MINUTES
OF
PRE -CONSTRUCTION MEETING
FONTANA AUTO MALL
ON -SITE SEWER PLANS FOR PARCEL MAP 14518
IN THE CITY OF FONTANA - RDA
LOCATION OF MEETING: City of Fontana Executive Conference Room
DATE: November 18, 1999 TIME: 9:00 a.m.
A. CONTRACTUAL
Status of Contract: Three Contracts were given to Contractor at meeting. Contracts to be
returned to Arrowhead Management Group.
Status of Performance Bond: Contractor to return with executed contracts
Status of Payment Bond: Contractor to return with executed contracts
Status of Certificates of Insurance: Contractor to return with executed contracts
- Status Permits: Contractor to obtain a no fee construction permit from the City of Fontana prior
to commencing work.
B. CONTRACTOR'S PROJECT SCHEDULE AND OTHER REQUIREMENTS OF THE
CONTRACT DOCUMENTS:
Status of Notice to Proceed: It was agreed that tentative start date will be November 29,1999.
PRIOR TO STARTING WORK THE FOLLOWING SHOULD BE COMPLETED BY
CONTRACTOR:
1) Approved construction schedule.
Page I
ARROWHEAD MANAGEMENT GROUP • 190 North Arrowhead Avenue • Suite E • Rialto, California 92376 • Phone: (909) 873-9660 • Fax: (909) 873-9661I
ti
i-
2) Names of individuals authorized to sign change order etc.
3) City of Fontana Business licence.
4) City of Fontana construction permit.
5) Contract signed by contractor with all required insurance and bonds.
Contractor's Schedule: Contractor to fax copy.of schedule to Arrowhead Management Group
today. Arrowhead Management Group to review.
Completion Time for Contract: 25 working days per Specifications:
General Conditions Page
Liquidated Damages: $500 / day_per Specifications Section 6-9 Liquidated Damages
City Business License and Appropriate State of California Required License: Contractor is in
process o f obtaining City License.
MATERIALS TO BE FURNISHED BY CONTRACTOR: (Shop Drawing Submittals)Refer to
"Green Book - Subsection 4-1.6 Trade Names or Equals". The specified contract completion time
shall not be effected by any circumstances developing from provisions of this subsection.
SUBCONTRACTORS: Contractor listed PMI as only subcontractor.
WORKING HOURS: Contractor activities shall be confined to hours between 7:00 A.M.
and 6.00 P.M. Monday through Friday: Excluding Holidays. Contractor stated that they would be
working from 7.00 a.m. to 3.30 p.m. Greg Bucknell said if Contractor needed to start earlier than 7:00
AM, 6:00 AM would be allowed if City Inspector could be present.
C. PAYMENTS
PROGRESS PAYMENTS: Closure date is 5 working days prior to the first Monday of each
month. Original invoice are to go to the Citv of Fontana Accounts Payable Department. Prior to issuing
invoice to the City Contractor should obtain signature from inspector and Arrowhead Management
Groub. Arrowhead Management Group will workout brocedure on how this will work in order to flow
smoothly.
10% RETENTION: Full 10% shall be deducted from all payments. Greg Bucknell said he
would allow contractor to go on 5% if good progress is being made
CHANGE ORDERS: Section 3 "Changes in Work" of the Greenbook.
Page 2
CERTIFIED PAYROLLS: Required. See General Conditions Section 10 - Wage Rates and
and Labor Code. Certified payroll is to be given to Arrowhead Management Group for review and
i'Iling. Arrowhead Management Group will notify Contractor if there are any problems with the
submittal.
D. RIGHT OF WAY AND UTILITIES:
NOTIFICATION OF AGENCIES: All required notification have been made.
COORDINATION WITH OTHER AGENCIES: Coordination issues have been and will continue
to be handled with other azencies as required.
RIGHT-OF-WAY REQUIREMENTS: Review Right of Way and Easements. We have a 15'
Loot wide easement for this work.
