City of Fontana
CALIFORNIA'
August 7, 2001
RE: Slover Avenue Sewer
• from Cherry Avenue to Hemlock Avenue
Weekly Statement of Working Days Report Nos. 20 Through 29
Dear Mr. Fischer:
Enclosed for the review are the weekly statementsof working days
for week ending July.27, 2001. You will be allowed (15) days in
which to protest in writing the correctness of the statements;
otherwise the statements shall be deemed to have been accepted by
you as correct.
If you need additional information, please contact the undersigned
at (909) 350-7632.
Sincerely,
COMMUNITY DEVELOPMENT DEPARTMENT
Engineering Division.
Donald Gdula
Consultant Project Coordinator
Special Projects
cc: Principal Civil Engineer/Special Projects
Consultant Public Works Inspector (SB) w/enclosures
www.fontana.org
8353 SIERRA AVENUE FONTANA, CALIFORNIA 92335-3528 (909) 350-7600
recycled paper
�1
CITY OF FONTANA
WEEKLY STATEMENT OF WORKING DAYS
PROJECT: SLOVER AVENUE SEWER FROM CHERRY AVENUE TO HEMLOCK AVENUE
REPORT NO.
29
TO: FISCHER PLUMBING
The following statement shows the number of working days charged to your contract for the week
ending:17/27/01
Date
Day
Weather, Weather Conditions or Other Conditions
Working
Day
Non -Working
Days
Caused by
Weather
Working Days
No Work
Done on
Controlling
Operation
(Note 2)
7/23/01
Mon.
Hot and Clear
1
0
0
7/24/01
Tue.
Hot and Clear
1
0
0
7/25/01
Wed.
Hot and Clear
1
0
0
7/26/01
Thur.
Hot and Clear
1
0
0
7/27/01
Fri.
Hot and Clear
1
0
0
Days this week
Days previously reported
Total days to date •
5
0
0
112
18
9
117
18
9
TIME EXTENSIONS
CCO Numbers
(Note 3)
Days Approved
Other
CCO
Days this report
Days previously reported.
Total days to date
0
0
25
0
25
25
0
COMPUTATION OF EXTENDED DATE FOR COMPLETION
1. First working day designated
2. Workingdaysspecified s ecified in contract
3. COMPUTE DATE FOR COMPLETION(if all days specified are workable)
4. Total time extension days approved to date (CCO plus other)
5. Total•non-working days to date (Note 4)
6. Sub Total (Line 4 plus Line 5)
7. EXTENDED DATE FOR COMPLETION (Line 3 plus Line 6)
8. Revised working days for contract (Line 2 plus Line 6)
9. Total working days to date
10. WORKING DAYS REMAINING (Line 8 minus Line 9)
Controlling Operation(s)
Number
of Dap
MMWMMEM
60
25
27
52
Numbered
Day (Note 4)
Day No. 744
Date
1/8/01
MMUMMMMWMOMM
Day No. 804 4/4/01
112
117
0
Day No. 856 ( 6/18/01
Remarks: (Note 5) (Continue on reverse)
WORKING AND NONWORKING days are shown for record only sine the contract time has elapesed.
The Contractor will be allowed fifteen (15) days in which to protest
in writing the correctness of the statement; otherwise the statement
shall be deemed to have been accepted by the Contractor as correct.
NOTE: All footnotes are on the reverse side.
8/7/01
Donald Gdula/Pro'ect Coordinator
INSTRUCTION TO RESIDENT ENGINEER
When recording nonworking days due to weather; state the reason why
the day was unworkable when the weather description itself does not
adequately describe conditions. For example,' "Clear -wet grade" to
describe conditions when the weather is clear, but the grade is too wet to
work. Do not list days merely as "Unworkable".
• 2. Enter days on which no productive work has been* performed . on the
controlling operation(s) for reasons other than weather:
3. List numbers of contract change orders providing for time extensions.
4 Do not include nonworking days, which occur after expiration of the
ExtendedDATE.OF;COMPLETION. On contracts that are overtime, the
total under WORKING DAYS shall not be greater than the .total of
REVISED WORKING. DAYS, (line 8). After approved total of working days
has been . reached, continue recording working and nonworking. days but
do not add into the totals. Make ' statement under REMARKS, the
WORKING and NONWORKING days are shown forrecord' only since the
contract time has elapsed.
5. ' Time extensions other, are to be explained under REMARKS and the
followinginformation is to be included:.
(a)' Cause of delay andspecification reference/under which approval
was granted. 0
• (b) Statement as to what controlling operation or operations are being'
delayed and to'what extent. .
(c) Dates for which the extension' was granted.
(d) Reference to supporting data. 0
ADDITIONAL REMARKS:
CITY OF FONTANA
WEEKLY STATEMENT OF WORKING DAYS
PROJECT: SLOVER AVENUE SEWER FROM CHERRY AVENUE TO HEMLOCK AVENUE
REPORT NO.
28
TO: FISCHER PLUMBXNG
The following statement shows the number of working days charged to your contract for the week
ending: 7/20/01
Date
Day
•
Weather, Weather. Conditions or Other Conditions
Working
Day
Non -Working
Days
Caused by
Weather
Working Days
No Work
Done on
Controlling
Operation
(Note 2)
7/16/01
Mon.
Hot and Clear
1
0
0
7/17/01
Tue.
Hot and Clear
1
0
0
7/18/01
Wed.
Hot and Clear
1
0
0
7/19/01
Thur.
Hot and Clear
1
0
0
7/20/01
Fri.
Hot and Clear
1
0
0
Days this week
Days previously reported
Total days to date
5
0
0
107
18
9
112
. 18
9
TIME EXTENSIONS
CCO Numbers
(Note 3)
Days Ap roved
CCO Other
Days this report
Days previously reported.
Total days to date
0
0
25
0
25
25
0
COMPUTATION OF EXTENDED DATE FOR COMPLETION
1. First working day designated
2. Workingdaysspecified s ecified in contract
3. COMPUTE DATE FOR COMPLETION(if all days specified are workable)
4. Total time extension days approved to date (CCO plus other)
5. Total non -working days to date (Note 4)
6. Sub Total (Line 4 plus Line 5)
7. EXTENDED DATE FOR COMPLETION (Line 3 plus Line 6)
8. Revised working days for contract (Line 2 plus Line 6)
9. Total working days to date
10. WORKING DAYS REMAINING (Line 8 minus Line 9)
Controlling Operation(s)
Number
of Days
....... ..........
60
mummwmais
25
27
52
MMOMMM
112
112
0
Numbered
Day (Note 4)
Day No. 744
Date
1/8/0l
MiiiMiiMMWMMUMEM
Day No. 804 4/4/01
Day No. 856 I 6/18/01
Remarks: (Note 5) (Continue on reverse)
The Contractor will be allowed fifteen (15) days in which to protest
in writing the correctness of the statement; otherwise the statement
shall be deemed to have been accepted by the Contractor as correct.
NOTE: All footnotes are on the reverse side.
Donald Gdula/Project Coordinator
8/7/01
r
• INSTRUCTION TO RESIDENT ENGINEER
When recording nonworking days due to weather; state the reason why
the day was unworkable when the weather description itself does not
adequately describe conditions. For example,' "Clear -wet grade" to
describe conditions when the weather is clear, but the grade is too wet to
work. Do not list days merely as "Unworkable".
2. Enter days on which no productive work has been performed . on the
controlling operation(s) for reasons other than weather.
3. List numbers of contract change orders providing for time extensions.
4. Do not include nonworking days, which occur after expiration of the
Extended, DATE OF COMPLETION. On contracts that are .overtime, the
total under WORKING DAYS shall not`. be greater than the .total of
REVISED WORKING. DAYS, (line 8). After approved total of workingdays
has been reached, continue recording working and nonworking. days but
do not add into the totals. Make statement under REMARKS. the
WORKING and NONWORKING days are shown for record only since the
contract time has elapsed.
5. Time extensions other, are to be explained under REMARKS and the
followinginformation is to be included:.
(a) Cause of delay .and specification reference/under which approval
was granted.
(b) Statement as to what controlling operation or operations are being
delayed and to what extent.
(c) Dates for which the extension was granted.
(d) Reference to supporting data.
ADDITIONAL REMARKS:
CITY OF FONTANA
WEEKLY STATEMENT OF WORKING DAYS
PROJECT: SLOVER AVENUE SEWER FROM CHERRY AVENUE TO HEMLOCK AVENUE
27
TO: FISCHER PLUMBING
The following statement shows the number of working days charged to your contract for the week
ending: 7/13/01 I
Date
Day
Weather, Weather Conditions or Other Conditions
Working
Day
Non -Working
Days
Caused by
Weather
I
Working Days
No Work
Done on
Controlling
Operation
(Note 2)
7/9/01
Mon.
Hot and Clear
1
0
0
7/10/01
Tue.
Hot and Clear
1
0
0
7/11/01
Wed.
Hot and Clear
1
0
0
7/12/01
Thur.
Hot and Clear
1
0
0
7/13/01
Fri.
Hot and Clear
1
0
0
Days this week
Days previously reported
Total days to date
5
0
0
102
18
9
107
18
9
TIME EXTENSIONS
CCO Numbers
(Note 3)
Days Approved
Other
CCO
Days this report -
Days previously reported.
Total days to date
5 & 6
25
0
0
0
25
0
COMPUTATION OF EXTENDED DATE FOR COMPLETION
1. First working day designated
2. Workingdaysspecified s ecified in contract
3. COMPUTE DATE FOR COMPLETION(if all days specified are workable)
4. Total time extension days approved to date (CCO plus other)
5. Total non -working days to date (Note 4)
6. Sub Total (Line 4 plus Line 5)
7. EXTENDED DATE FOR COMPLETION (Line 3 plus.Line.6)
8. Revised working days for contract (Line 2 plus Line 6)
9. Total working days to date
10. WORKING DAYS REMAINING (Line 8 minus Line 9)
Controlling Operation(s)
Number
of Days
MMWMWMg
60
MUMOWNO
25
27
52
aMMOMMMW
112
107
5
Numbered •
Day (Note 4)
Day No. 744
Date
1/8/01
ONOWNMWWWWWWWM
Day No. 804
4/4/01
Day No. 856 6/18/01
Remarks: (Note 5) (Continue on reverse)
The Contractor will be allowed fifteen (15) days in which to protest
in writing the correctness of the statement; otherwise the statement
shall be deemed to have been accepted by the Contractor as correct.
NOTE: All footnotes are on the reverse side.
Donald Gdula/Project Coordinator
8/7/01
INSTRUCTION TO RESIDENT ENGINEER
When recording nonworking days due to weather; state the reason why
the day was unworkable when the weather description itself does' not
adequately describe conditions. For example,. "Clear -wet grade" to
describe conditions when the weather is clear, but the grade is too wet to
work. Do not list days merely as "Unworkable".
2. Enter days on which no productive work has been performed • on the
controlling operation(s) for reasons other than weather.
3 • List numbers of contract change orders providing for time extensions.
4. Do not include nonworking days, which occur after expiration of the
Extended `DATE . OF COMPLETION. On contracts that are overtime, the
total under WORKING DAYS shall not. be greater than. the .total of
•REVISED WORKING. DAYS, (line 8). After approved total of working days
has ;'been . reached, continue recording working and nonworking. days but
do. not add into the totals. Make • statement under REMARKS. the
WORKING and NONWORKING days are shown for. record. only since the
contract time has elapsed.
•
5. Time extensions other, are to be explained under REMARKS and the
.following. information is to be included:.
(a)* Cause of delay . and specification• reference/under which approval
was granted. .
• (b) Statement as to what controlling operation or operations are being
delayed and tovwhat extent. .
(c) 'Dates for which the extension' was granted.
(d) Reference to supporting data.
ADDITIONAL REMARKS:
CITY OF FONTANA
WEEKLY STATEMENT OF WORKING DAYS
PROJECT: SLOVER AVENUE SEWER FROM CHERRY AVENUE TO HEMLOCK AVENUE
REPORT NO.
26
TO: FISCHER PLUMBING
The following statement shows the number of working days charged to your contract for the week
ending: 7/6/01
Date
Day
Weather, Weather Conditions or Other Conditions
Working
Day
Non -Working
Days
Caused by
Weather
Working Days
No Work
Done. on
Controlling
Operation
(Note 2)
7/2/01
Mon.
Hot and Clear
1
0
0
7/3/01
Tue.
Hot and Clear
1
0
0
7/4/01
Wed.
Holiday
0
0
0
7/5/01
Thur.
Hot and Clear
1
0
0
7/6/01
Fri.
Hot and Clear
1
0
0
Days this week
Days previously -reported
Total days to date
4
0
0
98
18
9
102
18
9
TIME EXTENSIONS
CCO Numbers
(Note 3)
Days Ap roved
CCO Other
Days this report
Days previously reported.
Total days to date
0
0
0
0
0
0
0
COMPUTATION OF EXTENDED DATE FOR COMPLETION
1. First working day designated
2. Workingdaysspecified s ecified in contract
3. COMPUTE DATE FOR COMPLETION(if all days specified are workable)
4. Total time extension days approved to date (CCO plus other).
5. Total non -working days to date (Note 4)
6. Sub Total (Line 4 plus Line 5)
7. EXTENDED DATE, FOR COMPLETION (Line 3 plus Line 6)
8. Revised working days for contract (Line 2 plus Line 6)
9. Total working days to date
10. WORKING DAYS REMAINING (Line 8 minus Line 9)
• Controlling Operation(s)
Number
of Days
MWEEMME
Numbered
Day (Note 4)
Day No. 744
Date
1/8/01
60
0
27
27
MMWMNMM
87
87
0
Day No. 804 4/4/01
Day No. 830
5/10/01
Remarks: (Note 5) (Continue on reverse) 1
WORKING and NONWORKING days are shown for record only since the contract time has elapsed.
The Contractor will be allowed fifteen (15) days in which to protest
in writing the correctness of the statement; otherwise the statement
shall be deemed to have been accepted by the Contractor as correct.
NOTE: All footnotes are on the reverse side.
