HomeMy WebLinkAboutFlood Control Facilities West EndId
11r
Sri
I�
REVISED
SUPPLEMENTAL REPORT
FLOOD CONTROL FACILITIES
BD FONTANA WEST END VENTURE
CITY OF FONTANA
January, 1986
Prepared by
Bill Mann & Associates
1814 Commercenter West
Suite A
San Bernardino, CA 92408
1
TABLE OF CONTENTS
P age
SECTION 1.
INTRODUCTION AND PURPOSE OF REVISED
1
SUPPLEMENTAL REPORT
"NA
1.1 PROJECT LOCATION
1
1
1.2 PURPOSE OF REVISED REPORT
SECTION 2.
REVIEW OF POTENTIAL INCREASED RUNOFF FROM
4
PROJECT DEVELOPMENT
2.1 GENERAL
4
ri
2.2 ESTIMATED INCREASED POST - DEVELOPMENT
5
DRAINAGE FLOWS FROM SITE
d
SECTION 3.
ELIMINATION OF FLOODING ALONG BANANA STREET
7
lw
3.1 GENERAL
7
SECTION 4.
REVISED FLOOD CONTROL FACILITIES PLAN
8
4.1 GENERAL
8
4.2 REVISED FLOOD CONTROL FACILITIES PLAN
8
4.3 FLOOD CONTROL PLAN SUMMARY
10
4.4 RUNOFF FROM SITE WEST OF EXISTING
12
ETIWANDA CHANNEL
1
do
1
iw
IK
SECTION 1. INTRODUCTION AND PURPOSE OF REVISED SUPPLEMENTAL REPORT
1.1 Project Location
A Specific Plan has been prepared for the approximate 1,500 acres located
north of Foothill Boulevard and east of East Avenue in the City of Fontana.
The Specific Plan was approved by the City of Fontana on April, 1985. The
Specific Plan area is shown on Figure No. 1.
'*
The project area is traversed by two major unimproved flood channels.
The
Etiwanda Creek Channel traverses the
westerly part of the site and the
San
Sevaine Creek Channel traverses the
approximate middle of the site.
The
j
existing San Sevaine Creek Channel is
due to be removed and combined with
the
y
existing Etiwanda Channel, thus elimir.ating the channelization of San Sevaine
Creek flows through the middle of the
site.
a'" Due to the proposed elimination of the existing San Sevaine Creek Channel,
certain flood control facilities are necessary north and south of the project
nRe area in addition to onsite channelization. The existing flood control
facilities and the proposed offsite flood control facilities are shown
schematically on Figure No. 1.
1.2 Purpose of Revised Report
The purpose of this revised report is to update the planned flood control
facilities proposed for the subject development.
As indicated above, the BD Fontana West End Venture project area is traversed
by the Etiwanda and San Sevaine Creek Channels. At the time the project area
Specific Plan was prepared, a "Flood Control Facilities Study" and a "Supple-
mental Report" with recommendations for the control of flood flows and
drainage were provided. The two reports and recommendations were based on,
6
and are in conformance with the Day, Etiwanda and San Sevaine Creeks System
y y
Drainage Plan prepared in March, 1983.
The two studies are listed below for reference.
West End Specific Plan, Flood Control Facilities Study,
September, 1984
West End Specific Plan, Flood Control Facility Alternatives,
ON Supplemental Report, November, 1984
rd
.s These studies and the plan of action for flood and drainage control were
it approved by the San Bernardino County Flood Control District and City of
Fontana. The Flood Control District approval letter and recommendations are
am
included in the Appendix for ready reference.
9
Two alternative flood control plans were presented in the above referenced
"Supplemental Report ". Alternate B was recommended and approved by the Flood
Control District and City of Fontana. A summary of the approved plan
(Alternate B) is also included in the Appendix for ready reference.
on
This report does not completely replace the two above mentioned reports. This
report does revise the recommended Flood Control Facilities Plan as described
in Section 4. The only major changes are in the proposed excavation for storm
flow detention north and south of the site.
The hydrology for the San Sevaine Creek Watershed is being updated and will be
..� submitted by a separate report.
B
3
SECTION 2. REVIEW OF POT ENTIAL INCREASED RUNOFF FROM PROJECT DEVELOPMENT
2.1 General
The recently developed San Bernardino County Detention Basin Policy states, "
I"
... the post - development peak flow rate generated by the site shall be less
di than or equal to 90% of the Ao�t development peak flow rate from the site for
all frequency storms up to and including the 100 -year frequency storm ...
Only 2, 10, 25 and 100 -year storm need to be analyzed."
.y When the "West End Specific Plan, Flood Control Facilities Study" was prepared
w
in September, 1984, it was recommended that the increase in the development
dw generated drainage runoff from the site be provided for by a combination of
providing onsite and offsite drainage detention capacity. Small storm flows
am (2 - year to approximately 5 - year frequency storms) were to be handled y
"onsite" detention facilities, with larger storm flows (increase) to be pro-
'""' vided for by improving "offsite" storm flow detention capacity. This concept
was accepted by the Flood Control District and City of Fontana.
ww
The following improvements of offsite drainage detention facilities were
proposed:
�I
a. Turnout from existing Etiwa Channel into Victoria Basin.
b. Excavation of 200,000 yd3 from the proposed Lower San Sevaine Basin
"1 (124 acre -feet)
Approximately 55+ acres (250 acre -feet) of onsite drainage retention facili-
ties were proposed to handle the residual increased development flows at a
cost of approximately $600,000.
However, it has always been the contention of the developer and the engineers
that the funds that would be placed in temporary onsite detention facilities
0
fl
could best serve the regional drainage and flood control system and the
general area as a whole by being applied to permanent facilities. Therefore,
it is recommended and the intent of this revised plan to place the funds into
the regional system, such as the expansion of the Lower San Sevaine Basin,
Hickory Basin and /or Jurupa Basin to compensate for increased drainage flows
from the development.