NOTIFICATION AND COORDINATION WITH UTILITIES: 48 Hour Notice is to be given
to Underground Service Alert. Also see General Conditions Section 3 of Specifications for other
notification requirements. Contractor is responsible.
UTILITY SERVICE PAYMENTS: Contractor said he will be setting a construction water meter.
This needs to be handled between Contractor and Fontana Water Co.
E. ENGINEERING/INSPECTION AND SURVEYING
ENGINEER OF RECORD: ASL Consulting Engineers, Inc. ASL will be in charge of design
inspection and field staking.
STAKING: John Bateman_(ASL) in charge of field staking. Bateman requested 48 hours notice.
Contractor wants 15' offsets.
INSPECTION: John Campbell (ASL) in chafe of field inspection and will onsite full time. All field
communications are to go thru John.,John will also coordinate testing with Contractor and Kleinfelder.
Campbell to turn over daily reports to Arrowhead Management Group.
RECORD DRAWI NGS: Contractor to provide redline drawings to Inspector for coordination. Inspector
to turn over to Arrowhead Management Group.
MATERIALS AND SOILS TESTING REQUIREMENTS: Klein elder will do all fiel
d testing. GreggQ g
said Kleinfelder should make determination as to timing and location o f testing. Campbell to coordinate
Kleinfelder required 24 hours notice.
Page 3
TRAFFIC CONTROL: The California Department of Transportation Traffic Manual will govern
all requirements as applicable.
PROTECTION OF EXISTING FACILITIES: Although we are not aware of any until crossings
Contractor to be responsible to protect should there be some discovered.
DUST CONTROL: Contractor to provide dust control
STORAGE OF MATERIAL AND EQUIPMENT: Contractor will not provide any onsite trailer
due to the size of the job. Contractor to provide metal container.
JOB SAFETY: —Con tractor is responsible for all safety requirements. Submittal showing design of
shoring bracing sloping for all trenches over 5' deep is to be submitted to Arrowhead Management
Group prior to trenching. Per Greenbook 7-10.4 Safety.
JOB SECURITY: No problems that anyone is aware of. Contractor to provide his securely measures.
G. OTHER MISCELLANEOUS ITEMS AND/OR COMMENTS, CONCERNS, QUESTIONS:
None
H. FINAL ACCEPTANCE OF WORK:
PUNCH LIST: Inspector and Contractor said they prefer to correct all items as construction
progressed. Punch List will be prepared by the Inspector. Second Punch List will be prepared if
necessary. Inspector will give completed Punch List to Glen Sams.
FINAL INSPECTION: Final inspection to be coordinated by Inspector.
FINAL ACCEPTANCE BY CITY COUNCIL: Once ASL and AMG are satisfied with the work,
AMG will issue a letter to Greg Bucknell. Greg will agendize the item for City Council approval.
FINAL PAYMENT: Final payment to be made not less than 35 days following filing of Notice of
Completion.
"ADDITIONAL NOTES OR COMMENTS"
Jim Maitland said he will be making spot visits to the site. Greg said if he was not available and field issues
needed to be addressed Carlos Navarro (City Chief Inspector) should be contacted. Also, i f Greg is not available
Yousu f Patanwala. Greg said once we have executed contracts AMG should copy the "CA" and "I"' sections of
the Contract Documents and make sure Contractor and Inspector get copies.
Page 4
•
CITY OF FONTANA
EMERGENCY INFORMATION FORM
PROJECT NAME: Fontana Auto Mall On -Site Sewer
LOCATION: Southwest corner of Valley Boulevard and Citrus Avenue
CONTRACTOR: K.A.S. Equipment & Rental, Inc.
ADDRESS: P.O. Box 9570 Ontario, CA 91762-9570
OFFICE PHONE: 909-623-5481 FAX NO. 909-397-7817
CONTACT PERSON: Danielle Reinberger RESIDENCE PHONE: 909-606-0624
BEEPER PHONE NO. 909-397-1795
JOB SUPERINTENDENT: Al Bitetti, Jr.
