ie ie it Y� is Yc ie Ye Yr & it Yr Yr Yr FLOW PROCESS FROM NODE 10.00 TO NODE 10.00 IS CODE= 12 ----------------------------------------------- »»>CLEAR MEMORY BANK # 1 ««< Yc it Ye Yc it it Y<Yc Ye Yr is it Yc it is Ye Yr Yt is it it Y: Yc Ye it Ye Yc it it it it Yr it Yc Yt is it Yc it it it Ye Yr it i<ir Ye Ye Yc i< ie ie is * sY is it ie Y: Yc Yc it ie Yr is i<Y:Yc Yr is ie Yr it Y: Yr ie FLOW PROCESS FROM NODE 10.00 TO NODE 34.00 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 48.0 INCH PIPE IS 36.5 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 21.4 UPSTREAM NODE ELEVATION(FEET) = 1075.90 DOWNSTREAM NODE ELEVATION(FEET) = 1039.50 FLOW LENGTH(FEET) = 1200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 48.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 220.13 TRAVEL TIME(MIN.) = .93 TC(MIN.) = 20.53 Yr Y: Yc r i; 4: Yr it i< is Y: is it it it Yc it is it Yr Y: Y: icir it Yt it Yt is Yr * it Yr Yr it is it Yt Yc is it it Yr Yr it i<* Y: Ye it i< it Yr Yt Yiir it Yr it is Ye Yr Yt is is Ye Yr i<Yc Ye Yc i< is i<Yc it FLOW PROCESS FROM NODE 34.00 TO NODE 34.00 IS CODE = 10 ---------------------------------------------------------------------------- »»>MAIN-STREAM MEMORY COPIED ONTO MEMORY BANK # 1 ««< Yc it � t it it is i; Ye it � Yr Yr is it is Yt Yr i; it & it Yt ie is it �YYe Yc � Y: Yr i< it Yc Yr is is i<ir Yt it is is it Yc Y: Yr Yr Yc Yr Ye Ye it Yt Yc i<is it Yc & it � � � Yr it i:Yt it � is Ye it it it FLOW PROCESS FROM NODE 34.00 TO NODE 34.00 IS CODE = 15 ---------------------------------------------------------------------------- >>>DEFINE MEMORY BANK # 1 ««< MEMORY BANK # 1 DEFINED AS FOLLOWS: Q(CFS) TC(MIN.) Fp(INCH/HR) Ap FM(INCH/HR) Ae(ACRES) 1 143.76 7.59 .685 .16 .108 43.13 2 171.75 14.06 .681 .16 .111 73.33 3 180.29 16.31 .678 .17 .113 85.34 4 181.54 16.79 .677 .17 .113 87.64 5 182.82 18.59 .674 .17 .115 94.54 6 182.42 18.94 .673 .17 .116 95.54 7 180.61 19.32 .672 .17 .117 95..97 TOTAL AREA = 95.97 Yr it it it it is it it is irit is Y: it it it Y: �'.c Yr Yr Yr i<� it Ye Yc it it ie it i<i; Yc it it it Ycir it it it it it is it it it ie Yt it Yc Y<Yr i<Yr Yr iv :r it Y: it is it it ie i; is it i< it ie'.: i< it Y: FLOW PROCESS FROM NODE 34.00 TO NODE 34.00 IS CODE = 14 ---------------------------------------------------------------------------- »»>MEMORY BANK # 2 COPIED ONTO MAIN -STREAM MEMORY««< ***MEMORY BANK # 2 IS EMPTY AND CAN NOT BE COPIED ONTO MAIN -STREAM MEMORY - PROCESS IGNORED.*** .,i:Y: it isa Yr i;iti:Y: Ye is i:�ir i<Yr it Yc it*ic-ki<�i; Yc is �•Yr Yr ie i;�i: is it it sir Y:ir�-k it i; Yr�i: Y: i<i: is �Yc Yc�Yr it �'i; �Y�ir�� �•ir is is is*�Yc is FLOW PROCESS FROM NODE 34.00 TO NODE 34.00 IS CODE = 12 ---------------------------------------------------------------------------- Page 2 f` »»>CLEAR MEMORY BANK # 2 ««< ***MEMORY BANK # 2 IS EMPTY - PROCESS IGNORED.*** is is is it is it ie is it it ie is is is is is it it is ie is * it it it it ie i� is is is is is ie is is is it is ie is is is * it is ie irir is is it it it is ie ie is is ic-ic *. is is is *ic it is is iric ie is is it FLOW PROCESS FROM NODE 34.00 TO NODE 34.00 IS CODE = 11 ---------------------------------------------------------------------------- »»>CONFLUENCE MEMORY BANK # 1 WITH THE MAIN -STREAM MEMORY««< ir* PEAK FLOW RATE TABLE ** Q Tc Intensit Fp AP FM Ae (CFS) (MIN.) (INCH/HR� (INCH/HR) (INCH/HR) (ACRES) 1 400.14 19.18 2.105 .61 .16 .10 211.86 2 398.58 19.62 2.077 .61 .16 .10 214.24 3 393.91 20.53 2.021 .61 .17 .10 218.08 4 388.11 21.43 1.970 .60 .17 .10 221.01 5 351.73 26.60 1.730 .58 .18 .10 230.78 6 340.72 28.22 1.670 .58 .18 .10 232.31 7 297.62 7.59 3.670 .62 .16 .10 89.08 8 366.43 14.06 2.537 .62 .16 .10 158.37 9 386.22 16.31 2.320 .61 .16 .10 184.02 10 389.73 16.79 2.280 .61 .16 .10 189.23 11 399.14 18.59 2.145 .61 .16 .10 207.05 12 400.26 18.94 2.121 .61 .16 .10 210.17 13 399.74 19.32 2.096 .61 .16 .10 212.73 TOTAL AREA = 232.31 COMPUTED CONFLUENCE ESTIMATES ARE AS FOLLOWS: PEAK FLOW RATE(CFS) = 400.26 TC(MIN.) = 18.945 EFFECTIVE AREA(ACRES) = 210.17 AREA -AVERAGED FM(INCH/HR) _ .10 AREA -AVERAGED Fp(INCH/HR) _ .61 AREA -AVERAGED Ap = .16 TOTAL AREA(ACRES) = 232.31 ***ic ie it is*ic it is it is it*ic*ic*.is is ie is sY it is is is is*ic it*ir is it it is is it is it ie it is it is it s4 is it it it is ie is ie is it it it is is is it it is ie ie is it it is is is is FLOW PROCESS FROM NODE 34.00 TO NODE 34.00 IS CODE = 12 ------------------------------------------------ »»>CLEAR MEMORY BANK # 1 ««< •ir*�Yiliricir*icir*irie-kiricirie*irieic*'.r*iciciric*iricic*ir*iesY*iriciririciciricieicicicsYirici�icirie*iririr'.ririri;iricir*icirieicsY FLOW PROCESS FROM NODE 34.00 TO NODE 35.00 IS CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 87.0 INCH PIPE IS 67.8 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 11.6 UPSTREAM NODE ELEVATION(FEET) = 1039.50 DOWNSTREAM NODE ELEVATION(FEET) = 1039.40 FLOW LENGTH(FEET) = 25.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 87.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 400.26 TRAVEL TIME(MIN.) = .04 TC(MIN.) = 18.98 ic:ic�•ic*it it fc is it ic°k is ie is is it it*ic ic�ic*ie •k it is it is is it it is is is ie ic* is is*ic sY ir*ic**ic it is is*ie icir it is is*ic is is is it is it it it it it*icic is FLOW PROCESS FROM NODE 35.00 TO NODE 35.00 IS CODE = 10 ---------------------------------------------------------------------------- >>>MAIN-STREAM MEMORY COPIED ONTO MEMORY BANK # 1 ««< Page 3 ie ie it it it is it it it ie it ie is & it ie ie ie is is it qe it is it is it it ie s4 it is it ie it it ie * it is ie is it it it it is ie it it is it ie ie ie ie it ie it it is is ie is it ie ie it ie ie is is ie it irir FLOW PROCESS FROM NODE 32.00 TO NODE 32.00 IS CODE = 15 ---------------------------------------------------------------------------- »»>DEFINE MEMORY BANK # 1 ««< MEMORY BANK # 1 DEFINED AS FOLLOWS: Q(CFS) TC(MIN.) Fp(INCH/HR) AP Fm(INCH/HR) Ae(ACRES) 1 67.98 14.06 .750 .10 .075 30.48 2 71.61 20.69 .750 .10 .075 40.83 TOTAL AREA = 40.83 �• is it is is it it ie. it is it it is*ir ie it it it is it it it is is is is it it is it is is it it it ie it ie ie is is sY is it is is it ie it is is it is it iciric is it it it ie is it ie it is is is is is it it it it FLOW PROCESS FROM NODE 32.00 TO NODE 32.00 IS CODE = 14 ---------------------------------------------------------------------------- »»>MEMORY BANK # 2 COPIED ONTO MAIN -STREAM MEMORY««< ***MEMORY BANK # 2 IS EMPTY AND CAN NOT BE COPIED ONTO MAIN -STREAM MEMORY - PROCESS IGNORED.*** is it it it**ic is*i: is is it it it it is is*ic it ic*iris*it is is it it it is*ir ie it *ir it it is it it is it is is is is is ie is is is is ie it is is ie is it it is it is is ie it*ir it R�:Y it FLOW PROCESS FROM NODE 32.00 TO NODE 32.00 IS CODE = 12 ---------------------------------------------------------------------------- »»>CLEAR MEMORY BANK # 2 ««< ----------------------------------------------------- ***MEMORY BANK # 2 IS EMPTY - PROCESS IGNORED.*** ..*ic is*ir is ici: it is �•4c ie is is**ie is it is it it it***ir is it is*ic is it*ic is ie it it sY it ie ie is is it it it it it is is it it is it irir it*ic it it icic*ir it is *ir it is FLOW PROCESS FROM NODE 32.00 TO NODE 35.00 I5 CODE = 3 »»>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< »»>USING COMPUTER -ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< DEPTH OF FLOW IN 72.0 INCH PIPE IS 57.3 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 16.6 UPSTREAM NODE ELEVATION(FEET) = 1052.00 DOWNSTREAM NODE ELEVATION(FEET) = 1039.40 FLOW LENGTH(FEET) = 1200.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 72.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 400.26 TRAVEL TIME(MIN.) = 1.21 TC(MIN.) = 20.19 is is �ti it ie it it is*ir ie ie it is it it it is*fit it*ic is �Y it is is it sY it it ie it is is ie**it is is is is it it is ie:**ic it*it it ie it is ie *ie it is it is it it is it it i.•*ic*ic FLOW PROCESS FROM NODE 35.00 TO NODE 35.00 IS CODE = 11 ------------------------------------------------ »»>CONFLUENCE MEMORY BANK # 1 WITH THE MAIN -STREAM MEMORY««< ** PEAK FLOW RATE TABLE ** Q Tc Intensity Fp Ap Fm Ae (CFS) (MIN.) (INCH/HR) (INCH/HR) (INCH/HR) (ACRES) 1 354.71 8.92 3.333 .63 .15 .09 108.42 2 435.11 15.33 2.408 .63 .15 .09 190.83 3 456.12 17.55 2.220 .63 .15 .10 219.95 4 459.89 18.03 2.185 .63 .15 .10 225.91 5 470.29 19.84 2.063 .63 .15 .10 246.54 6 471.60 20.19 2.042 .63 .15 .10 250.21 7 471.60 20.42 2.027 .63 .15 .10 252.27 8 471.28 20.56 2.019 .63 .15 .10 253.35 Page 4 9 469.84 20.86 2.002 .62 .15 .10 255.07 10 463.29 21.77 1.951 .62 .16 .10 258.91 11 455.75 22.68 1.904 .62 .16 .10 261.84 12 411.16 27.88 1.682 .60 .16 .10 271.61 13 398.08 29.50 1.626 .59 .17 .10 273.14 14 420.72 14.06 2.537 .63 .15 .09 175.06 15 470.84 20.69 2.011 .63 .15 .10 254.23 TOTAL AREA = 273.14 COMPUTED CONFLUENCE ESTIMATES ARE AS FOLLOWS: PEAK FLOW RATE(CFS) = 471.60 TC(MIN.) = 20.421 EFFECTIVE AREA(ACRES) = 252.27 AREA -AVERAGED FM(INCH/HR) _ .10 AREA -AVERAGED Fp(INCH/HR) = .63 AREA -AVERAGED Ap .15 TOTAL AREA(ACRES) = 273.14 isir4ritiri:irte4r�;icy:l�':4:ir�i:4r4rit4ris4t�Y:r&ieic#sYirir4ei;isie4cir4eicicir4r:r4ri:�'rirstiricirirfrieiciritirir4e4eics4irdrii'hi:Yric�irdcic FLOW PROCESS FROM NODE 35.00 TO NODE 35.00 IS CODE = 12 ---------------------------------------------------------------------------- »»>CLEAR MEMORY BANK # 1 ««< it :'r R-ir it it it ie Yr k��ic it f: is sY fr is is it it it it ��Y sY it it 4r:r is it 4c Y fc it it it ie Yr ie sY it ir:c&dc it dc�4r it sY it it it it it it it is k'r Yr :e ie it is �r �; icy it it sY FLOW PROCESS FROM NODE 35.00 TO NODE 400.00 IS CODE = 3 ---------------------------------------------- ------------------------------ >>>>>COMPUTE PIPE -FLOW TRAVEL TIME THRU SUBAREA««< >>>USING COMPUTER- ESTIMATED PIPESIZE (NON -PRESSURE FLOW)««< ------------------------------------------------------------------------- DEPTH OF FLOW IN 93.0 INCH PIPE IS 71.3 INCHES PIPE -FLOW VELOCITY(FEET/SEC.) = 12.2 UPSTREAM NODE ELEVATION(FEET) = 1039.40 DOWNSTREAM NODE ELEVATION(FEET) = 1036.08 FLOW LENGTH(FEET) = 825.00 MANNING'S N = .013 ESTIMATED PIPE DIAMETER(INCH) = 93.00 NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = 471.60 TRAVEL TIME(MIN.) = 1.13 TC(MIN.) = 21.55 �:cY'r:t it fc it it �'r4: 4r X4r i; ie 4r ie it 4c it it is ie&ie.k Yt it it ir'��Y 4: it it�4c�A:i:9: it is irir is 4r 4rit it d:4t�it Yr is it di��i: �f: is is �•9r it :c 4: fc 4r A•ir ir': FLOW PROCESS FROM NODE 400.00 TO NODE 400.00 IS CODE = 10 ---------------------------------------------------------------------------- »»>MAIN-STREAM MEMORY COPIED ONTO MEMORY BANK # 1 ««< .,,.4:i:h�:.4:�s;..:Y 4r it 4r ir:r���::'.•4;:r�ic :c �'c �•:r st�ic�4c 4e i;��ir ire �ir•1:'.r&&iri::c�#tic 4c it ir�ic ir��ie it it �irk�ic :r it it :r i; �• FLOW PROCESS FROM NODE 400.00 TO NODE 400.00 IS CODE = 15 --------------------------------------------------------------------------- »»>DEFINE MEMORY BANK # 1 ««< MEMORY BANK # 1 DEFINED AS FOLLOWS: Q(CFS) TC(MIN.) Fp(INCH/HR) Ap FM(INCH/HR) Ae(ACRES) 1 42.47 10.21 .750 .41 .307 14.14 2 42.76 10.51 .750 .41 .307 14.52 3 42.82 10.60 .750 .41 .307 14.64 4 43.09 11.07 .750 .41 .307 15.24 5 43.24 12.41 .750 .41 .307 16.69 6 43.23 12.42 .750 .41 .307 16.70 7 43.06 12.61 .750 .41 .307 16.84 8 42.62 12.91 .750 .41 .307 17.00 9 40.50 14.20 .750 .41 .307 17.36 TOTAL AREA = 17.36 Page 5 itiriric*ir.*it**irir***icir**icie*****iricirir***ir*********ir*ieiritiric***it*****4t*ie*****ic*****irie* FLOW PROCESS FROM NODE 400.00 TO NODE 400.00 IS CODE = 14 ---------------------------------------------------- »»>MEMORY BANK # 2 COPIED ONTO MAIN -STREAM MEMORY««< ***MEMORY BANK .# 2 IS EMPTY AND CAN NOT BE COPIED ONTO MAIN -STREAM MEMORY - PROCESS IGNORED.*** FLOW PROCESS FROM NODE 400.00 TO NODE 400.00 IS CODE = 12 --------------------------------------------------- »»>CLEAR MEMORY BANK # 2 ««< -------------------------------------------------------- ---------------------------------------------------------------------- ***MEMORY BANK # 2 IS EMPTY - PROCESS IGNORED.*** FLOW PROCESS FROM NODE 400.00 TO NODE 400.00 IS CODE = 11 ---------------------------------------------------------------------------- »»>CONFLUENCE MEMORY BANK # 1 WITH THE MAIN -STREAM MEMORY««< ** PEAK FLOW RATE TABLE ** Q Tc Intensit Fp Ap Fm Ae (CFS) (MIN.) (INCH/HR� (INCH/HR) (INCH/HR) (ACRES) 1 397.07 10.13 3.088 .67 .18 .12 122.45 2 459.32 15.23 2.417 .66 .17 .11 192.42 3 471.66 16.49 2.305 .65 .17 .11 208.19 4 489.59 18.71 2.137 .65 .17 .11 237.31 5 492.77 19.19 2.105 .65 .17 .11 243.27 6 501.17 20.97 1.996 .65 .17 .11 263.90 7 502.12 21.32 1.976 .65 .17 .11 267.57 8 501.89 21.55 1.963 .65 .17 .11 269.63 9 501.43 21.69 1.955 .64 .17 .11 270.71 10 500.86 21.82 1.948 .64 .17 .11 271.59 11 499.69 21.99 1.939 .64 .17 .11 272.43 12 492.29 22.90 1.893 .64 .17 .11 276.27 13 483.94 23.83 1.848 .64 .17 .11 279.20 14 435.56 29.06 1.641 .62 .18 .11 288.97 15 421.51 30.68 1.588 .61 .18 .11 290.50 16 398.18 10.21 3.074 .66 .18 .12 123.57 17 402.32 10.51 3.021 .66 .18 .12 127.83 18 403.64 10.60 3.004 .66 .18 .12 129.22 19 409.92 11.07 2.928 .66 .18 .12 135.90 20 427.45 12.41 2.733 .66 .18 .12 154.90 21 427.54 12.42 2.732 .66 .18 .12 155.00 22 429.79 12.61 2.708 .66 .18 .12 157.58 23 433.25 12.91 2.670 .66 .18 .12 161.69 24 447.87 14.20 2.521 .66 .17 .11 178.94 TOTAL AREA = 290.50 COMPUTED CONFLUENCE ESTIMATES ARE AS FOLLOWS: PEAK FLOW RATE(CFS) = 502.12 TC(MIN.) = 21.318 EFFECTIVE AREA(ACRES) = 267.57 AREA -AVERAGED FM(INCH/HR) = 11 AREA -AVERAGED Fp(INCH/HR) = .65 AREA -AVERAGED Ap = .17 TOTAL AREA(ACRES) = 290.50 ****it it it is is *it*********ir it******ir i.•* �•'.r*it*ic*****it*ic********ic *� R•*** �•ic***** *it**ir*ic** FLOW PROCESS FROM NODE 400.00 TO NODE 400.00 IS CODE = 12 -------------------------------------------- »»>CLEAR MEMORY BANK # 1 ««< Page 6 -END OF STUDY SUMMARY: TOTAL AREA(ACRES) = 290.50 TC(MIN.) = 21.32 EFFECTIVE AREA(ACRES) = 267.57 AREA -AVERAGED FM(INCH/HR)= .11 AREA -AVERAGED Fp(INCH/HR) _ .65 AREA -AVERAGED Ap = .17 PEAK FLOW RATE(CFS) = 502.12 PEAK FLOW RATE TABLE ** Q Tc Intensit Fp AP Fm Ae (CFS) (MIN.) (INCH/H� (INCH/HR) (INCH/HR) (ACRES) 1 397.07 10.13 3.088 .67 .18 .12 122.45 2 398.18 10.21 3.074 .66 .18 .12 123.57 3 402.32 10.51 3.021 .66 .18 .12 127.83 4 403.64 10.60 3.004 .66 .18 .12 129.22 5 409.92 11.07 2.928 .66 .18 .12 135.90 6 427.45 12.41 2.733 .66 .18 .12 154.90 7 427.54 12.42 2.732 .66 .18 .12 155.00 8 429.79 12.61 2.708 .66 .18 .12 157.58 9 433.25 12.91 2.670 .66 .18 .12 161.69 10 447.87 14.20 2.521 .66 .17 .11 178.94 11 459.32 15.23 2.417 .66 .17 .11 192.42 12 471.66 16.49 2.305 .65 .17 .11 208.19 13 489.59 18.71 2.137 .65 .17 .11 237.31 14 492.77 19.19 2.105 .65 .17 .11 243.27 15 501.17 20.97 1.996 .65 .17 .11 263.90 16 502.12 21.32 1.976 .65 .17 .11 267.57 17 501.89 21.55 1.963 .65 .17 .11 269.63 18 501.43 21.69 1.955 .64 .17 .11 270.71 19 500.86 21.82 1.948 .64 .17 .11 271.59 20 499.69 21.99 1.939 .64 .17 .11 272.43 21 492.29 22.90 1.893 .64 .17 .11 276.27 22 483.94 23.83 1.848 .64 .17 .11 279.20 23 435.56 29.06 1.641 .62 .18 .11 288.97 24 421.51 30.68 1.588 .61 .18 .11 290.50 END OF RATIONAL METHOD ANALYSIS Page 7 Technical Appendix I Hydrology Map Reproduced from Storm Drain Basis of Design Sycamore Hills II Tentative Tract No. 16495 RBF Consulting — February 2004 Technical Appendix J 100-Year Hydrograph Analysis including Detention Basin Sierra Business Park Basin Rating Curves Detention Basin Elevation ft Depth ft Submerge ft Head (ft) Area (sq ft) Area (ac) Storage ac-ft Outflow cfs 1030.2 0.0 0.0 0.0 0 0.00 0.00 0.0 1031.0 0.8 0.4 0.4 29,384 0.67 0.27 3.5 1032.0 1.8 1.0 0.8 80,031 1.84 1.65 11.7 1033.0 2.8 1.5 1.3 127,453 2.93 3.87 27.3 1034.0 3.8 2.0 1.8 130,661 3.00 6.83 42.9 1035.0 4.8 2.5 2.3 133,869 3.07 9.87 54.2 1036.0 5.8 3.1 2.7 137,078 3.15 12.98 63.5 1037.0 6.8 3.6 3.2 140,286 3.22 16.16 71.6 1038.0 7.8 4.1 3.7 143,494 3.29 19.42 78.8 1039.0 8.8 4.6 4.2 146,849 3.37 22.75 85.5 1040.0 9.8 5.2 4.6 150,205 3A5 26.16 91.7 1041.0 10.8 5.7 5.1 153,560 3.53 29.65 97.5 1042.0 11.8 6.2 5.6 156,916 3.60 33.21 102.9 1042.7 12.5 6.6 5.9 159,264 3.66 35.75 106.6 1043.0 12.8 6.8 6.0 160,271 3.68 36.85 108.1 1044.0 13.8 7.3 6.5 164,467 3.78 40.58 113.1 1045.0 14.8 7.8 7.0 168,664 3.87 44AI 117.8 1045.2 15.0 7.9 7.1 169,503 3.89 45.18 118.7 Bleeder Pipe HGL @ Basin 1036.8 Emergency Spillway - Trapezoidal Weir (10:1) Q1000 Length Depth Q (Rect) Q (Tri) Q (Total) cfs)(it) ft) cfs) cfs cfs 618 100 1.5 551 71 622 it is it it ie it it it ie is is it it is is it it it it it it is it it it is is it it it it it it it it it is it it it it is it ie it is it it it ie it it it it it it it it it it it it ie it it it i� it ie is it it it ie ie it F L 0 0 D R O U T I N G A N A L Y S I S USING ORANGE/SAN BERNARDINO COUNTY UNIT-HYDROGRAPH (1986 MANUAL) (c) Copyright 1989-93 Advanced Engineering Software (aes) Ver. 2.7A Release Date: 7/20/93 License ID 1202 Analysis prepared by: HUITT-ZOLLARS, INC. 15101 RED HILL AVENUE TUSTIN, CALIFORNIA 92780-6500 PHONE (714) 259-7900 * FAX (714) 259-0210 ski:iti: it ie it it it ie'k:ic it is is is is ie ir. it it it is ie it is DESCRIPTION OF STUDY' '�*******ir it it it ilir is sY it it it*ie *ir it it it SIERRA BUSINESS PARK it * DETENTION BASIN ' 100-YEAR HYDROLOGIC ANALYSIS is is s4 is it it it it it it it it ie it it it is it ie it it ie it it it ie ie***ir ie it oY is ie is it it it it it ie it it is it ie it it it is it ie it ie it it it ie i�ie is it**ie is it it**ie is FILE NAME: SBP-H10O.FLD TIME/DATE OF STUDY: 10:39 6/16/2004 it it it it it isis-kir*it it kie*ic it it it it it it ir*ir it it*ir it is is is ie it it*ie is it is it it it it it it it it*ir it it ie it is**ie it it it it it it it it it ie it is it it it it k FLOW PROCESS FROM NODE 102.00 TO NODE 400.00 IS CODE = 1 ---------------------------------------------------------------------------- »»>UNIT-HYDROGRAPH ANALYSIS««< (UNIT-HYDROGRAPH ADDED TO STREAM #1) WATERSHED AREA = 290.500 ACRES BASEFLOW = .000 CFS/SQUARE-MILE `USER ENTERED "LAG" TIME = .380 HOURS CAUTION: LAG TIME IS LESS THAN .50 HOURS. THE 5-MINUTE PERIOD UH MODEL (USED IN THIS COMPUTER PROGRAM) MAY BE TOO LARGE FOR PEAK FLOW ESTIMATES. VALLEY(DEVELOPED): "S"-CURVE PERCENTAGE (DECIMAL NOTATION) = .940 FOOTHILL "S"-CURVE PERCENTAGE (DECIMAL NOTATION) = .000 MOUNTAIN "S"-CURVE PERCENTAGE (DECIMAL NOTATION) = .000 VALLEY(UNDEVELOPED)/DESERT: "S"-CURVE PERCENTAGE (DECIMAL NOTATION) = .060 MAXIMUM WATERSHED LOSS RATE(INCH/HOUR) _ .139 LOW LOSS FRACTION = .133 *HYDROGRAPH MODEL #1 SPECIFIED* SPECIFIED PEAK 5-MINUTES RAINFALL(INCH)= .30 SPECIFIED PEAK 30-MINUTES RAINFALL(INCH)= .87 SPECIFIED PEAK 1-HOUR RAINFALL(INCH) = 1.35 SPECIFIED PEAK 3-HOUR RAINFALL(INCH) = 2.50 SPECIFIED PEAK 6-HOUR RAINFALL(INCH) = 3.50 SPECIFIED PEAK 24-HOUR RAINFALL(INCH) = 8.00 PRECIPITATION DEPTH -AREA REDUCTION FACTORS: 5-MINUTE FACTOR = .987 30-MINUTE FACTOR = .987 1-HOUR FACTOR = .987 3-HOUR FACTOR = .998 6-HOUR FACTOR = .999 24-HOUR FACTOR = .999 UNIT HYDROGRAPH TIME UNIT = 5.000 MINUTES Page 1 UNIT INTERVAL PERCENTAGE OF LAG -TIME = 21.930 --------------------------------------------------- UNIT HYDROGRAPH DETERMINATION ---------------------------------------------------------------------------- INTERVAL "S" GRAPH UNIT HYDROGRAPH NUMBER ---------------------------------------------------------------------------- MEAN VALUES ORDINATES(CFS) 1 1.321 46.425 2 5.767 156.191 3 16.283 369.457 4 30.430 497.003 5 48.283 627.233 6 65.646 609.986 7 78.482 450.960 8 86.634 286.393 9 91.560 173.065 10 94.741 111.746 11 96.612 65.742 12 97.443 29.212 13 97.945 17.613 14 98.428 16.985 15 98.897 16.479 16 99.363 16.350 17 99.461 3.469 18 99.519 2.034 19 99.572 1.874 20 99.615 1.495 21 99.657 1.469 22 99.697 1.399 23 99.736 1.379 24 99.768 1.135 25 99.797 1.017 26 99.824 .939 27 99.848 .833 28 99.870 .794 29 99.889 .659 30 99.907 .635 31 99.921 .500 32 99.934 .462 33 99.948 .462 34 99.961 .462 35 99.974 .462 36 99.987 .462 37 100.000 .454 TOTAL STORM RAINFALL(INCHES) = 8.00 TOTAL SOIL-LOSS(INCHES) = 1.02 TOTAL EFFECTIVE RAINFALL(INCHES) = 6.98 ---------------------------------------------------------------------------- TOTAL SOIL -LOSS VOLUME(ACRE-FEET) = 24.6570 TOTAL STORM RUNOFF VOLUME(ACRE-FEET) = 168.8094 ---------------------------------------------------------------------------- 2 4- H O U R S T O R M R U N O F F H Y D R 0 G R A P H Page 2 HYDROGRAPH IN FIVE-MINUTE INTERVALS(CFS) ---------------------------------------------------------------------------- TIME(HRS) VOLUME(AF) -------------------------------------------------------------- Q(CFS) 0. 125.0 250.0 375.0 500.0 .083 .0046 .67 Q .167 .0247 2.91 Q .250 .0813 8.23 Q .333 .1873 15.38 VQ .417 .3555 24.43 VQ .500 .5844 33.24 V Q .583 .8584 39.79 V Q .667 1.1614 43.99 V Q .750 1.4821 46.57 V Q .833 1.8145 48.27 V Q .917 2.1542 49.32 V Q 1.000 2.4975 49.85 V Q 1.083 2.8433 50.21 V Q 1.167 3.1916 50.56 V Q 1.250 3.5422 50.91 V Q 1.333 3.8952 51.26 V Q 1.417 4.2494 51.42 .v Q 1.500 4.6045 51.57 V Q , 1.583 4.9607 51.71 V Q 1.667 5.3178 51.85 V Q 1.750 5.6758 51.99 .v Q 1.833 6.0348 52.13 V Q 1.917 6.3948 52.27 V Q 2.000 6.7557 52.41 .V Q 2.083 7.1176 52.54 V Q 2.167 7.4804 52.68 V Q 2.250 7.8442 52.82 .V Q 2.333 8.2089 52.95 V Q 2.417 8.5745 53.09 V Q 2.500 8.9411 53.23 v Q 2.583 9.3086 53.36 V Q 2.667 9.6770 53.50 V Q 2.750 10.0464 53.64 v Q 2.833 10.4167 53.77 V Q 2.917 10.7880 53.91 V Q 3.000 11.1603 54.05 V Q 3.083 11.5336 54.20 V Q 3.167 11.9078 54.33 v Q 3.250 12.2829 54.47 V Q 3.333 12.6590 54.61 V Q 3.417 13.0361 54.75 VQ 3.500 13.4141 54.89 VQ 3.583 13.7931 55.03 VQ 3.667 14.1732 55.18 vQ 3.750 14.5542 55.32 VQ 3.833 14.9362 55.47 VQ 3.917 15.3193 55.62 VQ 4.000 15.7033 55.77 VQ , 4.083 16.0885 55.92 VQ 4.167 16.4746 56.07 VQ 4.250 16.8619 56.23 vQ 4.333 17.2502 56.38 Q 4.417 17.6395 56.54 Q , 4.500 18.0300 56.70 Q 4.583 18.4216 56.86 Q 4.667 18.8143 57.02 Q 4.750 19.2081 57.18 Q 4.833 19.6030 57.35 Q Page 3 4.917 19.9991 57.51 . Q 5.000 20.3964 57.68 Q ' 5.083 20.7948 57.85 Q ' 5.167 21.1944 58.02 Qv ' 5.250 21.5952 58.20 QV 5.333 21.9972 58.37 Qv ' 5.417 22.4004 58.55 QV 5.500 22.8048 58.73 Qv 5.583 23.2105 58.91 QV ' 5.667 23.6175 59.09 QV 5.750 24.0257 59.27 QV ' 5.833 24.4352 59.46 Qv 5.917 24.8460 59.65 QV ' 6.000 25.2582 59.84 QV 6.083 25.6716 60.03 Q V ' 6.167 26.0864 60.23 Q V ' 6.250 26.5026 60.43 Q v 6.333 26.9201 60.63 Q V 6.417 27.3391 60.83 _ Q V 6.500 27.7594 61.03 Q V 6.583 28.1812 61.24 _ Q v 6.667 28.6044 61.45 Q V ' 6.750 29.0290 61.66 Q v ' 6.833 29.4552 61.88 Q v 6.917 29.8828 62.09 Q V 7.000 30.3120 62.31 Q v 7.083 30.7426 62.54 Q V 7.167 31.1749 62.76 Q v ' 7.250 31.6087 62.99 Q v 7.333 32.0441 63.22 Q V 7.417 32.4811 63.45 Q v 7.500 32.9197 63.69 Q v ' 7.583 33.3600 63.93 Q V 7.667 33.8020 64.17 Q v ' 7.750 34.2456 64.42 Q v . 7.833 34.6910 64.67 Q v ' 7.917 35.1381 64.92 Q V ' 8.000 35.5870 65.18 Q V . 8.083 36.0377 65.44 Q v 8.167 36.4902 65.70 Q v . 8.250 36.9446 65.97 Q V ' 8.333 37.4008 66.24 Q V 8.417 37.8589 66.52 Q v 8.500 38.3190 66.80 Q V. 8.583 38.7810 67.08 Q V. ' 8.667 39.2450 67.37 Q V. ' 8.750 39.7110 67.66 Q V. ' 8.833 40.1790 67.96 Q V. ' 8.917 40.6491 68.26 Q V. 9.000 41.1214 68.57 Q V. 9.083 41.5957 68.88 Q V. 9.167 42.0723 69.19 Q V. 9.250 42.5510 69.52 Q v 9.333 43.0320 69.84 Q V 9.417 43.5153 70.17 Q v 9.500 44.0009 70.51 Q v 9.583 44.4889 70.85 Q V 9.667 44.9792 71.20 Q V 9.750 45.4720 71.56 Q V 9.833 45.9673 71.92 Q v 9.917 46.4652 72.29 Q .V 10.000 46.9656 72.66 Q ,v ' 10.083 47.4686 73.04 Q v 10.167 47.9743 73.43 Q .V 10.250 48.4827 73.82 Q v Page 4 10.333 48.9939 74.22 10.417 49.5080 74.64 10.500 50.0249 75.05 10.583 50.5447 75.48 10.667 51.0675 75.92 10.750 51.5935 76.36 10.833 52.1225 76.81 10.917 52.6547 77.28 11.000 53.1902 77.75 11.083 53.7290 78.23 11.167 54.2712 78.73 11.250 54.8168 79.23 11.333 55.3661 79.75 11.417 55.9189 80.28 11.500 56.4755 80.82 11.583 57.0359 81.37 11.667 57.6002 81.94 11.750 58.1685 82.52 11.833 58.7409 83.11 11.917 59.3175 83.73 12.000 59.8985 84.35 12.083 60.4823 84.78 12.167 61.0658 84.72 12.250 61.6422 83.69 12.333 62.2076 82.10 12.417 62.7581 79.93 12.500 63.2944 77.86 12.583 63.8217 76.57 12.667 64.3455 76.06 12.750 64.8696 76.10 12.833 65.3962 76.46 12.917 65.9269 77.06 13.000 66.4632 77.86 13.083 67.0056 78.76 13.167 67.5544 79.69 13.250 68.1100 80.67 13.333 68.6725 81.68 13.417 69.2428 82.81 13.500 69.8212 83.98 13.583 70.4081 85.22 13.667 71.0039 86.50 13.750 71.6090 87.86 13.833 72.2238 89.27 13.917 72.8488 90.76 14.000 73.4846 92.31 14.083 74.1334 94.20 14.167 74.7995 96.72 14.250 75.4912 100.44 14.333 76.2135 104.88 14.417 76.9719 110.11 14.500 77.7663 115.35 14.583 78.5924 119.95 14.667 79.4454 123.85 14.750 80.3225 127.36 14.833 81.2229 130.73 14.917 82.1466 134.12 15.000 83.0939 137.54 15.083 84.0666 141.24 15.167 85.0667 145.22 15.250 86.0973 149.65 15.333 87.1613 154.49 15.417 88.2645 160.19 15.500 89.4157 167.15 15.583 90.6301 176.34 15.667 91.9197 187.24 .V .V .V .V . v , . v v V v .v v V v v v v v V . v V v V V v v V v V v v v V V v v V v V Q v Q V Q V Q v Q v Q V Q v Q v Q v Q V Q v . Q v. Q. v . Q. v . Q. V . Q V. Q V. Q V. .Q V. .Q V. .Q v Q V Q v . Q v Q V Q V Q v Page 5 15.750 93.2986 200.22 Q v 15.833 94.7751 214.38 Q v 15.917 96.3599 230.12 Q V 16.000 98.0824 250.11 Q v 16.083 100.0414 284.43 QV 16.167 102.3412 333.93 v Q 16.250 105.0768 397.21 v Q 16.333 108.0819 436.35 v Q 16.417 111.2336 457.62 v Q 16.500 114.2308 435.19 v Q 16.583 116.8297 377.37 v Q 16.667 119.0080 316.29 Q V , 16.750 120.8414 266.20 Q v . 16.833 122.4189 229.05 Q V. 16.917 123.7932 199.56 Q V. 17.000 125.0112 176.86 Q V. , 17.083 126.1284 162.22 Q V. 17.167 127.1721 151.54 Q V 17.250 128.1456 141.35 Q V 17.333 129.0511 131.48 Q v 17.417 129.8772 119.94 Q. V 17.500 130.6439 111.33 Q V , 17.583 131.3634 104.47 Q V 17.667 132.0450 98.97 Q V , 17.750 132.6966 94.62 Q .V , 17.833 133.3228 90.92 Q V , 17.917 133.9271 87.75 Q V 18.000 134.5124 84.98 Q .V 18.083 135.0820 82.71 Q v , 18.167 135.6409 81.15 Q v 18.250 136.1969 80.74 Q v 18.333 136.7552 81.07 Q v 18.417 137.3213 82.19 Q v 18.500 137.8955 83.37 Q v 18.583 138.4733 83.91 Q v 18.667 139.0505 83.80 Q V 18.750 139.6239 83.26 Q V 18.833 140.1920 82.50 Q v 18.917 140.7540 81.59 Q V 19.000 141.3089 80.57 Q V 19.083 141.8566 79.53 Q v 19.167 142.3970 78.47 Q v 19.250 142.9310 77.54 Q V 19.333 143.4589 76.66 Q V 19.417 143.9807 75.76 Q v 19.500 144.4965 74.90 Q v 19.583 145.0066 74.07 Q v 19.667 145.5112 73.27 Q v 19.750 146.0105 72.51 Q v 19.833 146.5048 71.77 Q v 19.917 146.9942 71.05 Q v 20.000 147.4788 70.37 Q v 20.083 147.9588 69.70 Q v 20.167 148.4344 69.06 Q v 20.250 148.9057 68.43 Q V 20.333 149.3729 67.83 Q V 20.417 149.8360 67.25 Q v 20.500 150.2952 66.68 Q v 20.583 150.7507 66.13 Q V 20.667 151.2024 65.59 Q v 20.750 151.6506 65.07 Q v 20.833 152.0952 64.56 Q v 20.917 152.5365 64.07 Q v 21.000 152.9744 63.59 Q v 21.083 153.4092 63.12 Q v Page 6 21.167 21.250 21.333 21.417 21.500 21.583 21.667 21.750 21.833 21.917 22.000 22.083 22.167 22.250 22.333 22.417 22.500 22.583 22.667 22.750 22.833 22.917 23.000 23.083 23.166 23.250 23.333 23.416 23.500 23.583 23.666 23.750 23.833 23.916 24.000 24.083 24.166 24.250 24.333 24.416 24.500 24.583 24.666 24.750 24.833 24.916 25.000 25.083 25.166 25.250 25.333 25.416 25.500 25.583 25.666 25.750 25.833 25.916 26.000 26.083 26.166 26.250 26.333 26.416 26.500 153.8407 154.2692 154.6947 155.1173 155.5370 155.9540 156.3682 156.7797 157.1886 157.5950 157.9989 158.4003 158.7994 159.1961 159.5905 159.9826 160.3726 160.7604 161.1460 161.5296 161.9111 162.2907 162.6682 163.0439 163.4176 163.7895 164.1595 164.5277 164.8942 165.2589 165.6219 165.9832 166.3428 166.7008 167.0572 167.4075 167.7407 168.0360 168.2809 168.4627 168.5835 168.6592 168.7063 168.7360 168.7546 168.7666 168.7757 168.7830 168.7885 168.7924 168.7947 168.7967 168.7984 168.7999 168.8013 168.8025 168.8036 168.8046 168.8054 168.8061 168.8067 168.8073 168.8077 168.8081 168.8084 62.67 62.22 61.78 61.36 60.94 60.54 60.14 59.75 59.38 59.01 58.64 58.29 57.94 57.60 57.27 56.94 56.62 56.31 56.00 55.70 55.40 55.11 54.82 54.54 54.27 53.99 53.73 53.47 53.21 52.96 52.71 52.46 52.22 51.98 51.75 50.85 48.39 Q 42.88 Q 35.56 Q 26.40 Q 17.54 .Q 10.99 Q 6.83 Q 4.32 Q 2.70 Q 1.74 Q 1.32 Q 1.06 Q .81 Q .57 Q .33 Q .28 Q .25 Q .22 Q .20 Q .18 Q .16 Q .14 Q .12 Q 10 Q .09 Q .08 Q .07 Q 06 Q .05 0 Page 7 v v v v v v v v v v v v v v v v v v v . v . v . v . v . v . v . v. v v . 26.583 168.8087 .04 Q V. 26.666 168.8089 .03 Q V, 26.750 168.8091 .03 Q V. 26.833 168.8093 .02 Q V. 26.916 168.8094 .01 Q V. 27.000 168.8094 .01 Q V. is is is it 4r 4e 9e iric s4 is ie it tc it ie ie 4e sY is dr 4r4c is it is fc it is �Y it is it 4c 4r 4c dr is Yc it it it 4c is ie ie fr 4c it is 4c Yr is �c lr ie it �Y is it 4c4e fe is is 4c 4r 4c ie it is is is is 4e is FLOW PROCESS FROM NODE 400.00 TO NODE 400.00 IS CODE = 3 ---------------------------------------------------------------------------- »»>MODEL FLOW -THROUGH DETENTION BASIN ROUTING««< ROUTE RUNOFF HYDROGRAPH FROM STREAM NUMBER 1 THROUGH A FLOW -THROUGH DETENTION BASIN USING FIVE-MINUTE UNIT INTERVALS: SPECIFIED BASIN CONDITIONS ARE AS FOLLOWS: DEAD STORAGE(AF) = .000 SPECIFIED DEAD STORAGE(AF) FILLED = .000 SPECIFIED EFFECTIVE VOLUME(AF) FILLED ABOVE OUTLET = DETENTION BASIN CONSTANT LOSS RATE(CFS) = 28.40 BASIN DEPTH VERSUS OUTFLOW AND STORAGE INFORMATION: INTERVAL DEPTH OUTFLOW STORAGE NUMBER (FT) (CFS) (AF) 1 .00 .00 .000 2 .80 3.50 .270 3 1.80 11.70 1.650 4 2.80 27.30 3.870 5 3.80 42.90 6.830 6 4.80 54.20 9.870 7 5.80 63.50 12.980 8 6.80 71.60 16.160 9 7.80 78.80 19.420 10 8.80 85.50 22.750 11 9.80 91.70 26.160 12 10.80 97.50 29.650 13 11.80 102.90 33.210 14 12.50 106.60 35.750 15 12.80 108.10 36.850 16 13.80 113.10 40.580 17 14.80 117.80 44.410 18 15.00 118.70 45.180 INFLOW (STREAM 1) V _effective depth ----------- 1 (and volume) I I I II ...V........ detention 1<-->1 outflow basin - - I I ----------- I ^.••. I \ I I dead 1 basin outlet V 1 storage 1 OUTFLOW --------- Page 8 e (STREAM 1) BASIN ROUTING MODEL RESULTS (5-MINUTE INTERVALS): TIME DEAD -STORAGE INFLOW EFFECTIVE OUTFLOW EFFECTIVE (HRS) ----------- FILLED(AF) ---------------------------------------------------------- (CFS) DEPTH(FT) (CFS) VOLUME(AF) .083 .000 .7 .00 .0 .000 .167 .000 2.9 .00 .0 .000 .250 .000 8.2 .00 .0 .000 .333 .000 15.4 .00 .0 .000 .417 .000 24.4 .00 .0 .000 .500 .000 33.2 .09 .2 .032 .583 .000 39.8 .31 .9 .104 .667 .000 44.0 .59 2.0 .198 .750 .000 46.6 .82 3.1 .302 .833 .000 48.3 .90 4.0 .411 .917 .000 49.3 .98 4.7 .523 1.000 .000 49.8 1.06 5.3 .634 1.083 .000 50.2 1.14 6.0 .743 1.167 .000 50.6 1.22 6.6 .850 1.250 .000 50.9 1.30 7.3 .955 1.333 .000 51.3 1.37 7.9 1.058 1.417 .000 51.4 1.44 8.5 1.158 1.500 .000 51.6 1.51 9.1 1.255 1.583 .000 51.7 1.58 9.6 1.350 1.667 .000 51.8 1.65 10.2 1.441 1.750 .000 52.0 1.71 10.7 1.530 1.833 .000 52.1 1.78 11.2 1.616 1.917 .000 52.3 1.82 11.8 1.699 2.000 .000 52.4 1.86 12.3 1.779 2.083 .000 52.5 1.89 12.9 1.857 2.167 .000 52.7 1.93 13.4 1.932 2.250 .000 52.8 1.96 13.9 2.004 2.333 .000 53.0 1.99 14.4 2.074 2.417 .000 53.1 2.02 14.9 2.141 2.500 .000 53.2 2.05 15.4 2.206 2.583 .000 53.4 2.08 15.8 2.269 2.667 .000 53.5 2.11 16.3 2.330 2.750 .000 53.6 2.13 16.7 2.389 2.833 .000 53.8 2.16 17.1 2.446 2.917 .000 53.9 2.18 17.5 2.501 3.000 .000 54.1 2.21 17.9 2.555 3.083 .000 54.2 2.23 18.2 2.607 3.167 .000 54.3 2.25 18.6 2.657 3.250 .000 54.5 2.28 18.9 2.706 3.333 .000 54.6 2.30 19.3 2.754 3.417 .000 54.8 2.32 19.6 2.800 3.500 .000 54.9 2.34 19.9 2.845 3.583 .000 55.0 2.36 20.3 2.889 3.667 .000 55.2 2.38 20.6 2.932 3.750 .000 55.3 2.40 20.9 2.974 3.833 .000 55.5 2.41 21.1 3.015 3.917 .000 55.6 2.43 21.4 3.055 4.000 .000 55.8 2.45 21.7 3.094 4.083 .000 55.9 2.47 22.0 3.132 4.167 .000 56.1 2.48 22.2 3.169 4.250 .000 56.2 2.50 22.5 3.206 4.333 .000 56.4 2.52 22.8 3.242 4.417 .000 56.5 2.53 23.0 3.277 4.500 .000 56.7 2.55 23.3 3.312 4.583 .000 56.9 2.56 23.5 3.346 4.667 .000 57.0 2.58 23.7 3.380 _._ Page 9 4.750 .000 57.2 2.59 24.0 3.413 4.833 .000 57.3 2.61 24.2 3.445 4.917 .000 57.5 2.62 24.4 3.478 5.000 .000 57.7 2.64 24.7 3.509 5.083 .000 57.9 2.65 24.9 3.541 5.167 .000 58.0 2.67 25.1 3.572 5.250 .000 58.2 2.68 25.3 3.603 5.333 .000 58.4 2.69 25.5 3.634 5.417 .000 58.5 2.71 25.7 3.664 5.500 .000 58.7 2.72 26.0 3.694 5.583 .000 58.9 2.73 26.2 3.724 5.667 .000 59.1 2.75 26.4 3.754 5.750 .000 59.3 2.76 26.6 3.783 5.833 .000 59.5 2.77 26.8 3.812 5.917 .000 59.7 2.79 27.0 3.842 6.000 .000 59.8 2.80 27.2 3.871 6.083 .000 60.0 2.81 27.4 3.900 6.167 .000 60.2 2.82 27.5 3.930 6.250 .000 60.4 2.83 27.7 3.960 6.333 .000 60.6 2.84 27.9 3.990 6.417 .000 60.8 2.85 28.0 4.020 6.500 .000 61.0 2.86 28.2 4.051 6.583 .000 61.2 2.87 28.3 4.082 6.667 .000 61.4 2.88 28.5 4.113 6.750 .000 61.7 2.89 28.7 4.145 6.833 .000 61.9 2.90 28.8 4.177 6.917 .000 62.1 2.91 29.0 4.209 7.000 .000 62.3 2.93 29.2 4.242 7.083 .000 62.5 2.94 29.3 4.275 7.167 .000 62.8 2.95 29.5 4.308 7.250 .000 63.0 2.96 29.7 4.342 7.333 .000 63.2 2.97 29.9 4.376 7.417 .000 63.5 2.98 30.1 4.410 7.500 .000 63.7 2.99 30.2 4.445 7.583 .000 63.9 3.01 30.4 4.480 7.667 .000 64.2 3.02 30.6 4.516 7.750 .000 64.4 3.03 30.8 4.552 7.833 .000 64.7 3.04 31.0 4.588 7.917 .000 64.9 3.06 31.2 4.625 8.000 .000 65.2 3.07 31.4 4.662 8.083 .000 65.4 3.08 31.6 4.700 8.167 .000 65.7 3.09 31.8 4.738 8.250 .000 66.0 3.11 32.0 4.776 8.333 .000 66.2 3.12 32.2 4.815 8.417 .000 66.5 3.13 32.4 4.855 8.500 .000 66.8 3.15 32.6 4.895 8.583 .000 67.1 3.16 32.8 4.935 8.667 .000 67.4 3.17 33.0 4.976 8.750 .000 67.7 3.19 33.2 5.018 8.833 .000 68.0 3.20 33.5 5.060 8.917 .000 68.3 3.22 33.7 5.102 9.000 .000 68.6 3.23 33.9 5.145 9.083 .000 68.9 3.25 34.1 5.189 9.167 .000 69.2 3.26 34.4 5.233 9.250 .000 69.5 3.28 34.6 5.278 9.333 .000 69.8 3.29 34.8 5.324 9.417 .000 70.2 3.31 35.1 5.370 9.500 .000 70.5 3.32 35.3 5.416 9.583 .000 70.9 3.34 35.6 5.464 9.667 .000 71.2 3.35 35.8 5.512 9.750 .000 71.6 3.37 36.1 5.561 9.833 .000 71.9 3.39 36.3 5.610 9.917 .000 72.3 3.40 36.6 5.660 10.000 .000 72.7 3.42 36.9 5.711 10.083 .000 73.0 3.44 37.1 5.763 Page 10 10.167 .000 73.4 3.46 37.4 5.815 10.250 .000 73.8 3.48 37.7 5.868 10.333 .000 74.2 3.49 38.0 5.922 10.417 .000 74.6 3.51 38.3 5.977 10.500 .000 75.1 3.53 38.6 6.033 10.583 .000 75.5 3.55 38.8 6.090 10.667 .000 75.9 3.57 39.2 6.147 10.750 .000 76.4 3.59 39.5 6.206 10.833 .000 76.8 3.61 39.8 6.266 10.917 .000 77.3 3.63 40.1 6.326 11.000 .000 77.7 3.65 40.4 6.388 11.083 .000 78.2 3.67 40.7 6.450 11.167 .000 78.7 3.69 41.1 6.514 11.250 .000 79.2 3.72 41.4 6.579 11.333 .000 79.7 3.74 41.8 6.645 11.417 .000 80.3 3.76 42.1 6.712 11.500 .000 80.8 3.78 42.5 6.781 11.583 .000 81.4 3.81 42.8 6.851 11.667 .000 81.9 3.83 43.1 6.923 11.750 .000 82.5 3.85 43.4 6.997 11.833 .000 83.1 3.88 43.7 7.073 11.917 .000 83.7 3.91 43.9 7.151 12.000 .000 84.3 3.93 44.2 7.232 12.083 .000 84.8 3.96 44.5 7.313 12.167 .000 84.7 3.98 44.8 7.392 12.250 .000 83.7 4.01 45.1 7.462 12.333 .000 82.1 4.03 45.4 7.520 12.417 .000 79.9 4.04 45.5 7.561 12.500 .000 77.9 4.05 45.7 7.587 12.583 .000 76.6 4.05 45.7 7.604 12.667 .000 76.1 4.06 45.8 7.617 12.750 .000 76.1 4.06 45.8 7.630 12.833 .000 76.5 4.07 45.9 7.644 12.917 .000 77.1 4.07 46.0 7.663 13.000 .000 77.9 4.08 46.0 7.687 13.083 .000 78.8 4.09 46.1 7.716 13.167 .000 79.7 4.10 46.3 7.750 13.250 .000 80.7 4.12 46.4 7.791 13.333 .000 81.7 4.13 46.6 7.837 13.417 .000 82.8 4.15 46.7 7.890 13.500 .000 84.0 4.17 47.0 7.949 13.583 .000 85.2 4.19 47.2 8.016 13.667 .000 86.5 4.21 47.4 8.089 13.750 .000 87.9 4.24 47.7 8.170 13.833 .000 89.3 4.27 48.0 8.258 13.917 .000 90.8 4.30 48.4 8.354 14.000 .000 92.3 4.34 48.8 8.459 14.083 .000 94.2 4.37 49.2 8.573 14.167 .000 96.7 4.42 49.6 8.702 14.250 .000 100.4 4.47 50.1 8.853 14.333 .000 104.9 4.52 50.7 9.030 14.417 .000 110.1 4.59 51.5 9.238 14.500 .000 115.4 4.67 52.3 9.477 14.583 .000 120.0 4.76 53.2 9.741 14.667 .000 123.8 4.85 54.2 10.025 14.750 .000 127.4 4.95 55.1 10.327 14.833 .000 130.7 5.05 56.0 10.646 14.917 .000 134.1 5.16 57.0 10.981 15.000 .000 137.5 5.27 58.0 11.333 15.083 .000 141.2 5.39 59.1 11.703 15.167 .000 145.2 5.51 60.3 12.093 15.250 .000 149.6 5.65 61.5 12.504 15.333 .000 154.5 5.79 62.7 12.941 15.417 .000 160.2 5.93 64.0 13.408 15.500 .000 167.1 6.09 65.2 13.914 Page 11 15.583 .000 176.3 6.27 66.6 14.474 15.667 .000 187.2 6.47 68.1 15.099 15.750 .000 200.2 6.69 69.8 15.802 15.833 .000 214.4 6.93 71.6 16.589 15.917 .000 230.1 7.20 73.5 17.472 16.000 .000 250.1 7.51 75.6 18.479 16.083 .000 284.4 7.89 78.0 19.704 16.167 .000 333.9 8.35 80.9 21.251 16.250 .000 397.2 8.93 84.4 23.210 16.333 .000 436.3 9.58 88.3 25.411 16.417 .000 457.6 10.25 92.3 27.731 16.500 .000 435.2 10.86 96.1 29.871 16.583 .000 377.4 11.35 99.1 31.592 16.667 .000 316.3 11.71 101.4 32.876 16.750 .000 266.2 11.96 103.1 33.804 16.833 .000 229.1 12.15 104.2 34.468 16.917 .000 199.6 12.27 105.1 34.923 17.000 .000 176.9 12.35 105.6 35.218 17.083 .000 162.2 12.41 106.0 35.410 17.167 .000 151.5 12.44 106.2 35.527 17.250 .000 141.3 12.45 106.3 35.572 17.333 .000 131.5 12.44 106.3 35.550 17.417 .000 119.9 12.42 106.2 35.449 17.500 .000 111.3 12.37 106.0 35.290 17.583 .000 104.5 12.32 105.8 35.085 17.667 .000 99.0 12.25 105.5 34.845 17.750 .000 94.6 12.18 105.1 34.577 17.833 .000 90.9 12.10 104.7 34.287 17.917 .000 87.7 12.01 104.2 33.978 18.000 .000 85.0 11.92 103.8 33.652 18.083 .000 82.7 11.83 103.3 33.315 18.167 .000 81.1 11.73 102.8 32.970 18.250 .000 80.7 11.64 102.3 32.626 18.333 .000 81.1 11.54 101.8 32.288 18.417 .000 82.2 11.45 101.3 31.961 18.500 .000 83.4 11.36 100.8 31.646 18.583 .000 83.9 11.27 100.3 31.338 18.667 .000 83.8 11.19 99.8 31.032 18.750 .000 83.3 11.10 99.4 30.725 18.833 .000 82.5 11.02 98.9 30.417 18.917 .000 81.6 10.93 98.4 30.105 19.000 .000 80.6 10.84 98.0 29.790 19.083 .000 79.5 10.75 97.5 29.471 19.167 .000 78.5 10.66 96.9 29.148 19.250 .000 77.5 10.56 96.4 28.822 19.333 .000 76.7 10.47 95.9 28.495 19.417 .000 75.8 10.37 95.3 28.164 19.500 .000 74.9 10.28 94.8 27.832 19.583 .000 74.1 10.18 94.2 27.498 19.667 .000 73.3 10.09 93.6 27.162 19.750 .000 72.5 9.99 93.1 26.825 19.833 .000 71.8 9.89 92.5 26.486 19.917 .000 71.1 9.80 92.0 26.146 20.000 .000 70.4 9.70 91.4 25.806 20.083 .000 69.7 9.60 90.7 25.466 20.167 .000 69.1 9.50 90.1 25.125 20.250 .000 68.4 9.40 89.5 24.784 20.333 .000 67.8 9.30 