Local, temporary storm flow detention basins are as expensive to remove as the
facilities are to construct initially. There are many cases in the valley
area where storm flow detention cannot be accomplished in permanent regional
facilities due to the location of the development away from regional channels
and /or basins. However, the West End Venture development is in close
proximity to existing and proposed storm flow detention basins.
9
dW
di
dW
w
�I
0
2.2 Estimated Increased Post - Development Drainag Flows from S ite
The increase in drainage flows from the site has been calculated by analyzing
the present site conditions and future development. The increase in flows are
summarized in Table I.
Table I
Present Future
Condition Condition Increased Runoff (ac -ft)
Area (ac -ft) (ac -ft) 2 =yr 10 -yr 25 -yr 100 -yr
West End 126 (2 yr) 263 (2 yr) 137
Venture 290 (10 yr) 521 (10 yr) 231
Development
383 (25 yr). 647 (25 yr) 264
574 ( 100 yr) 893 ( 100 yr) 319
5
F
The increased runoff volume to be generated by the site upon full development
�*+ is approximately 320 acre -feet for a 100 -year storm. This is an increase of
IM approximately 56% over the runoff in the natural condition.
It should be noted this increase will be over a number of years and will not
occur immediately. It is intended to provide for the increase in site runoff
volume by assisting in the development of offsite detention facilities in
excess of the estimated increased runoff volume of 320 acre -feet.
a/
It is also emphasized that the construction of the
proposed
channel south of
*A
Foothill Boulevard will eliminate the major flood
flows
that outlet onto
rrY
Banana Street and floods the area along the street
during even minor floods.
Therefore, the project flood .control facilities will
not
only provide for
increased site generated flows, but will also, remove
storm
flows from Banana
do
Street that are generated offsite north of this
site and
presently pass
OM
through the site.
40
an
aw
OR
va
ri
i
DI
�kl
6
D
e
a
SECTION 3. ELIMINATION OF FLOODING BANANA STREET
3.1 General
, The San Sevaine Channel presently outlets onto Banana Street at Foothill
Boulevard. Due to the limited water - carrying capacity of Banana Street, even
small storms cause flooding along the street. Major storm flows on the street
in 1978 caused overflow and damage to homes along the street.
ar
"" The Flood Control Facilities Plan calls for the relocation of the existing San
do Sevaine Channel to the existing Etiwanda Channel alignment. The new channel
04 will be designed for the combined Etiwanda and San Sevaine Creek flows. Refer
„ to Figure No. 1 for the proposed ultimate channel construction between the
Devore Freeway and Foothill Boulevard and the proposed interim channel south
4W
of Foothill Boulevard. The new San Sevaine Channel will effectively remove
flood flows from Banana Street.
The elimination of the Banana Street flooding problem is emphasized in this
®. report because the removal of the downstream flooding due to offsite flows has
V1 a much greater benefit to the do; istream area than the elimination of
increased flows from the development. The proposed Flood Control Facilities
Plan for the project will eliminate the Banana Street flood problem and
Ai
provide for increased drainage flows generated by the project.
The proposed Flood Control Facilities Plan is discussed in Section 4.
E
e
E]
N
7
i
F
SECTION 4. REVISED FLOOD C ONTROL FACILITIES PLAN
4.1 General
It is proposed to increase the drainage detention capability in the offsite
Ali basins to compensate for the increased drainage flows that will be generated
by the site as it develops. The proposed drainage detention capability will
be developed in the Lower San Sevaine Basin, Hickory Basin and possibly
Jurupa Basin.
Refer to Figure No. 1 for the location of the BD Fontana West End Venture
project site and the proposed onsite and offsite flood control and drainage
detention facilities. The revised Flood Control Facilities Plan is discussed
in Section 4.2.
4.2 Revised Flood Control Facilities Plan
The "Flood Control Facilities Plan" for the BD Fontana West End Venture
generally includes the construction of the ultimate San Sevaine Channel
It is not proposed to make
any major
changes in the approved "Flood
Control
"interim" channel between
Facilities Plan" presented
in the "Flood Control Facilities
Alternatives,
Supplemental Report ", dated
November,
1984. The approved plan
(Alternate B)
storage, and partial excavation
is included in the Appendix
of this
report for ready reference. The above
referenced report should be
reviewed
for a detailed analysis of
the regional
flood problems in the general area.
detention,
if necessary.
It is proposed to increase the drainage detention capability in the offsite
Ali basins to compensate for the increased drainage flows that will be generated
by the site as it develops. The proposed drainage detention capability will
be developed in the Lower San Sevaine Basin, Hickory Basin and possibly
Jurupa Basin.
Refer to Figure No. 1 for the location of the BD Fontana West End Venture
project site and the proposed onsite and offsite flood control and drainage
detention facilities. The revised Flood Control Facilities Plan is discussed
in Section 4.2.
4.2 Revised Flood Control Facilities Plan
The "Flood Control Facilities Plan" for the BD Fontana West End Venture
generally includes the construction of the ultimate San Sevaine Channel
F
� 8
between the Devore Freeway and
Foothill
Boulevard, construction of an
"interim" channel between
Foothill
Boulevard
and the Santa Fe Railroad to the
south, the excavation of
200,000
yd3 in Lower San Sevaine Basin for debris
storage, and partial excavation
of
Lower San
Sevaine Basin and Hickory Basin
for storm flow detention.
Partial
excavation
in Jurupa Basin will be provided
for additional storm flow
detention,
if necessary.