ADDRESS: 1 1 174 Pipeline Avenue Pomona CA 91766
DAY PHONE: 909-623-5481 RESIDENCE PHONE: 626-810-2259
BEEPER PHONE NUMBER. 909-397-6356
FOREMAN: Steve Falkenstien
ADDRESS: 1 1 174 Pipeline Avenue, Pomona CA 91766
DAY PHONE: 909-623-5481 RESIDENCE PHONE: 909-737-5571
BEEPER PHONE NO. 909-397-2391
CITY OF FONTANA - EMERGENCY PHONE NUMBERS
Police Department:
General Information ................................. 909-350-7700
Emergencies.............................................911
Public Services Division: ...................... 909-350-6760
Curtis Aaron ................... Pager: 909-873-6460 Home: 619-949-0928
Engineering Division: ..... 909-350-7610
Yousuf Patanwala .....•......... Work: 909-350-6645 Home: 909-889-2819
Carlos Navarro ........ ...... Work: 909-350-6632 Home: 909-825-4727
Robert Savant .............. Work: 909-350-6635 Home: 909-881-5909
Emergency Information
The names, addresses and telephone numbers of the contractor and sub -contractors or his representatives, shall
be filed with the City Engineer and the Police Department prior to beginning work.
The contractor shall provide adequate detours to the satisfaction of the City Traffic Engineer. A detailed plan of such
detours shall be submitted to the City Traffic Engineer at least five (5) days prior to the time the contractor wishes
to close off the street or in any way restrict the traffic flow. In actual street closures, the submitted plan shall indicate
the route of the detour, the character of the temporary pavement where required, and a layout of the locations of
signs and lighting. In all other cases, the contractor shall provide adequate traffic flow in both directions. If traffic
cannot be maintained the contractor shall provide flagmen whose sole duties consist of directing traffic through and
around the work. In all cases, the approval of a suitable plan shall be granted to the contractor prior to the beginning
of construction.
Failure or refusal by the contractor to comply with the above mentioned requirements shall be sufficient cause for
the City Engineer to order the work done by city forces and the cost therein to be borne by the contractor.
cc: See Distribution List Revised: Nov.99
HF:hf
Page 5
Arrowhead
Management
Group
MEETING ATTENDANCE RECORD
Date: November 18, 1999 Time: 9:00 a.m.
Project Title: Fontana Auto Mall On -Site Sewer
Meeting Purpose: Pre- Construction Meeting
Meeting Location: City of Fontana Executive Conference Room Ca? City of Fontana City Hall, 8353
Sierra Avenue
Name (Please Print)
Representing
Address
Phone & Fax
l4v5 ()I L I T-7 Lh-)
C.v-1 3 S l -'5 &C..c
2
r, �t r ►2y t%.tfh.Y
/ L
aIV& �7ft&-Q> sr� ism
is v/,Y�-r --" C-r zG / S
`r�/7Z7-TG'�S
3
C��'�i
��,�t�"�;t-'0�
l°1,�En �-1Lt''•rGr fl4v'z5
C-9737
cl a9 -?q 3-U9/
4
,PA?WAIhS FRo'g I" �9
1 %81 1d i A. clf-"114 A 1/
3.7.5"- 'A 7
6
1117 '1 �i o �•«r t
��c{ 6 Z3 15-1
7
'�,
� i y 7 4° ,�'!� f�..�._-, c f''
� — � 2,? •S-
8
�o�i_ !� N1J{ UW--
l FlL t.,l
�?3 AO" + S sr-
y
2IQOM. ().C-GIk a?ZISDJV
`ram>35 r-7�2�3
9bt
e
'
10.