88.9 24.444 20.417 .000 67.2 9.20 88.3 24.103 20.500 .000 66.7 9.10 87.7 23.763 20.583 .000 66.1 9.00 87.0 23.424 20.667 .000 65.6 8.90 86.4 23.085 20.750 .000 65.1 8.80 85.8 22.746 20.833 .000 64.6 8.70 85.2 22.409 20.917 .000 64.1 8.60 84.5 22.073 Page 12 21.000 .000 63.6 8.50 83.8 21.738 21.083 .000 63.1 8.40 83.1 21.405 21.167 .000 62.7 8.30 82.5 21.073 21.250 .000 62.2 8.20 81.8 20.742 21.333 .000 61.8 8.10 81.1 20.413 21.417 .000 61.4 8.00 80.5 20.086 21.500 .000 60.9 7.90 79.8 19.761 21.583 .000 60.5 7.81 79.2 19.437 21.667 .000 60.1 7.71 78.5 19.115 21.750 .000 59.8 7.61 77.8 18.795 21.833 .000 59.4 7.51 77.1 18.478 21.917 .000 59.0 7.41 76.4 18.163 22.000 .000 58.6 7.32 75.7 17.850 22.083 .000 58.3 7.22 75.0 17.S39 22.167 .000 57.9 7.13 74.3 17.231 22.250 .000 57.6 7.03 73.6 16.925 22.333 .000 57.3 6.94 73.0 16.621 22.417 .000 56.9 6.85 72.3 16.320 22.500 .000 56.6 6.76 71.6 16.021 22.583 .000 56.3 6.66 70.9 15.725 22.667 .000 56.0 6.57 70.1 15.432 22.750 .000 55.7 6.48 69.4 15.143 22.833 .000 55.4 6.39 68.6 14.856 22.917 .000 55.1 6.30 67.9 14.572 23.000 .000 54.8 6.21 67.2 14.291 23.083 .000 54.5 6.12 66.5 14.013 23.167 .000 54.3 6.04 65.8 13.738 23.250 .000 54.0 5.95 65.1 13.466 23.333 .000 53.7 5.87 64.4 13.197 23.417 .000 53.5 5.78 63.7 12.931 23.500 .000 53.2 5.70 63.0 12.669 23.583 .000 53.0 5.62 62.2 12.409 23.667 .000 52.7 5.53 61.4 12.154 23.750 .000 52.5 5.45 60.7 11.902 23.833 .000 52.2 5.37 59.9 11.653 23.917 .000 52.0 5.29 59.2 11.408 24.000 .000 51.7 5.22 58.4 11.167 24.083 .000 50.9 5.14 57.7 10.924 24.167 .000 48.4 5.06 57.0 10.669 24.250 .000 42.9 4.96 56.2 10.382 24.333 .000 35.6 4.86 55.2 10.051 24.417 .000 26.4 4.73 54.1 9.665 24.500 .000 17.5 4.S9 52.6 9.227 24.583 .000 11.0 4.43 50.9 8.757 24.667 .000 6.8 4.27 49.2 8.270 24.750 .000 4.3 4.11 47.3 7.778 24.833 .000 2.7 3.95 45.5 7.287 24.917 .000 1.7 3.79 43.7 6.803 25.000 .000 1.3 3.63 41.5 6.330 25.083 .000 1.1 3.48 39.1 5.873 25.167 .000 .8 3.33 36.7 5.430 25.250 .000 .6 3.18 34.4 5.002 25.333 .000 .3 3.04 32.2 4.587 25.417 .000 .3 2.91 30.0 4.187 25.500 .000 .3 2.77 27.9 3.801 25.583 .000 .2 2.60 25.5 3.431 25.667 .000 .2 2.44 23.0 3.078 25.750 .000 .2 2.29 20.6 2.742 25.833 .000 .2 2.15 18.3 2.422 25.917 .000 .1 2.01 16.1 2.117 26.000 .000 .1 1.88 14.0 1.826 26.083 .000 .1 1.73 12.0 1.549 26.167 .000 .1 1.53 10.3 1.283 26.250 .000 .1 1.35 8.8 1.027 26.333 .000 .1 1.17 7.3 .782 Page 13 26.417 .000 .1 1.00 5.8 .547 26.500 .000 .0 .84 4.5 .320 26.583 .000 .0 .32 2.6 .107 26.667 .000 .0 .00 .7 .000 26.750 .000 .0 .00 .0 .000 26.833 .000 .0 .00 .0 .000 26.917 .000 .0 .00 .0 .000 27.000 .000 .0 .00 .0 .000 27.083 .000 .0 .00 .0 .000 27.167 .000 .0 .00 .0 .000 27.250 .000 .0 .00 .0 .000 27.333 .000 .0 .00 .0 .000 27.417 .000 .0 .00 .0 .000 27.500 .000 .0 .00 .0 .000 27.583 .000 .0 .00 .0 .000 27.667 .000 .0 .00 .0 .000 27.750 .000 .0 .00 .0 .000 27.833 .000 .0 .00 .0 .000 27.917 .000 .0 .00 .0 .000 28.000 .000 .0 .00 .0 .000 28.083 .000 .0 .00 .0 .000 28.167 .000 .0 .00 .0 .000 28.250 .000 .0 .00 .0 .000 28.333 .000 .0 .00 .0 .000 28.417 .000 .0 .00 .0 .000 28.500 .000 .0 .00 .0 .000 28.583 .000 .0 .00 .0 .000 28.667 .000 .0 .00 .0 .000 28.750 .000 .0 .00 .0 .000 28.833 .000 .0 .00 .0 .000 28.917 .000 .0 .00 .0 .000 29.000 .000 .0 .00 .0 .000 29.083 .000 .0 .00 .0 .000 29.167 .000 .0 .00 .0 .000 29.250 .000 .0 .00 .0 .000 29.333 .000 .0 .00 .0 .000 29.417 .000 .0 .00 .0 .000 29.500 .000 .0 .00 .0 .000 29.583 .000 .0 .00 .0 .000 29.667 .000 .0 .00 .0 .000 29.750 .000 .0 .00 .0 .000 29.833 .000 .0 .00 .0 .000 29.917 .000 .0 .00 .0 .000 30.000 .000 .0 .00 .0 .000 30.083 .000 .0 .00 .0 .000 30.167 .000 .0 .00 .0 .000 30.250 .000 .0 .00 .0 .000 30.333 .000 .0 .00 .0 .000 30.417 .000 .0 .00 .0 .000 30.500 .000 .0 .00 .0 .000 30.583 .000 .0 .00 .0 .000 30.667 .000 .0 .00 .0 .000 30.750 .000 .0 .00 .0 .000 30.833 .000 .0 .00 .0 .000 30.917 .000 .0 .00 .0 .000 31.000 .000 .0 .00 .0 .000 31.083 .000 .0 .00 .0 .000 31.167 .000 .0 .00 .0 .000 31.250 .000 .0 .00 .0 .000 31.333 .000 .0 .00 .0 .000 31.417 .000 .0 .00 .0 .000 31.500 .000 .0 .00 .0 .000 31.583 .000 .0 .00 .0 .000 31.667 .000 .0 .00 .0 .000 31.750 .000 .0 .00 .0 .000 Page 14 31.833 .000 .0 .00 .0 .000 31.917 .000 .0 .00 .0 .000 32.000 .000 .0 .00 .0 .000 32.083 .000 .0 .00 .0 .000 32.167 .000 .0 .00 .0 .000 32.250 .000 .0 .00 .0 .000 32.333 .000 .0 .00 .0 .000 32.417 .000 .0 .00 .0 .000 32.500 .000 .0 .00 .0 .000 32.583 .000 .0 .00 .0 .000 32.667 .000 .0 .00 .0 .000 32.750 .000 .0 .00 .0 32.833 .000 .0 .00 .0 .000 .000 32.917 .000 .0 .00 .0 .000 33.000 .000 .0 .00 .0 33.083 .000 .0 .00 .0 .000 .000 33.167 .000 .0 .00 .0 .000 33.250 .000 .0 .00 .0 .000 33.333 .000 .0 .00 .0 .000 33.417 .000 .0 .00 .0 .000 33.500 .000 .0 .00 .0 .000 33.583 .000 .0 .00 .0 .000 33.667 .000 .0 .00 .0 .000 33.750 .000 .0 .00 .0 .000 33.833 .000 .0 .00 .0 33.917 .000 .0 .00 .0 .000 .000 34.000 .000 .0 .00 .0 .000 34.083 .000 .0 .00 .0 .000 34.167 .000 .0 .00 .0 .000 34.250 .000 .0 .00 .0 .000 34.333 .000 .0 .00 .0 .000 34.417 .000 .0 .00 .0 .000 34.500 .000 .0 .00 .0 .000 34.583 .000 .0 .00 .0 .000 34.667 .000 .0 .00 .0 .000 34.750 .000 .0 .00 .0 .000 34.833 .000 .0 .00 .0 .000 34.917 .000 .0 .00 .0 .000 35.000 .000 .0 .00 .0 .000 35.083 .000 .0 .00 .0 .000 35.167 .000 .0 .00 .0 .000 35.250 .000 .0 .00 .0 .000 35.333 .000 .0 .00 .0 .000 35.417 .000 .0 .00 .0 35.500 .000 .0 .00 .0 .000 .000 35.583 .000 .0 .00 .0 .000 35.667 .000 .0 .00 .0 .000 35.750 .000 .0 .00 .0 .000 35.833 .000 .0 .00 .0 .000 35.917 .000 .0 .00 .0 .000 36.000 .000 .0 .00 .0 .000 36.083 .000 .0 .00 .0 .000 36.167 .000 .0 .00 .0 .000 36.250 .000 .0 .00 .0 .000 36.333 .000 .0 .00 .0 .000 36.417 .000 .0 .00 .0 .000 36.500 .000 .0 .00 .0 .000 36.583 .000 .0 .00 .0 .000 36.667 .000 .0 .00 .0 .000 36.750 .000 .0 .00 .0 .000 36.833 .000 .0 .00 .0 .000 36.917 .000 .0 .00 .0 .000 37.000 .000 .0 .00 .0 .000 37.083 .000 .0 .00 .0 .000 37.167 .000 .0 .00 .0 .000 Page 15 37.250 .000 .0 .00 .0 37.333 .000 .0 .00 .0 .000 37.417 .000 .0 .00 .0 .000 37.500 .000 .0 .00 .0 .000 37.583 .000 .0 .00 .0 .000 37.667 .000 .0 .00 .0 .000 37.750 .000 .0 .00 .0 .000 37.833 .000 .0 .00 .0 .000 37.917 .000 .0 .00 .0 .000 38.000 .000 .0 .00 .0 .000 38.083 .000 .0 .00 .0 .000 38.167 .000 .0 .00 .0 .000 38.250 .000 .0 .00 .0 .000 38.333 .000 .0 .00 .0 .000 38.417 .000 .0 .00 .0 .000 38.500 .000 .0 .00 .0 .000 38.583 .000 .0 .00 .0 .000 38.667 .000 .0 .00 .0 .000 38.750 .000 .0 .00 .0 .000 38.833 .000 .0 .00 .0 .000 38.917 .000 .0 .00 .0 .000 39.000 .000 .0 .00 .0 .000 .000 39.083 .000 .0 .00 .0 39.167 .000 .0 .00 .0 .000 39.250 .000 .0 .00 .0 .000 39.333 .000 .0 .00 .0 .000 39.417 .000 .0 .00 .0 .000 39.500 .000 .0 .00 .0 .000 39.583 .000 .0 .00 .0 .000 39.667 .000 .0 .00 .0 .000 39.750 .000 .0 .00 .0 .000 39.833 .000 .0 .00 .0 .000 39.917 .000 .0 .00 .0 .000 40.000 ---------------------------------------------------------- .000 .0 .00 .0 .000 .000 PROCESS SUMMARY OF STORAGE: INFLOW VOLUME = 168.809 AF BASIN STORAGE = .000 AF (WITH .000 AF INITIALLY FILLED) OUTFLOW VOLUME = 106.935 AF LOSS VOLUME = 61.874 AF :�:�*art::r��:s:���:t�-**��:��r�*�*��*�*���:�:�:i.����•�:�:��*��r�•::�:���:��:�:�::���:���**�:::se::*�:::�::: FLOW PROCESS FROM NODE 400.00 TO NODE 400.00 IS CODE 11 -------------------------------------------------------------------------- »»>VIEW STREAM NUMBER 1 HYDROGRAPH««< STREAM HYDROGRAPH IN FIVE-MINUTE INTERVALS(CFS) ----------------------------------------------- TIME(HRS) - ----------------------------- VOLUME(AF) Q(CFS) 0. 50.0 100.0 150.0 200.0 .083 .0000 ------------------------------------------ .00 Q .167 .0000 .00 Q .250 .0000 .00 Q .333 .0000 .00 Q .417 .0000 .00 Q ' .500 .0014 .21 Q .583 .0075 .88 Q ' .667 .0210 1.96 Q .750 .0425 3.13 Q .833 .0702 4.01 Q .917 .1023 4.67 Q ' 1.000 .1391 5.33 VQ Page 16 1.083 .1803 5.99 VQ 1.167 .2259 6.63 vQ 1.250 .2759 7.26 vQ 1.333 .3302 7.88 vQ 1.417 .3886 8.48 vQ 1.500 .4510 9.07 vQ 1.583 .5174 9.63 vQ 1.667 .5875 10.19 v Q 1.750 .6613 10.72 v Q 1.833 .7388 11.24 v Q 1.917 .8198 11.77 V Q 2.000 .9047 12.33 V Q 2.083 .9934 12.88 v Q 2.167 1.0858 13.42 v Q 2.250 1.1818 13.93 v Q 2.333 1.2812 14.43 V Q 2.417 1.3839 14.91 V Q 2.500 1.4898 15.38 v Q 2.583 1.5988 15.83 V Q 2.667 1.7108 16.26 v Q 2.750 1.8257 16.68 v Q 2.833 1.9434 17.09 V Q 2.917 2.0638 17.49 v Q 3.000 2.1869 17.87 v Q 3.083 2.3125 18.24 v Q 3.167 2.4406 18.60 v Q 3.250 2.5711 18.95 v Q 3.333 2.7039 19.29 .v Q 3.417 2.8391 19.62 .v Q 3.500 2.9764 19.94 .v Q 3.583 3.1159 20.25 :v Q 3.667 3.2575 20.56 .v Q 3.750 3.4011 20.86 .v Q 3.833 3.5467 21.15 .v Q 3.917 3.6943 21.43 v Q 4.000 3.8438 21.71 .v Q 4.083 3.9952 21.98 v Q 4.167 4.1484 22.24 .v Q 4.250 4.3034 22.50 .v Q 4.333 4.4601 22.76 v Q 4.417 4.6186 23.01 v Q 4.500 4.7787 23.26 .v Q 4.583 4.9406 23.50 .v Q 4.667 5.1040 23.74 v Q 4.750 5.2691 23.97 v Q 4.833 5.4358 24.20 V Q 4.917 5.6040 24.43 v Q 5.000 5.7738 24.65 v Q 5.083 5.9452 24.88 v Q 5.167 6.1180 25.10 v Q 5.250 6.2924 25.32 v Q 5.333 6.4682 25.53 v Q 5.417 6.6455 25.74 V Q 5.500 6.8243 25.96 v Q 5.583 7.0045 26.17 v Q 5.667 7.1862 26.38 v Q 5.750 7.3692 26.59 v Q 5.833 7.5538 26.79 v Q 5.917 7.7397 27.00 v Q 6.000 7.9271 27.20 V Q 6.083 8.1156 27.38 v Q 6.167 8.3053 27.54 v Q 6.250 8.4960 27.69 V Q 6.333 8.6878 27.85 v Q 6.417 8.8807 28.01 V Q Page 17 6.500 9.0748 28.17 V Q 6.583 9.2699 28.34 v Q , 6.667 9.4662 28.50 V Q 6.750 9.6636 28.67 V Q . 6.833 9.8622 28.83 V Q 6.917 10.0619 29.00 v Q 7.000 10.2629 29.17 V Q 7.083 10.4650 29.35 V Q 7.167 10.6683 29.52 v Q 7.250 10.8728 29.70 vQ 7.333 11.0786 29.88 VQ 7.417 11.2856 30.06 v Q 7.500 11.4938 30.24 V Q 7.583 11.7034 30.42 V Q 7.667 11.9142 30.61 v Q , 7.750 12.1263 30.80 V Q 7.833 12.3397 30.99 v Q 7.917 12.5544 31.18 v Q 8.000 12.7705 31.38 v Q 8.083 12.9880 31.57 v Q 8.167 13.2068 31.77 v Q 8.250 13.4270 31.98 VQ 8.333 13.6487 32.18 VQ 8.417 13.8717 32.39 VQ 8.500 14.0962 32.60 VQ 8.583 14.3221 32.81 VQ 8.667 14.5496 33.02 VQ 8.750 14.7785 33.24 VQ 8.833 15.0089 33.46 VQ 8.917 15.2409 33.68 VQ , 9.000 15.4744 33.91 VQ , 9.083 15.7095 34.14 VQ 9.167 15.9462 34.37 VQ 9.250 16.1846 34.60 Q , 9.333 16.4245 34.84 Q 9.417 16.6661 35.08 VQ 9.500 16.9094 35.33 VQ 9.583 17.1544 35.57 VQ , 9.667 17.4012 35.83 VQ 9.750 17.6497 36.08 VQ 9.833 17.8999 36.34 VQ 9.917 18.1520 36.60 VQ 10.000 18.4059 36.87 VQ 10.083 18.6617 37.14 VQ 10.167 18.9194 37.41 Q 10.250 19.1790 37.69 Q 10.333 19.4405 37.97 Q 10.417 19.7040 38.26 Q , 10.500 19.9695 38.55 Q 10.583 20.2371 38.85 Q 10.667 20.5067 39.15 Q 10.750 20.7785 39.46 Q , 10.833 21.0524 39.77 Q 10.917 21.3284 40.09 VQ , 11.000 21.6067 40.41 Q 11.083 21.8872 40.73 Q . 11.167 22.1701 41.07 Q . 11.250 22.4552 41.41 Q . 11.333 22.7428 41.75 Q . 11.417 23.0328 42.10 Q . 11.500 23.3252 42.46 Q . 11.583 23.6200 42.81 Q , 11.667 23.9169 43.11 Q . 11.750 24.2157 43.38 QV. 11.833 24.5164 43.66 QV. Page 18 11.917 24.8191 43.95 QV. 12.000 25.1238 44.24 QV. 12.083 25.4306 44.55 Qv. 12.167 25.7394 44.84 QV. , 12.250 26.0502 45.12 Q. 12.333 26.3625 45.36 Q. 12.417 26.6762 45.54 Q. 12.500 26.9907 45.67 QV 12.583 27.3058 45.75 QV 12.667 27.6212 45.80 QV 12.750 27.9369 45.85 QV 12.833 28.2531 45.90 QV 12.917 28.5696 45.96 QV 13.000 28.8867 46.04 Qv 13.083 29.2044 46.14 QV 13.167 29.5230 46.26 Q.V 13.250 29.8425 46.40 . Q.V 13.333 30.1632 46.56 Q.V 13.417 30.4851 46.74 Q.V 13.500 30.8084 46.95 Q.V 13.583 31.1334 47.18 Q.V 13.667 31.4601 47.44 Q.V 13.750 31.7889 47.73 Q.V 13.833 32.1197 48.04 Q. V 13.917 32.4530 48.39 Q. v 14.000 32.7888 48.76 Q. v 14.083 33.1274 49.17 Q. v 14.167 33.4692 49.62 Q. v 14.250 33.8145 50.14 Q v 14.333 34.1640 50.75 Q v 14.417 34.5184 51.47 Q v 14.500 34.8786 52.30 Q v 14.583 35.2452 53.23 Q v 14.667 35.6184 54.19 Q v 14.750 35.9980 55.12 Q v 14.833 36.3840 56.04 Q V 14.917 36.7767 57.02 Q v 15.000 37.1765 58.05 Q v 15.083 37.5837 59.13 Q v 15.167 37.9987 60.26 Q V 15.250 38.4220 61.46 Q v 15.333 38.8541 62.73 Q v 15.417 39.2947 63.99 Q v 15.500 39.7440 65.23 QV 15.583 40.2026 66.59 Q V 15.667 40.6716 68.10 Q V 15.750 41.1523 69.79 Q V 15.833 41.6455 71.62 QV 15.917 42.1519 73.52 QV 16.000 42.6726 75.61 Q . 16.083 43.2101 78.05 QV 16.167 43.7675 80.93 Q 16.250 44.3488 84.41 Q 16.333 44.9572 88.34 VQ 16.417 45.5931 92.32 VQ . 16.500 46.2547 96.07 V Q. 16.583 46.9375 99.14 V Q. 16.667 47.6360 101.42 v Q 16.750 48.3459 103.08 v Q 16.833 49.0639 104.25 v Q 16.917 49.7875 105.06 V .Q 17.000 50.5148 105.61 v .Q 17.083 51.2446 105.96 V.Q 17.167 51.9759 106.19 v.Q 17.250 52.7081 106.31 v.Q Page 19 17.333 53.4403 106.32 V.Q 17.417 54.1720 106.23 VQ 17.500 54.9023 106.05 VQ 17.583 55.6308 105.78 VQ 17.667 56.3571 105.46 ,Q 17.750 57.0809 105.09 ,Q 17.833 57.8018 104.68 QV 17.917 58.5197 104.24 QV 18.000 59.2345 103.78 Q v 18.083 59.9459 103.30 Q V 18.167 60.6538 102.79 Q V 18.250 61.3582 102.28 Q V 18.333 62.0590 101.76 Q V 18.417 62.7564 101.25 Q V , 18.500 63.4504 100.77 Q V 18.583 64.1411 100.29 Q v 18.667 64.8286 99.83 Q, v , 18.750 65.5129 99.36 Q. v 18.833 66.1940 98.90 Q. v 18.917 66.8719 98.43 Q, V , 19.000 67.5465 97.95 Q, V 19.083 68.2177 97.46 Q. v 19.167 68.8853 96.93 Q. V 19.250 69.5492 96.40 Q, V 19.333 70.2093 95.85 Q. v 19.417 70.8657 95.31 Q. V 19.500 71.5182 94.75 Q V 19.583 72.1670 94.20 Q V 19.667 72.8120 93.64 Q V , 19.750 73.4530 93.08 Q V 19.833 74.0902 92.52 Q V 19.917 74.7236 91.96 Q V 20.000 75.3528 91.37 Q V , 20.083 75.9778 90.75 Q v , 20.167 76.5985 90.13 Q v , 20.250 77.2150 89.51 Q V , 20.333 77.8271 88.89 Q v. 20.417 78.4351 88.27 Q V. 20.500 79.0387 87.65 Q V. 20.583 79.6381 87.03 Q V. 20.667 80.2333 86.42 Q V 20.750 80.8242 85.80 Q V 20.833 81.4106 85.15 Q V 20.917 81.9924 84.48 Q v 21.000 82.5696 83.80 Q V 21.083 83.1421 83.13 Q v 21.167 83.7100 82.46 Q .V 21.250 84.2733 81.79 Q V 21.333 84.8320 81.13 Q V 21.417 85.3862 80.47 Q ,V 21.500 85.9359 79.81 Q V 21.583 86.4811 79.16 Q V 21.667 87.0216 78.48 Q v 21.750 87.5572 77.77 Q V 21.833 88.0880 77.07 Q v 21.917 88.6140 76.37 Q V 22.000 89.1352 75.68 Q v 22.083 89.6516 74.99 Q . v 22.167 90.1634 74.31 Q v 22.250 90.6704 73.63 Q v , 22.333 91.1729 72.95 Q v 22.417 91.6707 72.29 Q V 22.500 92.1638 71.60 Q V 22.583 92.6519 70.87 Q V 22.667 93.1348 70.12 Q V , Page 20 22.750 93.6126 69.38 Q v 22.833 94.0854 68.64 Q v 22.917 94.5531 67.92 Q v 23.000 95.0159 67.20 Q v 23.083 95.4738 66.49 Q v 23.166 95.9269 65.78 Q v 23.250 96.3751 65.09 Q v 23.333 96.8186 64.40 Q v 23.416 97.2573 63.70 Q v 23.500 97.6910 62.96 Q v 23.583 98.1192 62.18 Q v 23.666 98.5422 61.41 Q v 23.750 98.9599 60.65 Q v 23.833 99.3724 59.90 Q v , 23.916 99.7799 59.17 Q v 24.000 100.1824 58.44 ,Q v , END OF FLOOD ROUTING ANALYSIS Page 21 Technical Appendix 00-Year Hydraulic Analysis H P a O O O O O 00 O r•C *� O O O O O O O O W x C7 a x' WZ H * O O O O O O O 0 a * x * o O O o o o 0 O 0 0 0 0 0 0 0 0 0 0 0 N N* x O O O p O O O O O O o x x 0 O o O O O O O O O O O O O O x O x O O O O O O O O CQ * 0 O O O O O m W pl H x x \ x H d k O Ln O Ln O Ln O Ln O Ln O Ln O O O o N N x H a x W x N M O o O O 0 p O O O p Q x x o Ln Ln un Ln o x M W W W W N O � a z x RC # # N N N N N N O O U x x M M M M M (+1 O O H rN x O O O O o O O O H W aQ # M M M N N U x x W � o 0 0 0 0 0 0 0 z p� x H F a u? W * o 0 o O o 0 0 0 U) H N of ri m m Ul O O N N O W H to ri m N M N !n a a W W W W x r O m o m O m N rl o [, p m O m Ln 0 w H W Ln a C7 # x o # W W U W x na .7 x 'a", Ol N N M N N. d' M N N W M N N W m N N W M O to W H M l0 W a r+y # to M10 Ol 10 0l 10 T Ol to (:7 m O m Ga (P�✓` W WWWW x SI'. W# 0 N O O N p O N. O O N 0 N 0 O HO H R H cn * O O O p p p x W x m m m m m m O O •� H H * 10 to to 1p b k o En W FC W # Of x to o 1D 0 w 0 10 0 10 to 10 to P1 rr14 n H 0 0 0 0 �nz�a x in H x z# O Ol M m Ln L` N N H LQ x # O 1+ H M N Ln 0 L` M of r- ri H In Ln L` z CA O U1 W # a x W # Zr M W M W M W M to M [r M tD M W M i H WHO # W o v3 Q H $ # .'L' O x O N of p M m Ln L` N N .CTJ. M to 10 to Ln h z � o # rj) 2aji H x P�' * m 10 N lO H r vl H 01 r r Vl W m ri Ln r o1 r4 W N O o l0 l0 o M W m ' o H W W # a p x m W 0 m ri. o m H o w ri O m H o 0 H o 0 H o o aW Ul * N O N O N O N O N o M (D M O M * O O O O O O. O # x W o W !h H L` m W W Ln of W' Or W M W O * O Ln Ln 1D N l� of L` O m U) W H # F a# w x O ri o 10 w ri o m 10 lD m o r1 (+). h ri H O Ln r m to m In M M o m Ul m N m W H N W M M M. M m M m M H a a# # M E. O � p � H � p O z Ep Hp E+ O Ho Hp El W a 0 a 0 a O a o a O 0,0 c7 [q o rn o ro o o rq o cry o Q p' rz� FzC .zt F2C FzC FzC a0 . O a 0 a 0 tW-1 0 a 00 4 p0 H O O p 001 o u U] O UI O U) O Ul 0 0 p a .h. p O '.7 O O H O H p W z0 z0 z 0 zp O zp p p m o W� W0 z �+ H z 0 H H a w # a H U] M m m m M cN z �7i O zi O z p z O 'fy O O .h H O O O O O O O [s] a ,a ao Ln o N m # a ULn U V UC U a Ud U �N U N U N # (HjNztq W W ut W in G 7 to W vt Ln Ln Ln in wl zHz H U) U) W Ul a U) Ul U] z # # # # # z W H m H Ll + # ID RE'. PE'. NW. Orl PH'. O RE'. o a co pE', o W H O� N HN ,�N N N m mM m0O a zH O # z N # Z N # z p�j #. z Vim' # z r # z r # co m H .% Oko O r Om Om O w ON pNza Ea O N O H p H H H H W H f O W H H m F m F m H m `� H F� CD M m F E N rn H Rm rymW w ato m m � CH z� z F N F H F H ~ FC FC O c/3 Eg- H U fy. 0)m �U) U\ \ w� � \ Ucn �U] aFC U) O a � 'J a 'J [4 a' 'a N '.�' ."� cca zzH 3 FC rC FC Q FC FC FC rC o U) U] U] U) U) U] W U) rn U # H H H H H H H H H z W cq H N m <r in io � m of uz oz z zW z z zz z z EH zz z W W HM zaH�C DI a w w w w w w DIw w w w O# z# it ic'.c irfr it is irfr tr irfr iefr fr4r is is frfrfrie ie irfr it it is irfrfrir is iefrfrie irfr*irfr itfrfrfrfrir it is ie is is itfrfric it irfr it ie it it is iefr*frfrfriefr *fr it it it PIPE -FLOW HYDRAULICS COMPUTER PROGRAM PACKAGE (Reference: LACFCD,LACRD, AND OCEMA HYDRAULICS CRITERION) (c) Copyright 1982-93 Advanced Engineering Software (aes) Ver. 4.6A Release Date: 7/18/93 License ID 1202 Analysis prepared by: HUITT-ZOLLARS, INC. 15101 RED HILL AVENUE TUSTIN, CALIFORNIA 92780-6500 PHONE (714) 259-7900 * FAX (714) 259-0210 irfr fric icfrfrfrfric it is icfrfrfrfriefr frfrfrirfrfrir DESCRIPTION OF STUDY i` SIERRA BUSINESS PARK it i` SIERRA AVENUE / SLOVER AVENUE STORM DRAIN i` 100-YEAR HYDRAULIC ANALYSIS is irfr irfr is irfrfrir irfr irfr frfrfr*fr irfr icfr*fricfr iv irfrfrfrfrfrfrirfr *isfrfr icfr frfr irfr irfr frfr *frfrfrfrfrfrfrfr iefr iefr it*frfrfrfrfr*irfr* --------------- FILE NAME: SBPMA100.HGL TIME/DATE OF STUDY: 7:49 6/17/2004 fr frfrirfr frfrit tYfr frirfr frfrfrfrfrfrfrfrfrfrfrfrfrfrfrfrfr*frfrfric it irfrfr*frfrfrfrfrfrfricicirfr frfrfrfrfrfrfrfrfrfrfrfricfr irfr fricfr frfr it icfrirfrfr GRADUALLY VARIED FLOW ANALYSIS FOR PIPE SYSTEM NODAL POINT STATUS TABLE (Note: "*" indicates nodal point data used.) UPSTREAM RUN DOWNSTREAM RUN NODE MODEL PRESSURE PRESSURE+ FLOW PRESSURE+ NUMBER PROCESS HEAD(FT) MOMENTUM(POUNDS) DEPTH(FT) MOMENTUM(POUNDS) 4997.86- 11.82* 41750.59 5.03 27006.21 1 FRICTION 5262.77- 11.21* 39321.17 4.50 29171.11 1 FRICTION+BEND 5347.58- 11.24* 39459.75 4.31 30220.23 1 FRICTION 5355.57- 11.22* 39385.61 4.30 30331.07 1 JUNCTION 2252.33- 8.49* 31334.17 6.48 DC 27519.51 1 FRICTION 2736.17- 9.97* 35411.84 6.48 DC 27519.51 1 JUNCTION 2740.83- 10.54* 34717.80 6.30 DC 25013.43 1 FRICTION 3121.17- 11.37* 37014.54 6.30 DC 25013.43 1 JUNCTION 3125.83- 11.38* 37038.80 6.30 DC 25013.43 1 FRICTION 3565.58- 12.34* 39687.25 6.30 DC 25013.43 1 JUNCTION 3582.33- 13.64* 38907.53 5.03 20667.79 1 FRICTION 3590.58- 13.65* 38927.13 4.99 20726.65 1 JUNCTION 3607.33- 11.97* 17024.79 2.41 11972.71 1 FRICTION 1 HYDRAULIC JUMP 3787.69- 4.32*Dc 8165.33 4.32*DC 8165.33 1 JUNCTION 3794.35- 5.17* 8126.47 3.75 7692.10 1 FRICTION 1 HYDRAULIC JUMP 4247.67- 4.22 DC 7541.13 3.07* 8594.43 1 JUNCTION 4252.33- 4.16*DC 8111.70 4.16*Dc 8111.70 Page 1 } FRICTION 4459.70- 5.05* 8778.84 4.16 DC 8111.70 } JUNCTION 4459.70- 6.33* 8122.28 3.51 6177.37 } FRICTION 4719.80- 6.11* 7900.30 3.50 6185.94 } JUNCTION 4724.46- 6.05* 7841.02 3.53 6167.94 } FRICTION 4974.99- 5.83* 7626.30 3.91 DC 6076.29 } JUNCTION 4974.99- 6.73* 6862.25 2.80 4478.40 } FRICTION 5219.37- 5.71* 5851.15 2.49 4847.70 } JUNCTION 5227.28- 4.51* 5022.78 3.12 4571.36 } FRICTION 5300.00- 4.46* 4981.84 3.09 4588.02 } JUNCTION 5300.00- 4.47* 4989.37 3.07 4600.37 } FRICTION } HYDRAULIC JUMP 5574.44- 4.36 4905.82 2.53* 5160.53 } FRICTION+BEND 5602.48- 4.34 4889.47 2.45* 5285.50 } JUNCTION 5607.14- 3.36*DC 5009.23 3.36*DC 5009.23 } FRICTION+BEND 5748.25- 4.90* 5880.55 3.36 DC 5009.23 } FRICTION 5895.25- 6.31* 6724.26 3.36 DC 5009.23 } JUNCTION 5895.25- 6.33* 6736.00 3.36 DC 5009.23 } FRICTION 5947.67- 6.83* 7039.37 3.36 DC 5009.23 } JUNCTION 5952.33- 8.21* 6927.50 3.27 DC 4051.30 } FRICTION 6132.50- 9.39* 7638.67 3.26 DC 4051.31 } JUNCTION 6132.50- 9.41* 7647.65 3.27 DC 4051.30 } FRICTION 6270.81- 10.32* 8193.07 2.97 4115.97 } FRICTION+BEND 6285.81- 10.51* 8310.81 3.26 DC 4051.31 } JUNCTION 6285.81- 10.53* 8319.78 3.27 DC 4051.30 } FRICTION+BEND 6343.04- 11.62* 8972.74 3.27 DC 4051.30 } FRICTION 6358.16- 11.78* 9072.53 3.27 DC 4051.30 } JUNCTION 6362.83- 13.00* 8980.87 3.12 DC 3194.26 } FRICTION 6763.18- 15.77* 10646.16 3.12 DC 3194.26 } JUNCTION 6773.18- 17.47* 9929.15 2.20 DC 1121.75 } FRICTION 6884.95- 17.29* 9820.62 2.20 DC 1121.75 } JUNCTION 6884.95- 17.33* 9822.01 2.17 DC 1086.37 } FRICTION 7143.95- 16.89* 9554.36 2.17 DC 1086.37 } JUNCTION 7149.45- 17.01* 9538.11 1.97 941.33 } FRICTION Page 2 7239.93- 16.73* 9367.95 1.97 941.59 1 FRICTION+BEND 7315.36- 16.54* 9257.41 2.05 DC 939.31 1 JUNCTION 7315.36- 16.63* 9256.20 1.88 857.46 1 FRICTION+BEND 7348.91- 16.54* 9205.87 1.97 DC 854.81 1 JUNCTION 7348.91- 16.61* 9203.98 1.82 782.54 1 FRICTION+BEND 7373.43- 16.55* 9167.27 1.84 781.66 1 FRICTION 7387.93- 16.50* 9137.35 1.90 DC 780.43 ------------------------------------------------------------------------------ MAXIMUM NUMBER OF ENERGY BALANCES USED IN EACH PROFILE = 25 ------------------------------------------------------------------------------ NOTE: STEADY FLOW HYDRAULIC HEAD -LOSS COMPUTATIONS BASED ON THE MOST CONSERVATIVE FORMULAE FROM THE CURRENT LACRD,LACFCD, AND OCEMA DESIGN MANUALS. it Y 4r it it �r it it ir:; is is 4r 4r*ie it is it t;isi; 4e ie is it it*i:4c ie fe is it it ie it*ic it is it ie fe*4e it 4r it it 4;*4r*ic ie 4c it 4r'.c it �r is 4c ir*it it Yc ie ie it it it i; 9c �'c S: DOWNSTREAM PIPE FLOW CONTROL DATA: NODE NUMBER = 4997.86 FLOWLINE ELEVATION = 1030.88 PIPE FLOW = 645.50 CPS PIPE DIAMETER = 108.00 INCHES ASSUMED DOWNSTREAM CONTROL HGL = 1042.700 ----------------------------------------------------------- NODE 4997.86 : HGL = < 1042.700>;EGL= < 1044.299>;FLOWLINE= < 1030.880> fr it it dt 4r is*:r*ir sY 4c it*i: it Y: kie it 4r 4r is***ir it is Tr is s4 is it 4r sY is it ie*4e:r �e it it is ic'.;*sY ir'„'4: it it 4r is ic'.r is 4e :e ie*ic is it 4r 4e 4r it***i; i-4r :c FLOW PROCESS FROM NODE 4997.86 TO NODE 5262.77 IS CODE = 1 UPSTREAM NODE 5262.77 ELEVATION = 1032.20 (FLOW IS UNDER PRESSURE) ------------------------------------------------------------------------------ CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 645.50 CPS PIPE DIAMETER = 108.00 INCHES PIPE LENGTH = 264.91 FEET MANNING'S N = .01300 SF=(Q/K)**2 = (( 645.50)/( 12486.090))**2 = .00267 HF=L*SF = ( 264.91)*( .00267) = .708 ------------------------------------------------------------------------------ NODE 5262.77 : HGL = < 1043.408>;EGL= < 1045.007>;FLOWLINE= < 1032.200> 4;dr:ric:c*::4; 4r it it �•ir it**'.csY'.r*ir it k is*ir*sY it it it it is*Yr 4r Yr it*ir it Y 4r is**4r*ir 4r 4l it ir:c it it it ie*�Y Y it Yr sY 9t*Y :c :c Yr fe it it it is*fr :r FLOW PROCESS FROM NODE 5262.77 TO NODE 5347.58 IS CODE = 3 UPSTREAM NODE 5347.58 ELEVATION = 1032.63 (FLOW IS UNDER PRESSURE) --------------------------------------------------------- CALCULATE PIPE -BEND LOSSES(OCEMA): PIPE FLOW = 645.50 CPS PIPE DIAMETER = 108.00 INCHES CENTRAL ANGLE = 32.000 DEGREES MANNING'S N = .01300 PIPE LENGTH = 84.81 FEET BEND COEFFICIENT(KB) = .14907 FLOW VELOCITY = 10.15 FEET/SEC. VELOCITY HEAD = 1.599 FEET HB=KB*(VELOCITY HEAD) = ( .149)*( 1.599) = .238 SF=(Q/K)**2 = (( 645.50)/( 12486.380))**2 = .00267 HF=L*SF = ( 84.81)*( .00267) = .227 TOTAL HEAD LOSSES = HB + HF = ( .238)+( .227) _ .465 NODE 5347.58 : HGL = < 1043.873>;EGL= < 1045.472>;FLOWLINE= < 1032.630> 4c*4t 4r*ir is it is ic*f:4:*�c fr Yc is*i:4c ic.4c4r it it sY it it*?r is it 4t it Y �r i'tic*9r do dr*�ic:c:r is fr it is is is it*ir it Y;Y; 4t it*ir is***:t 4c 4c 4c �c ieir it it 4r FLOW PROCESS FROM NODE 5347.58 TO NODE 5355.57 IS CODE = 1 UPSTREAM NODE 5355.57 ELEVATION = 1032.67 (FLOW IS UNDER PRESSURE) ------------------------------------------------------------------------------ CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 645.50 CPS PIPE DIAMETER = 108.00 INCHES PIPE LENGTH = 7.99 FEET MANNING'S N = .01300 SF=(Q/K)**2 = (( 645.50)/( 12483.760))**2 = .00267 HF=L*SF = ( 7.99)*( .00267) = .021 ------------------------------------------------------------------------------ Page 3 NODE 5355.57 : HGL = < 1043.894>;EGL= < 1045.493>;FLOWLINE= < 1032.670> ie it it it is it it ie$oY is ie is ie it ie it ie ie ie it it is is it it it is it ie it ie is is is it is ie ie ie it it fe it it is it is is it ie it it it irir 4c it it ie s4 it it is is it is is is irir is it it it is it it FLOW PROCESS FROM NODE 2247.67 TO NODE 2252.33 IS CODE = 5 UPSTREAM NODE 2252.33 ELEVATION = 1033.77 (FLOW IS UNDER PRESSURE) ------------------------------------------------------------------------------ CALCULATE JUNCTION LOSSES: PIPE FLOW DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY (CFS) (INCHES) (DEGREES) ELEVATION DEPTH(FT.) (FT/SEC) UPSTREAM 645.50 90.00 .00 1033.77 6.48 14.611 DOWNSTREAM 645.50 108.00 - 1032.67 6.29 10.147 LATERAL #1 .00 .00 .00 .00 .00 .000 LATERAL #2 .00 .00 .00 .00 .00 .000 Q5 .00===Q5 EQUALS BASIN INPUT=== LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: DY=(Q2*V2-Q1*V1*COS(DELTAl)-Q3*V3*COS(DELTA3)- Q4*V4*COS(DELTA4))/((A1+A2)*16.1)+FRICTION LOSSES UPSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00707 DOWNSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00267 AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS .00487 JUNCTION LENGTH = 4.66 FEET FRICTION LOSSES = .023 FEET ENTRANCE LOSSES = .000 FEET JUNCTION LOSSES = (DY+HV1-HV2)+(ENTRANCE LOSSES) JUNCTION LOSSES = ( .078)+( .000) = .078 NODE 2252.33 : HGL = < 1042.256>;EGL= < 1045.571>;FLOWLINE= < 1033.770> is it it is it k it it it is it ic*ir is it it is it is it ir�ir is is it it it it it it it ir*ic it it it it it is it is it ie is it it it it is it is is it it is it is it it ie is it is it it it is it is is is is it it it FLOW PROCESS FROM NODE 2252.33 TO NODE 2736.17 IS CODE = 1 UPSTREAM NODE 2736.17 ELEVATION = 1035.71 (FLOW IS UNDER PRESSURE) ----- ------------------------------------------------------------------ CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 645.50 CFS PIPE DIAMETER = 90.00 INCHES PIPE LENGTH = 483.84 FEET MANNING'S N = .01300 SF=(Q/K)**2 = (( 645.50)/( 7678.799))**2 = .00707 HF=L*SF = ( 483.84)*( .00707) = 3.419 NODE 2736.17 -------------------------------------------------- : HGL = < 1045.676>;EGL= < 1048.990>;FLOWLINE= < 1035.710> it is it it*ir it it it it it it is it it*ir is it is it is it it s4 is is is it ie it it it ie is it is it*it it it is is it it it it it ie it is Y it it ir.*it is it**is ie&ic it it it it is it is it *ie it is FLOW PROCESS FROM NODE 2736.17 TO NODE 2740.83 IS CODE = 5 UPSTREAM NODE ------------------------------------------------------------------------------ 2740.83 ELEVATION = 1035.72 (FLOW IS UNDER PRESSURE) CALCULATE JUNCTION LOSSES: PIPE FLOW DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY (CFS) (INCHES) (DEGREES) ELEVATION DEPTH(FT.) (FT/SEC) UPSTREAM 603.99 90.00 .00 1035.72 6.30 13.672 DOWNSTREAM 645.50 90.00 - 1035.71 6.48 14.611 LATERAL #1 41.51 24.00 45.00 1038.77 1.96 13.213 LATERAL #2 .00 .00 .00 .00 .00 .000 Q5 .00===Q5 EQUALS BASIN INPUT=== LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: DY=(Q2*V2-Ql*Vl*COS(DELTAI)-Q3*V3*COS(DELTA3)- Q4*V4 *COS (DELTA4))/((Al+A2)*16.1)+FRICTION LOSSES UPSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00619 DOWNSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00707 AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS .00663 JUNCTION LENGTH = 4.66 FEET FRICTION LOSSES = .031 FEET ENTRANCE LOSSES = .000 FEET JUNCTION LOSSES = (DY+HV1-HV2)+(ENTRANCE LOSSES) JUNCTION LOSSES = ( .171)+( .000) = .171 ------------------------------------------------------------------------------ NODE 2740.83 : HGL = < 1046.259>;EGL= < 1049.161>;FLOWLINE= < 1035.720> Page 4 ici�iritiriririririeiticitici: iciriticitiriririticiritirititiritsYicirititiciriririririciricitititieieieir*iriciririciririeiricirieieitiririritir it itiriris FLOW PROCESS FROM NODE 2740.83 TO NODE 3121.17 IS CODE = 1 UPSTREAM NODE 3121.17 ELEVATION = 1037.24 (FLOW IS UNDER PRESSURE) ------------------------------------------------------------------------------ CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 603.99 CFS PIPE DIAMETER = 90.00 INCHES PIPE LENGTH = 380.34 FEET MANNING'S N = .01300 SF=(Q/K)**2 = (( 603.99)/( 7678.758))**2 = .00619 HF=L*SF = ( 380.34)*( .00619) = 2.353 NODE 3121.17 : HGL = < 1048.612>;EGL= < 1051.515>;FLOWLINE= < 1037.240> FLOW PROCESS FROM NODE 3121.17 TO NODE 3125.83 IS CODE = 5 UPSTREAM NODE 3125.83 ELEVATION = 1037.26 (FLOW IS UNDER PRESSURE) ------------------------------------------------------------------------------ CALCULATE JUNCTION LOSSES: PIPE FLOW DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY (CFS) (INCHES) (DEGREES) ELEVATION DEPTH(FT.) (FT/SEC) UPSTREAM 603.99 90.00 .00 1037.26 6.30 13.672 DOWNSTREAM 603.99 90.00 - 1037.24 6.30 13.672 LATERAL #1 .00 24.00 45.00 1040.08 .00 .000 LATERAL #2 .00 .00 .00 .00 .00 .000 Q5 .00===Q5 EQUALS BASIN INPUT=== LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: DY=(Q2*V2-Q1*V1*COS(DELTAI)-Q3*V3*COS(DELTA3)- Q4*V4*COS(DELTA4))/((A1+A2)*16.1)+FRICTION LOSSES UPSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00619 DOWNSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00619 AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS .00619 JUNCTION LENGTH = 4.66 FEET FRICTION LOSSES = .029 FEET ENTRANCE LOSSES = .000 FEET JUNCTION LOSSES = (DY+HV1-HV2)+(ENTRANCE LOSSES) JUNCTION LOSSES = ( .029)+( .000) = .029 ------------------------------------------------------------------------------ NODE 3125.83 : HGL = < 1048.641>;EGL= < 1051.543>;FLOWLINE= < 1037.260> it it *iris*ir it ie is*ir it ie is it is*ir*ir is is is it it sY is it is ir*ir*ic is is it it**ir ie it it it it is ie is is it it*ie&ic it ie it sY ih ie it *ir is it is is it it is ie it it it is FLOW PROCESS FROM NODE 3125.83 TO NODE 3565.58 IS CODE = 1 UPSTREAM NODE 3565.58 ELEVATION = 1039.02 (FLOW IS UNDER PRESSURE) ------------------------------------------------------------------------------ CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 603.99 CFS PIPE DIAMETER = 90.00 INCHES PIPE LENGTH = 439.75 FEET MANNING'S N = .01300 SF=(Q/K)**2 = (( 603.99)/( 7678.778))**2 = .00619 HF=L*SF = ( 439.75)*( .00619) = 2.721 NODE 3565.58 HGL = < 1051.362>;EGL= < 1054.264>;FLOWLINE= < 1039.020> is ir*i::lir***�•*it*i:i:R•�'i.•*ir*ir it**ir it f:ic:r it it it ir'z it it ir*ir:r it is*it*ir'.r it it it it it it is �•'.t ie i.•*ir it is it is*:.•�•ir it it it*'..•*ir *.ir FLOW PROCESS FROM NODE 3565.58 TO NODE 3582.33 IS CODE = 5 UPSTREAM NODE 3582.33 ELEVATION = 1039.09 (FLOW IS UNDER PRESSURE) ------------------------------------------------------------------------------ CALCULATE JUNCTION LOSSES: PIPE FLOW DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY (CFS) (INCHES) (DEGREES) ELEVATION DEPTH(FT.) (FT/SEC) UPSTREAM 515.11 90.00 .00 1039.09 5.87 11.660 DOWNSTREAM 603.99 90.00 - 1039.02 6.30 13.672 LATERAL #1 88.88 54.00 30.00 1040.55 2.76 5.588 LATERAL #2 .00 .00 .00 .00 .00 .000 Q5 .00===Q5 EQUALS BASIN INPUT=== LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: Page 5 DY=(Q2*V2-Q1itV1*COS(DELTAI)-Q3*V3*COS(DELTA3)- Q4*V4*COS(DELTA4))/((A1+A2)*16.1)+FRICTION LOSSES UPSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00450 DOWNSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00619 AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS .00534 JUNCTION LENGTH = 16.75 FEET FRICTION LOSSES = .089 FEET ENTRANCE LOSSES = .000 FEET JUNCTION LOSSES = (DY+HV1-HV2)+(ENTRANCE LOSSES) ,JUNCTION LOSSES = ( .578)+( .000) = r578 ------------------------------------------------------------------------------ NODE 3582.33 : HGL = < 1052.732>;EGL= < 1054.843>;FLOWLINE= < 1039.090> FLOW PROCESS FROM NODE 3582.33 TO NODE 3590.58 IS CODE = 1 UPSTREAM NODE 3590.58 ELEVATION = 1039.12 (FLOW IS UNDER PRESSURE) ------------------------------------------------------------------------------ CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 515.11 CFS PIPE DIAMETER = 90.00 INCHES PIPE LENGTH = 8.25 FEET MANNING'S N = .01300 SF=(Q/K)**2 = (( 515.11)/( 7680.423))**2 = .00450 HF=L*SF = ( 8.25)*( .00450) = .037 ------------------------------------------------------- -------------------- NODE 3590.58 : HGL = < 1052.769>;EGL= < 1054.880>;FLOWLINE= < 1039.120> FLOW PROCESS FROM NODE 3590.58 TO NODE 3607.33 IS CODE = 5 UPSTREAM NODE 3607.33 ELEVATION = 1041.68 (FLOW IS UNDER PRESSURE) ------------------------------------------------------------------------------ CALCULATE JUNCTION LOSSES: PIPE FLOW DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY (CFS) (INCHES) (DEGREES) ELEVATION DEPTH(FT.) (FT/SEC) UPSTREAM 234.47 60.00 .00 1041.68 4.32 11.941 DOWNSTREAM 515.11 90.00 - 1039.12 5.87 11.660 LATERAL #1 280.64 72.00 30.00 1039.90 4.58 9.926 LATERAL #2 .00 .00 .00 .00 .00 .000 Q5 .00===Q5 EQUALS BASIN INPUT=== LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: DY=(Q2itV2-Ql*Vl*COS(DELTAI)-Q3*V3*COS(DELTA3)- Q4*V4^•COS(DELTA4))/((Al+A2)*16.1)+FRICTION LOSSES UPSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00810 DOWNSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00450 AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS .00630 JUNCTION LENGTH = 16.75 FEET FRICTION LOSSES = .106 FEET ENTRANCE LOSSES = .000 FEET JUNCTION LOSSES = (DY+HV1-HV2)+(ENTRANCE LOSSES) JUNCTION LOSSES = ( .981)+( .000) = .981 ------------------------------------------------------------------------------ NODE 3607.33 : HGL = < 1053.647>;EGL= < 1055.861>;FLOWLINE= < 1041.680> »»»»»»»»» i.