Donald Gdula/Project Coordinator
8/7/01
INSTRUCTION TO RESIDENT ENGINEER
When recording nonworking days due to weather; state the reason why.
the day was unworkable when the weather description itselfdoes not
adequately describe conditions. For example,' "Clear -wet grade" to
describe conditions when the weather is clear, but the grade is too wet to
work. Do not list days merely as "Unworkable".
• 2. Enter days on which no productive work has been performed on the
controlling operation(s) for reasons other than weather.
3 List numbers of contract change orders providing for time extensions-.
4. Do not include nonworking days, which occur after expiration of the
Extended DATE -OF .COMPLETION. On contracts that are overtime, the
total under WORKING DAYS shall not `. be greater ` than the .total of
REVISED WORKING. DAYS, (line 8). After approved total of working days
has been. reached, continue recording working and nonworkingdays but
do not add into the totals. Make statement under REMARKS. the
WORKING and NONWORKING days are shown for. record. only since the
contract time has elapsed.
5. Time extensions other, are to be explained under REMARKS and the
followinginformation is to be included:.
(a)' Cause of delay and specification reference/under which approval
was granted. . .
(b) • Statement as to what controlling operation or operations are being
delayed and to'what extent.
(c) Dates for which the extension' was granted.
(d) Reference to supporting data.
ADDITIONAL REMARKS:
CITY OF FONTANA
WEEKLY STATEMENT OF WORKING DAYS
PROJECT: SLOVER AVENUE SEWER FROM CHERRY AVENUE TO HEMLOCK AVENUE
REPORT NO.
25
TO: FISCHER PLUMBING
The following statement shows the number of working days charged to your contract for the
week ending: 6/29/01
Date
Day
Weather, Weather Conditions or Other Conditions
Working
Day
Non -Working
Days
Caused by
Weather
Working Days
No Work
Done on
Controlling
Operation
(Note 2)
6/25/01
Mon.
Hot and Clear
1
0
0
6/26/01
Tue.
Hot and Clear
1
0
0 ,
6/27/01
Wed.
Hot and Clear
1
0
0
6/28/01
Thur.
Hot and Clear
i
0
0
6/29/01
Fri.
Hot and Clear
1
0
0
Days this week
Days previously reported
Total days to date
5
0
0
93
18
9
98
18
9
TIME EXTENSIONS
CCO Numbers
(Note 3)
Days Approved
Other
CCO
Days this report
Days previously reported.
Total days to date
0
0
0
0
0
0
0
COMPUTATION OF EXTENDED DATE FOR COMPLETION
1. First working day designated
2. Workingdaysspecified s ecified in contract
3. COMPUTE DATE FOR COMPLETION(if all days specified are workable)
4. Total time extension days approved to date (CCO plus other)
5. Total non -working days to date (Note 4)
6. Sub Total (Line 4 plus Line 5)
7. EXTENDED DATE FOR COMPLETION (Line 3 plus Line 6)
8. Revised working days for contract (Line 2 plus Line 6)
9. Total working days to date
10. WORKING DAYS REMAINING (Line 8 minus Line 9)
Controlling Operations)
Number
• of Days
AMMEMME
60
0
27
27
87
87
0
Numbered
Day (Note 4)
Day No. 744
Date
1/8/01
MMONMWMONOMMUR
Day No. 804 4/4/01
Day No. 830 1 5/10/01
Remarks: (Note 5) (Continue on reverse)
WORKING and NONWORKING days are shown for record only since the contract time has elapsed.
The Contractor will be allowed fifteen (15) days in which to protest
in writing the correctness of the statement; otherwise the statement
shall be deemed to have been accepted by the Contractor as correct.
NOTE: All footnotes are on the reverse side.
Donald Gdula/Project Coordinator
8/7/01
INSTRUCTION TO RESIDENT ENGINEER
1. When recording nonworking days due to weather; state the reason why
the day was unworkable when the weather description itself does not
adequately describe conditions. For example,. "Clear -wet grade" to
describe conditions when the weather is clear, but the grade is too wet to
. work. Do not list days merely as "Unworkable".
2. Enter days on which no productive work has been performed on the
controlling operation(s) for reasons other than weather.
3. List numbers of contract change orders providing for time extensions.
4. Do not include nonworking days, which occur after expiration of the
Extended DATE. OF:COMPLETION. On contracts that are overtime, the
total under WORKING DAYS shall not be • greater than the .total of
REVISED WORKING. DAYS, (line 8). After approved total of working days
has been reached, continue recording working and nonworking. days but
do not add into the totals. Make statement under REMARKS. the
WORKING and NONWORKING days are shown for record. only since the
contract time has elapsed.
5. Time extensions other, are to be explained under REMARKS and the
followinginformation is to be included:.
(a) Cause of delay .and specification reference/under which approval
was granted. 0
• (b) . Statement as to what controlling operation .or operations are being
delayed and to•what extent. .
(c) Dates for which the extension' was granted.
(d) Reference to supporting data.
ADDITIONAL REMARKS:
CITY OF FONTANA
WEEKLY STATEMENT OF WORKING DAYS
PROJECT: SLOVER AVENUE SEWER FROM CHERRY AVENUE TO HEMLOCK AVENUE
REPORT NO.
24
TO: FISCHER PLUMBING
The following statement shows the number of working days charged to your contract for the week ending: 6/22/01
Date
Day
Weather, Weather Conditions or Other Conditions
Working
Day
Non -Working
Days
Caused by
Weather
Working Days
No Work
Done'on
Controlling
Operation
(Note 2)
6/18/01
Mon.
Hot and Clear
1
0
0
6/19/01
Tue.
Hot and Clear
1
0
0
6/20/01
Wed.
Hot and Clear
1
0
0
6/21/01
Thur.
Hot and Clear
1
0
0
6/22/01
Fri.
Hot and Clear
1
0
0
Days this week
Days previously reported
Total days to date
5
0
0
88
18
9
93
18
9
TIME EXTENSIONS
CCO Numbers
(Note 3)
Days Ap roved
CCO Other
Days this report
Days previously reported.
Total days to date
0
0
0
0
0
0
0
COMPUTATION OF EXTENDED DATE FOR COMPLETION
1. First working day designated
2. Workingdaysspecified s ecified in contract
3. COMPUTE DATE FOR COMPLETION(if all days specified are workable)
4. Total time extension days approved to date (CCO plus other)
5. Total non -working days to date (Note 4)
6. Sub Total (Line 4 plus Line 5)
7. EXTENDED DATE FOR COMPLETION (Line 3 plus Line 6)
8. Revised working days for contract (Line 2 plus Line 6)
9. Total working days to date
10. WORKING DAYS REMAINING (Line 8 minus Line 9)
Controlling Operation(s)
Number
of Days
aMMUMMM
Numbered
Day .(Note.4)
Day No. 744
Date
1/8/01
60
UMMMaMNNMMWMMMM
SMOAWOOM
0
27
27
ONVAMMON
87
87
0
Day No. 804
4/4/01
Day No. 830 I 5/10/01
Remarks: (Note 5) (Continue on reverse)
WORKING and NONWORKING days are shownfor record only since the contract time has elapsed.
The Contractor will be allowed fifteen (15) days in which to protest
in writing the correctness of the statement; otherwise the statement
shall be deemed to have been accepted by the Contractor as correct.
NOTE: All footnotes are on the reverse side.
8/7/01
Donald Gdula/Project Coordinator
INSTRUCTION TO RESIDENT ENGINEER
1. When recording nonworking days due to weather; state the reason why
the day was' unworkable when the weather description itself does not
adequately describe conditions. For example,. "Clear -wet grade" to
describe conditions when the weather is clear, but the grade is too wet to
work. Do not list days merely as "Unworkable".
2. Enter days on which no productive work has beenperformed • on the
controlling operation(s) for reasons other than weather.
3. • List numbers of contract change orders providing for time extensions.
4. ' Do not include nonworking days, which occur after expiration of the
Extended DATE. OF :COMPLETION. On contracts that are overtime, the
total under WORKING DAYS , shall not't be greater than. the. .total of
'REVISED WORKING. DAYS, (line 8). After approved total of working .days
has .been.reached, continue recording working and nonworking- days but
do not add into the totals. Make • statement under REMARKS. the
WORKING and NONWORKING days are shown for .record. only since the
contract time has elapsed.
5 Time extensions other, are to be explained under REMARKS and the
.following. information is to be included:.
(a)' Cause of delay and specification reference/under which approval
was granted.
(b) Statement as to what controlling operation or operations are being
delayed and to'what extent.
(c) Dates for which the extension'was granted.
(d) Reference to supporting data. '
ADDITIONAL REMARKS:
CITY OF FONTANA,
WEEKLY STATEMENT OF WORKING DAYS
PROJECT: SLOVER AVENUE SEWER FROM CHERRY AVENUE TO HEMLOCK AVENUE
REPORT NO. 23
TO: FISCHER PLUMBING
The following statement shows the number of working days charged to your contract for the week ending: 6/15/01
Date
Day
Weather, Weather Conditions or Other Conditions
Working
Day
Non -Working
Days
Caused by
Weather
Working Days
No Work
Done on
Controlling
Operation
(Note 2)
6/11/01
Mon.
Hot and Clear
1
0
0
6/12/01
Tue.
Hot and Clear
1
0
0
6/13/01
Wed.
Hot and Clear
1
0
0
6/14/01
Thur.
Hot and Clear
1
0
0
6/15/01
Fri.
Hot and Clear
1
0
0
Days this week
Days previously -reported
Total days to date
5
0
0
83
18
9 .
88
18
9
TIME EXTENSIONS
CCO Numbers
(Note 3)
Days Ap roved
CCO Other
Days this report
.Days previously reported.
Total days to date
0
0
0
0
0
0
0
COMPUTATION OF EXTENDED DATE FOR COMPLETION
1. First working day designated
2. Workingdaysspecified s ecified in contract
3. COMPUTE DATE FOR COMPLETION(if all days specified are workable)
4. Total time extension days approved to date (CCO plus other)
5. Total non -working days to date (Note 4)
6. Sub Total (Line 4 plus Line 5)
7. EXTENDED DATE FOR COMPLETION (Line 3 plus Line 6)
8. Revised working days for contract (Line 2 plus Line 6)
9. Total working days to date
10. WORKING DAYS REMAINING (Line 8 minus Line 9)
Controlling Operation(s)
Number
of Days
ammmgma
60
Numbered
Day (Note 4)
Day No. 744
Date
1/8/01
0
27
27
87
87
0
Day No. 804 4/4/01
Day No. 830 I 5/10/01
Remarks: (Note 5) (Continue on reverse)
WORKING and NONWORKING days are shown for record only since the contract time has elapsed.
The Contractor will be allowed fifteen (15) days in which to protest
in writing the correctness of the statement; otherwise the statement
shall be deemed to have been accepted by the Contractor as correct.
NOTE: All footnotes are on the reverse side.
v_CacaQ_Q2__
8/7/01
Donald Gdula/Project Coordinator
r
INSTRUCTION TO RESIDENT ENGINEER
1. When recording nonworking days due to weather; state the reason why
the day was unworkable when the weather description itself does not
adequately describe conditions. For example,. "Clear -wet grade" to.
describe conditions when the weather is clear, but the grade is too wet to
work. Do not list days merely as "Unworkable".
2. Enter days on which no productive work has been performed on the
controlling operation(s) for reasons other than weather.
3. List numbers of contract change orders providing for time extensions.
4. Do not include nonworking days, which occur after expiration of the
Extended DATE OF -COMPLETION. On contracts that are overtime, the
total under WORKING DAYS shall not* be greater than the .total of
REVISED WORKING DAYS, (line 8). After approved total of working days
has been reached, continue recording working and nonworkingdays but
do not add into the totals. Make statement under REMARKS. the
WORKING and NONWORKING days are shown for record only since the
contract time has elapsed.
5. Time extensions other, are to be explained under REMARKS and the
following information is to be included:.
(a) Cause of delay and specification reference/under which approval
was granted.
(b) Statement as to what controlling operation or operations are being
delayed and to•what extent.
(c) Dates for which the extension was granted.
(d) Reference to supporting data.
ADDITIONAL REMARKS:
CITY OF FONTANA
WEEKLY STATEMENT OF WORKING DAYS
PROJECT: SLOVER AVENUE SEWER FROM CHERRY AVENUE TO HEMLOCK AVENUE
REPORT NO. 22
TO: FISCHER PLUMBING
The following statement shows the number of working days charged to your contract for the week ending: 6/08/01
Date
Day
4
Weather, Weather Conditions or Other Conditions
Working
Day
Non -Working
Days
Caused by
Weather
Working Days
No Work
Done on
Controlling
Operation
(Note 2)
6/4/01
Mon.
Hot and Clear
1
,0
0
6/5/01
Tue.
Hot and Clear
1
0
0
6/6/01
Wed.
Hot and Clear
1
0
0
6/7/01
Thur.
Hot and Clear
1
0
0
6/8/01
Fri.
Hot and Clear
1
0
0
Days this week
Days previously reported
Total days to date
5
0
0
78
18
9
83
18
9
TIME EXTENSIONS
CCO Numbers
(Note 3)
Days Ap roved
CCO Other
Days this report
Days previously reported.
Total days to date
0
0
0
0
0
0
0
COMPUTATION OF EXTENDED DATE FOR COMPLETION
1. First working day designated
2. Workingdaysspecified s ecified in contract
3. COMPUTE DATE FOR'COMPLETION(if all days specified are workable)
4. Total time extension days approved to date (CCO plus other)
5. Total non -working days to date (Note 4)
6. Sub Total (Line 4 plus Line 5)
7. EXTENDED DATE FOR COMPLETION (Line 3 plus Line 6)
8. Revised working days for contract (Line 2 plus Line 6)
9. Total working days to date
10. WORKING DAYS REMAINING (Line 8 minus Line 9)
Controlling Operation(s)
Number
of Days
MWMOiMg
60
0
27
27
87
83
4
Numbered.
Day (Note 4)
Day No. 744
Date
1/8/0l
MgaMMWMMOMMOM
Day No. 804
4/4/01
Day No. 830 l 5/10/01
Remarks: (Note 5) (Continue on reverse)
The Contractor will be allowed fifteen (15) days in which to protest
in writing the correctness of the statement; otherwise the statement
shall, be deemed to have been accepted by the Contractor as correct.