F
� 8
The revised plan does not include any proposed changes to the basic flood
control channel improvements recommended in the "Supplemental Plan ". The
recommended revisions include the design of and additional excavation in the
proposed Lower San Sevaine Basin, the design of and partial excavation of
Hickory Basin, and excavation in Jurupa Basin, if necessary. The proposed
changes involve enhancement of storm flow detention to compensate for the
increased runoff to be generated by site development.
Under. the "revised plan ", the proposed excavation in Lower San Sevaine Basin
has been increased from 200,000 yd to 400,000 yd (215 acre - feet). It is
proposed to provide in excess of 140 acre -feet in Hickory Basin by construc-
ting the basin embankment and spillway. Flows from San Sevaine Channel will
be turned into the basin by a 36 -inch RCP. The proposed 400,000 yd excava-
tion in Lower San Sevaine Basin is in addition to the proposed 200,000 yd
excavation included in the original plan for debris control.
The estimated increase in runoff volume due to the proposed development is 320
acre -feet based on a 100 -year design storm. The proposed detention volume to
be provided in the Lower San Sevaine Basin and Hickory Basin is 355 acre -feet
or 111% of the projected increase in runoff volume.
The revised Flood Control Facilities Plan is summarized below. The estimated
construction cost has been updated from the November, 1984 "Supplemental
Report" using the ENR Index.
The hydrology for the San Sevaine Creek Watershed is being updated and will be
submitted by a separate report and is not included herein.
As shown -in Table I, the increased runoff from the entire site for a 2 -year
storm is estimated at 137 acre -feet. The construction of Hickory Basin with a
turnout from San Sevaine Channel will compensate for the increased runoff from
small storms.
H
J
E
9
4.3 Flood Control Plan Summary
+� The revised "Flood Control Facilities Plan" generally includes the construc-
tion of the ultimate San Sevaine Channel between the Devore Freeway and
Foothill Boulevard, construction of an "interim" channel between Foothill
Boulevard and the Santa Fe Railroad to the south, the excavation for some
ww debris and storm flow capacity in the proposed Lower San Sevaine Basin,
dd
excavation within the proposed Hickory Basin, and partial excavation in Jurupa
Basin, if necessary.
u/
*� Refer to Figure No. 1 for a schematic location and description of the compo-
nents of the plan.
Specifically, the features and estimated cost of the Flood Control Facilities
Plan are as follows:
s
+rr
a. Construction of the ultimate San Sevaine Channel (combined Etiwanda
and San, Sevaine Creeks flow) from the Devore Freeway to Foothill
Boulevard. Until the ultimate San Sevaine Channel is constructed
■.
below Foothill Boulevard in accordance with the "Drainage Plan"
and /or the Lower San Sevaine Basin is constructed, existing
Etiwanda and San Sevaine Creek flows cannot be comingled. There -
fore, a trapezoidal concrete channel is proposed with a separator
wall separating the flows. Existing Etiwanda Creek flows would be
directed to the existing RCB under Foothill Boulevard, and existing
San Sevaine Creek flows would be directed to the proposed "interim"
channel south of Foothill Boulevard.
Estimated Cost = $5,435,000
b. Construction of an "interim" earth channel along the ultimate
channel alignment from Foothill Boulevard southerly to connect to
the existing San Sevaine Channel immediately south of the Santa Fe
h
q
10
M
9
0
IIRR
Ai
rrr
w
err
r
�.r
.rr
+q
4 1
4 4
dW
Railroad. The construction would include the ultimate road
crossing structures.
estimated Cost = $2,000,000
C. Develop "offsite" drainage detention capability in the Lower San
Sevaine Basin to partially compensate for necessary "onsite"
retention of drainage flows. Excavation in the Lower San Sevaine
Basin would approximate 400,000 yd3. The material will be placed
in the basin levee.
Estimated Cost = $ 600,000
d. Develop 200,000 yd3 of debris storage in Lower San Sevaine Basin to
provide for major flood debris production on San Sevaine Creek.
The material will be placed in the basin levee.
Estimated Cost = $ 300,000
The combined excavation of 600,000 yd3 described in "c" and " d "
above is equivalent to approximately 215 acre -feet of storm flow
detention.
e. Develop "offsite" drainage detention capability in Hickory Basin to
compensate for necessary "onsite" detention of increased drainage
flows from the site. Storm flow detention in excess of 140
acre -feet will be provided by constructing the basin levee,
spillway and turnout.
Estimated Cost = $ 300,000
SUBTOTAL = $ 8,735,000
0
Because of the area below the Devore Freeway tributary to the existing San
Sevaine Channel, it will be necessary to construct a channel or storm drain
from the existing San Sevaine Channel to the proposed concrete lined channel
for purposes of conveying local drainage flows to the channel. The excavation
of the Lower San Sevaine Basin does not provide for local drainage flows north
and northeast of the site originating southeasterly of the Devore Freeway.
R ol
The storm drain or channel would be located along Baseline Avenue and is shown
schematically on Figure No. I.
Storm Drain Estimated Cost = $1,200,000
Estimated Flood Control Facilities Plan Cost =, $9,835,000
Because of the liabilities involved with comingling Etiwanda and San Sevaine
Creek flows prior to an adequate concrete lined channel being constructed
downstream of the project area, thesc flows must be kept separated. There-
fore, a trapezoidal channel with a wall separating the flows is recommended.
A schematic depiction of the channel is included herein as Figure No. 2. The
dw final size and configuration of the channel cross - section will depend on final
design of the channel system.
OR
4.4 Runoff from Site West of Existing Etiwanda Channel
The runoff values shown in Table I are for the entire site. The "revised"
Flood Control Facilities Plan provides for the increased runoff from the
entire site, as described in Subsections 4.2 and 4.3, by partial excavation of
the proposed Lower San Sevaine Basin and the construction of Hickory Basin.