0S7f�'a
9y9-%L?-'�o9'
II
12
13
14
15
16
E:\E\WP-FILES\AUTOMALL\SIGNIN.FRM Page_ I_ of
FUNCTION
CITY OF FONTANA:
CONTRACTOR
CONSTRUCTION
MANAGER:
Arrowhead
Management
Group
CONSTRUCTION
PROJECT TEAM DIRECTORY
FONTANA AUTO MALL
ON -SITE SEWER FOR PARCEL MAP 14518
IN THE CITY OF FONTANA - RDA
November 18,1999
COMPANY/ADDRESS CONTACT(S)
City of Fontana Greg Bucknell
Principal Civil Engineer/Special Projects 909-350-6646
8353 Sierra Avenue 909-350-6618 (FAX)
Fontana, California 92335
Inspection/Associate Engineer: Carlos Navarro .
909-350-6632
909-350-6618 (FAX)
K.A.S. Equipment & Rental, Inc.
Project Manager
P.O. Box 9570
Ontario, California 91762-9570.
Superintendent:
Arrowhead Management Group
Construction Manager
190 N. Arrowhead Avenue, Suite E
Rialto, California 92376
Administration:
Dave Rodman
909-623-5481.
909-397-7817 (FAX)
Al Bitetti
909-623-5481
909-397-7817 (FAX)
Glen R. Sams
909-873-9660
909-873-9661 (FAX)
Karla Perez Vertti
909-873-9660
909-873-9661 (FAX)
Page I of 3
ARROWHEAD MANAGEMENT GROUP -190 North Arrowhead Avenue - Suite E - Riafto, California 92376 - Phone: (909) 873-9660 - Fax: (909) 873-9661
•
C�
FUNCTION
AFFILIATED
AGENCY:
ENGINEERING DESIGN
AND SURVEYING:
(Engineer of
Record)
PROJECT TEAM DIRECTORY, cont'd
. COMPANY/ADDRESS
Caltrans
464 W. 4`h Street, 6`h Floor
San Bernardino, CA 92401
County of Flood Control
Flood Control Inspector
825 E. 1 Street
San Bernardino, California 92415
ASL Consulting Engineers
Project Manager
225 W. Hospitality Lane, Suite 206
San Bernardino, California 92408
Inspection:
ASL Consulting Engineers
Surveying
1 Jenner Street, Suite 200
Ir*-ine, California 92618
GEOTECHNICAL/SOILS
ENGINEER:
Kleinfelder, Inc.
Area Manager
1940 Orange Tree Lane
Redlands, California 92373
UTILITY
COORDINATION:
G.E. Goodrich
Senior Project Manager
2720 Camino Capistrano, Suite A
San Clemente, California 92672
UTILITIES:
Southern California Edison
Service Planner
7951 Redwood Avenue
Fontana, California 92336
Page 2 of 3
CONTACT(S)
Raj Chharan
909-383-7973
909-383-4224 (FAX)
Rick Lucas
909-3 87-2648
909-387-2897 (FAX)
Jim Maitland
909-381-3666
909-3 81-4176 (FAX)
John Cambell
909-381-3666
909-381-4176 (FAX)
Larry Bateman
949-727-7099
949-450-8784 (FAX)
Allan Evans
909-793-2691
909-792-1704 (FAX)
Ron Weatherholt
949-498-1969.
949-361-2817 (FAX)
Frans Stewart
909-357-6223
909-357-6185 (FAX)
r
� •
r
PROJECT TEAM DIRECTORY, cont'd
FUNCTION COMPANY/ADDRESS
CONTACT(S)
UTILITIES
(Cont'd):
Pacific Bell
Joel Dinnauer. Jr.
Facilities Engineer
909-359-2273
3073 Adam Street
909-359-7120 (FAX)
Riverside, California 92504
Southern California Gas Co.
Alan Keselof
Planning Associate
909-335-7781
P.O. Box 3003
909-335-7527 (FAX)
Redlands, California 92373
Fontana Water Company
Al Krohn
Senior Inspector
909-822-2201
P.O. Box 987
909-823-5046 (FAX) ;
Fontana, California 92334
Comcast
Paul Cyr
Construction Technician
909-390-4738
1205 Dupont Avenue
909-975-3340 (FAX)
Ontario, California 91761
Page 3 of 3
:7
•
Arrowhead
Management
Croup
AGENDA
FOR
PRE -CONSTRUCTION MEETING
FONTANA AUTO MALL
ON -SITE SEWER PLANS FOR PARCEL MAP 14518
IN THE CITY OF FONTANA - RDA
LOCATION OF MEETING: City of Fontana Executive Conference Room
DATE: November 18, 1999 TIME: 9:00 a.m.