NOTE: All footnotes are on the reverse side.
Donald Gdula/Project Coordinator
8/7/01
J
INSTRUCTION TO RESIDENT ENGINEER
1. When recording nonworking days due to weather; state the reason why
the day was unworkablewhen the weather description itself does not
adequately describe conditions. For example; "Clear -wet grade" to
describe conditions when the weather is clear, but the grade is too wet to
work. Do not list days merely as "Unworkable".
2. Enter days on which no productive work has been performed on the
controlling operation(s) for reasons other than weather.
3. List numbers of contract change orders providing for time extensions.
4. Do not include nonworking days, which occur after expiration of the
Extended DATE OF COMPLETION. On contracts that are overtime, the
total under WORKING DAYS. shall not begreater than the .total of
REVISED WORKING DAYS, (line 8). After approved total of working days
has been reached, continue recording working and nonworkingdays but
do not add into the totals. Make statement under REMARKS. the
WORKING and NONWORKING days are shown for record only since the
contract time has elapsed.
5. Time extensions other, are to be explained under REMARKS and the
following information is to be included:.
(a)* Cause of delay and specification reference/under which approval
was granted.
(b) Statement as to what controlling operation or operations are being
delayed and to' what extent.
(c) Dates for which the extension was granted.
(d) Reference to supporting data.
ADDITIONAL REMARKS:
CITY OF FONTANA
WEEKLY STATEMENT OF WORKING DAYS
PROJECT: SLOVER AVENUE SEWER FROM CHERRY AVENUE TO HEMLOCK AVENUE
TO: FISCHER PLUMBING
REPORT NO.
21
The following statement shows the number of working days charged to your contract for the
week ending: 6/01/01
Date
Day
Weather, Weather Conditions or Other Conditions
Working
Day
Non -Working
Days
Caused by
Weather
Working Days
No Work
Done on
Controlling
Operation
(Note 2)
5/28/01
Mon.
Holiday
0
10
0
5/29/01
Tue.
Hot and Clear
1
0
0
5/30/01
Wed.
Hot and Clear
1
0
0
5/31/01
Thur.
Hot and Clear
1
0
0
6/1/01
Fri.
Hot and. Clear
0
0
1
Days this week
Days previously reported
Total days to date
3
0
1
75
18
8
78
18
9
TIME EXTENSIONS
CCO Numbers
(Note 3)
Days Approved
Other
CCO
.Days
Days
Total
this report
previously reported.
days to date
0
0
0
0
0
0
0
COMPUTATION OF EXTENDED DATE FOR COMPLETION
1. First working day designated
2. Working days specified in contract
3. COMPUTE DATE FOR COMPLETION(if all days specified are workable)
4. Total time extension days approved to date (CCO plus other)
5. Total non -working days to date (Note 4)
6. Sub Total (Line 4 plus Line 5)
7. EXTENDED DATE FOR COMPLETION (Line 3 plus Line 6)
8. Revised working days for contract (Line 2 plus Line 6)
9. Total working days to date
10. WORKING DAYS REMAINING (Line 8 minus Line 9)
Number
of Days
OMMEMEM
Numbered
Day (Note 4)
Day No. 744
Date
1/8/01
60
MMaWaiMUM
0
27
27
87
78
9
Day No. 830 f 5/10/01
Controlling Operation(s) Foreman Randy Kent was off for personal reasons and the crew did not
work on Friday, June 1, 2001.
Remarks: (Note 5) (Continue on reverse)
The Contractor will be allowed fifteen (15) days in which to protest
in writing the correctness of the statement; otherwise the statement
shall be deemed to have been accepted by the Contractor as correct.
NOTE: All footnotes are on the reverse side.
Donald Gdula/Project Coordinator
8/7/01
INSTRUCTION TO RESIDENT ENGINEER
When recording nonworking days due to weather; state the reason why
the day was unworkable when the weather description itself does not
adequately describe conditions. For example, "Clear -wet grade" to
describe conditions when the weather is clear, but the grade is too wet to
work. Do not list days merely as "Unworkable".
2. Enter days on which no productive work has been performed on the
controlling operation(s) for reasons other than weather.
3. List numbers of contract change orders providing for time extensions.
4. Do not include nonworking days, which occur after expiration of the
• Extended DATE OF COMPLETION. On contracts that are overtime, the
total, under WORKING DAYS shall not be' greater than the .total of
REVISED WORKING DAYS, (line 8). After approved total of working days
has 'been :reached, continue recording working and nonworkingdays but
do not add into the totals. Make statement under REMARKS. the
WORKING and NONWORKING days are shown for record only since the
contract time has elapsed.
5. Time extensions other, are to be explained under REMARKS and the
followinginformation is to be included:.
(a) Cause of delay and specification reference/under which approval
was granted.
(b) Statement as to what controlling operation or operations are being
delayed and :to what extent.
(c) Dates for which the extension was granted.
(d) Reference to supporting data.
ADDITIONAL REMARKS:
CITY OF FONTANA
WEEKLY STATEMENT OF WORKING DAYS
PROJECT: SLOVER AVENUE SEWER FROM CHERRY AVENUE TO HEMLOCK AVENUE
REPORT NO. 20
TO: FISCHER PLUMBING
The following statement shows the number of working days charged to your contract for the week
ending: 5/25/01
Date
Day
Weather, Weather Conditions or Other Conditions
Working
Day
Non -Working
Days
Caused by
Weather
Working Days
No Work
Done on
Controlling
Operation
(Note 2)
5/21/01
Mon.
Hot and Clear
1
0
0
5/22/01
Tue.
Hot and Clear
1
0
0
5/23/01
Wed.
Hot and Clear
1
0
0
5/24/01
Thur.
Hot and Clear
1
0
0
5/25/01
Fri.
Hot and Clear
1
0
0
Days this week
Days previously reported
Total days to date
5
0
0
70
18
8
75
18
8
TIME EXTENSIONS
CCO Numbers
(Note 3)
Days Ap roved
CCO Other
Days this report
Days previously reported.
Total days to date
0
0
0
0
0
0
0
COMPUTATION OF EXTENDED DATE FOR COMPLETION
1. First working day designated
2. Workingdaysspecified s ecified in contract
3. COMPUTE DATE FOR COMPLETION(if all days specified are workable)
4. Total time extension days approved to date (CCO plus other)
5. Total non -working days to date (Note 4)
6. Sub Total (Line 4 plus Line 5)
7. EXTENDED DATE FOR COMPLETION (Line 3 plus Line 6)
8. Revised working days for contract (Line 2 plus Line 6)
9. Total working days to date
10. WORKING DAYS REMAINING (Line 8 minus Line 9)
Controlling Operation(s)
Number
of Days
MEMEMOM
60
Numbered
Day (Note 4)
Day No. 744
Date
1/8/01
EEMMWM
0
26
26
Day No. 804
4/4/01
nWOMMW
Day No. 830
5/10/01
86
75
11
Remarks: (Note 5) (Continue on reverse)
The Contractor will be allowed fifteen (15) days in which to protest
in writing the correctness of the statement; otherwise the statement
shall be deemed to have been accepted by the Contractor as correct.
NOTE: All footnotes are on the reverse side.
8/7/01
Donald Gdula/Project Coordinator
• •
INSTRUCTION TO RESIDENT ENGINEER
When recording nonworking days due to weather; state the reason why
the day was unworkable when the weather description itself does not
adequately describe conditions. For example; "Clear -wet grade" to
describe conditions when the weather is clear, but the grade is too wet to
work. Do not list days merely as "Unworkable".
2. Enter days on which no productive work has been performed on the
controlling operation(s) for reasons other than weather.
3.. List numbers of contract change orders providing for time extensions.
4. Do not include nonworking days, which occur after expiration of the
Extended ' DATE OF -COMPLETION. On contracts that are overtime, the
total under WORKING DAYS shall not begreater than the .total of
REVISED WORKING DAYS, (line 8). After approved total of working days.
has 'been reached, continue recording working and nonworkingdays but
do not add into the, totals. Make statement under REMARKS. the
WORKING and NONWORKING days are shown for record only since the
contract time has elapsed.
5. Time extensions other, are to be explained under REMARKS and the
following information is to be included:.
(a) Cause of delay and specification reference/under which approval
was granted.
(b) Statement as to what controlling operation or operations are being
delayed and to what extent.
(c) Dates for which the extension was granted.
(d) Reference to supporting data.
ADDITIONAL REMARKS:
Fischer Plumbing
Mike Fischer, Owner
1372 W. 26th Street
San Bernardino, CA 92405
City of Fontana
CALIF ORNIA
May 31, 2001"
RE: Slover Avenue Sewer
from Cherry Avenue to Hemlock Avenue.
Weekly Statement of Working Days Report Nos. 1'8 and 19
Dear Mr. Fischer:
Enclosed for the review are the weekly statements of working days
for week ending May 18, 2001. You will be allowed (15) days in
which to protest in writing the correctness of the statements;
otherwise the statements shall be deemed to have been accepted by
you as correct.
•
If you need additional information, please contact the undersigned
at (909) 350-7632.
Sincerely,,
COMMUNITY DEVELOPMENT DEPARTMENT
Engineering Division
Donald Gdula
Consultant Project Coordinator
Special Projects
cc: Principal Civil Engineer/Special Projects
Consultant Public Works Inspector (SB) w/enclosures
www.fontana.org
8353 SIERRA AVENUE FONTANA, CALIFORNIA 92335-3528 (909) 350-7600
recycled paper,
CITY OF FONTANA
WEEKLY STATEMENT OF WORKING DAYS
PROJECT: SLOVER AVENUE SEWER FROM CHERRY AVENUE TO HEMLOCK AVENUE
REPORT NO. 18
TO: FISCHER PLUMBING
The following statement shows the number of working days charged to your contract for the week
ending: 5/11/01
Date
Day
Weather, Weather Conditions or Other Conditions
Working
Day
Non -Working
Days
Caused by
Weather
Working Days
No Work
Done on
Controlling
Operation
(Note 2)
5/7/01
Mon.
Hot and Clear
1
0
0
5/8/01
Tue.
Hot and Clear
1
0
0
5/9/01
Wed.
Hot and Clear
1
0
0
5/10/01
Thur.
Hot and Clear
1
0
0
5/11/01
Fri.
Hot and Clear
1
0
0
Days this week
Days previously reported
Total days to date
5
0
0
• 60
18
8
65
18
8
TIME EXTENSIONS
CCO Numbers
(Note 3)
Days Ap roved
CCO Other
Days this report
Days previously reported.
Total days to date
0
0
0
0
0
0
0
10
0
COMPUTATION OF EXTENDED DATE FOR COMPLETION
1. First working day. designated
2. Working days specified in contract
3. COMPUTE DATE FOR COMPLETION(if all days specified are workable)
4. Total time extension days approved to date (CCO plus other)
5, Total non -working days to date (Note 4)
6. Sub Total (Line 4 plus Line 5)
7. EXTENDED DATE FOR COMPLETION (Line 3 plus Line 6)
8. Revised working days for contract (Line 2 plus Line 6)
9. Total working days to date
10. WORKING DAYS REMAINING (Line 8 minus Line 9)
Number
of Days
60
Numbered
Day (Note 4)
Date
1/8/01
Day No. 744
Day No. 804 1 4/4/01
0
26
26
MigWOMMM
86
65
21
Day No. 830
5/10/01
Controlling Operation(s)
Remarks: (Note 5) (Continue on reverse)
The Contractor will be allowed fifteen (15) days in which to protest
in writing the correctness of the statement; otherwise the statement
shall be deemed to have been accepted by the Contractor as correct.
NOTE: All footnotes are on the reverse side.
5/31/01
Donald Gdula/Project Coordinator
INSTRUCTION TO RESIDENT ENGINEER
1. When recording nonworking days due to weather; state the reason why
the day was unworkable when the weather description itself does not
adequately describe conditions. For example,' "Clear -wet grade" to
describe conditions when the weather is clear, but the grade is too wet to
work. Do not list days merely as "Unworkable".
2. Enter days on which no productive work has been performed • on the
. controlling operation(s) for reasons other than weather.
3. List numbers of contract change orders providing for time extensions.
4 Do not include nonworking days, which occur after expiration of the
Extended' DATE. OF -COMPLETION. ..On contracts that are overtime, the
total under WORKING DAYS shall not': be' greater than the .total of
REVISED WORKING. DAYS, (line 8). After approved total of working days
has been reached, continue recording working and nonworking. days but
do not add into the totals. Make ' statement under REMARKS. the
WORKING and NONWORKING days are shown for record.only since the
contract time has elapsed.
5. Time extensions other, are to be explained under REMARKS and the
followinginformation is to be included:.
(a)Cause of delay . and specification reference/under which approval
was granted.
• (b) Statement as to what controlling operation or operations are being
delayed and to'what extent.
(c) Dates for which the extension' was granted:
(d) Reference to supporting data.
ADDITIONAL REMARKS:
CITY OF FONTANA
WEEKLY STATEMENT OF WORKING DAYS
PROJECT: SLOVER AVENUE SEWER FROM CHERRY AVENUE TO HEMLOCK AVENUE
REPORT NO.
•
19
TO: FISCHER PLUMBING
The following statement shows the number of working days charged to your contract for the.week ending: 5/18/01
Date
Day
Weather, Weather Conditions or Other Conditions
Working
Day
Non -Working
Days
Caused by
Weather
Working Days
No Work
Done on
Controlling
Operation
(Note 2)
5/14/01
Mon.
Hot and Clear
1
0
0
5/15/01
Tue.
Hot and Clear
1
0
0
5/16/01
Wed.
Hot and Clear
1
0
0
5/17/01
- Thur.
Hot and Clear
1
10
0
5/18/01
Fri.
Hot and Clear •
1
10
0
Days this week
Days previously reported
Total days to date
5
0
0
65
18
8
70
18
8
TIME EXTENSIONS
.
CCO Numbers
(Note 3)
Days Ap roved
CCO Other
Days this report
Days previously reported.