However, due to the necessity of constructing parallel channels to separate
Etiwanda and San Sevaine Creek flows, it is not possible to direct flows from
the site west of the existing Etiwanda Channel to the interim channel to be
constructed south of Foothil.1 Boulevard.
M
V
YJ
D
+wi
do
w
ri
am
do
go
ud
Oft
tai
OR
id
w
There are 166 acres of the proposed development west of the existing Etiwanda
Channel. The 166 acres will generate 60 acre -feet of increased runoff based
on a 100 -year storm.
There are approximately 550 acres of the proposed development located between
the existing Etiwanda Channel and the existing San Sevaine Channel. A portion
of the approximate 550 acres historically drained to Etiwanda Channel, with
the remainder draining southerly. The runoff from the 550 acres will be
directed by storm drains to the San Sevaine Channel and then into Hickory
Basin in accordance with the Day, Etiwanda and San Sevaine Creeks System
Drainage Plan.
The increased runoff from the development west of the existing Etiwanda
Channel will be more than compensated for by the direction of drainage flows
i
east of the Etiwanda Channel to San Sevaine Creek and Hickory Basin.
13
U-11 IL - 1 IL-1 IL -1 IL-1 U. _j &i:i..i tai.
CHANN R/W
100 - 105'
SEPARATOR WALL
A
r -Morn &Inn
SAKI SFVAINF
VARIES
24' - 25'
COMBINED CHANNEL
ETIWANDA AND SAN SEVAINE
CREEKS FLOWS
NOTE - CHANNEL DIMENSIONS ARE PRELIMINARY.
FINAL DIMENSIONS WILL DEPEND ON
FINAL HYDRAU AND DE FIGURE N0.2
VARIES VARIES
9' -II' 13' -14'
FLOOD CONTROL /AIRPORTS
825 East Third Street • San Bernardino, CA 92415 -0835 • (714) 383.1665
n
City of Fontana
P. 0. Box 518
Fontana, CA 92335
Attention: Mr. Bob Shoenborn
Director of Public Works
ENVIRONMENTAL
PUBLIC WORKS AGENCY
UN Ate. V, 11`N�
MICHAEL G. WALKER
�\!r Director
January 7. 1985
File: 1- 701/1.00
1- 801/1.00
124.0209
Re: Zone 1, Etiwanda & San
Sevaine Channel Systems
West End Specific Plan
Gentlemen:
This office has completed review of the West End Specific Plan Flood Control
Facilities Study plus Supplemental Report, proposed Etiwanda & San Sevaine
Channel alignments, and detention basin proposals submitted by Bill Mann
& Assocites for our review by letters dated October 2, 1984, October 16,
1984, October 30 , 1984, and November 13, 1984 (copies attached). The West
End Specific Plan proposes an urban project to be located generally east
of East Avenue, south of Baseline Road, west of Hemlock Avenue and north,
of Foothill Boulevard in the northwest portion of the City of Fontana.
The West End -Specific Plan Flood Control Facilities Study describes the
existing. District facilities along the Etiwanda and San Sevaine Creek Systems.
The West End Specific Plan also discusses the flood hazards to the site
from these facilities. The plan should also address the possibility of
the Etiwanda and San Sevaine Creek flows comingling upstream of the Devore
Freeway and then the comingled flows entering either San Sevaine Channel
or Etiwanda Channel, then traversing the site. The Supplemental Report
discusses two alternatives for protecting the proposed development from
San Sevaine and Etiwanda Creek flows. Both alternatives follow the "Day,
Etiwanda and San Sevaine Creeks System Drainage Plan" with minor modifications..
B.ill Mann & Associates' letter dated October 16, 1984, proposes to increase
the storage volume of San Sevaine Basin OS by substantially increasing
the basin's levee height. 'Phis proposal pertains to -both alternatives
mentioned above. Raising the din height may increase the District's maintenance
costs by:
1. Having to remove all vegetation which might hide rodent holes
' in areas of possible piping — these: areas. are greatly increased
when levee height is increased. Vegetation and grasses which
would cover the levee or trees with deep root systems would not
be acceptable. Certain shrubs with - I shallow root systems may'
be acceptable.
1 JA 09 00
1 -
■
r
Letter to the City of Fontana
January 7, 1985
Page 2
2. Increasing the number of times a year inspection of the levee
must occur.
3. Having to repair any erosion immediately after it occurs in order
to guarantee the dams structural integrity and restore the required
storage capacity.
The District presently does not have the maintenance personnel to adequately
accomplish the above. If maintenance does not occur the District may be
responsible for any downstream damage resulting from the lack of adequate
maintenance. It may be, by the time of construction, the District may
have adequate personnel. An alternative may be the formation of a maintenance
district.
The increased height would make the basin more visible and may have environ—
mental impacts. Since the proposed freeway southerly of the basin will
be elevated above existing ground, the increased height may not be a problem.
Both the original -and new proposals would have to go through the environmental
process. It appears there may be more objection to the elevated levee.
The District would not object to the proposal if the environmental concerns
can be mitigated including the safety concern in storing water above surrounding
natural ground level. It is generally felt the benefit from the increased
storage volume will outweigh the increased maintenance costs and environmental
concerns.
Of the two alternatives proposed, Alternative "B" is recommended. This
alternative would - involve the construction of a concrete trapezoidal channel
with a separator wall for Etiwanda and San Sevaine Creeks between the Devore
Freeway and Foothill Boulevard. Downstream of Foothill Boulevard, Etiwand a
Creek flows would be returned to the existing historical flowpath while
San Sevaine Creek flows would be conducted south in an interim earth graded
channel to the Santa Fe Railroad where the flows are returned to the existing
historical flowpath near Hickory Basin. In addition, San Sevaine Basin
05 and Victoria Basin would be upgraded to provide flood protection, water
conservation, and flow attenuation.