PURPOSE OF THE PRE -CONSTRUCTION MEETING
The purpose of the meeting is 1) Familiarize the team with the project policies and procedures and
Contract Documents that are to be observed during performance of the work 2) Establish preliminary
schedules, lines of communications and operational procedures; and 3) develop mutual understanding
concerning administration of the contract.
A. CONTRACTUAL
Status of Contract:
- Status of Performance Bond:
- Status of Payment Bond:
- Status of Certificates of Insurance:
- Status Permits:
Page I
B. CONTRACTOR'S PROJECT SCHEDULE AND OTHER REQUIREMENTS OF THE
CONTRACT DOCUMENTS:
Status of Notice to Proceed:
- Contractor's Schedule:
Completion Time for Contract: 25 working days per Specifications:
General Conditions Page
Liquidated Damages: $500 / day_per Specifications Section 6-9 Liquidated Damages
City Business License and Appropriate State of California Required License:
MATERIALS TO BE FURNISHED BY CONTRACTOR: (Shop Drawing Submittals)Refer to
"Green Book - Subsection 4- ( 6 "Trade Names or Equals". The specified contract completion time
shall not be effected by any circumstances developing from provisions of this subsection.
SUBCONTRACTORS:
WORKING HOURS: Contractor activities shall be confined to hours between 7:00 A.M.
and 6.00 P.M. Monde through Friday Excluding Holidays.
Page 2
C. PAYMENTS
PROGRESS PAYMENTS: Closure date is 5 working days prior to the first Monday of each
month.
10% RETENTION: Full 10% shall be deducted from all payments.
CHANGE ORDERS: Section 3 "Changes in Work" of the Greenbook.
CERTIFIED PAYROLLS: Required. See General Conditions Section 10 - Wage Rates and
and Labor Code.
D. RIGHT OF WAY AND UTILITIES:
NOTIFICATION OF AGENCIES:
COORDINATION WITH OTHER AGENCIES:
RIGHT-OF-WAY REQUIREMENTS: Review Right of Way and Easements.
NOTIFICATION AND COORDINATION WITH UTILITIES: 48 Hour Notice is to be given
to Underground Service Alert Also see General Conditions Section 3 of Specifications for other
notification requirements
Page 3
UTILITY SERVICE PAYMENTS:
E. ENGINEERING/INSPECTION AND SURVEYING
ENGINEER OF RECORD: ASL Consulting Engineers, Inc.
STAKING:
INSPECTION:
RECORD DRAWINGS•
MATERIALS AND SOILS TESTING REQUIREMENTS:
F. CONSTRUCTION
TRAFFIC CONTROL:
Page 4
PROTECTION OF EXISTING FACILITIES:
DUST CONTROL:
STORAGE OF MATERIAL AND EQUIPMENT:
JOB SAFETY:
JOB SECURITY-
G. OTHER MISCELLANEOUS ITEMS AND/OR COMMENTS, CONCERNS, QUESTIONS:
H. FINAL ACCEPTANCE OF WORK:
PUNCH LIST:
Page 5
FINAL INSPECTION:
FINAL ACCEPTANCE BY CITY COUNCIL:
FINAL PAYMENT:
"ADDITIONAL NOTES OR COMMENTS"
r
CITY OF FONTANA
EMERGENCY INFORMATION FORM
PROJECT NAME: Fontana Auto Mall On -Site Sewer
LOCATION: Southwest corner of Valley Boulevard and Citrus Avenue
CONTRACTOR: K.A.S. Equipment & Rental Inc.
ADDRESS: P.O. Box 9570 Ontario, CA 91762-9570
OFFICE PHONE: 909-623-5481 FAX NO. 909-397-7817
CONTACT PERSON: Danielle Reinberger RESIDENCE PHONE: 909-606-0624
BEEPER PHONE NO. 909-397-1795
JOB SUPERINTENDENT: Al Bitetti Jr.
ADDRESS: 1 1 174 Pipeline Avenue Pomona CA 91766
DAY PHONE: 909-623-5481 RESIDENCE PHONE: 626-810-2259
BEEPER PHONE NUMBER. 909-397-6356
FOREMAN: Steve Falkenstien
ADDRESS: 1 1 174 Pipeline Avenue Pomona CA 91766
DAY PHONE: 909-623-5481 RESIDENCE PHONE: 909-737-5571
BEEPER PHONE NO. 909-397-2391
CITY OF FONTANA - EMERGENCY PHONE NUMBERS
Police Department:
General Information ................................. 909-350-7700
Emergencies...............................................911
Public Services Division:.. .............................. 909-350-6760
Curtis Aaron ................ Pager: 909-873-6460 Home: 619-949-0928
Engineering Division: .................................... 909-350-7610
Yousuf Patanwala ............... Work: 909-350-6645 Home: 909-889-2819
Carlos Navarro ................ Work: 909-350-6632 Home: 909-825-4727
Robert Savant .................. Work: 909-350-6635 Home: 909-881-5909
Emergency Information
The names, addresses and telephone numbers of the contractor and sub -contractors or his representatives, shall
be filed with the City Engineer and the Police Department prior to beginning work.
The contractor shall provide adequate detours to the satisfaction of the City Traffic Engineer. A detailed plan of such
detours shall be submitted to the City Traffic Engineer at least five (5) days prior to the time the contractor wishes
to close off the street or in anyway restrict the traffic flow. In actual street closures, the submitted plan shall indicate
the route of the detour, the character of the temporary pavement where required, and a layout of the locations of
signs and lighting. In all other cases, the contractor shall provide adequate traffic flow in both directions. If traffic
cannot be maintained the contractor shall provide flagmen whose sole duties consist of directing traffic through and
around the work. In all cases, the approval of a suitable plan shall be granted to the contractor prior to the beginning
of construction. .
Failure or refusal by the contractor to comply with the above mentioned requirements shall be sufficient cause for
the City Engineer to order the work done by city forces and the cost therein to be borne by the contractor.
cc: See Distribution List Revised: Nov.99
HF:hf
SENT BY:ARROWHEAD ;11- 4-39 ; 1:18PM ; ARROWHEAD GROUP-)
9093506613;# 1/ 1
Arrowhead •
Management
Croup
MEMORANDUM,
Via Facsimile
TO:. Project Team Members
FROM: Glen R. Sams. Arrowhead Management Group
DATE: November 4, 1999
RE: Preconstruction Meeting
On -Site Sewer
Fontana Auto Mall
A Pre -Construction Meeting will be held November 18, 1999 at 9:00 a.m.
at the City of
Fontana Executive Conference Room at Fontana City Hall, 8353 Sierra Avenue,
Please contact
Glen Sams @ (909) 873-9660 if you have questions. We look forward to your participation.
Requested Attendees:
Fax No.
Dave Rodman, K.A.S. Equipment & Rental, Inc.
909-397-7817
Greg Bucknell, City of Fontana
909-350-6613
Jim Maitland, ASL Consulting Engineers
909-381-4176
Larry Bateman, ASL Consulting Engineers
714.727-7097
Allan Evans, Kleinfelder
909-792-1704
Ron Wetherholt, G.E. Goodrich
949-361-2817
Raj Chharan, Caltrans
909-383-4224
Fran Stewart, Southern California Edison
909-357-6185
Alan Keseloff, Southern California Gas Co.
909-335-7527
AI Krohn, Fontana Water Company
909-823-5046
Joel Dinnauer, Jr., Pacific Bell
909-359-7120
Paul Cyr, Comcast .
909-975-3340
GRS: kpv