Total days to date
0
0
0
0
0
0
• 0
0
0
COMPUTATION OF EXTENDED DATE FOR COMPLETION
1. First working day designated
2. Working days specified in contract
3. COMPUTE DATE FOR COMPLETION(if all days specified are workable)
4. Total time extension days approved to date (CCO plus other)
5. Total'non-working days to date (Note 4)
6. Sub Total (Line 4 plus Line 5)
7. EXTENDED DATE FOR COMPLETION (Line 3 plus Line 6)
8. Revised working days for contract (Line 2 plus Line 6)
9. Total working days to date
10. WORKING DAYS REMAINING (Line 8 minus Line 9)
Number
.of Days
MUMMUMM
60
Numbered
Day (Note 4)
Date
1/8/01
Day No. 744
0
26
26
86
70
16
Day No. 804 I 4/4/01
Da No. 830 r 5/10/01
Controlling Operation(s)
Remarks: (Note 5) (Continue on reverse)
The Contractor will be allowed fifteen (15) days in which to protest
in writing the correctness of the statement; otherwise the statement
shall be deemed to have been accepted by the Contractor as correct.
NOTE: All footnotes are on the reverse side.
5/31/01
Donald Gdula/Project Coordinator
INSTRUCTION TO RESIDENT ENGINEER
When recording nonworking days due to weather; .state the reason why
the day was unworkable when the weather description itself does not
adequately describe conditions. For example; "Clear -wet grade" to
describe conditions when the weather is clear, but the grade is too wet to
work. Do not list days merely as "Unworkable".
Enter days on which no productive work has been performed on the
controlling operation(s) for reasons other than weather.
3. List numbers of contract change orders providing for time extensions.
4. Do not include nonworking days, which occur after expiration of the
Extended DATE. OF COMPLETlON. On contracts that are overtime, the
total under WORKING DAYS. shall not': be. greater than the .total of
REVISED WORKING DAYS, (line 8). After approved total of working days
has been reached, continue recording working and nonworking. days but
do not add into the totals. Make ' statement under REMARKS. the
WORKING and NONWORKING days, are shown for record.only since the
contract time has elapsed.
5. Time extensions other, are to be explained under REMARKS and the
followinginformation is to be. included:.
(a) Cause of delay . and specification reference/under which approval
was granted.
• (b) Statement as to what controlling operation or operations are being
delayed and to' what extent.
(c) Dates for which the extension was granted.
(d) Reference to supporting data.
ADDITIONAL REMARKS:
Fischer Plumbing.
Mike Fischer, Owner
1372 W. 26th Street
San Bernardino, CA 92405
City of Fontana
CALIFORNIA'
May 15, 2001
RE: Slover Avenue Sewer
from Cherry Avenue to Hemlock Avenue
Weekly Statement of Working Days Report Nos. 16 and 17
Dear Mr. Fischer:
Enclosed for the review is the weekly statement of working days
for week ending May. 4, 2001. You will be allowed (15) days in
which to protest in writing the correctness of the statements;
otherwise the statements shall be deemed to have been accepted by
you as correct.
If you need additional information, please contact the undersigned
at (909) 350-7632.
Sincerely,
COMMUNITY DEVELOPMENT DEPARTMENT
Engineering Division
Donald Gdula
Consultant Project Coordinator
Special Projects
cc: Principal Civil Engineer/Special Projects
Consultant Public Works Inspector (SB) w/enclosures
www.fontana.org
8353 SIERRA AVENUE FONTANA, CALIFORNIA 92335-3528 (909) 350-7600
* recycled paper
J
CITY OF FONTANA
WEEKLY STATEMENT OF WORKING DAYS
PROJECT: SLOVER AVENUE SEWER FROM CHERRY AVENUE TO HEMLOCK AVENUE
REPORT NO. 17
TO: FISCHER PLUMBING
The following statement shows the number of working days charged to your contract for the week
ending: 5/4/01
Date
Day
Weather, Weather Conditions or Other Conditions
Working
Day
Non -Working
Days
Caused by
Weather
Working Days
No Work
Done on
Controlling
Operation
(Note 2)
4/30/01
Mon.
Warm and Clear
1
0
0
5/1/01
Tue.
Warm and Clear
1
0
0
5/2/01
Wed.
Warm and Clear
1
0
0
5/3/01
Thur.
High Wind
0
1
0
5/4/01
Fri.
Warm and Clear
1 •
0
0
Days this week
Days previously reported
Total days to date
4
1
0
56
17
8
60
18
8
TIME EXTENSIONS
CCO Numbers
(Note 3)
Days Ap roved
CCO Other
Days this report
Days previously reported. .
Total days to date
0
0
0
0
0
0
0
0
0
COMPUTATION OF EXTENDED DATE FOR COMPLETION
Number
of Days
Numbered
Day (Note 4)
Date
1. First working day designated
daysspecified
Working in contract
3. COMPUTE DATE FOR COMPLETION(if all days specified are workable)
4. Total time extension days approved to date (CCO plus other)
5. Total non -working days to date (Note 4)
6. Sub Total (Line 4 plus Line 5)
7. EXTENDED DATE FOR COMPLETION (Line 3'plus Line 6)
8. Revised working days for contract (Line 2 plus Line 6)
9. Total working days to date
10. WORKING DAYS REMAINING (Line 8 minus Line 9)
Managne
60
1/8/01
Day No. 744
WisMONWN
0
26
26
86
60
26
Day No. 804 4/4/01
Day No. 830
5/10/01
Controlling Operation(s) Thursday, May 3, 2001 was a non -working day due to
high winds.
Remarks: (Note 5) (Continue on reverse)
The Contractor will be allowed fifteen (15) days in which to protest
in writing the correctness of the statement; otherwise the statement
shall be deemed to have been accepted by the Contractor as correct.
NOTE: All footnotes are on the reverse side.
5/15/01
Donald Gdula/Project Coordinator
INSTRUCTION TO RESIDENT ENGINEER
When recording nonworking days due to weather; state the reason why
the day was unworkable when the weather description itself does not
adequately describe conditions. For example; "Clear -wet grade" to
describe conditions when the weather is clear, but the grade is too wet to
work. Do not list days merely as "Unworkable".
2. Enter days on which no productive work has been performed on the
controlling operation(s) for reasons other than weather.
3. List numbers of contract change orders providing for time extensions:
4 Do not include nonworking days, which occur after expiration of the
Extended DATE. OF: COMPLETION. On contracts that are overtime, the
total under WORKING DAYS shall not: be' greater than the .total of
REVISED WORKING. DAYS, (line 8). After approved total of working days
has been 'reached, continue recording working and nonworking. days, but
do not add into the totals. Make ' statement under . REMARKS. the
WORKING' and NONWORKING days are shown for record. only since the
contract time has elapsed.
5. Time extensions other, are to be explained under REMARKS and the
followinginformation is to be included:.
(a)' Cause of delay and specification reference/under which approval
was granted.
(b) Statement as to what controlling operation or operations are being
delayed and to what extent.
(c) Dates for which the extension was granted.
(d) Reference to supporting data.
ADDITIONAL, REMARKS:
CITY OF FONTANA
WEEKLY STATEMENT OF. WORKING DAYS
PROJECT: SLOVER AVENUE SEWER FROM CHERRY AVENUE TO HEMLOCK AVENUE
TO: FISCHER PLUMBING'
REPORT1NO. 16
The following statement shows the number of working days charged to your contract for the week ending: 4/27/01
Date
Day
Weather,
Weather Conditions or Other Conditions
Working
Day
Non -Working
Days
Caused by
Weather
Working Days
No Work
Done on
Controlling
Operation
(Note 2)
4/23/01
Mon.
Warm and
Clear
1
0
0
4/24/01
Tue.
Warm and
Clear
1
0
0
4/25/01
Wed.
Warm and
Clear
1
0
0
4/26/01
Thur.
Warm and
Clear
' 1
0
0
4/27/01
Fri.
Warm and
Clear
1
0
0
Days this week
Days previously reported
Total days to date
5
0
0
.
51
17
8
56
17
8
TIME EXTENSIONS
CCO Numbers
(Note 3)
Days Ap roved
CCO Other
Days this report
Days previously reported.
Total days to date
•
0
0
0
0
0
0
• 0
0
0
COMPUTATION OF EXTENDED DATE FOR COMPLETION
Number
1. First working day designated
2. Working days specified in contract
3. COMPUTE DATE FOR COMPLETION(if all days specified are workable)
4. Total time extension days approved to date (CCO plus other)
5. Total non -working days to date (Note 4)
6. Sub Total (Line 4 plus Line 5)
7. EXTENDED DATE FOR COMPLETION (Line 3 plus Line 6)
8. Revised working days for contract (Line 2 plus Line 6)
9. Total working days to date
10. WORKING DAYS'REMAINING (Line 8 minus Line 9)
Controlling Operation(s)
of Days
60
Numbered
Day (Note 4)
Date
1/0/01
Day No. 744
0
25
25
85
56 .
29
Day No. 804 J 4/4/01
Day No. 829
5/9/01
Remarks: (Note 5) (Continue on reverse)
The Contractor will be allowed fifteen (15) days in which to protest
in writing the correctness of thestatement; otherwise the statement
shall be deemed to have been accepted by the Contractor as correct.
NOTE: All footnotes are on the reverse side.
5/15/01
Donald Gdula/Project Coordinator
INSTRUCTION TO RESIDENT ENGINEER
When recording nonworking days due to weather; state the reason why
the day was unworkable when the weather description itself does not
adequately describe conditions. For example,. "Clear -wet grade" to
describe conditions when the weather is clear, but the grade is too wet to
work. Do not list days merely as "Unworkable
2 Enter days on which no productive work has been performed • on the
controlling operation(s) for reasons other than weather.
3. • List numbers of contract change orders providing for time extensions'.
4. Do not include nonworking days, which occur after expiration of the
Extended DATE OF -COMPLETION. On contracts that are .overtime, the
total under WORKING DAYS shall not'. be. greater than the .total of
REVISED WORKING. DAYS, (line 8). After approved total of workingdays
has been reached, continue recording working and nonworking_ days but
do not add into the totals. Make statement under REMARKS. the
WORKING and NONWORKING days are shown for record. only since •the
contract time has elapsed.
5. Time extensions other, are to be explained under REMARKS and the
followinginformation is to be included:.
(a)* Cause of delay and specification reference/under which approval
was granted.
• (b) Statement as to what controlling operation or operations are being
delayed and to•what extent.
(c) Dates for which the extension was granted.
(d) • Reference to supporting data.
ADDITIONAL REMARKS:
Fischer Plumbing
Mike Fischer, Owner
1372 W. 26th Street
San Bernardino, CA 92405
City of Fontana
CALIFORNIA
April 26, 2001
RE: Slover Avenue Sewer
. from Cherry Avenue to Hemlock Avenue
Weekly Statement of Working Days Report Nos. 13, 14 and 15'
Dear Mr. Fischer:
Enclosed for the, review is the weekly statementof working days
for week ending April 20, 2001. You will be allowed (15) days in
which to protest in writing the correctness of the statements;
otherwise the statements shall be deemed to have been accepted by
you as correct.
If you need additional information, please contact the undersigned
at (909) 350-7632.
Sincerely,
COMMUNITY DEVELOPMENT DEPARTMENT
Engineering Division
Donald Gdula
Consultant Project Coordinator
Special Projects
cc: Principal Civil Engineer/Special Projects
Consultant Public Works Inspector (SB) w/enclosures
www.fontana.org
8353 SIERRA AVENUE FONTANA, CALIFORNIA 92335-3528 (909) 350-7600
11) recycled paper
CITY OF FONTANA
WEEKLY STATEMENT OF WORKING DAYS
PROJECT: SLOVER AVENUE SEWER FROM CHERRY AVENUE TO HEMLOCK AVENUE
REPORT NO. 13
TO: FISCHER PLUMBING
The following statement shows the number of working days charged to your contract for the week
ending: 4/6/01
Date
Day
Weather, Weather Conditions or Other Conditions
' Working
Day
Non -Working
Days
Caused by
Weather ,
Working Days
No Work
Done on
Controlling
Operation
(Note 2)
4/2/01
Mon.
Cool and Clear
1
0
0
4/3/01
Tue.
Cool and Clear
1
0
0
4/4/01
Wed.
Cloudy and Cold
1
0
0
4/5/01
Thur.
Cloudy and Cool
1
0
0
4/6/01
Fri.
Cloudy and Cool
1
0
0
Days this week
Days previously reported
Total days to date
5
0
0
37
16
8
42
16
8
TIME EXTENSIONS
CCO Numbers
(Note 3)
Days Approved
Other
CCO
Days this report
Days previously reported.
Total days to date
0
0
'0
0
0
0
0
0
0
COMPUTATION OF EXTENDED DATE FOR COMPLETION
Number
of Days
Numbered
Day (Note 4)
Date
1. First working day designated
dayssp
ecified Working s ecified in contract
3. COMPUTE DATE FOR COMPLETION(if all days specified.are workable)
4. Total time extension days approved to date (CCO plus other)
5. Total non -working days to date (Note 4)
6. Sub Total (Line 4 plus Line 5)
7. EXTENDED DATE FOR COMPLETION (Line 3 plus Line 6)
8. Revised working days for contract (Line 2 plus Line 6)
9. Total working days to date.
10. WORKING DAYS REMAINING (Line 8 minus Line 9)
VgiMMOMOM
60
1/8/01
Day No. 744
Day No. 804
0
24
24
4/4/01
MgMMWMO
84
42
42
Day No. 828 I 5/8/01
Controlling Operation(s)
Remarks: (Note 5) (Continue on reverse)
The Contractor will be allowed fifteen (15) days in which to protest
in writing the correctness of the statement; otherwise the statement
shall be deemed to have been accepted by the Contractor as correct.
NOTE: All footnotes are on the reverse side.
4/26/01
Donald Gdula/Project Coordinator
INSTRUCTION TO RESIDENT ENGINEER
1. When recording nonworking days due to weather; state the reason why
the day was unworkable when the weather description itself does not
adequately describe conditions. For example,. "Clear -wet grade" to
describe conditions when the weather is clear, but the grade is too wet to
work. Do not list days merely as "Unworkable".
2 Enter days on which no productive work has been performed on the
controlling operation(s) for reasons other than weather.