The District has easement for San Sevaine -Creek downstream of Hickory Basin
through the old Kaiser Steel Plant. The District does not presently maintain
this easement. This easement has been maintained by the property owner.
The flowrate through this channel reach will not be increased, but the
volume of .flow will be increased. The possible liabilities which may be
incurred by the District and City from the increased volume of flow and
the strength of the District easement will be reviewed by County Counsel
to determine if the present fee owner must be consulted.
' Letter to the City of Fontana
January 7, 1985
Page 3
t
According to the ultimate,.onsite drainage plan, the local tributary flows
to the site from the northeast would be intercepted by a storm drain in
Adequate provisions shall be provided to protect the site from
Baseline Road and conducted to the proposed San Sevaine Channel. Also,
'
the flows generated onsite would be intercepted by storm drains within
Channel. This
the development and conducted to the proposed San - Sevaine
A plan showing these provisions shall be provided and approved
would help alleviate the existing flooding problems along Banana Street.
Also, detention basins would be provided along with the expansion of existing
'
District Basins to handle the incremental flows generated by the development
The flow in Etiwanda Creek, San Sevaine Creek and Banana Street
from all frequency storms. This may not cover all liabilities arising
from development of subject site. According to the Supplemental Report
'
these facilities would not be developed until Phase III. It appears Phase
storm event. Due to the complexity of the downstream drainage
I & Il can be adequately protected from San Sevaine - Etiwanda Creek over
and tributary flows by a combination of structural walls, earth berms and
'
water carrying streets, as discussed on page 27 of the Supplemental Report,
along Banana
hydrology and hydraulic calculations shall be provided and
but this does not address the downstream drainage problems
Street.
our recommendations for Phase I are as follows:
1.
Adequate provisions shall be provided to protect the site from
'
San Sevaine Creek - Etiwanda Creek overflow and tributary flows.
A plan showing these provisions shall be provided and approved
prior to approval of Phase I.
'
2.
The flow in Etiwanda Creek, San Sevaine Creek and Banana Street
shall not be increased due to the development by any frequency
storm event. Due to the complexity of the downstream drainage
'
_proposed solution a preliminary plan plus adequate
problems .and d
approve
hydrology and hydraulic calculations shall be provided and
prior to approval of Phase I. The solution will necessitate improve-
ment of San Sevaine Basin N5, Victoria Basin and onsi to detention
'
to handle the increased flows generated by the development. Develop-
ment of the District's Hickory Basin (downstream of the site)
may also be necessary.
'
3.
A plan plus the necessary hydrology and hydraulic calculations
shall be provided prior to approval of Phase I showing there exists
adequate developable storage volume in Victoria Basin and San
Sevaine Basin n5 to be used by City of Rancho Cucamonga the County
and the City of Fontana
'
U.
Preliminary basin development plans for San Sevaine Basin 05 and
Victoria Basin plus the necessary hydrology and hydraulic calculations
shall be provided prior to approval of Phase I showing Alternative
' 11
B is feasible. The calculations shall include:
II
II
II
n
0
Letter to the City of Fontana
January 7, 1985
Page 4
(a) inflow hydrographs,
(b) basin depth vs. capacity curves,
(c) basin depth vs outflow curves.,
(d) outflow hydrographs, and
(e)'sizing of Etiwanda and 'San Sevaine Channels
(f) debris volume determination
5. Phase I, as proposed, represents approximately 1/3 of the entire
developable area and no drainage facilities are scheduled in this
phase except the expansion of San Sevaine Basin N5 and Victoria
Basin to handle the inc. emental flows generated by this phase.
This precedent is extremely dangerous as it creates development
and increases runoff without providing the .proportionate share
of the drainage system. Later sales could put subsequent owner(s)
in a- position of responsibility for a disproportionate share of
the system and the subsequent owner(s) could possibly receive
relief from some of the costs at the expense of the San Bernardino.
County Flood Control District and /or other entities. Therefore, ,
there needs to be guarantees in the West End Specific Plan that
the necessary facilities are constructed at an equitable cost
by existing and future owners. Development of the West End Specific
Plan area shall be tied to the necessary regional flood control
improvements.
Our recommendations for Phase II are as follows:
1
1
1.
Etiwanda Channel shall be improved to the ultimate concrete divided
'
channel section from the Devore Freeway to East Avenue based on
4
Alternative "B" and calculations provided by recommendation
for Phase I. San Sevaine flows shall not enter at this time unless
'
the recommendations for Phase III are met.
2.
The flow in San Sevaine Creek and Etiwanda Creek shall not be
increased due to the development. An adequate plan and supporting
calculations shall be pro -ided.
3.
Some form of energy dissipation shall be provided where Etiwanda
'
Creek Channel flows are returned to natural.
4.
If it is deemed by the District that there is an adverse effect
on the downstream property where Etiwanda Channel flows are returned
be from
- to natural, a flowage acceptance letter shall- obtained
the property owner. If it can be shown there is no adverse effect
'
on the downstream property the letter may not be necessary.
1
1
Letter to the City of Fontana
January 7, 1985
'
Page 5
Our recommendations for Phase III are as follows:
1. 'San Sevaine Channel shall be improved to the ultimate* concrete- .
%.!.
channel
l section from the Devore Freeway through •Foothi *ll -Boulevard, Y,� i
based on Alternative "B" and calculations provided by-Recommendatiow.
4 for Phase I. Energy dissipation shall be -provided -where the.
concrete channel ends.
2. An earth graded charnel shall be provided for San* Sevaine Creek
from Foothill Boulevard to the old Kaiser Steel Plant property
as described in Alternative "B ". All road and railroad crossings
shall be improved to ultimate design. Bottom controls will be
necessary if the flow velocities when calculated are determined
to be excessively erosive and degradation of flowline profile.'
can reasonably be expected.