•»»»» it»»» » »»»» it»»»»»»»»»»»»»»»»»»»»»»»»» ic» is �Y»»»»» it»»»» it »»»»»» sY R•»» »* ic'.r FLOW PROCESS FROM NODE 3607.33 TO NODE 3787.69 IS CODE = 1 UPSTREAM NODE 3787.69 ELEVATION = 1051.41 (HYDRAULIC JUMP OCCURS) ------------------------------------------------------------------------------ CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 234.47 CFS PIPE DIAMETER = 60.00 INCHES PIPE LENGTH = 180.36 FEET MANNING'S N = .01300 ------------------------------------------------------------------------------ HYDRAULIC JUMP: DOWNSTREAM RUN ANALYSIS RESULTS ------------------------------------------------------------------------------ NORMAL DEPTH(FT) = 2.16 CRITICAL DEPTH(FT) = 4.32 ------------------------------------------------------------------------------ UPSTREAM CONTROL ASSUMED FLOWDEPTH(FT) = 4.32 ------------------------------------------------------------------------------ ------------------------------------------------------------------------------ GRADUALLY VARIED FLOW PROFILE COMPUTED INFORMATION: Page 6 ------------------------------------------------------------------------------ DISTANCE FROM FLOW DEPTH VELOCITY SPECIFIC PRESSURE+ CONTROL(FT) (FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUNDS) .000 4.318 13.002 6.945 8165.33 .097 4.232 13.225 6.950 8170.35 .400 4.146 13.467 6.964 8185.61 .924 4.059 13.728 6.988 8211.48 1.693 3.973 14.010 7.023 8248.38 2.733 3.887 14.312 7.070 8296.83 4.074 3.801 14.637 7.130 8357.42 5.755 3.714 14.986 7.204 8430.81 7.820 3.628 15.361 7.294 8517.77 10.326 3.542 15.762 7.402 8619.16 13.338 3.455 16.193 7.530 8735.92 16.938 3.369 16.655 7.679 8869.15 21.228 3.283 17.152 7.854 9020.05 26.336 3.196 17.685 8.056 9190.00 32.424 3.110 18.259 8.290 9380.54 39.703 3.024 18.877 8.560 9593.40 48.456 2.937 19.543 8.872 9830.59 59.063 2.851 20.263 9.231 10094.34 72.067 2.765 21.042 9.644 10387.23 88.261 2.679 21.887 10.121 10712.21 108.885 2.592 22.804 10.672 11072.67 136.018 2.506 23.803 11.309 11472.56 173.568 2.420 24.894 12.048 11916.41 180.360 ------------------------------------------------------------------------------ 2.409 25.031 12.144 11972.71 HYDRAULIC JUMP: UPSTREAM RUN ANALYSIS RESULTS ------------------------------------------------------------------------------ DOWNSTREAM CONTROL ASSUMED PRESSURE HEAD(FT) = 11.97 ------------------------------------------------------------------------- PRESSURE FLOW PROFILE COMPUTED ------------------------------------------------------------------------------ INFORMATION: DISTANCE FROM PRESSURE VELOCITY SPECIFIC PRESSURE+ CONTROL(FT) HEAD(FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUNDS) .000 11.967 11.941 14.181 17024.79 151.971 5.000 11.941 7.214 8488.97 ASSUMED DOWNSTREAM PRESSURE HEAD(FT) 5.00 ------------------------------------------------------------------ GRADUALLY VARIED FLOW PROFILE ------------------------------------------------------------------------------ COMPUTED INFORMATION: DISTANCE FROM FLOW DEPTH VELOCITY SPECIFIC PRESSURE+ CONTROL(FT) (FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUNDS) 151.971 5.000 11.938 7.214 8488.97 152.499 4.973 11.946 7.190 8459.28 152.967 4.945 11.961 7.168 8432.69 153.399 4.918 11.980 7.148 8408.14 153.800 4.891 12.003 7.129 8385.27 154.176 4.864 12.029 7.112 8363.89 154.529 4.836 12.058 7.095 8343.85 154.860 4.809 12.089 7.080 8325.06 155.170 4.782 12.123 7.065 8307.46 155.462 4.755 12.159 7.052 8290.99 155.734 4.727 12.197 7.039 8275.62 155.989 4.700 12.237 7.027 8261.31 156.226 4.673 12.280 7.016 8248.04 156.445 4.646 12.324 7.005 8235.79 156.648 4.618 12.370 6.996 8224.54 156.833 4.591 12.419 6.987 8214.28 157.001 4.564 12.469 6.979 8205.00 157.153 4.536 12.521 6.972 8196.70 157.287 4.509 12.575 6.966 8189.37 157.404 4.482 12.630 6.961 8183.02 Page 7 157.504 4.455 12.688 6.956 8177.63 157.586 4.427 12.747 6.952 8173.21 157.650 4.400 12.808 6.949 8169.77 157.696 4.373 12.871 6.947 8167.31 157.725 4.346 12.936 6.946 8165.82 157.734 4.318 13.002 6.945 8165.33 180.360 4.318 13.002 6.945 8165.33 ------------------------END OF HYDRAULIC JUMP ANALYSIS------------------------ PRESSURE+MOMENTUM BALANCE OCCURS AT 125.05 FEET UPSTREAM OF NODE 3607.33 DOWNSTREAM DEPTH = 6.234 FEET, UPSTREAM CONJUGATE DEPTH = 2.882 FEET ------------------------------------------------------------------------------ NODE 3787.69 : HGL = < 1055.728>;EGL= < 1058.355>;FLOWLINE= < 1051.410> it it sk it it*ic is it it is it it is is is ie it*sk it it it it*ir it it it it it is it it is it is*it sk it sk. ie is it it sk ie sk it sk it it it sk fr it it*it ie it sk *it is it it it it *ir sk it it sk it* FLOW PROCESS FROM NODE 3787.69 TO NODE 3794.35 IS CODE = 5 UPSTREAM NODE 3794.35 ELEVATION = 1051.48 (FLOW IS AT CRITICAL DEPTH) -------------------------------------------------------- CALCULATE JUNCTION LOSSES: PIPE FLOW DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY (CFS) (INCHES) (DEGREES) ELEVATION DEPTH(FT.) (FT/SEC) UPSTREAM 221.86 60.00 .00 1051.48 4.22 11.299 DOWNSTREAM 234.47 60.00 - 1051.41 4.32 13.006 LATERAL #1 7.96 24.00 45.00 1052.86 1.00 2.534 LATERAL #2 4.65 21.00 85.00 1053.17 .79 1.933 Q5 .00===Q5 EQUALS BASIN INPUT=== LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: DY=(Q2*V2-Ql*V1*COS(DELTAl)-Q3*V3*COS(DELTA3)- Q4*V4*COS(DELTA4))/((A1+A2)*16.1)+FRICTION LOSSES UPSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00726 DOWNSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00746 AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS .00736 JUNCTION LENGTH = 6.66 FEET FRICTION LOSSES = .049 FEET ENTRANCE LOSSES = .000 FEET JUNCTION LOSSES = (DY+HV1-HV2)+(ENTRANCE LOSSES) JUNCTION LOSSES ( .275)+( .000) = .275 -------------------------------------------------------------- NODE 3794.35 : HGL = < 1056.648>;EGL= < 1058.630>;FLOWLINE= < 1051.480> is it it is ir*�-ie*i:skit*ir ie is it ie**sk sk it k****sY*ir**ie sk *.sk is sk it**sY *iris**ir*ie**skit*sk is**ir ie sk is it it ie is sk sY it is it it sk sk it sk FLOW PROCESS FROM NODE 3794.35 TO NODE 4247.67 IS CODE = 1 UPSTREAM NODE 4247.67 ELEVATION = 1055.28 (HYDRAULIC JUMP OCCURS) ------------------------------------------------------------------------------ CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 221.86 CFS PIPE DIAMETER = 60.00 INCHES PIPE LENGTH = 453.32 FEET MANNING'S N = .01300 ------------------------------------------------------------------------------ HYDRAULIC JUMP: DOWNSTREAM RUN ANALYSIS RESULTS ------------------------------------------------------------------------------ NORMAL DEPTH(FT) = 3.82 CRITICAL DEPTH(FT) = 4.22 ------------------------ UPSTREAM CONTROL ASSUMED FLOWDEPTH(FT) = 3.07 GRADUALLY VARIED FLOW PROFILE COMPUTED INFORMATION: ------------------------------------------------------------------------------ DISTANCE FROM FLOW DEPTH VELOCITY SPECIFIC PRESSURE+ CONTROL(FT) (FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUNDS) .000 3.070 17.543 7.852 8594.43 12.222 3.100 17.344 7.774 8532.46 24.642 3.130 17.150 7.700 8472.94 37.280 3.160 16.960 7.629 8415.79 50.156 3.190 16.776 7.562 8360.96 63.294 3.219 16.596 7.499 8308.37 76.721 3.249 16.421 7.439 8257.98 90.469 3.279 16.250 7.382 8209.71 Page 8 104.575 3.309 16.083 7.328 8163.52 119.083 3.339 15.920 7.277 8119.35 134.045 3.369 15.761 7.228 8077.15 149.523 3.399 15.606 7.183 8036.87 165.595 3.428 15.455 7.140 7998.47 182.354 3.458 15.307 7.099 7961.90 199.921 3.488 15.163 7.061 7927.12 218.448 3.518 15.023 7.025 7894.08 238.137 3.548 14.886 6.991 7862.75 259.260 3.578 14.752 6.959 7833.09 282.200 3.608 14.621 6.929 7805.05 307.515 3.638 14.494 6.902 7778.62 336.070 3.667 14.369 6.876 7753.74 369.314 3.697 14.248 6.851 7730.39 409.964 3.727 14.129 6.829 7708.54 453.320 ------------------------------------------------------------------------------ 3.751 14.037 6.812 7692.10 HYDRAULIC JUMP: UPSTREAM RUN ANALYSIS RESULTS ------------------------------------------------------------------------------ DOWNSTREAM CONTROL ASSUMED PRESSURE HEAD(FT) = 5.17 -----------------------------------------------------------------=- PRESSURE FLOW PROFILE COMPUTED ------------------------------------------------------------------------------ INFORMATION: DISTANCE FROM PRESSURE VELOCITY SPECIFIC PRESSURE+ CONTROL(FT) HEAD(FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUNDS) .000 5.168 11.299 7.150 8126.47 148.883 5.000 11.299 6.982 7921.05 ASSUMED DOWNSTREAM PRESSURE HEAD(FT) 5.00 --------------- GRADUALLY VARIED ------------------------------------------------------------------------------ --------------___________________ FLOW PROFILE COMPUTED INFORMATION: DISTANCE FROM FLOW DEPTH VELOCITY SPECIFIC PRESSURE+ CONTROL(FT) (FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUNDS) 148.883 5.000 11.296 6.982 7921.05 168.808 4.969 11.305 6.955 7887.02 183.753 4.938 11.322 6.930 7856.39 196.588 4.907 11.344 6.906 7828.00 208.017 4.876 11.371 6.885 7801.46 218.392 4.845 11.401 6.864 7776.56 227.925 4.814 11.434 6.845 7753.16 236.752 4.782 11.470 6.827 7731.16 244.971 4.751 11.509 6.810 7710.50 252.649 4.720 11.551 6.793 7691.11 259.838 4.689 11.595 6.778 7672.97 266.573 4.658 11.642 6.764 7656.04 272.881 4.627 11.691 6.751 7640.30 278.783 4.596 11.742 6.738 7625.73 284.289 4.565 11.796 6.727 7612.33 289.407 4.534 11.852 6.717 7600.08 294.138 4.503 11.910 6.707 7588.97 298.477 4.472 11.971 6.698 7579.02 302.417 4.441 12.034 6.691 7570.21 305.942 4.410 12.099 6.684 7562.55 309.035 4.379 12.166 6.678 7556.05 311.668 4.347 12.236 6.674 7550.71 313.807 4.316 12.308 6.670 7546.53 315.411 4.285 12.382 6.667 7543.54 316.424 4.254 12.458 6.666 7541.73 316.780 4.223 12.536 6.665 7541.13 453.320 4.223 12.536 6.665 7541.13 ------------------------END OF HYDRAULIC JUMP ANALYSIS------------------------ PRESSURE+MOMENTUM BALANCE OCCURS AT 194.20 FEET UPSTREAM OF NODE 3794.35 DOWNSTREAM ----------------------------------------------------------------------------- DEPTH = 4.913 FEET, UPSTREAM CONJUGATE DEPTH = 3.578 FEET Page 9 NODE 4247.67 : HGL = < 1058.350>;EGL= < 1063.132>;FLOWLINE= < 1055.280> itieiticirieiricieieicirieiriciricieitit$tit�Yirititititicitit�Yiritititirititirititititicieirititicicicitieiticititicieitieieicitiriefticiririeitieiricirit FLOW PROCESS FROM NODE 4247.67 TO NODE 4252.33 IS CODE = 5 UPSTREAM NODE 4252.33 ELEVATION = 1055.83 (FLOW IS SUPERCRITICAL) ------------------------------------------------------------------------------ CALCULATE JUNCTION LOSSES: PIPE FLOW DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY (CFS) (INCHES) (DEGREES) ELEVATION DEPTH(FT.) (FT/SEC) UPSTREAM 221.86 54.00 .00 1055.83 4.16 14.442 DOWNSTREAM 221.86 60.00 - 1055.28 4.22 17.548 LATERAL #1 .00 .00 .00 .00 .00 .000 LATERAL #2 .00 .00 .00 .00 .00 .000 Q5 .00===Q5 EQUALS BASIN INPUT=== LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: DY=(Q2*V2-QI*V1*COS(DELTAI)-Q3*V3*COS(DELTA3)- Q4*V4 *COS (DELTA4))/((Al+A2)*16.1)+FRICTION LOSSES UPSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .01103 DOWNSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .01499 AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS .01301 JUNCTION LENGTH = 4.66 FEET FRICTION LOSSES = .061 FEET ENTRANCE LOSSES = .000 FEET JUNCTION LOSSES = (DY+HV1-HV2)+(ENTRANCE LOSSES) JUNCTION LOSSES = ( .099)+( .000) = .099 NODE 4252.33 : HGL = < 1059.992>;EGL= < 1063.231>;FLOWLINE= < 1055.830> itic ie it * itit ie is * it * it ie it is it it is it it is � is it it it is it?t it is ie it it is it it it it it it it it ie it it it * * it it it it ie it it it it ie it is is � is it it it is & it it ie is is it it it FLOW PROCESS FROM NODE 4252.33 TO NODE 4459.70 IS CODE = 1 UPSTREAM NODE 4459.70 ELEVATION = ------------------------------------------------------ 1057.80 (FLOW UNSEALS IN REACH) CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 221.86 CFS PIPE DIAMETER = 54.00 INCHES PIPE LENGTH = 207.37 FEET MANNING'S N = .01300 ===> NORMAL PIPEFLOW ------------------------------------------------------------------------------ IS PRESSURE FLOW NORMAL DEPTH(FT) = 4.50 CRITICAL DEPTH(FT) = 4.16 DOWNSTREAM CONTROL ASSUMED FLOWDEPTH(FT) = 4.16 GRADUALLY VARIED FLOW ------------------------------------------------------------------------------ PROFILE COMPUTED INFORMATION: DISTANCE FROM FLOW DEPTH VELOCITY SPECIFIC PRESSURE+ CONTROL(FT) (FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUNDS) .000 4.162 14.438 7.401 8111.70 .110 4.176 14.408 7.401 8111.86 .441 4.189 14.379 7.402 8112.35 .997 4.203 14.351 7.403 8113.15 1.779 4.216 14.323 7.404 8114.29 2.788 4.230 14.296 7.405 8115.75 4.024 4.243 14.270 7.407 8117.55 5.487 4.257 14.244 7.409 8119.69 7.173 4.270 14.219 7.412 8122.17 9.079 4.284 14.195 7.415 8125.00 11.201 4.297 14.172 7.418 8128.20 13.532 4.311 14.150 7.422 8131.75 16.066 4.324 14.128 7.426 8135.68 18.795 4.338 14.107 7.430 8140.00 21.709 4.351 14.087 7.435 8144.70 24.800 4.365 14.068 7.440 8149.82 28.055 4.378 14.050 7.446 8155.36 31.464 4.392 14.033 7.452 8161.35 35.014 4.405 14.017 7.458 8167.80 38.693 4.419 14.003 7.465 8174.75 Page 10 42.487 4.432 13.989 7.473 8182.23 46.383 4.446 13.976 7.481 8190.28 50.367 4.459 13.966 7.490 8198.98 54.426 4.473 13.956 7.499 8208.41 58.544 4.486 13.949 7.510 8218.75 62.708 4.500 13.945 7.522 8230.42 FLOW IS UNDER PRESSURE 207.370 5.088 13.950 8.110 8814.03 ------------------------------------------------------------------------------ NODE 4459.70 : HGL = < 1062.853>;EGL= < 1065.874>;FLOWLINE= < 1057.800> irkk �•k it ie it is i:kkkir kir kie kirk kir irk kit it irkkkkkirkkkkir it itkie ki�ir irkkkkkicic irk ick it kirirkkkkkkkick irk irkkk FLOW PROCESS FROM NODE 4459.70 TO NODE 4459.70 IS CODE = 5 UPSTREAM NODE ------------------------------------------------------------------------------ 4459.70 ELEVATION = 1057.80 (FLOW IS UNDER PRESSURE) CALCULATE JUNCTION LOSSES: PIPE FLOW DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY (CFS) (INCHES) (DEGREES) ELEVATION DEPTH(FT.) (FT/SEC) UPSTREAM 182.75 54.00 .00 1057.80 3.91 11.490 DOWNSTREAM 221.86 54.00 - 1057.80 4.16 13.950 LATERAL #1 39.11 24.00 45.00 1057.80 1.95 12.449 LATERAL #2 .00 .00 .00 .00 .00 .000 Q5 .00===Q5 EQUALS BASIN INPUT=== LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: DY=(Q2*V2-Q1*Vl*COS(DELTAl)-Q3*V3*COS(DELTA3)- Q4*V4irCOS(DELTA4))/((A1+A2)*16.1)+FRICTION LOSSES UPSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00864 DOWNSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .01273 AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS .01068 JUNCTION LENGTH = 1.00 FEET FRICTION LOSSES = .011 FEET ENTRANCE LOSSES = .000 FEET JUNCTION LOSSES = (DY+HVI-HV2)+(ENTRANCE LOSSES) JUNCTION LOSSES = ( .310)+( .000) = .310 NODE 4459.70 HGL = < 1064. 134>; EGL= < 1066. 184>; FLOWLINE= < 1057.800> k kkkkkkkkk'.ckkkkkkkkki.•fekkkk*kirkkkkkickkkk*kkkkkkkkirk kkkkkkkir'..•k kkkk�.•kkkkkkkkk::k irk FLOW PROCESS FROM NODE 4459.70 TO NODE 4719.80 IS CODE = 1 UPSTREAM NODE 4719.80 ELEVATION = 1060.27 (FLOW IS UNDER PRESSURE) ------------------------------------------------------------------------------ CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 182.75 CFS PIPE DIAMETER = 54.00 INCHES PIPE LENGTH = 260.10 FEET MANNING'S N .01300 SF=(Q/K)**2 = (( 182.75)/( 1966.482))**2 = .00864 HF=L*SF = ( 260.10)*( .00864) = 2.246 NODE 4719.80 : HGL = < 1066.380>;EGL= < 1068.430>;FLOWLINE= < 1060.270> ick it irkkk �•ick kki: kkirirkirkkkkkkkkkkkkkkkkkkkkirk kirkkkkki.•kkkkirkkkkkkk k:�•k k�irkkkkkk kkki:k FLOW PROCESS FROM NODE 4719.80 TO NODE 4724.46 IS CODE = 5 UPSTREAM NODE ------------------------------------------------------------------------------ 4724.46 ELEVATION = 1060.37 (FLOW IS UNDER PRESSURE) CALCULATE JUNCTION LOSSES: PIPE FLOW DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY (CFS) (INCHES) (DEGREES) ELEVATION DEPTH(FT.) (FT/SEC) UPSTREAM 182.75 54.00 .00 1060.37 3.91 11.490 DOWNSTREAM 182.75 54.00 - 1060.27 3.91 11.491 LATERAL #1 .00 24.00 45.00 1061.70 .00 .000 LATERAL #2 .00 .00 .00 .00 .00 .000 Q5 .00===Q5 EQUALS BASIN INPUT=== LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: DY=(Q2*V2-Q1*V1*COS(DELTAI)-Q3*V3=COS(DELTA3)- Q4*V4*COS(DELTA4))/((A1+A2)*16.1)+FRICTION LOSSES Page 11 UPSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00864 DOWNSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00864 AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS .00864 JUNCTION LENGTH = 4.66 FEET FRICTION LOSSES = .040 FEET ENTRANCE LOSSES .000 FEET JUNCTION LOSSES = (DY+HVl-HV2)+(ENTRANCE LOSSES) JUNCTION LOSSES = ( .040)+( .000) = .040 NODE 4724.46 : HGL = < 1066.420>;EGL= < 1068.471>;FLOWLINE= < 1060.370> is irie ie ie ie �Y is is is is*ir it it is is ie it is is it is it ie ie it ie is it is is it is ie ie it is ie is ie it ie it it it it is it is is is is it is is it ie is is is is is it is it ie s4 it it ie ie ie is is is ic* FLOW PROCESS FROM NODE 4724.46 TO NODE 4974.99 IS CODE = 1 UPSTREAM NODE 4974.99 ELEVATION = 1062.75 (FLOW IS UNDER PRESSURE) ------------------------------------------------------------- CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 182.75 CFS PIPE DIAMETER = 54.00 INCHES PIPE LENGTH = 250.53 FEET MANNING'S N = .01300 SF=(Q/K)**2 = (( 182.75)/( 1966.478))**2 = .00864 HF=L*SF = ( 250.53)*( .00864) = 2.164 NODE 4974.99 : HGL = < 1068. 584>; EGL= < 1070. 634>; FLOWLINE= < 1062.750> is is �•i: is it it is is is is is it it is*it is it it is is is is is i:ir it is it it ie it it sY is it is it it is ie is is it is is it it is ie it is ie is it is is is is**k is it is it is it it it is it*it it it* FLOW PROCESS FROM NODE 4974.99 TO NODE 4974.99 IS CODE = 5 UPSTREAM NODE 4974.99 ELEVATION = 1062.75 (FLOW IS UNDER PRESSURE) ------------------------------------------------------------------------------ CALCULATE JUNCTION LOSSES: PIPE FLOW DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY (CFS) (INCHES) (DEGREES) ELEVATION DEPTH(FT.) (FT/SEC) UPSTREAM 140.71 54.00 .00 1062.75 3.49 8.847 DOWNSTREAM 182.75 54.00 - 1062.75 3.91 11.490 M LATERAL #1 42.04 24.00 45.00 1062.75 1.96 13.382 LATERAL #2 .00 .00 .00 .00 .00 .000 Q5 .00===Q5 EQUALS BASIN INPUT=== LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: DY=(Q2*V2-Ql*V1*COS(DELTAI)-Q3*V3*COS(DELTA3) Q4*V4*COS(DELTA4))/((AI+A2)*16.1)+FRICTION LOSSES UPSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00512 DOWNSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00864 AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS .00688 JUNCTION LENGTH = 1.00 FEET FRICTION LOSSES = .007 FEET ENTRANCE LOSSES = .000 FEET JUNCTION LOSSES = (DY+HV1-HV2)+(ENTRANCE LOSSES) JUNCTION LOSSES = ( .065)+( .000) = .065 NODE 4974.99 : HGL = < 1069.484>;EGL= < 1070.699>;FLOWLINE= < 1062.750> is it is is is*ic it is it it it is i:i:*ir ir. is it**ir is it is it is it: irit is it it is is it it is it is it it it it it it is is is is is �c it ie ie fr is**.ici: is it it it is is it is is it is is it is is is FLOW PROCESS FROM NODE 4974.99 TO NODE 5219.37 IS CODE = 1 UPSTREAM NODE 5219.37 ELEVATION = 1065.02 (FLOW IS UNDER PRESSURE) ------------------------------------------------------------------------------ CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 140.71 CFS PIPE DIAMETER = 54.00 INCHES PIPE LENGTH = 244.38 FEET MANNING'S N = .01300 SF=(Q/K)**2 = (( 140.71)/( 1966.486))**2 = .00512 HF=L*SF = ( 244.38)*( .00512) = 1.251 NODE 5219.37 : HGL = < 1070.735>;EGL= < 1071.950>;FLOWLINE= < 1065.020> it is it it is �•ic ie i:i:iritir*iri:i.•i: sY is is is it it it is is it it is*�•iri: ie is is it is is is it i:ics: it it i:ic is is it it is is it is it*i:icit it ie is it is it is it is it is is *ir it is FLOW PROCESS FROM NODE 5219.37 TO NODE 5227.28 IS CODE = 5 UPSTREAM NODE 5227.28 ELEVATION = 1065.56 (FLOW IS UNDER PRESSURE) --------------------------------------------- CALCULATE JUNCTION LOSSES: Page 12 PIPE FLOW DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY (CFS) (INCHES) (DEGREES) ELEVATION DEPTH(FT.) (FT/SEC) UPSTREAM 140.71 48.00 .00 1065.56 3.52 11.197 DOWNSTREAM 140.71 54.00 - 1065.02 3.49 8.847 LATERAL #1 .00 36.00 45.00 1066.20 .00 .000 LATERAL #2 .00 .00 .00 .00 .00 .000 Q5 .00===Q5 EQUALS BASIN INPUT=== LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: DY=(Q2*V2-Ql*V1*COS(DELTAI)-Q3*V3*COS(DELTA3)- Q4*V4*COS(DELTA4))/((A1+A2)*16.1)+FRICTION LOSSES UPSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00959 DOWNSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00512 AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS .00736 JUNCTION LENGTH = 7.91 FEET FRICTION LOSSES = .058 FEET ENTRANCE LOSSES = .000 FEET JUNCTION LOSSES = (DY+HV1-HV2)+(ENTRANCE LOSSES) JUNCTION LOSSES = ( .068)+( .000) = .068 NODE 5227.28 : HGL = < 1070.072>;EGL= < 1072.019>;FLOWLINE= < 1065.560> it it it*�-4e it*ir it it it it it it it*ie it it ie ie*4r it is �Y ici:i:*ir is it it Yt it it is ie it 4t iri: it it it it it it it it is it is it is it it**ir it is it*ir it ie it ie ie is it it ie it is FLOW PROCESS FROM NODE 5227.28 TO NODE 5300.00 IS CODE = 1 UPSTREAM NODE 5300.00 ELEVATION = 1066.31 (FLOW IS UNDER PRESSURE) ------------------------------------------------------------------------------ CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 140.71 CFS PIPE DIAMETER = 48.00 INCHES PIPE LENGTH = 72.72 FEET MANNING'S N = .01300 SF=(Q/K)**2 = (( 140.71)/( 1436.358))**2 = .00960 HF=L*SF = ( 72.72)*( .00960) = .698 NODE 5300.00 : HGL = < 1070.770>;EGL= < 1072.716>;FLOWLINE= < 1066.310> it it is*�•**it it**ir*::ir*i:ic**ir is is it is it is it it is it*'.r*ir it ie it it*ir ie*k***ir is sY*ic it*ic*ie is ie*ir*ic ie it it is*ic is it it****ic is FLOW PROCESS FROM NODE 5300.00 TO NODE 5300.00 IS CODE = 5 UPSTREAM NODE 5300.00 ELEVATION = 1066.31 (FLOW IS UNDER PRESSURE) ------------------------------------------------------------------------------ CALCULATE JUNCTION LOSSES: PIPE FLOW DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY (CFS) (INCHES) (DEGREES) ELEVATION DEPTH(FT.) (FT/SEC) UPSTREAM 140.71 48.00 .00 1066.31 3.52 11.197 DOWNSTREAM 140.71 48.00 - 1066.31 3.52 11.197 LATERAL #1 .00 24.00 45.00 1067.61 .00 .000 LATERAL #2 .00 .00 .00 .00 .00 .000 Q5 .00===Q5 EQUALS BASIN INPUT=== LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: DY=(Q2*V2-Q1*V1*COS(DELTAI)-Q3*V3*COS(DELTA3)- Q4*V4*COS(DELTA4))/((A1+A2)*16.1)+FRICTION LOSSES UPSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00959 DOWNSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00959 AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS .00959 JUNCTION LENGTH = 1.00 FEET FRICTION LOSSES = .010 FEET ENTRANCE LOSSES = .000 FEET JUNCTION LOSSES = (DY+HVl-HV2)+(ENTRANCE LOSSES) JUNCTION LOSSES = ( .010)+( .000) = .010 NODE 5300.00 : HGL = < 1070.779>;EGL= < 1072.726>;FLOWLINE= < 1066.310> is is is is**ir it is is it it it i; *i: it it*ie is is it is it*sY it is it is it iY'x is it it it it it is it ie it is it it ie it it is is is is ic.*ic is is is it ie is*ic it is is it ie ie it it it is it is is FLOW PROCESS FROM NODE 5300.00 TO NODE 5574.44 IS CODE = 1 UPSTREAM NODE 5574.44 ELEVATION = 1069.05 (HYDRAULIC JUMP OCCURS) ------------------------------------------------------------------------------ CALCULATE FRICTION LOSSES(LACFCD) PIPE FLOW = 140.71 CFS PIPE DIAMETER = 48.00 INCHES Page 13 PIPE LENGTH = 274.44 FEET MANNING'S N = .01300 ­7 --------------------------------------------------------------------------- HYDRAULIC JUMP: DOWNSTREAM RUN ANALYSIS RESULTS ------------------------------------------------------------------------------ NORMAL DEPTH(FT) = 3.21 CRITICAL DEPTH(FT) = 3.52 UPSTREAM CONTROL ------------------------------------------------------------------------------ ASSUMED FLOWDEPTH(FT) = 2.53 ------------------------------------------------------------------------------ GRADUALLY VARIED FLOW PROFILE COMPUTED INFORMATION: ------------------------------------------------------------------------------ DISTANCE FROM FLOW DEPTH VELOCITY SPECIFIC PRESSURE+ CONTROL(FT) (FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUNDS) .000 2.527 16.816 6.920 5160.53 10.207 2.554 16.607 6.839 5117.90 20.579 2.581 16.404 6.762 5077.06 31.130 2.609 16.207 6.690 5037.97 41.878 2.636 16.015 6.621 5000.58 52.841 2.663 15.829 6.556 4964.82 64.043 2.691 15.648 6.495 4930.67 75.509 2.718 15.472 6.437 4898.05 87.269 2.745 15.301 6.383 4866.94 99.360 2.773 15.134 6.331 4837.30 111.823 2.800 14.972 6.283 4809.07 124.709 2.827 14.815 6.237 4782.23 138.080 2.854 14.662 6.195 4756.73 152.013 2.882 14.513 6.154 4732.55 166.603 2.909 14.368 6.117 4709.64 181.973 2.936 14.227 6.081 4687.98 198.287 2.964 14.090 6.048 4667.54 215.761 2.991 13.957 6.018 4648.28 234.702 3.018 13.827 5.989 4630.18 255.556 3.046 13.701 5.962 4613.22 274.440 3.068 13.602 5.942 4600.37 ------------------------------------------------------------------------------ HYDRAULIC JUMP: UPSTREAM RUN ANALYSIS RESULTS ------------------------------------------------------------------------------ ------------------------------------------------------------------------------ DOWNSTREAM CONTROL ASSUMED PRESSURE ------------------------------------------------------------------------------ HEAD(FT) = 4.47 ------------------------------------------------------------------------------ PRESSURE FLOW PROFILE COMPUTED INFORMATION: ------------------------------------------------------------------------------ DISTANCE FROM PRESSURE VELOCITY SPECIFIC PRESSURE+ CONTROL(FT) HEAD(FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUNDS) .000 4.469 11.197 6.416 4989.37 274.440 4.362 11.197 6.309 4905.82 ------------------------END OF HYDRAULIC JUMP ANALYSIS------------------------ PRESSURE+MOMENTUM BALANCE OCCURS AT 208.70 FEET UPSTREAM OF NODE 5300.00 DOWNSTREAM DEPTH = 4.388 FEET, UPSTREAM CONJUGATE DEPTH = 2.695 FEET ------------------------------------------------------------------------------ NODE 5574.44 : HGL = < 1071.577>;EGL= < 1075.970>;FLOWLINE= < 1069.050> ,......, is i; is it ;� is is i; it it ie i; is it is it ie is it is it is i; icic is it it is is � it is is i; is sY it i; is is it is is it is it it it is ie it it ie is it is it it is it it it is is is ii it it � it it i; it FLOW PROCESS FROM NODE 5574.44 TO NODE 5602.48 IS CODE = 3 UPSTREAM NODE 5602.48 ELEVATION = 1069.34 (FLOW IS SUPERCRITICAL) ------------------------------------------------------------------------------ CALCULATE PIPE -BEND LOSSES(OCEMA): PIPE FLOW = 140.71 CFS PIPE DIAMETER = 48.00 INCHES CENTRAL ANGLE _ .000 DEGREES MANNING'S N = .01300 PIPE LENGTH = 28.04 FEET ------------------------------------------------------------------------------ NORMAL DEPTH(FT) = 3.15 CRITICAL DEPTH(FT) = 3.52 UPSTREAM CONTROL ASSUMED FLOWDEPTH(FT) = 2.45 ------------------------------------------------------------------------------ ------------------------------------------------------------------------------ GRADUALLY VARIED FLOW PROFILE COMPUTED INFORMATION: ------------------------------------------------------------------------------ Page 14 DISTANCE FROM FLOW DEPTH VELOCITY SPECIFIC PRESSURE+ CONTROL(FT) (FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUNDS) .000 2.453 17.413 7.164 5285.50 10.480 2.481 17.181 7.067 5236.42 21.134 2.509 16.956 6.976 5189.42 28.040 2.527 16.816 6.920 5160.53 ------------------------------------------------------------------------------ NODE 5602.48 ; HGL = < 1071.793>;EGL= < 1076.504>;FLOWLINE= < 1069.340> FLOW PROCESS FROM NODE 5602.48 TO NODE 5607.14 IS CODE = 5 UPSTREAM NODE ------------------------------------------------------------------------------ 5607.14 ELEVATION = 1069.88 (FLOW IS SUPERCRITICAL) CALCULATE JUNCTION LOSSES: PIPE FLOW DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY (CFS) (INCHES) (DEGREES) ELEVATION DEPTH(FT.) (FT/SEC) UPSTREAM 140.71 42.00 .00 1069.88 3.36 14.832 DOWNSTREAM 140.71 48.00 - 1069.34 3.52 17.419 LATERAL#1 .00 .00 .00 .00 .00 .000 LATERAL #2 .00 .00 .00 .00 .00 .000 Q5 .00===Q5 EQUALS BASIN INPUT=== LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: DY=(Q2*V2-Q1*V1*COS(DELTAI)-Q3*V3*COS(DELTA3)- Q4*V4*COS(DELTA4))/((A1+A2)*16.1)+FRICTION LOSSES UPSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .01703 DOWNSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .01990 AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS .01847 JUNCTION LENGTH = 4.66 FEET FRICTION LOSSES = .086 FEET ENTRANCE LOSSES = .000 FEET JUNCTION LOSSES = (DY+HV1-HV2)+(ENTRANCE LOSSES) JUNCTION LOSSES = ( .148)+( .000) = .148 NODE 5607.14 : HGL = < 1073.236>;EGL= < 1076.652>;FLOWLINE= < 1069.880> it it it is it is it ie it is R•it k-k is ie it it it is*it*ic it it is it it it it it is it it it is it it is it is is is is is it it is it is is it it it is is is it it is it it is it it it it it is it it do it it is is is FLOW PROCESS FROM NODE 5607.14 TO NODE 5748.25 IS CODE = 3 UPSTREAM NODE 5748.25 ELEVATION = 1071.30 (FLOW UNSEALS IN REACH) ------------------------------------------------------------------------------ CALCULATE PIPE -BEND LOSSES(OCEMA): PIPE FLOW = 140.71 CFS PIPE DIAMETER = 42.00 INCHES CENTRAL ANGLE = 2.000 DEGREES MANNING'S N = .01300 PIPE LENGTH = 141.11 FEET BEND COEFFICIENT(KB) = .03645 ADJUSTED CENTRAL ANGLE = ( 2.000)*( 134.95/ 141.11) = 1.913 FLOW VELOCITY = 14.63 FEET/SEC. VELOCITY HEAD = 3.321 FEET HB=KB*(VELOCITY HEAD) _ ( .036)*( 3.321) _ .121 SF= .01949 HF=L*SF = ( 141.11)*( .01949) = 2.751 TOTAL HEAD LOSSES = HB + HF = ( .121)+( 2.751) = 2.872 ===> NORMAL PIPEFLOW IS PRESSURE FLOW - - ---------------------------------------------------------------------- NORMAL DEPTH(FT) = 3.50 CRITICAL DEPTH(FT) 3.36 ------------------------------------------------------------------------------ ------------------------------------------------------------------------------ DOWNSTREAM CONTROL ASSUMED FLOWDEPTH(FT) = 3.36 ------------------------------------------------------------------------------ ------------------------------------------------------------------------------ GRADUALLY VARIED FLOW PROFILE COMPUTED INFORMATION: ------------------------------------------------------------------------------ DISTANCE FROM FLOW DEPTH VELOCITY SPECIFIC PRESSURE+ CONTROL(FT) (FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUNDS) 000 3.356 14.827 6.772 5009.23 .009 3.362 14.815 6.772 5009.26 .036 3.368 14.803 6.773 5009.38 .081 3.374 14.791 6.773 5009.56 .144 3.379 14.779 6.773 5009.83 .226 3.385 14.768 6.774 5010.17 Page 15 .326 3.391 14.757 6.775 5010.60 .446 3.397 14.747 6.775 5011.10 .583 3.402 14.736 6.776 5011.69 .740 3.408 14.726 6.778 5012.37 .917 3.414 14.716 6.779 5013.14 1.112 3.420 14.707 6.780 5013.99 1.328 3.425 14.698 6.782 5014.94 1.563 3.431 14.689 6.784 5015.98 1.819 3.437 14.681 6.786 5017.13 2.095 3.443 14.673 6.788 5018.38 2.392 3.448 14.665 6.790 5019.74 2.711 3.454 14.658 6.792 5021.21 3.052 3.460 14.651 6.795 5022.81 3.416 3.466 14.645 6.798 5024.53 3.803 3.471 14.639 6.801 5026.40 4.216 3.477 14.634 6.804 5028.41 4.655 3.483 14.629 6.808 5030.60 5.124 3.489 14.625 6.812 5032.98 5.627 3.494 14.622 6.816 5035.61 6.180 3.500 14.621 6.821 5038.59 FLOW IS UNDER PRESSURE 141.110 4.902 14.625 8.224 5880.55 ------------------------------------------------------------------------------ NODE 5748.25 : HGL = < 1076.203>;EGL= < 1079.524>;FLOWLINE= < 1071.300> it it it -kit*ir it it is*ir sY it is it is it it it ie it ie it *ic it it it it it ie itie*ir ie it it it is is it it it it is it is is *ir is it it***ir ie it it »•i: it is fir is it it*sY *ic it it 8r FLOW PROCESS FROM NODE 5748.25 TO NODE 5895.25 IS CODE = 1 UPSTREAM NODE 5895.25 ELEVATION = 1072.77 (FLOW IS UNDER PRESSURE) ------------------------------------------------------------------------------ CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 140.71 CFS PIPE DIAMETER = 42.00 INCHES PIPE LENGTH = 147.00 FEET MANNING'S N = .01300 SF=(Q/K)**2 = (( 140.71)/( 1006.112))**2 = .01956 HF=L*SF = ( 147.00)*( .01956) = 2.875 ------------------------------------------------------------------------------ NODE 5895.25 : HGL = < 1079.078>;EGL= < 1082.399>;FLOWLINE= < 1072.770> is it it ie is it it is is*ir*i:*ir*i:Y»'*ir ie*ir*ir*ir is i:ic**ir*ir it*ie**it it sY it is it it*ie*ir it it it is is it it it is is it ir'k is it ie it it it it**ir*ir it FLOW PROCESS FROM NODE 5895.25 TO NODE 5895.25 IS CODE = 5 UPSTREAM NODE 5895.25 ELEVATION = 1072.77 (FLOW IS UNDER PRESSURE) ------------------------------------------------------------------------------ CALCULATE JUNCTION LOSSES: PIPE FLOW DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY (CFS) (INCHES) (DEGREES) ELEVATION DEPTH(FT.) (FT/SEC) UPSTREAM 140.71 42.00 .00 1072.77 3.36 14.625 DOWNSTREAM 140.71 42.00 - 1072.77 3.36 14.625 LATERAL #1 .00 .00 .00 .00 .00 .000 LATERAL #2 .00 .00 .00 .00 .00 .000 Q5 .00===Q5 EQUALS BASIN INPUT=== LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: DY=(Q2*V2-Q1*V1*COS(DELTAl)-Q3*V3*COS(DELTA3)- Q4*V4*COS(DELTA4))/((A1+A2)*16.1)+FRICTION LOSSES UPSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .01956 DOWNSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .01956 AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS .01956 JUNCTION LENGTH = 1.00 FEET FRICTION LOSSES = .020 FEET ENTRANCE LOSSES = .000 FEET JUNCTION LOSSES = (DY+HV1-HV2)+(ENTRANCE LOSSES) JUNCTION LOSSES = ( .020)+( .000) = .020 ------------------------------------------------------------------------------ NODE 5895.25 : HGL = < 1079.097>;EGL= < 1082.419>;FLOWLINE= < 1072.770> .. ,. »•iti: it is it is it it it ic'.c:c it it s;i:»•.*i: is is it*it*it:Yi:it*it*ic*»•ir*»•i:**iti:i: it it it**i:ir»•it*ir it it*»•ic+,t*»•ir it it*it**fir is is is FLOW PROCESS FROM NODE 5895.25 TO NODE 5947.67 IS CODE = 1 Page 16 UPSTREAM NODE 5947.67 ELEVATION = 1073.29 (FLOW IS UNDER PRESSURE) ------------------------------------------------------------------------------ CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 140.71 CFS PIPE DIAMETER 42.00 INCHES PIPE LENGTH = 52.42 FEET MANNING'S N = .01300 SF=(Q/K)**2 = (( 140.71)/( 1006.131))**2 = .01956 HF=L*SF = ( 52.42)*( .01956) = 1.025 ---------------------------------------------------------- NODE 5947.67 : HGL = < 1080.123>;EGL= < 1083.444>;FLOWLINE= < 1073.290> is it is is is it is it irir i�ir it it it iir it it it it it is it*ir iv is it is is it is ir'.r it it is it it it is it is it it is it is is is it it it it is it it ick it is it i<ir *ir ie it is ie it it i*ic is is FLOW PROCESS FROM NODE 5947.67 TO NODE 5952.33 IS CODE = 5 UPSTREAM NODE 5952.33 ELEVATION = 1073.33 (FLOW IS UNDER PRESSURE) ------------------------------------------------------------------------------ CALCULATE JUNCTION LOSSES: PIPE FLOW DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY (CFS) (INCHES) (DEGREES) ELEVATION DEPTH(FT.) (FT/SEC) UPSTREAM 123.04 42.00 .00 1073.33 3.27 12.789 DOWNSTREAM 140.71 42.00 - 1073.29 3.36 14.625 LATERAL #1 17.67 24.00 45.00 1073.50 1.51 5.625 LATERAL #2 .00 .00 .00 .00 .00 .000 Q5 .00===Q5 EQUALS BASIN INPUT=== LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: DY=(Q2*V2-Q1*VI*COS(DELTAI)-Q3*V3*COS(DELTA3)- Q4*V4*COS(DELTA4))/((Al+A2)*16.1)+FRICTION LOSSES UPSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .01495 DOWNSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .01956 AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS .01726 JUNCTION LENGTH = 4.66 FEET FRICTION LOSSES = .080 FEET ENTRANCE LOSSES = .000 FEET JUNCTION LOSSES = (DY+HV1-HV2)+(ENTRANCE LOSSES) JUNCTION LOSSES = ( .635)+( .000) = .635 ------------------------------------------------------------------------------ NODE 5952.33 : HGL = < 1081.540>;EGL= < 1084.079>;FLOWLINE= < 1073.330> ....*'.c*ir is ir'.r it*::*ir �•�•*.**ir it**it**iris*ic is is it*ir is it is*ir it***ir is it it it it ie*ic it it*ic is it*.*ir it ie it*ir it it it*ic is is*�•ir is FLOW PROCESS FROM NODE 5952.33 TO NODE 6132.50 IS CODE = 1 UPSTREAM NODE 6132.50 ELEVATION = 1074.84 (FLOW IS UNDER PRESSURE) ------------------------------------------------------------------------------ CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 123.04 CFS PIPE DIAMETER = 42.00 INCHES PIPE LENGTH = 180.17 FEET MANNING'S N = .01300 SF=(Q/K)**2 = (( 123.04)/( 1006.102))**2 = .01496 HF=L*SF = ( 180.17)*( .01496) = 2.695 ------------------------------------------------------------------------------ NODE 6132.50 : HGL = < 1084.234>;EGL= < 1086.774>;FLOWLINE= < 1074.840> it&**:.•i:i.•.*iri:**s:*ir*ir is is*it it it***it*ic*ic*ir is is*ir is it is*ir is it*ir it ie it it*ic it is it is*ie it it it*it it *ir it it ie it is is it is is is it it FLOW PROCESS FROM NODE 6132.50 TO NODE 6132.50 IS CODE = 5 UPSTREAM NODE 6132.50 ELEVATION = 1074.84 (FLOW IS UNDER PRESSURE) ------------------------------------------------------------------------------ CALCULATE JUNCTION LOSSES: PIPE FLOW DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY (CFS) (INCHES) (DEGREES) ELEVATION DEPTH(FT.) (FT/SEC) UPSTREAM 123.04 42.00 .00 1074.84 3.27 12.789 DOWNSTREAM 123.04 42.00 - 1074.84 3.27 12.789 LATERAL #1 .00 24.00 45.00 1075.91 .00 .000 LATERAL #2 .00 .00 .00 .00 .00 .000 Q5 .00===Q5 EQUALS BASIN INPUT=== LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: DY=(Q2*V2-QlirV1*COS(DELTAI)-Q3*V3*COS(DELTA3)- Q4*V4*COS(DELTA4))/((A1+A2)*16.1)+FRICTION LOSSES UPSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .01495 Page 17 DOWNSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .01495 AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS .01495 JUNCTION LENGTH = 1.00 FEET FRICTION LOSSES = .015 FEET ENTRANCE LOSSES = .000 FEET JUNCTION LOSSES = (DY+HV1-HV2)+(ENTRANCE LOSSES) JUNCTION LOSSES = ( .015)+( .000) = .015 ------------------------------------------------------------------------------ NODE 6132.50 : HGL = < 1084. 249>; EGL= < 1086. 789>; FLOWLINE= < 1074.840> it it s: is ie*ic is is is is*ic is is is it is is is is is it it it it it sY it icic is it ie*it sr it ie it it is is is it sY sY it ie sY sY sk is it ie is*ie is it it is ie ie it is is is it is it is is it is ie it s4 FLOW PROCESS FROM NODE 6132.50 TO NODE 6270.81 IS CODE = 1 UPSTREAM NODE 6270.81 ELEVATION = 1076.00 (FLOW IS UNDER PRESSURE) ------------------------------------------------------------------------------ CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 123.04 CFS PIPE DIAMETER = 42.00 INCHES PIPE LENGTH = 138.31 FEET MANNING'S N = .01300 SF=(Q/K)**2 = (( 123.04)/( 1006.114))**2 = .01496 HF=L*SF = ( 138.31)*( .01496) = 2.068 NODE 6270.81 : HGL = < 1086.318>;EGL= < 1088.857>;FLOWLINE= < 1076.000> itiririt itiriri: icirir**icitit*ic**stsYsYit*&iririt*irsY*icicicsYiririricicitic*iritir**sY•&ititicitiririricsYiricicsYicirieitiritsY*iricicic* FLOW PROCESS FROM NODE 6270.81 TO NODE 6285.81 IS CODE = 3 UPSTREAM NODE 6285.81 ELEVATION = 1076.32 (FLOW IS UNDER PRESSURE) ------------------------------------------------------------------------------ CALCULATE PIPE -BEND LOSSES(OCEMA): PIPE FLOW = 123.04 CFS PIPE DIAMETER = 42.00 INCHES CENTRAL ANGLE = 19.000 DEGREES MANNING'S N = .01300 PIPE LENGTH = 15.00 FEET BEND COEFFICIENT(KB) = .11487 FLOW VELOCITY = 12.79 FEET/SEC. VELOCITY HEAD = 2.539 FEET HB=KB*(VELOCITY HEAD) = ( .115)*( 2.539) = .292 SF=(Q/K)**2 = (( 123.04)/( 1006.196))**2 = .01495 HF=L*SF = ( 15.00)*( .01495) = .224 TOTAL HEAD LOSSES = HB + HF = ( .292)+( .224) _ .516 NODE 6285.81 : HGL = < 1086.834>;EGL= < 1089.373>;FLOWLINE= < 1076.320> is is ** � is is '..•ir':**ic it is*ic * it i.•'« 4: �•ic ic*ic is *'c °k *it is*ir it*ic it it is is �•*k *:c R•its: is it it is is is*ir**ir**ie*it*iris i; is is is it ie is i.• FLOW PROCESS FROM NODE 6285.81 TO NODE 6285.81 IS CODE = 5 UPSTREAM NODE 6285.81 ELEVATION = 1076.32 (FLOW IS UNDER PRESSURE) ------------------------------------------------------------------------------ CALCULATE JUNCTION LOSSES: PIPE FLOW DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY (CFS) (INCHES) (DEGREES) ELEVATION DEPTH(FT.) (FT/SEC) UPSTREAM 123.04 42.00 .00 1076.32 3.27 12.789 DOWNSTREAM 123.04 42.00 - 1076.32 3.27 12.788 LATERAL #1 .00 21.00 52.00 1077.33 .00 .000 LATERAL #2 .00 .00 .00 .00 .00 .000 Q5 .00===Q5 EQUALS BASIN INPUT=== LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: DY=(Q2*V2-Q1*V1*COS(DELTAI)-Q3*V3*COS(DELTA3)- Q4*V4*COS(DELTA4))/((A1+A2)*16.1)+FRICTION LOSSES UPSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .01495 DOWNSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .01495 AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS .01495 JUNCTION LENGTH = 1.00 FEET FRICTION LOSSES = .015 FEET ENTRANCE LOSSES = .000 FEET JUNCTION LOSSES = (DY+HV1-HV2)+(ENTRANCE LOSSES) JUNCTION LOSSES = ( .015)+( .000) = .015 NODE 6285.81 : HGL = < 1086.849>;EGL= < 1089.388>;FLOWLINE= < 1076.320> is*ic it**it is it*ir •..