3. List numbers of contract change orders providing for time extensions.
4. Do not include nonworking days, which occur after expiration of the
Extended DATE OF -COMPLETION. On contracts that are overtime, the
total under WORKING DAYS shall not be greater than the .total of
REVISED WORKING. DAYS, (line 8). After approved total of working days
has been reached, continue recording working and nonworking. days but
do not add into the. totals. Make statement under REMARKS, the
WORKING and NONWORKING days are shown for record only since the
contract time has elapsed.
5 Time extensions other, are to be explained under REMARKS and the
followinginformation is to be included:.
(a) Cause of delayand specification reference/under which approval
was granted.
(b) Statement as to what controlling operation .or operations are being
delayed and to'what extent.
(c) Dates for which the extension was granted.
(d) Reference to supporting data.
ADDITIONAL REMARKS:
CITY OF FONTANA
• WEEKLY STATEMENT OF WORKING DAYS
PROJECT: SLOVER AVENUE SEWER FROM CHERRY AVENUE TO HEMLOCK AVENUE
REPORT NO. 14
TO: FISCHER PLUMBING
The following statement shows the number of working days charged to your contract for the week
ending: 4/13/01
Date
Day
Weather, Weather Conditions or Other Conditions
Working
Day
Non -Working
Days
Caused by
Weather
Working Days
No Work
Done on
Controlling
Operation
(Note 2)
4/9/01
Mon.
Rain
0
1
0
4/10/01
Tue.
Cloudy
1
0
0
4/11/01
Wed.
Cloudy
1
0
0
4/12/01
Thur.
Cool and Clear
1
0
0
4/13/01
Fri.
Cool and Clear
1
0
0
Days this week
Days previously -reported
Total days to date .
4
1
0
42
16
8
46
17
8
TIME EXTENSIONS
CCO Numbers
(Note 3)
Days Approved
Other
CCO
Days this report
Days previously reported.
Total days to date
0
0
0
0
0
0
0
0
0
COMPUTATION OF EXTENDED DATE FOR COMPLETION
1. First working day designated
2. Working days specified in contract
3. COMPUTE DATE FOR COMPLETION(if all days specified are workable)
4. Total time extension days approved to date (CCO plus other)
5. Total non -working days to date (Note 4)
.6. Sub Total (Line 4 plus Line 5)
7. EXTENDED DATE FOR COMPLETION (Line 3 plus Line 6)
8. Revised working days for contract (Line 2 plus Line 6)
9. Total working days to date
10. WORKING DAYS REMAINING (Line 8 minus Line 9)
Number•
of Days
60
Numbered
Day (Note 4)
Date
1/8/01
Day No. 744
0
25
25
MWMiiiMgMi
85
46
39
Day No. 804 4/4/01
Day No. 829
5/9/01
Controlling Operationa)
Remarks: (Note 5) (Continue on reverse)
The Contractor will be allowed fifteen (15) days in which to protest
in writing the correctness of the statement; otherwise the statement
shall be deemed to have been accepted by the Contractor as correct.
NOTE: All footnotes are on the reverse side.
4/26/01
Donald Gdula/Pro'ect Coordinator
INSTRUCTION TO RESIDENT ENGINEER
When recording nonworking days due to weather; state the reason why
the day was unworkable when the weather description itself does not
adequately describe conditions. For example; "Clear -wet grade" to
. describe conditions when the weather is clear, but the grade is too wet to
work. Do not -list days merely as "Unworkable".
2. Enter days. on which no productive work has been performed on the
controlling operation(s) for reasons other than weather.
3. List numbers of contract change orders providing for time extensions.
4. Do not include nonworking days, which occur after expiration of the
Extended DATE OF -COMPLETION. On contracts that are overtime, the
total under WORKING DAYS shall not; be greater than the .total of
REVISED WORKING. DAYS, (line 8). After approved total of working days
has been reached, continue recording working and nonworking_ days but
do not add into the totals. Make statement under REMARKS. the
WORKING and NONWORKING days are shown for record* only since the
contract time has elapsed.
5. Time extensions other, are to be explained under REMARKS and the
followinginformation is to be included:.
(a)Cause of delay . and specification reference/under which approval
was granted.
(b) Statement as to what controlling operation or operations are being
delayed and to what extent.
(c) Dates for which the extension was granted.
(d) Reference to supporting data.
ADDITIONAL REMARKS:
•
CITY OF FONTANA
WEEKLY STATEMENT OF WORKING DAYS
PROJECT: SLOVER AVENUE SEWER FROM CHERRY AVENUE TO HEMLOCK AVENUE
REPORT
NO. 15
TO: FISCHER PLUMING
The following statement shows the number of working days charged, to your contract for the week ending: 4/20/01
Date
Day
Weather, Weather Conditions or Other Conditions
Working
Day
Non -Working
Days
Caused by
Weather
Working Days
No Work
Done on
Controlling
Operation
(Note 2)
4/16/01'
Mon.
Very Warm and Clear
1
0
0
4/17/01
Tue.
Very Warm and Clear
1
0
0
4/18/01
Wed.
Very Warm and Clear
i
0
0
4/19/01
Thur.
Warm and Clear
1
0
0
4/20/01
Fri.
Warm and Clear
1
0
0
Days this week
Days previously reported
Total days to date
5
0
0
46
17
8
51
17
8
TIME EXTENSIONS
•
CCO Numbers
• (Note.3.).
Days Ap roved
CCO Other
Days this report
Days previously reported.
Total days to date
0
0.
0
0
0
0
0
0
0
COMPUTATION OF EXTENDED DATE FOR COMPLETION
1. First working day designated
2. Workingspecified
da s y in contract
3. COMPUTE DATE FOR COMPLETION(if all days specified are workable)
4. Total time extension days approved to date (CCO plus other)
5. Total non -working days to date (Note 4)
6. Sub Total (Line 4 plus Line 5)
7. EXTENDED DATE FOR COMPLETION (Line 3 plus Line 6)
8. Revised working days for contract (Line 2 plus Line 6)
9. Total working days to date
10. WORKING DAYS REMAINING (Line 8 minus Line 9)
Controlling Operation(s)
Number
of Days
WMMONWO
60
Numbered
Day (Note 4)
Date
1/8/01
Day No. 744
0
25
25
85
51
34
Day No. 804 4/4/01
Day No. 829 J • 5/9/01
Remarks: (Note 5) (Continue on reverse)
The Contractor will be allowed fifteen (15) days in which to protest
in writing the correctness of the statement; otherwise the statement
shall be deemed to have been accepted by the Contractor as correct.
NOTE: All footnotes are on the reverse side.
4/26/01
Gdula/Project Coordinator
•
INSTRUCTION TO RESIDENT ENGINEER
When recording nonworking days due to weather; state the reason why.
the day was unworkable when the weather description itself does not
adequately describe conditions. For example; "Clear -wet grade" to
describe conditions when the weather is clear, but the grade is too wet to
work. Do not list days merely as "Unworkable".
2 Enter days on which no productive work has been performed on the
controlling operation(s) for reasons other than weather.
3. List numbers of contract change orders providing for time extensions.
4. Do not include nonworking days, which occur after expiration of the
Extended DATE OF -COMPLETION. On contracts that are overtime, the
total under WORKING DAYS shall not': be greater than the .total' of
REVISED WORKING DAYS, (line 8). After approved total of working days
has been reached, continue recording working and nonworkingdays but
do not add into the totals. Make statement under REMARKS. the
WORKING and NONWORKING days are shown for record' only since the
contract time has elapsed.
5. Time extensions other, are to be explained under REMARKS and the
followinginformation is to be included:.
(a) Cause of delay . and specification reference/under which approval
was granted.
(b) Statement as to what controlling operation .or operations are being
delayed and to what extent.
(c) Dates for which the extension was granted.
(d) Reference to supporting data. '
ADDITIONAL REMARKS:
Fischer Plumbing
Mike Fischer, Owner
1372 W. 26th Street
San Bernardino, CA 92405
City of Fontana
CALIFORNIA
April 4, 2001
RE: Slover Avenue Sewer
from Cherry Avenue to Hemlock Avenue
Weekly Statements of Working Days Report Nos. 10, 11 and 12
Dear Mr. Fischer:
Enclosed for the review are the weekly statements of working days
for week ending March 30, 2001. You will be allowed (15) days in
which to protest in writing the correctness of the statement;
otherwise the statement shall be deemed to have been accepted by
you as correct.
If you need additional information, please contact the undersigned
at (909) 350-7632.
Sincerely,
COMMUNITY DEVELOPMENT DEPARTMENT
Engineering. Division
Donald Gdula
Consultant Project Coordinator
Special Projects
cc: Principal Civil Engineer/Special Projects
Consultant Public Works Inspector (SB)
www.fontana.org
8353 SIERRA AVENUE FONTANA, CALIFORNIA 92335-3528 (909) 350-7600
recycled paper
CITY OF FONTANA
WEEKLY STATEMENT OF WORKING DAYS
PROJECT: SLOVER AVENUE SEWER FROM CHERRY AVENUE TO HEMLOCK AVENUE
REPORT NO.
10
TO: FISCHER PLUMBING
The following statement shows the number of working days charged to your contract for the week ending:, 3/16/01
Date
Day
Weather, Weather Conditions or Other Conditions
Working
Day
Non -Working
Days
Caused by
Weather
Working Days
No Work
Done on
Controlling
Operation
(Note 2)
3/12/01
Mon.
Clear
1
0
0
3/13/01
Tue.
Clear
1
0
0
3/14/01
Wed.
Clear
1
0
0
'3/15/01
Thur.
Clear
1
0
0
3/16/01
Fri.
Clear
1
0
0
Adjustment for Holiday on 2/19/01
1
Days thls week
Days previously reported
Total days to date
5
0
1
22
16
7
27
16
8
TIME EXTENSIONS
CCO Numbers
(Note 3)
Days Ap roved
CCO Other
Days this report
Days previously reported.
Total days to date
0
°0
0
0
0
7
' 0
0
7
COMPUTATION OF EXTENDED DATE FOR COMPLETION
1. First working day designated
2. Working days specified in contract
3. COMPUTE DATE FOR COMPLETION(if all days specified are workable)
4. Total time extension days approved to date (CCO plus other)
5. Total non -working days to date (Note 4)
6. Sub Total (Line 4 plus Line 5)
7. EXTENDED DATE FOR COMPLETION (Line 3 plus Line 6)
8. Revised working days for contract (Line 2 plus Line 6)
9. Total working days to date
10. WORKING DAYS REMAINING (Line 8 minus Line 9)
Number
of Days
:...........................
60
Numbered
Day (Note 4)
Date
1/8/01
Day No. 744
Day No. 804 4/4/01
0
24
24
MMWMMIEM
84
27
57
Day No. 828 1 5/8/01
Controlling Operation(s)
Remarks: (Note 5) (Continue on reverse)
Adjustment'of working days add one (1) Working day to contract completion date for the Holiday
on Monday February 19, 2001.
The Contractor will be allowed fifteen (15) days in which to protest
in writing the correctness of the statement; otherwise the statement
shall be deemed to have been accepted by the Contractor as correct.
NOTE: All footnotes are on the reverse side.
Donald Gdula/Project Coordinator
4/3/01
•
INSTRUCTION TO RESIDENT ENGINEER
When recording nonworking days due to weather; state the reason why
the day was unworkable when the weather description itself does not
adequately describe conditions. For example; "Clear -wet grade" to
describe conditions when the weather is clear, but the grade is too wet to
work. Do not list days merely as "Unworkable".
•
Enter days on which no productive work has been performed on the
controlling operation(s) for reasons other than weather.
3. List numbers of contract change orders providing for time extensions.
•
4. Do not include nonworking days, which occur after expiration of the
Extended DATE OF :COMPLETION. On contracts that are overtime, the
total under WORKING DAYS , shall not : be greater than the .total of
REVISED WORKING. DAYS, (line 8). After approved total of working days
has 'been reached, continue recording working and nonworkingdays but
do not add into . the totals. Make statement under REMARKS. the
WORKING and NONWORKING days are shown forrecord' only since the
contract time has elapsed.
5. Time extensions other, are to be explained under REMARKS and the
'.following. information is to be included:.
(a)Cause of delay . and specification reference/under which approval
was granted.
(b) • Statement as to what controlling operation or operations are being
delayed and to' what extent. .
(c) Dates for which the extension' was granted.
(d) Reference to supporting data.
ADDITIONAL REMARKS:
CITY OF FONTANA
WEEKLY STATEMENT OF WORKING DAYS
PROJECT: SLOVER AVENUE SEWER FROM CHERRY AVENUE TO HEMLOCK AVENUE
REPORT NO. 11
TO: FISCHER PLUMBING
The following statement shows the number of working days charged to your contract for the week ending: 3/23/01
Date
Day
Weather, Weather Conditions or Other Conditions
Working
Day
.
Non -Working
Days
Caused by
Weather
Working Days
No Work
Done on
Controlling
Operation'
(Note 2)
3/19/01
Mon.
Clear
1
0
0
3/20/01
Tue.
Clear
1
0
0
3/21/01
Wed.
Clear
1
0
0
3/22/01
Thur.
Clear
1
0
0
3/23/01
Fri.
Partly Cloudy
1
0
0
Days this week
Days previously reported
Total days to date
5
0
0
27
16
8
32
16
8
TIME EXTENSIONS
CCO Numbers
(Note 3)
Days Ap roved
CCO Other
Days this report
Days previously reported.
Total days to date
0
0
0
0
0
0
0
0
0
COMPUTATION OF EXTENDED DATE FOR COMPLETION
1. First working day designated
2. Workingdaysspecified s ecified in contract
3. COMPUTE DATE FOR COMPLETION(if all days specified are workable)
4. Total time extension days approved to date (CCO plus other)
5. Total non -working days to date (Note 4)
6. Sub Total (Line 4 plus Line 5)
7. EXTENDED DATE FOR COMPLETION (Line 3 plus Line 6)
8. Revised working days for contract (Line 2 plus Line 6)
9. Total working days to date
10. WORKING DAYS REMAINING (Line 8 minus Line 9)
Controlling Operation(s)
Number
of Days
60
Numbered
Day'(Note 4)
Date
1/8/o1
Day No. 744
Day No. 804 1 4/4/01
0
24
24
84
32
52
Day No. 828
5/8/oi
Remarks: (Note 5) (Continue on reverse)
The Contractor will be allowed fifteen (15) days in which to protest
in writing the correctness of the statement; otherwise the statement
shall be deemed to have been accepted by the Contractor as correct.