3. If it is deemed by the District that there is an- adverse:. effect,%- - . - .,! .
on the downstream property where the earth San Sevaine;
Channel is returned to its existing flowpath a flowage :acceptance :;
'
letter shall be obtained from the downstream property owner..
If it can be shown there is no adverse effect on the downstream... • .
property, the letter may not be necessary. By taking. the• flows
into Hickory Basin, then returning them to the natural- flowpath-.. %.••.
the adverse effects on the downstream owner may be.m•itigated..
This possibility would require documentation and flood. routing -. :
'
calculations to verify that peak flow rates are not increased.. :
4. San Sevaine Basin #5 shall be adequately excavated for flow attenuation ; -:•f .
and debris retention per plan and calculations provided as.•part :r'�...-
of Phase I.
'5 . On site drainage facilities shall be provided to conduct the-tributary
'
flows to Etiwanda and San Sevaine Channels. The City may want
to require a portion of the system to be installed under Phases
I and II.
It appears this project will provide -lore than its fair share of improvements :
:
to the Etiwanda - San Sevaine Creeks System. For an equitable solution +.
to the Etiwanda - San Sevaine Creeks drainage problems, the District, City
'
,
of Fontana and other affected cities should meet and consider: •forming a
development advisory committee(s). The committee(s)•; should include major s,•.
developers/owners in the Etiwanda and San Sevaine watershed. The goal
of the committee(s) would be to form policy and guidelines, and determine
'
what means of funding may be available to construct ultimate channel facilities :
for Etiwanda and San Sevaine Creeks. A steering .committee and technical,
'
committee similiar to that formulated for the development of the Day, Etiwanda
and San Sevaine Creeks Drainage Plan and the Day Creek Water Project is
recommended. As part of the development policy a reimbursement program
'r
Letter to the City of Fontana
January 7. 1985
Page 6
could be established for developers who provide facilities whose costs
are greater than the developments fair share. This could be developed
by the technical and steering committee(s).
Should you have any further questions concerning this matter, please feel
free to contact Allan J. Kielhold, Chief, rater Resources Division at (714)
383 - 2388.
Very truly yours,
CHARLES L. LAIRD
Assistant Director Administration
Flood Control
CLL :RWC :mjs
cc: City of Fontana,
Attn: Terry Draper, Planning Director
Attn: Reed Flory., Prog. Dir. (West End Spec. Plan)
DB Investors, Inc.
Attn: Joe Di Iorio
City of Rancho Cucamonga,
Attn: Lloyd Hubbs, City Engr.
Attn: Jack Lam. Community Development Dir.
City of Ontario
Attn: Leroy Bender
Riverside County FC & WCD
Attn: Bob Nelson.
Bill Mann
Mike Walker
bcc: —4tiben Montes
Tony Gray
Ken Miller
Bill Collins
Pete Mercado
i
L.LL .MANN & ASSOCIATES
Civil Engineering • Drainage — Flood Control • Special Studies
February 11, 1985 File: 84 -14
Mr. Charles L. Laird
Assistant Director
San Bernardino County
Department of Transportation/
Flood Control /Airports
825 East Third Street
San Bernardino, California 92415
Subject: West End Specific Plan -
Etiwanda and San Sevaine
Channel SyStem:s, Fontana
Dear Chuck:.
Reference is made to your letter dated January 7, 1985, in response to the
"Flood Control Facilities Study, West End Specific Plan" and the-"Supple- '
mental Report, Flood Control Facility Alternatives, West End Specific Plan"
prepared by Bill Mann & Associates. The reports were prepared for the West
End Specific Plan located at Foothill Boulevard and East Avenue.
We have had an opportunity to review your letter with Bob Schoenborn and
Reed Flory of the City of Fontana. Some concerns have been raised on
several recommendations in your letter and several items are in need of
clarification.
The items of concerns are listed below witli reference to the page number and
paragraph in•yout letter of January 7th.
I. Maintenance of the Dam (levee) for Proposed San Sevaine Basin No. 5
Page 1, Paragraph 3
Reference is made to the future increased maintenance costs by raising
the proposed basin design height and the possible lack of maintenance
personnnel to adequately inspect the proposed facility at the time of
construction.
The proposed basin will provide approximately 1,700 to •2,400 acre-feet
of flood storage depending upon final levee design height.
The. proposed basin is a major feature of Lite Day, Etiwand4 .and San
Sevaine Creeks System Drainage Plan and will benefit both County.4re•as
1814 COMMERCENTER WEST • SUITE A • SAN BERNARDINO, CA. 92408 • (714) 885.4309
February 11, 1985
San Bernardino County
Page two
in allowing channel downsizing and will provide significaflt water con-
servation benefits. The basin construction, as a part of the regional
flood control system, will assist in allowing the development of the
North Fontana area. The regional nature of the plan and the increased
tax base due to the proposed development in the area should provide for
future maintenance costs by Flood Control District personnel without
having to form a maintenance district.
We agree with the last sentence if the second paragraph on page two:
"It is generally felt the benefit from the increased storage volume
will outweigh the increased maintenance costs and environmental concerns. "
Due to the potential costs and uncertainty involved with the establishing
of a maintenance district, we need to resolve this issue as soon as
possible. It should also be noted this basin is a major feature in the
proposed San Sevaine Creek Bureau of Reclamation Project.
2. A pp roval of Alt "B"
Page 2, Paragrap 3
There is some concern that the District has not accepted Alternatg , " B "
as the preferred alternate. As far as the undersigned is c'oncdrned - ,.
the flood control facilities proposed in Alternate "B" have been accepted
and are recommended by the District. However, the recommendation-of
the Alternate "B" facilities by the District should be clarified with
the City.