•ir it �•it �•ic is «s:ici:ici:*it is*�k**ir it*sYi: it it*i:i: it ie it �•*ir it s: it it •k it it is is is ir'.: �•*ir it it is it is it it it it*ic*ir is is FLOW PROCESS FROM NODE 6285.81 TO NODE 6343.04 IS CODE = 3 Page 18 UPSTREAM NODE 6343.04 ELEVATION = 1076.66 (FLOW IS UNDER PRESSURE) CALCULATE PIPE -BEND LOSSES(OCEMA): PIPE FLOW = 123.04 CFS PIPE DIAMETER = 42.00 INCHES CENTRAL ANGLE = 73.000 DEGREES MANNING'S N = .01300 PIPE LENGTH = 57.23 FEET BEND COEFFICIENT(KB) = .22515 FLOW VELOCITY = 12.79 FEET/SEC. VELOCITY HEAD = 2.540 FEET HB=KB*(VELOCITY HEAD) = ( 225)*( 2.540) = .572 SF=(Q/K)**2 = (( 123.04)/( 1006.087))**2 = .01496 HF=L*SF = ( 57.23)*( .01496) = .856 TOTAL HEAD LOSSES = HB + HF = ( .572)+( .856) = 1.428 ------------------------------------------------------------------------------ NODE 6343.04 : HGL = < 1088.277>;EGL= < 1090.816>;FLOWLINE= < 1076.660> ie it it it is is it iric ie it. it is ie is it is ir&ie it it is it it ie it it it is is is it it it*ir is it sY it it it it ie is ie it it is it h it it it it is is is is it icie is is it it it it is it it is it is it is is FLOW PROCESS FROM NODE 6343.04 TO NODE 6358.16 IS CODE = 1 UPSTREAM NODE 6358.16 ELEVATION = 1076.72 (FLOW IS UNDER PRESSURE) ------------------------------------------------------------------------------ CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 123.04 CFS PIPE DIAMETER = 42.00 INCHES PIPE LENGTH = 15.12 FEET MANNING'S N = .01300 SF=(Q/K)**2 = (( 123.04)/( 1006.229))**2 = .01495 HF=L*SF = ( 15.12)*( .01495) = .226 --------------------------------------------------------------- NODE 6358.16 : HGL = < 1088.503>;EGL= < 1091.042>;FLOWLINE= < 1076.720> it is it it is it it it is is it it * ie is * Yr * it it is it is it is it it is is it is it it it is is it is is it is it is is it it it is ie it *. is it it ie is ie sY it it is it is * it it it is is is it is ie it is is it is FLOW PROCESS FROM NODE 6358.16 TO NODE 6362.83 IS CODE = 5 UPSTREAM NODE 6362.83 ELEVATION = 1076.74 (FLOW IS UNDER PRESSURE) ------------------------------------------------------------------------------ CALCULATE JUNCTION LOSSES: PIPE FLOW DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY (CFS) (INCHES) (DEGREES) ELEVATION DEPTH(FT.) (FT/SEC) UPSTREAM 105.16 42.00 .00 1076.74 3.12 10.930 DOWNSTREAM 123.04 42.00 - 1076.72 3.27 12.789 LATERAL #1 17.88 24.00 54.00 1077.50 1.52 5.691 LATERAL #2 .00 .00 .00 .00 .00 .000 Q5 .00===Q5 EQUALS BASIN INPUT=== LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: DY=(Q2*V2-Ql*V1*COS(DELTAI)-Q3*V3*COS(DELTA3)- Q4*V4*COS(DELTA4))/((Al+A2)*16.1)+FRICTION LOSSES UPSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .01092 DOWNSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .01495 AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS .01294 JUNCTION LENGTH = 4.67 FEET FRICTION LOSSES = .060 FEET ENTRANCE LOSSES = .000 FEET JUNCTION LOSSES = (DY+HV1-HV2)+(ENTRANCE LOSSES) JUNCTION LOSSES = ( .552)+( .000) = .552 NODE 6362.83 : HGL = < 1089.739>;EGL= < 1091.594>;FLOWLINE= < 1076.740> *ir it it**is is***ir it icg•ic::*�•ic ie is it is it is it*ic*ir it**ic is***ir is it it is is it it it it it is is it it *ie it is it*it it it'hit**it ie it it it it it it**it FLOW PROCESS FROM NODE 6362.83 TO NODE 6763.18 IS CODE = 1 UPSTREAM NODE 6763.18 ELEVATION = 1078.34 (FLOW IS UNDER PRESSURE) ---------------------------------------------------- CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 105.16 CFS PIPE DIAMETER 42.00 INCHES PIPE LENGTH = 400.35 FEET MANNING'S N = .01300 SF=(Q/K)**2 = (( 105.16)/( 1006.102))**2 = .01092 HF=L*SF = ( 400.35)*( .01092) = 4.374 ------------------------------------------------------------------------------ NODE 6763.18 : HGL = < 1094.113>;EGL= < 1095.968>;FLOWLINE= < 1078.340> '.r* �•::ir**it it*i:*ir it is*it*i:*ir is it i:i:ir*ic ir;;i.•***ic**ir�•iri::it ie*ic::ir�-it*ir**ic it is is it*ir*ic i.•.ir it �•i: �•it*it is**it it*i: Page 19 FLOW PROCESS FROM NODE 6763.18 TO NODE 6773.18 IS CODE = 5 UPSTREAM NODE 6773.18 ELEVATION = 1078.37 (FLOW IS UNDER PRESSURE) ------------------------------------------------------------------------------ CALCULATE JUNCTION LOSSES: PIPE FLOW DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY (CFS) (INCHES) (DEGREES) ELEVATION DEPTH(FT.) (FT/SEC) UPSTREAM 49.37 42.00 .00 1078.37 2.20 5.132 DOWNSTREAM 105.16 42.00 - 1078.34 3.12 10.930 LATERAL #1 55.79 36.00 30.00 1078.85 2.42 7.893 LATERAL #2 .00 .00 .00 .00 .00 .000 Q5 .00===Q5 EQUALS BASIN INPUT=== LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: DY=(Q2*V2-Ql*V1*COS(DELTAI)-Q3*V3*COS (DELTA3)- Q4*V4*COS(DELTA4))/((A1+A2)*16.1)+FRICTION LOSSES UPSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00241 DOWNSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .01092 AVERAGED FRICTION SLOPE INJUNCTION ASSUMED AS .00667 JUNCTION LENGTH = 10.00 FEET FRICTION LOSSES = .067 FEET ENTRANCE LOSSES = .000 FEET JUNCTION LOSSES = (DY+HV1-HV2)+(ENTRANCE LOSSES) JUNCTION LOSSES = ( .282)+( .000) = .282 NODE 6773.18 : HGL = < 1095.841>;EGL= < 1096.250>;FLOWLINE= < 1078.370> «««it «* « «« « �• «it «'.r * «««ic is «««««««««««««««ir ««««:� ««««««««�° ««««««««««it «««««««««ic «««««ic FLOW PROCESS FROM NODE 6773.18 TO NODE 6884.95 IS CODE = 1 UPSTREAM NODE 6884.95 ELEVATION = 1078.82 (FLOW IS UNDER PRESSURE) ------------------------------------------------------------------------------ CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 49.37 CFS PIPE DIAMETER = 42.00 INCHES PIPE LENGTH = 111.77 FEET MANNING'S N = .01300 SF=(Q/K)**2 = (( 49.37)/( 1006.271))**2 = .00241 HF=L*SF = ( 111.77)*( .00241) = .269 NODE 6884.95 : HGL = < 1096.110>;EGL= < 1096.519>;FLOWLINE= < 1078.820> FLOW PROCESS FROM NODE 6884.95 TO NODE 6884.95 IS CODE = 5 UPSTREAM NODE 6884.95 ELEVATION = 1078.82 (FLOW IS UNDER PRESSURE) ------------------------------------------------------------------------------ CALCULATE JUNCTION LOSSES: PIPE FLOW DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY (CFS) (INCHES) (DEGREES) ELEVATION DEPTH(FT.) (FT/SEC) UPSTREAM 48.19 42.00 .00 1078.82 2.17 5.009 DOWNSTREAM 49.37 42.00 - 1078.82 2.20 5.131 LATERAL #1 1.18 21.00 90.00 1080.18 .39 .491 LATERAL #2 .00 .00 .00 .00 .00 .000 Q5 .00===Q5 EQUALS BASIN INPUT=== LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: DY=(Q2*V2-Q1*V1*COS(DELTAI)-Q3*V3*COS(DELTA3)- Q4*V4*COS(DELTA4))/((A1+A2)*16.1)+FRICTION LOSSES UPSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00229 DOWNSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00241 AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS .00235 JUNCTION LENGTH = 1.00 FEET FRICTION LOSSES = .002 FEET ENTRANCE LOSSES = .000 FEET JUNCTION LOSSES = (DY+HV1-HV2)+(ENTRANCE LOSSES) JUNCTION LOSSES = ( .022)+( .000) = .022 NODE 6884.95 : HGL = < 1096.151>;EGL= < 1096.541>;FLOWLINE= < 1078.820> FLOW PROCESS FROM NODE 6884.95 TO NODE 7143.95 IS CODE = 1 Page 20 UPSTREAM NODE 7143.95 ELEVATION = 1079.86 (FLOW IS UNDER PRESSURE) ------------------------------------------------------------------------------ CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 48.19 CFS PIPE DIAMETER = 42.00 INCHES PIPE LENGTH = 259.00 FEET MANNING'S N = .01300 SF=(Q/K)**2 = (( 48.19)/( 1006.169))**2 = .00229 HF=L*SF = ( 259.00)*( .00229) = .594 ------------------------------------------------------------------------------ NODE 7143.95 : HGL = < 1096.745>;EGL= < 1097.135>;FLOWLINE= < 1079.860> icirieiciciticisiciciricftititie�ritirieiriciriric4titiriciciciciticitieisicieieiriricititicicititieitieiriricicirfciritic4cir*iciritieiritieitirieiriciric FLOW PROCESS FROM NODE 7143.95 TO NODE 7149.45 IS CODE = 5 UPSTREAM NODE 7149.45 ELEVATION = 1079.88 (FLOW IS UNDER PRESSURE) ------------------------------------------------------------------------------ CALCULATE JUNCTION LOSSES: PIPE FLOW DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY (CFS) (INCHES) (DEGREES) ELEVATION DEPTH(FT.) (FT/SEC) UPSTREAM 43.16 42.00 .00 1079.88 2.05 4.485 DOWNSTREAM 48.19 42.00 - 1079.86 2.17 5.009 LATERAL #1 5.03 24.00 45.00 1080.89 .79 1.601 LATERAL #2 .00 .00 .00 .00 .00 .000 Q5 .00===Q5 EQUALS BASIN INPUT=== LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: DY=(Q2*V2-Ql*Vl*COS(DELTAl)-Q3*V3*COS(DELTA3)- Q4*V4*COS(DELTA4))/((A1+A2)*16.1)+FRICTION LOSSES UPSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00184 DOWNSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00229 AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS .00207 JUNCTION LENGTH = 5.50 FEET FRICTION LOSSES = .011 FEET ENTRANCE LOSSES = .000 FEET JUNCTION LOSSES = (DY+HV1-HV2)+(ENTRANCE LOSSES) JUNCTION LOSSES = ( .070)+( .000) = .070 ----------------------------------------------------------- NODE 7149.45 : HGL = < 1096.892>;EGL= < 1097.205>;FLOWLINE= < 1079.880> is is ie is it is it i.• � * it is it is it it it it it it it * is it it is it it it it * * is it *. ie it it it it it is ie is it is it it it it k it it is it it is it it it it k it it it it it it it Yk irir it it is it is FLOW PROCESS FROM NODE 7149.45 TO NODE 7239.93 IS CODE = 1 UPSTREAM NODE 7239.93 ELEVATION = 1080.33 (FLOW IS UNDER PRESSURE) ------------------------------------------------------------------------------ CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 43.16 CFS PIPE DIAMETER = 42.00 INCHES PIPE LENGTH = 90.48 FEET MANNING'S N = .01300 SF=(Q/K)**2 = (( 43.16)/( 1006.110))**2 = .00184 HF=L*SF = ( 90.48)*( .00184) = .167 ------------------------------------------------------------------------------ NODE 7239.93 : HGL = < 1097.059>;EGL= < 1097.371>;FLOWLINE= < 1080.330> ..**i: it is �•i: it it it �'ie is k ie ie*ic it is ie is**.*ie is it is it**ic it it ie is it*it*it it sY is**:rir*k*ir it is 4t is it is it it it it ie it is it it it it it it is ie *ic it FLOW PROCESS FROM NODE 7239.93 TO NODE 7315.36 IS CODE = 3 UPSTREAM NODE 7315.36 ELEVATION = 1080.71 (FLOW IS UNDER PRESSURE) --------------------------------------------------------- CALCULATE PIPE -BEND LOSSES(OCEMA): PIPE FLOW = 43.16 CFS PIPE DIAMETER = 42.00 INCHES CENTRAL ANGLE = 48.000 DEGREES MANNING'S N = .01300 PIPE LENGTH = 75.43 FEET BEND COEFFICIENT(KB) = .18257 FLOW VELOCITY = 4.49 FEET/SEC. VELOCITY HEAD = .313 FEET HB=KB*(VELOCITY HEAD) = ( .183)*( .313) = .057 SF=(Q/K)**2 = (( 43.16)/( 1005.893))**2 = .00184 HF=L*SF = ( 75.43)*( .00184) = .139 TOTAL HEAD LOSSES = HB + HF = ( .057)+( .139) _ .196 ------------------------------------------------------------------------------ NODE 7315.36 : HGL = < 1097.255>;EGL= < 1097.567>;FLOWLINE= < 1080.710> *iri:ir*ir it*i:*:c*�:c**it�•ic it i:*it it ir'x*it it*ir ie is it ie it ie ie it it it it ir'.c*ii*ie it is ie it it**.ic it it it i.•it ie ie ir**�$r it it ie it it s; ie ie it is is Page 21 FLOW PROCESS FROM NODE 7315.36 TO NODE 7315.36 IS CODE = 5 UPSTREAM NODE 7315.36 ELEVATION = 1080.71 (FLOW IS UNDER PRESSURE) ------------------------------------------------------------------------------ CALCULATE JUNCTION LOSSES: PIPE FLOW DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY (CFS) (INCHES) (DEGREES) ELEVATION DEPTH(FT.) (FT/SEC) UPSTREAM 40.17 42.00 .00 1080.71 1.97 4.175 DOWNSTREAM 43.16 42.00 - 1080.71 2.05 4.486 LATERAL #1 2.99 21.00 72.00 1081.96 .63 1.243 LATERAL #2 .00 .00 .00 .00 .00 .000 Q5 .00===Q5 EQUALS BASIN INPUT=== LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: DY=(Q2*V2-Q1*V1*COS(DELTAI)-Q3*V3*COS(DELTA3)- Q4*V4*COS(DELTA4))/((A1+A2)*16.1)+FRICTION LOSSES UPSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00159 DOWNSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00184 AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS .00172 JUNCTION LENGTH = 1.00 FEET FRICTION LOSSES = .002 FEET ENTRANCE LOSSES = .000 FEET JUNCTION LOSSES = (DY+HV1-HV2)+(ENTRANCE LOSSES) JUNCTION LOSSES = ( .040)+( .000) = .040 NODE 7315.36 : HGL = < 1097. 336>; EGL= < 1097.607>;FLOWLINE= < 1080.710> is it it sY it it ie ie it**ir it is it it it it it it is it it it icir it it it it ir*it is is it is it is is it it is it is is ie it ie it sY*ic sY is it is is it ie it it it it* is it it is it is it it it it is is it FLOW PROCESS FROM NODE 7315.36 TO NODE 7348.91 IS CODE = 3 UPSTREAM NODE 7348.91 ELEVATION = 1080.88 (FLOW IS UNDER PRESSURE) ------------------------------------------------------------------------------ CALCULATE PIPE -BEND LOSSES(OCEMA): PIPE FLOW = 40.17 CFS PIPE DIAMETER = 42.00 INCHES CENTRAL ANGLE = 21.000 DEGREES MANNING'S N = .01300 PIPE LENGTH = 33.55 FEET BEND COEFFICIENT(KB) = .12076 FLOW VELOCITY = 4.17 FEET/SEC. VELOCITY HEAD = .271 FEET HB=KB*(VELOCITY HEAD) = ( 121)*( .271) = .033 SF=(Q/K)**2 = (( 40.17)/( 1005.938))**2 = .00159 HF=L*SF = ( 33.55)*( .00159) = .053 TOTAL HEAD LOSSES = HB + HF = ( .033)+( .053) _ .086 NODE 7348.91 : HGL = < 1097.423>;EGL= < 1097.693>;FLOWLINE= < 1080.880> is is it it**ir is it**ir it is is it is it *iris*it it is it*ir it ie it it it is is is ie is it it is is it is it it it it is it is is****ir is is itir*****ie it :t °k is it sY is it*ie it FLOW PROCESS FROM NODE 7348.91 TO NODE 7348.91 IS CODE = 5 UPSTREAM NODE 7348.91 ELEVATION = 1080.88 (FLOW IS UNDER PRESSURE) ------------------------------------------------------------------------------ CALCULATE JUNCTION LOSSES: PIPE FLOW DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY (CFS) (INCHES) (DEGREES) ELEVATION DEPTH(FT.) (FT/SEC) UPSTREAM 37.47 42.00 .00 1080.88 1.90 3.895 DOWNSTREAM 40.17 42.00 - 1080.88 1.97 4.175 LATERAL #1 2.70 21.00 62.00 1082.13 .60 1.123 LATERAL #2 .00 .00 .00 .00 .00 .000 Q5 .00===Q5 EQUALS BASIN INPUT=== LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: DY=(Q2*V2-Q1*Vl*COS(DELTAl)-Q3*V3*COS (DELTA3)- Q4*V4*COS(DELTA4))/((A1+A2)*16.1)+FRICTION LOSSES UPSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00139 DOWNSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00159 AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS .00149 JUNCTION LENGTH = 1.00 FEET FRICTION LOSSES = .001 FEET ENTRANCE LOSSES = .000 FEET JUNCTION LOSSES = (DY+HV1-HV2)+(ENTRANCE LOSSES) JUNCTION LOSSES = ( .032)+( .000) = .032 ------------------------------------------------------------------------------ Page 22 NODE 7348.91 : HGL = < 1097.490>;EGL= < 1097.725>;FLOWLINE= < 1080.880> it is is is it it ie ie ie is is it ie ie it is is is ie ie iric is ie is it is it is is is it icic is is is it is it is it it ie it ie it is is it is is is is is it it sY is it ie ie ie ieic ie ie it ie it is it it it it it it ie FLOW PROCESS FROM NODE 7348.91 TO NODE 7373.43 IS CODE = 3 UPSTREAM NODE 7373.43 ELEVATION = 1081.00 (FLOW IS UNDER PRESSURE) ------------------------------------------------------------------------------ CALCULATE PIPE -BEND LOSSES(OCEMA): PIPE FLOW = 37.47 CFS PIPE DIAMETER = 42.00 INCHES CENTRAL ANGLE = 16.000 DEGREES MANNING'S N = .01300 PIPE LENGTH = 24.52 FEET BEND COEFFICIENT(KB) = .10541 FLOW VELOCITY = 3.90 FEET/SEC. VELOCITY HEAD = .236 FEET HB=KB*(VELOCITY HEAD) = ( 105)*( .236) = .025 SF=(Q/K)**2 = (( 37.47)/( 1006.189))**2 = .00139 HF=L*SF = ( 24.52)*( .00139) = 034 TOTAL HEAD LOSSES = HB + HF = ( .025)+( .034) _ .059 NODE 7373.43 : HGL = < 1097.549>;EGL= < 1097.784>;FLOWLINE= < 1081.000> it ie it it it is is ic* is is it it it it ie is ie it it is is �Y it is it it it is it is is is is is it is is is is is it it is it is is it is it is it it ie it is is it it is is it irie it alit it ie it it is is it it is it it FLOW PROCESS FROM NODE 7373.43 TO NODE 7387.93 IS CODE = 1 UPSTREAM NODE 7387.93 ELEVATION = 1081.07 (FLOW IS UNDER PRESSURE) ------------------------------------------------------------------------------ CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW 37.47 CFS PIPE DIAMETER = 42.00 INCHES PIPE LENGTH = 14.50 FEET MANNING'S N = .01300 SF=(Q/K)**2 = (( 37.47)/( 1008.418))**2 = .00138 HF=L*SF = ( 14.50)*( .00138) = .020 NODE 7387.93 : HGL = < 1097.569>;EGL= < 1097.804>;FLOWLINE= < 1081.070> it is ic* kit**ir i.•i: i.•'.cR•ir*it it it it it it is*ir it is is is it it is it icic it*ir.*it 4r it it it**ir*ic it ie ie it is ie ic*:c***ir*itit it *ic 4e***ir is*ir it k UPSTREAM PIPE FLOW CONTROL DATA: NODE NUMBER = 7387.93 FLOWLINE ELEVATION = 1081.07 ASSUMED UPSTREAM CONTROL HGL = 1082.97 FOR DOWNSTREAM RUN ANALYSIS ---------------------------------------- END OF GRADUALLY VARIED FLOW ANALYSIS Page 23 is it is it it it is it is is sY ic'h iv ie it it it it ie it it it is it is it*ir is it it***ic it it it it is is is ie is it it is ie sY it is is icit ie ie is**ie it is it it it ie is it irie is it it is is iric PIPE -FLOW HYDRAULICS COMPUTER PROGRAM PACKAGE (Reference: LACFCD,LACRD, AND OCEMA HYDRAULICS CRITERION) (c) Copyright 1982-93 Advanced Engineering Software (aes) Ver. 4.6A Release Date: 7/18/93 License ID 1202 Analysis prepared by: HUITT-ZOLLARS, INC. 15101 RED HILL AVENUE TUSTIN, CALIFORNIA 92780-6500 PHONE (714) 259-7900 * FAX (714) 259-0210 DESCRIPTION OF STUDY***********icicieiciri:i:iriririririricir * SIERRA BUSINESS PARK * STORM DRAIN LINE A 100-YEAR HYDRAULIC ANALYSIS it iri: it it is is it it is it*ir***ir is ir-k is it it it it it i�ir it is*ir it ie is is is it is is it it i�ir it is it ie is is it it is it ieic it it it it it is is is it it is it Yr is it is it ie is ------------------------------------------------------------------------------ FILE NAME: SBPLINEA.HGL TIME/DATE OF STUDY: 8:18 6/17/2004 * * * is is � ie is is * *.* it it itYc is it ie it it is it is is it is icir is is is it it is it is it it is it it it it it it is is ie it is is it is it is it it it is it is is it is it * is is it is is it it it it it is GRADUALLY VARIED FLOW ANALYSIS FOR PIPE SYSTEM NODAL POINT STATUS TABLE (Note: "*" indicates nodal point data used.) UPSTREAM RUN DOWNSTREAM RUN NODE MODEL PRESSURE PRESSURE+ FLOW PRESSURE+ NUMBER PROCESS HEAD(FT) MOMENTUM(POUNDS) DEPTH(FT) MOMENTUM(POUNDS) .00- 14.10* 25100.28 3.69 10374.20 1 FRICTION 17.49- 14.02* 24956.40 3.69 10376.01 1 FRICTION 51.95- 13.85* 24664.74 3.69 10374.33 1 FRICTION+BEND 146.24- 13.69* 24381.54 3.68 10390.60 1 FRICTION 166.52- 13.59* 24206.77 3.68 10389.20 1 FRICTION+BEND 195.97- 13.68* 24361.63 3.68 10394.20 1 FRICTION 226.24- 13.54* 24107.44 3.67 10397.32 1 FRICTION+BEND 1101.35- 13.63* 24262.31 3.67 10403.68 1 FRICTION 1887.40- 9.93* 17747.24 3.07 11914.05 1 FRICTION+BEND 1958.09- 8.69* 15555.89 3.36 11038.91 1 FRICTION 1987.87- 8.00* 14345.03 3.60 10524.81 1 JUNCTION 1996.03- 7.36* 13083.83 3.81 10305.36 1 FRICTION 2345.29- 6.20* 11371.01 3.93 10157.14 1 JUNCTION 2345.29- 6.26* 11379.48 3.83 10173.97 1 FRICTION 2489.38- 5.78* 10664.36 3.90 10087.78 1 MANHOLE 2494.54- 5.82* 10729.94 3.79 10228.51 1 FRICTION 1 HYDRAULIC JUMP 2679.01- 4.72 9725.59 3.81* 10200.39 Page 1 I JUNCTION 2679.01- 4.79 9740.40 3.79* 10219.45 1 FRICTION 2966.03- 4.60 DC 9715.70 3.67* 10397.04 1 TRANSITION 2971.61- 4.56*DC 10344.96 4.56*DC 10344.96 1 FRICTION 3203.94- 4.57*DC 10344.98 4.56*DC 10344.96 1 JUNCTION 3211.10- 6.30* 9488.90 3.53 7848.82 1 FRICTION 3272.58- 5.91* 9015.88 3.87 7595.16 1 JUNCTION 3277.74- 5.91* 9012.46 3.80 7629.77 1 FRICTION 3764.00- 5.29* 8253.78 4.22 DC 7513.93 1 JUNCTION 3769.16- 5.59* 6515.49 3.09 5355.04 1 FRICTION 3833.29- 5.34* 6262.57 3.14 5319.05 1 JUNCTION 3833.29- 5.34* 6269.31 3.12 5331.79 1 FRICTION 4034.03- 4.61* 5537.23 3.72 DC 5112.42 1 JUNCTION 4041.19- 5.30* 4804.56 3.24 DC 3407.24 1 FRICTION 4045.48- 5.30* 4800.88 3.23 DC 3407.25 1 JUNCTION 4045.48- 5.30* 4804.62 3.24 DC 3407.24 1 FRICTION 4402.92- 5.03* 4535.48 3.24 DC 3407.24 1 FRICTION+BEND 4473.70- 5.20* 4705.16 3.24 DC 3407.24 1 FRICTION 4535.03- 5.15* 4656.93 3.24 DC 3407.24 1 MANHOLE 4540.19- 5.18* 4681.52 3.24 DC 3407.24 1 FRICTION 5035.03- 4.80* 4311.64 3.24 DC 3407.24 1 MANHOLE 5040.19- 4.83* 4336.34 3.24 DC 3407.24 1 FRICTION 5535.03- 4.44* 3953.10 3.24 DC 3407.24 1 MANHOLE 5540.19- 4.46* 3977.93 3.24 DC 3407.24 1 FRICTION 5542.24- 4.46* 3974.93 3.24 DC 3407.24 1 FRICTION+BEND 5577.58- ------------------------------------------------------------------------------ 4.42* 3936.83 3.24 DC 3407.24 MAXIMUM NUMBER ------------------------------------------------------------------------------ OF ENERGY BALANCES USED IN EACH PROFILE = 25 NOTE: STEADY FLOW HYDRAULIC HEAD -LOSS COMPUTATIONS BASED ON THE MOST CONSERVATIVE FORMULAE FROM THE CURRENT LACRD,LACFCD, AND OCEMA DESIGN MANUALS. *i:i:i:ir*i: is is is i:*i: *it is �•:: i; �•*i:ir*i:***i:i: it it::**ic*ir it*iriric*ic*ir it*�..•ie**ici:*iric�•ic�•*ir it is X•ic is is it it it is is*ir �'.r DOWNSTREAM PIPE FLOW CONTROL DATA: NODE NUMBER = .00 FLOWLINE ELEVATION = 1039.50 PIPE FLOW = 283.70 CFS PIPE DIAMETER = 72.00 INCHES ASSUMED DOWNSTREAM ------------------------------------------------------------------------------ CONTROL HGL = 1053.600 NODE .00 : HGL = < 1053.600>;EGL= < 1055.163>;FLOWLINE= < 1039.500> it it i:i: it it it it is it it it it �•i: is it it it it is kir is it is it it it is*iri: it it*ir it is is**ir it ie it it*ir is itit is is it it is it it is it*ic s4 is it it 4r it it it it it i:*ir it ie Page 2 FLOW PROCESS FROM NODE .00 TO NODE 17.49 IS CODE = 1 UPSTREAM NODE 17.49 ELEVATION = 1039.66 (FLOW IS UNDER PRESSURE) ------------------------------------------------------------------------------ CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 283.70 CFS PIPE DIAMETER 72.00 INCHES PIPE LENGTH = 17.49 FEET MANNING'S N = .01300 SF=(Q/K)**2 = (( 283.70)/( 4234.906))**2 = .00449 HF=L*SF = ( 17.49)*( .00449) = .078 ------------------------------------------------------------------------------ NODE 17.49 : HGL = < 1053.678>;EGL= < 1055.242>;FLOWLINE= < 1039.660> it it it it it is it is it it is is it*it is it is is it it it is is irYt is is it it it it it it ie is it is it ie it is it it is it it is it it it it is ie it it it is it is it it it it is*i:*ic is it it ie it it sY it is FLOW PROCESS FROM NODE 17.49 TO NODE 51.95 IS CODE = 1 UPSTREAM NODE 51.95 ELEVATION = 1039.98 (FLOW IS UNDER PRESSURE) ------------------------------------------------------------------------------ CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 283.70 CFS PIPE DIAMETER = 72.00 INCHES PIPE LENGTH = 34.46 FEET MANNING'S N = .01300 SF=(Q/K)**2 = (( 283.70)/( 4236.382))**2 = .00448 HF=L*SF = ( 34.46)*( .00448) = .155 ------------------------------------------------------------------------------ NODE 51.95 : HGL = < 1053.833>;EGL= < 1055.396>;FLOWLINE= < 1039.980> *.*Y it it it ie*i: it it is *ir it it is**ic i; ie is is is sY it it irir it it it it is it it is it ie it it ie is*ic it it it is it ie**ic s4 it it it is it ie ie is is ie it is ie is is it is it ie it ir* FLOW PROCESS FROM NODE 51.95 TO NODE 146.24 IS CODE = 3 UPSTREAM NODE 146.24 ELEVATION = 1040.84 (FLOW IS UNDER PRESSURE) ------------------------------------------------------------------------------ CALCULATE PIPE -BEND LOSSES(OCEMA): PIPE FLOW = 283.70 CFS PIPE DIAMETER = 72.00 INCHES CENTRAL ANGLE = 45.000 DEGREES MANNING'S N = .01300 PIPE LENGTH = 94.29 FEET BEND COEFFICIENT(KB) = .17678 FLOW VELOCITY = 10.03 FEET/SEC. VELOCITY HEAD = 1.563 FEET HB=KB*(VELOCITY HEAD) = ( .177)*( 1.563) = .276 SF=(Q/K)**2 = (( 283.70)/( 4235.069))**2 = .00449 HF=L*SF = ( 94.29)*( .00449) = .423 TOTAL HEAD LOSSES = HB + HT = ( .276)+( .423) _ .699 NODE 146.24 : HGL = < 1054.533>;EGL= < 1056.096>;FLOWLINE= < 1040.840> it is it sY it it it it ie sY sY is it is it it it ie it it*ir is it is**it it is sY is*ic is it is is is it it it ie it is is it**ic it i:*it is it ie it*ic*it it is**ir it is**ir is*ic is it is FLOW PROCESS FROM NODE 146.24 TO NODE 166.52 IS CODE 1 UPSTREAM NODE 166.52 ELEVATION = 1041.03 (FLOW IS UNDER PRESSURE) ------------------------------------------------------------------------------ CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 283.70 CFS PIPE DIAMETER = 72.00 INCHES PIPE LENGTH = 20.28 FEET MANNING'S N = .01300 SF=(Q/K)**2 = (( 283.70)/( 4233.688))**2 = .00449 HF=L*SF = ( 20.28)*( .00449) = .091 NODE 166.52 : HGL = < 1054.624>;EGL= < 1056.187>;FLOWLINE= < 1041.030> it is is is it is is it is sY �• is it i; is is �..• it ie * is it it is is is sY is it it it it is it is it is it it is * is it it is is is is * is it i:ir is it it ie ie is * is it it is is it is is it is is it is is ie it it is FLOW PROCESS FROM NODE 166.52 TO NODE 195.97 IS CODE = 3 UPSTREAM NODE 195.97 ELEVATION = 1041.30 (FLOW IS UNDER PRESSURE) ------------------------------------------------------------------------------ CALCULATE PIPE -BEND LOSSES(OCEMA): PIPE FLOW = 283.70 CFS PIPE DIAMETER = 72.00 INCHES CENTRAL ANGLE = 30.000 DEGREES MANNING'S N = .01300 PIPE LENGTH = 29.45 FEET BEND COEFFICIENT(KB) = .14434 FLOW VELOCITY = 10.03 FEET/SEC. VELOCITY HEAD = 1.563 FEET HB=KB*(VELOCITY HEAD) = ( 144)*( 1.563) = .226 SF=(Q/K)**2 = (( 283.70)/( 4235.350))**2 = .00449 HF=L*SF = ( 29.45)*( .00449) = .132 TOTAL HEAD LOSSES = HB + HF = ( .226)+( .132) _ .358 ------------------------------------------------------------------------------ Page 3 NODE 195.97 : HGL = < 1054.981>;EGL= < 1056.545>;FLOWLINE= < 1041.300> ie Yc Yt Ye is Yc Yc ie Yr is is it it Yc Yr Yt * * Yc it it ie * * * Ye it it ie it * it * it ie Yr Ye Yr it is ie Yt ieYe Yc Yt Yr * Yr Yc is it is Yc it ie ie Yc Yr Yr it * Yt is is Yr ie is Yc it Ye Ye Yc * ie it * Yc FLOW PROCESS FROM NODE 195.97 TO NODE 226.24 IS CODE = 1 UPSTREAM NODE 226.24 ELEVATION = 1041.58 (FLOW IS UNDER PRESSURE) ------------------------------------------------------------------------------ CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 283.70 CFS PIPE DIAMETER = 72.00 INCHES PIPE LENGTH = 30.27 FEET MANNING'S N = .01300 SF=(Q/K)**2 = (( 283.70)/( 4234.605))**2 = .00449 HF=L*SF = ( 30.27)*( .00449) = .136 ------------------------------------------------------------------------------ NODE 226.24 : HGL = < 1055.117>;EGL= < 1056.681>;FLOWLINE= < 1041.580> �'cic:rir�"•*YeYeicicY:Ye**Ycir*isic**irYrfcYc**ie*irirYc**icicirieYe*ir*ie*it**it***ir**ieYt&YcYrYc*YeieicirYririr**iricYrYcieirirYr FLOW PROCESS FROM NODE 226.24 TO NODE 1101.35 IS CODE = 3 UPSTREAM NODE 1101.35 ELEVATION = 1041.85 (FLOW IS UNDER PRESSURE) ---------------------------•--------------------------------------------------- CALCULATE PIPE -BEND LOSSES(OCEMA): PIPE FLOW = 283.70 CFS PIPE DIAMETER = 72.00 INCHES CENTRAL ANGLE = 30.000 DEGREES MANNING'S N = .01300 PIPE LENGTH = 29.45 FEET BEND COEFFICIENT(KB) = .14434 FLOW VELOCITY = 10.03 FEET/SEC. VELOCITY HEAD = 1.563 FEET HB=KB*(VELOCITY HEAD) = ( 144)*( 1.563) = .226 SF=(Q/K)**2 = (( 283.70)/( 4235.350))**2 = .00449 HF=L*SF = ( 29.45)*( .00449) = .132 TOTAL HEAD LOSSES = HB + HF = ( .226)+( .132) _ .358 NODE 1101.35 : HGL = < 1055.475>;EGL= < 1057.038>;FLOWLINE= < 1041.850> Yc it it �• Yc Yt * it Yc * * Yc is * Yc * *Yr Yr ie it ie Yt * it it Yt ilir is it it Yr Yt is Yr * * * it is Y� Ytic * is Yc ir* * Yr Yr Yc Yc is is is Yc Yr it i� Yc Yc is Yr Yt �• Yc Yc Yc * Yr * * it Ye Y: FLOW PROCESS FROM NODE 1101.35 TO NODE 1887.40 IS CODE = 1 UPSTREAM NODE 1887.40 ELEVATION = 1049.07 (FLOW IS UNDER PRESSURE) ------------------------------------------------------------------------------ CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 283.70 CFS PIPE DIAMETER = 72.00 INCHES PIPE LENGTH = 786.05 FEET MANNING'S N = .01300 SF=(Q/K)**2 = (( 283.70)/( 4235.143))**2 = .00449 HF=L*SF = ( 786.05)*( .00449) = 3.527 NODE 1887.40 : HGL = < 1059.002>;EGL= < 1060.566>;FLOWLINE= < 1049.070> Yr * it Yc Yc i:.Y: is Yc Ye is ie Yc Yc Yc Y: Yc it Yc Yr is Yr it Yc Yc it Yt Yt * Yc Yt Ye is it is Ye ie it Yr * * Yc Yc Yr * * *Yr is * is Yc it is * it Yr Yc is * Yc Yt Ye is Yr Yt * Yc it Ye Yc it * Yc it ie it * FLOW PROCESS FROM NODE 1887.40 TO NODE 1958.09 IS CODE = 3 UPSTREAM NODE 1958.09 ELEVATION = 1051.02 (FLOW IS UNDER PRESSURE) ------------------------------------------------------------------------------ CALCULATE PIPE -BEND LOSSES(OCEMA): PIPE FLOW = 283.70 CFS PIPE DIAMETER = 72.00 INCHES CENTRAL ANGLE = 90.000 DEGREES MANNING'S N = .01300 PIPE LENGTH = 70.69 FEET BEND COEFFICIENT(KB) = .25000 FLOW VELOCITY = 10.03 FEET/SEC. VELOCITY HEAD = 1.563 FEET HB=KB*(VELOCITY HEAD) = ( 250)*( 1.563) = .391 SF=(Q/K)**2 = (( 283.70)/( 4234.570))**2 = .00449 HF=L*SF = ( 70.69)*( .00449) = .317 TOTAL HEAD LOSSES = HB + HF = ( .391)+( .317) _ .708 ---------------------------------------------------------------- NODE 1958.09 : HGL = < 1059.710>;EGL= < 1061.274>;FLOWLINE= < 1051.020> Yc is Yr Yc * is Yr Y: it it is Ye it s4 is icic Yc Yc Yr is sY YCYt is Yr Y: Yt is is ie Yc Yr is Ye k Yc Yc Yr is Yc Yr is is Yr is Yc * it ic.Yc * Yr Yr Y: * Yc Yr is is Yr * * �r is YtYt Yt Yc is Yt is * Yt Yc Yt ic'.: FLOW PROCESS FROM NODE 1958.09 TO NODE 1987.87 IS CODE 1 UPSTREAM NODE 1987.87 ELEVATION = 1051.84 (FLOW IS UNDER PRESSURE) ------------------------------------------------------------------------------ CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 283.70 CFS PIPE DIAMETER = 72.00 INCHES PIPE LENGTH = 29.78 FEET MANNING'S N = .01300 Page 4 SF=(Q/K)**2 = (( 283.70)/( 4236.508))*-2 = .00448 HF=L*SF = ( ------------------------------------------------------------------------------ 29.78)*( .00448) = .134 NODE 1987.87 : HGL = < 1059.844>;EGL= < 1061.407>;FLOWLINE= < 1051.840> it is is iFic it ie it i� it it it it it it it is it ic'it it it it it ie is it it it is it it it it it it it it it is is it is it is is it it it it it it it it it ie is it it it ie is it ie is it it it it is ie it it it ie is is is FLOW PROCESS FROM NODE 1987.87 TO NODE 1996.03 IS CODE = 5 UPSTREAM NODE ------------------------------------------------------------------------------ 1996.03 ELEVATION = 1052.07 (FLOW IS UNDER PRESSURE) CALCULATE JUNCTION LOSSES: PIPE FLOW DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY (CFS) (INCHES) (DEGREES) ELEVATION DEPTH(FT.) (FT/SEC) UPSTREAM 276.90 66.00 .00 1052.07 4.61 11.655 DOWNSTREAM 283.70 72.00 - 1051.84 4.61 10.034 LATERAL #1 6.80 24.00 60.00 1052.07 .92 2.165 LATERAL #2 .00 .00 .00 .00 .00 .000 Q5 .00===Q5 EQUALS BASIN INPUT=== LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: DY=(Q2*V2-Q1*V1*COS(DELTAl)-Q3*V3*COS(DELTA3)- Q4*V4*COS(DELTA4))/((A1+A2)*16.1)+FRICTION LOSSES UPSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00680 DOWNSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00449 AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS .00564 JUNCTION LENGTH = 8.16 FEET FRICTION LOSSES = .046 FEET ENTRANCE LOSSES = .000 FEET JUNCTION LOSSES = (DY+HV1-HV2)+(ENTRANCE LOSSES) JUNCTION LOSSES = ( .129)+( .000) = .129 NODE 1996.03 : HGL = < 1059.427>;EGL= < 1061.536>;FLOWLINE= < 1052.070> is**i.•�•:.•ie ie is is*ir it s:ici:***ire•*�•�•*ir it R•ic***�"*ie it it it �•*it it it it**ir it �•k*ir**ic ie it*ir *ir it is it*�•*ie it it*****iric'c FLOW PROCESS FROM NODE 1996.03 TO NODE 2345.29 IS CODE = 1 UPSTREAM NODE 2345.29 ELEVATION = 1055.60 (FLOW IS UNDER PRESSURE) ------------------------------------------------------------------------------ CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 276.90 CFS PIPE DIAMETER = 66.00 INCHES PIPE LENGTH = 349.26 FEET MANNING'S N = .01300 SF=(Q/K)**2 = (( 276.90)/( 3358.142))**2 = .00680 HF=L*SF = ( 349.26)*( .00680) = 2.375 ------------------------------------------------------------------------------ NODE 2345.29 : HGL = < 1061.802>;EGL= < 1063.911>;FLOWLINE= < 1055.600> iei:ir*ir**ie ir:r it it it dr**ic ir:c it it*ir*ir**4c ic. it it*ir it ie irit*.ir***ir*ir*ir it**ir it**ic it i;'.r ie �Y is *ir ire•*ir �•***ir*ir it *ir it FLOW PROCESS FROM NODE 2345.29 TO NODE 2345.29 IS CODE = 5 UPSTREAM NODE 2345.29 ELEVATION = 1055.60 (FLOW IS UNDER PRESSURE) ------------------------------------------------------------------------------ CALCULATE JUNCTION LOSSES: PIPE FLOW DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY (CFS) (INCHES) (DEGREES) ELEVATION DEPTH(FT.) (FT/SEC) UPSTREAM 275.20 66.00 .00 1055.60 4.60 11.583 DOWNSTREAM 276.90 66.00 - 1055.60 4.61 11.655 LATERAL #1 1.70 24.00 30.00 1055.60 .45 .541 LATERAL #2 .00 .00 .00 .00 .00 .000 Q5 .00===Q5 EQUALS BASIN INPUT=== LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: DY=(Q2*V2-Ql*Vl*COS(DELTAI)-Q3*V3*COS(DELTA3)- Q4*V4*COS(DELTA4))/((Al+A2)*16.1)+FRICTION LOSSES UPSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00672 DOWNSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00680 AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS .00676 JUNCTION LENGTH = 1.00 FEET FRICTION LOSSES = .007 FEET ENTRANCE LOSSES = .000 FEET JUNCTION LOSSES = (DY+HV1-HV2)+(ENTRANCE LOSSES) Page 5 JUNCTION LOSSES = ( .031)+( .000) = .031 ------------------------------------------------------------------------------ NODE 2345.29 : HGL = < 1061.859>;EGL= < 1063.942>;FLOWLINE= < 1055.600> is it ie is it it sY it it it ie it is ie it is it ie it it it ie ie it is it is it it ie it it it it ie is ie it is is ie is is is it ie is ie ie is ie is ie it icir it it is ie ie ie ie is it is it it it ie ie it is is is is is is FLOW PROCESS FROM NODE 2345.29 TO NODE 2489.38 IS CODE = 1 UPSTREAM NODE 2489.38 ELEVATION = 1057.05 (FLOW IS UNDER PRESSURE) ------------------------------------------------------------------------------ CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 275.20 CFS PIPE DIAMETER = 66.00 INCHES PIPE LENGTH = 144.09 FEET MANNING'S N = .01300 SF=(Q/K)**2 = CC 275.20)/( 3357.983))**2 = .00672 HF=L*SF = ( 144.09)*( .00672) = .968 NODE 2489.38 : HGL = < 1062.827>;EGL= < 1064.910>;FLOWLINE= < 1057.050> icicieicir*ieirisieiciricir*iricic*icicieicieie*iricicicieieiriciricir**ieiricil*iritieicicieitiriciricicicirieieieiriciririricicicirieieieieieiric* FLOW PROCESS FROM NODE 2489.38 TO NODE 2494.54 IS CODE = 2 UPSTREAM NODE 2494.54 ELEVATION = 1057.11 (FLOW IS UNDER PRESSURE) ----------------------------------------------------------------------------- CALCULATE MANHOLE LOSSES(LACFCD): PIPE FLOW = 275.20 CFS PIPE DIAMETER = 66.00 INCHES FLOW VELOCITY = 11.58 FEET/SEC. VELOCITY HEAD = 2.083 FEET HMN = .05*(VELOCITY HEAD) = .05*( 2.083) = .104 NODE 2494.54 : HGL = < 1062.931>;EGL= < 1065.014>;FLOWLINE= < 1057.110> is it icic it is it it it it**ic is it is it it it is it it it is is it it it is it*ir ie ie it it is it it is is is it*ir it it ie it is is*ic**ie it it ie it it irir is ie it it is it ie it it it ie ie it is it FLOW PROCESS FROM NODE 2494.54 TO NODE 2679.01 IS CODE = 1 UPSTREAM NODE 2679.01 ------------------------------------------------------------------------------ ELEVATION = 1058.97 (HYDRAULIC JUMP OCCURS) CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 275.20 CFS PIPE DIAMETER= 66.00 INCHES PIPE LENGTH = ------------------------------------------------------------------------------ 184.47 FEET MANNING'S N = .01300 HYDRAULIC JUMP: ------------------------------------------------------------------------------ DOWNSTREAM RUN ANALYSIS RESULTS NORMAL DEPTH(FT) = 3.78 CRITICAL DEPTH(FT) = 4.60 UPSTREAM CONTROL ASSUMED FLOWDEPTH(FT) 3.81 - ------------------------------------------------------------------ GRADUALLY VARIED ------------------------------------------------------------------------------ FLOW PROFILE COMPUTED INFORMATION: DISTANCE FROM FLOW DEPTH VELOCITY SPECIFIC PRESSURE+ CONTROL(FT) (FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUNDS) .000 3.809 15.672 7.625 10200.39 7.031 3.807 15.678 7.626 10202.09 14.372 3.806 15.684 7.628 10203.79 22.053 3.805 15.690 7.630 10205.50 30.103 3.804 15.695 7.631 10207.21 38.559 3.802 15.701 7.633 10208.92 47.463 3.801 15.707 7.634 10210.64 56.864 3.800 15.713 7.636 10212.36 66.817 3.798 15.719 7.637 10214.08 77.391 3.797 15.725 7.639 10215.81 88.665 3.796 15.731 7.641 10217.54 100.736 3.795 15.736 7.642 10219.27 113.723 3.793 15.742 7.644 10221.01 127.771 3.792 15.748 7.645 10222.75 143.066 3.791 15.754 7.647 10224.50 159.847 3.789 15.760 7.649 10226.24 178.426 3.788 15.766 7.650 10228.00 184.470 ------------------------------------------------------------------------------ 3.788 15.768 7.651 10228.51 HYDRAULIC JUMP: UPSTREAM RUN ANALYSIS RESULTS Page 6 ------------------------------------------------------------------------------ ------------------------------------------------------------------------------ DOWNSTREAM CONTROL ASSUMED PRESSURE HEAD(FT) = 5.82 ------------------------------------------------------------------------------ PRESSURE FLOW PROFILE COMPUTED INFORMATION: ------------------------------------------------------------------------------ DISTANCE FROM PRESSURE VELOCITY SPECIFIC PRESSURE+ CONTROL(FT) HEAD(FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUNDS) .000 5.821 11.583 7.904 10729.94 95.272 ------------------------------------------------------------------------------ 5.500 11.583 7.583 10254.39 ------------------------------------------------------------------------------ ASSUMED DOWNSTREAM PRESSURE HEAD(FT) = ------------------------------------------------------------------------------ 5.50 ------------------------------------------------------------------------------ GRADUALLY VARIED FLOW PROFILE COMPUTED INFORMATION: ------------------------------------------------------------------------------ DISTANCE FROM FLOW DEPTH VELOCITY SPECIFIC PRESSURE+ CONTROL(FT) (FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUNDS) 95.272 5.500 11.580 7.583 10254.39 104.170 5.464 11.590 7.551 10206.64 111.660 5.428 11.609 7.522 10163.55 118.406 5.392 11.634 7.495 10123.54 124.601 5.356 11.663 7.470 10086.10 130.349 5.320 11.696 7.446 10050.92 135.715 5.284 11.733 7.423 10017.81 140.743 5.248 11.773 7.402 9986.65 145.465 5.212 11.816 7.382 9957.35 149.904 5.176 11.862 7.363 9929.83 154.076 5.140 11.911 7.345 9904.05 157.994 5.105 11.963 7.328 9879.96 161.664 5.069 12.017 7.312 9857.55 165.094 5.033 12.074 7.298 9836.79 168.285 4.997 12.134 7.284 9817.67 171.239 4.961 12.196 7.272 9800.17 173.954 4.925 12.261 7.261 9784.30 176.427 4.889 12.329 7.250 9770.06 178.652 4.853 12.399 7.241 9757.45 180.624 4.817 12.471 7.233 9746.48 182.332 4.781 12.546 7.227 9737.15 183.765 4.745 12.624 7.221 9729.48 184.470 4.723 12.673 7.218 9725.59 ------------------------END OF HYDRAULIC JUMP ANALYSIS------------------------ PRESSURE+MOMENTUM BALANCE OCCURS AT 102.33 FEET UPSTREAM OF NODE 2494.54 DOWNSTREAM DEPTH = 5.471 ------------------------------------------------------------------------------ FEET, UPSTREAM CONJUGATE DEPTH = 3.797 FEET NODE 2679.01 : HGL = < 1062.779>;EGL= < 1066.595>;FLOWLINE= < 1058.970> FLOW PROCESS FROM NODE 2679.01 TO NODE 2679.01 IS CODE = 5 UPSTREAM NODE ------------------------------------------------------------------------------ 2679.01 ELEVATION = 1058.97 (FLOW IS SUPERCRITICAL) CALCULATE JUNCTION LOSSES: PIPE FLOW DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY (CFS) (INCHES) (DEGREES) ELEVATION DEPTH(FT.) (FT/SEC) UPSTREAM 275.20 66.00 .00 1058.97 4.60 15.742 DOWNSTREAM 275.20 66.00 - 1058.97 4.60 15.677 LATERAL #1 .00 24.00 60.00 1058.97 .00 .000 LATERAL #2 .00 .00 .00 .00 .00 .000 Q5 .00===Q5 EQUALS BASIN INPUT=== LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: DY=(Q2*V2-Q1*V1*COS(DELTAl)-Q3*V3*COS(DELTA3)- Q4*V4*COS(DELTA4))/((Al+A2)*16.1)+FRICTION LOSSES UPSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00996 DOWNSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00986 AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS .00991 JUNCTION LENGTH = 1.00 FEET Page 7 FRICTION LOSSES = .010 FEET ENTRANCE LOSSES = .000 FEET JUNCTION LOSSES = (DY+HV1-HV2)+(ENTRANCE LOSSES) JUNCTION LOSSES = ( .017)+( .000) = ------------------------------------------------------------------------------ .017 NODE 2679.01 : HGL = < 1062.764>;EGL= < 1066.612>;FLOWLINE= < 1058.970> is ic;t it is ie it Yt it it is*it ie:s iris it it irie ie ie is it it is it kie ie is it it ie ie is it is it it ie ie is it*ic is it ie ie is is it is it is is it ie it is it it ie it it it it is is it it it it it*it FLOW PROCESS FROM NODE 2679.01 TO NODE 2966.03 IS CODE = 1 UPSTREAM NODE 2966.03 ELEVATION = ------------------------------------------------------------------------------ 1061.76 (FLOW IS SUPERCRITICAL) CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 275.20 CFS PIPE DIAMETER = 66.00 INCHES PIPE LENGTH = 287.02 FEET MANNING'S N = .01300 ------------------------------------------------------------------------------ NORMAL DEPTH(FT) = 3.83 CRITICAL DEPTH(FT) = 4.60 ---------------------------------------------------------------------------- UPSTREAM CONTROL ASSUMED FLOWDEPTH(FT) = 3.67 ---------------------------------------------------------=-- GRADUALLY VARIED FLOW PROFILE COMPUTED INFORMATION: ------------------------------------------------------------------------------ DISTANCE FROM FLOW DEPTH VELOCITY SPECIFIC PRESSURE+ CONTROL(FT) (FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUNDS) .000 3.675 16.310 7.808 10397.04 8.443 3.681 16.279 7.799 10387.10 17.188 3.687 16.249 7.789 10377.24 26.260 3.693 16.218 7.780 10367.48 35.692 3.699 16.188 7.771 10357.80 45.518 3.706 16.158 7.762 10348.21 55.779 3.712 16.128 7.753 10338.71 66.521 3.718 16.098 7.744 10329.29 77.800 3.724 16.068 7.735 10319.96 89.680 3.730 16.038 7.727 10310.71 102.240 3.736 16.009 7.718 10301.55 115.573 3.743 15.979 7.710 10292.48 129.795 3.749 15.950 7.701 10283.48 145.047 3.755 15.921 7.693 10274.58 161.510 3.761 15.892 7.685 10265.75 179.413 3.767 15.863 7.677 10257.01 199.062 3.773 15.834 7.669 10248.35 220.868 3.780 15.805 7.661 10239.77 245.409 3.786 15.777 7.653 10231.28 273.531 3.792 15.749 7.645 10222.87 287.020 3.794 15.737 ------------------------------------------------------------------------------ 7.642 10219.45 NODE 2966.03 : HGL = < 1065.435>;EGL= < 1069.568>;FLOWLINE= < 1061.760> it it � is i.