NOTE: All footnotes are on the reverse side.
Donald Gdula/Project Coordinator
4/3/01
INSTRUCTION TO RESIDENT ENGINEER
When recording nonworking days due to weather; state the reason why
the day was unworkable when the weather description itself does not
adequately describe conditions. For example; "Clear -wet grade" to
describe conditions when the weather is clear, but the grade is too wet to
work. Do not list days merely as "Unworkable".
2 Enter days • on which no productive work has been performed on the
controlling operation(s) for reasons other than weather.
3 List numbers of contract change orders providing for time. extensions.
4. Do not include nonworking days, which occur after expiration of the
Extended DATE.. OF :COMPLETION. On contracts that are .overtime, the
total under WORKING DAYS shall not be greater than the total of
REVISED WORKING DAYS, (line 8). After approved total of working days
has been reached, continue recording working and nonworking. days but
do not add into the totals. Make statement under REMARKS. the
WORKING and NONWORKING days are shown for record only since the
contract time has elapsed.
5. Time extensions other, are to be explained under REMARKS and the
-following-information is to be included:
(a)Cause of delay and specification reference/under which approval
was granted.
• (b) Statement as to what controlling operation or operations are being
delayed and to what extent.
(c) Dates for which the extension was granted.
(d) Reference to supporting data.
ADDITIONAL REMARKS:
CITY OF FONTANA
WEEKLY STATEMENT OF WORKING DAYS
PROJECT: SLOVER AVENUE SEWER FROM CHERRY AVENUE TO HEMLOCK AVENUE
REPORT NO. 12
TO: FISCHER PLUMBXNG
The following statement shows the number of working days charged to your contract for the week ending: 3/30/01
Date
Day
Weather, Weather Conditions or Other Conditions
Working
Day
Non -Working
Days
Caused by
Weather
Working Days
No Work
Done on
Controlling
Operation
(Note 2)
3/26/01
Mon.
Warm and Clear
1
0
0
3/27/01
Tue.
Warm and Clear
1
0
0
3/28/01
Wed.
Warm and Clear
1
0
0
3/29/01
Thur.
Warm and Clear
1
0
0
3/30/01
Fri.
Warm and Clear
1
0
0
Days this week
Days previously reported
Total days to date
5
0
0
32
16
8
37
16
8
TIME EXTENSIONS
CCO Numbers
(Note 3)
'Days Ap roved
CCO Other
Days this report
Days previously reported.
Total days to date
0
0
0
0
0
0
0
•0;
0
COMPUTATION OF EXTENDED DATE FOR.COMPLETION
Number
of Days
Numbered
Day (Note 4)
Date
1. First working day designated
2. Workingdaysspecified s ecified in contract
3. COMPUTE DATE FOR COMPLETION(if all days specified are workable)
4. Total time extension days approved to date (CCO plus other)
5. Total non -working days to date (Note 4)
6. Sub Total (Line 4 plus Line 5)
7. EXTENDED DATE FOR COMPLETION (Line 3 plus Line 6)
8. Revised working days for contract (Line 2 plus Line 6)
9. Total working days to date
10. WORKING DAYS REMAINING (Line 8 minus Line 9)
60
EMMOW
0
24
24
84
37
47
1/8/01
Day No. 744
DarNo. 804 f 4/4/01
Day No. 828 I 5/8/01
Controlling Operation(a)
Remarks: (Note 5) (Continue on reverse)
The Contractor will be allowed fifteen (15) days in which to protest
in writing the correctness of the statement; otherwise the statement
shall be deemed to have been accepted by the Contractor as correct.
NOTE: All footnotes are on the reverse side.
Donald Gdula/Project Coordinator
4/3/01
• •
INSTRUCTION TO RESIDENT ENGINEER
1. When recording nonworking days due to weather; state the reason why
the day was unworkable when the weather description itself does not
adequately describe conditions. For example,' "Clear -wet grade" to
describe conditions when the weather is clear, but the grade is too wet to
work. Do not list days merely as "Unworkable".
Enter days on which no productive work has been performed on the
controlling operation(s) for reasons other than weather.
. List numbers of contract change orders providing for time extensions'.
4 Do not include nonworking days, which occur after expiration of the
Extended DATE. OF: COMPLETION. On contracts that are .overtime, the
total under WORKING DAYS shall not be greater than. the total of
REVISED WORKING. DAYS, (line 8). After approved total of working days
has been reached, continue recording working and nonworking. days but
do not add into the totals. Make statement under REMARKS. the
WORKING and NONWORKING days are shown for record only since the
contract time has elapsed.
5 Time .extensions other, are to be explained under REMARKS and the
following: information is to be included:.
(a)* Cause of delay and specification reference/under which approval
was granted.
• (b) • Statement as to what controlling operation or operations are being
decayed and to' what extent.
(c) Dates for which the extension was granted.
(d) Reference to 'supporting data. .
ADDITIONAL REMARKS:
:1 VTh R,VI'YlV. , , ,
• •
City of Fontana
CALIFORNIA
Fischer Plumbing
Mike Fischer, Owner
1372 W. 26th Street
San Bernardino, CA 92405
RE: Slover Avenue Sewer
from Cherry Avenue to Hemlock Avenue
Weekly Statement of Working Days Report No. 9
Dear Mr. Fischer:
March 1 , 2001
Enclosed for the review is the weekly statement of working days
for week ending March 9, 2001. You will be allowed (15) days in
which to protest in writing the correctness of the statement;
otherwise the statement shall be deemed to have been accepted by
you as correct.
If you need additional information, please contact the undersigned
at (909) 350-7632.
Sincerely,
Community Development Department
Engineering Division
Donald Gdula
Consultant Project Coordinator
Special Projects
Enclosures: Weekly Statement of Working Days
cc: Principal Civil Engineer/Special Projects
Consultant Public Works Inspector (SB) w/enclosures
www.fontana.org
8353 SIERRA AVENUE FONTANA, CALIFORNIA 92335-3528 (909) 350-7600
recycled paper
'�ex;v e.^erw
:atn ae;,n:
4,414444
CITY OF FONTANA
WEEKLY STATEMENT OF WORKING DAYS
PROJECT: SLOVER AVENUE SEWER FROM CHERRY AVENUE TO HEMLOCK AVENUE
REPORT NO.
9
TO: FISCHER PLUMBING
The following statement shows the number of working days charged to your contract for the week ending: 3/9/01
Date
Day
Weather, Weather Conditions or Other Conditions
•
Working
Day
Non -Working
Days
Caused by
Weather
Working Days
No Work
Done on
Controlling
Operation
(Note 2)
3/5/01
Mon.
Clear
1
0
0
3/6/01
Tue.
Rain
0
11
0
3/7/01
Wed.
Rain
0
1
0
3/8/01
Thur.
Clear
1
0
0
3/9/01
Fri.
Clear
1
0
0
Days this week
Days previously reported
Total days to date
3
2
0
19
14
7
22
16
7
TIME EXTENSIONS
CCO Numbers
(Note 3)
Days Ap roved
CCO Other
'Days this report
Days previously reported.
Total days to date
0
0
0
0..
0
7
0
0
7
COMPUTATION OF EXTENDED DATE FOR COMPLETION
Number
Numbered
Day (Note 4)
Date
of Days
1. First working day designated
..................................
••�•��������v•�•••�•��•��••�•����
.••60•J.
Day No. 744
01
Vein
2.
Working days specified in contract
............................... ........ :.:.:.WM•
3.
COMPUTE DATE FOR COMPLETION(ifall days specified are workable)
�.
%'•%%;:."?�:<�'%`:'
DayNo. 804 4/4/01
4.
Total time extension days approved to date, (CCO plus other)
M1•�0
`•�:::::::>•::::::»<•>#........,.;;•.�:.;;:.,.:,.:.;:..;:.:;..;,;.;;..::.�,
5.
Total non -working days to date (Note 4)
23
».:».:»'::` •:: >:
:? r »4,> >:'!
6
7 .
8.
Sub Total (Line 4 plus Line 5)23 DATEON(Line 3plus Line
EXTENDED FOR.COMPLETION 6)
Revised workingdays for contract(Line 2plus Line
Y 6)
.::a827•::5/701
Day No ..:: 8•:::::::..:::::::.::.
:;:>:
�::: �.
m:.:::::_
:...............................:
83
::... •
9. Total working days to date
22
)yss`': s`:;::^`::;:<v:<::':>>?;3.%,'•
10. WORKING DAYS REMAINING (Line 8 minus Line 9)
61
.;:.<:;.:.;::,::::;;;;�.:.:.:.......:..........;:..;.......
Controlling Operation(s) Add two (2) working days to contract completion date due to rain on Tuesday
3/6/01 and Wednesday 3/7/01.
Remarks: (Note 5) (Continue on reverse)
The Contractor will be allowed fifteen (15) days in which to protest
in writing the correctness of the statement; otherwise the statement
shall be deemed to have been accepted by the Contractor as correct.
NOTE: All footnotes are on the reverse side.
3/16/01
Donald Gdula/Project Coordinator
City of Fontana
CALIFORNIA'
Fischer Plumbing
Mike Fischer, Owner
1372 W. 26th Street
.San Bernardino, CA 92405
RE: Stover Avenue Sewer
from Cherry Avenue to Hemlock Avenue
Weekly Statement of Working Days Report No. 8
Dear Mr. Fischer:
March 6, 2001
,Enclosed for the review is the weekly statement of working days
for week ending March 2, 2001. You will be allowed (15) days in
which to protest in writing the correctness of the statement;
otherwise the statement shall be deemed to have been accepted by
you as correct.
If you need additional information, please contact the undersigned
at (909) 350-7632.
Sincerely,
Community Development Department
Engineering Division
Donald Gdula
Consultant Project Coordinator
Special Projects
Enclosures: Weekly Statement of Working Days
cc: Principal Civil Engineer/Special Projects
Consultant Public Works Inspector (SB) w/enclosures
www.fontana.org
8353 SIERRA AVENUE FONTANA, CALIFORNIA 92335-3528 (909) 350-7600
recycled paper
CITY OF FONTANA
WEEKLY STATEMENT OF WORKING DAYS
PROJECT: SLOVER AVENUE SEWER FROM CHERRY AVENUE TO HEMLOCK AVENUE
REPORT NO.
8
TO: FISCHER PLUMBING
The following statement shows the number of working days charged to your contract for the week,ending:13/2/01
Date
Day
Weather, Weather Conditions or Other Conditions
Working
Day
Non -Working
Days
Caused by
Weather
Working Days
No Work
Done on
Controlling
Operation
(Note 2)
2/26/01
Mon.
Rain
0
1
0
2/27/01
Tue.
Rain
0 •
.1
0
2/28/01
Wed.
Cloudy and Cool
1
0
0
3/1/01
Thur.
Clear
1
0
0
3/2/01
Fri.
Clear
1
0
0
Days this week
Days previously reported
Total days to date
3
2
0
16
12
7
19
•14
7
TIME EXTENSIONS .
CCO Numbers
(Note 3)
Days Ap roved
CCO Other
Days this report
Days previously reported.
Total days to date
0
0
0
0
.0•
7
0
0
7
COMPUTATION OF EXTENDED DATE FOR COMPLETION
Number
Numbered
Day (Note 4)
Date
of Days
1.
First working day designated
...:....<::....::.:.::..:..........
E<:: :> >•:r: ::::
Rey No. 744
1/8/01
2.
Working days specified in contract
60
MUMOMftig0WWWia
3.
COMPUTE DATE FOR COMPLETION(if all days specified are workable)
":,. ,
""""`'""``""`"'
Day No.
804 4/4/01
4
Total time extension days approvedto dateplus other)0J
y pp (CCO
:'•::»'•»'•s::>::s::>:>f:#::?>::>>?:::??
5.
6.
Total non -working g days to date (Note 4) .
Sub Total (Line 4 plus Line 5)2
21
=£':h�•,'"�•,•��:a:;?'�>;:��:••<.:::'s.,
:•.r>.>.:::>:•>;:;:s;:•>;
.:..:::.:..::.:•,:x..
..:
::.a:
i>�� �: �>%::
>::>F�•z:•
7. EXTENDED DATE FOR COMPLETION(Line 3 plusLine
6)
>»:<%;<.i:.#i::#>::»a
""""' ..........
Day No.
825
5/3/01
Revised working days for contract (Line 2 plus Line 6
81
:•'. >':«"• «2 `•>:•.< ::z'. :#> ..
9. Total working days to date
19
�• • � �•••:::::;::;s::>:�::;:;
10. WORKING DAYS REMAINING (Line 8 minus Line 9)
62
,....,.,,
..:;-;:;:
Controlling Operation(s)
Remarks: (Note 5) (Continue on reverse)
The Contractor will be allowed fifteen (15) days in which to protest
in writing the correctness of the statement; otherwise the statement
shall be deemed to have been accepted by the Contractor as correct.
NOTE: All footnotes are on the reverse side.
3/6/01
Donald Gdula/Project Coordinator
INSTRUCTION TO RESIDENT ENGINEER
When recording nonworking days due to weather; state the reason why
the day was unworkable when the weather description itself does not
adequately describe conditions. For example,' "Clear -wet grade" to,
describe conditions when the weather is clear, but the grade is too wet to
work. Do not list days merely as "Unworkable".
Enter days on which no productive work has been performed on the
controlling operation(s) for reasons other than weather.
3. • List numbers of contract change orders providing for time extensions.
•
4. Do not include nonworking days, which occur after expiration of the
Extended. DATE. OF:COMPLETION. On contracts that are overtime, the
total under WORKING DAYS shall not: be• greater .than the .total of
REVISED WORKING. DAYS, (line 8). After approved total of working days
has been . reached, continue recording working and nonworking. days: but
do not add into the totals. Make statement under REMARKS. the
WORKING and NONWORKING days are shown for. record. only since the
contract time has elapsed.
Time extensions other, are to be explained under REMARKS and the
following, information is to be included:.
(a) Cause of delay . and specification reference/under which approval
was granted. .