3. Downst Dra Proble alo ,Banana Str eet
Page 3, Pa ra raph 1
The last sentence includes, ".. but this does not address the downstream
drainage problems along Banana Street ".
The first phase of residential development is proposed between the
existing Etiwanda and San Sevaine Channels outside the San Sevaine Creek
overflow area. Therefore, the initial phase will have no effect on
Banana Street. Later phases of development will require the relocation
of San Sevaine Channel as recommended in Alternate
Therefore, the flood flows will be removed from Banana Street. Addi-
tionally, storm drains are proposed to handle onsite local flows.
If the proposed commercial area to the east of the existing San Sevaine
Channel develops prior to the proposed channel. construction, it will be
necessary to mitigate onsite increased drainage flows with retention
basins.
9 � •
5
u
n
II
February ll, 1985
San Bernardino County
Page three
4. Use of the Victoria Basin and _Lower San Sevaine Basin to Mitigate
Increased Development Drainage Runoff
We are working with the Cities of Rancho Cucamonga and Fontana and the
District to develop sufficient storm storage volume to hopefully
satisfy both needs. Additional storage volume can be provided in
Victoria Basins by raising the levee height and by degrading the basin
on a temporary basis. The turnout from the existing Etiwanda Channel
is a. part of the Day, Etiwanda and San Sevaine Creeks Systems Drainage
Plan and is a part of the proposed Upper San Sevaine Creek Bureau of
Reclamation Project.
5. Phase I Recommendations
II
n
Pages 3 and 4
Recommendation No. 5 states
in this phase except the
Victoria Basin to handle
phase ".
that " drainage facilities are scheduled
expansion of San Sevaine Basin No. 5 and ,
the incremental flows generated by this
n
u
n
n
u
n
11.
II
This is not necessarily the case. A storm drain plan has been prepared
.by Hall b Foreman, Engineers for the development. A schematic plan
view of the plan is enclosed, Additionally, onsite retention
facilities are proposed as part nf the plan although we are attempting
to gain approval to provide the major part of onsite retention in the
regional facilities.
Recommendation No. 2 refers to the potential increased flow ,.in 'San „
Sevaine and Etiwanda Creeks. It is assumed the refe 1 rence'to,.increase
in flows pertains to peak flows. If some flows are detained •upst ' ream, ;.
and onsite, this may increase the duration of flows downstream..
6. Phase II Recommendations
Page 4
Recommendation No. 2 refers to increased flows ". It is assumed the
reference. is to peak flows, as the duration of flow may be increased
due to attenuation.
7. Phase. III Reco mmendations
Page 5
Onsite drainage facilities are proposed as discussed in No. 5 above.
We still believe the requirement of a downstream flowage acceptance
11
February JI, 1985
San Bernardino County
Page four
letter by the developer and /or the City is not warranted due to the
historical flows by both Etiwanda and San Sevaine Creeks. We believe
it can be shown that it will not be necessary and that the upstream
property has aright to outlet flows in the historical watercourses if
done in a reasonable manner.
8. General
1
Sincerely yours,
The Day,.Etiwanda and San Sevaine Creeks Systems Drainage Plan has gone
through the environmental review process and the EIR has been approved
by the Environmental Review Board. It is assumed the EIR will fulfill
the environmental review process for the Drainage Plan. However, it is
recognized the plan revision to go to a higher .levee (dam) on the
proposed Lower San Sevaine Basin may require a focused new EIR for that
part of the project due to potential safety and aesthetic concerns.
Due to the time constraints and the necessary time frame necessary in
obtaining plan approvals, it will be necessary to begin design on the
proposed flood control facilities in the very near future. We would
like to meet with you at an early date to discuss procedures, hydraulic
and design criteria.
We appreciate the assistance your staff has provided in reviewing the
proposed flood control facility plan, recognizing there are still some
issues to resolve.
> 'MAN/,/
. E
Consulting Eigineer
BCM:sw
Encl as noted
cc: City of Fontana
attn: Bob Schoenborn
Reed Flory
Joe DiIorio
Hall b Foreman
attn: Hugh Foreman
DEPARTMENT OF TRANS DRTATIONI COUNTY OF SAN BERNARDINO
"
�•ti; ENVIRONMENTAL
t FLOOD CONTROUA1RPORTS �.11 1 PUBLIC WORKS AGENCY
\1• 414 h \4111 h1f
' 825 East Third Street San Bernardino, CA 92415 -0835 (714) 383.1665 �% MICHAEL G. WALKER
1 .' Director
March 5, 1985
File: 1- 701/1.00
1-801/1.00
124.0209
Bill Mann & Associates
1814 Commercenter West
San Bernardino, CA 92408
Attention: Mr. Bill C. Mann
Re: Zone 1, Etiwanda and San
Sevaine Creeks — West End
Specific Plan
Gentlemen:
_Reference is made to your letter dated February 11, 1985, in response to our
letter dated January 7, 1985, commenting on your reports entitled "Flood +
Control Facilities Study, West End Specific Plan" and the "Supplemental '
Report, Flood Control Facility Alternatives, West End Specific Plan ".
Our comments are listed below as referenced in your February 11, 1985 letter
and our January 7. 1985 letter.
1. Maintenance of the Dam (Levee) for Proposed San Sevaine Basin No. 5
A maintenance district may not be necessary in this case. The answer
will come forth from policy being developed for detention basins. The
staff recommended detention basin policy which goes to the Board of
Supervisors, and the policy recommends further study of financing
alternatives for construction and maintenance of detention basins and
drainage (flood control) facilities.
2. Approval of Alternate "B"
The District supports and recommends Alternate "B" over Alternate "A ".
3. Downstream Drainage Problems Along Banana Street
As tentative maps are filed the effect of the proposed development on the
downstream properties and the proposed mitigation measures will be
reviewed in more detail. The proposed downstream mitigation measures
are adequate for specific plan purposes.