• � it ft it it * is it it * it i� is ie it is it it ie is is � it it is it it is is is is it it it it sY it it it � is it it is it is * is is it is ie it it it it it ie is is it it it is is it is it it it is it it FLOW PROCESS FROM NODE 2966.03 TO NODE 2971.61 IS CODE = 9 UPSTREAM NODE 2971.61 ELEVATION = 1061.81 (FLOW IS SUPERCRITICAL) ------------------------------------------------------------------------------ CALCULATE TRANSITION LOSSES(LACFCD): PIPE FLOW = 275.20 CFS TRANSITION STRUCTURE LENGTH = 5.58 FEET TOTAL -ANGLE -OF -TRANSITION = 3.000 DEGREES PIPE DIAMETER: UPSTREAM = 60.00 INCHES; DOWNSTREAM = 66.00 INCHES MANNING'S N: UPSTREAM = .01300; DOWNSTREAM = .01300 VELOCITY: UPSTREAM = 14.64 FEET/SEC.; DOWNSTREAM = 16.32 FEET/SEC. VELOCITY HEAD: UPSTREAM = 3.328 FEET; DOWNSTREAM = 4.133 FEET HT = .1*(V2*V2-Vl*V1)/64.4 TRANSITION LOSS COEFFICIENT = .10000 TRANSITION LOSS = .081 AVERAGE TRANSITION STRUCTURE FRICTION SLOPE ASSUMED = .01030 HF= L*SF = ( 5.58)*(.01030) = .057 TOTAL LOSSES = (HT)+(HF) = ( .081)+( .057) _ .138 NODE 2971.61 : HGL = < 1066. 373>; EGL= < 1069. 702>; FLOWLINE= < 1061.810> Page 8 4; 4c:c4eir*'!c*i;Ycici;i;Yeicfcf;itiriei;f;ici;ic4;*itiefti;Y;ieiei;i;f;�'c4cir4ri;Yici;iriciciefeYtirieYicirir4ticieiclelcirieicYt*it4e�Y*ici;*Yitit FLOW PROCESS FROM NODE 2971.61 TO NODE 3203.94 IS CODE = 1 UPSTREAM NODE 3203.94 ELEVATION = 1064.07 (FLOW IS SUBCRITICAL) ---------------------------------------------------------------------------- CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 275.20 CFS PIPE DIAMETER = 60.00 INCHES PIPE LENGTH = 232.33 FEET MANNING'S N = .01300 ------------------------------------------------------------------------------ NORMAL DEPTH(FT) = 4.57 & 4.80 CRITICAL DEPTH(FT) = 4.56 NOTE: SUGGEST CONSIDERATION OF WAVE ACTION, UNCERTAINTY, ETC. DOWNSTREAM CONTROL ASSUMED FLOWDEPTH(FT) = 4.56 GRADUALLY VARIED FLOW PROFILE COMPUTED INFORMATION: DISTANCE FROM FLOW DEPTH VELOCITY SPECIFIC PRESSURE+ CONTROL(FT) (FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUNDS) .000 4.563 14.636 7.892 10344.96 .005 4.563 14.636 7.892 10344.96 .020 4.564 14.635 7.892 10344.96 .047 4.564 14.635 7.892 10344.96 .086 4.564 14.634 7.892 10344.96 .139 4.564 14.634 7.892 10344.96 .208 4.564 14.633 7.892 10344.96 .292 4.565 14.633 7.892 10344.96 .396 4.565 14.633 7.892 10344.96 .521 4.565 14.632 7.892 10344.96 .669 4.565 14.632 7.892 10344.96 .845 4.565 14.631 7.892 10344.96 1.051 4.566 14.631 7.892 10344.96 1.294 4.566 14.630 7.892 10344.96 1.579 4.566 14.630 7.892 10344.96 1.915 4.566 14.629 7.892 10344.96 2.312 4.566 14.629 7.892 10344.97 2.785 4.567 14.629 7.892 10344.97 3.354 4.567 14.628 7.892 10344.97 4.049 4.567 14.628 7.892 10344.97 4.916 4.567 14.627 7.892 10344.97 6.031 4.567 14.627 7.892 10344.97 7.543 4.568 14.626 7.892 10344.97 9.776 4.568 14.626 7.892 10344.98 13.783 4.568 14.626 7.892 10344.98 232.330 4.568 14.625 7.892 10344.98 NODE 3203.94 : HGL = < 1068.638>;EGL= < 1071.961>;FLOWLINE= < 1064.070> FLOW PROCESS FROM NODE 3203.94 TO NODE 3211.10 IS CODE = 5 UPSTREAM NODE 3211.10 ELEVATION = 1064.17 (FLOW IS AT CRITICAL DEPTH) ------------------------------------------------------------------------------ CALCULATE JUNCTION LOSSES: PIPE FLOW DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY (CFS) (INCHES) (DEGREES) ELEVATION DEPTH(FT.) (FT/SEC) UPSTREAM 221.30 60.00 .00 1064.17 4.22 11.270 DOWNSTREAM 275.20 60.00 - 1064.07 4.56 14.630 LATERAL #1 1.60 30.00 45.00 1064.17 .41 .326 LATERAL #2 52.30 24.00 60.00 1064.17 1.98 16.648 Q5 .00===Q5 EQUALS BASIN INPUT=== LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: DY=(Q2*V2-Q1*V1*COS(DELTAI)-Q3*V3*COS(DELTA3)- Q4*V4*COS(DELTA4))/((Al+A2)*16.1)+FRICTION LOSSES UPSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00722 DOWNSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00973 Page 9 AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS .00847 JUNCTION LENGTH = 7.16 FEET FRICTION LOSSES = .061 FEET ENTRANCE LOSSES = .000 FEET JUNCTION LOSSES = (DY+HV1-HV2)+(ENTRANCE LOSSES) JUNCTION LOSSES = ( .481)+( .000) = .481 ------------------------------------------------------------------------------ NODE 3211.10 : HGL = < 1070.470>;EGL= < 1072.442>;FLOWLINE= < 1064.170> ie oY ie it it is i�ir is it it is ie is it it*ic ie is is it ie it is sY it ie it 4c it ie it it ie it ie it ie is is it ie is it is it ie ie is ie it ie is is ie***ie is is is ie it is is is is it ie is is it is ie is it FLOW PROCESS FROM NODE 3211.10 TO NODE 3272.58 IS CODE = 1 UPSTREAM NODE 3272.58 ELEVATION = 1065.00 (FLOW IS UNDER PRESSURE) ---------------------------------------------------- CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 221.30 CFS PIPE DIAMETER = 60.00 INCHES PIPE LENGTH = 61.48 FEET MANNING'S N = .01300 SF=(Q/K)**2 = (( 221.30)/( 2604.184))**2 = .00722 HF=L*SF = ( 61.48)*( .00722) = .444 ------------------------------------------------------------------------------ NODE 3272.58 : HGL = < 1070.914>;EGL= < 1072.886>;FLOWLINE= < 1065.000> is ir*ic is is is is it it sY is ir*ie it*ic it ie ie it is is it ie is is ie it it it**ic it it ie ie is is it s4 it is*ir is ie eY ie it it it fr ie it it*irir it it is it ie iric*ic it it it it it is is ie FLOW PROCESS FROM NODE 3272.58 TO NODE 3277.74 IS CODE = 5 UPSTREAM NODE 3277.74 ELEVATION = 1065.04 (FLOW IS UNDER PRESSURE) ------------------------------------------------------------------------------ CALCULATE JUNCTION LOSSES: PIPE FLOW DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY (CFS) (INCHES) (DEGREES) ELEVATION DEPTH(FT.) (FT/SEC) UPSTREAM 221.30 60.00 .00 1065.04 4.22 11.271 DOWNSTREAM 221.30 60.00 - 1065.00 4.22 11.271 LATERAL #1 .00 24.00 60.00 1065.04 .00 .000 LATERAL #2 .00 .00 .00 .00 .00 .000 Q5 .00===Q5 EQUALS BASIN INPUT=== LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: DY=(Q2*V2-Ql*V1*COS(DELTAI)-Q3*V3irCOS(DELTA3)- Q4*V4*COS(DELTA4))/((A1+A2)*16.1)+FRICTION LOSSES UPSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00722 DOWNSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00722 AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS .00722 JUNCTION LENGTH = 5.16 FEET FRICTION LOSSES = .037 FEET ENTRANCE LOSSES = .000 FEET JUNCTION LOSSES = (DY+HV1-HV2)+(ENTRANCE LOSSES) JUNCTION LOSSES = ( .037)+( .000) = .037 ------------------------------------------------------------------------------ NODE 3277.74 : HGL = < 1070.951>;EGL= < 1072.923>;FLOWLINE= < 1065.040> it it is*ic it is ie it is it i:ic:c Y it icir*it it is is is is it ie it it is*ir is is ie it it it it ie is it it it it is is x�**ic ie it it is*ic is it is is it it is it it is it it is it is it °k it is is is FLOW PROCESS FROM NODE 3277.74 TO NODE 3764.00 IS CODE = 1 UPSTREAM NODE 3764.00 ELEVATION = 1069.17 (FLOW IS UNDER PRESSURE) ------------------------------------------------------------------------------ CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 221.30 CFS PIPE DIAMETER = 60.00 INCHES PIPE LENGTH = 486.26 FEET MANNING'S N = .01300 SF=(Q/K)**2 = (( 221.30)/( 2604.451))**2 = .00722 HF=L*SF = ( 486.26)*( .00722) = 3.511 ----------------------------------------------------------------- NODE 3764.00 : HGL = < 1074.462>;EGL= < 1076.434>;FLOWLINE= < 1069.170> it is is Yc * it it * it is it is is it is is is icir ic.*ic is it it it ie is it it it icic it it is is it is iric is is is is is it is * it is is is is it is is is is it it is is it is is it it is it it it it is is is is it FLOW PROCESS FROM NODE 3764.00 TO NODE 3769.16 IS CODE = 5 UPSTREAM NODE 3769.16 ELEVATION = 1069.23 (FLOW IS UNDER PRESSURE) ---------------------------------------------------------- CALCULATE JUNCTION LOSSES: PIPE FLOW DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY (CFS) (INCHES) (DEGREES) ELEVATION DEPTH(FT.) (FT/SEC) Page 10 UPSTREAM 162.00 54.00 DOWNSTREAM 221.30 60.00 LATERAL #1 59.30 24.00 LATERAL #2 .00 .00 Q5 .00===Q5 EQUALS .00 1069.23 3.72 10.186 - 1069.17 4.22 11.271 45.00 1069.23 1.99 18.876 .00 .00 .00 .000 BASIN INPUT=== LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: DY=(Q2*v2-Ql*V1*COS(DELTAI)-Q3*V3*COS(DELTA3)- Q4*v4*coS(DELTA4))/((A1+A2)*16.1)+FRICTION LOSSES UPSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00679 DOWNSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00722 AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS .00700 JUNCTION LENGTH = 5.16 FEET FRICTION LOSSES = .036 FEET ENTRANCE LOSSES = .000 FEET ** CAUTION: TOTAL ENERGY LOSS COMPUTED USING (PRESSURE+MOMENTUM) IS NEGATIVE. COMPUTER CHOOSES ZERO ENERGY LOSS FOR TOTAL JUNCTION LOSS. ------------------------------------------------------------------------------ NODE 3769.16 : HGL = < 1074.823>;EGL= < 1076.434>;FLOWLINE= < 1069.230> is it it 4r*ic it it*ir*ic iris it it ie ie is it i:•k it it it it it it is it it it it it it it it it is it is is it it it*ie it it ie is is is**it ie it it it it it it***iris it is it it ie**ir itx FLOW PROCESS FROM NODE 3769.16 TO NODE 3833.29 IS CODE = 1 UPSTREAM NODE 3833.29 ELEVATION = 1069.92 (FLOW IS UNDER PRESSURE) ------------------------------------------------------------------------------ CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 162.00 CFS PIPE DIAMETER = 54.00 INCHES PIPE LENGTH = 64.13 FEET MANNING'S N .01300 SF=(Q/K)**2 = (( 162.00)/( 1966.576))**2 = .00679 HF=L*SF = ( 64.13)*( .00679) = .435 ------------------------------------------------------------------------------ NODE 3833.29 : HGL = < 1075.258>;EGL= < 1076.869>;FLOWLINE= < 1069.920> it*it °kit***'„•k�•ie*sY*. it it �-it is is*ir it*ic it it*ic it*it it it it sY it it it it*iris*it it it it sY it*ir it it it it it*ir ir°k it it it*ir •'..•ie*it is sY sY it it** FLOW PROCESS FROM NODE 3833.29 TO NODE 3833.29 IS CODE = 5 UPSTREAM NODE 3833.29 ELEVATION = 1069.92 (FLOW IS UNDER PRESSURE) ------------------------------------------------------------------------------ CALCULATE JUNCTION LOSSES: PIPE FLOW DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY (CFS) (INCHES) (DEGREES) ELEVATION DEPTH(FT.) (FT/SEC) UPSTREAM 162.00 54.00 .00 1069.92 3.72 10.186 DOWNSTREAM 162.00 54.00 - 1069.92 3.72 10.186 LATERAL #1 .00 24.00 45.00 1069.92 .00 .000 LATERAL #2 .00 .00 .00 .00 .00 .000 Q5 .00===Q5 EQUALS BASIN INPUT=== LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: DY=(Q2*V2-Ql*V1*COS(DELTAI)-Q3*V3*COS(DELTA3)- Q4*V4*COS(DELTA4))/((Al+A2)*16.1)+FRICTION LOSSES UPSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00679 DOWNSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00679 AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS .00679 JUNCTION LENGTH = 1.00 FEET FRICTION LOSSES = .007 FEET ENTRANCE LOSSES .000 FEET JUNCTION LOSSES = (DY+HV1-HV2)+(ENTRANCE LOSSES) JUNCTION LOSSES = ( .007)+( .000) = .007 NODE 3833.29 : HGL = < 1075.265>;EGL= < 1076.876>;FLOWLINE= < 1069.920> .. it it is*�•*ir*9: it*ir is is it ie *iris*ir****&**ici.•**ir it*ir it is it i;ir**�•*ir it it ir*ir*it ic°k sY it*it it is �•ir**it is is k *ir it it it it*ir FLOW PROCESS FROM NODE 3833.29 TO NODE 4034.03 IS CODE = 1 UPSTREAM NODE 4034.03 ELEVATION = 1072.02 (FLOW IS UNDER PRESSURE) ------------------------------------------------------------------------------ CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 162.00 CFS PIPE DIAMETER = 54.00 INCHES PIPE LENGTH = 200.74 FEET MANNING'S N = .01300 Page 11 SF=(Q/K)**2 = (( 162.00)/( 1966.504))**2 = .00679 HF=L*SF = ( ------------------------------------------------------------------------------ 200.74)*( .00679) = 1.362 NODE 4034.03 : HGL = < 1076.627>;EGL= < 1078.238>;FLOWLINE= < 1072.020> is is it is is is ie is it it it is it i� it ie it it it it is it is it is it is it it is is it it it it is is is it is is is it is is is it is is it it it is is it is is is it it ie it is it is it is is icic is it is is it is it it FLOW PROCESS FROM NODE 4034.03 TO NODE 4041.19 IS CODE = 5 UPSTREAM NODE ------------------------------------------------------------------------------ 4041.19 ELEVATION = 1072.05 (FLOW IS UNDER PRESSURE) CALCULATE JUNCTION LOSSES: PIPE FLOW DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY (CFS) (INCHES) (DEGREES) ELEVATION DEPTH(FT.) (FT/SEC) UPSTREAM 120.80 54.00 .00 1072.05 3.24 7.596 DOWNSTREAM 162.00 54.00 - 1072.02 3.72 10.186 LATERAL #1 41.20 24.00 45.00 1072.05 1.96 13.114 LATERAL #2 .00 .00 .00 .00 .00 .000 Q5 .00===Q5 EQUALS BASIN INPUT=== LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: DY=(Q2*V2-Q1*V1*COS(DELTAI)-Q3*V3*COS (DELTA3)- Q4*V4*COS(DELTA4))/((A1+A2)*16.1)+FRICTION LOSSES UPSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00377 DOWNSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00679 AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS .00528 JUNCTION LENGTH = 7.16 FEET FRICTION LOSSES = .038 FEET ENTRANCE LOSSES = .000 FEET JUNCTION LOSSES = (DY+HV1-HV2)+(ENTRANCE LOSSES) JUNCTION LOSSES = ( .007)+( .000) = .007 NODE 4041.19 : HGL = < 1077.350>;EGL= < 1078.245>;FLOWLINE= < 1072.050> is i:.* it is it it is it is is it it *ic is fc it it it it is it is is ie is is is is sY it it is is is is is it it it is is is * it it it it it it it it it * it it it it it is it it is * is it it ie is it is is is it it is is FLOW PROCESS FROM NODE 4041.19 TO NODE 4045.48 IS CODE = 1 UPSTREAM NODE 4045.48 ELEVATION = 1072.07 (FLOW IS UNDER ------------------------------------------------------------- PRESSURE) CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 120.80 CFS PIPE DIAMETER = 54.00 INCHES PIPE LENGTH = 4.29 FEET MANNING'S N = .01300 SF=(Q/K)**2 = (( 120.80)/( 1971.077))**2 = .00376 HF=L*SF = ( ------------------------------------------------------------------------------ 4.29)*( .00376) = .016 NODE 4045.48 : HGL = < 1077.366>;EGL= < 1078.262>;FLOWLINE= < 1072.070> •..•*ic it it i:ici: it is it is it it sY is ie is it is is it *ic it& it is is it it ie*ir is it it it is it it it*ie*ir it is is it ic-k it it it**it is it it it is is it is is*ic ie it is it ie ie it is is FLOW PROCESS FROM NODE 4045.48 TO NODE 4045.48 IS CODE = 5 UPSTREAM NODE ------------------------------------------------------------------------------ 4045.48 ELEVATION = 1072.07 (FLOW IS UNDER PRESSURE) CALCULATE JUNCTION LOSSES: PIPE FLOW DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY (CFS) (INCHES) (DEGREES) ELEVATION DEPTH(FT.) (FT/SEC) UPSTREAM 120.80 54.00 .00 1072.07 3.24 7.595 DOWNSTREAM 120.80 54.00 - 1072.07 3.24 7.595 LATERAL #1 .00 24.00 45.00 1072.07 .00 .000 LATERAL #2 .00 .00 .00 .00 .00 .000 Q5 .00===Q5 EQUALS BASIN INPUT=== LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: DY=(Q2*V2-Q1*V1*COS(DELTAI)-Q3*V3*COS (DE LTA3)- Q4*V4*COS(DELTA4))/((A1+A2)*16.1)+FRICTION LOSSES UPSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00377 DOWNSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00377 AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS .00377 JUNCTION LENGTH = 1.00 FEET FRICTION LOSSES = .004 FEET ENTRANCE LOSSES = .000 FEET JUNCTION LOSSES = (DY+HV1-HV2)+(ENTRANCE LOSSES) Page 12 JUNCTION LOSSES = ( .004)+( .000) = .004 ------------------------------------------------------------------------ NODE 4045.48 : HGL = < 1077.370>;EGL= < 1078.265>;FLOWLINE= < 1072.070> FLOW PROCESS FROM NODE 4045.48 TO NODE 4402.92 IS CODE = 1 UPSTREAM NODE 4402.92 ELEVATION = 1073.69 (FLOW IS UNDER PRESSURE) ------------------------------------------------------------------------------ CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 120.80 CFS PIPE DIAMETER = 54.00 INCHES PIPE LENGTH = 357.44 FEET MANNING'S N = .01300 SF=(Q/K)**2 = (( 120.80)/( 1966.448))**2 = .00377 HF=L*SF = (' 357.44)*( .00377) = 1.349 ------------------------------------------------------------------------------ NODE 4402.92 : HGL = < 1078.718>;EGL= < 1079.614>;FLOWLINE= < 1073.690> is irir ** is it sk it is it it ie is * it it ie it is ie it it :4 is it ie it is it it is is it ie it it ie ie it it it it is it it it ie'ie it is it is is it is it it it it ie ie is ie is ie it ie it it if is it it it * is is FLOW PROCESS FROM NODE 4402.92 TO NODE 4473.70 IS CODE = 3 UPSTREAM NODE 4473.70 ELEVATION = 1074.01 (FLOW IS UNDER PRESSURE) ------------------------------------------------------------------------------ CALCULATE PIPE -BEND LOSSES(OCEMA): PIPE FLOW = 120.80 CFS PIPE DIAMETER = 54.00 INCHES CENTRAL ANGLE = 90.000 DEGREES MANNING'S N = .01300 PIPE LENGTH = 70.78 FEET BEND COEFFICIENT(KB) = .25000 FLOW VELOCITY = 7.60 FEET/SEC. VELOCITY HEAD = .896 FEET HB=KB*(VELOCITY HEAD) = ( 250)*( .896) = .224 SF=(Q/K)**2 = (( 120.80)/( 1966.723))**2 = .00377 HF=L*SF = ( 70.78)*( .00377) = .267 TOTAL HEAD LOSSES = HB + HF = ( .224)+( .267) _ .491 ------------------------------------------------------------------------------ NODE 4473.70 : HGL = < 1079.209>;EGL= < 1080.105>;FLOWLINE= < 1074.010> it :': it it s4 ir'..•ir it *ir it 4c it it is is****i: it is it is it it sY is it is is is irir is is it it it it is it is it it ie is is it is it it*ir it it is it it is it is is is it is 4c it it it is it it it it it FLOW PROCESS FROM NODE 4473.70 TO NODE 4535.03 IS CODE = 1 UPSTREAM NODE 4535.03 ELEVATION = 1074.29 (FLOW IS UNDER PRESSURE) -------------------------------------------------------------------- CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 120.80 CFS PIPE DIAMETER = 54.00 INCHES PIPE LENGTH = 61.33 FEET MANNING'S N = .01300 SF=(Q/K)**2 = (( 120.80)/( 1966.433))**2 = .00377 HF=L*SF = ( 61.33)*( .00377) = .231 ------------------------------------------------------------------------------ NODE 4535.03 : HGL = < 1079.441>;EGL= < 1080.337>;FLOWLINE= < 1074.290> is it**ie *i.•i: k is it is is it is is*i: **ic*ir it is it it it'tt ie is is it is it it it it it is is it i; is is it it it is is is it*ir it k it is it it is it it is it ie it sY it is it xt is it**i: it FLOW PROCESS FROM NODE 4535.03 TO NODE 4540.19 IS CODE = 2 UPSTREAM NODE 4540.19 ELEVATION = 1074.31 (FLOW IS UNDER PRESSURE) ------------------------------------------------------------------------------ CALCULATE MANHOLE LOSSES(LACFCD): PIPE FLOW = 120.80 CFS PIPE DIAMETER = 54.00 INCHES FLOW VELOCITY = 7.60 FEET/SEC. VELOCITY HEAD = .896 FEET HMN = .05*(VELOCITY HEAD) = .05*( .896) = .045 ------------------------------------------------------------------------------ NODE 4540.19 HGL = < 1079.486>;EGL= < 1080.381>;FLOWLINE= < 1074.310> i:i:*ir irir ic:Y it ie*ir it :r*ir«irsY is i:**k is*ir*sY it**'r ie is it sY it ie it*ic it**�'*ir*ir is it is is ie it ie it***it sY is is**ic it it it it *�k is*i: is FLOW PROCESS FROM NODE 4540.19 TO NODE 5035.03 IS CODE = 1 UPSTREAM NODE 5035.03 ELEVATION = 1076.55 (FLOW IS UNDER PRESSURE) ------------------------------------------------------------------------------ CALCULATE FRICTION LOSSES(LACFCD); PIPE FLOW = 120.80 CFS PIPE DIAMETER = 54.00 INCHES PIPE LENGTH = 494.84 FEET MANNING'S N = .01300 SF=(Q/K)**2 = (( 120.80)/( 1966.487))**2 = .00377 HF=L*SF = ( 494.84)*( .00377) = 1.867 ------------------------------------------------------------------------------ Page 13 NODE 5035.03 : HGL = < 1081.353>;EGL= < 1082.249>;FLOWLINE= < 1076.550> it ie it it 4c is it ie it it is is is ie is * it is ie is it ie is it is is it ie. is it it ie & it is it it ie it ie ie is ie ie is it it ie it is is it ie ie it ie it is is is it is is it is it is is is is is ie is * �Y ie is it FLOW PROCESS FROM NODE 5035.03 TO NODE 5040.19 IS CODE = 2 UPSTREAM NODE 5040.19 ELEVATION = 1076.57 (FLOW IS UNDER PRESSURE) -------------------------------------------------------------- CALCULATE MANHOLE LOSSES(LACFCD): PIPE FLOW = 120.80 CFS PIPE DIAMETER = 54.00 INCHES FLOW VELOCITY = 7.60 FEET/SEC. VELOCITY HEAD = .896 FEET HMN = .05*(VELOCITY HEAD) = .05*( .896) = .045 ----------------------------------------- ------------------------- NODE 5040.19 : HGL = < 1081.398>;EGL= < 1082.294>;FLOWLINE= < 1076.570> it is is Yc it ie it is it is is it is it it it it is it is iric it iF it ir'k it k it it it it it it ie sY ie is is it is it it ir'& is is it is is it it it is ie it is is is it it ie iF it it is it is it Yc it is irie is it is FLOW PROCESS FROM NODE 5040.19 TO NODE 5535.03 IS CODE = 1 UPSTREAM NODE 5535.03 ELEVATION = 1078.81 (FLOW SEALS IN REACH) -- ------------------------------------------------------------ CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 120.80 CFS PIPE DIAMETER = 54.00 INCHES PIPE LENGTH = 494.84 FEET MANNING'S N = .01300 DOWNSTREAM CONTROL ASSUMED PRESSURE HEAD(FT) = 4.83 PRESSURE FLOW PROFILE COMPUTED INFORMATION: ------------------------------------------------------------------------------ DISTANCE FROM PRESSURE VELOCITY SPECIFIC PRESSURE+ CONTROL(FT) HEAD(FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUNDS) .000 4.828 7.595 5.724 4336.34 435.068 4.500 7.595 5.396 4011.03 -----------------------------------------------_----------------- NORMAL DEPTH(FT) = 3.38 CRITICAL DEPTH(FT) - 3.24 ASSUMED DOWNSTREAM PRESSURE HEAD(FT) = 4.50 GRADUALLY VARIED FLOW PROFILE COMPUTED INFORMATION: ----------------------------------=------------------------- DISTANCE FROM FLOW DEPTH VELOCITY SPECIFIC PRESSURE+ CONTROL(FT) (FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUNDS) 435.068 4.500 7.593 5.396 4011.03 479.983 4.455 7.606 5.354 3969.54 494.840 4.436 7.615 5.337 3953.10 --------------------------------------------------------------------- NODE 5535.03 : HGL = < 1083.246>;EGL= < 1084.147>;FLOWLINE= < 1078.810> it it ic****ir ie*ir it*::'.r .r**#ir ie �-**ic it ie it it :Fir*ir it s4 ie**ic is*ir**ic iF it it is i.•i:*ir it it it*4r***ie it is**ic is it is it*ir*ic�ie ie FLOW PROCESS FROM NODE 5535.03 TO NODE 5540.19 IS CODE = 2 -_UPSTREAM NODE 5540.19 ELEVATION = 1078.83 (FLOW IS SUBCRITICAL) -------------------------------------------------------------------- CALCULATE MANHOLE LOSSES(LACFCD): PIPE FLOW = 120.80 CFS PIPE DIAMETER = 54.00 INCHES AVERAGED VELOCITY HEAD = .899 FEET HMN = .05*(AVERAGED VELOCITY HEAD) = .05*( .899) _ .045 -------------------------------------------------------------------------- NODE 5540.19 : HGL = < 1083.294>;EGL= < 1084.192>;FLOWLINE= < 1078.830> R•ir**-k�:ic:Fic**ft*i:*k4r is is it is is is sY it is it is it it is i;ic*�•ic it iF it sY is sY*ir it it ilic it it ic'.t it it it it*ic*ir*ic is it*ic ie is*itit it it �•i: k is FLOW PROCESS FROM NODE 5540.19 TO NODE 5542.24 IS CODE = 1 UPSTREAM NODE 5542.24 ELEVATION = 1078.84 (FLOW IS SUBCRITICAL) ------------------------------------------------------------------------------ CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 120.80 CFS PIPE DIAMETER = 54.00 INCHES PIPE LENGTH = 2.05 FEET MANNING'S N = .01300 -------------------------------------------------_----------------- NORMAL DEPTH(FT) = 3.27 CRITICAL DEPTH(FT) - 3.24 Page 14 DOWNSTREAM CONTROL ASSUMED FLOWDEPTH(FT) = 4.46 GRADUALLY VARIED FLOW PROFILE COMPUTED INFORMATION: ------------------------------------------------------------------------------ DISTANCE FROM FLOW DEPTH VELOCITY SPECIFIC PRESSURE+ CONTROL(FT) (FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUNDS) .000 4.465 7.602 5.362 3977.93 2.050 4.461 7.603 5.359 3974.93 ------------------------------------------------------------------------------ NODE 5542.24 : HGL = < 1083.301>;EGL= < 1084.199>;FLOWLINE= < 1078.840> it it 4c-ic s4 �t ie is is is sY sY'.c is ie 4t4ric ir�i: is it stir is is it 4t is is is is is it it 4r it Y ic+Y ie dt it it ie ie ie �c Yt Yc it sY 4e is stir fc ic:t it it ic�Yr is is Y is is do it ie Y is is �Y Yr FLOW PROCESS FROM NODE 5542.24 TO NODE 5577.58 IS CODE = 3 UPSTREAM NODE 5577.58 ELEVATION = 1079.00 (FLOW IS SUBCRITICAL) -- ------------------------------------------------------------------------ CALCULATE PIPE -BEND LOSSES(OCEMA): PIPE FLOW = 120.80 CFS PIPE DIAMETER = 54.00 INCHES CENTRAL ANGLE = 90.000 DEGREES MANNING'S N = .01300 PIPE LENGTH = 35.34 FEET ------------------------------------------------------------------- NORMAL DEPTH(FT) = 3.38 CRITICAL DEPTH(FT) = 3.24 DOWNSTREAM CONTROL ASSUMED FLOWDEPTH(FT) = 4.46 GRADUALLY VARIED FLOW PROFILE COMPUTED INFORMATION: ------------------------------------------------------------------------------ DISTANCE FROM FLOW DEPTH VELOCITY SPECIFIC PRESSURE+ CONTROL(FT) (FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUNDS) .000 4.461 7.603 5.359 3974.93 35.137 4.418 7.625 5.321 3937.07 35.340 4.418 7.625 5.321 3936.83 ------------------------------------------------------------ NODE 5577.58 : HGL = < 1083.418>;EGL= < 1084.321>;FLOWLINE= < 1079.000> :ci: 4ek��•:r ic�:t 4c is i::t 4t is it it k it fc is 4r*ic ickk�: is 4t ie is is 4c it it�it is 4r ir4t sY*ic���ir ick�it�ie is fc ir�ir is is ic�it is it is it sY ic�ic it': is :e UPSTREAM PIPE FLOW CONTROL DATA: NODE NUMBER = 5577.58 FLOWLINE ELEVATION = 1079.00 ASSUMED UPSTREAM CONTROL HGL = 1082.24 FOR DOWNSTREAM RUN ANALYSIS END OF GRADUALLY VARIED FLOW ANALYSIS Page 15 is it is is ie ie ie ieie is it is it is is it is it it is ie it is ie it it is it is it is ie is is is is ie ie it it ie is it it is is is is it is ie is ie it it ie is ie is ie it it ie is it *.ic it is ie ie ie ie is is iric is PIPE -FLOW HYDRAULICS COMPUTER PROGRAM PACKAGE (Reference: LACFCD,LACRD, AND OCEMA HYDRAULICS CRITERION) (c) Copyright 1982-93 Advanced Engineering software (aes) Ver. 4.6A Release Date: 7/18/93 License ID 1202 Analysis prepared by: HUITT-ZOLLARS, INC. 15101 RED HILL AVENUE TUSTIN, CALIFORNIA 92780-6500 PHONE (714) 259-7900 * FAX (714) 259-0210 ie ir'.c it it it is is it it it is sY it is is is is it*;r it it ie it is DESCRIPTION OF STUDY ******ir it it ie it is it it is it it is ie is it is is ie it is it SIERRA BUSINESS PARK STORM DRAIN LINE H 'c 100-YEAR HYDRAULIC ANALYSIS it is irir it it ie it ie ie ie ie ie it ie is is is is is it is is it it ie ie ie sY is it it it ie it ie is it is it is it is is is is is it ie is is it it ie ie ie. is it it is ie is ie ie it sY ie it is it is it is is it ------------------------------------------------.------------------------------ FILE NAME: SBPLINEH.HGL TIME/DATE OF STUDY: 8:16 6/17/2004 .. is is R-�-**ic is �ir is is is is is it it*ir**ir*it*ie is it is*ici:*ic it is i�sY is it is is it it it is it***.***it ic'k is it*ir it is is k it it is 4c it °k is**ic is it it GRADUALLY VARIED FLOW ANALYSIS FOR PIPE SYSTEM NODAL POINT STATUS TABLE ��� (Note: indicates nodal point data used.) UPSTREAM RUN DOWNSTREAM RUN NODE MODEL PRESSURE PRESSURE+ FLOW PRESSURE+ NUMBER PROCESS HEAD(FT) MOMENTUM(POUNDS) DEPTH(FT) MOMENTUM(POUNDS) .00- 13.20* 11887.18 2.12 2617.90 1 FRICTION 72.77- 12.58* 11269.41 2.12 2617.22 1 FRICTION+BEND 166.05- 11.87* 10567.57 2.12 2615.28 1 FRICTION 175.31- 11.79* 10488.25 2.12 2614.65 1 FRICTION+BEND 210.65- 11.57* 10270.61 2.12 2617.92 1 FRICTION 243.90- 11.28* 9984.79 2.12 2615.76 1 FRICTION+BEND 261.57- 11.21* 9907.75 2.12 2614.93 1 FRICTION 1063.20- 4.35* 3112.59 2.21 2543.90 1 FRICTION+BEND 1133.89- 3.53* 2542.68 2.33 2467.39 1 FRICTION 1 HYDRAULIC JUMP 1186.66- 2.81*Dc 2348.72 2.81*Dc 2348.72 1 JUNCTION 1186.66- 3.62* 2022.77 2.25 1661.15 1 FRICTION 1 HYDRAULIC JUMP 1733.59- 2.49 DC 1638.00 2.38* 1643.01 1 FRICTION+BEND 1804.29- 2.49 DC 1638.00 2.39* 1642.17 1 FRICTION 1980.58- 2.49*Dc 1638.00 2.49*Dc 1638.00 1 JUNCTION 1980.58- 3.15* 1699.43 2.50 DC 1567.93 1 FRICTION 2112.44- 2.94* 1632.16 2.50 DC 1567.93 1 JUNCTION 2112.44- 3.57* 1737.31 2.36 DC 1345.80 Page 1 I FRICTION 2312.44- 3.05* 1488.22 2.36 DC 1345.80 1 JUNCTION 2312.44- 3.53* 1566.75 2.15 1129.48 1 FRICTION 2512.44- 2.85* 1248.01 2.20 DC 1128.68 1 JUNCTION 2512.44- 3.12* 1205.93 2.12 DC 965.02 1 FRICTION 2712.44- 2.88* 1109.01 2.12 DC 965.02 1 JUNCTION 2712.44- 3.37* 1161.82 1.92 DC 746.31 1 FRICTION 2912.44- 2.91* 960.33 1.92 DC 746.31 1 JUNCTION 2912.44- 3.29* 995.88 1.64 541.00 1 FRICTION 3112.44- 2.56* 700.75 1.69 DC 540.29 1 JUNCTION 3112.44- 2.91* 726.70 1.35 348.42 1 FRICTION 3312.44- 1.97* 414.87 1.42 DC 347.03 1 CATCH BASIN 3312.44- 2.26* 312.04 1.42 DC 122.55 MAXIMUM NUMBER OF ENERGY BALANCES ------------------------------------------------------------------------------ -------------------------------------- USED IN EACH PROFILE = 25 NOTE: STEADY FLOW HYDRAULIC HEAD -LOSS COMPUTATIONS BASED ON THE MOST CONSERVATIVE FORMULAE FROM THE CURRENT LACRD,LACFCD, AND OCEMA DESIGN MANUALS. it fc::'.eR•4t'c*i.•.'.c ie it it it it l:i:4.•'.•�•k 9r irk':*:r it ir'r it it**4 it k fr 4c**4r is Pc it ir:r�'.ric'.rdc*9e is it ir:r*4r it it �r 4r:c*.*ir it :r it it 4r it it :c ir* DOWNSTREAM PIPE FLOW CONTROL DATA: NODE NUMBER = .00 FLOWLINE ELEVATION = 1039.50 PIPE FLOW = 91.50 CFS PIPE DIAMETER = 54.00 INCHES ASSUMED DOWNSTREAM CONTROL HGL = ------------------------------------------------------------------------------ 1052.700 NODE .00 : HGL = < 1052.700>;EGL= < 1053.214>;FLOWLINE= < 1039.500> i:i:i:iti: iY ici: is it*�Yr'.: is 9c***ir it Yr is ic:r 4r it it it is is*Yr Yr is f: it it 4r is 4r it*ir �c*:Y is is is it**ic is it 4c**ic sY is ie ie it it 4e 4r it is it****Y*ic FLOW PROCESS FROM NODE .00 TO NODE 72.77 IS CODE = 1 UPSTREAM NODE 72.77 ELEVATION ------------------------------------------------------------------------------ = 1040.28 (FLOW IS UNDER PRESSURE) CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 91.50 CFS PIPE DIAMETER = 54.00 INCHES PIPE LENGTH = 72.77 FEET MANNING'S N = .01300 SF=(Q/K)**2 = (( 91.50)/( 1966.207))**2 = .00217 HF=L*SF = ( 72.77)*( .00217) = ------------------------------------------------------------------------------ .158 NODE 72.77 : HGL = < 1052.858>;EGL= < 1053.371>;FLOWLINE= < 1040.280> �'r:'r?r4:*':'.ri:*:c«•ic it*ic:.•**sY**4rs::c%:*:c*'x �c is*ic***:cir*.*ir it it �'r****�^4cYe Y:ir 4r*ir is �Y**ie**i: :: it *k :r is 4c 4c 4c 4e it :r ic* FLOW PROCESS FROM NODE 72.77 TO NODE 166.05 IS CODE = 3 UPSTREAM NODE 166.05 ELEVATION = 1041.28 (FLOW IS UNDER PRESSURE) ------------------------------------------------------------------------------ CALCULATE PIPE -BEND LOSSES(OCEMA): PIPE FLOW = 91.50 CFS PIPE DIAMETER = 54.00 INCHES CENTRAL ANGLE = 45.000 DEGREES MANNING'S N = .01300 PIPE LENGTH = 93.28 FEET BEND COEFFICIENT(KB) = .17678 FLOW VELOCITY = 5.75 FEET/SEC. VELOCITY HEAD = .514 FEET HB=KB*(VELOCITY HEAD) = ( .177)*( .514) = .091 SF=(Q/K)**2 = (( 91.50)/( 1966.368))**2 = .00217 HF=L*SF = ( 93.28)*( .00217) = .202 TOTAL HEAD LOSSES = HB + HF = ( .091)+( .202) _ .293 ------------------------------------------------------------------------------ NODE 166.05 : HGL = < 1053.150>;EGL= < 1053.664>;FLOWLINE= < 1041.280> Page 2 ick kkir it ie irk ickkkkkki�k ie is irkkkkkkkkkkkk�'e*it**.k*ir.lei•***ic*.1..ir**ic it***,Y,{r*,h it it it it ie it it it it it ie it it ie is ie 4t FLOW PROCESS FROM NODE 166.05 TO NODE 175.31 IS CODE = 1 --UPSTREAM NODE 175.31 ' ELEVATION = 1041.38 (FLOW IS UNDER PRESSURE) ------------------------------------------------------------- CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 91.50 CFS PIPE DIAMETER = 54.00 INCHES PIPE LENGTH = 9.26 FEET MANNING'S N = .01300 SF=(Q/K)**2 = (( 91.50)/( 1967.885))**2 = .00216 HF=L*SF = ( 9.26)*( .00216) = .020 ----------------------------------------------------- -------------- NODE 175.31 : HGL = < 1053.170>;EGL= < 1053.684>;FLOWLINE= < 1041.380> itkkkkiskkkkkkkir ickkirk kit ick itkkkkkkkkkkie itkkkkkkkkkkkkkkkkkkkisk ki; kick kickkkkkic irk it kirkkk FLOW PROCESS FROM NODE 175.31 TO NODE 210.65 IS CODE = 3 --UPSTREAM NODE 210.65 ELEVATION = 1041.75 (FLOW IS UNDER PRESSURE) ---------------------------------------------------------------- CALCULATE PIPE -BEND LOSSES(OCEMA): PIPE FLOW = 91.50 CFS PIPE DIAMETER = 54.00 INCHES CENTRAL ANGLE = 30.000 DEGREES MANNING'S N = .01300 PIPE LENGTH = 35.34 FEET BEND COEFFICIENT(KB) = .14434 FLOW VELOCITY = 5.75 FEET/SEC. VELOCITY HEAD = .514 FEET HB=KB*(VELOCITY HEAD) = ( 144)*( .514) = .074 SF=(Q/K)**2 = (( 91.50)/( 1967.182))**2 = .00216 HF=L*SF = ( 35.34)*( .00216) = .076 TOTAL HEAD LOSSES = HB + HF = ( .074)+( .076) _ .151 NODE 210.65 : HGL = < 1053.321>;EGL= < 1053.835>;FLOWLINE= < 1041.750> k kkk*kkkkkkkkkkkkk*�;kkkkkkkkkkkitkkir itkkkkkk:Ykkkkkk$rkkkkiekkkirkkkickkkkkkkkkkiskkkk FLOW PROCESS FROM NODE 210.65 TO NODE 243.90 IS CODE = 1 UPSTREAM NODE 243.90 ELEVATION = 1042.11 (FLOW IS UNDER PRESSURE) -------------------------------------------------------------------------- CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 91.50 CFS PIPE DIAMETER = 54.00 INCHES PIPE LENGTH = 33.25 FEET MANNING'S N = .01300 SF=(Q/K)**2 = (( 91.50)/( 1966.011))**2 = .00217 HF=L*SF = ( 33.25)*( .00217) = .072 -------------------------------------------------------------- NODE 243.90 : HGL = < 1053.393>;EGL= < 1053.907>;FLOWLINE= < 1042.110> �i.•kkkkkkkirkkkkkk*kki:kk*kkkkkkkkkkkkk�.r�•kkk �-ic is it ie**irir it*it*it it it "***i: it is*i:**ic it irk*ir it it*�• FLOW PROCESS FROM NODE 243.90 TO NODE 261.57 IS CODE = 3 --UPSTREAM NODE 261.57 ELEVATION = 1042.30 (FLOW IS UNDER PRESSURE) --------------------------------------------------------------- CALCULATE PIPE -BEND LOSSES(OCEMA): PIPE FLOW = 91.50 CFS PIPE DIAMETER = 54.00 INCHES CENTRAL ANGLE = 30.000 DEGREES MANNING'S N = .01300 PIPE LENGTH = 17.67 FEET BEND COEFFICIENT(KB) = .14434 FLOW VELOCITY = 5.75 FEET/SEC. VELOCITY HEAD = .514 FEET HB=KB*(VELOCITY HEAD) = ( 144)*( .514) = .074 SF=(Q/K)**2 = (( 91.50)/( 1966.651))**2 = .00216 HF=L*SF = ( 17.67)*( .00216) = .038 TOTAL HEAD LOSSES = HB + HF = ( .074)+( .038) _ .112 ---------------------------------------------------------------------- NODE 261.57 : HGL = < 1053.505>;EGL= < 1054.019>;FLOWLINE= < 1042.300> kk�•ici; it irkkkk �•k kkkkkkkir*irkkkkkkkkkk*kit it itkkkkkic kirkk kkkkkkkkkkkkit k irk kirk kirk kkkkkirkk FLOW PROCESS FROM NODE 261.57 TO NODE 1063.20 IS CODE = 1 UPSTREAM NODE 1063.20 ELEVATION = 1050.88 (FLOW SEALS IN REACH) -- -------------------------------------------------------------------- CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 91.50 CFS PIPE DIAMETER = 54.00 INCHES PIPE LENGTH = 801.63 FEET MANNING'S N = .01300 Page 3 DOWNSTREAM CONTROL ASSUMED PRESSURE HEAD(FT) = 11.21 PRESSURE FLOW ------------------------------------------------------------------------------ PROFILE COMPUTED INFORMATION: DISTANCE FROM PRESSURE VELOCITY SPECIFIC PRESSURE+ CONTROL(FT) HEAD(FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUNDS) .000 11.205 5.753 11.719 9907.75 785.348 ------------------------------------------------------------------------------ 4.500 5.753 5.014 3253.10 NORMAL DEPTH(FT) = 2.12 CRITICAL DEPTH(FT) = 2.81 ASSUMED DOWNSTREAM PRESSURE HEAD(FT) 4.50 ------------------------------------------------------------------------- GRADUALLY VARIED FLOW PROFILE COMPUTED INFORMATION: DISTANCE FROM ----------------------------------------- FLOW DEPTH VELOCITY SPECIFIC PRESSURE+ CONTROL(FT) (FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUNDS) 785.348 4.500 5.751 5.014 3253.10 792.808 4.432 5.769 4.949 3189.12 799.857 4.364 5.802 4.888 3128.11 801.630 ------------------------------------------------------------------------------ 4.347 5.813 4.872 3112.59 NODE 1063.20 : HGL = < 1055.227>;EGL= < 1055.752>;FLOWLINE= < 1050.880> f: lr it �c�4c it tY �Y k9r ir;r it it 4 it 4r 4t it dt ie&ir is �'t 4t it it it Y it 4r it 4r it it it is ie �r it is is 4r 4r 4r Yr 4r it 4e it it it it it4r is is it it Yr ': i:4r is is sY it Yr 4 it it sY it it fir. it FLOW PROCESS FROM NODE 1063.20 TO NODE 1133.89 IS CODE = 3 UPSTREAM NODE ------------------------------------------------------------------------------ 1133.89 ELEVATION = 1051.64 (FLOW IS SUBCRITICAL) CALCULATE PIPE -BEND LOSSES(OCEMA): PIPE FLOW = 91.50 CFS PIPE DIAMETER = 54.00 INCHES CENTRAL ANGLE = 90.000 DEGREES MANNING'S N = .01300 PIPE LENGTH = 70.69 FEET NORMAL DEPTH(FT) = 2.11 CRITICAL DEPTH(FT) = 2.81 --------------------------------------------------------------------- DOWNSTREAM CONTROL ASSUMED FLOWDEPTH(FT) = 4.35 ----------------------------------------------------------------- GRADUALLY VARIED FLOW PROFILE COMPUTED INFORMATION: --------------------------------------------------------------------- DISTANCE FROM FLOW DEPTH VELOCITY SPECIFIC PRESSURE+ CONTROL(FT) (FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUNDS) .000 4.347 5.813 4.872 3112.59 6.118 4.285 5.854 4.818 3059.51 12.083 4.224 5.901 4.765 3008.07 17.911 4.162 5.955 4.713 2958.24 23.612 4.100 6.014 4.662 2910.01 29.191 4.039 6.080 4.613 2863.39 34.650 3.977 6.150 4.565 2818.40 39.991 3.915 6.227 4.518 2775.07 45.210 3.854 6.309 4.472 2733.45 50.304 3.792 6.396 4.428 2693.58 55.268 3.730 6.489 4.385 2655.50 60.094 3.669 6.588 4.343 2619.27 64.774 3.607 6.694 4.303 2584.95 69.296 3.545 6.805 4.265 2552.61 70.690 3.526 6.842 4.253 2542.68 NODE 1133.89 : HGL = < 1055.166>;EGL= < 1055.893>;FLOWLINE= < 1051.640> i:�4: �4c',:tr it �k ir��4r�ie�&�:r die it kir 4r�ir it it sY'..•Y��4r k ic:r ir�zt ie 4r it ir:rir.�•dr �ic:r��it'r is&«�k�ic'..•�•&'.e�oY �: klr 4r'x�iri:'r FLOW PROCESS FROM NODE 1133.89 TO NODE 1186.66 IS CODE = 1 UPSTREAM NODE 1186.66 ELEVATION = 1052.20 (HYDRAULIC JUMP OCCURS) -------------------------------------------------------- CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 91.50 CFS PIPE DIAMETER = 54.00 INCHES Page 4 PIPE LENGTH = ------------------------------------------------------------------------------ 52.77 FEET MANNING'S N = .01300 HYDRAULIC JUMP: DOWNSTREAM RUN ANALYSIS RESULTS ------------------------------------------------------------------------------ NORMAL DEPTH(FT) = 2.12 CRITICAL DEPTH(FT) = 2.81 UPSTREAM CONTROL ASSUMED FLOWDEPTH(FT) 2.81 ------------------------------------------------------------------------ GRADUALLY VARIED ------------------------------------------------------------------------------ FLOW PROFILE COMPUTED INFORMATION: DISTANCE FROM FLOW DEPTH VELOCITY SPECIFIC PRESSURE+ CONTROL(FT) (FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUNDS) .000 2.806 8.772 4.001 2348.72 .084 2.778 8.874 4.002 2349.05 .344 2.751 8.979 4.004 2350.08 .799 2.724 9.086 4.006 2351.80 1.468 2.696 9.196 4.010 2354.25 2.371 2.669 9.309 4.015 2357.43 3.535 2.641 9.426 4.022 2361.37 4.989 2.614 9.545 4.030 2366.09 6.768 2.587 9.668 4.039 2371.60 8.913 2.559 9.794 4.050 2377.94 11.474 2.532 9.924 4.062 2385.11 14.508 2.504 10.058 4.076 2393.15 18.090 2.477 10.195 4.092 2402.08 22.308 2.450 10.337 4.110 2411.93 27.277 2.422 10.482 4.129 2422.72 33.143 2.395 10.632 4.151 2434.48 40.099 2.367 10.786 4.175 2447.25 48.405 2.340 10.945 4.201 2461.05 52.770 2.328 11.016 4.214 2467.39 ------------------------------------------------------------------------------ HYDRAULIC JUMP: UPSTREAM RUN ANALYSIS RESULTS ------------------------------------------------------------------------------ ------------------------------------------------------------------------------ DOWNSTREAM CONTROL ASSUMED FLOWDEPTH(FT) = 3.53 ---------------------------------------------------------------------- GRADUALLY VARIED ------------------------------------------------------------------------------ FLOW PROFILE COMPUTED INFORMATION: DISTANCE FROM FLOW DEPTH VELOCITY SPECIFIC PRESSURE+ CONTROL(FT) (FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUNDS) .000 3.526 6.842 4.253 2542.68 2.064 3.497 6.898 4.236 2528.58 4.087 3.468 6.955 4.220 2514.93 6.069 3.439 7.013 4.203 2501.74 8.007 3.411 7.073 4.188 2489.03 9.898 3.382 7.134 4.173 2476.81 11.742 3.353 7.198 4.158 2465.07 13.535 3.324 7.262 4.144 2453.83 15.275 3.295 7.329 4.130 2443.09 16.959 3.267 7.397 4.117 2432.88 18.584 3.238 7.467 4.104 2423.19 20.147 3.209 7.539 4.092 2414.03 21.644 3.180 7.613 4.081 2405.43 23.070 3.151 7.689 4.070 2397.38 24.423 3.123 7.766 4.060 2389.89 25.696 3.094 7.846 4.050 2382.99 26.886 3.065 7.928 4.042 2376.68 27.985 3.036 8.012 4.034 2370.97 28.989 3.007 8.099 4.026 2365.88 29.889 2.979 8.187 4.020 2361.42 30.679 2.950 8.278 4.015 2357.61 31.349 2.921 8.372 4.010 2354.45 31.891 2.892 8.468 4.006 2351.97 32.294 2.863 8.567 4.004 2350.17 32.546 2.835 8.668 4.002 2349.08 Page 5 32.633 2.806 8.772 4.001 2348.72 52.770 2.806 8.772 4.001 2348.72 ------------------------END OF HYDRAULIC JUMP ANALYSIS------------------------ PRESSURE+MOMENTUM BALANCE OCCURS AT 15.42 FEET UPSTREAM OF NODE 1133.89 DOWNSTREAM DEPTH = 3.293 FEET, UPSTREAM CONJUGATE DEPTH = 2.378 FEET ------------------------------------------------------------------------------ NODE 1186.66 : HGL = < 1055.006>;EGL= < 1056.201>;FLOWLINE= < 1052.200> icieicir*iriciesY*iricic*iriric*iriricicieicirieicicirieiciriricieieiciciricirieitieirieitiriciticsYicicieicirieiririeicirieicir*iriricic*ieieiciricir FLOW PROCESS FROM NODE 1186.66 TO NODE 1186.66 IS CODE = 5 UPSTREAM NODE 1186.66 ELEVATION = 1052.20 (FLOW IS AT CRITICAL DEPTH) ------------------------------------------------------------------------------ CALCULATE JUNCTION LOSSES: PIPE FLOW DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY (CFS) (INCHES) (DEGREES) ELEVATION DEPTH(FT.) (FT/SEC) UPSTREAM 67.80 48.00 .00 1052.20 2.49 5.665 DOWNSTREAM 91.50 54.00 - 1052.20 2.81 8.775 LATERAL #1 23.70 24.00 45.00 1052.20 1.73 7.544 LATERAL #2 .00 .00 .00 .00 .00 .000 Q5 .00===Q5 EQUALS BASIN INPUT=== LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: DY=(Q2*V2-Q1*V1*COS(DELTAI)-Q3*V3 *COS (DELTA3)- Q4*V4*COS(DELTA4))/((A1+A2)*16.1)+FRICTION LOSSES UPSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00195 DOWNSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00427 AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS .00311 JUNCTION LENGTH = 1.00 FEET FRICTION LOSSES = .003 FEET ENTRANCE LOSSES = .000 FEET JUNCTION LOSSES = (DY+HV1- HV2) +(ENTRANCE LOSSES) JUNCTION LOSSES = ( .120)+( .000) = .120 ------------------------------------------------------------------------------ NODE 1186.66 : HGL = < 1055.823>;EGL= < 1056.321>;FLOWLINE= < 1052.200> it it it it it it it is is is is * it it it is it it it it is it it it it it is ie it is ie is is it ie ie is is it it is it it it it it sY it icir is it is is it is it it it it * is ie it is ie it is it ie ie it is is it it it i� FLOW PROCESS FROM NODE 1186.66 TO NODE 1733.59 IS CODE = 1 UPSTREAM NODE 1733.59 ELEVATION = 1055.50 (HYDRAULIC JUMP OCCURS) ------------------------------------------------------------------ CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 67.80 CFS PIPE DIAMETER = 48.00 INCHES PIPE LENGTH = 546.93 FEET MANNING'S N = .01300 ------------------------------------------------------------------------------ HYDRAULIC JUMP: DOWNSTREAM RUN ANALYSIS RESULTS ------------------------------------------------------------------------------ NORMAL DEPTH(FT) ------------------------------------------------------------------------------ = 2.25 CRITICAL DEPTH(FT) = 2.49 ------------------------------------------------------------------------------ UPSTREAM CONTROL ------------------------------------------------------------------------------ ASSUMED FLOWDEPTH(FT) = 2.38 ------------------------------------------------------------------------------ GRADUALLY VARIED FLOW PROFILE COMPUTED INFORMATION: ------------------------------------------------------------------------------ DISTANCE FROM FLOW DEPTH VELOCITY SPECIFIC PRESSURE+ CONTROL(FT) (FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUNDS) .000 2.377 8.711 3.556 1643.01 1.056 2.372 8.733 3.557 1643.49 2.207 2.367 8.755 3.558 1643.99 3.460 2.362 8.778 3.559 1644.51 4.826 2.357 8.800 3.560 1645.05 6.315 2.351 8.823 3.561 1645.62 7.939 2.346 8.846 3.562 1646.21 9.714 2.341 8.869 3.564 1646.82 11.658 2.336 8.892 3.565 1647.46 13.789 2.331 8.915 3.566 1648.12 16.133 2.326 8.939 3.568 1648.81 18.719 2.321 8.962 3.569 1649.51 21.582 2.316 8.986 3.571 1650.25 Page 6 24.769 2.311 9.009 3.572 1651.00 28.333 2.306 9.033 3.574 1651.78 32.349 2.301 9.057 3.576 1652.58 36.912 2.296 9.081 3.578 1653.41 42.149 2.291 9.106 3.579 1654.26 48.243 2.286 9.130 3.581 1655.14 55.458 2.281 9.155 3.583 1656.04 64.205 2.276 9.180 3.585 1656.97 75.171 2.271 9.204 3.587 1657.92 89.648 2.266 9.229 3.589 1658.90 110.533 2.261 9.255 3.592 1659.90 147.128 2.256 9.280 3.594 1660.93 546.930 2.255 9.285 3.594 1661.15 ------------------------------------------------------------------------------ HYDRAULIC JUMP: UPSTREAM RUN ANALYSIS RESULTS DOWNSTREAM CONTROL ASSUMED FLOWDEPTH(FT) 3.62 - ---------------------------------------------------------------------------- GRADUALLY VARIED FLOW PROFILE COMPUTED INFORMATION: ------------------------------------------------------------------------------ DISTANCE FROM CONTROL(FT) .000 8.897 17.664 26.308 34.831 43.234 51.517 59.677 67.713 75.617 83.385 91.005 98.469 105.761 112.864 119.759 126.418 132.809 138.892 144.615 149.912 154.694 158.841 162.186 164.488 165.372 546.930 FLOW DEPTH VELOCITY SPECIFIC PRESSURE+ (FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUNDS) 3.623 5.664 4.121 2022.77 3.578 5.716 4.085 1995.84 3.532 5.772 4.050 1969.69 3.487 5.831 4.015 1944.34 3.441 5.894 3.981 1919.81 3.396 5.960 3.948 1896.11 3.350 6.030 3.915 1873.26 3.305 6.104 3.884 1851.28 3.260 6.181 3.853 1830.20 3.214 6.263 3.824 1810.03 3.169 6.349 3.795 1790.81 3.123 6.438 3.767 1772.56 3.078 6.533 3.741 1755.30 3.032 6.631 3.716 1739.07 2.987 6.735 3.692 1723.90 2.941 6.843 3.669 1709.82 2.896 6.956 3.648 1696.86 2.851 7.075 3.628 1685.07 2.805 7.199 3.610 1674.49 2.760 7.330 3.594 1665.14 2.714 7.466 3.580 1657.09 2.669 7.609 3.568 1650.38 2.623 7.759 3.559 1645.06 2.578 7.916 3.552 1641.18 2.533 8.080 3.547 1638.80 2.487 8.253 3.546 1638.00 2.487 8.253 3.546 1638.00 --------------- -------END OF HYDRAULIC JUMP ANALYSIS------------------------ PRESSURE+MOMENTUM BALANCE OCCURS AT 147.30 FEET UPSTREAM OF NODE 1186.66 DOWNSTREAM DEPTH = 2.737 FEET, UPSTREAM CONJUGATE DEPTH = 2.255 FEET ------------------------------------------------------------------------------ NODE 1733.59 : HGL = < 1057.877>;EGL= < 1059.056>;FLOWLINE= < 1055.500> FLOW PROCESS FROM NODE 1733.59 TO NODE 1804.29 IS CODE = 3 UPSTREAM NODE 1804.29 ELEVATION = 1055.86 (FLOW IS SUPERCRITICAL) ------------------------------------------------------------------------------ CALCULATE PIPE -BEND LOSSES(OCEMA): PIPE FLOW = 67.80 CFS PIPE DIAMETER = 48.00 INCHES CENTRAL ANGLE = 90.000 DEGREES MANNING'S N = .01300 PIPE LENGTH = 70.70 FEET NORMAL DEPTH(FT) = 2.38 CRITICAL DEPTH(FT) = 2.49 Page 7 UPSTREAM CONTROL ASSUMED FLOWDEPTH(FT) = 2.39 GRADUALLY VARIED ----------------------------------------------------------------------------- FLOW PROFILE COMPUTED INFORMATION: DISTANCE FROM FLOW DEPTH VELOCITY SPECIFIC PRESSURE+ CONTROL(FT) (FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUNDS) .000 2.386 8.670 3.554 1642.17 1.079 2.386 8.671 3.554 1642.21 2.209 2.385 8.673 3.554 1642.24 3.393 2.385 8.675 3.554 1642.28 4.638 2.384 8.677 3.554 1642.31 5.948 2.384 8.679 3.554 1642.35 7.332 2.384 8.680 3.554 1642.39 8.796 2.383 8.682 3.554 1642.42 10.350 2.383 8.684 3.555 1642.46 12.004 2.382 8.686 3.555 1642.49 13.773 2.382 8.688 3.555 1642.53 15.671 2.382 8.689 3.555 1642.57 17.717 2.381 8.691 3.555 1642.60 19.937 2.381 8.693 3.555 1642.64 22.358 2.380 8.695 3.555 1642.67 25.022 2.380 8.697 3.555 1642.71 27.977 2.380 8.698 3.555 1642.75 31.293 2.379 8.700 3.555 1642.79 35.068 2.379 8.702 3.555 1642.82 39.441 2.378 8.704 3.555 1642.86 44.634 2.378 8.706 3.555 1642.90 51.015 2.377 8.707 3.556 1642.94 59.273 2.377 8.709 3.556 1642.97 70.700 ------------------------------------------------------------------------------ 2.377 8.711 3.556 1643.01 NODE 1804.29 : HGL = < 1058.246>;EGL= < 1059.414>;FLOWLINE= < 1055.860> FLOW PROCESS FROM NODE 1804.29 TO NODE 1980.58 IS CODE = 1 UPSTREAM NODE 1980.58 ELEVATION = -- ------------------------------------------------------------------------ 1056.75 (FLOW IS SUPERCRITICAL) CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 67.80 CFS PIPE DIAMETER = 48.00 INCHES PIPE LENGTH = ------------------------------------------------------------------------------ 176.29 FEET MANNING'S N = .01300 NORMAL DEPTH(FT) = 2.38 CRITICAL DEPTH(FT) = 2.49 UPSTREAM CONTROL ASSUMED FLOWDEPTH(FT) = 2.49 GRADUALLY VARIED ------------------------------------------------------------------------------ FLOW PROFILE COMPUTED INFORMATION: DISTANCE FROM FLOW DEPTH VELOCITY SPECIFIC PRESSURE+ CONTROL(FT) (FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUNDS) .000 2.487 8.253 3.546 1638.00 .023 2.483 8.270 3.546 1638.00 .093 2.479 8.286 3.546 1638.02 .216 2.475 8.303 3.546 1638.06 .395 2.470 8.319 3.546 1638.11 .637 2.466 8.336 3.546 1638.17 .948 2.462 8.353 3.546 1638.25 1.335 2.458 8.370 3.546 1638.34 1.807 2.454 8.386 3.546 1638.45 2.374 2.449 8.403 3.547 1638.57 3.049 2.445 8.420 3.547 1638.70 3.847 2.441 8.438 3.547 1638.85 4.786 2.437 8.455 3.548 1639.01 5.888 2.433 8.472 3.548 1639.19 7.182 2.428 8.489 3.548 1639.38 Page 8 8.704 2.424 8.507 3.549 1639.59 10.503 2.420 8.524 3.549 1639.81 12.644 2.416 8.542 3.550 1640.05 15.218 2.412 8.560 3.550 1640.30 18.360 2.408 8.577 3.551 1640.57 22.277 2.403 8.595 3.551 1640.85 27.319 2.399 8.613 3.552 1641.15 34.137 2.395 8.631 3.552 1641.46 44.201 2.391 8.649 3.553 1641.79 62.219 2.387 8.668 3.554 1642.14 176.290 ------------------------------------------------------------------ 2.386 8.670 3.554 1642.17 NODE 1980.58 : HGL = < 1059.237>;EGL= < 1060.296>;FLOWLINE= < 1056.750> is ic*it is it sY is it it it is*ir is it*ic is it ie it it it ie it is it is irir it it ie sY it ie it it it is it it is ie it is ie it it is it it it it is is it it is ie it it it is it it it it is ie it it it ie it it it FLOW PROCESS FROM NODE 1980.58 TO NODE 1980.58 IS CODE = 5 UPSTREAM NODE 1980.58 ELEVATION = 1056.75 (FLOW IS AT CRITICAL DEPTH) -- ------------------------------------------------------------ CALCULATE JUNCTION LOSSES: PIPE FLOW DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY (CFS) (INCHES) (DEGREES) ELEVATION DEPTH(FT.) (FT/SEC) UPSTREAM 63.40 42.00 .00 1056.75 2.50 6.949 DOWNSTREAM 67.80 48.00 - 1056.75 2.49 8.256 LATERAL #1 .00 .00 .00 .00 .00 LATERAL #2 .00 .00 .00 .00 .00 .000 Q5 4.40===Q5 EQUALS BASIN INPUT=== .000 LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: DY=(Q2*V2-Ql*Vl*COS(DELTAI)-Q3*V3*COS(DELTA3)- Q4*V4*COS(DELTA4))/((A1+A2)*16.1)+FRICTION LOSSES UPSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00349 DOWNSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00443 AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS .00396 JUNCTION LENGTH = 1.00 FEET FRICTION LOSSES = .004 FEET ENTRANCE LOSSES .212 FEET JUNCTION LOSSES = (DY+HV1-HV2)+(ENTRANCE LOSSES) JUNCTION LOSSES ------------------------------------------------------------------------------ = ( .144)+( .212) = .356 NODE 1980.58 : HGL = < 1059.901>;EGL= < 1060.651>;FLOWLINE= < 1056.750> ....2Y*ir it it*ic it �-ir it it sY it it it it it it it it*ic it it it it it*i;#it it it it sY it it ie it*ir ie*it ie it it ie is it is it it is it it ir�it it it is it it it it it ie it is*it**ir FLOW PROCESS FROM NODE 1980.58 TO NODE 2112.44 IS CODE _ 1 UPSTREAM NODE 2112.44 -- - ---------------------------------------------------------------- ELEVATION = 1057.35 (FLOW IS SUBCRITICAL) CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 63.40 CFS PIPE DIAMETER = 42.00 INCHES PIPE LENGTH = ------------------------------------------------------------------------------ 131.86 FEET MANNING'S N = .01300 NORMAL DEPTH(FT) = 2.68 CRITICAL DEPTH(FT) = 2.50 DOWNSTREAM CONTROL ASSUMED FLOWDEPTH(FT) = 3.15 -------------------------------------______________________________________ GRADUALLY VARIED FLOW PROFILE COMPUTED INFORMATION: ------------------------------------------------------------ DISTANCE FROM FLOW DEPTH VELOCITY SPECIFIC PRESSURE+ CONTROL(FT) (FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUNDS) .000 3.151 6.947 3.901 1699.43 11.649 3.132 6.978 3.889 1692.51 23.277 3.114 7.009 3.877 1685.75 34.906 3.095 7.042 3.865 1679.16 46.555 3.076 7.075 3.854 1672.74 58.246 3.057 7.110 3.843 1666.48 70.001 3.038 7.145 3.832 1660.40 81.845 3.020 7.181 3.821 1654.49 93.805 3.001 7.219 3.811 1648.76 Page 9 105.911 2.982 7.257 3.800 1643.20 118.199 2.963 7.296 3.790 1637.82 130.708 2.945 7.336 3.781 1632.62 131.860 2.943 7.340 3.780 1632.16 ----------------------------------------------------------- NODE 2112.44 : HGL = < 1060.293>;EGL= < 1061.130>;FLOWLINE= < 1057.350> ic*it is is it it it is is it it it is it is it it it it it it it it is ie it 'e*ic is it is is it it is sY it is is it it is is it is it it it it is is it ie it 'tic is is is is is it is it it it it it is it is is ie it it ie FLOW PROCESS FROM NODE 2112.44 TO NODE 2112.44 IS CODE = 5 UPSTREAM NODE 2112.44 ELEVATION = 1057.35 (FLOW UNSEALS IN REACH) ---------------------------------------------------------------------------- CALCULATE JUNCTION LOSSES: PIPE FLOW DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY (CFS) (INCHES) (DEGREES) ELEVATION DEPTH(FT.) (FT/SEC) UPSTREAM 56.60 42.00 .00 1057.35 2.36 5.883 DOWNSTREAM 63.40 42.00 - 1057.35 2.50 7.342 LATERAL #1 .00 .00 .00 .00 .00 .000 LATERAL #2 .00 .00 .00 .00 .00 .000 Q5 6.80===Q5 EQUALS BASIN INPUT=== LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: DY=(Q2*V2-Q1*V1*COS(DELTAl)-Q3*V3*COS(DELTA3)- Q4*V4*COS(DELTA4))/((A1+A2)*16.1)+FRICTION LOSSES UPSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00316 DOWNSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00380 AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS .00348 JUNCTION LENGTH = 1.00 FEET FRICTION LOSSES = .003 FEET ENTRANCE LOSSES = .167 FEET JUNCTION LOSSES = (DY+HV1-HV2)+(ENTRANCE LOSSES) JUNCTION LOSSES = ( .159)+( .167) = .327 NODE 2112.44 : HGL = < 1060.919>;EGL < 1061.456>;FLOWLINE= < 1057.350> is is is is*ir is is it ir*ir it it is it it it it is*ir it it k is it ir°k it it ir'k it is it is is is it*it is it it is it iric*ic it ir%ic it**ir ir'..•ic**ic *ir it ie is it is ie***�•ir FLOW PROCESS FROM NODE 2112.44 TO NODE 2312.44 IS CODE = 1 UPSTREAM NODE 2312.44 ELEVATION = 1058.35 (FLOW -- ------------------------------------------------------------------------ SEALS IN REACH) CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 56.60 CFS PIPE DIAMETER = 42.00 INCHES PIPE LENGTH = 200.00 FEET MANNING'S N = .01300 DOWNSTREAM CONTROL ASSUMED PRESSURE HEAD(FT) = 3.57 PRESSURE FLOW PROFILE ------------------------------------------------------------------------------ COMPUTED INFORMATION: DISTANCE FROM PRESSURE VELOCITY SPECIFIC PRESSURE+ CONTROL(FT) HEAD(FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUNDS) .000 3.569 5.883 4.106 1737.31 37.595 ----------------------------------------------------_----------------- 3.500 5.883 4.037 1695.89 NORMAL DEPTH(FT) = 2.36 CRITICAL DEPTH(FT) 2.36 ASSUMED DOWNSTREAM PRESSURE HEAD(FT) = 3.50 GRADUALLY VARIED FLOW PROFILE COMPUTED INFORMATION: ----------------------------------------------------------- DISTANCE FROM FLOW DEPTH VELOCITY SPECIFIC PRESSURE+ CONTROL(FT) (FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUNDS) 37.595 3.500 5.881 4.037 1695.89 58.987 3.454 5.896 3.994 1670.13 77.813 3.409 5.923 3.954 1645.83 95.430 3.363 5.958 3.915 1622.57 112.226 3.317 6.001 3.877 1600.23 128.411 3.272 6.049 3.840 1578.75 144.117 3.226 6.103 3.805 1558.12 Page 10 159.433 3.180 6.162 3.770 1538.32 174.428 3.135 6.226 3.737 1519.35 189.151 3.089 6.296 3.705 1501.23 200_---------- 0003_-----055 6.351 3.682 1488.22 -------- ------------------------------------------- NODE 2312.44 : HGL = < 1061.405>;EGL= < 1062.032>;FLOWLINE= < 1058.350> is it it is is it is is it it it it icic it �4 it it is it ie it is ie it ie ie is is it it is is is it it it it is it ie ir$r k it it is it ie is it it it ie ir. oY it it it is it it is ie&ic it ie ie ie it it it it it ie it it FLOW PROCESS FROM NODE 2312.44 TO NODE 2312.44 IS CODE = 5 --UPSTREAM-NODE 2312.44 ELEVATION = 1058.35 (FLOW UNSEALS IN REACH) ------------------------------------------------------------- CALCULATE JUNCTION LOSSES: PIPE FLOW DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY UPSTREAM (49.60 (142.00) (DEGREOESO) ELEVATION1058.35O DEPTH(FT.) (FT/SEC) 5.155 DOWNSTREAM 56.60 42.00 - 1058.35 2.36 6.353 LATERAL #1 .00 .00 .00 .00 .00 .000 LATERAL #2 .00 .00 .00 .00 .00 .000 Q5 7.00===Q5 EQUALS BASIN INPUT=== LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: DY=(Q2*V2-Q1*V1*COS(DELTAI)-Q3*V3*COS(DELTA3)- Q4*V4*COS(DELTA4))/((A1+A2)*16.1)+FRICTION LOSSES UPSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00243 DOWNSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00288 AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS .00265 JUNCTION LENGTH = 1.00 FEET FRICTION LOSSES = .003 FEET ENTRANCE LOSSES = .125 FEET JUNCTION LOSSES = (DY+HV1-HV2)+(ENTRANCE LOSSES) JUNCTION LOSSES = ( .140)+( .125) = .265 NODE 2312.44 : HGL = < 1061.884>;EGL= < 1062.297>;FLOWLINE < 1058.350> it it it is*ir is it*is it is is*it it*ir*ir it is is is is ie it ie it is*ir*k is ie it ie ik it is is it it is is ir&sY-k it is ie k it ie*ir it it it*it k it is sY it it it it*it is it it*ir FLOW PROCESS FROM NODE 2312.44 TO NODE 2512.44 IS CODE = 1 --UPSTREAM-NODE 2512.44 ELEVATION = 1059.35 (FLOW --------------------------------------------------------------- SEALS IN REACH) CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 49.60 CFS PIPE DIAMETER = 42.00 INCHES PIPE LENGTH = 200.00 FEET MANNING'S N = .01300 DOWNSTREAM CONTROL ASSUMED PRESSURE HEAD(FT) = 3.53 PRESSURE FLOW PROFILE --------------------------- COMPUTED INFORMATION: DISTANCEFROM PRESSURE VELOCITY SPECIFIC HEAD(FT) (FT/SEC) ENERGY(FT) PRESSURE+ .000 3.534 5.155 3.947 MOMENTUM(POUNDS) 1566.75 ---------13_350----------3_500------5_155----------3_913 1546.15 NORMAL DEPTH(FT) = ------------------------- 2.15 CRITICAL DEPTH(FT) = 2.20 ASSUMED DOWNSTREAM ---------------------------- PRESSURE HEAD(FT) = 3.50 -------- GRADUALLY VARIED FLOW PROFILE COMPUTED INFORMATION: --------------------------------------------- ______________ DISTANCE FROM CONTROL(FT) FLOW DEPTH VELOCITY SPECIFIC (FT) (FT/SEC) ENERGY(FT) PRESSURE+ 13.350 3.500 5.154 3.913 MOMENTUM(POUNDS) 1546.15 31.597 3.448 5.170 3.863 1516.50 48.310 3.396 5.198 3.816 1488.26 64.259 3.344 5.236 3.770 1461.05 79.671 94.671 3.292 5.281 3.725 1434.79 109.340 3.240 5.333 3.682 3.188 5.391 3.640 1409.44 1384.99 Page 11 123.730 3.136 5.454 3.598 1361.45 137.881 3.084 5.524 3.558 1338.83 151.822 3.032 5.599 3.519 1317.15 165.574 2.980 5.680 3.482 1296.44 179.151 2.928 5.768 3.445 1276.72 192.564 2.876 5.861 3.410 1258.03 200.000 2.847 5.916 3.391 ---------------------------------------------------------------------- 1248.01 NODE 2512.44 : HGL = < 1062.197>;EGL= < 1062.741>;FLOWLINE= < 1059.350> ieieicieieicicieiririrYiriticic irici;sYititiriririeirieirir*iricicici:ieicicicsYie*ic*icie*irieiciricieiriciritir**icYiriricieieirieiririciciritir* FLOW PROCESS FROM NODE 2512.44 TO NODE 2512.44 IS CODE = 5 UPSTREAM NODE 2512.44 ELEVATION = 1059.35 (FLOW -- -- -------------------------------------------------------------- UNSEALS IN REACH) CALCULATE JUNCTION LOSSES: PIPE FLOW DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY (CFS) (INCHES) (DEGREES) ELEVATION DEPTH(FT.) (FT/SEC) UPSTREAM 42.40 36.00 .00 1059.35 2.12 5.998 DOWNSTREAM 49.60 42.00 - 1059.35 2.20 5.918 LATERAL #1 .00 .00 .00 .00 .00 LATERAL #2 .00 .00 .00 .00 .000 .00 Q5 7.20===Q5 EQUALS BASIN INPUT=== .000 LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: DY=(Q2*V2-Q1*V1*COS(DELTAI)-Q3*V3*COS(DELTA3)- Q4*V4*COS(DELTA4))/((A1+A2)*16.1)+FRICTION LOSSES UPSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00404 DOWNSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00246 AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS .00325 JUNCTION LENGTH = 1.00 FEET FRICTION LOSSES = .003 FEET ENTRANCE LOSSES = .109 FEET JUNCTION LOSSES = (DY+HV1-HV2)+(ENTRANCE LOSSES) JUNCTION LOSSES = ( .176)+( .109) = .284 ------------------------------------------------------------------------------ NODE 2512.44 : HGL = < 1062.467>;EGL= < 1063.025>;FLOWLINE= < 1059.350> it 4r is **it is it it is it it it is irir �•sY it it it it ie*ic it it is it***ir it it is it it*ir is *ie it is it*** �.*ir'..•ie it is it lr**R•ir is is*ic it *ir ir* �•-k #ic* �. ;Y FLOW PROCESS FROM NODE 2512.44 TO NODE 2712.44 IS CODE = 1 UPSTREAM NODE 2712.44 ELEVATION = 1060.35 (FLOW ------------------------------------------------------------------------------ SEALS IN REACH) CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 42.40 CFS PIPE DIAMETER = 36.00 INCHES PIPE LENGTH = 200.00 FEET MANNING'S N = .01300 DOWNSTREAM CONTROL ASSUMED PRESSURE HEAD(FT) 3.12 PRESSURE FLOW PROFILE COMPUTED INFORMATION: ------------------------------------------------------------------------------ DISTANCE FROM PRESSURE VELOCITY SPECIFIC PRESSURE+ CONTROL(FT) HEAD(FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUNDS) .000 3.117 5.998 3.675 1205.93 121.636 3.000 5.998 3.559 ------------------------------------------------------------------------------ 1154.48 NORMAL DEPTH(FT) = 2.22 CRITICAL DEPTH(FT) = 2.12 ASSUMED DOWNSTREAM PRESSURE HEAD(FT) = 3.00 GRADUALLY VARIED FLOW PROFILE COMPUTED INFORMATION: ------------------------------------------------------------------------------ DISTANCE FROM FLOW DEPTH VELOCITY SPECIFIC PRESSURE+ CONTROL(FT) (FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUNDS) 121.636 3.000 5.997 3.559 1154.48 146.828 2.969 6.007 3.530 1141.67 167.310 2.938 6.027 3.502 1129.61 185.850 2.907 6.052 3.476 1118.09 Page 12 --------200_000----------2_881 6.077 3.455 1109.01 --------------------------------- ---- NODE 2712.44 : HGL = < 1063.231>;EGL= < 1063.805>;FLOWLINE= < 1060.350> dcictt4ciriris4eirStsY�:rite'cdrdcir'ciriefrirkirir�rireYirsYiciritiY4r*ieirieYr�c4cir9riciciriciesYirkirieY�rir�rieirfe4c:t9eirirkir'cicfeir9rsY4ricic FLOW PROCESS FROM NODE 2712.44 TO NODE 2712.44 IS CODE = 5 --UPSTREAM NODE 2712.44 ELEVATION = 1060.35 (FLOW UNSEALS IN REACH) ---------------------------------- CALCULATE JUNCTION LOSSES: PIPE FLOW DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY UPSTREAM (35.00 (136.00) (DEGREES) 5 ) E1060.3DEPTH(FT.) (FT/SEC) 51 DOWNSTREAM 42.40 36.00 - 1060.35 2.12 6.079 LATERAL #1 .00 .00 .00 .00 .00 .000 LATERAL #2 .00 .00 .00 .00 .00 .000 Q5 7.40===Q5 EQUALS BASIN INPUT-= LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: DY=(Q2*V2-Q1*Vl*COS(DELTAl)-Q3*V3*COS(DELTA3)- Q4*V4*COS(DELTA4))/((A1+A2)*16.1)+FRICTION LOSSES UPSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00275 DOWNSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00352 AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS .00314 JUNCTION LENGTH = 1.00 FEET FRICTION LOSSES = .003 FEET ENTRANCE LOSSES = .115 FEET JUNCTION LOSSES = (DY+HV1-HV2)+(ENTRANCE LOSSES) JUNCTION LOSSES = ( .183)+( .115) = .298 ------------------------------------- ------------------------------ NODE 2712.44 : HGL = < 1063.723>;EGL= < 1064.103>;FLOWLINE= < 1060.350> FLOW PROCESS FROM NODE 2712.44 TO NODE 2912.44 IS CODE = 1 UPSTREAM NODE 2912.44 ELEVATION = 1061.35 (FLOW SEALS IN REACH) --------------------------------------------------------------- CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 35.00 CFS PIPE DIAMETER = 36.00 INCHES PIPE LENGTH = 200.00 FEET MANNING'S N = .01300 DOWNSTREAM CONTROL ASSUMED PRESSURE HEAD(FT) = 3.37 PRESSURE FLOW PROFILE COMPUTED INFORMATION: --------------------------------------- -------------------------- DISTANCE FROM PRESSURE VELOCITY SPECIFIC PRESSURE+ CONTROL(FT) HEAD(FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUNDS) .000 3.373 4.951 3.753 1161.82 165_881----------3_000- 4.951 3.381 997.46 -------- -----------------------------_---------------- NORMAL DEPTH(FT) = 1.92 CRITICAL DEPTH(FT) - 1.92 ASSUMED DOWNSTREAM PRESSURE HEAD(FT) = 3.00 GRADUALLY VARIED FLOW PROFILE COMPUTED INFORMATION: --------------------------- - DISTANCE FROM FLOW DEPTH VELOCITY SPECIFIC PRESSURE+ CONTROL(FT) (FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUNDS) 165.881 3.000 4.950 3.381 997.46 182.861 2.957 4.964 3.340 979.48 198.200 2.914 4.991 3.301 962.39 200.000 2.909 4.995 3.296 960.33 ------------------------------------------------ --------------------- NODE 2912.44 : HGL = < 1064.259>;EGL= < 1064.646>;FLOWLINE= < 1061.350> ::**ic*4c :: �•ic***4rf:*ir is is*ic is ir**9r*ic 4r sY is is �•.e it is 4r**it*ic ic:cir**Y'c4r**ic**ie 4r 4r it*sY�: 4t 4rk*ir is k it °k it 4c it****.. FLOW PROCESS FROM NODE 2912.44 TO NODE 2912.44 IS CODE = 5 UPSTREAM NODE 2912.44 ELEVATION = 1061.35 (FLOW UNSEALS IN REACH) Page 13 ----------------------------------------- CALCULATE JUNCTION LOSSES: PIPE FLOW DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY (27.40 (236.00) (DEGR.00) E1061.35LEVATION UPSTREAM DEP1.69T.) (FT3.877 DOWNSTREAM 35.00 36.00 - 1061.35 1.92 4.997 LATERAL #1 .00 .00 .00 .00 .00 LATERAL #2 .00 .00 .00 .00 .000 .00 Q5 7.60===Q5 EQUALS BASIN INPUT=== .000 LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: DY=(Q2*V2-Q1*V1*COS(DELTAI)-Q3*V3*COS(DELTA3)- Q4*V4*COS(DELTA4))/((A1+A2)*16.1)+FRICTION LOSSES UPSTREAM: MANNING'S N = .01300; FRICTION SLOPE = DOWNSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00169 AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS .00206 .00242 JUNCTION LENGTH = 1.00 FEET FRICTION LOSSES = .002 FEET ENTRANCE LOSSES = .078 FEET JUNCTION LOSSES = (DY+HV1-HV2)+(ENTRANCE LOSSES) JUNCTION LOSSES = ( .151)+( .078) = .228 --------------------------------------------- ------------------------- NODE 2912.44 : HGL = < 1064.641>;EGL= < 1064.875>;FLOWLINE= < 1061.350> FLOW PROCESS FROM NODE 2912.44 TO NODE 3112.44 IS CODE = 1 --UPSTREAM NODE 3112.44 ELEVATION = 1062.35 (FLOW ----------------------------------------------------------------- SEALS IN REACH) CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 27.40 CFS PIPE DIAMETER = 36.00 INCHES PIPE LENGTH = 200.00 FEET MANNING'S N = .01300 DOWNSTREAM CONTROL ASSUMED PRESSURE HEAD(FT) = 3.29 --------- ------------------------------ - PRESSURE FLOW PROFILE COMPUTED INFORMATION: ------------------------------------- DISTANCE FROM PRESSURE VELOCITY SPECIFIC CONTROL(FT) HEAD(FT) (FT/SEC) ENERGY(FT) PRESSURE+ .000 3.291 3.876 3.525 MOMENTUM(POUNDS) 995.88 ---------87_9073.000 ---------------------3_876 867.44 --------3_233 NORMAL DEPTH(FT) = 1.64 CRITICAL DEPTH(FT) = 1.69 ASSUMED DOWNSTREAM PRESSURE HEAD(FT) = 3.00 GRADUALLY VARIED FLOW PROFILE COMPUTED INFORMATION: --------- ------------------ -------------------------- ------------------------ DISTANCE FROM FLOW DEPTH VELOCITY SPECIFIC CONTROL(FT) (FT) (FT/SEC) PRESSURE+ ENERGY(FT) 87.907 3.000 3.875 3.233 MOMENTUM(POUNDS) 102.684 2.948 3.890 3.183 867.44 845.21 116.654 2.895 3.918 3.134 823.77 130.210 2.843 3.954 3.086 802.97 143.473 2.791 3.997 3.039 782.78 156.509 2.738 4.047 2.993 763.19 169.359 2.686 4.103 2.948 744.22 182.053 2.634 4.165 2.903 725.88 194.609 2.581 4.234 2.860 708.21 2_-----559 4.265 2.841 200_000---------- -------- 700.75 ------------------------------------------- NODE 3112.44 : HGL = < 1064.909>;EGL= < 1065.191>;FLOWLINE= < 1062.350> ::eta:**�t�:�t�:*�:*�:**::�:***�:*:.•*x�-***�:**�•**�;*********�***********�t**�•:�*�:*****�*�:****** FLOW PROCESS FROM NODE 3112.44 TO NODE 3112.44 IS CODE = 5 UPSTREAM NODE 3112.44 ELEVATION = 1062.35 (FLOW IS ------------------------------------------------------------------------------ SUBCRITICAL) Page 14 CALCULATE JUNCTION LOSSES: PIPE FLOW DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY (CFS) (INCHES) (DEGREES) ELEVATION DEPTH(FT.) (FT/SEC) UPSTREAM 19.50 36.00 .00 1062.35 1.42 2.784 DOWNSTREAM 27.40 36.00 - 1062.35 1.69 4.267 LATERAL #1 .00 .00 .00 .00 .00 .000 LATERAL #2 .00 .00 .00 .00 .00 .000 Q5 7.90===Q5 EQUALS BASIN INPUT=== LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: DY=(Q2*V2-Q1*V1*COS(DELTAI)-Q3*V3*COS(DELTA3)- Q4*V4*COS(DELTA4))/((A1+A2)*16.1)+FRICTION LOSSES UPSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00075 DOWNSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00158 AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS .00117 JUNCTION LENGTH = 1.00 FEET FRICTION LOSSES = .001 FEET ENTRANCE LOSSES = .057 FEET JUNCTION LOSSES = (DY+HV1-HV2)+(ENTRANCE LOSSES) JUNCTION LOSSES = ( .131)+( .057) = .188 NODE 3112.44 : HGL = < 1065.259>;EGL= < 1065.379>;FLOWLINE= < 1062.350> is 4: **9r �Y it is dr is it 4e Ye ie is ie is it 4r 4r'.r de ir*it it it it it Ye fe 4r it ie fc 4r ir:r ie it is is is ie k Y 4r 4e �r dr it it it it 4e ie it it ie is it it 4e ie 4r ie fr it it it 4c it �Yx is eY fc 4r FLOW PROCESS FROM NODE 3112.44 TO NODE 3312.44 IS CODE = 1 UPSTREAM NODE 3312.44 ELEVATION = 1063.35 (FLOW IS SUBCRITICAL) CALCULATE FRICTION ----------------------------------------------------- LOSSES(LACFCD): PIPE FLOW = 19.50 CFS PIPE DIAMETER = 36.00 INCHES PIPE LENGTH = 200.00 FEET MANNING'S N = .01300 ------------------------------------------------------------------------------ NORMAL DEPTH(FT) = 1.34 CRITICAL DEPTH(FT) = 1.42 DOWNSTREAM CONTROL ASSUMED FLOWDEPTH(FT) 2.91 ---------------------------------------------------------------------- GRADUALLY VARIED FLOW PROFILE ------------------------------------------------------------------------------ COMPUTED INFORMATION: DISTANCE FROM FLOW DEPTH VELOCITY SPECIFIC PRESSURE+ CONTROL(FT) (FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUNDS) .000 2.909 2.783 3.029 726.70 13.456 2.849 2.811 2.972 701.79 26.748 2.789 2.846 2.915 677.43 39.915 2.730 2.887 2.859 653.63 52.979 2.670 2.933 2.804 630.44 65.956 2.610 2.986 2.749 607.87 78.854 2.551 3.044 2.694 585.96 91.682 2.491 3.107 2.641 564.75 104.442 2.431 3.177 2.588 544.26 117.137 2.371 3.253 2.536 524.53 129.766 2.312 3.335 2.485 505.60 142.328 2.252 3.425 2.434 487.49 154.817 2.192 3.522 2.385 470.25 167.228 2.133 3.627 2.337 453.91 179.552 2.073 3.742 2.290 438.50 191.774 2.013 3.865 2.245 424.09 200.000 ------------------------------------------------------------------------------ 1.973 3.956 2.216 414.87 NODE 3312.44 : HGL = < 1065.323>;EGL= < 1065.566>;FLOWLINE= < 1063.350> 4rR•.'e*.4::r fe ie*ic::ir*sF�:*4eY:*k4r ie ie �r is zY ie icic Yr 4r it it 4t*ir it ie it it �r is ie 4r it R-sY 4e 's4c*k ft it*sti*4t*4ci:'e*:c Yc 4r Yt is Y*�•4c :e it 4r �•*ic FLOW PROCESS FROM NODE 3312.44 TO NODE 3312.44 IS CODE = 8 UPSTREAM NODE 3312.44 ELEVATION = 1063.35 (FLOW IS SUBCRITICAL) ------------------------------------------------------------------------------ CALCULATE CATCH BASIN ENTRANCE LOSSES(LACFCD): PIPE FLOW = 19.50 CFS PIPE DIAMETER = 36.00 INCHES FLOW VELOCITY = 3.96 FEET/SEC. VELOCITY HEAD = .243 FEET Page 15 CATCH BASIN ENERGY LOSS = .2*(VELOCITY HEAD) = .2*( .243) = .049 ---------------------------------------------------------------------------- NODE 3312.44 : HGL = < 1065.614>;EGL= < 1065.614>;FLOWLINE= < 1063.350> :ricirYricieirsYiricirsY4r3rirsYiriririe�tie4rirfrir�tir4r4t4rir�cieirdrir4rJtirtiie�c49ricirtrsYicicYfcie4rYirieirirsYieYfrkkir4e4r�rxirie4r4r4tieir UPSTREAM PIPE FLOW CONTROL DATA: NODE NUMBER = 3312.44 FLOWLINE ELEVATION = 1063.35 ASSUMED UPSTREAM CONTROL HGL = 1064.77 FOR DOWNSTREAM RUN ANALYSIS END OF GRADUALLY VARIED FLOW ANALYSIS Page 16 Technical Appendix L 25-Year Hydraulic Analysis it it it it it is it irit iriric ie is ie ie ie it it ie it it it it is it ie is is is ie is is ie it it ie it is it ie is is it it it is it it is ie it it it it it it it it it is is it it it it is is is sic fc is it is is is it is PIPE -FLOW HYDRAULICS COMPUTER PROGRAM PACKAGE (Reference: LACFCD,LACRD, AND OCEMA HYDRAULICS CRITERION) (c) Copyright 1982-93 Advanced Engineering Software (aes) Ver. 4.6A Release Date: 7/18/93 License ID 1202 Analysis prepared by: HUITT-ZOLLARS, INC. 15101 RED HILL AVENUE TUSTIN, CALIFORNIA 92780-6500 PHONE (714) 259-7900 * FAX (714) 259-0210 it it ie it is is is is it«•ie *ic it it ie it ie is it ie it ie it it it DESCRIPTION OF STUDY 'Y**i`ie it is ie it ie ie ie is is it it it it ie irir it ie it ie is * SIERRA BUSINESS PARK SIERRA AVENUE / SLOVER AVENUE STORM DRAIN it * 25-YEAR HYDRAULIC ANALYSIS it is is*ir is 4r it ie it it*ic is is R•ic ie ie is*ic is*ie it is is it ie xic ir�lc is it ir'.cie sY is*ir is k it is ie it is is is fe it ir'.e is is ie it it is is ie is it***ic it it it*ir ------------------------------------------------------------------------------ FILE NAME: SBPMA025.HGL TIME/DATE OF STUDY: 8:12 6/17/2004 ir'.,•*ir *ir it it is '.c icy it ie it it ie ie:Yi: is it is ie it ie°X is it it*it ie it it ie is ie it ie is it ie is ie ie*ic it ie ie it is it it it it it ie sY it is is is#ir ie it ie it is it it is it ie is is GRADUALLY VARIED FLOW ANALYSIS FOR PIPE SYSTEM NODAL POINT STATUS TABLE (Note: "*" indicates nodal point data used.) UPSTREAM RUN DOWNSTREAM RUN NODE MODEL PRESSURE PRESSURE+ FLOW PRESSURE+ NUMBER PROCESS HEAD(FT) MOMENTUM(POUNDS) DEPTH(FT) MOMENTUM(POUNDS) 4997.86- 11.82* 36738.25 4.43 19316.20 1 FRICTION 5262.77- 10.93* 33198.99 3.98 20820.43 1 FRICTION+BEND 5347.58- 10.78* 32608.66 3.81 21602.60 1 FRICTION 5355.57- 10.75* 32501.05 3.80 21686.76 - 1 JUNCTION 2252.33- 8.66* 24599.28 5.80 DC 19305.12 1 FRICTION 2736.17- 8.79* 24954.72 5.80 DC 19305.12 1 JUNCTION 2740.83- 9.12* 24572.52 5.62 DC 17709.84 1 FRICTION 3121.17- 9.04* 24337.12 5.62 DC 17709.84 1 JUNCTION 3125.83- 9.04* 24330.37 5.62 DC 17709.84 1 FRICTION 3565.58- 8.94* 24051.13 5.62 DC 17709.84 1 JUNCTION 3582.33- 9.71* 23471.05 4.18 15100.35 1 FRICTION 3590.58- 9.71* 23450.08 4.15 15152.73 1 JUNCTION 3607.33- 7.67* 9635.42 2.07 8861.13 1 FRICTION 1 HYDRAULIC JUMP 3787.69- 3.87*Dc 5746.38 3.87*DC 5746.39 1 JUNCTION 3794.35- 4.70* 5722.49 3.13 5580.68 1 FRICTION 1 HYDRAULIC JUMP 4247.67- 3.77 DC 5322.83 2.70* 6133.59 1 JUNCTION 4252.33- 3.82 DC 5610.75 3.38* 5732.73 Page 1 } FRICTION 4459.70- 3.82*DC 5610.75 3.82*DC 5610.75 } JUNCTION 4459.70- 5.04* 5236.48 2.89 4481.55 } FRICTION } HYDRAULIC JUMP 4719.80- 3.50 DC 4260.43 2.90* 4473.95 } JUNCTION 4724.46- 3.50 DC 4260.43 2.92* 4458.09 } FRICTION 4974.99- 3.50*DC 4260.43 3.50*DC 4260.43 } JUNCTION 4974.99- 4.63* 3818.66 2.40 3239.34 } FRICTION } HYDRAULIC JUMP 5219.37- 3.08 DC 2978.43 2.15* 3519.56 } JUNCTION 5227.28- 3.17 DC 3126.47 2.58* 3302.66 } FRICTION 5300.00- 3.16 DC 3126.45 2.58* 3302.48 } JUNCTION 5300.00- 3.29 3133.71 2.57* 3312.22 } FRICTION 5574.44- 3.16 DC 3126.45 2.28* 3584.53 } FRICTION+BEND 5602.48- 3.16 DC 3126.45 2.23* 3652.22 } JUNCTION 5607.14- 3.16*DC 3385.03 3.16*DC 3385.03 } FRICTION+BEND 5748.25- 3.31* 3398.08 3.16 DC 3385.03 } FRICTION 5895.25- 3.43* 3426.66 3.16 DC 3385.06 } JUNCTION 5895.25- 3.46* 3437.86 3.16 DC 3385.03 } FRICTION 5947.67- 3.66* 3556.78 3.16 DC 3385.03 } JUNCTION 5952.33- 4.48* 3478.40 3.00 DC 2774.54 } FRICTION 6132.50- 4.60* 3546.43 3.01 DC 2774.47 } JUNCTION 6132.50- 4.61* 3551.84 2.95 2776.42 } FRICTION 6270.81- 4.69* 3603.55 2.60 2859.51 } FRICTION+BEND 6285.81- 4.68* 3598.11 3.01 DC 2774.47 } JUNCTION 6285.81- 4.69* 3603.52 3.02 DC 2774.44 } FRICTION+BEND 6343.04- 5.21* 3915.72 3.02 DC 2774.44 } FRICTION 6358.16- 5.29* 3961.52 3.02 DC 2774.44 } JUNCTION 6362.83- 5.85* 3936.30 2.88 DC 2370.57 } FRICTION 6763.18- 7.15* 4713.17 2.88 DC 2370.57 } JUNCTION 6773.18- 8.26* 4232.68 1.97 DC 854.54 } FRICTION 6884.95- 7.99* 4069.47 1.97 DC 854.54 } JUNCTION 6884.95- 8.01* 4070.40 1.95 DC 827.88 } FRICTION 7143.95- 7.37* 3682.05 1.95 DC 827.88 } JUNCTION 7149.45- 7.45* 3667.17 1.74 719.70 } FRICTION Page 2 7239.93- 7.11* 3463.12 1.74 719.87 1 FRICTION+BEND 7315.36- 6.85* 3312.71 1.84 DC 716.40 1 JUNCTION 7315.36- 6.91* 3311.92 1.67 655.79 1 FRICTION+BEND 7348.91- 6.80* 3244.03 1.77 Dc 652.53 1 JUNCTION 7348.91- 6.84* 3242.79 1.62 598.69 1 FRICTION+BEND 7373.43- 6.76* 3194.09 1.64 597.61 1 FRICTION 7387.93- 6.70* 3160.08 1.71 Dc 596_07 ------------------------------------------------------------ MAXIMUM NUMBER OF ENERGY BALANCES USED IN EACH PROFILE = 25 NOTE: STEADY FLOW HYDRAULIC HEAD -LOSS COMPUTATIONS BASED ON THE MOST CONSERVATIVE FORMULAE FROM THE CURRENT LACRD,LACFCD, AND OCEMA DESIGN MANUALS. it * it it it it it it it it it it it it it ie is is it * it it ie is it it it is it it is is is it it is it it it it it it ie is it it it it it ie it it it it it it is it sY it it it is it is it it is it it it is st irir it it is DOWNSTREAM PIPE FLOW CONTROL DATA: NODE NUMBER = 4997.86 FLOWLINE ELEVATION = 1030.88 PIPE FLOW = 502.12 CFS PIPE DIAMETER = 108.00 INCHES ASSUMED DOWNSTREAM CONTROL HGL = 1042.700 ------------------------------------------------------------------ NODE 4997.86 : HGL = < 1042. 700>; EGL= < 1043. 667>; FLOWLINE= < 1030.880> k is * it it it is is * * is is it it is Y it is it it it it is ie it it it it irit it it it is it it it it it is °k it it # is it is is it it it it it ilir it it is ie sY it it is it it it it it it it it i:* ie is it it ie FLOW PROCESS FROM NODE 4997.86 TO NODE 5262.77 IS CODE = 1 UPSTREAM NODE 5262.77 ELEVATION = 1032.20 (FLOW IS UNDER PRESSURE) --------------------------------------------------------------- CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 502.12 CFS PIPE DIAMETER = 108.00 INCHES PIPE LENGTH = 264.91 FEET MANNING'S N = .01300 SF=(Q/K)**2 = (( 502.12)/( 12485.280))**2 = .00162 HF=L*SF = ( 264.91)*( .00162) = .428 --------------------------------------------------------------- NODE 5262.77 : HGL = < 1043.128>;EGL= < 1044.096>;FLOWLINE= < 1032.200> it it i:*it it it it it ie it it*ir it it is is*i:i: it it is k it is it**ir ie is it is ie it it is is it is it°k is it it it it it it it is it it k*it it it is it is it it it it it is it is it it it it it *ie FLOW PROCESS FROM NODE 5262.77 TO NODE 5347.58 IS CODE = 3 -- - UPSTREAMNODE5347.58 ELEVATION = 1032.63 (FLOW IS UNDER PRESSURE) -------------------------------------------------------------- CALCULATE PIPE -BEND LOSSES(OCEMA): PIPE FLOW = 502.12 CFS PIPE DIAMETER = 108.00 INCHES CENTRAL ANGLE = 32.000 DEGREES MANNING'S N = .01300 PIPE LENGTH = 84.81 FEET BEND COEFFICIENT(KB) = .14907 FLOW VELOCITY = 7.89 FEET/SEC. VELOCITY HEAD = .967 FEET HB=KB*(VELOCITY HEAD) = ( 149)*( .967) = .144 SF=(Q/K)**2 = (( 502.12)/( 12485.850))**2 = .00162 HF=L*SF = ( 84.81)*( .00162) = .137 TOTAL HEAD LOSSES = HB + HF = ( .144)+( .137) _ .281 --------------------------------------------- NODE 5347.58 : HGL = < 1043.410>;EGL= < 1044.377>;FLOWLINE= < 1032.630> iri:*ic irir it i:*ir is is it it i::ric*iri:*ic id it*�'it fr 4c**ir*ir*ic ir:Y°k is ir*it ir.;*�ir it it is it*ir:r it it it it*i: *Y it it**ir is is it*ic is it is it it FLOW PROCESS FROM NODE 5347.58 TO NODE 5355.57 IS CODE = 1 UPSTREAM NODE 5355.57 ELEVATION = 1032.67 (FLOW IS UNDER PRESSURE) -- ---------------------------------------------------------------- CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 502.12 CFS PIPE DIAMETER = 108.00 INCHES PIPE LENGTH = 7.99 FEET MANNING'S N = .01300 SF=(Q/K)**2 = (( 502.12)/( 12536.640))**2 = .00160 HF=L*SF = ( 7.99)*( .00160) = .013 Page 3 NODE 5355.57 : HGL = < 1043.423>;EGL= < 1044.390>;FLOWLINE= < 1032.670> it it it ie 4c 4c de it is is 'e it is 4t it is it k Yr it dr is is k*Y it 4r it fr ie it ie 4c it ie is it sY 4t dr s4 ie fi it 4r it it it it:'c k 4r it ie Y is 4r Yr*ir it it do 9t it 4t it irie ie it ie it 4c sY it it FLOW PROCESS FROM NODE 2247.67 TO NODE 2252.33 IS CODE = 5 UPSTREAM NODE -- -------------------------------------------------------------------- 2252.33 ELEVATION = 1033.77 (FLOW IS UNDER PRESSURE) CALCULATE JUNCTION LOSSES: PIPE FLOW DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY (CFS) (INCHES) (DEGREES) ELEVATION DEPTH(FT.) (FT/SEC) UPSTREAM 502.12 90.00 .00 1033.77 5.80 11.366 DOWNSTREAM 502.12 108.00 - 1032.67 5.52 7.893 LATERAL #1 .00 .00 .00 .00 .00 LATERAL #2 .00 .00 .00 .00 .00 .000 Q5 .00===Q5 EQUALS BASIN INPUT=== .000 LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: DY=(Q2*V2-Ql*Vl*COS(DELTAI)-Q3*V3*COS(DELTA3)- Q4*V4*COS(DELTA4))/((A1+A2)*16.1)+FRICTION LOSSES UPSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00428 DOWNSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00162 AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS .00295 JUNCTION LENGTH = 4.66 FEET FRICTION LOSSES = .014 FEET ENTRANCE LOSSES = .000 FEET JUNCTION LOSSES = (DY+HV1-HV2)+(ENTRANCE LOSSES) JUNCTION LOSSES = ( .047)+( .000) = .047 NODE 2252.33 : HGL = < 1042.432>;EGL= < 1044.437>;FLOWLINE= < 1033.770> *ir it sY*:rit:rir:t*it ir:c it 4r is*4t is do ie it it �Y it ie it 4t 4t it it it Yt it 4c ie it 4r*ie ir$t sY ie eY is ie 4c is is it k it is it �'r is is it it is is it fr *:r it it is it ic'.c it it 3c :c it FLOW PROCESS FROM NODE 2252.33 TO NODE 2736.17 IS CODE = 1 UPSTREAMNODE2736.17 -- - ELEVATION = 1035.71 (FLOW IS UNDER -- ---------------------------------------------------------- PRESSURE) CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 502.12 CFS PIPE DIAMETER = 90.00 INCHES PIPE LENGTH = 483.84 FEET MANNING'S N = .01300 SF=(Q/K)**2 = (( 502.12)/( 7678.587))**2 = .00428 HF=L*SF = ( ------------------------------------------------------------------- 483.84)*( .00428) = 2.069 NODE 2736.17 : HGL = < 1044.500>;EGL= < 1046.506>;FLOWLINE= < 1035.710> 't:ri:'.•it*4: it it i:Yr:cir:e is it it is it*i<it 4c is*ir is fr is is it it*i: is 4c st it it*ie it 4c ie*ir it �•it �r is k:t 4r ie 4c*:t*:e4t*:c it it it eY is is 4i do is is $r it ie ir'c FLOW PROCESS FROM NODE 2736.17 TO NODE 2740.83 IS CODE = 5 UPSTREAM NODE -- --------------------------------------------------------------------- 2740.83 ELEVATION = 1035.72 (FLOW IS UNDER PRESSURE) CALCULATE JUNCTION LOSSES: PIPE FLOW DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY (CFS) (INCHES) (DEGREES) ELEVATION DEPTH(FT.) (FT/SEC) UPSTREAM 471.60 90.00 .00 1035.72 5.62 10.675 DOWNSTREAM 502.12 90.00 - 1035.71 5.80 11.366 LATERAL #1 30.52 24.00 45.00 1038.77 1.87 9.715 LATERAL #2 .00 .00 .00 .00 .00 Q5 .00===Q5 EQUALS BASIN INPUT=== .000 LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: DY=(Q2*V2-Q1*Vl*COS(DELTAI)-Q3*V3*COS(DELTA3)- Q4*V4*COS(DELTA4))/((A1+A2)*16.1)+FRICTION LOSSES UPSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00377 DOWNSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00428 AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS .00402 JUNCTION LENGTH = 4.66 FEET FRICTION LOSSES = .019 FEET ENTRANCE LOSSES = .000 FEET JUNCTION LOSSES = (DY+HV1-HV2)+(ENTRANCE LOSSES) JUNCTION LOSSES = ( .108)+( .000) = .108 -------------------------------------------------------------------- NODE 2740.83 : HGL = < 1044.845>;EGL= < 1046.614>;FLOWLINE= < 1035.720> Page 4 is * it it Ye it it it 9e it it Yr Yr * it it it it ie is * it ie itie it ie ie irYe * * it Yr * Ye it it ieYr it it ie Ye is it is Ye Yi* * * * ieYt is Ye irYr YrYc ie Yc Ye it ie *. it ie * it *Ye it Ye it i�Ye FLOW PROCESS FROM NODE 2740.83 TO NODE 3121.17 IS CODE = 1 --UPSTREAM-NODE 3121.17 ELEVATION = 1037.24 (FLOW IS UNDER PRESSURE) -------------------------------------------------- --------------- CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 471.60 CFS PIPE DIAMETER = 90.00 INCHES PIPE LENGTH = 380.34 FEET MANNING'S N = .01300 SF=(Q/K)**2 = (( 471.60)/( 7678.897))**2 = .00377 HF=L*SF = ( 380.34)*( .00377) = 1.435 ---------------------------------------- ------------------------- NODE 3121.17 : HGL = < 1046.279>;EGL= < 1048.049>;FLOWLINE= < 1037.240> �'i:ir*ir is*ir it Y:i:ir**ic**Y:it**.**.ie it*it Yt it*ir it is is it Ye it is it it it Yt it it is ie is it it it Ye***ir it it**i: it******irYt*i: *ir it it it*it FLOW PROCESS FROM NODE 3121.17 TO NODE 3125.83 IS CODE = 5 UPSTREAM NODE 3125.83 ELEVATION = 1037.26 (FLOW IS UNDER PRESSURE) ------- ---------------------------------------------- CALCULATE JUNCTION LOSSES: PIPE FLOW DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY (CFS) (INCHES) (DEGREES) ELEVATION DEPTH(FT.) (FT/SEC) UPSTREAM 471.60 90.00 .00 1037.26 5.62 10.675 DOWNSTREAM 471.60 90.00 - 1037.24 5.62 10.675 LATERAL #1 .00 24.00 45.00 1040.08 .00 .000 LATERAL #2 .00 .00 .00 .00 .00 .000 Q5 .00===Q5 EQUALS BASIN INPUT=== LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: DY=(Q2*V2-Q1*V1*COS(DELTAl)-Q3*V3*COS(DELTA3)- Q4*V4*COS(DELTA4))/((A1+A2)*16.1)+FRICTION LOSSES UPSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00377 DOWNSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00377 AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS .00377 JUNCTION LENGTH = 4.66 FEET FRICTION LOSSES = .018 FEET ENTRANCE LOSSES = .000 FEET JUNCTION LOSSES = (DY+HV1-HV2)+(ENTRANCE LOSSES) JUNCTION LOSSES = ( .018)+( .000) = .018 ------------------------------ -------------------------------------- NODE 3125.83 : HGL = < 1046.297>;EGL= < 1048.066>;FLOWLINE= < 1037.260> *i:*�•'k is*ir :: isitY:iei:ir*ir**Y:it*iri.•ir*it**ie it:k*�•ic***it it is ir***Y: it*ic itie*it is**ic�•Yt it*°k it irYr*ie*ir ic�•ir it is*iris �- FLOW PROCESS FROM NODE 3125.83 TO NODE 3565.58 IS CODE = 1 UPSTREAM NODE 3565.58 ELEVATION = 1039.02 (FLOW IS UNDER PRESSURE) -------------------------------------------------- CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 471.60 CFS PIPE DIAMETER = 90.00 INCHES PIPE LENGTH = 439.75 FEET MANNING'S N = .01300 SF=(Q/K)**2 = CC 471.60)/( 7678.810))**2 = .00377 HF=L*SF = ( 439.75)*( .00377) = 1.659 ------------------------------- ------------------------------------- NODE 3565.58 HGL = < 1047.956>;EGL= < 1049.725>;FLOWLINE= < 1039.020> �:ir�•*X**ic it ic?c�•Y;*ic*i: ie �k*it****ic*it*Yr it it it**ir is ie ie**it Yr is *Yr is**it it Yr *ic is Yc*it it is �•ic*it**ir it*ic*ic it*ir it is it FLOW PROCESS FROM NODE 3565.58 TO NODE 3582.33 IS CODE = 5 --UPSTREAM-NODE- 3582.33 ELEVATION = 1039.09 (FLOW IS UNDER PRESSURE) -------------------------------------------------------- CALCULATE JUNCTION LOSSES: PIPE FLOW DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY UPSTREAM 400.26 (190.00) (DEGREES) E1039.09N DEP5.18T.) (FT/SEC) .060 DOWNSTREAM 471.60 90.00 - 1039.02 5.62 10.675 LATERAL #1 71.34 54.00 30.00 1040.55 2.46 4.486 LATERAL #2 .00 .00 .00 .00 .00 .000 Q5 .00===Q5 EQUALS BASIN INPUT=== LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: Page 5 DY=(Q2*V2-Q1*Vl*COS(DELTAl)-Q3*V3*COS(DELTA3) Q4*V4*COS(DELTA4))/((A1+A2)*16.1)+FRICTION LOSSES UPSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00272 DOWNSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00377 AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS .00324 JUNCTION LENGTH = 16.75 FEET FRICTION LOSSES = .054 FEET ENTRANCE LOSSES = .000 FEET JUNCTION LOSSES = (DY+HV1-HV2)+(ENTRANCE LOSSES) JUNCTION LOSSES = ( .354)+( .000) = .354 ----------------------------------------------------- NODE 3582.33 : HGL = < 1048.805>;EGL= < 1050.079>;FLOWLINE= < 1039.090> * is it is it is it it it is it *. it it is it it it it it is it is is itieic it it is is it it it is is it is ie * it it it it is it ie iric it it is it is is ie ie is * * * * *. * * * is is it is it is ie is it it it it FLOW PROCESS FROM NODE 3582.33 TO NODE 3590.58 IS CODE = 1 UPSTREAM NODE 3590.58 ELEVATION = 1039.12 (FLOW IS UNDER PRESSURE) --------------------------------------------------------------- CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 400.26 CFS PIPE DIAMETER = 90.00 INCHES PIPE LENGTH = 8.25 FEET MANNING'S N = .01300 SF=(Q/K)**2 = (( 400.26)/( 7671.058))**2 = .00272 HF=L*SF = ( 8.25)*( .00272) = .022 --------------------------------------------------- ---------------- NODE 3590.58 : HGL = < 1048.827>;EGL= < 1050.102>;FLOWLINE= < 1039.120> ip it it it it it is it is it is is is it it it it it it * it it is is it it is it ie is * it it is is it it it is ie is it it is iric is is *. it it is is it it it it it is sY it it it it is itic it it is it it it it it ie it it FLOW PROCESS FROM NODE 3590.58 TO NODE 3607.33 IS CODE = 5 --UPSTREAM NODE 3607.33 ELEVATION = 1041.68 (FLOW IS UNDER PRESSURE) -------------------------------------------------------- CALCULATE JUNCTION LOSSES: PIPE FLOW DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY (CFS) (INCHES) (DEGREES) ELEVATION DEPTH(FT.) (FT/SEC) UPSTREAM 182.82 60.00 .00 1041.68 3.87 9.311 DOWNSTREAM 400.26 90.00 - 1039.12 5.18 9.060 LATERAL #1 217.64 72.00 30.00 1039.90 4.04 7.697 LATERAL #2 .00 .00 .00 .00 .00 .000 Q5 .00===Q5 EQUALS BASIN INPUT=== LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: DY=(Q2*V2-Ql*V1*COS(DELTAI)-Q3*V3*COS(DELTA3)- Q4*V4*COS(DELTA4))/((Al+A2)*16.1)+FRICTION LOSSES UPSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00493 DOWNSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00272 AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS .00382 JUNCTION LENGTH = 16.75 FEET FRICTION LOSSES = .064 FEET ENTRANCE LOSSES = .000 FEET JUNCTION LOSSES = (DY+HV1-HV2)+(ENTRANCE LOSSES) JUNCTION LOSSES = ( .596)+( .000) = .596 ------------------------------------------------ ------------------ NODE 3607.33 : HGL = < 1049.352>;EGL= < 1050.698>;FLOWLINE= < 1041.680> ic„•*..::i:*ic�•i:**�•i:*i:*i•**ir it is it it**it*******it*.ic is irti•*iti:i.•*�-it it �•�-ie*i:ir:.c**ici;•&*:4 is *it i:#ic*:k *ir it :: i.-*i:. FLOW PROCESS FROM NODE 3607.33 TO NODE 3787.69 IS CODE = 1 UPSTREAM NODE 3787.69 ELEVATION = 1051.41 (HYDRAULIC JUMP OCCURS) --------------------------------------------------------------- CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 182.82 CFS PIPE DIAMETER 60.00 INCHES PIPE LENGTH = 180.36 FEET MANNING'S N = .01300 --------------------------------------------------------------- HYDRAULIC JUMP: DOWNSTREAM RUN ANALYSIS RESULTS ----------------------------------------------_----- ------------ NORMAL DEPTH(FT) = 1.89 CRITICAL DEPTH(FT) 3.87 UPSTREAM CONTROL ASSUMED FLOWDEPTH(FT) 3.87 GRADUALLY VARIED FLOW PROFILE COMPUTED INFORMATION: Page 6 ------------------------------------------------------------------------------ DISTANCE FROM FLOW DEPTH VELOCITY SPECIFIC PRESSURE+ CONTROL(FT) (FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUNDS) .000 3.867 11.217 5.822 5746.39 .081 3.787 11.454 5.826 5750.31 .318 3.708 11.705 5.837 5761.50 .729 3.629 11.974 5.857 5780.36 1.333 3.550 12.261 5.885 5807.29 2.156 3.470 12.566 5.924 5842.75 3.224 3.391 12.892 5.973 5887.26 4.571 3.312 13.240 6.035 5941.38 6.237 3.233 13.612 6.111 6005.74 8.270 3.153 14.009 6.202 6081.06 10.728 3.074 14.434 6.311 6168.09 13.681 2.995 14.889 6.439 6267.74 17.217 2.916 15.377 6.589 6380.97 21.447 2.836 15.901 6.765 6508.90 26.512 2.757 16.465 6.969 6652.77 32.593 2.678 17.072 7.206 6814.01 39.935 2.599 17.727 7.481 6994.22 48.867 2.519 18.435 7.800 7195.24 59.858 2.440 19.203 8.169 7419.20 73.595 2.361 20.036 8.598 7668.50 91.148 2.281 20.944 9.097 7945.98 114.319 2.202 21.935 9.678 8254.89 146.489 2.123 23.019 10.356 8599.06 180.360 ------------------------------------------------------------------------------ 2.068 23.834 10.894 8861.13 HYDRAULIC JUMP: UPSTREAM RUN ANALYSIS RESULTS DOWNSTREAM CONTROL ASSUMED PRESSURE HEAD(FT) = 7.67 PRESSURE FLOW PROFILE COMPUTED INFORMATION: ----------------------------------------------------------- DISTANCE FROM PRESSURE VELOCITY SPECIFIC PRESSURE+ CONTROL(FT) HEAD(FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUNDS) .000 7.672 9.311 9.018 9635.42 54.506 5.000 9.311 6.346 6361.78 ASSUMED DOWNSTREAM PRESSURE HEAD(FT) = 5.00 GRADUALLY VARIED FLOW PROFILE COMPUTED INFORMATION: ------------------------------------------------------------------------------ DISTANCE FROM FLOW DEPTH VELOCITY SPECIFIC PRESSURE+ CONTROL(FT) (FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUNDS) 54.506 5.000 9.308 6.346 6361.78 55.346 4.955 9.322 6.305 6311.28 56.114 4.910 9.34E 6.267 6264.88 56.837 4.865 9.378 6.231 6221.25 57.522 4.819 9.417 6.197 6179.96 58.175 4.774 9.460 6.165 6140.79 58.798 4.729 9.508 6.134 6103.59 59.392 4.684 9.561 6.104 6068.28 59.959 4.639 9.618 6.076 6034.81 60.498 4.594 9.679 6.049 6003.13 61.011 4.548 9.745 6.024 5973.23 61.497 4.503 9.814 6.000 5945.10 61.956 4.458 9.887 5.977 5918.73 62.388 4.413 9.964 5.956 5894.14 62.792 4.368 10.045 5.936 5871.34 63.168 4.323 10.130 5.917 5850.34 63.514 4.277 10.219 5.900 5831.17 63.830 4.232 10.311 5.884 5813.85 64.115 4.187 10.408 5.870 5798.41 64.367 4.142 10.509 5.858 5784.90 Page 7 64.585 4.097 10.614 5.847 5773.33 64.768 4.052 10.723 5.838 5763.77 64.913 4.006 10.837 5.831 5756.24 65.020 3.961 10.955 5.826 5750.80 65.085 3.916 11.077 5.823 5747.50 65.108 3.871 11.205 5.822 5746.38 180_360 3.871 11.205 5.822 5746.38 -------- --- ---END OF HYDRAULIC JUMP ANALYSIS------------------------ PRESSURE+MOMENTUM BALANCE OCCURS AT 14.80 FEET UPSTREAM OF NODE 3607.33 DOWNSTREAM DEPTH = 6.946 FEET, UPSTREAM CONJUGATE DEPTH = 2.092 FEET ------- ---------------------------------------- ------------------------- NODE 3787.69 : HGL = < 1055.277>;EGL= < 1057.232>;FLOWLINE= < 1051.410> it it is is is is it ie ir',r is it ie it**i:isi:*it ie is it ie is it is is ie is it is*ic it is is it is is itit*ie is ie ie sY it sY is ie is it it it ie ie it****it it is it icx****i; is is it FLOW PROCESS FROM NODE 3787.69 TO NODE 3794.35 IS CODE = 5 --UPSTREAM NODE 3794.35 ELEVATION = 1051.48 (FLOW IS AT CRITICAL DEPTH) ---------------------------------------------- --- -------------- CALCULATE JUNCTION LOSSES: PIPE FLOW DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY UPSTREAM 172.93 (260.00) (DEGREES) E1051.48N DEPTH(FT.) (FT/SEC) .032 DOWNSTREAM 182.82 60.00 - 1051.41 3.87 11.208 LATERAL #1 6.24 24.00 45.00 1052.86 .88 1.986 LATERAL #2 3.65 21.00 85.00 1053.17 .70 1.517 Q5 .00===Q5 EQUALS BASIN INPUT=== LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: DY=(Q2*V2-Ql*V1*COS(DELTAl)-Q3*V3*COS(DELTA3)- Q4*V4*COS(DELTA4))/((A1+A2)*16.1)+FRICTION LOSSES UPSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00381 DOWNSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00552 AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS .00466 JUNCTION LENGTH = 6.66 FEET FRICTION LOSSES = .031 FEET ENTRANCE LOSSES = .000 FEET JUNCTION LOSSES = (DY+HV1-HV2)+(ENTRANCE LOSSES) JUNCTION LOSSES = ( .212)+( .000) = .212 --------------------------------------------- ---------------------- NODE 3794.35 : HGL = < 1056.177>;EGL= < 1057.444>;FLOWLINE= < 1051.480> is **i: *it is*ir it is is it*:t**ic k it it is#*ic i�ie icic it itic**ir it it it it it it ir**ic it is is ie is ic'.r is it it it it is is itit*it it***R-ir*it it it is it �•i: * FLOW PROCESS FROM NODE 3794.35 TO NODE 4247.67 IS CODE = 1 UPSTREAM NODE 4247.67 ELEVATION = 1055.28 (HYDRAULIC JUMP OCCURS) -------------------------------------------------------------- CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 172.93 CFS PIPE DIAMETER = 60.00 INCHES PIPE LENGTH = 453.32 FEET MANNING'S N = .01300 ----------------------------------------------------------------- HYDRAULIC JUMP: DOWNSTREAM RUN ANALYSIS RESULTS ----------------------------------------------- NORMAL DEPTH(FT) = 3.16 CRITICAL DEPTH(FT) = 3.77 UPSTREAM CONTROL ASSUMED FLOWDEPTH(FT) = 2.70 GRADUALLY VARIED FLOW PROFILE COMPUTED INFORMATION: ------------------------------------------------------------ DISTANCE FROM FLOW DEPTH VELOCITY SPECIFIC PRESSURE+ CONTROL(FT) (FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUNDS) .000 2.702 15.971 6.665 6133.59 9.322 2.720 15.838 6.617 6101.44 18.864 2.738 15.707 6.572 6070.16 28.646 2.756 15.579 6.527 6039.73 38.691 2.774 15.453 6.485 6010.13 49.025 2.793 15.329 6.444 5981.34 59.678 2.811 15.207 6.404 5953.36 70.685 2.829 15.087 6.366 5926.15 Page 8 82.087 93.934 2.847 2.866 14.970 14.854 6.329 5899.72 106.282 2.884 14.740 6.294 6.259 5874.04 5849.10 119.203 132.781 2.902 2.920 14.628 14.517 6.226 5824.89 147.124 2.938 14.409 6.195 6.164 5801.39 5778.59 162.365 178.675 2.957 2.975 14.302 14.197 6.135 5756.48 196.284 2.993 14.094 6.106 6.079 5735.05 5714.28 215.496 236.744 3.011 3.029 13.992 13.892 6.053 5694.17 260.658 3.048 13.793 6.028 6.004 5674.69 5655.85 288.217 321.059 3.066 3.084 13.696 13.601 5.980 5637.63 362.258 3.102 13.507 5.958 5.937 5620.02 5603.00 418.716 3203_127 3.120 13.414 13.380 5.916 5586.58 -453_-_-------- -------------------------------------------- 5.909 5580.68 HYDRAULIC JUMP: UPSTREAM RUN ANALYSIS RESULTS ------------------------------------------------------- DOWNSTREAM CONTROL ASSUMED FLOWDEPTH(FT) ___________________________ = 4.70 GRADUALLY VARIED FLOW -- ------------ PROFILE ------- --------------------------------- COMPUTED INFORMATION: DISTANCE FROM FLOW DEPTH CONTROL(FT) (FT) ---------------- VELOCITY (FT/SEC) ---- ------------------- SPECIFIC __ PRESSURE+ .000 4.697 9.029 ENERGY(FT) MOMENTUM(POUNDS) 5.964 5.472 4.660 9.072 5.939 5722.49 5692.67 10.769 15.901 4.623 4.586 9.118 9.166 5.915 5663.97 20.871 4.549 9.217 5.891 5.869 5636.38 5609.88 25.685 30.343 4.512 4.474 9.271 9.327 5.847 5584.49 34.847 4.437 9.385 5.826 5.806 5560.19 5536.99 39.196 43.389 4.400 4.363 9.447 9.510 5.787 5514.90 47.422 4.326 9.576 5.768 5.751 5493.92 5474.06 51.291 54.992 4.289 4.251 9.645 9.716 5.734 5455.35 58.519 4.214 9.789 5.718 5.703 5437.78 5421.38 61.862 65.013 4.177 4.140 9.866 9.945 5.689 5406.15 67.962 4.103 10.026 5.677 5.665 5392.13 5379.33 70.696 73.200 4.066 4.029 10.110 10.197 5.654 5.644 5367.77 75.457 3.991 10.287 5.636 5357.47 5348.46 77.449 79.151 3.954 3.917 10.380 10.476 5.628 5340.75 80.538 3.880 10.574 5.622 5.617 5334.38 5329.37 81.578 82.235 3.843 3.806 10.676 10.781 5.614 5325.76 82.465 3.768 10.889 5.612 5.611 5323.57 5322.83 -----' 3.768 10.889 5.611 5322.83 --453_320------ ---END OF HYDRAULIC JUMP ANALYSIS---------------- _ PRESSURE+MOMENTUM BALANCE OCCURS ------- DEPTH = 4.512 ---------------------------------- AT 25.58 FEET UPSTREAM OF FEET, UPSTREAM CONJUGATE DEPTH NODE 3794.35 = 3.122 FEET NODE 4247.67 : HGL = < 1057.982>;EGL= < -------------------------------- 1061.945>;FLOWLINE= < 1055.280> #;; ;':„ �f:': it 4c�B:'ci:Yr':'c'.:iri:�4: is ir-k it e; is kic'r 4e�4r it 4r k it 4c 4r ir�ie:���r:rir*ir fc i:fc-.r:r:c�ir Yt 4c it:::s is it Yt�ir is it d: it is k::it ir':� FLOW PROCESS FROM NODE 4247.67 TO NODE 4252.33 IS CODE = 5 UPSTREAM NODE 4252.33 ------------------------------- ELEVATION = 1055.83 (FLOW IS SUPERCRITICAL) CALCULATE JUNCTION LOSSES: PIPE FLOW DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY Page 9 UPSTREAM 172.93 (254.00) (DEGREES) E1055.83N DEPTH(.) (F13.497 DOWNSTREAM 172.93 60.00 - 1055.28 3.77 LATERAL #1 .00 .00 .00 .00 15.976 .00 LATERAL #2 Q5 .00 .00 .00 .00 .000 .00 .000 .00===Q5 EQUALS BASIN INPUT=== LACFCD AND OCEMA DY=(Q2*V2-Q1*V1*COS(DELTAI)-Q3*V3*COS(DELTA3)- FLOW JUNCTION FORMULAE USED: 4irCOSMANNING)S/N(A1+A01300;1)FRICTIONN LOSS UPSTREAM: SLOPE ES DOWNSTREAM: MANNING'S N = .01300; FRICTION SLOPE= .00927 AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS .01361 JUNCTION LENGTH = 4.66 FEET .01144 FRICTION LOSSES -JUNCTION LOSSES = .053 FEET ENTRANCE LOSSES = (DY+HVl-HV2)+(ENTRANCE LOSSES) = .000 FEET JUNCTION LOSSES -------------------------- = ( .094)+( .000) = .094 ------------------------------------------ NODE 4252.33 : HGL = < 1059.209>;EGL= < 1062.038>;FLOWLINE= < 1055.830> k kirk irkkkkkkkkir ick irkkkkkiekkkkkkirkkkkirkkkic k irkkkkkkkkkkie 4tkkk; kkkkkkkkkk*kkkkkickkkk FLOW PROCESS FROM NODE 4252.33 TO NODE 4459.70 IS CODE = 1 --UPSTREAM-NODE- 4459.70 ELEVATION = ------------------------ -------------------------------------- 1057.80 (FLOW IS SUPERCRITICAL) CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = PIPE LENGTH = 172.93 CFS 207.37 FEET PIPE DIAMETER = MANNING'S 54.00 INCHES -------------------------------------- N = .01300 NORMAL DEPTH(FT) ---------------------------------------------------------------------------- = 3.34 CRITICAL DEPTH(FT) = 3.82 UPSTREAM CONTROL ASSUMED FLOWDEPTH(FT) ----------------------------- 3.82 - GRADUALLY VARIED ------------ FLOW PROFILE COMPUTED - INFORMATION: DISTANCE FROM CONTROL(FT) ---------------- FLOW DEPTH VELOCITY (FT) (FT/SEC) - - ---------------------------------- SPECIFIC PRESSURE+ .000 3.823 12.003 ENERGY(FT) 6.062 MOMENTUM(POUNDS) .108 3.804 12.055 6.062 5610.75 5610.97 .444 1.023 3.785 12.108 3.766 12.162 6.063 6.064 5611.60 1.866 3.747 12.217 6.066 5612.66 5614.16 2.995 4.437 3.728 12.273 3.708 12.330 6.068 6.071 5616.09 6.224 3.689 12.388 6.074 5618.46 5621.27 8.391 10.982 3.670 12.448 3.651 12.508 6.078 5624.54 14.048 3.632 12.570 6.082 6.087 5628.25 5632.42 17.654 21.876 3.613 12.632 3,.593 12.696 6.092 5637.06 26.810 3.574 12.761 6.098 6.105 5642.16 5647.73 32.578 39.335 3.555 12.828 3.536 12.895 6.112 6.120 5653.79 47.288 3.517 12.964 6.128 5660.32 5667.35 56.716 68.011 3.498 13.033 3.479 13.105 6.137 5674.87 81.746 3.459 13.177 6.147 6.157 5682.89 5691.43 98.812 120.701 3.440 13.251 3.421 13.325 6.168 5700.48 150.210 3.402 13.402 6.180 6.193 5710.05 5720.15 193.626 3703_379- 3.383 13.479 13.493 6.206 5730.78 --------207_---------- -------------------------- 6.208 5732.73 NODE 4459.70 : HGL = < 1061.623>;EGL= < ---------------------- 1063.862>;FLOWLINE= < 1057.800> isi:i;kit it irk itkk �•kkitk kkkkkki.•kkkkkkkkkkkitk kicirkkkkkkkkirkkkit irkkkickkkkkkkkkkiti:kkkkkk'.t is it Page 10 FLOW PROCESS FROM NODE 4459.70 TO NODE 4459.70 IS CODE = 5 4459.70 --UPSTREAM-NODE- -------------------------- ELEVATION = 1057.80 (FLOW IS AT CRITICAL DEPTH) ------------------------------------ CALCULATE JUNCTION LOSSES: PIPE FLOW DIAMETER ANGLE FLOWLINE (CFS) (INCHES) (DEGREES) ELEVATION CRITICAL VELOCITY UPSTREAM 142.21 54.00 .00 1057.80 DEPTH(FT.) (FT/SEC) 3.50 DOWNSTREAM LATERAL #1 172.93 54.00 1057.80 30.72 24.00 8.941 3.82 12.007 LATERAL #2 45.00 1057.80 .00 .00 1.87 9.778 Q5 .00 .00 .00===Q5 EQUALS BASIN INPUT==-- .00 .000 LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: DY=(Q2*V2-Q1*V1*COS(DELTAl)-Q3*V3*COS (DELTA3)- Q4*V4*COS(DELTA4))/((Al+A2)*16.1)+FRICTION LOSSES UPSTREAM: MANNING'S N = .01300; FRICTION SLOPE = DOWNSTREAM: MANNING'S N = FRICTION .00523 .01300; SLOPE = AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS .00729 JUNCTION LENGTH .00626 = 1.00 FEET FRICTION LOSSES JUNCTION LOSSES = .006 FEET ENTRANCE LOSSES = (DY+HV1-HV2)+(ENTRANCE = .000 FEET --JUNCTION LOSSES ----------- LOSSES) = (--_223)+( .000) = .223 NODE 4459.70 : ------- _ ____ ------------------------ HGL = < 1062.844>;EGL= < 1064.085>;FLOWLINE= < 1057.800> FLOW PROCESS FROM NODE 4459.70 TO NODE 4719.80 IS CODE = 1 NODE 4719.80 --UPSTREAM ELEVATION = 1060.27 (HYDRAULIC JUMP OCCURS) -------------------- ------------------------------------------------ CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = PIPE LENGTH = 142.21 CFS PIPE DIAMETER = 260.10 FEET 54.00 INCHES --------------------------- MANNING'S N = .01300 --HYDRAULIC-JUMP_-DOWNSTREAM RUN ANALYSIS RESULTS ---------------------------------------------------- NORMAL DEPTH(FT) - = 2.89 - ------ CRITICAL DEPTH(FT) 3.50 UPSTREAM CONTROL ASSUMED FLOWDEPTH(FT) 2.90 --GRADUALLY VARIED ------------- FLOW PROFILE COMPUTED INFORMATION: ----------------------- DISTANCE FROM CONTROL(FT) FLOW DEPTH VELOCITY SPECIFIC (FT) (FT/SEC) ENERGY(FT) PRESSURE+ .000 2.898 13.133 5.577 MOMENTUM(POUNDS) 4.909 10.031 2.897 13.135 5.578 4473.95 4474.29 1S.385 2.897 13.137 5.578 2.896 13.140 5.579 4474.64 20.992 26.877 2.896 13.142 5.579 4474.98 4475.32 33.068 2.895 13.144 5.580 2.895 13.147 5.580 4475.66 39.600 46.509 2.894 13.149 5.581 4476.01 4476.35 53.844 2.894 13.151 5.581 2.894 13.154 5.582 4476.69 61.657 70.017 2.893 13.156 5.582 4477.04 4477.38 79.002 2.893 13.158 5.583 2.892 13.161 5.583 4477.73 88.714 99.280 2.892 13.163 5.584 4478.07 4478.42 110.862 2.891 13.165 5.584 2.891 13.168 5.585 4478.76 123.675 138.011 2.890 13.170 5.585 4479.11 4479.45 154.275 2.890 13.172 5.586 2.890 13.175 4479.80 173.065 5.586 2.889 13.177 5.587 4480.15 4480.49 195.305 222.544 2.889 13.179 5.587 2.888 13.182 4480.84 5.588 4481.19 Page 11 257.694 2.888 2.888 13.184 13.184 5.589 4481.54 --------260.100 ---------------------------------- 5.589 4481.55 ---------------------------------- HYDRAULIC JUMP: UPSTREAM RUN ANALYSIS RESULTS DOWNSTREAM CONTROL ASSUMED PRESSURE HEAD(FT) = 5.04 PRESSURE FLOW ------------------------------ PROFILE COMPUTED INFORMATION: DISTANCE FROM CONTROL(FT) PRESSURE HEAD(FT) VELOCITY (FT/SEC) SPECIFIC ______ - PRESSURE+ .000 5.043 8.942 ENERGY(FT) 6.285 MOMENTUM(POUNDS) 127.372 4.500 8.942 5.741 5236.48 4697.16 ASSUMED DOWNSTREAM PRESSURE HEAD(FT) = 4.50 GRADUALLY VARIED FLOW PROFILE COMPUTED INFORMATION: ------------- DISTANCE FROM CONTROL(FT) ---------------------- FLOW DEPTH (FT) VELOCITY (FT/SEC) SPECIFIC PRESSURE+ 127.372 4.500 8.939 ENERGY(FT) 5.741 MOMENTUM(POUNDS) 4697.16 135.453 142.519 4.460 4.420 8.951 8.975 5.705 4661.13 149.034 4.381 9.004 5.672 5.640 4628.06 4597.00 155.134 160.893 4.341 4.301 9.040 9.080 5.610 5.582 4567.63 166.357 4.261 9.125 5.555 4539.78 4513.35 171.554 176.507 4.221 4.181 9.175 9.228 5.529 4488.28 181.228 4.142 9.285 5.504 5.481 4464.52 4442.05 185.728 190.012 4.102 4.062 9.345 9.410 5.459 4420.85 194.082 4.022 9.478 5.438 5.418 4400.92 4382.24 197.937 201.575 3.982 3.942 9.549 9.624 5.399 4364.83 204.990 3.903 9.703 5.382 5.365 4348.70 4333.84 208.176 211.120 3.863 3.823 9.786 9.872 5.351 4320.29 213.812 3.783 9.961 5.337 5.325 4308.05 4297.14 216.234 218.369 3.743 3.703 10.055 10.152 5.314 4287.60 220.193 3.664 10.253 5.305 5.297 4279.44 4272.69 221.679 222.794 3.624 3.584 10.358 10.468 5.291 4267.38 223.498 3.544 10.581 5.286 5.284 4263.54 4261.22 223.745 260.100 3.504 3.504 10.699 10.699 5.283 4260.43 ------------------------END 5.283 4260.43 OF HYDRAULIC PRESSURE+MOMENTUM BALANCE JUMP ANALYSIS -------------_-_-_ OCCURS -------DOWNSTREAM DEPTH = 4.205 FEET, --------------------------- AT 173.63 FEET UPSTREAM OF NODE 4459.70 UPSTREAM CONJUGATE DEPTH = 2.892 FEET NODE 4719.80 : HGL = < 1063.168>;EGL= < 1065.847>;FLOWLINE= < 1060.270> :4 � ir'k ie � is is it it it is is i; it it it kic it irir is is it is it is is is it is Yc is is it it it ie is ic_ic it is ie it � it it ie is is is ie is is it it it it it it it is it ie � ie is ie it it it is is is it is FLOW PROCESS FROM NODE 4719.80 TO NODE 4724.46 IS CODE = 5 --UPSTREAM NODE -------------------------------- 4724.46 ELEVATION = 1060.37 (FLOW IS SUPERCRITICAL) CALCULATE JUNCTION LOSSES: PIPE FLOW DIAMETER (CFS) (INCHES) ANGLE (DEGREES) FLOWLINE CRITICAL VELOCITY ELEVATION UPSTREAM 142.21 54.00 .00 DEPTH(FT.) 1060.37 (FT/SEC) 3.50 13.027 DOWNSTREAM 142.21 54.00 - 1060.27 3.50 13.137 LATERAL #1 LATERAL #2 .00 24.00 45.00 1061.70 .00 .000 Q5 .00 .00 .00 .00===Q5 EQUALS BASIN .00 INPUT=== .00 .000 Page 12 LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: DY=(Q2*V2-Q1*Vl*COS(DELTAl)-Q3irV3*COS(DELTA3)- Q4*V4*COS(DELTA4))/((A1+A2)*l6.1)+FRICTION LOSSES UPSTREAM: MANNING'S DOWNSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00920 N = FRICTION AVERAGED FRICTION .01300; SLOPE = .00939 SLOPE IN JUNCTION ASSUMED AS JUNCTION LENGTH = 4.66 FEET .00929 FRICTION LOSSES = JUNCTION LOSSES = .043 FEET ENTRANCE LOSSES = .000 (DY+HV1-HV2)+(ENTRANCE FEET JUNCTION LOSSES = ------------------------ ( .077)+( .000) = LOSSES) .077 ------------------------------ NODE 4724.46 : HGL = < 1063.289>;EGL= _ < 1065.924>;FLOWLINE= < _ ____ 1060.370> icx:Yiciriciciciciricic*iriricieiriciririeiricieicieicieiciririeiriciciciririrsYiriciririeicieirie&ieicicicicisiciricirie***ieiriririeiririciriciricie FLOW PROCESS FROM 4974.99 NODE 4724.46 TO NODE 4974.99 IS CODE _ 1 --UPSTREAM-NODE ELEVATION = ---------------------------------------- 1062.75 (FLOW IS SUPERCRITICAL) CALCULATE FRICTION LOSSES(LACFCD): --------------------------- PIPE FLOW = LENGTH = 142.21 CFS 250.53 FEET PIPE DIAMETER = 54.00 INCHES --PIPE- --------------------------------------------------- MANNING'S N = .01300 NORMAL DEPTH(FT) = --------------------------- 2.89 ----- CRITICAL DEPTH(FT) = - - -------- 3.50 UPSTREAM CONTROL ASSUMED FLOWDEPTH(FT) 3.50 __________ VARIED FLOW -- ------------- -GRADUALLY PROFILE COMPUTED ----------------- INFORMATION: DISTANCE FROM CONTROL(FT) FLOW DEPTH VELOCITY (FT) (FT/SEC) ------------------------------------ SPECIFIC PRESSURE+ .000 3.504 10.699 ENERGY(FT) MOMENTUM(POUNDS) 5.283 .102 3.479 10.774 5.283 4260.43 4260.74 .417 .966 3.455 10.851 3.430 10.929 5.284 4261.66 1.768 3.405 11.010 5.286 5.289 4263.22 4265.42 2.848 4.235 3.381 11.092 3.356 11.176 5.292 4268.26 5.960 3.331 11.263 5.297 5.302 4271.77 4275.96 8.062 10.587 3.306 11.351 3.282 11.441 5.308 4280.83 13.589 3.257 11.533 5.315 5.323 4286.40 4292.68 17.134 21.302 3.232 11.627 3.207 11.723 5.333 4299.69 26.194 3.183 11.822 5.343 5.354 4307.44 4315.94 31.936 38.690 3.158 11.922 3.133 12.025 5.367 4325.21 46.671 3.109 12.130 5.380 5.395 4335.27 4346.13 56.169 67.590 3.084 12.238 3.059 12.348 5.411 4357.80 81.532 98.919 3.034 12.461 5.428 5.447 4370.31 4383.68 121.301 3.010 12.576 2.985 12.694 5.467 5.489 4397.92 151.583 196.294 2.960 12.814 5.512 4413.04 4429.08 250_5302_919 2.935 12.938 13.023 5.536 5.554 4446.05 ---------- ----------------------------- 4458.09 NODE 4974.99 : HGL = < 1066.254>;EGL= < ------------------ 1068.033>;FLOWLINE= < 1062.750> *ic*ic*i:ic*-k*�,.;*;'t°k is ie*is it is*ir*ir*ir*ic*st it it it it ie°k it it it it*it is it is it is it it it is it it it is it it*ir is k-k ie it is*ie it it it is ie is is*ir* FLOW PROCESS FROM NODE 4974.99 TO NODE UPSTREAM NODE 4974.99 4974.99 IS CODE = 5 -------------------------------------- ELEVATION = 1062.75 (FLOW IS AT CRITICAL DEPTH) CALCULATE JUNCTION LOSSES: --------------------------- PIPE FLOW DIAMETER ANGLE FLOWLINE CRITICAL (CFS) (INCHES) (DEGREES) ELEVATION VELOCITY DEPTH(FT.) (FT/SEC) Page 13 UPSTREAM 109.34 54.00 .00 1062.75 3.08 6.875 DOWNSTREAM LATERAL #1 142.21 54.00 1062.75 3.50 32.87 24.00 45.00 10.702 LATERAL #2 1062.75 1.90 .00 .00 .00 10.463 Q5 .00 .00 .00===Q5 EQUALS BASIN INPUT=== .000 LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: DY=(Q2*V2-Ql*V1*COS(DELTAI)-Q3*V3*COS (DELTA3)- Q4*V4 *COS (DELTA4))/((A1+A2)*16.1)+FRICTION LOSSES UPSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00309 DOWNSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00578 AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS JUNCTION LENGTH .00444 = 1.00 FEET FRICTION LOSSES JUNCTION LOSSES = .004 FEET ENTRANCE LOSSES = .000 = (DY+HV1-HV2)+(ENTRANCE LOSSES) FEET JUNCTION LOSSES ----------------------- = ( .081)+( .000) = .081 NODE 4974.99 : -------------------------------- HGL = < 1067.380>;EGL= < 1068.114>;FLOWLINE= < _ ____ 1062.750> *ir 9r iric 4c:c;r*:r sY 4r**ic it it is 4c fr 4e 4c 4r is it*Yt fair sY*Tc is it 4r ie it fe ic:r is is 4r is ie Y***ir*4r:r*4c ie ie*4r is ie*ie it :r**Yr it 4c it it 'r is is :c is ie FLOW PROCESS FROM NODE 4974.99 TO NODE 5219.37 IS CODE = 1 --UPSTREAM-NODE- 5219.37 ----------------- ELEVATION = 1065.02 (HYDRAULIC JUMP OCCURS) CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = PIPE LENGTH - 109.34 CFS PIPE DIAMETER = 54.00 INCHES 244.38 FEET ------------------------------------------- MANNING, S N = .01300 HYDRAULIC JUMP: ------------------------------------------------ ----------------------------------- DOWNSTREAM RUN ANALYSIS RESULTS NORMAL DEPTH(FT) = 2.45 CRITICAL DEPTH(FT) - - 3.08 UPSTREAM CONTROL ASSUMED FLOWDEPTH(FT) = 2.15 --GRADUALLY VARIED ------------------------------- FLOW PROFILE COMPUTED INFORMATION: DISTANCE FROM CONTROL(FT) ---------------------------------- _ FLOW DEPTH VELOCITY SPECIFIC PRESSURE+ (FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUNDS) 7.005 2.158 14.500 5.425 3502.68 14.263 21.702 2.170 14.395 5.390 2.183 3486.18 29.370 14.291 5.356 2.195 14.189 5.323 3470.03 3454.23 37.291 45.492 2.207 14.088 5.291 2.219 13.988 3438.78 54.002 5.260 2.232 13.891 5.229 3423.67 3408.90 62.857 72.101 2.244 13.794 5.200 2.256 3394.45 81.783 13.699 5.172 2.268 13.605 5.144 3380.34 3366.54 91.965 102.721 2.281 13.512 5.117 2.293 3353.05 114.143 13.421 5.091 2.305 13.330 5.066 3339.88 3327.01 126.349 139.489 2.317 13.241 5.042 2.330 13.154 3314.44 153.760 5.018 2.342 13.067 4.995 3302.16 3290.18 169.430 186.875 2.354 12.981 4.972 2.366 3278.48 206.644 12.897 4.951 2.379 12.814 4.930 3267.06 3255.92 229.591 244.3802_397 2.391 12.732 4.909 3245.06 -------- ---------- 12.688 4.899 ------------------------------------------------- 3239.34 HYDRAULIC JUMP: UPSTREAM RUN ANALYSIS RESULTS DOWNSTREAM CONTROL ASSUMED PRESSURE HEAD(FT) 4.63 _____________________________________________ -- PRESSURE FLOW PROFILE COMPUTED INFORMATION: Page 14 ------------------------- DISTANCE FROM CONTROL(FT) PRESSURE HEAD(FT) VELOCITY (FT/SEC) ________ SPECIFIC ____ PRESSURE+ .000 4.630 6.875 ENERGY(FT) 5.364 MOMENTUM(POUNDS) 20.971 -4.500 6.875 5.234 3818.66 3689.67 ASSUMED DOWNSTREAM PRESSURE HEAD(FT) ---------------- ------------------------------=---------------------- 4.50 GRADUALLY VARIED FLOW PROFILE ------ ---------- COMPUTED INFORMATION: ____ ___ ____ DISTANCE FROM CONTROL(FT) FLOW DEPTH (FT) ______ VELOCITY (FT/SEC) SPECIFIC ENERGY(FT) PRESSURE+ 20.971 4.500 6.873 5.234 MOMENTUM(POUNDS) 29.379 37.127 4.443 4.386 6.889 5.180 3689.67 3636.71 44.501 4.329 6.920 6.959 5.130 5.082 3586.86 51.583 58.419 4.272 4.215 7.006 5.035 3539.23 3493.55 65.033 4.158 7.060 7.120 4.990 4.946 3449.69 71.443 77.656 4.101 4.044 7.186 4.904 3407.60 3367.24 83.679 3.987 7.258 7.335 4.863 4.823 3328.63 89.511 95.149 3.930 3.873 7.418 4.785 3291.77 3256.68 100.590 3.816 7.507 7.601 4.749 4.714 3223.40 105.823 110.838 3.759 3.702 7.701 4.681 3191.96 3162.41 115.621 3.646 7.807 7.920 4.650 4.620 3134.80 120.153 124.412 3.589 3.532 8.038 4.592 3109.17 3085.60 128.373 3.475 8.163 8.295 4.567 4.544 3064.15 132.002 135.262 3.418 3.361 8.434 4.523 3044.88 3027.88 138.103 3.304 8.580 8.734 4.505 4.489 3013.22 140.468 142.285 3.247 3.190 8.897 4.477 3001.00 2991.30 143.463 3.133 9.067 9.247 4.467 4.461 2984.23 143.886 3.076 3.076 9.437 4.459 2979.91 2978.43 --------244_380 -----------END PRESSURE+MOMENTUM 9.437 OF HYDRAULIC JUMP 4.459 ANALYSIS------------------------ 2978.43 BALANCE OCCURS AT 84.68 FEET, FEET UPSTREAM OF NODE 4974.99 ----DOWNSTREAM -DEPTH -=-3_978- DEPTH = 2.346 FEET NODE 5219.37 : -UPSTREAM HGL = < 1067.166>;EGL= < 1070.481>;FLOWLINE= -CONJUGATE < 1065.020> 4r'.c;r sY 4c it �c stic it 4r s: sY it it it*ic::*„-ir it is it is it it*ir;r it it**sY �e it it 4r is is*4r FLOW PROCESS FROM is ic. is 9e{t°kic:c*'lc k Y is 4c*4c*'c ;c is it4r �'t :c 4e Yc it 4t it is 4r**� NODE 5219.37 TO NODE 5227.28 IS CODE = 5 5227.28 ELEVATION = 1065.56 (FLOW --UPSTREAM-NODE- - ------- ----- ------------- IS SUPERCRITICAL) CALCULATE JUNCTION LOSSES: ------- ------- ---- -------------- ---- PIPE FLOW DIAMETER (CFS) (INCHES) ANGLE (DEGREES) FLOWLINE CRITICAL VELOCITY ELEVATION UPSTREAM 109.34 48.00 DEPTH(FT.) 1065.56 (FT/SEC) DOWNSTREAM LATERAL #1 109.34 54.00 .00 1065.02 3.16 12.737 3.08 14.611 LATERAL #2 .00 36.00 .00 45.00 1066.20 .00 .000 Q5 .00 .00 00 .00===Q5 EQUALS BASIN INPUT=== 00 .000 LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: DY=(Q2*V2-Q1*V1*COS(DELTAI)-Q3*V3*COS(DELTA3)- Q4*V4*COS(DELTA4))/((A1+A2)*16.1)+FRICTION LOSSES UPSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .01031 DOWNSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .01455 AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS .01243 JUNCTION LENGTH = 7.91 FEET Page 15 FRICTION LOSSES = .098 FEET ENTRANCE LOSSES = .000 FEET JUNCTION LOSSES = (DY+HV1-HV2)+(ENTRANCE LOSSES) --JUNCTION LOSSES = ( .182)+( .000) = .182 --------------------- ------- -_ ------------------------ _ NODE 5227.28 HGL = < 1068.144>;EGL= < 1070.663>;FLOWLINE= < 1065.560> ____ '.t*ie�-ic.c it4:ir*i:;ri:ft:r iv it is it 4: Y is Y 4c fr it 4c is it fc:c;c is 4c 4t it it is is it it it Yt fc it is it is is it 4t it 4c 4c �r is 4cit*:c 9r is it it Yc is is is Yt it Y is is is 4r 4. it ie FLOW PROCESS FROM NODE 5227.28 TO NODE 5300.00 IS CODE = 1 --UPSTREAM-NODE 5300.00 ELEVATION = 1066.31 (FLOW IS SUPERCRITICAL) ----------- --------- -: CALCULATE FRICTION LOSSES(LACFCD)CD): ----------- ------- ------------------ ---- PIPE FLOW 109.34 CFS PIPE DIAMETER = 48.00 INCHES PIPE LENGTH 72.72 FEET MANNING'S N = .01300 ------------------------------ NORMAL DEPTH(FT) = 2,58 -- CRITICAL DEPTH(FT)H(FT) 3.16 ------------------------------ __________ UPSTREAM CONTROL ASSUMED FLOWDEPTH FT) 2.58 -- -GRADUALLY VARIED FLOW PROFILE COMPUTED INFORMATION ------------------------------- ______ ----------------------- DISTANCE FROM FLOW DEPTH VELOCITY SPECIFIC PRESSURE+ CONTROL(FT) (FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUNDS) .000 2.584 12.731 5.102 4.435 2.584 12.731 53302.49 9.059 .102 3302.4 2.584 12.731 5.102 3302.51 13.888 2.584 12.732 5.102 3302.52 18.943 2.584 12.732 5.103 24.243 2.584 12.732 5.103 3302.55 3302.5 5 29.817 2.584 12.732 7 5.103 3302. 35.694 2.584 12.732 .103 3302.58 41.906 2.584 12.732 5.103 3302.60 5.103 3302.6 48.496 2.584 12.732 1 5.103 3302.6 55.514 2.584 12.732 3 63.013 2.584 12.733 71.077 2.584 12.733 5.103 5.103 3302.66 66 -----72_720 2.584 12.733 5.103 3302.66 ------------------------------ ____ NODE 5300.00 HGL -------------' - < 1068.894>;EGL= < 1071.412>;FLOWLINE= < 1066.310> *fir :: it*u' ic*icic*;': 'c',; «'*ir is �-ir*ic irit#4r*4r it is is 4:ic:c*is 4t 4c*4r ic*it**it 4r �r it*4t it 4r 4t it is k Ye f:*ic is it *. tt Y it it 4c it Yc 4t it *Yc is ft* FLOW PROCESS FROM NODE 5300.00 TO NODE 5300.00 IS CODE = 5 --UPSTREAM-NODE -------- 5300.00 ELEVATION --1066.31 (FLOW IS SUPERCRITICAL) ------------------------------------ ----- CALCULATE JUNCTION LOSSES: ------------ PIPE FLOW DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY (CFS) (INCHES) (DEGREES) ELEVATION DEPTH(FT.) (FT/SEC) UPSTREAM 109.34 48.00 .00 1066.31 3.16 12.817 DOWNSTREAM 109.34 48.00 1066.31 3.16 12.735 LATERAL #1 .00 24.00 45.00 1067.61 .00 LATERAL #2 .00 .00 .00 .00 .00 .000 Q5 .00===Q5 EQUALS BASIN INPUT== .000 LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: DY=(Q2*V2-Q1*Vl*COS(DELTAl)-Q3*V3*CO5(DELTA3)- Q4*V4*COS(DELTA4))/((Al+A2)*16.1)+FRICTION LOSSES UPSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .01047 DOWNSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .01031 AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS .01039 JUNCTION LENGTH = 1.00 FEET FRICTION LOSSES = .010 FEET ENTRANCE LOSSES = .000 FEET JUNCTION LOSSES = (DY+HV1-HV2)(ENTRANCE LOSSES) + -JUNCTION LOSSES = ( .018)+( .000) = .018 ----------------------------- _ _ _ _____ NODE 5300.00 : HGL = < 1068.880>;EGL= < 1071.431>;FLOWLINE= < 1066.310> Page 16 t;. is icie is it it it is it it ie it it it it it is it it it it it & it it it it is it ie is is it ie ie ie it ie it is is is it is it ie it is it it it is it it ie is it it it it is ie it it is is is sY it it it ie is it it is it is FLOW PROCESS FROM NODE 5300.00 TO NODE 5574.44 IS CODE 5574.44 ELEVATION = 1069.05 (FLOW = 1 --UPSTREAM-NODE- ------ -------------------- IS SUPERCRITICAL) CALCULATE FRICTION LOSSES(LACFCD): ______ ---------- PIPE FLOW PIPE LENGTH = 109.34 CFS 274.44 FEET PIPE DIAMETER = 48.00 INCHES ---------------------------- N = .01300 NORMAL DEPTH(FT) = 2.61 --------------------------- ----MANNING'S _ _ CRITICAL DEPTH(FT) 3.16 UPSTREAM CONTROL ASSUMED FLOWDEPTH(FT) = 2.28 ----_ --GRADUALLY VARIED FLOW PROFILE -- - ------------- COMPUTED INFORMATION: DISTANCE FROM CONTROL(FT) ---------------- FLOW DEPTH (FT) VELOCITY (FT/SEC) SPECIFIC ______ PRESSURE+ .000 2.279 14.780 ENERGY(FT) 5.673 MOMENTUM(POUNDS) 6.990 14.162 2.292 2.306 14.675 5.638 3584.53 3568.47 21.530 2.319 14.571 14.470 5.605 5.572 3552.80 29.115 36.936 2.332 2.346 14.369 5.541 3537.49 3522.55 45.020 2.359 14.271 14.173 5.510 5.480 3507.98 62.094 2.386 3493.76 88 3466.35 71.157 2.399 13.983 13.890 5.424 5.397 3453.15 80.632 90.575 2.413 2.426 13.798 5.371 34 0.29 3427.75 101.058 2.439 13.708 13.618 5.321 3415.54 112.166 124.010 2.453 2.466 13.531 5 297 3403.64 3392.05 136.729 2.479 13.444 13.359 5.252 3380.77 150.511 165.605 2.493 2.506 13.275 5.210 3369.79 3359.10 182.364 2.519 13.192 13.110 5.190 338.71 201.305 223.226 2.533 2.546 13.030 5.171 3338.60 3328.78 249.467 2.560 12.950 12.872 5.152 5.134 3319.24 274.440 --------------- 2.570 12.813 5.121 3312.22 3312.22 NODE 5574.44 : HGL = < 1071.329>;EGL= < 1074.723>;FLOWLINE= < 1069.050> .c'`..•iri;.tir'k..ic.r it is i;��ir ic��ir �•ir �4 it is it it is icic it is FLOW PROCESS FROM ie is is it is it it i; is is it is it it it is is is i; is is it i.•ir it ie it ie it it it is ic�ic it is it it icic i; ki; is NODE 5574.44 TO NODE 5602.48 IS CODE NODE ELEVATION = N 1069.34 (FLOW = 3 --UPSTREAM - --5602_48- - - ----------------------------- , IS SUPERCRITICAL) CALCULATE PIPE -BEND LOSSES(OCEMA): ------ PIPE FLOW = CENTRAL ANGLE _ 109.34 CFS DEGREES PIPE DIAMETER = 48.00 INCHES PIPE LENGTH = ------------------------------ .000 28.04 FEET MANNING'S N = .01300 NORMAL DEPTH(FT) = 2.58 ---------------------_-------- CRITICAL DEPTH(FT) 3.16 UPSTREAM CONTROL ASSUMED FLOWDEPTH(FT) = 2.23 --_----- --GRADUALLY-VARIED --- FLOW PROFILE COMPUTED INFORMATION: DISTANCE FROM CONTROL(FT) -------------------------- FLOW DEPTH VELOCITY (FT) (FT/SEC) SPECIFIC PRESSURE+ .000 2.226 15.213 ENERGY(FT) 5.822 MOMENTUM(POUNDS) 7.233 14.652 2.240 2.254 15.094 5.780 5222 3633. 3647 .9 22.272 2.269 14.978 14.863 5.740 5.701 3615 .1 ---- -----28.040 2.279 14.780 5.673 3597.36 3584.53 Page 17 NODE 5602.48 : HGL = < 1071. 566>; EGL= < 1075. 162>; FLOWLINE= < 1069.340> it it ie is it it it it ie sY it is is is it is is it it it it it is is is it it it is it is it is ie it Yt it it ir$ic it it it it is it it it it is it ie is ft it is is it is it it ie it is is is it it is it ie it it it it ie it FLOW PROCESS FROM NODE 5602.48 TO NODE 5607.14 IS CODE = 5 --UPSTREAM-NODE- 5607.14 ELEVATION = 1069.88 (FLOW IS SUPERCRITICAL) ------ -------------------------------- CALCULATE JUNCTION LOSSES: -------------- PIPE FLOW FLOW DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY (CFS) (INCHES) (DEGREES) ELEVATION DEPTH(FT.) (FT/SEC) UPSTREAM 109.34 42.00 DOWNSTREAM .00 1069.88 3.16 11.951 109.34 48.00 - 1069.34 3.16 15.218 LATERAL #1 .00 .00 .00 .00 .00 LATERAL #2 .00 .00 .00 .00 .000 '00 •000 Q5 •00===Q5 EQUALS BASIN INPUT=== LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: DY=(Q2*V2-Q1*Vl*COS(DELTAI)-Q3*V3*COS (DELTA3)- Q4*V4*COS(DELTA4))/((A1+A2)*16.1)+FRICTION LOSSES UPSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .01036 DOWNSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .01626 AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS .01331 JUNCTION LENGTH = 4.66 FEET FRICTION LOSSES = .062 FEET ENTRANCE LOSSES .000 FEET JUNCTION LOSSES = (DY+HV1-HV2)+(ENTRANCE LOSSES) -JUNCTION LOSSES = ( .100)+( .000) = .100 ------- ------------- ------- --- ____ -------------------- _ _ NODE 5607.14 : HGL = < 1073.044>;EGL= < 1075.262>;FLOWLINE= < 1069.880> ., i:it*Yc*it it it *ic it it it*ic*ic it it ir'.tit*ir it ie it it it is****it is it is is*7r it is ie*ic it ir°k is is ie ic'.c it Yt it*ir*ir it -k is it it it it sk it it it***ic is FLOW PROCESS FROM NODE 5607.14 TO NODE 5748.25 IS CODE = 3 --UPSTREAM -NODE 5748.25 ELEVATION = 1071.30 (FLOW IS SUBCRITICAL) ---------------------------------------- _ ___ CALCULATE PIPE -BEND LOSSES(OCEMA): --- PIPE FLOW = 109.34 CFS PIPE DIAMETER = 42.00 INCHES CENTRAL ANGLE = 2.000 DEGREES MANNING'S N = .01300 PIPE LENGTH = 141.11 FEET ===> NORMAL PIPEFLOW IS PRESSURE FLOW --------------------------- ___ NORMAL DEPTH(FT) = 3.50 = CRITICAL DEPTH(FT)3.16 DOWNSTREAM CONTROL ASSUMED FLOWDEPTH(FT) = 3.16 ---------------- -----------------------______------------ - --------------- ----GRADUALLY- VARIED FLOW PROFILE COMPUTED INFORMATION: --------------------------------------- ____ DISTANCE FROM FLOW DEPTH VELOCITY SPECIFIC PRESSURE+ CONTROL(FT) (FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUNDS) .000 3.164 11.947 5.382 .653 3.177 11.911 3385.14 2.814 3.191 11.876 5.382 382 3385.45 6.821 3.204 11.842 5.383 3385.97 13.053 3.218 11.809 3385.70 21.903 3.231 11.777 5.384 3387.64 33.734 3.244 11.746 5.388 3388.79 48.797 3.258 11.715 5.390 3390.15 67.142 3.271 11.686 3391.74 88.536 3.285 11.657 5.396 3393.54 112.430 3.298 11.629 5.400 3395.56 138.026 3.312 11.603 5.403 3397.1 141.110 3.313 11.600 5.404 3398.08 -------_--_ _ _ 3398.08 --------------- NODE 5748.25 : HGL = < 1074.613>;EGL= .< 1076.704>;FLOWLINE= < 1071.300> i:it*it it i:'..'ici: it is i:*it it i;it**:tic ititir*ir is it::ir**ir it it*ic irir it it is it it is it is is*�k it icir is it*ic is it it it it it is *ic it *i: ie it it is is it** FLOW PROCESS FROM NODE 5748.25 TO NODE 5895.25 IS CODE = 1 UPSTREAM NODE 5895.2S ELEVATION = 1072.77 (FLOW IS SUBCRITICAL) Page 18 --------------------------------------------------------------------- CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW PIPE LENGTH 109.34 CFS 147.00 FEET PIPE DIAMETER = 42.00 INCHES MANNING'S ===> NORMAL PIPEFLOW IS PRESSURE FLOW --------------------------------- N = .01300 NORMAL DEPTH(FT) = 3.50 __ CRITICAL DEPTH(FT) -3. 3.16 DOWNSTREAM CONTROL ASSUMED FLOWDEPTH(FT) _____ ------------------------------- 3.31 --GRADUALLY VARIED FLOW PROFILE COMPUTED INFORMATION: ------ DISTANCE FROM CONTROL(FT) FLOW DEPTH (FT) ______ VELOCITY (FT/SEC) _____ SPECIFIC PRESSURE+ .000 3.313 11.600 ENERGY(FT) MOMENTUM(POUNDS) 5.404 10.442 21.060 3.321 3.328 11.585 5.406 3398.08 3399.44 31.773 3.336 11.571 11.558 5.409 5.411 3400.88 42.501 53.173 3.343 11.544 5.414 3402.38 3403.96 63.724 3.351 3.358 11.531 11.519 5.417 3405.62 74.100 84.255 3.366 11.506 5.420 5.423 3407.35 3409.16 94.151 3.373 3.381 11.494 11.483 5.426 3411.05 103.759 3.388 11.471 5.429 5.433 3413.01 113.058 122.031 3.395 11.461 5.436 3415.07 3417.20 130.670 3.403 3.410 11.450 11.440 5.440 5.444 3419.42 138.968 146.924 3.418 3.425 11.430 5.448 3421.73 3424.14 3.425 11.421 11.421 5.452 5.452 3426.64 -147_000 --------------------------- 3426.66 NODE 5895.25 : --------------------- HGL = < 1076.195>;EGL= < _ _ ___ _ ____ 1078.222>;FLOWLINE= < 1072.770> FLOW PROCESS FROM NODE 5895.25 5895.25 TO NODE 5895.25 IS CODE = 5 --UPSTREAM-NODE- ------------ ELEVATION = 1072.77 (FLOW IS SUBCRITICAL) ------ -------------------------- CALCULATE JUNCTION LOSSES: ________ ---------- PIPE FLOW DIAMETER 109.34 (242.00) ANGLE FLOWLINE CRITICAL (DEGREOEOS) ELEVATION VELOCITY UPSTREAM DEPTH(FT.) (F11.392 DOWNSTREAM LATERAL #1 109.34 42.00 - 1072.77 3.16 11.425 LATERAL #2 .00 .00 .00 .00 .00 .00 .00 .000 Q5 .00 .00 .00 .00===Q5 EQUALS BASIN INPUT=== .000 LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: DY=(Q2*V2-Q1*Vl*COS(DELTAI)-Q3*V3*Cos (DELTA3)- Q4*V4 *COS (DELTA4))/((Al+A2)*16.1)+FRICTION LOSSES UPSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .01078 DOWNSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .01055 AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS .01066 JUNCTION LENGTH = 1.00 FEET FRICTION LOSSES = .011 FEET ENTRANCE LOSSES = .000 FEET JUNCTION LOSSES = (DY+HV1-HV2)+(ENTRANCE LOSSES) JUNCTION LOSSES = ( .019)+( .000) = .019 ------------------------------- _ ____ -------------------- NODE 5895.25 : HGL = < 1076.226>;EGL= < 1078.241>;FLOWLINE= < 1072.770> FLOW PROCESS FROM NODE 5895.25 TO NODE 5947.67 IS CODE = 1 --UPSTREAM-NODE 5947.67 ELEVATION = 1073.29 (FLOW UNSEALS IN REACH) ----------- -------------- CALCULATE FRICTION LOSSES(LACFCD): Page 19 PIPE FLOW = PIPE LENGTH = 109.34 CFS 52.42 FEET PIPE DIAMETER = 42.00 INCHES ===> NORMAL PIPEFLOW IS PRESSURE FLOW ------------------------------ MANNING'S N = .01300 NORMAL. DEPTH(FT) --------------- ---------------------------------------------- = 3.50 ------ CRITICAL DEPTH(FT) -- 3.16 DOWNSTREAM CONTROL ASSUMED FLOWDEPTH(FT) = 3.46 _ --GRADUALLY VARIED -- - ------------ FLOW PROFILE COMPUTED INFORMATION: DISTANCE FROM CONTROL(FT) FLOW DEPTH (FT) VELOCITY (FT/SEC) SPECIFIC PRESSURE+ .000 3.456 11.389 ENERGY(FT) MOMENTUM(POUNDS) 5.471 1.379 2.745 3.457 3.459 11.387 5.472 3437.86 3438.58 4.096 3.461 11.385 11.384 5.473 5.474 3439.30 5.433 6.757 3.463 3.464 11.382 5.476 3440.03 3440.77 8.065 3.466 11.381 11.379 5.477 5.478 3441.52 9.360 10.640 3.468 3.470 11.378 5.479 3442.28 3443.04 11.906 3.472 11.376 11.375 5.481 5.482 3443.81 13.157 14.394 3.473 3.475 11.374 5.483 3444.59 3445.38 15.615 3.477 11.373 11.371 5.485 5.486 3446.18 16.822 18.014 3.479 11.370 5.487 3446.99 3447.80 19.190 3.480 3.482 11.369 11.368 5.489 3448.63 20.350 21.495 3.484 11.367 5.490 5.492 3449.47 3450.32 22.623 3.486 3.488 11.366 11.365 5.493 3451.18 23.734 24.828 3.489 11.364 5.495 5.496 3452.06 3452.94 25.904 3.491 3.493 11.364 11.363 5.497 34S3.84 26.959 3.495 11.362 5.499 5.501 3454.76 27.994 29.004 3.496 11.362 5.502 3455.70 3456.65 29.979 3.498 3.500 11.361 11.361 5.504 3457.63 FLOW IS UNDER PRESSURE 5.505 3458.65 ---------52_420---- 3.663 ------------------------------- 11.365 5.669 3556.79 NODE 5947.67 : HGL = < 1076.953>;EGL= < _ 1078.959>;FLOWLINE= < 1073.290> FLOW PROCESS FROM NODE 5947.67 TO NODE UPSTREAM NODE 5952.33 ELEVATION = 1073.33 5952.33 IS CODE = 5 (FLOW - ------------------------------- IS UNDER PRESSURE) CALCULATE JUNCTION LOSSES: __ ----------'- PIPE FLOW DIAMETER (95.50 (I42.00) ANGLE (DEGR.0E00) FLOWLINE CRITICAL E1073.33N VELOCITY UPSTREAM DEP3.0(2T.) (FT9.926 DOWNSTREAM LATERAL #1 109.34 42.00 13.84 24.00 1073.29 3.16 11.365 LATERAL #2 .00 .00 45.00 1073.50 1.34 4.405 Q5 .00 .00===Q5 EQUALS BASIN .00 .00 INPUT=== .000 LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: DY=(Q2*V2-Ql*vl*COS(DELTAI)-Q3*V3 *COS (DELTA3)- UPSTREAM4*COSMANNING'S/N(A1+A01300;1)FRICTIONNSLOPEES .00901 DOWNSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .01181 AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS .01041 JUNCTION LENGTH = 4.66 FEET FRICTION LOSSES = .049 FEET ENTRANCE LOSSES = .000 FEET JUNCTION LOSSES = (DY+HV1-HV2)+(ENTRANCE LOSSES) Page 20 --JUNCTION LOSSES = ( .385)+( .000) = .385 ------- ------ _______ _ ------------ NODE 5952.33 HGL - < 1077.814>;EGL= < 1079.344>;FLOWLINE= < 1073.330> ieieirYciritirieiririeiairYeYrieir*iei:*ieYrYrYric*isir****Yr*ic*ie*YtYc*YtYrYrirYrieYeifieieYrieicieieirit*it*irfr**Yr*ic***irYricieieir FLOW PROCESS FROM NODE 5952.33 TO NODE 6132.50 IS CODE = 1 UPSTREAM - NODE 6132.50 ELEVATION = 1074.84 (FLOW IS UNDER PRESSURE) -------------- ---------- ---- ------------- ------- --------- ---------- --- CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW 95.50 CFS PIPE DIAMETER = 42.00 INCHES PIPE LENGTH = 180.17 FEET MANNING'S N = .01300 SF=(Q/K)**2 = (( 95.50)/( 1006.074))**2 = .00901 HF=L*SF = ( 180.17)*( .00901) = 1.623 -------------------------- _ ____ NODE 6132.50 : HGL = < 1079.437>;EGL= < 1080.967>;FLOWLINE= < 1074.840> is Ye it ie it it Yr is Yr it it is it it eY it it it ir:Y*Yr Yt***�-******.**ir it it Ye is it is is it it ir-k it ie it it Yr it is is*ir Yr it ie**ir*ie it*}*****Yc is it it it FLOW PROCESS FROM NODE 6132.50 TO NODE 6132.50 IS CODE = 5 --UPSTREAM-NODE- 6132.50 ELEVATION = 1074.84 (FLOW IS UNDER PRESSURE) ---- ---- CALCULATE JUNCTION LOSSES: -------------------- ----- ------- --------- ---------- --- PIPE FLOW DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY (CFS) (INCHES) (DEGREES) ELEVATION DEPTH(FT.) (FT/SEC) UPSTREAM 95.50 42.00 .00 1074.84 3.02 9.926 DOWNSTREAM 95.50 42.00 1074.84 3.02 LATERAL #1 .00 24.00 45.00 1075.91 .00 9.926 LATERAL #2 .00 .00 .00 00 .000 Q5 .00===Q5 EQUALS BASIN INPUT=== '00 .000 LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: DY=(Q2*V2-Q1*Vl*COS(DELTAI)-Q3*V3*COS(DELTA3)- Q4*V4*COS(DELTA4))/((A1+A2)*16.1)+FRICTION LOSSES UPSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00901 DOWNSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00901 AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS .00901 JUNCTION LENGTH = 1.00 FEET FRICTION LOSSES = .009 FEET ENTRANCE LOSSES = .000 FEET JUNCTION LOSSES = (DY+HV1-HV2)+(ENTRANCE LOSSES) --JUNCTION- ------------------------ LOSSES = ( .009)+( .000) .009 ------------------------ _ _ __ ____ NODE 6132.50 : HGL = < 1079.446>;EGL= < 1080.976>;FLOWLINE= < 1074.840> sk„•i:iri: Yr it i.•i:it****�•**ie it is ir***iri.•*it**i:',r*�-is*�•**ir*ici.•*ir *ir it �•*ir****ic �•***s: it*ti �-*ir*ir**ir is FLOW PROCESS FROM NODE 6132.50 TO NODE 6270.81 IS CODE = 1 UPSTREAM -------- NODE 6270.81 ELEVATION = 1076.00 (FLOW IS UNDER PRESSURE) ------------------------------------------------------------- CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW 95.50 CFS PIPE DIAMETER = 42.00 INCHES PIPE LENGTH = 138.31 FEET MANNING'S N = .01300 SF=(Q/K)**2 = CC 95.50)/( 1006.082))**2 = .00901 HF=L*SF = ( 138.31)*( .00901) = 1.246 ------------- _ _ NODE 6270.81 : HGL = < 1080.693>;EGL= < 1082.222>;FLOWLINE= < 1076.000> '.•ir�•i;ir*Y:ir**ir Yr �•iri:i:ic*�•i: it ie is is ie it*::*ir is Yr*ir Yc*ir is is �•i:****ir*Yr Yr is Ye Y:ire•**ir*Yc it it***ir ic�•ic*i: Ye *ir ie**ie is FLOW PROCESS FROM NODE 6270.81 TO NODE 6285.81 IS CODE = 3 UPSTREAM --- NODE 6285.81 ELEVATION = 1076.32 (FLOW IS UNDER PRESSURE) ---------------- ___________________ CALCULATE PIPE -BEND LOSSES(OCEMA): - PIPE FLOW = 95.50 CFS PIPE DIAMETER = 42.00 INCHES CENTRAL ANGLE = 19.000 DEGREES MANNING'S N = .01300 PIPE LENGTH = 15.00 FEET BEND COEFFICIENT(KB) = .11487 FLOW VELOCITY = 9.93 FEET/SEC. VELOCITY HEAD = 1.530 FEET HB=KB*(VELOCITY HEAD) _ ( .115)*( 1.530) _ .176 SF=(Q/K)**2 = CC 95.50)/( 1005.999))**2 = .00901 Page 21 HF=L*SF = ( 15.00)*( .00901) = .135 --TOTAL-HEAD-LOSSES = HB + HF = ( .176)+( .135) _ .311 --------------------- _ _ __ NODE 6285.81 - HGL - ------------------------ < 1081.003>;EGL= < 1082.533>;FLOWLINE= < 1076.320> it it is it it is iir it it*ic it is i�ir it is it is s4 it it iir is it it ie it irir Y it is is it is it it is it it ie it is it it is is it sY it it ie**ic it ie is it is is is it it it is is it it is it is is i:ir FLOW PROCESS FROM NODE 6285.81 TO NODE 6285.81 IS CODE = 5 UPSTREAM NODE 6285.81 ELEVATION = 1076.32 (FLOW IS UNDER PRESSURE) -------- ----- ----- ---- CALCULATE JUNCTION LOSSES: --------- ---------------- ------- --------- ---------- --- PIPE FLOW DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY (CFS) (INCHES) (DEGREES) ELEVATION DEPTH(FT.) (FT/SEC) . UPSTREAM 95.50 42.00 00 1076.32 3.02 DOWNSTREAM 95.50 42.00 1076.32 3.02 9.926 LATERAL #1 9.926 .00 21.00 52.00 1077.33 .00 LATERAL #2 .00 .00 .00 00 .000 00 Q5 .00===Q5 EQUALS BASIN INPUT=== •000 LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: DY=(Q2*V2-Ql*Vl*COS(DELTAI)-Q3*V3*COS(DELTA3)- Q4*V4 *COS (DELTA4))/((A1+A2)*16.1)+FRICTION LOSSES UPSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00901 DOWNSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00901 AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS .00901 JUNCTION LENGTH = 1.00 FEET FRICTION LOSSES = .009 FEET ENTRANCE LOSSES = .000 FEET JUNCTION LOSSES = (DY+HV1-HV2)+(ENTRANCE LOSSES) JUNCTION LOSSES = ( .009)+( .000) = .009 --------------- ----- ---- ____ ---- NODE 6285.81 HGL = < 1081.012>;EGL= < 1082.542>;FLOWLINE= < 1076.320> ie;; is it*ic it it qr i:ic**ir�•ic it is is is**ie it it is it is it it it it it*ic is iP 'r ie is it it Yr ir:Y�-ic it is it is is it it is it is it is is ie it is it it it *ir is it it it it*ir is it* FLOW PROCESS FROM NODE 6285.81 TO NODE 6343.04 IS CODE = 3 --UPSTREAM-NODE- 6343.04 ELEVATION = 1076.66 (FLOW IS UNDER PRESSURE) --------------- -- --------------------- CALCULATE PIPE -BEND LOSSES(OCEMA): ------ PIPE FLOW = 95.50 CFS PIPE DIAMETER = 42.00 INCHES CENTRAL ANGLE = 73.000 DEGREES MANNING'S N = .01300 PIPE LENGTH = 57.23 FEET BEND COEFFICIENT(KB) = .22515 FLOW VELOCITY = 9.93 FEET/SEC. VELOCITY HEAD = 1.530 FEET HB=KB*(VELOCITY HEAD) = ( 225)*( 1.530) = .344 SF=(Q/K)**2 = (( 95.50)/( 1006.126))**2 = .00901 HF=L*SF = ( 57.23)*( .00901) = --TOTAL-HEAD 344)5151 6 -LOSSES = HB + HF = ( 516) = 860 ----------------------------------------------- NODE 6343.04 : HGL = < 1081.872>;EGL= < 1083.402>;FLOWLINE= < 1076.660> ir:::: is sY it it is*ir*'.:ir**;k*ir**ic ie it is sY it is it is ie*.ic ie is is it it is is*tic*i: it is it it it it ie is it is it it ic:k �Y k***ir sY ie is is it it ie**ie it it*ic FLOW PROCESS FROM NODE 6343.04 TO NODE 6358.16 IS CODE = 1 --UPSTREAM NODE 6358.16 ELEVATION = 3.076.72 (FLOW IS UNDER PRESSURE) -------------------- CALCULATE FRICTION LOSSES(LACFCD): PIPE FLOW = 95.50 CFS PIPE DIAMETER = 42.00 INCHES SFPE LENGTH = (Q/K)**2 = (( 1595?50)/( 1006.102))**2N1FEET G'5.00901 01300 HF=L*SF = ( 15.12)*( .00901) = 136 ------------ ------------- -- _ _ NODE 6358.16 HGL = < 1082.009>;EGL= < 1083.539>;FLOWLINE= < 1076.720> ____ is �•ic is is is*::t.ir. sY is i:i: is it is*ire-*&ir iric it is*ir it is it it i:i: it if*ic*sY�-*i:i: it is it***ir it it is*ir ie*ir it is it is �-ir is sF.ir it�ir it it it is it is FLOW PROCESS FROM NODE 6358.16 TO NODE 6362.83 IS CODE = 5 --UPSTREAM-NODE 6362.83 ELEVATION = 1076.74 (FLOW IS UNDER PRESSURE) ---- ----- -- ---- CALCULATE JUNCTION LOSSES: - ------------------- ------- --------- ---------- --- PIPE FLOW DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY Page 22 (CFS) (INCHES) (DEGREES) ELEVATION DEPTH(FT.) (FT/SEC) UPSTREAM 85.54 42.00 DOWNSTREAM .00 1076.74 2,88 95.50 42.00 1076.72 3.02 8.891 LATERAL #1 9.96 24.00 54.00 1077.50 1.13 9.926 3.170 LATERAL #2 .00 .00 .00 .00 Q5 .00===Q5 EQUALS BASIN INPUT=== .00 .000 LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: DY=(Q2*V2-Q1*V1*COS(DELTAI)-Q3*V3*COS(DELTA3)- Q4*V4*COS(DELTA4))/((A1+A2)*16.1)+FRICTION LOSSES UPSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00723 DOWNSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00901 AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS .00812 JUNCTION LENGTH = 4.67 FEET ANCE JUNCTION LOSSES =(DY+0HV1FHV2)+(ENTRANCETLOSSES)OSSES = 000 FEET --JUNCTION - LOSSES -=-(--_280)+(_-_000) = .280 NODE 6362.83 : HGL = < 1082.592>;EGL= < 1083.819>;FLOWLINE= < 1076.740> FLOW PROCESS FROM NODE 6362.83 TO NODE 6763.18 IS CODE = 1 UPSTREAM - NODE 6763.18 ELEVATION = 1078.34 (FLOW IS UNDER PRESSURE) ----------- -- ---------------------------------------------- CALCULATE FRICTION LOSSES(LACFCD):------'--- PIPE FLOW 85.54 CFS PIPE DIAMETER 42.00 INCHES PIPE LENGTH = 400.35 FEET MANNING'S N = .01300 SF=(Q/K)**2 = (( 85.54)/( 1006.090))**2 = .00723 HF=L*SF = ( 400.35)*( .00723) = 2.894 ----------------------------- NODE 6763.18 : HGL = < 1085.486>;EGL= < 1086.713>;FLOWLINE= < 1078.340> FLOW PROCESS FROM NODE 6763.18 TO NODE 6773.18 IS CODE = 5 UPSTREAM - NODE 6773.18 ELEVATION = 1078.37 (FLOW IS UNDER PRESSURE) --------------- CALCULATE JUNCTION LOSSES: - ------------------------ - ------ --------- ---------- --- PIPE FLOW DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY UPSTREAM (40.16 (I42.00) (DEGREES) ELEVATION DEPTH(FT.) (FT/SEC) DOWNSTREAM 85.54 42.00 •00 1078.37 1.97 4.174 8891 LATERAL #1 45.38 36.00 30.00 1078.85 2.19 6.420 LATERAL #2 .00 .00 .00 .00 '00 •.00 Q5 •00===Q5 EQUALS BASIN INPUT=== 0 LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: DY=(Q2*V2-Ql*V1*COS(DELTAI)-Q3*V3*COS(DELTA3)- Q4*V4*COS(DELTA4))/((A1+A2)*16.1)+FRICTION LOSSES UPSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00159 DOWNSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00723 AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS .00441 JUNCTION LENGTH = 10.00 FEET FRICTION LOSSES = •044 FEET ENTRANCE LOSSES = .000 FEET JUNCTION LOSSES = (DY+HV1-HV2)+(ENTRANCE LOSSES) JUNCTION LOSSES = ( .187)+( .000) = .187 --------------- _------------- _ ---NODE 6773.1$ :.HGL - ------------------------ - < 1086.629>;EGL= < 1086.900>;FLOWLINE= < 1078.370> #ir#it####s;ir#ir####.######is4:fe#####ie##ir#�•#ir###i:#####ir##is##############ir#####ir#ie#### FLOW PROCESS FROM NODE 6773.18 TO NODE 6884.95 IS CODE = 1 UPSTREAM NODE 6884.95 ELEVATION = 1078.82 (FLOW IS UNDER PRESSURE) -- --------- ---------- _ CALCULATE FRICTION-LOSSES(LACFCD): ------------------------------------------ ------------- PIPE FLOW = 40.16 CFS PIPE DIAMETER = 42.00 INCHES PIPE LENGTH = 111.77 FEET MANNING'S N = .01300 Page 23 SF=(Q/K)**2 = (( 40.16)/( 1006.059))**2 = .00159 HF=L*SF = ( 111.77)*( .00159) = .178 -- ----------------------- -- _ _ __ NODE 6884.95 - HGL - ------------------------ < 1086.807>;EGL= < 1087.078>;FLOWLINE= < 1078.820> Yc Yc Ye Yr is it it Yc it Yt it ie it Ye it Yr ie Yr ie ie it ie is Yr Yr Yc * Yr Yc Yr Yr ie it Yr * it Yr Yr is * Ye is Yr ie it it is *Yr Ye is Yc it Yc Yc * * * Yr sY Yr Ye is Yc ie it Yr Yr it Yr fe icYe Ye is Yc Yc it FLOW PROCESS FROM NODE 6884.95 TO NODE 6884.95 IS CODE = 5 --UPSTREAM-NODE --6884.95 ELEVATION = 1078.82 (FLOW IS UNDER PRESSURE) --------------------------------------------------- CALCULATE JUNCTION LOSSES: ---------- PIPE FLOW DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY UPSTREAM (39S20 (INCHES) (DEGREOESS) ELEVATION DEPTH�(1.5T.) (FT/SEC) DOWNSTREAM 40.16 42.00 4.075 LATERAL #1 1078.82 1.97 4.174 .96 21.00 90.00 1080.18 .35 LATERAL #2 .00 .00 .00 .00 .399 Q5 .00===Q5 EQUALS BASIN INPUT=== .00 •000 LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: DY=(Q2*V2-Q1*V1*COS(DELTAI)-Q3*V3*COS(DELTA3)- Q4*V4*COS(DELTA4))/((A1+A2)*16.1)+FRICTION LOSSES UPSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00152 DOWNSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00159 AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS .00156 JUNCTION LENGTH = 1.00 FEET FRICTION LOSSES = .002 FEET ENTRANCE LOSSES = .000 FEET JUNCTION LOSSES = (DY+HV1-HV2)+(ENTRANCE LOSSES) JUNCTION LOSSES = ( .014)+( .000) = .014 -------- ------- ------------- ------- -_ _ _ ____ ------------------ NODE 6884.95 : HGL = < 1086.834>;EGL= < 1087.092>;FLOWLINE=-< 1078.820> &ir it Yr it*Yr is ir'.•*****)Y is is Yc* is*Yt it Yc*Yr Yc it*ic Yt Ye it Yr Yr Ye Yc Yc it it Yr is is Yt Yr*Yt Yt*Ye*Ye it is Yr**�*Yr*ir ie icit is it Ys*ic Yc i�Yr*Yr Yr Yr FLOW PROCESS FROM NODE 6884.95 TO NODE 7143.95 IS CODE = 1 UPSTREAM - NODE 7143.95 ELEVATION = 1079.86 (FLOW IS UNDER PRESSURE) ------------- -------------------------------------------- CALCULATE FRICTION LOSSES(LACFCD):--------' PIPE FLOW 39.20 CFS PIPE DIAMETER = 42.00 INCHES PIPE LENGTH = 259.00 FEET MANNING'S N = .01300 SF=(Q/K)**2 = C( 39.20)/( 1006.087))**2 = .00152 --HF=L*SF-=-(- 259.00)*( .00152) = .393 ------------ -------- -------------------------------------------- NODE 7143.95 : HGL = < 1087.228>;EGL= < 1087.485>;FLOWLINE= < 1079.860> �•Yc Yr is*Yc Yr i�°k Yc Yt*Yr**'kYc****ir it is***Y: ie is it Yc i; it Yr it***Yt*Yc*ir it*ir Yc it Yr it Yr*ir***Yc is***Yr** it Yc sY *Yr it*Yc**ic*ic FLOW PROCESS FROM NODE 7143.95 TO NODE 7149.45 IS CODE = 5 UPSTREAM - NODE 7149.45 ELEVATION = 1079.88 (FLOW IS UNDER PRESSURE) ------------ ---------------- CALCULATE JUNCTION LOSSES: - -------------------------------------- '- PIPE FLOW DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY UPSTREAM (35.09 (242.00 (DEGREES) E1079T88N DEPiH84T.) (FT/SEC) DOWNSTREAM 39.20 42.00 1079.86 1.95 3.075 LATERAL #1 4.11 24.00 45.00 1080.89 71 1.308 LATERAL #2 .00 .00 .00 .00 1.308 Q5 .00===Q5 EQUALS BASIN INPUT=== '00 •000 LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: DY=(Q2*V2-Q1*VI*COS(DELTAI)-Q3*V3*COS(DELTA3)- Q4*V4 *COS (DE LTA4))/((Al+A2)*16.1)+FRICTION LOSSES UPSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00122 DOWNSTREAM: MANNING'S N = .01300; FRICTION SLOPE = 00152 AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS .00137 JUNCTION LENGTH = 5.50 FEET FRICTION LOSSES = .008 FEET ENTRANCE LOSSES = .000 FEET JUNCTION LOSSES = (DY+HV1-HV2)+(ENTRANCE LOSSES) Page 24 --JUNCTION-LOSSES = ( .046)+( .000) = .046 -------------- ------- --- ---- FLOW 7149.45 HGL - - ------------------- - < 1087.325>;EGL= < 1087.532>;FLOWLINE= < 1079.880> Yc Ye YeYc Yt Ye *Yt Yt * Yr Yc Ye Yc Yc * Yr Yc Yc Yr Yc Yc Yc is Yr Yr Ye YrYt * Yc YrYt it Yc.Yt YrYcYt lY Yc 4r Yr Yr * * YC * Yt * * it Ye * * * Yt * grYe Yt YcYe Ye Yc ii YtY: Yc Yr Ye Ye it icYc Yc * Yc FLOW PROCESS FROM NODE 7149.45 TO NODE 7239.93 IS CODE = 1 UPSTREAM - NODE 7239.93 ELEVATION = 1080.33 (FLOW IS UNDER PRESSURE) ------------ ------------ CALCULATE FRICTION LOSSES(LACFCD): ---------- ------- --------- ---------- --- PIPE FLOW = 35.09 CFS PIPE DIAMETER = 42.00 INCHES PIPE LENGTH = 90.48 FEET MANNING'S N = .01300 SF=(Q/K)**2 =CC 35.09)/( 1005.892))**2 = .00122 --HF_L*SF ( 90.48)*( .00122) = .110 --------------------------- NODE 7239.93 HGL = < 1087.435>;EGL= < 1087.642>;FLOWLINE= < 1080.330> Ye Ye it Yr Ye * Ye Yc Yr Yc Yr * Yr Yr Yc Yc Yc & Ye Yo Yc Yr Yt Ye Ye Yt Yr Ye Yc Yt Yc Yr Yr Yt Yc YtYt Yr Yc Yr Yc Ye * Ye Yr Yc * Yr * Yr Ye Yc Ye Yr Yc Yt Ye Yc YCYe Yc Yc Ye it Ye Yc Yt * Ye Yr Yt Yc Yr Yr Yc Yt Ye Yr FLOW PROCESS FROM NODE 7239.93 TO NODE 7315.36 IS CODE = 3 --UPSTREAM -------- NODE 7315.36 ELEVATION = 1080.71 (FLOW IS UNDER PRESSURE) ------------- __________________ CALCULATE PIPE -BEND LOSSES(OCEMA); PIPE FLOW = 35.09 CFS PIPE DIAMETER = 42.00 INCHES CENTRAL ANGLE = 48.000 DEGREES MANNING'S N = .01300 PIPE LENGTH = 75.43 FEET BEND COEFFICIENT(KB) = .18257 FLOW VELOCITY = 3.65 FEET/SEC. VELOCITY HEAD = .207 FEET HB=KB*(VELOCITY HEAD) = ( 183)*( .207) = .038 SF=(Q/K)**2 = (( 35.09)/( 1006.482))**2 = .00122 HF=L*SF = ( 75.43)*( .00122) = 092 --TOTAL HEAD LOSSES = HB + HF = ( .038)+( .092) _ .129 --------- ------ _ _--------------- _ _ ____ -------------------- NODE 7315.36 : HGL = < 1087.565>;EGL= < 1087.771>;FLOWLINE= < 1080.710> * Ye Yt Yt :P Yc Yr �'t * YrYr * * * Yc * Ye Yt Yr Y: Yc Yr Ye Yc Yr Yr Yr * * * it Yr * Yt Yr Yc Yr Yt Yc * Yc Yt Yt Yt Yc Yc Ye Yc * * Yr Yr Yr Yr Yr is Yr Ye Yt Yr Yr Yc * Ye Yr Yr Yr Yc Yc * * Yc Yt Yr Yt Yr Yc Yc FLOW PROCESS FROM NODE 7315.36 TO NODE 7315.36 IS CODE = 5 UPSTREAM - NODE 7315.36 ELEVATION = 1080.71 (FLOW IS UNDER PRESSURE) ---------------------- ------------- _______ ------------ CALCULATE JUNCTION LOSSES: --- --------- --- PIPE FLOW DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY UPSTREAM (32.66 (I42.00) (DEGRE0ES0) ELEVATION DEP1H��T.) (FT/SEC) DOWNSTREAM 35.09 42.00 1080.71 1.84 3.647 LATERAL #1 2.43 21.00 72.00 1081.96 56 1.640 LATERAL #2 .00 .00 00 _00 1.010 Q5 .00===Q5 EQUALS BASIN INPUT=== '00 .000 LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: DY=(Q2*V2-Q1*Vl*COS(DELTAI)-Q3*V3*COS(DELTA3)- UPSTREAM4*COSMANNING'S/NCA1+A01300;1)FRICTIONNSLOPEE= .00105 DOWNSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00122 AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS .00114 JUNCTION LENGTH = 1.00 FEET FRICTION LOSSES = .001 FEET ENTRANCE LOSSES = .000 FEET JUNCTION LOSSES = (DY+HV1-HV2)+(ENTRANCE LOSSES) JUNCTION LOSSES = ( .026)+( .000) = .026 ------- ------------- _ _ NODE 7315.36 : HGL = < 1087.619>;EGL= < 1087.798>;FLOWLINE= < 1080.710> Yt Y: Yr Yr Yr Yc Yr Yt Yt Yt Yc Yr Yt * Yc Yr Yt Yc Yr Yc Yc Yc Yc ie Yc Yr Ye Yc Ye Yc Yr Yc Yc Yr Yt Yc Yr Ye Yr Yr Yr Yc Yr Yc Yc Yc Yt.Yc Yc Yr * Yc Yc YrYc Yr Yc Yc it Yc Yr'k Yc Yc Yc Yc Yr Ye Yt Yr Yt Yc Yr Yr Yt Yr * Yr FLOW PROCESS FROM NODE 7315.36 TO NODE 7348.91 IS CODE = 3 UPSTREAM NODE 7348.91 ELEVATION = 1080.88 (FLOW IS UNDER PRESSURE) --------------- ---- _______ CALCULATE PIPE -BEND LOSSES(OCEMA): PIPE FLOW = 32.66 CFS PIPE DIAMETER = 42.00 INCHES CENTRAL ANGLE = 21.000 DEGREES MANNING'S N = .01300 Page 25 PIPE LENGTH = 33.55 FEET BEND COEFFICIENT(KB) = .12076 FLOW VELOCITY = 3.39 FEET/SEC. VELOCITY HEAD = .179 FEET HB=KB*(VELOCITY HEAD) _ ( 121)*( 10.07.036))*179) = 022 66)/( SF=(Q/K)irit2 = (( 32.*2 = .00105 HF=L*SF = ( 33.55)*( .00105) = 035 TOTAL HEAD LOSSES = HB + HF = ( .022)+( .035) _ .057 ---------------------- _ _ NODE 7348.91 : HGL = < 1087.676>;EGL= < 1087.854>;FLOWLINE= < 1080.880> itk kkkkfc kk kkkkkis iekkkkX kkitkkkkkkkkkkirkkkkkkkititkkkkirk kit irkkkkkkkkkkkiekkkisk kirk ie itk is it FLOW PROCESS FROM NODE 7348.91 TO NODE 7348.91 IS CODE = 5 --UPSTREAM-NODE- 7348.91 ELEVATION = 1080.88 (FLOW IS UNDER PRESSURE) -------------------------- -- _ - CALCULATE JUNCTION LOSSES: -------------- PIPE FLOW DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY UPSTREAM (30.46 (142.00) (DEGREES) E1080T88N DEPiH�iT.) (FT/SEC) DOWNSTREAM 32.66 42.00 1080.88 1.77 LATERAL #1 2.20 21.00 62.00 1082.13 54 3.394 LATERAL #2 .00 .00 00 pp .915 Q5 .00===Q5 EQUALS BASIN INPUT=== '00 .000 LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: DY=(Q2*V2-Q1*VI*COS(DELTAI)-Q3*V3*COS(DELTA3)- Q4*V4*COS(DELTA4))/((Al+A2)*16.1)+FRICTION LOSSES UPSTREAM: MANNING'S N = .01300; FRICTION SLOPE = .00092 DOWNSTREAM' MANNING'S N = .01300; FRICTION SLOPE = .001105 AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS .00099 JUNCTION LENGTH = 1.00 FEET FRICTION LOSSES = .001 FEET ENTRANCE LOSSES = .000 FEET JUNCTION LOSSES = (DY+HV1-HV2)+(ENTRANCE LOSSES) JUNCTION LOSSES = ( .021)+( .000) = .021 ------- --------------- ------- -- ---------- _ _ --- NODE 7348.91 HGL = < 1087.720>;EGL= < 1087.876>;FLOWLINE= < 1080.880> ____ '.: ickkkki:kk*kkki:kic kir ic*kkick�•kkkkkkkkkkkkir*kkkk*':kkkkk�rkkkk �•kk irkkkki.•k*k4tkit�•i:kit�•i4is�- FLOW PROCESS FROM NODE 7348.91 TO NODE 7373.43 IS CODE = 3 --UPSTREAM-NODE 7373.43 ELEVATION = 1081.00 (FLOW IS UNDER PRESSURE) --------------- __________ --------------------------------- CALCULATE PIPE -BEND LOSSES(OCEMA): ----- PIPE FLOW = 30.46 CFS PIPE DIAMETER = 42.00 INCHES CENTRAL ANGLE = 16.000 DEGREES MANNING'S N = .01300 PIPE LENGTH = 24.52 FEET BEND COEFFICIENT(KB) = .10541 FLOW VELOCITY = 3.17 FEET/SEC. VELOCITY HEAD = .156 FEET HB=KB*(VELOCITY HEAD) = ( 105)*( .156) = .016 SF=(Q/K)**2 = (( 30.46)/( 1004.767))**2 = .00092 HF=L*SF = ( 24.52)*( .00092) = 023 --TOTAL-HEAD-LOSSES = HB + HF = ( .016)+( .023) .039 -------------------------------- NODE 7373.43 : HGL = < 1087.759>;EGL= < 1087.915>;FLOWLINE= < 1081.000> k is kitkk kk kkic is irk �•k kirkk �•k kit it*kkkk*•k-k**ir is it it it is is it is it it it it it it it is it it it it is*ic it is it*ir it*iris*ir it it it �Y it *ic* FLOW PROCESS FROM NODE 7373.43 TO NODE 7387.93 IS CODE = 1 --UPSTREAM-NODE- 7387.93 ELEVATION = 1081.07 (FLOW IS UNDER PRESSURE) -------------------- CALCULATE FRICTION LOSSES(LACFCD):------- PIPE FLOW 30.46 CFS PIPE DIAMETER = 42.00 INCHES PIPE LENGTH = 14.50 FEET MANNING'S N = .01300 SF=(Q/K)**2 = (( 30.46)/( 1005.531))**2 = .00092 HF=L*SF = ( 14.50)*( .00092) = .013 ------- _ _ NODE 7387.93 : HGL = < 1087.772>;EGL= < 1087.928>;FLOWLINE= < 1081.070> ..i:kkki:ic'„•k kic Yc ick kkkkir kk irk kkkkk*ickkkkkkkiek irkkkkkirkkkkkkic kirk k;ck*kkkkitk is*ki: kickkkkkk UPSTREAM PIPE FLOW CONTROL DATA: Page 26 NODE NUMBER = 7387.93 FLOWLINE ELEVATION = 1081.07 ASSUMED UPSTREAM CONTROL HGL = 1082.78 FOR DOWNSTREAM RUN ANALYSIS ---------------------------------------------- _____________ END OF GRADUALLY VARIED FLOW ANALYSIS Page 27 HYDROLOGY MA --- ----- -- - - - --- - 10 -- --- INTERSTATE "" �- 103 102 909 l00� iv �. ~e � � 1 j 1Y131.10 .20 102.10 �,y0 1Q - I ✓ AC (14A>B FId 48 AG J 3Yhli, �. 2.95 AC nIlr „I 1 GGV-#,• 103,30 a 110 109 10 t� 107 wo ce na14c ®.rah zd i I cs.rcr j<, �PY.�� 4dKR;41., � .�'c.i\ Wit?!, c.e: ae��A� �� �.= ..,./r �J �,"_.�-/,�I:::1^ —,1 �.c��1 i I�,.i •. ��t �(}4F7S:YI3i1� I. ii� 1 YaummP•••^Wsml.m 1.�5- +CPC li{ 11 1p��'l �rP e tl ,kJF'' M �F�,ksWSPo bP` L 1 1 �.. / h�v�5j(9G3✓� rs sa P U� •�-_ @Sly .iY iYFf7a li 200 it SY 125;1J �,� • t< �P 6 1 • �\ akle' v� f � k Q1� • P� �PiY" k b�y ,t N' "^Y,'i(,� . t� 1, v,. }, l" r r P�rr.% k+rwc ""z f x r r rek i %� 1 y"ri�ixY1�YIP' Um",i ,,,f JUY t. f f d� r .,rye-L]J -.mv ks "Al b 1°A%1 y uY, f � 'k 11✓ � A 405 �I ^,'rY'T tyy ✓ �u 1 QF tl h f � It�f 1 � J i � ' ,XY �� i�.. k6i� I ". � Y� � � �k �fJ�i F�'�I�P tl�„y.������ G ✓ �" 4 N%� Ld ..tt4 r r xc. r rs { s , rrJr ra P of rt JT��P k F J v W EMPIRE CENTER CITY OF FONTANA,CALIFORNIA ME �: Y dy �j Il "d I� �o 1A VIV J, 4� 14� 61, Ak l Q` W —d I, iud�yh, y�, JJ lj, q Xf" U1111 --p q �l� 'Mph not . .... . ... .... ) , Id. �� rm,R, P"I yl 1, A3N f "'n'a Swox" I J, l, Illy V, It i�, W A 4 y� I A�11,1 —TF—,,,' 7,7,7j— -7 W* V4 .. ...... .. 5p Inq1W V'1� I "M !NNE 7N y, Ad, 'I [AV a -n AliJA-7 Ip)ldy/m d T J" Tlk, 'd P� y� eq� R IL m4A,