(b) Statement as to what controlling operation or operations are being'
delayed and to what extent. .
(c) Dates for which the extension was granted.
(d) . Reference to supporting data.
ADDITIONAL REMARKS:
Fischer Plumbing
Mike Fischer, Owner
1372 W. 26th Street
San Bernardino, CA 92405
City of Fontana
CALIFORNIA
March 1, 2001
RE: Slover Avenue Sewer
from Cherry Avenue to Hemlock Avenue
Weekly Statements of Working Days Report Nos..6 and 7
Dear Mr. Fischer:
Enclosed for the review are the weekly statements of working days
for week ending February 23, 2001. You will be allowed (15) days
in which to protest in writing the correctness of the statement;
otherwise the statement shall be deemed to have been accepted by
you as correct.
If you need additional information, please contact the undersigned
at (909) 350-7632.
Sincerely,
COMMUNITY DEVELOPMENT DEPARTMENT
Engineering Division
Donald Gdula
Consultant Project Coordinator
Special Projects
cc: Principal Civil Engineer/Special Projects
Consultant Public Works Inspector (SB)
www.fontana.org
8353 SIERRA AVENUE FONTANA, CALIFORNIA 92335-3528 (909) 350-7600
CITY OF FONTANA
WEEKLY STATEMENT OF. WORKING DAYS
PROJECT: SLOVER AVENUE SEWER FROM CHERRY AVENUE TO HEMLOCK AVENUE
REPORT NO.
6
TO: FISCHER PLUMBING
The following statement shows the number of working days charged to your contract for the week ending: 02/16/01
Date
Day
Weather, Weather Conditions or Other Conditions
Working
Day
Non -Working
Days
Caused by
Weather
Working Days
No Work
Done on
Controlling
Operation
(Note 2)
2/12/01
Mon.
Rain
0
1
0
2/13/01
Tue.
Rain
0
1
0
2/14/01
Wed.
Clear and cool
0
1
0
.2/15/01
Thur.
Clear and Warm
1
0
0
2/16/01
Fri.
Clear and Warm
1
0
0
Days thls week
Days previously reported
Total days to date
2
3
0
10
8
7
12
11
7
TIME EXTENSIONS
CCO Numbers
(Note 3)
Days Ap roved
CCO Other
"
Days
Days
Total
this report
previously reported.
days to date
0
0
0
0
0
7
0
0
7
COMPUTATION OF EXTENDED DATE FOR COMPLETION
1. First working day designated
2. Working days specified in contract
3. COMPUTE DATE FOR COMPLETION(if all days specified are workable)
4. Total time extension days approved to date (CCO plus other)
5. Total non -working days to date (Note 4)
6. Sub Total (Line 4 plus Line 5)
7. EXTENDED DATE FOR COMPLETION (Line 3 plus Line 6)
8.. Revised working days for contract (Line 2 plus Line 6)
9. Total working days to date
10. WORKING DAYS REMAINING (Line 8 minus Line 9)
Number
of Days
MMMENaMi
60
0•
18
18
IMOMMWM
78
12
66
Numbered
Day (Note 4)
Day No. 744
Date
1/8/01
MOMOMMiNgffigNiMM
Day No. 804 ( 4/4/01
Day No. 822
4/30/01
Controlling Operation(s)
February 14, 2001 was non -working day. The roadway was too wet to stripe for traffic
control per the approved plans. Stripping has to be in place before the digging operation could start.
Remarks: (Note 5) (Continue on reverse)
The Contractor will be allowed fifteen (15) days in which to protest
in writing the correctness of the statement; otherwise the statement
shall be deemed to have been accepted by the Contractor as correct.
NOTE: All footnotes are on the reverse side.
3/1/01
Donald Gdula/Project Coordinator
INSTRUCTION TO RESIDENT ENGINEER,
When recording nonworking days due to weather; state the reason why
the day was unworkable when the weather description itself does not
adequately describe conditions. For example,' "Clear -wet grade" to
describe conditions when the weather is clear, but the grade is too wet to
.work. Do not list days merely as "Unworkable".
•
Enter days on which no productive work has been performed on the
controlling operation(s) for reasons other than weather.
3. List numbers of contract change orders providing for time extensions'.
4. * Do not include nonworking days, which occur after expiration of the
Extended DATE. OF COMPLETION. On contracts that are .overtime, the
total under WORKING DAYS shall not be greater than the .total of
REVISED WORKING. DAYS, (line 8). After approved total of working days
has been reached, continue recording working .and nonworking. days but
do not add into the totals. Make statement under REMARKS. the
WORKING and NONWORKING days are shown for .record' only since the
contract time has elapsed.
5. • Time extensions other, are to be explained under REMARKS and the
following. information is to be included:.
(a)* Cause of delay .and specification reference/under which approval
was granted.
• (b) Statement as to what controlling operation or operations are being
delayed and to'what extent..
(c) Dates for which the extensionwas granted.
(d) Reference to supporting data.
ADDITIONAL. REMARKS:
CITY OF FONTANA
WEEKLY'STATEMENT OF WORKING DAYS
PROJECT: SLOVER AVENUE SEWER FROM CHERRY AVENUE TO HEMLOCK AVENUE
TO: FISCHER PLUMBING
REPORT NO. 7
The following statement shows the number of working days charged to your contract for the week ending: 02/23/01
Date
Day
Weather, Weather Conditions or Other Conditions
Working
Day
Non -Working
Days
Caused by
Weather
Working Days
No Work
Done on
Controlling
Operation
(Note 2)
2/19/01
Mon.
Cloudy
1
0
0
2/20/01
Tue.
Clear and cool
1
0
0
2/21/01
Wed.
Clear and cool
1
0
0
2/22/01
Thur.
Clear and Warm
1
0
0
2/23/01
Fri.
Rain
0
1
0
Days this week
Days previously reported
Total days to date
4
1
0
12
11
7
16
12
7
TIME EXTENSIONS
CCO Numbers
(Note 3)
Days Approved
Other
CCO
Days, this report
Days previously reported,
Total days to date
0
0
0
0
.0
7
. 0
0
7
COMPUTATION OF EXTENDED DATE FOR COMPLETION
Number
1. First working day designated
2. Working days specified in contract
3. COMPUTE DATE FOR COMPLETION(if all days specified are workable)
4. Total time extension days approved to date (CCO plus other)
5. Total non -working days to date (Note 4)
6. Sub Total (Line 4 plus Line 5)
7. EXTENDED DATE FOR COMPLETION (Line 3 plus Line 6)
8. Revised working days for contract (Line 2 plus Line 6)
9. Total working days to date
10. WORKING DAYS REMAINING (Line 8 minus Line 9)
Controlling Operation(s)
of Days
OMMWM
60
WWWWWW
0
19
19
79
16
63
Numbered
Day (Note 4)
Date
Day No. 744
1/8/01
MMOMOMMUMMMeg
Day No. 804 4/4/01
Day No. 823
5/1/01
Remarks: (Note 5) (Continue on reverse)
The Contractor will be allowed fifteen (15) days in which to protest
in writing the correctness of the statement; otherwise the statement
shall be deemed to have been accepted by the Contractor as correct.
NOTE: All footnotes are on the reverse side.
Donald Gdula/Project Coordinator
3/1/01
INSTRUCTION TO RESIDENT ENGINEER
1. When recording nonworking days due to weather; state the reason why
the day was unworkable when the weather description itself does not
adequately describe conditions. For example; "Clear -wet grade" to
describe conditions when the weather is clear, but the grade is too wet to
work. Do not list days merely as "Unworkable".
2. Enter days on which no productive work has been performed on the
controlling operation(s) for reasons other than weather.
3. List numbers of contract change orders providing for time extensions.
4. Do not include nonworking days, which occur after expiration of the
Extended DATE. OF COMPLETION. On contracts that.are overtime, the
total under WORKING DAYS shall not ". be • greater than the' .total of
REVISED WORKING. DAYS, (line 8). After approved total of working days
has been .reached, continue recording working and nonworking days but
do not add into the totals. Make statement under REMARKS. the
WORKING and NONWORKING days are shown for.record'only since the
contract time has elapsed.
5. Time extensions other, are to be explained under REMARKS and the
followinginformation is to be included:.
(a) Cause of delay .and specification reference/under which approval
was granted.
(b) Statement as to what controlling operation or operations are being
delayed and ta'what extent.
(c) . Dates for which the extension'was granted.
• (d) Reference to supporting data.
ADDITIONAL REMARKS:
Fischer Plumbing
Mike Fischer, Owner
1372 W. 26th Street
San Bernardino, CA 92405
City of Fontana
CALIFORNIA
February 20, 2001
RE: Slover Avenue Sewer
from Cherry Avenue to Hemlock Avenue
Weekly Statement of Working Days Report No. 5
Dear Mr. Fischer:
Enclosed for the review is the weekly statement of working days
for week ending February 9, 2001. You will be allowed (15) days in
which to protest in writing the correctness of the statement;
otherwise the statement shall be deemed to have been accepted by
you as correct.
If you need additional information, please contact the undersigned
at (909) 350-7632.
Sincerely,
COMMUNITY DEVELOPMENT DEPARTMENT
Engineering Division
Donald Gdula
Consultant Project Coordinator
Special Projects
cc: Principal Civil Engineer/Special Projects
Consultant Public Works Inspector (SB)
www.fontana.org
8353 SIERRA AVENUE FONTANA, CALIFORNIA 92335-3528 (909) 350-7600
* recycled paper
CITY OF FONTANA
WEEKLY STATEMENT OF WORKING DAYS
PROJECT: SLOVER AVENUE SEWER FROM CHERRY AVENUE TO HEMLOCK AVENUE
TO: FISCHER PLUMBING
REPORT NO. 5
The following statement shows the number of working days charged to your contract for the week
ending: 02/09/01
Date
Day
Weather, Weather Conditions or Other Conditions
Working
Day
Non -Working
Days
Caused by
Weather
Working Days
No Work
Done on
Controlling
Operation
(Note 2)
2/5/01
Mon.
Clear and Warm
0
'0
1
2/6/01
Tue.
Clear and Warm
0
0
1
2/7/01
Wed.
Clear and Warm
0
0
1
2/8/01
Thur.
Clear and Warm
0
0
1
2/9/01
Fri.
Clear and Warm
0
0
1
Days this week
Days • previously reported
Total days to date
0
0
5
10
8
0
10 ..
8
5
TIME EXTENSIONS
CCO Numbers
(Note 3)
Days Approved
CCO
Other
Days this report
Days previously reported.
Total days to date
0
0
5
0
0
2
0
0
7
COMPUTATION OF EXTENDED DATE FOR COMPLETION
1. First working day designated
2. Workingdaysspecified s ecified in contract
3. COMPUTE DATE FOR COMPLETION(if all days specified are workable)
4. Total time extension days approved to date (CCO plus other)
5. Total non -working days to date (Note 4)
6. Sub Total (Line 4 plus Line 5)
7. EXTENDED DATE FOR COMPLETION (Line 3 plus Line 6)
8. Revised working days for contract (Line 2 plus Line 6)
9. Total working days to date
10. WORKING DAYS REMAINING (Line 8 minus Line 9)
Number
of Days
MUMMEN
Numbered
Day (Note 4)
Day No. 744
Date
1/8/01
60
7
8
15
Dar No.804.•.•. ....•.;.4/4/01
><:.....
75
10
65
Day No. 819 J 4/25/01
Controlling Operation(s)
February 5 thru 9, 2001 were non -working days. Traffic control plans were being revised because
the encroachment at the Union Pacific Railraod has not been approved.
Remarks: (Note 5) (Continue on reverse)
The Contractor will be allowed fifteen (15).days in which to protest
in writing the correctness of the statement; otherwise the statement
shall be deemed to have been accepted by the Contractor as correct.
NOTE: All footnotes are on the reverse side.
2/19/01
Donald Gdula/Project Coordinator
•
INSTRUCTION TO RESIDENT ENGINEER
When recording nonworking days due to weather; state the reason why
the day was unworkable when the weather description itself does not
adequately describe conditions. For example,. "Clear -wet grade" to
describe conditions when the weather is clear, but the grade is too wet to
work. Do not list days merely as "Unworkable".
2. Enter days on which no productive work has been performed . on the
controlling operation(s) for reasons other than weather.
3. ' List numbers of contract change orders providing for time extensions.
4. Do not include nonworking days, which occur after expiration of the
Extended DATE OF:COMPLETION. On contracts that are overtime, the
total under WORKING DAYS . shall not be greater than the .total of
REVISED WORKING. DAYS, (line 8). After approved total of working days
has 'been reached, continue recording working and nonworkingdays but
do not add into the totals. Make statement under REMARKS. the
WORKING and NONWORKING days are shown for record' only since the
contract time has elapsed.
5. ' Time extensions other, are to be explained under REMARKS and the
followinginformation is to be included:.
(a) Cause of delay . and specification reference/under. which approval
was granted.
(b) . Statement as to what controlling operation or operations are being
• delayed and to' what extent. .
(c) Dates for which the extension was granted.
(d) Reference to supporting data.
ADDITIONAL REMARKS:
Fischer Plumbing
Mike Fischer, Owner
1372 W. 26th Street
San Bernardino, CA 92405
City of Fontana
CALIFORNIA'
February 20, 2001
RE: Slover Avenue Sewer
from Cherry Avenue to Hemlock Avenue
Weekly Statement of Working Days Report Nos 1,2,3,and 4
Dear Mr. Fischer:
Enclosed for the review is the weekly statement of working days
reports 1,2,3, and .4 which I found to have incorrect revised
working days and working days remaining. You will be allowed '(15).
days in which to protest in writing the correctness of the
statement; otherwise the statement shall be deemed to have been
accepted by you as correct.
If you need additional information, please contact the undersigned
at (909) 350-7632.
Sincerely,
COMMUNITY DEVELOPMENT DEPARTMENT
Engineering Division
Donald Gdula
Consultant Project Coordinator
Special Projects
cc: Principal Civil Engineer/Special Projects
Consultant Public Works Inspector (SB)
www.fontana.org
8353 SIERRA AVENUE FONTANA, CALIFORNIA 92335-3528 (909) 350-7600
40 recycled paper
CITY OF FONTANA
WEEKLY STATEMENT OF WORKING DAYS
PROJECT: SLOVER AVENUE SEWER FROM CHERRY AVENUE TO HEMLOCK AVENUE
TO: FISCHER PLUMBING
The following statement shows the number of working days charged to your contract for the. week ending:101/12/01 1
Date
Day
.