4. Use of the Victoria Basin ar.d Lower San Sevaine Basin to Mitigate
Increased Drainage Runoff
We concur, but backup calculations and substantiation of \ agreement
between the parties involved are still necessary.
Letter to Bill Mann & Associates
March 5. 1985
Page 2
5. Phase I Recommendations
We generally concur with _y_Qur statements. We will also look at the
increased duration of flow and the increased_ frequency of occurrence of
damaging flow to determine if there is an adverse effect on the downstream
properties.-
6. Phase II Recommendations
See 5 above
7, Phase III Recommendations
Flowage acceptance letters are quite often required as part. of development
within the county. A flowage acceptance letter is only necessary if
is lkely to be an
the flow characteristics are changed
Based onnthe there
required calculations and
adverse effect on the property.
plans to be submitted, a determination will be made. ti
8. We concur with your statements.
Anytime you wish to /need to meet regarding this project, please feel free to
contact Allan J. Kielhold, Chief. Water Resources Division at (714) 383-2388,
or myself at (714) 383 -120
Very truly yours.
CHARLES L. LAIRD, Assistant Director
Transportation /Flood Control /Airports
CLL:RWC:mjs
cc: City of Fontana, Bob Schoenborn /Reed Flory
Joe Di Iorio
Hall and Foreman, Hugh Foreman
Ruben Montes
Allan J. Kielhold
2. Alternate "B"
Alternate "B" generally includes the construction of the ulti -
mate San Sevaine Channel between the Devore Freeway and Foothill
Boulevard, construction of an "interim" channel between Foot-
hill Boulevard and the Santa Fe Railroad to the south, and the •
excavation for some debris and storm flow capacity in the
proposed Lower San Sevaine Basin.
•
Refer to Fi_gur.e No. 2 for a schematic location and description
of the components of Alternative "B ".
•
Specifically, the features and estimated cost of Alternate "B"
are as follows: •
r-
? 2.1 Construction of the ultimate San Sevaine Channel (combined
Etiwanda and San Sevaine Creeks flow) from the Devore Free, -
r - way to Foothill Boulevard. Until the ultimate San Sevaine
Channel is constructed below Foothill Boulevard in accor- ,
dance with the "Drainage Plan" and/or the Lower San Sevaine
Basin is constructed, existing Etiwanda and San Sevaine
Creek flows cannot be comi.ngl ed . Therefore, a trapezoidal
concrete channel is proposed with ;i separator wall separa-
ting the flows. Existing Etiwanda Creek flows would be
directed to the existing RCB under Foothill Boulevard,and
existing San Sevaine Creek flow; would be directed to the
- proposed "interim" channel south of Foothill Boulevard.•
•
Due to the need to separate.Etiwnnda and San Sevaine Creek
flows, the channel cost for this reach is higher than the
channel in Alternate "A ".
Estimated Cost = $ 5,175,000
•
2 . 2 Construction of an "interim" e a r t h channel along the ulti-
mate channe,l alignment from F o o t h i l l Boulevard southerly
8
to connect to the existing San Sevaine Channel immediately
south of the Santa Fe Railroad. The construction would
include the ultimate road crossing structures. A set of
schematic plans for the interim channel construction is
included in the Appendix for gener.ral information only.
Estimated Cost = $ 1,800,000
• 2.3 Develop "offsite" drainage retention capability in Victoria
Basin and the Lower Snn Sevainc Basin to partially compen-
sate for necessary "onsite" retention of drainage flows.
Excavation in the Lower San Sevaine Basin would approximate
200,000 yd
•
Estimated Cost = $ 445,000 ,
2.4 Develop 200,000 yd of debris storage in Lower San Sevaine
Basin to provide for major flood debris production on San
Sevaine Creek.
Estimated Cost = $ 350,000 •
•
Subtotal = $ 7,770,000
2.5 Because of the area below the Devore Freeway tributary to
the existing San Seval.ne Channel, it will be necessary to
construct a channel or storm drain from the existing San
Sevaine Channel to the proposed concrete lined channel for
purposes of conveying local drainage flows to the channel.
• The excavation of the Lower San Sevaine Basin does not pro-
.
vide for local dr;ii.nat;c flows north and northeast of the
site originating southeasterly or the Dcvoro Freeway. The
•
•
] 0
storm drain or channel would be located along Baseline
Avenue and is shown schematically on Figure No. 1.
Storm Drain Estimated Cost = $ 1,000.000
Estimated Alternate "B" Cost = $ 8,770,000
As indicated in the discussion of Altornate "A ". the cost of
the onsite storm - drain and drainage retention system is not
included herein.
Alternate "B as proposed herein, is approximately $2,500,000
less expensive than Alternate "A ". Ilowever, the facilities pro-
posed under Alternate "A" are regional in nature and will provide
benefits to the area in general, both to the north and south.of,
the site. Components of Alternate "B" are also regional in natxure.
1.
Alternate "B" will. provide direct benefits to the area along .
Banana Street south of Foothill Boulevard at less expense to
the xcgio.n. This alternate wi 11 not requi.r.e the complete ex-
cavation of the Lower San Sevaine Basi..n i.nitially, and will re-
serve the bulk of the material to be excavated for the construc-
tion of the Foothill .Freeway, if needed.
Because of the li.nhil n
.ities ivolved with comingling Etiwanda and
San Sevaine Creeks flows prior to an adequate concrete lined
channel being constructed downstream of the project area, these
flows must be kept separated. Therefore, a trapezoidal channel
wi.th.a wall scpaxating the flows is recommended. A schematic
depiction.of the channel is included herein as Figure No. 3.
The final size and configuration of the channel cross- section
will depend on final design or the rh:innel. system.
11