Weather, Weather Conditions or Other Conditions
Working
Day
Non -Working
Days
Caused by
Weather
Working Days
No Work
Done on
Controlling
Operation
(Note 2)
1/8/01
Mon.
Rainy and Cold
0
1
0
1/9/01
Tue.
Clear and Cool
1
0
0
1/10/01
Wed.
Clear and Cool
1
0
0
1/11/01
Thur.
Rainy and Cold
0
1
0
1/12/01
Fri.
Rainy and Cold
0
1
0
Days this week
Days previously reported
Total days to date
2
3
0
0
0
0
2
3
0
TIME EXTENSIONS
CCO Numbers
(Note 3)
Days Approved
CCO
Other
Days this report
Days previously reported.
Total days to date
0
0
0
0
0
0
0
0
0
COMPUTATION OF EXTENDED DATE FOR COMPLETION
1. First working day designated
2. Workingdaysspecified s ecified in contract
3. COMPUTE DATE FOR COMPLETION(if all days specified are workable)
4. Total time extension days approved to date (CCO plus other)
5. Total non -working days to date (Note 4)
6. Sub Total (Line 4 plus Line 5)
7. EXTENDED DATE FOR COMPLETION (Line 3 plus Line 6)
8. Revised working days for contract (Line 2 plus Line 6)
9. Total working•days to date
10. WORKING DAYS REMAINING (Line 8 minus Line 9)
. Controlling Operation(s)
Number
of Days
OMMEMNR
60
MMOMMW
0
3
3
Numbered
Day (Note 4)
Day No. 744
Date
1/8/01
MOMMEWWWWONN
Day No. 804
4/4/01
omwmgmm
63
2
61
Day No. 807 i
4/9/01
Remarks: (Note 5) (Continue on reverse)
The Contractor will be allowed fifteen (15) days in which to protest
in writing the correctness of the statement; otherwise the statement
shall be deemed to have been accepted by the Contractor as correct.
NOTE: All footnotes are on the reverse side.
2/19/01
Donald Gdula/Project Coordinator
INSTRUCTION TO RESIDENT ENGINEER
1. When recording nonworking days due to weather; state the reason why
the day was unworkable when the weather description itself does not
adequately describe conditions. For example,* "Clear -wet grade" to
describe conditions when the weather is clear, but the grade is too wet to
work. Do not list days merely as "Unworkable".
2. Enter days on which no productive work has been performed on the
controlling operation(s) for reasons other than weather.
3. List numbers of contract change orders providing for time extensions.
4. Do not include nonworking days, which occur after expiration of the
Extended DATE OF :COMPLETION. On contracts that are overtime, the
total under WORKING DAYS shall not be greater than the .total of
REVISED WORKING DAYS, (line 8). After approved total of working days
has been reached, continue recording working and nonworking days but
do not add into the totals. Make statement under REMARKS. the
WORKING and NONWORKING days are shown for record only since the
contract time has elapsed.
5. Time extensions other, are to be explained under REMARKS and the
.followinginformation is to be included:.
(a) Cause of delay .and specification reference/under which approval
was granted.
(b) Statement as to what controlling operation or operations are being
delayed and to what extent.
(c) Dates for which the extension was granted.
-(d) Reference to supporting data.
ADDITIONAL REMARKS:
CITY OF FONTANA
WEEKLY STATEMENT OF WORKING DAYS
PROJECT: SLOVER AVENUE SEWER FROM CHERRY AVENUE TO HEMLOCK AVENUE
REPORT NO.
2
TO: FISCHER PLUMBING
The following statement shows the number of working days charged to your contract for the week
ending:101/19/01
Date
Day
Weather, Weather Conditions or Other Conditions
Working
Day
Non -Working
Days
Caused by
Weather
Working Days
No Work
Done on
Controlling
Operation
(Note 2)
1/15/01
Mon.
Light Rain. and Cold
1
0
0
1/16/01
Tue.
Cloudy and Cool
1
0
0
1/17/01
Wed.
Very Windy
0
1
0
1/18/01
Thur.
Clear and Cool
1
0
0
1/19/01
Fri.
Clear and Cool
1
0
0
Days this week
Days previously reported
Total days to date
4
1
0
2
3
0
6
4
0
TIME EXTENSIONS
CCO Numbers
(Note 3)
Days Approved
CCO
Other
Days this report",
Days previously reported.
Total days to date
0
0
0
0
0
0
0
0
0
COMPUTTATION OF EXTENDED DATE FOR COMPLETION
1. First working day designated
2. Workingdaysspecified s ecified in contract
3. COMPUTE DATE FOR COMPLETION(if all days specified are workable)
4. Total time extension days approved to date (CCO plus other)
5. Total non -working days to date (Note 4)
6. Sub Total (Line 4 plus Line 5)
7. EXTENDED DATE FOR COMPLETION (Line 3 plus Line 6)
8. Revised working days for contract (Line 2 plus Line 6)
9. Total working days to date
10. WORKING DAYS REMAINING (Line 8 minus Line 9)
Number
of Days
OMMWMME
Numbered
Day (Note 4)
Day No. 744
Date
1/8/01
60
., Da....•••No.•.. •..8•04... ... ..'4�• 4 ..';
01:>:`•.....
0
4
4
WWWMME
64
6
58
Day No. 808 l 4/10/01
Controlling Operation(s)
Remarks: (Note 5) (Continue on reverse)
The Contractor will be allowed fifteen (15) days in which to protest
in writing the correctness of the statement; otherwise the statement
shall be deemed to have been accepted by the Contractor as correct.
NOTE: All footnotes are on the reverse side.
2/19/01
Donald Gdula/Project Coordinator
• '•
INSTRUCTION TO RESIDENT ENGINEER
1. When recording nonworking days due to weather; state the reason why
the day was unworkable when the weather description itself does not
adequately describe conditions. For example,' "Clear -wet grade" to
describe conditions when the weather is clear, but the grade is too wet to
work. Do not list days merely as "Unworkable".
2. Enter days on which no productive work, has been performed on the
controlling operation(s) for reasons other than weather.
3. List numbers of contract change orders providing for time extensions.
4. Do not include nonworking days, which occur after expiration of the
Extended DATE OF -COMPLETION. , On contracts that are overtime, the
total under WORKING DAYS shall not be greater than the .total of
REVISED WORKING DAYS, (line 8). 'After approved total of working days
has been reached, continue recording working and nonworkingdays but
do not add into the totals. Make statement under REMARKS. the
WORKING and NONWORKING days are shown for record only since the
contract time has elapsed.
5. Time extensions other, are to be explained under REMARKS and the
following information is to be included:.
(a)Cause of delay and specification reference/under which approval
was granted.
• (b) • Statement as to what controlling operation or operations are being
delayed and to'what extent.
(c) Dates for which the extension'was granted.
(d) Reference to supporting data.
ADDITIONAL REMARKS:
CITY OF FONTANA
WEEKLY STATEMENT OF WORKING DAYS
PROJECT: SLOVER AVENUE SEWER FROM CHERRY AVENUE TO HEMLOCK AVENUE
REPORT NO. 3
TO: FISCHER PLUMBING
The following statement shows the number of working days charged to your contract for the week ending: 01/26/01
Date
Day
Weather, Weather Conditions or Other Conditions
•
Working
• Day
Non -Working
Days
Caused by
Weather
I
Working Days
No Work
Done on
Controlling
Operation
(Note 2)
1/22/01
Mon.
Clear
1
0
0
1/23/01
Tue.
Clear
1
0
0
1/24/01
Wed.
Rain
0
1
0
1/25/01
Thur.
Clear
1
0
0.
1/26/01
Fri.
Rain
0
1
0
Days this week
Days previously reported
Total days to date
3
2
0
6
4
0
9
6
0
TIME EXTENSIONS
CCO Numbers •
(Note 3)
Days
Approved
Other
CCO
Days this report
Days previously reported.
Total days to date
0
0
0
0
0
0
0
0
0
COMPUTATION OF EXTENDED DATE FOR COMPLETION
1. First working day designated
2. Workingdaysspecified s ecified in contract
3. COMPUTE DATE FOR COMPLETION(if all days specified are workable)
4. Total time extension days approved to date (CCO plus other)
• 5. Total non -working days to date (Note 4)
6. Sub Total (Line 4 plus Line 5)
7. EXTENDED DATE FOR COMPLETION'(Line 3 plus Line 6)
8. Revised working days for contract (Line 2 plus Line 6)
9. Total working days to date
10. WORKING DAYS REMAINING (Line 8 minus Line 9)
Controlling Operation(s)
• Number
of Days
....................................
Numbered •
Day (Note 4)
Day No. 744
Date
1/8/01
60
0
6
6
MOMMOMMMENN
Day No. 804
4/4/01
UMMOM
66
9
57
Day No. 810 1 4/12/01
Remarks:' (Note 5) (Continue on reverse)
The Contractor will be allowed fifteen (15) days in which to protest
in writing the correctness of the statement; otherwise the statement
shall be deemed to have been accepted by the Contractor as correct.
NOTE: All footnotes are on the reverse side.
2/19/01
Donald Gdula/Project Coordinator
• s
INSTRUCTION TO RESIDENT ENGINEER
When recording nonworking days due to weather; state the reason why
the day was unworkable when the weather description itself does not
adequately describe conditions. For example,. "Clear -wet grade" to
describe conditions when the weather is clear, but the grade is too wet to
work. Do not list days merely as "Unworkable".
2. Enter days 'on which no productive work has been performed on the
controlling operation(s) for reasons other than weather.
3. List numbers of contract change orders providing for time extensions.
4. Do not include nonworking days, which occur after expiration of the
Extended DATE OF :COMPLETION. On contracts that are overtime, the
total under WORKING DAYS shall not : be greater than the .total of
REVISED WORKING DAYS, (line 8). After approved total of working days
has been reached, continue recording working and nonworkingdays but
do not add into the totals. Make statement under REMARKS. the
WORKING and NONWORKING days are shown for record.only since the •
contract time has elapsed.
5. Time extensions other, are to be explained under REMARKS and the
followinginformation is to be included:.
(a) Cause of delay and specification reference/under which approval
was granted.
(b) Statement as to what controlling operation or operations are being
delayed and to what extent.
(c) Dates for which the extension was granted.
(d) Reference to supporting data.
ADDITIONAL REMARKS:
CITY OF FONTANA
WEEKLY STATEMENT OF WORKING DAYS
PROJECT: SLOVER AVENUE SEWER FROM CHERRY AVENUE TO HEMLOCK AVENUE
REPORT NO.
TO: FISCHER PLUMBING
The following statement shows the number of working days charged to your contract for the week
ending: 02/02/01
Date
Day
Weather, Weather Conditions or Other Conditions
Working
Day
Non -Working
Days
Caused by
Weather
Working Days
No Work
Done on
Controlling
Operation
(Note 2)
1/29/01
Mon.
Clear and Cool
1
0
0
1/30/01
Tue.
Very Windy
0
1
0
1/31/01
Wed.
Very Windy •
0
1
0
2/1/01
Thur.
Very Windy
0
0
1
2/2/01
Fri.
Clear and Warm
.0
0
1
Days this week
Days previously reported
Total days to date
1
2
2
9
6
0
10
8
2
TIME EXTENSIONS
CCO Numbers
(Note 3)
Days
Approved
Other
CCO
Days this report'
Days previously reported.
Total days to date
0
0
2
0
0
0
0
0
2
COMPUTATION OF EXTENDED DATE FOR COMPLETION
1. First working day designated
2. Workingdaysspecified in contract
3. COMPUTE DATE FOR COMPLETION(if all days specified are workable)
4. Total time extension days approved to date (CCO plus other)
5. Total non -working days to date (Note 4)
6. Sub Total (Line 4 plus Line 5)
7. EXTENDED DATE FOR COMPLETION (Line 3 plus Line 6)
8. Revised working days for contract (Line 2 plus Line 6)
9. Total working days to date
10. WORKING DAYS REMAINING (Line 8 minus Line 9)
Number
of Days
60
2
8
10
Numbered
Day (Note 4)
Day No. 744
Date
1/8/01
i•":'Da`•:'•#r:No: 804'# ...rt`4/4 01#'....
Y 7�`� /
70
10
60
Day No. 814 l 4/18/01
Controlling Operation(s)
February 1 and 2, 2001 were non -working days. Traffic control plans were being revised because
the encroachment at the Union Pacific Railraod has not been approved.
Remarks: (Note 5) (Continue on reverse)
The Contractor will be allowed fifteen (15) days in which to protest
in writing the correctness of the statement; otherwise the statement
shall be deemed to have been accepted by the Contractor as correct.
NOTE: All footnotes are on the reverse side.
Donald Gdula/Project Coordinator
INSTRUCTION TO RESIDENT ENGINEER
1. When recording nonworking days due to weather; state the reason why
the day was unworkable when the weather description itself does not
adequately describe conditions. For example,' "Clear -wet grade" to
describe conditions when the weather is clear, but the grade is too wet to
work. Do not list days merely as "Unworkable".
2. Enter days on which no productive work has been performed • on the
controlling operation(s) for reasons other than weather.
3. List numbers of contract change orders providing for time extensions.
4. Do not include nonworking days, which occur after expiration of the
Extended DATE OF :COMPLETION. On contracts that are overtime, the
total under WORKING DAYS shall not be greater than the .total of
REVISED WORKING. DAYS, (line 8). After approved total of working days
has been reached, continue recording working and nonworking; days but
do not add into the totals. Make statement under REMARKS. the
WORKING and NONWORKING days are shown for record only since the
contract time has elapsed.
5. Time extensions other, are to be explained under REMARKS and the
followinginformation is to be included:.
(a)Cause of delay and specification reference/under which approval
was granted. •
• (b) Statement as to what controlling operation or operations are being
delayed and to what extent.
(c) Dates for which the extension -was granted.
(d) Reference to supporting data.
ADDITIONAL REMARKS: